GN001 Marking Supports Nos 60 120 150 180


GN002 Drilling Nos 34 68 84 101
GN003 Marking, Drilling Nos 18 36 45 54
GN004 Fixing Fisher, Rod & Clamps Support Nos 21 42 52 62
GN005 Fixing Fisher, Rod & Channel Support Nos 16 32 40 48
GN006 Marking & Hanging Supports with Clamps Nos 11 22 27 32
GN007 Marking & Hanging Supports with Channels Nos 9 18 23 27
GN008 Hanging Supports with clamps in Existing Rods Nos 108 216 270 324
GN009 Hanging Supports with Channels in Existing Rods Nos 54 108 135 162
GN010 Cutting of Threaded Rods Nos 386 771 964 1157
GN011 MS / GI Channels Cutting Nos 90 180 225 270
GN012 MS / GI Pipes Cutting Upto Dia 50 mm Nos 90 180 225 270
GN013 MS / GI Pipes Cutting Upto Dia 65 to 100 mm Nos 54 108 135 162
GN014 MS / GI Pipes Cutting Upto Dia 125 to 200 mm Nos 39 77 96 116
GN015 PVC sleeve pipe cutting and fixing Nos 34 68 84 101
GN016 GI Sleeve pipe cutting Nos 14 27 34 41
GN017 PVC/ GI Sleeve Pipe fixing in wall Nos 18 36 45 54
GN018 PVC/ GI Sleeve Pipe fixing in slab Nos 14 27 34 41
GN019 Painting of Pipes Upto Dia 50 mm Mts 135 270 338 405
GN020 Painting of Pipes Dia 65 to 100 mm Mts 90 180 225 270
GN021 Painting of MS Channel Mts 90 180 225 270
GN022 Duct / Pipe riser support fabrication Nos 14 27 34 41
GN023 Nos 0 0 0
GN024 0 0 0
GN025 0 0 0
GN026 0 0 0
GN021 0 0 0
GN022 0 0 0
GN023 0 0 0
GN024 0 0 0

