MUSE MRL Date : 7 Aug 2012

Sheet / Sheets : 1 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

1. Controller Installation

Install the controller, LCRD(Regen Drive), ARO & EIP according to a shop drawing.
Controller UD/LCRD* ARO E&I Panel
Model
Standard Standard Option Standard
Muse Top floor
Overhead
landing
*) ”Regen” logo is indicated at the box of LCRD & UD.

[Data plate for LCRD(or UD)]

[LCRD (or UD)]

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 2 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

1.1. Controller
Install controller as following figures.

< Steel beam < Concrete


structure > structure >

< Steel beam


structure with < Concrete
ARO > structure with
ARO >

*) The function of ARO is equal to the function of ARD (or ALP)

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 3 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

1.2. EIP (E&I Panel)


Install EIP at top landing as following photos

EIP

Fixing
bracket

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 4 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

[Shop drawing]

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 5 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

Controller UD/LCRD ARO EIP


Model
Standard Standard Option Standard
Muse MMR Machine room

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 6 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

2. Machine room wiring

GeN2 MMR(w/ LCRD) GeN2 MRL


KAA21311AB

2.1. 3 phases wiring [Building DB  EIP]

R – S – T, N(Neutral) & Earth shall be provided to EIP.

[EIP]
R – S – T, N(Neutral) & Earth (EIP to Controller)

TB2

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 7 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

2.2. Lighting power wiring [EIP  Controller]

 No need for lighting power from building DB.


 Connect 1 of 3 phases and neutral.

4E

R S T N

4E of controller Hoistway
(Car fan & light) & pit light

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 8 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

2.3. 3 phases wiring [Controller  Drive (UD, LCRD, 60CR)]

-.OVFR3B-401/402 UD – w/o ARO

TB1

TB2

-.OVFR2B-403/404 & OVF2A-406(60CR)

TB2
TB1
TB1

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 9 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

2.4. 3 phases wiring [Drive (UD, LCRD, 60CR)  Motor]

-.OVFR3B-401/402 UD – ARO+GGP 1.5T, 2.0T

TB7

PIN

-.OVFR2B-403/404 – optimized 2.6T, 3.2T, 4.1T

TB7

U,V,W

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 10 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

2.5. Connection [Controller  EIP]

GeN2 MMR(w/ LCRD) GeN2 MRL


KAA21311AB

Field panel

SPBC-2

AP-I/O

START CONN. Function END CONN.


1E 8P Safety line at hoistway, brake power EC1 8P
3E 8P Landing door jumper EC3 7P
4E 2P Car lighting (220Vac) FSK1 TERM
P4M 9P ERO line for EPI EC2 9P
PX5 8P CAN communication SPBC-P100 9P

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 11 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

2.1.6. Connection between controller & drive

-.OVFR3B-401/402 UD

Field panel

DCPB

AP-I/O

START CONN. Function END CONN.


(Field panel) (Drive)
1D 4P CAN Communication P2(DCPB) 4P
2D 4P UIB/DIB power (110Vac) P1(DCPB) 4P
3D 2P Brake power (GGP) P5(DCPB) 4P
5D 4P Brake_SFC P21(DCPB) 4P
6D 3P Brake_I-BRK P8(DCPB) 3P
10D 7P Brake power (24Vdc), BS1/2 P7(DCPB) 6P
Signal (BOMCO-W)
PX8 7P PRS P3(DCPB) 5P

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 12 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

-.OVFR2B-403/404 LCRD

START CONN. Function END CONN.


(Field panel)
1D 4P CAN communication P8(GDCB) 4P
2D 4P UIB/DIB power(110Vac) P11(GDCB) 10P
3D 2P Brake power P111(HVIB) 4P
5D 4P Brake_SFC(MRL) P102(HVIB) 4P
6D 3P Brake_I-BRK P6(HVIB) 3P
10D 7P Brake power(24Vdc), BS1/2 P5(GDCB) 7P
signal (BOMCO-W)
PX8 7P PRS(1LV, 2LV, UIS,DIS, THB) P6(GDCB) 9P

-.OVFR2A-406 60CR

START CONN. Function END CONN.


