Professional Documents
Culture Documents
Content
1 Introduction
2 Construction Flow Chart
3 Quantity
4 Equipment list
5 Work schedule
6 Work Procedure for Interception Facility
7 Work Procedure of rebar work
8 Work Procedure of rebar work
9 Work Procedure of scaffolding
10 Work Procedure of Concrete work
11 Quality Management
12 Safety Management
Attached Documents
Attachment – 1 Construction Schedule
Attachment – 2 Wire mesh catalogue
Attachment – 3 Step concrete work for SDT
Attachment – 4 Expansion joint material
Attachment – 5 Wall form work drawing and calculation
Attachment – 6 Drawings and calculations for temporary scaffolding
Attachment – 7 Inspection and Testing plan (SDT)
Attachment – 8 Risk assessment
Attachment – 9 FDT plan
0
1
1. Introduction
This method describes ground foundations, pile head treatment, lean concrete placement,
rebar and formwork installation, concrete placement and Sludge Digestion Tank
The method statement consists of site preparation, material supply, quality plan and other
related work to contractor’s responsibility for implementation of the construction work in
accordance with the project’s specification.
1
2. Construction Flow Chart
Summary of construction work flow chart for Sludge Digestion Tank is shown below.
3. Quantity
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
2
(1) Sludge digestion Tank
※Methods statement for steel handrails, steel stairs and painting (anti-corrosion coating) and
Asphalt roofing are to be submitted separately.
4. Equipment list
List of major equipment are listed below.
3
No. Description Unit Quantity
1 Surveying Equipment set 1
2 Generator 125KVA set 1
3 Submersible Pump set 2
4 Electric Welding Machine set 1
5 4t truck with crane set 1
6 Concrete Cutting Saw / Concrete Cutter set 1
7 Excavator 0.5 or 0.7/ Long Arm Excavator unit 1
8 Bulldozer 3B set 1
9 Plate Compactor/Tamping Rammer/10t roller set 1
10 Pile pressing Machine unit 1
11 Rough Terrain Crane 25t unit 1
12 Dump Truck unit 2
13 Concrete Pump Car 8t/10t/16t unit 1
14 Truck Mixer 5~6㎥ unit 10
15 Concrete Vibrator ( φ60×1 φ50×2 φ32×1) unit 4
16 Par Loader unit 1
5. Work schedule
Schedule of Sludge digestion Tank shown in Attachment – 1
4
Check the height of the bottom of the excavation and excavate to the bottom sand
(EL.6.5). The excavated sand is transported by pay loader to the temporary area.
2.
Cross section
5
Lean concrete is casting used hopper with a 25 t crane and a 20 t crane.
Plan
20t Crane
Maximum Operation radius is 17m
Hoper(0.5t)+Concrete(0.3㎥:0.71t)=1.21t
25t Crane
Maximum Operation radius is 20m
Hoper(0.5t)+Concrete(0.5㎥:1.2t)=1.7t
6
Temporary H100×100-beams are installed when casting of the inside of the PHC pile. The
temporary H100×100-beams are used as the supports for scaffolding and supports. After
the top slab has been casting, the H-beam is cut and removed and casting concrete. The
H100×100-beam is installed by a 25t crane
Cross section
H-Beam detail
Plan
7
5. Casting concrete Base slab EL10.05(Tank side)
Rebars and formwork for the Base slab are installed and concrete is casting by concrete
pump truck. Also install wire mesh 1 m pitch to prevent concrete sliding above the
slope side.
※The method of installation the rebar, formwork and concrete is in accordance with the
attached work procedures.
Wire mesh catalogue shown in Attachment – 2.
Step concrete work for SDT shown in Attachment – 3
The steps for casting concrete plan are to be submitted separately
Working plan
8
After the casting concrete and the formwork is removed, sand is backfilled into the base slab to
level the base of the scaffolding and Support.