1 of 1
Productivity Norms - R3
S.No.
DESCRIPTION OF ACTIVITY - HVAC Unit REMARK

Pers

Pers

Pers

Pers
on

on

on

on
1

4
AC001 Duct (Upto 300mm Width) Installation With Supports SqMts 10 20 25 30
AC002 Duct ( 301 to 600 mm Width) Installation With Supports SqMts 13 27 33 40
AC003 Duct ( 601 to 900 mm Width) Installation With Supports SqMts 16 32 40 48
AC004 Duct (Above 900 mm Width) Installation With Supports SqMts 20 40 50 60
AC005 Duct (Upto 300mm Width) Installation In Existing Supports SqMts 16 32 40 48
AC006 Duct ( 301 to 600 mm Width) Installation In Existing Supports SqMts 20 40 50 60
AC007 Duct ( 601 to 900 mm Width) Installation In Existing Supports SqMts 20 40 50 60
AC008 Duct (Above 900 mm Width) Installation In Existing Supports SqMts 27 53 67 80
AC009 motorized dampers fixing Nos 10 20 25 30
AC010 Pre insulated duct installtion 301 mm 600 mm SqMts 11 23 28 34
AC011 Pre insulated duct installtion 601 mm 900 mm SqMts 13 26 32 39
AC012 Duct Insulation without Corners & Canvas Clothing SqMts 24 48 60 72
AC013 Canvas Clothing SqMts 32 64 80 96
AC014 Duct Insulation with Corners & Canvas Clothing SqMts 20 40 50 60
AC015 Chilled water pipe installation with Existing supports upto 2'' Mts 31 62 77 92
AC016 Chilled water pipe installation with Existing supports upto 2 1/2'' to 4" Mts 31 62 77 92
AC017 Chilled water pipe installation with Existing supports upto 5'' to 6" Mts 25 50 63 75
AC018 Chilled water pipe installation with Existing supports upto 8'' to 10" Mts 15 30 38 45
AC019 Chilled water pipe installation with Existing supports upto 12'' to 14" Mts 12 24 30 36
AC020 Chilled water pipe installation with Existing supports upto 16'' to 18" Mts 9 17 21 26
AC015 Chilled water pipe installation with supports upto 2'' Mts 11 21 26 32
AC016 Chilled water pipe installation with supports upto 2 1/2'' to 4" Mts 9 18 22 26
AC017 Chilled water pipe installation with supports upto 5'' to 6" Mts 6 12 15 18
AC018 Chilled water pipe installation with supports upto 8'' to 10" Mts 5 10 13 15
AC019 Chilled water pipe installation with supports upto 12'' to 14" Mts 4 8 10 12
AC020 Chilled water pipe installation with supports upto 16'' to 18" Mts 3 6 7 9
AC021 Chilled water pipe insulation Dia upto 2'' Mts 13 27 33 40
AC022 Chilled water pipe insulation Dia 2 1/2'' to 4" Mts 11 23 29 34
AC023 Chilled water pipe insulation Dia 5'' to 6" Mts 9 18 22 27
AC024 Chilled water pipe insulation Dia 8'' to 10" Mts 7 15 18 22
AC025 Chilled water pipe insulation Dia 12'' to 14" Mts 6 12 15 18
AC026 Chilled water pipe insulation Dia 16'' to 18" Mts 6 11 14 17
AC027 FCU / VAV fixing / Hanging Nos 3 7 8 10
AC028 FCU / AHU / Fan / VAV Mouth ( Flexible Duct) Connection Nos 5 10 13 15
AC029 FCU valve package Assembly & fixing Nos 1 3 3 4
AC030 FCU valve package (Ready made) fixing Nos 2 4 5 6
AC031 AHU Ch Water pipe Conn with Valve Package 2'' Nos 1 3 3 4
AC032 AHU Ch Water pipe Conn with Valve Package 2 1/2'' to 4" Nos 1 2 3 3
AC033 Duct cladding below 300 mm SqMts 9 17 22 26
AC034 Duct cladding 301 mm to 600 mm SqMts 10 20 25 30
AC035 Duct cladding Above 600 mm SqMts 14 29 36 43
AC036 Pipe cladding below 100 mm Mts 9 17 22 26
AC037 Pipe cladding 125 mm to 200 mm Mts 8 15 19 23
AC038 Pipe cladding Dia 250 to 300 mm Mts 7 14 18 21
AC039 Pipe cladding Dia 350 to 600 mm Mts 6 13 16 19
AC040 Supply diffuser fixing in tiles Nos 4 7 9 11
AC041 Return diffuser fixing in tiles Nos 7 15 18 22
AC042 Supply diffuser fixing in gypsum F/C Nos 4 7 9 11
AC043 Return diffuser fixing in gypsum F/C Nos 7 15 18 22
AC044 VCD / NRD fixing Nos 10 20 25 30
AC045 Fire damper fixing Nos 8 16 20 24
AC046 Copper pipe bracing upto 1 5/8" dia (joints) Nos 17 33 42 50
AC047 Copper pipe bracing above 1 5/8" dia to 2 5/8' (joints) Nos 10 20 25 30
AC048 Refreigent piping work with insulation upto 7/8" dia Mts 19 38 48 57
AC049 Refreigent piping work with insulation above 7/8" dia Mts 13 26 33 39
AC050 Pressure testing of Split unit Ref. Pipes Nos 5 9 11 14
AC051 Indoor Split unit fixing Nos 5 9 11 14
AC052 Outdoor unit fixing Nos 5 9 12 14
AC053 Split unit Commisioning Nos 5 9 11 14
AC054 FCU / Exhaust Fan / Indoor unit Wiring Termination Nos 5 9 11 14
AC055 Wired Thermostat Fixing & wiring Nos 5 9 11 14
AC056 Outdoor unit Wiring Termination Nos 5 9 11 14
AC057 Inline exhaust fan fixing Nos 3 6 8 9
AC058 Roof mounted fan installation Nos 5 9 11 14
AC059 Wall mounted fan installation Nos 6 12 15 18
AC060 Installation of pre-insulated CHW Pipes Upto 4'' Mts 8 17 21 25
AC061 Installation of pre-insulated CHW Pipes-5'' TO 8'' Mts 4 7 9 11
AC062 Installation of pre-insulated CHW Pipes-10'' TO 14'' Mts 3 6 7 9
AC063 Installation of pre-insulated CHW Pipes-16'' TO 20'' Mts 2 5 6 7
AC064 Installation of pre-insulated CHW Pipes-24'' TO 26'' Mts 2 4 5 6
AC065 Return Air Grille Fixing Nos 20 40 50 60
AC066 Supply Air Grille Fixing Nos 13 27 33 40
AC067 Motorized dampers fixing Nos 7 13 17 20