(Field panel) (Drive)
1D 4P CAN communication P8(GDCB) 4P
2D 4P UIB/DIB ower (110Vac) P11(GDCB) 10P
5D 4P Brake_SFC, BRK power(24Vdc) P102(PDB- 4P
2)
PX8 7P PRS(1LV, 2LV, UIS, DIS, THB) P6(GDCB) 9P

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 13 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

2. 7. Connection between DRIVE & MOTOR_BRK

-.OVFR3B-401/402 UD + GGP 1.5T, 2.0T

START CONN. Function END CONN.


P7 6P BS1, BS2(Machine brake), THB 140C P2 6P
P8 3P BRK DC+, BRK DC- P1 3P

P8:1 BRK_DC+ P1:1

P8:2 B M
BRK_DC- P1:3 BV U
B1 BRK
power
P1:2 PE
P8:3
B
Machine

P7:2 P2 1
Machine
BS1 1/BN BS1
P2 3 4/BK
P2 2 3/BU
P7:3 BS2 BRK S/W
P2 4 1/BN BS2
P2 6 4/BK
P7:1 24V P2 5 3/BU
P7:4
Return
Machine W/ BS
Machine W/O BS

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 14 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

-.OVFR3B-401/402 UD + BOMCO-W

START CONN. Function END CONN.


7D 4P BS1, BS2(Machine brake), THB 140C TERM
P2
4D 3P BRK DC+, BRK DC-, BRK_PE TERM

4D 1
P2:5
BRK_DC+
B
BV B M BRK
4D 3 B1
P2:6
U power
BRK_DC-
4D 2 PE
P2:9
B
BRK_PE
Machine

NC1 P2:2 7D 1 BS1

COM1 P2:1 7D 3
BS1 BSR*30VDC
NO1
7D 4 BS2

NC2 P2:4 7D 2
BRK S/W

COM2 P2:3
BS2
NO2

Machine Brake

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 15 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

-.OVFR2B-403/404 LCRD + GGP/Optimized 2.6T, 3.2T, 4.1T

START CONN. Function END CONN.


P5 7P BS1, BS2(Machine brake) P2 6P
4D 3P BRK DC+, BRK DC- P1 3P

4D 1 P1:1 P5:1
BS1

BRK_DC+ B BRK S/W


B M P5:2 BS2
4D 3 B1
P1:3 U
BV
BRK_DC-
PE P5:3
4D 2 P1:2
B Machine
Machine P5:4
P2 1 1/BN BS1
P2 3 4/BK
P2 2 3/BU
P5:6 24V
P5:7 P2 4 1/BN
Return BS2
P2 6 4/BK
P2 5 3/BU

Machine W/O BS
BRK
Machine W/ BS
power

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 16 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

-.OVFR2B-403/404 LCRD +WAN-YUAN/BOMCO-W

START CONN. Function END CONN.


7D 4P BS1, BS2(Machine brake), THB 140C P2 TERM
4D 3P BRK DC+, BRK DC-, BRK_PE P1 TERM

4D 1 P1:1

BRK_DC+ B
B M
4D 3 U
B1 BRK
P1:3 BV
power
BRK_DC-
4D 2 P1:2 PE
B
Machine

NC1 P2:2 7D 1 BS1

COM1 P2:1 7D 3
BS1 BSR*30VDC
NO1
7D 4 BS2

NC2 P2:4 7D 2 BRK S/W

COM2 P2:3
BS2
NO2

Machine Brake

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 17 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

-. OVFR2B-403/404 LCRD/60CR +BOMCO2-S

START CONN. Function END CONN.