Cross section
6. Casting
concrete Base
slab EL9.55(Pump room side)
Rebars and formwork for the base slab are installed and concrete is casting by concrete
pump truck. Water stop material for expansion joints is installed prior to casting and
after the concrete is casting, joint filler material is installed to form the expansion joint.
After concrete is casting on the other side, remove the top joint filler material for
expansion joint and fill with sealant. (Detailed installation method are provided in the
catalog.)
※The method of installation the rebar, formwork and concrete is in accordance with the
attached work procedures.
Plan
Cross section
After casting base slab EL9.55 (Pump room side), rebar and formwork for the wall
(EL12.0) are installed and concrete is casting by concrete pump truck. Expansion joint
water stop is installed only for Below EL11.3.
20mm
Joint material thickness is proposed at 20 mm.
Drawing sheet No 73
※The method of installation the rebar, formwork and concrete is in accordance with the
attached work procedures.
Plan
Cross section
EL11.3
10
After Casting concrete wall EL12.0 (Pump room side), sand backfill around SDT and
northwest side STP area. FDT should be conducted every 500 m3 based on the FDT.
Compaction should be carried out every 30 cm by watering and 10t -roller, but 1 m near
structures that cannot be compacted with a 10-ton roller should be compacted every 15 cm
with a plate compactor or rammer.
※ FDT plan shown in Attachment – 9
.
Sand backfill area
: Access road
Cross section
Plan
Cross section
Scaffolding image
11
9. Casting concrete wall EL13.7(Pump room side)
After casting wall EL12.85 (Tank side), rebar and formwork for the wall (EL13.7) are
installed and concrete is casting by concrete pump truck.
※The method of installation the rebar, formwork and concrete is in accordance with the
attached work procedures.
Plan
Cross section
10. Casting concrete middle slab and wall EL12.6(Pump room side)
After casting wall EL13.7 (Pump room side), rebar and formwork for the middle slab
(EL12.6) are installed and concrete is casting by concrete pump truck.
※The method of installation the rebar, formwork and concrete is in accordance with the
attached work procedures.
Cross section
Plan
12
11. Casting concrete wall EL14.35(Tank side)
After casting middle slab EL12.6 (Pump room side), rebar and formwork for the wall
(EL14.35) are installed and concrete is casting by concrete pump truck.
※The method of installation the rebar, formwork and concrete is in accordance with the
attached work procedures.
Plan
Cross section
13
12. Casting concrete top slab EL16.60(Tank side)
After casting wall EL14.35 (Tank side), rebar and formwork for the top slab (EL16.60)
are installed and concrete is casting by concrete pump truck.
※The method of installation the rebar, formwork and concrete is in accordance with the
attached work procedures.
Plan
Cross section
13. Casting concrete top slab EL13.95(Pump room side) and top slab opening(Tank side)
After casting top slab EL16.60 (Tank side), rebars and formwork for the top slab
(EL13.95) (Pump room side) and top slab opening (Tank side)are installed and concrete
is casting by concrete pump truck.
※The method of installation the rebar, formwork and concrete is in accordance with the
attached work procedures.
Plan
Cross section
14
14. Casting concrete wall of scum storage EL15.6(Pump room side)
After casting top slab EL13.95(Pump room side) and top slab opening (Tank side),
rebar and formwork for the wall (EL15.6) are installed and concrete is casting by
concrete pump truck.
※The method of installation the rebar, formwork and concrete is in accordance with the
attached work procedures.
Plan
Cross section
15
15. Casting concrete top slab of scum storage EL15.85(Pump room side)
After casting concrete wall of scum storage EL15.6 (Pump room side), rebar and
formwork for the top slab (EL15.85) are installed and concrete is casting by concrete
pump truck.
※The method of installation the rebar, formwork and concrete is in accordance with the
attached work procedures.
Plan
Cross section
16
16. Casting concrete for stairs and middle slab(inside)(Pump room side)
After casting concrete top slab of scum storage (EL15.85), rebar and formwork for
stairs and middle slab are installed and concrete is casting by concrete pump truck.