1 of 2
Productivity Norms - R3
S.No.
DESCRIPTION OF ACTIVITY - HVAC Unit REMARK

Pers

Pers

Pers

Pers
on

on

on

on
1

4
AC068 Chilled water pumps instalation Nos 1.0 2 3 3
AC069 Duct accoustic installtion SqMts 13 27 33 40
AC070 Fresh air /exhaust louver installtion Nos 9 18 23 27
AC071 Sound attenuator installation Nos 1 3 3 4
AC072 Duct joint insulation Nos 11 22 27 32
AC073 Duct joint foster Nos 14 27 34 41
AC074 Welding of CHW pipe joints dia 65 to 80 mm Nos 14 27 34 41
AC075 Welding of CHW pipe joints dia 100 to 125 mm Nos 11 22 27 32
AC076 Welding of CHW pipe joints dia 150 mm Nos 9 18 23 27
AC077 Welding of CHW Pipe joints dia 200mm Nos 8 15 19 23
AC078 Welding of CHW Pipe joints dia 250 mm Nos 7 14 17 20
AC079 Welding of CHW Pipe joints dia 300 mm Nos 6 12 15 18
AC080 Welding of CHW Pipe joints dia 350mm Nos 5 11 14 16
AC081 Chemical pouring for pre insultd. CHW pipe dia Upto 150 mm Nos 6 12 15 18
AC082 Chemical pouring for pre insultd. CHW pipe dia 200 to 300 mm Nos 5 11 14 16
AC083 Chemical pouring for pre insultd. CHW pipe dia 350 to 400 mm Nos 5 10 12 15
AC084 Chemical pouring for pre insultd. CHW pipe dia 400 to 600 mm Nos 5 9 11 14
AC085 Jet diffuser fixing Nos 6 11 14 17
AC086 Linear slot diffuser fixing Mts 6 11 14 17
AC087 Duct / Pipe riser support fabrication Nos 9 18 23 27

2 of 2
Productivity Norms - R3
S.No.
DESCRIPTION OF ACTIVITY - Electrical Unit REMARK