7D 4P BS1, BS2(Machine brake), THB 140C TERM
P2
4D 3P BRK DC+, BRK DC-, BRK_PE TERM

4D 1
P2:5
BRK_DC+
B
BV B M BRK
B1
4D 3
P2:6
U power
BRK_DC-
4D 2 PE
P2:9
B
BRK_PE
Machine

NC1 P2:2 7D 1 BS1

COM1 P2:1 7D 3
BS1 BSR*30VDC
NO1
7D 4 BS2

7D 2
BRK S/W
NC2 P2:4

COM2 P2:3
BS2
NO2

Machine Brake

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 18 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

-. OVFR2B-403/404 LCRD/60CR +BOMCO2-B

START CONN. Function END CONN.


8D 6P BS1, BS2(Machine brake), THB 140C TERM
P2
4D 3P BRK DC+, BRK DC-, BRK_PE TERM

4D 1
P2:5
BRK_DC+
B
BV B M BRK
B1
4D 3
P2:6
U power
BRK_DC-
4D 2 PE
P2:9
B
BRK_PE
Machine

8D 1 P2:2 NC1
BS1

BS1
8D 3 P2:1 COM1
BSR*30VDC

8D 4 P2:4 NC2

8D 2 BS2
BRK S/W
P2:3 COM2

BS2 8D 5

P2:6 NC3
BS3 8D 6
BS3
P2:5 COM3

Machine Brake

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 19 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

2.8. Hoistway wiring

START CONN. Function END CONN.


DCPB(UD)
P9 GDCB(LCRD) 8P ENC(Rotary Encoder) ENC 8P
GDCB(60CR)

START CONN. Function END CONN.


P3M 3P Governor (GRS) TERM 3P

START CONN. Function END CONN.


P7 5P R-ENC(Sub_Encoder)_MRL PIN 4P

2.9. Wiring for ARO (Automatic Rescue Operation)

*)MRL
START CONN. Function END CONN.
(EIP) (ARO)
EA1 10P UPS_24V, ARO_ST C1 9P
EA2 4P Drive*110V, MRO*BAT+, C3 2P
EA3 9P BAT*VF, BAT*SPB C2 2P
P3A 2P
P3(BCB) 6P
EA4 10P BAT P4(BCB) 10P

*)MRL/MR
START CONN. Function END CONN.
(HIVB) (ARO)
TB9 TERM MRO+, MRO- C5 3P

*)MRL/MR
START CONN. Function END CONN.
(Field panel) (ARO)
1A 5P CAN_24V, SPB+ C4 5
2A 3P ARO*OUT TB3 TERM

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 20 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

3. Checking connection of shield cable


3.1. Check the CAN bus cable (from drive to controller) to make sure the shield layer
properly connected on both ends of the cable.
Attention: Must connect drain wire to PE on both ends of the cable.

Check the drain wire of this cable

3.2. Check the Motor Cable and make sure the shield layer properly connected on both
ends of the cable.
Attention: Must put the shield layer out of cable skin and use clamps to fasten
shield layer of the cable.

3.3. Check the fixing condition of EMC plate


Attention: EMC plate must be installed on the sheet metal of Regen drive.

Attention: The cable of rotary encoder must be separated with motor 3 phases
cable and the each wire of the encoder cable must be twisted.

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 21 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

1. Shield cable must be


earthed
2. The cable must be
connected by the clamp.

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 22 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

4. MSK connection

4.1. Prepare MSK tool as following (Korean standard)

Items Drawing No. Q’ty Remarks


LSD cable AEG16C771*A/B/C/D 1 Provided by factory
MSK kit assy. FIE00C682*A 1 Field tool kit assy.
Adapter cable AEG01C225*A 1 MSK adapter cable
#2
MSB Unit AEG01C226*A 1 Pendant switch
assy.
Siren or alarm AEG01C227*B 1 Siren assy. (A/V)

Jumper kit Asy


(Field Tool)

Adapter cable #2
(Field tool)
LSD Cable
(Factory supply)
Note) LSD cable will be
used for interphone after
MSK operation.

