January February March April May June July August September October November December
1 Packing Hall AHU 01 Admin Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
2 Packing Hall AHU 02 Admin Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
3 Packing Hall AHU 03 Admin Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
4 Packing Hall AHU 04 Admin Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
5 Chilled Water AHU 01 Admin Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
6 Chilled Water AHU 02 Admin Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
Compressor
7 Compressor AHU 01 Room Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
Compressor
8 Compressor AHU 02 Monthly Planned Planned Planned Planned
Room Roof
Actual Actual Actual Actual
January February March April May June July August September October November December
9 Dehumidifier 01 Admin Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
10 Dehumidifier 02 Admin Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
11 FAHU 01 Utility Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
12 FAHU 02 Utility Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
13 Dehumidifier 01 Seasoning Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
14 Dehumidifier 02 Seasoning Roof Monthly Planned Planned Planned Planned
14 Dehumidifier 02 Seasoning Roof Monthly
Actual Actual Actual Actual
January February March April May June July August September October November December
15 AHU 01 Cool Point Seasoning Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
16 AHU 01 Cool Point Seasoning Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
17 AHU 01 ASRS Outside Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
FGWH Loading
18 AHU 02 Monthly Planned Planned Planned Planned
Dock
Actual Actual Actual Actual
January February March April May June July August September October November December
19 Exhaust Fan 01 QA Lab Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
20 Exhaust Fan 02 QA Lab Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
21 Exhaust Fan 03 QA Lab Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
22 Exhaust Fan 04 QA Lab Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
23 Exhaust Fan 05 Utility Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
24 Exhaust Fan 06 Utility Roof Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
Cold Store
25 Exhaust Fan 07 Monthly Planned Planned Planned Planned
inside(PC32)
Actual Actual Actual Actual
January February March April May June July August September October November December
RPM Roof (PC 32
26 Exhaust Fan 09 Monthly Planned Planned Planned Planned
Seasoning)
Actual Actual Actual Actual
January February March April May June July August September October November December
27 TEF 07 PC 32 Fryer Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
28 TEF 08 PC 32 Fryer Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
KK Seasoning
29 TEF 11 Monthly Planned Planned Planned Planned
Drum
Actual Actual Actual Actual
January February March April May June July August September October November December