Perso

Perso

Perso

Perso
n

n
1

4
EL001 GI Trunking Installation With Support Fixing Mts 27 53 67 80
EL002 GI Trunking Installation With existing Supports Mts 44 89 111 133
EL003 Cable Tray Installation With Support Fixing (Up to 300 mm Width) Mts 13 27 33 40
EL004 Cable Tray Installation With Support Fixing (301 to 600 mm Width) Mts 11 22 28 33
EL005 Cable Tray Installation With Support Fixing (601 to 900 mm Width) Mts 10 20 25 30
EL006 Cable Tray Installation With Existing Support (Up to 300 mm Width) Mts 25 50 63 75
EL007 Cable Tray Installation With Existing Support (301 to 600 mm Width) Mts 22 44 56 67
EL008 Cable Tray Installation With Existing Support (601 to 900 mm Width) Mts 20 40 50 60
EL009 C Channel Fixing in Riser For Cable Tray work Nos 13 27 33 40
EL010 Cable Tray Installation in Riser With Existing Support (Up to 300 mm Width) Mts 18 36 45 55
EL011 Cable Tray Installation in Riser With Existing Support (301 to 600 mm Width) Mts 14 29 36 43
EL012 Cable Tray Installation in Riser With Existing Support (601 to 900 mm Width) Mts 12 24 29 35
EL013 GI Clamp Fixing for Conduiting Nos 50 100 125 150
EL014 GI conduiting (Straight) with Existing supports Mts 80 160 200 240
EL015 GI conduiting (with bends) with Existing supports Mts 50 100 125 150
EL016 GI conduiting (Straight) with Drilling & Support Fixing supports Mts 50 100 125 150
EL017 GI conduiting (With Bends)with Drilling & Support Fixing supports Mts 36 72 90 108
EL018 PVC conduiting in slabs / core walls Points 7 13 20 27
EL019 PVC Floor conduiting Mts 54 108 135 162
EL020 Wire Pulling for Lighting (DB to 1st Light & Switch) Circuit 3 6 8 9
EL021 Wire Pulling for Lighting (Light to Light point Looping) Point 27 54 68 81
EL022 Single core Power wiring (DB to 1st Socket) Mts 10 20 25 30
EL023 Single core Power wiring (Socket to Socket Looping) Point 5 10 13 15
EL024 Single core Power wiring for Equipments (WH,FCU,AC,Pump) Point 20 40 50 60
EL025 Fixing of earth link (for Tray / Trunking) Nos 25 50 63 75
EL026 Cable pulling in Duct Pipe (3/ 4 C Up to 10 sq mm )+ Earth Cable Mts 67 133 167 200
EL027 Cable pulling in Duct Pipe (3/ 4 C 16 to 35 sq mm )+ Earth Cable Mts 36 73 91 109
EL028 Cable pulling in Duct Pipe (3/ 4 C 50 to70 sq mm )+ Earth Cable Mts 25 50 63 75
EL029 Cable pulling in Duct Pipe (3/ 4 C 95 sq mm )+ Earth Cable Mts 16 32 40 48
EL030 Cable pulling in Duct Pipe (3/ 4 C 120 sq mm )+ Earth Cable Mts 11 23 29 34
EL031 Cable pulling in Duct Pipe (3/ 4 C 150 sq mm )+ Earth Cable Mts 10 20 25 30
EL032 Cable pulling in Duct Pipe (3/ 4 C 185 sq mm )+ Earth Cable Mts 8 16 20 24
EL033 Cable pulling in Duct Pipe (3/ 4 C 240 sq mm )+ Earth Cable Mts 7 13 17 20
EL034 Cable pulling in Duct Pipe (3/ 4 C 300 sq mm )+ Earth Cable Mts 6 11 14 17
EL035 Cable pulling in Duct Pipe (1 / 2C Upto 6 sq mm )+ Earth Cable Mts 400 800 1000 1200
EL036 Cable pulling in Duct Pipe (1 / 2C 10 to 35 sq mm )+ Earth Cable Mts 267 533 667 800
EL037 Cable pulling in Duct Pipe (1 / 2C 50 to 70 sq mm )+ Earth Cable Mts 200 400 500 600
EL038 Cable pulling in Duct Pipe (1/ 2 C 95 to 400 sq mm )+ Earth Cable Mts 67 133 167 200
EL039 Cable Laying in Tray / Ladder(3/ 4 C Upto 10 sq mm )+ Earth Cable Mts 133 267 333 400
EL040 Cable Laying in Tray / Ladder (3/ 4 C 16 to 35 sq mm )+ Earth Cable Mts 100 200 250 300
EL041 Cable Laying in Tray / Ladder (3/ 4 C 50 to70 sq mm )+ Earth Cable Mts 50 100 125 150
EL042 Cable Laying in Tray / Ladder (3/ 4 C 95 sq mm )+ Earth Cable Mts 31 62 77 92
EL043 Cable Laying in Tray / Ladder (3/ 4 C 120 sq mm )+ Earth Cable Mts 22 44 56 67
EL044 Cable Laying in Tray / Ladder (3/ 4 C 150 sq mm )+ Earth Cable Mts 20 40 50 60
EL045 Cable Laying in Tray / Ladder (3/ 4 C 185 sq mm )+ Earth Cable Mts 16 32 40 48
EL046 Cable Laying in Tray / Ladder (3/ 4 C 240 sq mm )+ Earth Cable Mts 13 27 33 40
EL047 Cable Laying in Tray / Ladder (1C 630 sq mm )+ Earth Cable Mts 10 20 25 30
EL048 Cable Dressing in Tray / Ladder (3/ 4 C Upto 70 sq mm )+ Earth Cable Mts 80 160 200 240
EL049 Cable Dressing in Tray / Ladder (3/ 4 C 95 to1500 sq mm )+ Earth Cable Mts 67 133 167 200
EL050 Cable Dressing in Tray / Ladder (3/ 4 C 185 to 240 sq mm )+ Earth Cable Mts 50 100 125 150
EL051 Wood Fixing & Leveling for GI Back Box Nos 20 40 50 60
EL052 GI Box fixing Nos 45 90 113 135
EL053 PVC conduiting in Walls Nos 20 40 50 60
EL054 Clock tower light fixing Nos 5 9 11 14
EL055 Cable glanding for street light Nos 27 54 68 81
EL056 Switches and sockets fixing Nos 39 77 96 116
EL057 Duct pipe laying Mts 54 108 135 162
EL058 Light fixtures Template Marking Nos 34 68 84 101
EL059 Drilling For Light Fixtures Nos 20 40 50 60
EL060 Light fixtures installation with Existing Drilling Nos 14 29 36 43
EL061 Fire alarm wiring Mts 18 36 45 54
EL062 Fire alarm wiring Points 6 12 15 18
EL063 Cabling for CCTV ,PA,Tel& Data ,Access control Points 9 18 23 27
EL064 Floor box installation in Screed Nos 5 9 11 14
EL065 Floor box installation in Raised Floor Nos 9 18 23 27
EL066 DB Back Box Fixing Nos 6 12 15 18
EL067 DB (8 / 12 way) Dressing & Termination Nos 1 2 2 3
EL068 DB (4 / 6 way) Dressing & Termination Nos 2 4 5 6
EL069 SMDB installation Nos 0 0.8 1 1
EL070 IT termination Nos 14 27 34 41
EL071 Floor box power termination Nos 27 54 68 81
EL072 Fire alarm accessories installation with addressing Nos 12 25 31 37
EL073 Fire alarm panel installation with Dressing Nos 1 1 2 2
EL074 Speaker installation Nos 12 25 31 37