※The method of installation the rebar, formwork and concrete is in accordance with the
attached work procedures.
Plan
Cross section
17. Casting concrete for stairs(outside) and Hand hole(outside) (Pump room side)
After casting stairs and middle slab (inside), rebar and formwork for stairs and middle
slab (outside) and Hand hole(out side) are installed and concrete is casting by concrete
pump truck.
※The method of installation the rebar, formwork and concrete is in accordance with the
attached work procedures.
17
18. Leakage test up to EL14.8(Tank side)
After casting concrete top slab EL15.85, remove sand from base slab and fill water to
EL14.8 using well water. Then conduct leak check.
Cross section
18
※Methods statement for steel handrails, steel stairs and painting (anti-corrosion coating) and
Asphalt roofing are to be submitted separately.
7.1 Material
1) Reinforcement bar strength is SD390.
2) SLS will be used Dia. 14,16,20,22,25
3) The reinforcement steel bar must be free of rust, paint, oil, grease, mud or any
other substance that may prevent adhesion with the concrete, as well as other
elements that may cause corrosion or erosion.
4) The size and length of the reinforcement steel bar should not be less than the
values shown in the submitted drawings.
19
(The strength of the spacer shall be equal to or greater than the strength of the
concrete.)
3) The quantity of spacers that are placed in the concrete shall be more than 2
units per 1㎥on the sides of the structure, and more than 4units per 1㎥ on
the bottom surface.
4) Before placing the concrete shall be rapidly reviewed the accuracy of the
placement and cleanliness of the reinforcing bar, and if necessary those must be
adjusted correctly.
5) Unless specified in the Drawings or required by the Consultant, concrete
covering shall meet the requirement shown in the table below, with tolerance
approximately equal ±3mm.
7.3 Joints
1) Joints shall not be permitted except in the places that are shown on the
Drawings and accepted by the Consultant in writing.
2) Joints shall be done by overlapping the ends in a length not shorter than 35
times of the diameter of the steel bar, fastening them with tie wire.
3) Position of joint adjacent rebar shall be provided by shifting to each other.
8.2 Structure
1) Forms shall be placed in the shapes, elevations and dimensions designed
adequately for the structure, and shall be so constructed as to prevent
deformation due to load, drying and wetting, vibration and other causes.
2) Forms shall be fitted in accurate alignment to assure surfaces free from
irregularities.
3) Unless otherwise instructed by the Consultant, the Contractor shall use forms
that allow making beveled at the corners of reinforced concrete structure.
20
4) Forms and joints shall be sufficiently tight to prevent leakage of grout and
cement paste during placing of concrete.
5) The form and brackets shall be installed on a firm ground or reinforced
concrete base, so that they can support the weight and load during the
construction being prohibited untying bundle.
6) Forms shall be structured considering easy installation and dismantling, and
shall be readily removable without impact, shock, or damage to the concrete.
Formwork shall be fixed in correct position according to working drawings.
And dimensions of the form shall be inspected by the Consultant.
8.3 Assembling
1) Studs and walls shall be spaced to prevent distortion of the formed material
2) Forms shall be designed, constructed, and maintained to insure that after their
removal the finished concrete members will have true surface free of offset,
waviness or bulges.
3) In places where the water proof paint is applied on the inside walls, the remover
of formwork shall not be used.
8.4 Removal
1) When the time of removal of formwork and supports is determined on the basis
of concrete strength tests, removal shall not be started until the concrete has
reached design strength.
2) In principle, the forms are allowed to be removed under the following
compressive strength of concrete;
21
9. Work Procedure of scaffolding
9.1 Assembly
1) Scaffolding is a temporary structure used to support access and working
platform of structure.
2) The component consists of base jack, U-head, load bearing base, scaffold
coupler, and scaffold part.
3) The scaffolding shall be made of safe and appropriate materials maintained in
good condition, with a size and shape sufficient and with endurance necessary
for the works.