30 TEF 12 KK Fryer Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
31 TEF 13 PC 50 Blancher Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
32 TEF 14 PC 32 Blancher Monthly
32 TEF 14 PC 32 Blancher Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
33 TEF 15 PC 50 Fryer Inlet Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
chiller and Air
34 Cooling Tower compressor Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
35 GD Compressors Compressor room Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
36 N2 Dryers GD Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
37 Compressors Atlas Copco Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
Air Dryer Atlas Copco Planned Planned Planned Planned
Actual Actual Actual Actual
intenance Schedule of Utilities 2022
Frequency
Sr.# Maintenance Checks Check Clean
Hours
1 Check Diesel Day Tank Level Daily
2 Check Engine Oil Level Daily
3 Check Radiator Coolant Level Daily
4 Inspect Diesel Generator for Leaks Daily
5 Check Air Filter Restriction Indicator Daily
6 Check Charge Alternator Daily
7 Drain Water from Primary Fuel Filters Daily
19 Check Coolant Lines & Radiator Hoses for Wear 8 Months 300 Hrs.
& Cracks
20 Check Electrical Connections (Batteries, Starter 8 Months 300 Hrs.
Motor & Alternator Connections
21 Check Engine Ground 8 Months 300 Hrs.
22 Clean Radiator Matrix 8 Months 300 Hrs.
23 Replace Air Cleaner Element 8 Months 300 Hrs.
24 Replace Engine Oil & Filters 8 Months 300 Hrs.
25 Replace Water Seperator Element 8 Months 300 Hrs.
Date: __ /___/____
Chilled duct
29
diffusers
Packaging HALL
Dehumidifier Grills = 05 nos
Diffuser Grills
QTY Pc 32 QTY
Exahust
9 duct 14
diffusers
Chilled
duct 17
diffusers
9 31
nos
Preventive Maintenance Plan
Chilled, Exhaust, Fresh Air Ducts Diffuser Grills & Halton H
Schaff
11 Chilled duct diffusers Cleaning 9 Boota Tabassum
PC 32
12 Exahust duct diffusers Cleaning. 14 Boota Tabassum
13 Chilled duct diffusers Cleaning 17 Boota Tabassum
aging Hall
As per Boil out
/stock count
PepsiCo Planned Maintenance Schedule of Utilities 2022
January February March April May June July August September October November December
1 Strainer 01 Process water Pump 01 Y Type Pump Room Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
2 Strainer 02 Process water Pump 02 Y Type Pump Room Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
3 Strainer 03 Process water Pump 03 Y Type Pump Room Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
4 Strainer 04 Main RO HP Pump 02 Y Type Pump Room Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
5 Strainer 05 3rd RO Feed water Tank 01 Y Type Pump Room Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
Cooling Tower Circulation Compressor
6 Strainer 06 Y Type Monthly Planned Planned Planned Planned
Pump 01 Room
Actual Actual Actual Actual
January February March April May June July August September October November December
Cooling Tower Circulation Compressor
7 Strainer 07 Y Type Monthly Planned Planned Planned Planned
Pump 02 Room
Actual Actual Actual Actual
January February March April May June July August September October November December
8 Strainer 08 Chilled Water Pump 01 Y Type Chiller Roon Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
9 Strainer 09 Chilled Water Pump 02 Y Type Chiller Roon Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
10 Strainer 10 Chilled Water Pump 03 Y Type Chiller Roon Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
11 Strainer 11 Cooling Tower Pump 01 Y Type Chiller Roon Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
12 Strainer 12 Cooling Tower Pump 02 Y Type Chiller Roon Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
Chiller Roon Monthly January February March April May June July August September October November December
13 Strainer 13 Cooling Tower Pump 03 Y Type Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
14 Strainer 14 Thermal Oil Pump 01 Y Type Thermal Room Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
15 Strainer 15 Thermal Oil Pump 02 Y Type Thermal Room Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
16 Strainer 16 Thermal Oil Re-Filling Pump 01 Y Type Thermal Room Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
17 Strainer 17 Thermal Oil Re-Filling Pump 02 Y Type Thermal Room Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
18 Strainer 18 Diesel decanting Pump 01 Y Type Diesel Decanting Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
19 Strainer 19 Diesel decanting Pump 02 Y Type Diesel Decanting Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
Water Reservoir
20 Strainer 20 Recycle ROCD Pump 01 Y Type Planned Planned Planned Planned
Roof
Actual Actual Actual Actual
January February March April May June July August September October November December
21 Strainer 21 Boiler Feed Water Pump 01 Y Type Boiler Room Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
22 Strainer 22 Boiler Feed Water Pump 02 Y Type Boiler Room Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
23 Strainer 23 Old FF Pump 01 Y Type Pump Room Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
24 Strainer 24 CHW AHU 01 Y Type Utility Roof Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
25 Strainer 25 CHW AHU 02 Y Type Utility Roof Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
26 Strainer 26 Packing Hall AHU 01 Y Type Admin Roof Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
27 Strainer 27 Packing Hall AHU 02 Y Type Admin Roof Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
28 Strainer 28 Packing Hall AHU 03 Y Type Admin Roof Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
29 Strainer 29 Packing Hall AHU 04 Y Type Admin Roof Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
30 Strainer 30 Natural Gas Line Near UPS Room Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
31 Strainer 31 Natural Gas Line Behind VO Tanks Planned Planned Planned Planned
Actual Actual Actual Actual
d Maintenance Schedule of Utilities 2022
Compressor
6 Strainer 06 Cooling Tower Circulation Pump 01 Y Type Room Monthly
Compressor
7 Strainer 07 Cooling Tower Circulation Pump 02 Y Type Monthly
Room
Diesel
18 Strainer 18 Diesel decanting Pump 01 Y Type
Decanting
Diesel
19 Strainer 19 Diesel decanting Pump 02 Y Type
Decanting
Water
20 Strainer 20 Recycle ROCD Pump 01 Y Type
Reservoir Roof
Behind VO
31 Strainer 31 Natural Gas Line
Tanks
Date: __ /___/____
January February March April May June July August September October November
1 Turbine 03 Gate 02 Monthly Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
Admin Front
2 Turbine 02 Monthly Planned Planned Planned Planned
Canteen
Actual Actual Actual Actual
January February March April May June July August September October November
Storm water Pump 01 Centrifugal Laundary area Monthly Planned Planned Planned Planned
3 Actual Actual Actual Actual
January February March April May June July August September October November
Storm water Pump 02 Centrifugal Laundary area Monthly Planned Planned Planned Planned
4 Actual Actual Actual Actual
January February March April May June July August September October November
Storm water pump 03 Centrifugal Laundary area Monthly Planned Planned Planned Planned
5 Actual Actual Actual Actual
January February March April May June July August September October November
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
Preventive & Periodic Maintenance Plan for Centrifugal Pum
Electrical
Inspection Test DE
GE Value
Vibration
Motor Inspection Sound
Current Ampere
Rated Ampere
Motor
Temperature
Motor Inspection
Inspection Test
Frequency
Check Status
Inspect Motor Isolator 1-W
Inspect Motor Ground 1-W
Inspect Motor Resistance 1-W
Inspect Motor Terminal Box for Cables Looseness 1-W
ce Plan for Centrifugal Pumps
aintenance
0.5
0.5
1
0.2
0.5
1
0.5
0.2
0.5
1
1
1
2
0.5
0.5
0.5
0.5
0.5
al
ection
Inspection Test
Work Duration Comments
Status
0.1
0.2
0.2
0.5
Preventive Maintenance Plan
AHU 01(Packing Hall)
Date: __ /__ /____ Location: Admin Roof
Last
Sr.# Maintenance Checks Frequency Check Clean Replace Next Due Remarks
replaced
Mechanical
Rated:______ Current:_______
E&I
Fresh air duct Temperature sensor
19 Monthly
inspection.