MSB Unit A/V Alarm

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 23 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

Procedure Location
Remove P102C, P4M, & P104C from factory GECB AP-IO
Connect P102C & P4M to LSD cable after checking
cable number (Type: Wago connector)
Connect P102C, P4M, connectors to controller GECB AP-IO
Connect P104C (jumper connector) GECB AP-IO
Connect 2H (jumper connector) Field panel

Connect GND of LSD to the earth plate

(P102C), (P4M), (P104C)


GECB AP-IO

(2H)
Field panel

1) MSK connectors should be removed after MSK operation.


2) Do not connect any cable without checking.

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 24 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

MSK kit

LSD Cable is for interphone at pit

For connection of Pit E. Stop & GTC

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 25 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

Connection of MSK pendant switch

Pendant switch MSK connector


Common #8 of P102C
Up signal #6 of P4M
Down signal #7 of P4M
Safety chain #1 of P102C
E.stop #9 of P102C

Connection of MSK jumper

P102C (#4 & #5)


P4M (#8 & #9)
P104C (#1 & #2, #2 & #3)
2H (#2 & #4, #4 & #5)

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 26 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

4.1. Bridge of landing door switch

Put the jumper bridge so that Inspection (or INS) is right position as following
drawing (DW LED of GECB will be on)

[Door bypassed]

[Normal condition]

 Door bridge is located at the EIP (E&I panel)


 In case of MMR, door bridge can be at the controller

4.2. CDS(=Car Door Switch/Gate Switch) Jumper


 CDS can be bypassed by the bridge of #4 & #5 of P102C
(DFC(=Door Fully Closed) LED of GECB will be on)

P102C #4 #5

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 27 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

[Hoistway net cable]

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 28 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

4.3. Install safety box and connect as following table for the safety chain.

Housing Connection point Safety line Position


2H-02 SAF-06 GTC
Pit safety box
2H-04 SAF-08 1PES/2PES
*) For MSK, jump between SAF-06 & SAF-09 (GTC, 1PES/2PES), It shall be
removed after MSK operation.

Note) The function of 2H is as followings after MSK.

Housing Connection Function


Controller Hoistway
2H-02 4H-01 SAF-11 Pit lighting
2H-04 4H-02 SAF-12

Pay attention to poor contact for WAGO connector.


It causes abnormal operation.

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 29 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

5. Start-up (MSK)

Before start up, to ensure those:

1. Mechanical installation should be completed for MSK operation. (e.g.


Governor, emergency stop switch, hoistway lighting, running platform,
motor, & etc.
2. Electric connection should be completed for MSK.
3. Follow WWJSSS & local safety regulation.

5.1. Mega check


Remove HL1 & HL2 from PE. If normal, connect again.

Check point Standard


PE & HL1
PE & HL2
More than 0.5 MΩ
PE & Line terminal(L1-L3)
PE & motor terminal(U1-W1)

5.2. Voltage check

 Measure 3 phases voltage & neutral at the line side of OCB after switching on
building power.
 Measure 3 phases voltage & neutral at the line side of OCB after switching on OCB.

Allowance: Rated voltage[Vac]±5%

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 30 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

 Check the output of transformer (TRF1).

PS1
110Vac
PS2

PS3

54Vac

PS4

 Check input & output of SMPS after switching on F2C

220Vac 27Vdc

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 31 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

5.3. GECB check

 PY1 of GECB AP-IO


Pin. No Terminal Standard
1 27Vdc 27Vdc±10%
2 27Vdc 27Vdc±10%
3 HL2 0V
4 HL2 0V
5 27Vdc 27Vdc±10%
6 HL2 0V

 PY2 of GECB AP-IO


Pin. No Terminal Standard
1 110V(Checking points: PY2:3) 110Vac±10%
2 HL1
3 HL1

5.4. RSL(Remote Serial Link) check

Check the volt after removing P1H & P101C, connect back after measurement.
Type Check points Standard
Hall Link P1H:4 & HL2 27Vdc±10%
Car Link P101C:4 & HL2 27Vdc±10%

