You are on page 1of 2

CHILLER PRE-COMMISSIONING ACTIVITY

Sr.
Description Data (Yes / No / NA) Remarks
No.

Electrical & Chiller Penal Installed Properly, door


1
should open, Should not located in open if not IP65

RY RB YB
2 Check Voltage Line to Line (400-450)

RN YN BN
3 Check Voltage Phase to Natural (should be 210-250)

Check Voltage Neutral to Earthing (should be less


4
than 3 VAC)

Chiller Cable Size Properly Installed with LUGS & Gland


5
also check the tightness

Pump Cable Size Properly Installed with LUGS & Gland


6
also check the tightness

7 check tightness of all the chiller electrical penal cable

Pressure gauges & Temperature gauge installed should


8 installed properly

Before Commissioning conform that the vendor have


9
taken the Hydro test
Raw Water Connection Provided in Hot / well or buffer
10
Tank

Raw Water Connection Provided in Cooling tower


11
Sump

If sepearte PVC Tank provide for cold and hot water


12
conform the equalizing line installed properly

Flush the water properly form Chiller Piping,


13
Condenser Piping, Clean the pot staniner & Y Stainer

Flow switch wiring should be done properly and after


14 doing wiring make sure that the flow switch should trip
when the pump off of flow is stop

IF water cooled loop the two common wire with each


other and connect two NO to the FS connection make
15
sure that the flow switch should trip when the pump
off of flow is stop,
Start one by one pump and check the rotation of all
16
pumps

The pressure difference across the chiller recirculation


17
should be at least 0.4 - 0.7 kg / cm2

The pressure difference across the condenser


18
recirculation should be at least 0.4 - 0.7 kg / cm2

If chiller is (1W + 1S) then please shut off the inlet and
19 outlet butterfly of standby chiller afterward do the
commissioning

When star the pump first kick the pump and check the
20
rotation of the pump.

Insure that the refirgerant valve of chiller should be


21
open

If SPPR alarm is coming never interchange the wire on


22 PCB always interchage the RY or YB From the main
incoming connection only.

You might also like