PM DAILY ACTIVITIES REPORT

Job Description : WTP Equipment Maintenance and Services


Unit : Water Softener
Location :
JDE/SAP
Cost center

NO ACTIVITIES DATE START/FINISH Remark

Start
Install Scaffolding
1 Finish
Start
Install Skillet/LOTO
2 Finish
Start
Setting Media Box
3 Finish
Start
Open Manhole Secondary
4 Finish
Start
Open Manhole Primary
5 Finish
Start
Flush out Media Secondary
6 Finish
Start
Flush out Media Primary
7 Finish
Start
Dismantle Strainer Secondary
8 Finish
Start
Dismantle Strainer Primary
9 Finish
Start
Washing/Clean The Media Secondary
10 Finish
Start
Washing/Clean The Media Primary
11 Finish
Start
Install Strainer Secondary
12 Finish
Start
Install Strainer Primary
13 Finish
Start
Flush In Media Secondary
14 Finish
Start
Flush In Media Primary
15 Finish
Start
Close Manhole Secondary
16 Finish
Start
Close Manhole Primary
17 Finish
Start
Dismantle Skillet/LOTO
18 Finish
Start
Dismantle Scaffolding
19 Finish
Start
House Keeping
20 Finish
Start
Working Completed
21 Finish