4) After the scaffolding is completed, the scaffolding should have a sheet on the
outside.
5) The flooring isn’t using a material deformed, damaged, or corroded
6) The width of the flooring is material more than 40 cm.
7) No damage or corrosion to the taut fittings.
8) No damage or corrosion on joint fittings.
9) The height of the lower is part of the baseboard between 15 cm and 40 cm, or
the baseboard is at least 15 cm high.
22
10) The handrail properly is attached to the gable end with a
minimum height of 85 cm.
11) Jack-up type bases with fittings and root clamps. And sill
plates are not damaged or corroded.
12) Rootstock must be secured by clamps.
13) Handrails/railing frames should be installed at staircase
openings.
Drawings and calculations for temporary scaffolding for the wall shown in Attachment
–6
Class of Concrete
Item Usage
For all the reinforced concrete structures such as elevated water tank, Reservoir tank,
Class A
valve box etc.
For thrust block, lean-mixed concrete foundation, leveling concrete, pipe supporting base
Class B
etc.
Mix Design
23
Cement water Sand Rock W/B S/A Admixture Slump Remark
Class
(Kg) (L) (Kg) (Kg) (cc) (cm)
Lean
B 285 180 890 1100 0.63 0.45 1800 10±2.5 Concrete
RC
Structure
A 330 175 870 1090 0.53 0.44 2400 12.5±2.5 Air
Content<4%
10.2 Concrete Casting
1) Position and level of each structures shall be measured from reference point.
2) Before concrete casting, dust or other foreign materials shall be removed from
inside of forms by spreading water, so that it shall be cleaned and keep wet.
3) In order to prevent segregation of concrete, the total time, ranging from the
start of mixing until the completion of the placement, shall not exceed the
standards listed below.
Total time ranging from the start of Max. 2.0 hours Max. 1.5 hours
mixing until the completion of the
placement
STP site
24
CPAC Plant 12 Boeng Snor
4
STP site
25
10.3 Compaction
1) Immediately after placing, each layer shall be compacted with a mechanical
vibrator. The form shall be beaten with hammer for uniform placing.
(Prepare four vibrators φ60 :1nos φ50:2nos φ35:1nos on the site,
including spares.)
2) The number of units and power of the vibrating equipment shall at all times be
adequate to properly consolidate all the concrete. And vibrators are inserted
less than every 50 cm of one layer.
3) If placing concrete in more than two layers separately, concrete in the upper
layer shall be placed carefully installing the vibrator 0.10m below from the top
of existing layer, in principle, before the bottom layer begins to harden, so that
both layers remain incorporated later.
4) After concrete placement, re-vibration is performed after the bleeding is
confirmed
10.4 Construction Joint
1) If the new concrete layer is placed on the concrete already placed, the
Contractor shall completely remove the layer of grout, poor-quality concrete
and loose aggregate grains from the surface of old concrete by chipping an
electric drill also laitance is removed by wire brush, and moisture the surface
sufficiently
2) The area where the new concrete is placed must to be filed down with a wire
brush or by sand blasting, removing surface water. Before placing of new
concrete, the form must be firmly rested.
3) The Contractor shall, present to the Consultant the plan of construction joint
prior to the concrete work for his approval. The location of the construction
joint shall not affect structural characteristics, durability, impermeability and
appearance of the structure.
10.6 Curing
1) After placing the concrete, curing must be performed so that the concrete
maintains the temperature and moisture necessary for the generation of effects
and is not affected by adverse reactions.
2) When a level of tightening becomes enough for working without risk of
damaging the surface the exposed portion shall be covered with a curing tarp or
wet cloth, keeping the wet condition more than 5 days or longer after surface of
concrete become cold.