1 of 2
Productivity Norms - R3
S.No.
DESCRIPTION OF ACTIVITY - Electrical Unit REMARK

Perso

Perso

Perso

Perso
n

n
1

4
EL075 CCTV installation Nos 8 15 19 23
EL076 Isolator fixing With termination Nos 27 54 68 81
EL077 Wall cutting & conduiting Nos 9 18 23 27
EL078 Cable termination (Lugs) Nos 13 20 33 40
EL079 Cable gland Work Upto 4Cx10 mm Nos 20 40 50 60
EL080 Cable gland Work 4Cx 16 to 50 mm Nos 6 11 14 17
EL081 Cable gland Work 4Cx 70 & Above Nos 14 28 35 42
EL082 Testing & Commissioning ( Continuity & Insulation resistance) – Lighting , Power & Earthing Points 0 20 30 40
EL083 Testing & Commissioning ( Continuity) - Fire Alarm System ) Points 0 20 30 40
EL084 Rope Pulling in Duct Pipes & PVC , GI Conduits Points 0 15 20 30
EL085 Mandrel Test Points 0 50 100 150
EL086 PVC Conduiting Installation In Open Surface - Above false ceiling Points 0 20 30 40
EL087 Checking Installed Existing PVC Conduits in Slab , Floor , External Area Points 0 15 20 30
EL088 Checking Installed Existing Ducts in Slab , Floor , External Area Points 0 50 70 100
EL089 Lightning Arrestor System Copper Tape Clamp Installation Points 0 30 40 60
EL090 Lightning Arrestor System Copper Tape Installation Points 0 30 60 90
EL091 Lightning Arrestor System System Air Rod With Base Installation Points 0 10 15 20

2 of 2
Productivity Norms - R3
S.No.
DESCRIPTION OF ACTIVITY - Plumbing Unit REMARK

