Professional Documents
Culture Documents
Project:
8 x 135 MW
LIGNITE BASED THERMAL POWER PLANT, BHADRESH
Doc. Title:
Doc No:
RWPL/OPR/CL_
Issue Date: No of Sheets:
02/09/2013
(including cover sheet)
6
Revision Record:
Sr. Verification /
Activity Check
No Remarks
1 Ensure PTWs related to respective areas are returned before normalizing the system &
taking system into service.
2 HT/LT side on 6.6 KV/415 V supply charged, DC voltage, UPS, Battery chargers are
healthy & in service.
3 Ensure all monitoring & testing instrument are put in service & are normal.
4 All protections & interlocks are in service.
5 Ensure Bed material filling system through.
6 Ensure all coal feeders outlet gate is closed.
7 Ensure CW System is started (refer doc. no. RWPL/OPR/SOP_007) & maintain CW
header pressure 0.20Mpa to 0.23Mpa.
8 Ensure ACW System is started (refer doc. no. RWPL/OPR/SOP_005) & maintain CW
header pressure > 0.40Mpa.
9 Ensure CCCW System is started (refer doc no. RWPL/OPR/SOP_006) & maintain
CCCW header pressure > 0.45Mpa.
10 Ensure PAC/IAC with dryer is started (refer doc no. RWPL/OPR/SOP_002) & header
pressure > 0.65Mpa.
11 Ensure local drum gauge glass & hydra step in service.
12 Ensure oil gun cleaning is done & atomization test completed.
13 Ensure LDO line flushing up to oil gun completed & oil strainer cleaned.
14 Ensure LDO pump is lined up & started (refer doc. no. RWPL/OPR/SOP_004) & put in
long recirculation with discharge pressure 2.5Mpa.
15 Ensure hot well make up system is lined up to maintain normal hot well level (650mm to
750mm).
16 Ensure CEP & condensate system is lined up then Start CEP in recirculation.
17 Ensure Deaerator level normal (1800mm to 1900mm) and its pegging has been charged
from PRDS (adjacent unit).
18 Ensure BFP & feed-water system is lined up then start BFP in recirculation.
19 Ensure drum filled up to –100 to –150 mm by using CEP or BFP according to drum
pressure.
20 Ensure Chemical dozing system ready (start dozing by consulting to chemist).
Sr. Verification /
Activity Check
No Remarks
22 Ensure all soot blowers are in retracted condition & soot blower valve is in close
condition.
23 Ensure Coal handling system ready & Coal filled in bunkers.
26 Ensure HP-LP Bypass oil pumps are healthy & recirculation pump ON.
27 Ensure U valve blower, ID fan, SA fan, PA fan lined up and air path through.
28 Ensure two U valve blower are started (refer doc. No. RWPL/OPR/SOP_043) & ensure
proper air flow to both U seal. Put third one on link mode (CV of U seal header to PA
header should be closed & in AUTO mode). Maintain discharge pressure 47KPa
29 Ensure both ID fans are started (refer doc. No. RWPL/OPR/SOP_010) & furnace draft is
between – 50 Pa to + 50 Pa.
30 Ensure both SA fans are started (refer doc. No. RWPL/OPR/SOP_011).
31 Ensure both PA fans are started (refer doc. No. RWPL/OPR/SOP_009).
Ensure loading of PA fan is increased (upto 90,000 Nm³/hr) for proper fluidization of bed
32
material & check for fluidization through view glass.
33 Ensure loading of SA fan is increased (upto 60,000 Nm³/hr).
Ensure RH side gas damper is closed & maintain 30% to 40% of rated air flow (Air flow
34
should be > 138,000 Nm³/hr).
Ensure economizer recirculation valve is open if there is no feed water flow through
35
economiser.
36 Ensure MFT is reset by purging or Hot start PB & LDO in longest recirculation.
37 Ensure EBD and CBD lines are through to maintain drum level -100mm.
38 Ensure ESP fields are OFF & rapping motors are ON. So as to avoid chances of fire.
Lit up Ignition Duct one Oil Gun each side if bed temp.<350. (Take other pair according to
39
need.)
40 Ensure ignition Duct Outlet temp <800 ºC also Flue gas temp rise < 85 oC/hr.
Sr. Verification /
Activity Check
No Remarks
41 All monitoring & testing instrument are put in service & normal .
MOT level > 1670mm & AC lube oil pump running with discharge header pressure
42 0.3Mpa ± 0.05Mpa.& AC Jacking oil pump running with discharge header pressure 15
MPa ± 1.5 MPa.
43 Turbine is on barring gear.
44 Heaters are ready with water side valves open & steam side valves closed
45 Water seal for GSC, LPH-6 and LPH-7 header charged & established.
53 Charge MS line by slowly opening IBV. Then open MS stop valve and close IBV.
58 Ensure vacuum breaker valve close then start vacuum pumps and pull vacuum.
Sr. Verification /
Activity Check
No Remarks
Start the coal inching when average bed temp.> 325˚C and Monitor the Bed temp. & %
59
O2
60 Gradually increase the coal feeding and gradually decrease the oil consumption.
Ensure rate of rise of cyclone inlet temperature should be less than 80˚C/hr & metal
61
temperature difference of top & bottom of drum less than 50˚C.
62 Ensure outer metal temperature of ignition duct & u-seal is normal at all locations.
Ensure CT fans are lined up & started (refer doc.no. RWPL/OPR/SOP_031) to maintain
63
CW inlet temperature between 30˚C to 34˚C.
64 Ensure HRH & CRH line drains are open.
65 Ensure HP/LP bypass oil pump lined up & started (refer doc.no. RWPL/OPR/SOP_034).
Ensure that the rotating speed is raised to 3000 rpm (@250rpm per minute) & warm up
79
for 5 minutes.
Sr. Verification /
Activity Check
No Remarks
81 Ensure AOP is stopped at 3000 rpm and MOT exhaust fan is running.
95 Ensure that turbine casing drains & MS line drains closed at 34MW load.