26
10.7 Quality Test
1) Parameter for testing
Concrete Temperature
Slump
Air Content
Unit Volume Weight of water (Only Class A)
Chloride Content
Compressive Strength of Test Piece
WC
No Description Specification
1 Concrete compressive Max Capacity: 1000KN
machine Ram diameter: 180mm
2 Concrete mold size 1 Diameter 100mm Height 200mm
2 Diameter 150mm Height 300mm
3 Pool for curing mold Size:2950mm×700㎜×700㎜
Pool temperature:27℃~33℃
2) Sampling Test
The slump test and air content, unless otherwise directed by the Consultant,
shall be made in principle in each 20m3 of concrete or each structure under
continuous placing.
The standard value of slump shall be in 5 to 12 cm. The standard value of air
content shall be less than 4.0%.
The period and the frequency of sampling for testing the compressive strength
test of concrete and controlling the ratio of water and cement, in principle,
and unless otherwise instructed by the Consultant, at least once on the volume
27
of concrete placed in one day at each site, or once every 20㎥ of concrete
placed continuously, de pending on the importance of the structures and the
magnitude of the work.
The number of samples shall be six (6) in each sampling. The three (3) of
those shall be tested for 7 days strength and others for 28 days strength.
2) Separators
28
Use 9 mm separators and prevent cracking at the separator position, as
bleeding water is a major cause of settlement cracking, taking into account the
speed, height and placing sequence.
3) Surface cracks.
Reticulated cracks that form on the surface due to rapid evaporation of water
from the top surface after the concrete has been placed. If the evaporation of
water from the surface is higher than the rise in bleeding, the surface tends to
dry out and stiffen easily, so start watering immediately after pressing is
completed. Tapping should be carried out immediately after placing as concrete
cracks can occur due to settlement caused by consolidation and bleeding
phenomena. Check the weather and avoid direct sunlight. Prepare sheets, etc.
Prevent the temperature of concrete from rising at the time of placing by
cooling materials such as mixing water and aggregate, and spraying water to
control temperature rise.
If this should occur, the concrete should be re-shaken and recovered by
tamping or other treatment.
4) Cold Joint
The two main causes of cold joints are 'overlaying after the prescribed time'
and 'improper casting', and it is important to control the time interval between
overlaying of the upper and lower layers. Control of placing time and jointing
time as quality control. The planned placing sequence of the placing layers
should be controlled.
5) Honeycomb
Honeycomb occurs due to 'separation of materials' and 'insufficient compaction'
when placing concrete, etc. As countermeasures, the falling height of the
placing should be kept below 1.5 m to prevent separation of materials, the
compaction layer should be kept below 50 cm, and vibrators 60 mm and 40 mm
should be prepared and used for the following. Vibrator placement drawing
blow.
6) Poor joint
Planning times for layers and controlling the implementation time as a
countermeasure against poor joints. Control the joint height (marking on the
vibrator) and use a hose or similar to ensure that the vibrator can be inserted at
the bottom of the joint surface. Insert the vibrator vertically 30 cm spacing. Be
careful not to touch the rebar, steel frame, wiring, and formwork into which the
vibrator is poured.
29
At this time, if the vibration time is too long, the aggregate will sink to the
bottom and the paste will rise too. Much. Insert the vibrator vertically30cm
spacing. Be careful not to touch the rebar, steel frame, wiring, and formwork
into which the vibrator is poured.
The vibration is applied for 5 to 15 seconds. At this time, if the vibration time is
too long, the aggregate will sink to the bottom and the paste will rise too much.
8) Thermal crack
Concrete is exothermic due to the hydration reaction between cement and
water, and the resulting rise and fall in temperature causes deformation
(expansion and contraction) of the concrete, which, when internally or
externally constrained, causes tensile stress in the concrete and cracking, to
prevent concrete temperatures from rising, check the weather and avoid direct
sunlight. Prepare sheets, etc. Prevent the temperature of concrete from rising at
the time of placing by cooling materials such as mixing water and aggregate
cooled with ice, and spraying water to control temperature rise. Since a
thickness of 50 cm or more is considered mass concrete, more attention should
be paid to temperature control during casting concrete.
30