Perso

Perso

Perso

Perso
n

n
1

4
PL001 PPR pipe installation in H/L in Existing Supports Mts 15 30 38 45
PL002 PPR pipe installation in Wall Mts 18 36 45 54
PL003 Copper pipe installation H/L in Existing Supports -15mm to 35mm Mts 77 154 193 231
PL004 Copper pipe installation H/L in Existing Supports -42 mm to 67 mm Mts 68 135 169 203
PL005 Copper pipe installation H/L in Existing Supports -78 mm to 108mm Mts 54 108 135 162
PL006 Support fixing on pedestal @ Roof for Copper Pipe Nos 31 62 77 92
PL007 Copper pipe installation @ Roof in Existing Supports -15mm to 35mm Mts 108 216 270 324
PL008 Copper pipe installation @ Roof in Existing Supports -42 mm to 67 mm Mts 90 180 225 270
PL009 Copper pipe installation @ Roof in Existing Supports -78 mm to 108mm Mts 54 108 135 162
PL010 Joint Insulation of Water Pipes @ Roof Mts 21 42 52 62
PL011 Joint Insulation of Water Pipes @ H/L Mts 14 27 34 41
PL012 Joint Brazing of Copper pipe Upto Dia 54 mm Nos 32 64 79 95
PL013 Joint Brazing of Copper pipe Dia 54 to 67mm Nos 27 54 68 81
PL014 Joint Brazing of Copper pipe Dia 78 to 108mm Nos 21 42 52 62
PL015 Bath Room H/LCopper pipe installation in Existing Supports Nos 1 2 3 3
PL016 EWC / Bidet assembly & Installation floor mounted Nos 3 6 8 9
PL017 EWC / Bidet assembly & Installation wall mounted Nos 2 4 5 6
PL018 Counter tap wash basin fixing with Seal Nos 3 6 8 9
PL019 Wall mounted wash basin fixing Nos 3 6 8 9
PL020 Bath Tub fixing Nos 0 0.7 1 1
PL021 Shower Tray Fixing Nos 2 4 5 6
PL022 Urinal Fixing Nos 2 4 5 6
PL023 Ablution flaucet fixing Nos 21 42 52 62
PL024 Paper towel dispenser fixing Nos 12 25 31 37
PL025 Hand dryer fixing Nos 10 21 26 31
PL026 Towel rail fixing Nos 10 21 26 31
PL027 Robe Hooks fixing Nos 10 21 26 31
PL028 Toilet paper holder fixing Nos 12 25 31 37
PL029 Soap holder fixing Nos 10 21 26 31
PL030 Soap holder in Tile Nos 4 8 10 12
PL031 Pantry sink with mixer fixing Nos 1 2 3 3
PL032 Jonitor Sink Nos 2 4 5 6
PL033 Bath mixer Nos 2 4 5 6
PL034 Wash Basin mixer Nos 2 4 5 6
PL035 Water Heater Fixing Nos 2 3 4 5
PL036 Drainage pipe installation H/L in Existing Supports -Dia 50mm to 110mm Mts 61 121 152 182
PL037 Drainage pipe installation H/L in Existing Supports -Dia 160mm Mts 50 100 125 150
PL038 Bath Room Drainage pipe installation Nos 1 2 3 3
PL039 Waste pipe installation Mts 25 49 61 74
PL040 Floor trap Fixing Nos 4 7 9 11
PL041 Gully trap Installation Nos 2 3 4 5
PL042 RWO Fixing Nos 3 7 8 10
PL043 Grating Fixing Mts 5 10 13 15
PL044 Isolating valve Fixing Upto 2 1/2 " Nos 6 12 15 18
PL045 Isolating valve Fixing Above 2 1/2 " Nos 4 8 10 12
PL046 Concealed valve Fixing Nos 3 6 8 9
PL047 Flow control valve installation Nos 6 12 15 18
PL048 Non return valve installation Nos 4 8 10 12
PL049 PRV installation Nos 1 2 3 3
PL050 Air relief valve installation Nos 6 12 15 18
PL051 Float valve installation 1 1/4'' to 2'' Nos 4 8 10 12
PL052 Bib tap fixing Nos 8 16 20 24
PL053 Water meter installation Upto 50 mm dia Nos 4 8 10 12
PL054 Water meter installation Above 50 mm dia Nos 3 6 7 9
PL055 FF pipe threading Dia Upto 50 mm Piece 16 32 40 48
PL056 FF pipe Grooviing Dia 65 to 100 mm Piece 11 23 29 34
PL057 FF pipe Grooviing Dia 125 to 200 mm Piece 9 18 22 27
PL058 FF pipe installation with existing threading Dia Upto 50 mm with Existing Support Mts 45 91 114 136
PL059 FF pipe installation with existing Grooving Dia 65 to100 mm with Existing Support Mts 45 91 114 136
PL060 FF pipe installation with existing Grooving Dia 125 to 150 mm with Existing Support Mts 38 77 96 115
PL061 FF pipe installation with existing Grooving Dia 200 to 250 mm with Existing Support Mts 22 44 56 67
PL062 FF pipe installation with existing threading Dia Upto 50 mm with Support Mts 16 32 40 48
PL063 FF pipe installation with existing Grooving Dia 65 to100 mm with Support Mts 14 28 34 41
PL064 FF pipe installation with existing Grooving Dia 125 to 150 mm with Support Mts 11 22 28 33
PL065 FF pipe installation with existing Grooving Dia 200 to 250 mm with Support Mts 7 13 17 20
PL066 Fire extinguisher carbon dioxide type (4.5 kg) Nos 10 20 25 30
PL067 Fire extinguisher dry powder type (6 liter) Nos 10 20 25 30
PL068 Fire extinguisher AFFF powder type (6 liter) Nos 10 20 25 30
PL069 Fire blanket installation Nos 10 20 25 30
PL070 Fire hose reel cabinet installation ( 25 mm dia* 30 m long) Nos 2 3 4 5
PL071 Fire hydrant with valve fixing Nos 1 2 2 3