5.5. Brake power check

GGP/GeN2 1.5T/Optimized GeN2 2.6T/3.2T/4.1T/5T


PS:03 54Vac 54Vdc±10%
PS:04 OS2
BOMCO-1/BOMCO-2/BOMCO-W
PS-03 124Vac(BRK*VAC_P) 124Vdc±10%
PS-04 87.5Vac(BRK*VAC_H)_BOMCO-1 87.5Vdc±10%
PS-05 62Vac(BRK*VAC_P)_BOMCO-2 62Vdc±10%
PS-06 OS5

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 32 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

5.6. Door power supply check


Door motor supply (220Vac)
3C:01 220Vac (L) 220Vac±10%
3C:03 220Vac (N)
Door controller supply (110Vac)
3C:01 110Vac (L) 110Vac±10%
3C:03 OS

5.7. Battery check (at controller)

 Check LED condition of SPBC board (After convert to ERO mode and switching
on OCB.

LED Meaning Condition


BAT-CHARGE Charging / Charging condition
MAINTENANCE Charging finished
FAULT Charging
Battery providing power to
BAT-MODE
SPBC

Off
On
Flickering

Note:
The battery is charged by SPBC. For full charging, at least 8 hours shoul be
charged.
In case of power failure, battery will be discharged by the command of
SPBC_III.

If the power supply is cut for long period (>6hours), disconnect the battery
temporarily.

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 33 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

5.8. Safety chain check (110Vac)

 In case of MSK operation, some of safety switches are bypassed by MSK


adapter kit, but following switches are to be installed & connected

1PES (1st Pit Emergency Switch), 2PES (1st Pit Emergency Switch),
GTC(Governor Tension Check Switch)

5.9. Main board input signal check


To check if input signal of GECB board is correct.
- P104C:1[/1LS-27Vdc], P104C:2[/2LS-27Vdc]
- PX8:7 [MOT_THM – 24Vdc]
- P7:2[BS1 – 24Vdc], P7:3[BS2-24Vdc]
- P1:3[UIB-110Vac], P1:5[DIB-110Vac]

5.10. GECB & SPBC check

-. Check if the signal of car & landing door is correct by LED of SPBC.

DW: Landing door


DFC: Car & landing
door

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 34 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

-. Check communication between CAN & SVT (Service tool).


Conditi
LED Description
on
Off
CAN_OK CAN Bus communication normal On
SPB_OK Software condition ok Flicker

Press
“DDO”

Service Tool
port

Note) DW/DFC shall be capital letter in MSK operation.


Unpublished Work Copyright © OTIS Elevator Company
MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 35 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

-. Check communication between GECB & SPBC.


 Check input status by seeing LED on SPBC
LED Description Status
Off
GRP/J Line voltage error
On
NOR/DIAG Normal mode
Flicker
INS Inspection mode
ES Emergency stop
DW Landing door closed
DFC Door closed (Car/landing)
DOL Open limit switch /
DOB Door open button /
DZ Coor zone
CAN-OK CAN link
RSL Remote serial link

Note) 3 LEDs, INS, DW & DFC, shall be on for MSK operation.

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 36 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

6. Parameter setup

6.1. Parameter of GECB & GDCB will be set by the factory. However setting values are
required to check before real operation.

Refer to parameter list enclosed in the controller.

M-GECB-1-3-1-7-GOON(Service)
SPB Type 255 w/o ARO
0 w/ ARO
M-GECB-1-3-1-4-GOON(Drive)
DRV-TYP 1
M-GECB-1-3-1-1-GOON(System)
TOP Top floor Start from 0
(Bottom floor = 0)
M-GECB-1-3-1-5-GOON(Doors)
Door 13 To be same each
Rear 13 other

-. Check GECB software version


GeN2 MMR, IRIS: GAA30780DAK or higher [M-GECB-1-2-3-GOON(Part)]
GeN2 comfort: GAA30780DAH or higher [M-GECB-1-2-3-GOON(Part)]

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 37 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