Remarks
Last
Sr.# Maintenance Checks Frequency Check Clean Replace Next Due Remarks
replaced
Mechanical
Rated:______ Current:_______
E&I
Fresh air duct Temperature sensor Daily visually inspection
19
inspection. during linewalk
Last
Sr.# Maintenance Checks Frequency Check Clean Replace Next Due Remarks
replaced
Mechanical
Rated:______ Current:_______
E&I
Fresh air duct Temperature sensor Daily visually inspection
19
inspection. during linewalk
Last
Sr.# Maintenance Checks Frequency Check Clean Replace Next Due Remarks
replaced
Mechanical
Rated:______ Current:_______
E&I
Fresh air duct Temperature sensor Daily visually inspection
19
inspection. during linewalk
Last
Sr.# Maintenance Checks Frequency Check Clean Replace Next Due Remarks
replaced
Mechanical
Rated:______ Current:_______
Last
Sr.# Maintenance Checks Frequency Check Clean Replace Next Due Remarks
replaced
Mechanical
Rated:______ Current:_______
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
9 VFD inspection.
13 Drain check.
14 Strainer cleaning.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
9 VFD inspection.
13 Drain check.
14 Strainer cleaning.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
10 VFD inspection.
14 Drain check.
15 Strainer cleaning.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
10 VFD inspection.
14 Drain check.
15 Strainer cleaning.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
8 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
8 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
10 VFD inspection.
14 Drain check.
Inlet and outlet flexible connection
16
inspection
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
10 VFD inspection.
14 Drain check.
Inlet and outlet flexible connection
16
inspection
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
4 Gas inspection.
Rated:______ Current:_______
9 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
4 Gas inspection.
Rated:______ Current:_______
9 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
4 Gas inspection.
Rated:______ Current:_______
9 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
4 Gas inspection.
Rated:______ Current:_______
9 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
2 Platform Cleaning
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
2 Platform Cleaning
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
2 Platform Cleaning
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
2 Platform Cleaning
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
2 Platform Cleaning
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
2 Platform Cleaning
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
2 Platform Cleaning
Rated:______ Current:_______
10 VFD inspection.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
Rated:______ Current:_______
14 VFD inspection.
15 Platform cleaning.
Comments:
Sr.# Maintenance Checks Frequency Check Clean Replace Last replaced Next Due Remarks
4 Clean compressor.
Comments:
Sr # Filters Area Size (Inch) Company Pressure (Bar) Quarter # 01 Quarter # 02 Quarter # 03 Quarter # 04
January February March April May June July August September October November
1 CPR Main Header Stainer Outer Area 2.5 KITZ 16 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
2 CPR Steam Line Stainer Utility 2.5 KITZ 16 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
Ketchup/Mayo Hot Water
3 Tank Stainer Outer Area 1 Local 16 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
Ketchup Main Steam Planned Planned Planned Planned
4 Header Stainer Ketchup 2 KITZ 16
Actual Actual Actual Actual
January February March April May June July August September October November
Ketchup Condensate Tank
5 Outer Area 2 KITZ 16 Planned Planned Planned Planned
Stainer
Actual Actual Actual Actual
January February March April May June July August September October November
6 DCM Condensate Tank Outer Area 2 KITZ 16 Planned Planned Planned Planned
Stainer
Actual Actual Actual Actual
January February March April May June July August September October November
DCM Hot Water Tank Planned Planned Planned Planned
7 Outer Area 1 Local 16
Stainer
Actual Actual Actual Actual
January February March April May June July August September October November
Noodle Backside Planned Planned Planned Planned
8 Outer Area 1.5 Local 16
Condensate Tank Stainer
Actual Actual Actual Actual
January February March April May June July August September October November
Noodle Backside Hot Planned January Planned Planned Planned
9 Outer Area 1.5 Local 16
Water Tank Stainer
Actual Actual Actual Actual
February March April May June July August September October November
Noodle Palm Oil Tank 60 Planned January Planned Planned Planned
10 Outer Area 1 Local 16
Ton
Actual Actual Actual Actual
February March April May June July August September October November