1 of 2
Productivity Norms - R3
S.No.
DESCRIPTION OF ACTIVITY - Plumbing Unit REMARK

Perso

Perso

Perso

Perso
n

n
1

4
PL072 4 way breeching inlet Nos 2 4 5 6
PL073 Landing valve - Wet Riser Nos 2 4 5 6
PL074 HDPE Pipe installation -35 mm to 100 mm Mts 15 31 38 46
PL075 HDPE Pipe installation -110 mm to 250 mm Mts 13 25 31 38
PL076 HPVC Pipe installation -35 mm to 100 mm Mts 25 50 63 75
PL077 HPVC Pipe installation -110 mm to 250 mm Mts 15 31 38 46
PL078 50mm dia Solenoid valve Nos 2 4 5 6
PL079 Drainage pipe laying works ( upvc) B/G (All Sizes) Mts 18 36 45 55
PL080 GRP panel water tank, size 3000 x 2000 x 1000 (22 SqMt) Nos 0 0 0.33 0
PL081 GRP panel water tank, size 3000 x 2000 x 2000 (32 SqMt) Nos 0 0 0.23 0
PL082 GRP panel water tank, size 3000 x 2000 x 3000 (42 SqMt) Nos 0 0 0.18 0
PL083 GRP panel water tank, size 3000 x 2000 x 4000 (52 SqMt) Nos 0 0 0.14 0
PL084 vent cowls installation Nos 40 80 100 120
PL085 Floor clean out Installation Nos 1 3 3 4
PL086 Bubbler Fixing For Irrigation Nos 16 32 40 48
PL087 Sprayer Fixing For Irrigation Nos 10 20 25 30
PL088 Lateral Line Laying For Irrigation Roll 1 1 1 2
PL089 Rectangular Box Fixing For Irrigation Nos 8 16 20 24
PL090 Pump Installation Nos 0 1 0.5 1
PL091 Nos 0 0 0 0
PL092 Nos 0 0 0 0
PL093 0 0 0 0
PL094 0 0 0 0