31 Contract Min Max Default Actual


Interface Type 0 4 - 1
Drive Type 25 999 - Driver value
ARO Type 1 4 1 1: w/o ARO
4: w/ ARO
Motor Type 100 999 Motor value
Duty speed 10 16000 - Speed
Rated rpm 1 5000 - Motor RPM
Inertia kg/m2 0.1 20000
Encoder Type 0 1 - Encoder
Encoder PPR 1000 10000 -
Duty load 10 16384 No of passenger
AC Main 50 480 380Vac
Load weigh Type 0 3 - Load weighing device type
Balance 0 77 - 45~47
Vane sensor Type 0 99 - PRS type
DDP 0 45 -
Number of DZ 2 140 - Service floor
Bottom DZ 0 20 - 0
DZ in 1LS 0 5 1 No of vane within 1LS zone
E.g. If speed is 60m/min, data shall be 1000. (90m/min=1500, 105m/min=1750)

[Parameter display]

Duty Speed 1.Try to convert to ERO mode for


mm/s changing parameter.
1000> XXXXX
Rated rpm
400> XXXXX

Encoder PPR
3600> XXXXX

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 38 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

32 Adjustment Min Max Default Actual


Profile delay ms 0 10000 0 Increase by 10 in case of
start jerk
VelRate div 0 3 0 0

35 Profile Min Max Default Actual


Insp Speed 10 630 - 300
Nom Speed 0 16000 - Rated speed
Accel 25 1200 -
Decel 25 1200 -
Jerk 100 2400 -
Base Speed(5) 50 100 -

Note) In case of no LWB with roll back, set LWB Type as 0.

-. Check GDCB software version


GeN2 MMR, IRIS: AP230924DAH or higher [M-DRIVE-1-1-GOON]
GeN2 comfort: AP230924DAH or higher [M-DRIVE-1-1-GOON]

-. In case that parameter of PROFILE (M-2-3-5 is changed, actual distance


of LS shall be bigger than the requirement of LS distance in (M-2-1-7).

7. RE (Rotary Encoder) calibration

7.1. If the system is normal, Rotary encoder will be calibrated automatically.


(LRT operation)

RE calibration will be conducted in following 3 cases.


 Resuming power supply and 1st operation
 After changing parameter
 After error outbreak

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 39 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

During LRT operation, noise will come out from the motor,
but it is normal. And it won’t be conducted in normal operation.
If error is detected (Brake drop), it will be conducted.

During LRT operation, do not access car top, hoistway.


 Car will be moved.

The system is normal but a car is not moved even with up/down signal:

7.2. After RE calibration, the car direction should be checked by pressing pendant
switch whether the direction is correct.

-. Follow instruction in following table

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 40 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

Condition Action to be taken


1 Direction is same with command Move to next process
2 Direction is opposite to command Change car direction by SVT.
(Running condition is OK) Car Dir 0/1
<>
3 Car stopped or error outbreak Change 2 motor phases
 Change motor phase by SVT
501 Pos Tracking  Interchange 2 motor phases (HVIB)
000:00:00:00.04
Motor Phase 0/1
<>
502 Vel Tracking
000:00:00:00.04

100 Inv SW Oct


000:00:00:00.04

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 41 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

[To change parameter by SVT]

M 2 3 2
☞ MODULE DRIVE SETUP ADJUSTMENT

Note) Data value shall be “0” or “1”.

Unpublished Work Copyright © OTIS Elevator Company


MUSE MRL Date : 7 Aug 2012
Sheet / Sheets : 42 / 42
DOC No.: Draft
ACD3 CONTROLLER
Testing & Commissioning
MSK Operation (Start-up)

8. Test running

1. Try to run the car whether it moves to designated direction.


2. Check the condition is complied to local safety rules or WWJSSS.
 Siren shall be activated during running if landing door hasn’t
been installed

Controller

Adapter cable
#1

LSD Cable
Cross head

Bottom floor Travelling cable


support

300mm or bigger

400m
m

[Layout for MSK operation]

Unpublished Work Copyright © OTIS Elevator Company