PM DAILY ACTIVITIES REPORT

Location / Unit : Mechanical Floatation Unit


JDE/SAP :

NO ACTIVITIES DATE Remark

Start
1 Inspect the whole Condition of Unit
Finish

Start
2 Install Scaffolding
Finish

Start
3 Install Skillet/LOTO
Finish

Start
4 Open Manhole
Finish

Clean the Internal and External of Mechanical Flotation Unit such as


Start
5 cleaning floor Disposal and stick slid,wall and roof by using water
cleaner (Solvent)
Finish

Start
6 Cleaning Oil Box

Finish

Start
7 Cleaning Rotor Agitator
Finish

Start
8 Cleaning Skimmer Assembly
Finish

Start
9 Cleaning External MFU
Finish

Start
10 Repair Louder Cover and door Covered Plate
Finish

Start
11 Repair Skimmer Assembly
Finish

Re-paint The Lounder Cover and door by Using Switable paint or Start
12
designated by Company
Finish

Start
13 Replace All Cover Louder and door Gasket

Finish

Start
14 House Keeping
Finish

Start
15 Dismantle Skillet/Loto
Finish

Start
16 Runing test
Finish
Start :
Completed :
Prepared,By Reviewed,By

PT EFK-Supv PT TPE-CS