Noodle Palm Oil Tank 13 Planned January Planned Planned Planned
11 Outer Area 1 KITZ 16
Ton
Actual Actual Actual Actual
February March April May June July August September October November
12 Noodle 600 Noodle 2 KITZ 16 Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
13 Noodle 800 Noodle 2 KITZ 16 Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
14 Kettle 1 Ketchup 1 KITZ 16 Planned January Planned Planned Planned
14 Kettle 1 Ketchup 1 KITZ 16
Actual Actual Actual Actual
February March April May June July August September October November
15 Kettle 2 Ketchup 1 KITZ 16 Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
16 Kettle 3 Ketchup 1 KITZ 16 Planned January Planned Planned Planned
Actual Actual Actual Actual
Schedule of Steam Stainers 2019
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
UPFL Planned Maintenance Schedule of PSVs Planned Inspection 2019
Sr # Filters Area Type of Media Set Pressure Popping Pressure Quarter # 01 Quarter # 02 Quarter # 03 Quarter # 04
January February March April May June July August September October November
1 Boiler 4 PSV 1 Boiler House Steam 10 Bar 10.4 Bar Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
2 Boiler 4 PSV 2 Boiler House Steam 10 Bar 10.6 Bar Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
3 Boiler 4 Economiser PSV Boiler House Water 20 Bar 20.2 Bar Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
4 Open Kettle Ketchup Steam 3 Kg/Cm2 3.8 Kg/Cm2 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
5 Vaccum Kettle 1 Ketchup Steam 4.5 Kg/Cm2 5.2 Kg/Cm2 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
6 Vaccum Kettle 2 Ketchup Steam 4.5 Kg/Cm2 65 PSI Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
7 Vaccum Kettle 3 Ketchup Steam 4.5 Kg/Cm2 65 PSI Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
8 Noodle 300 Heat Exchanger Noodle Steam 10 Kg/Cm2 Circuit Off Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
9 Noodle 600 Heat Exchanger Noodle Steam 10 Kg/Cm2 8.4 Bar Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
10 Noodle 800 Heat Exchanger Noodle Steam 10 Kg/Cm2 8.9 Bar Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
11 Altas Copco 1 New Utility Hub Air 9 Kg/Cm2 Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
12 Altas Copco 2 New Utility Hub Air 9 Kg/Cm2 Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
13 Sanco VS-20 1 Utility Roof Air 9 Kg/Cm2 10.2 Bar Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
14 Sanco VS-20 2 Utility Roof Air 9 Kg/Cm2 10.1 Bar Planned January Planned Planned Planned
14 Sanco VS-20 2 Utility Roof Air 9 Kg/Cm2 10.1 Bar
Actual Actual Actual Actual
February March April May June July August September October November
15 Process Water Supply Outer Area Water 5 Kg/Cm2 Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
16 Fire Fighting Header Outer Area Water 8 Kg/Cm2 Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
17 DCM Open Kettle DCM Steam 5 Kg/Cm2 3.6 Bar Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
18 Autoclave DCM Steam 8 Kg/Cm2 3 Bar Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
19 HFO Circuit Fuel Line Outer Area Fuel 6 Kg/Cm2 Circuit Off Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
20 CPR Main Header Outer Area Steam 9 Kg/Cm2 Circuit Off Planned January Planned Planned Planned
Actual Actual Actual Actual
edule of PSVs Planned Inspection 2019
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
UPFL Planned Maintenance Schedule of PSVs Planned Inspection 2019
Sr # Filters Area Type of Media Set Pressure Popping Pressure Quarter # 01 Quarter # 02 Quarter # 03 Quarter # 04
January February March April May June July August September October November
1 Boiler 4 PSV 1 Boiler House Steam 10 Bar 10.4 Bar Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
2 Boiler 4 PSV 2 Boiler House Steam 10 Bar 10.6 Bar Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
3 Boiler 4 Economiser PSV Boiler House Water 20 Bar 20.2 Bar Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
4 Open Kettle Ketchup Steam 3 Kg/Cm2 3.8 Kg/Cm2 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
5 Vaccum Kettle 1 Ketchup Steam 4.5 Kg/Cm2 5.2 Kg/Cm2 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
6 Vaccum Kettle 2 Ketchup Steam 4.5 Kg/Cm2 65 PSI Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
7 Vaccum Kettle 3 Ketchup Steam 4.5 Kg/Cm2 65 PSI Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
8 Noodle 300 Heat Exchanger Noodle Steam 10 Kg/Cm2 Circuit Off Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November
9 Noodle 600 Heat Exchanger Noodle Steam 10 Kg/Cm2 8.4 Bar Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
10 Noodle 800 Heat Exchanger Noodle Steam 10 Kg/Cm2 8.9 Bar Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
11 Altas Copco 1 New Utility Hub Air 9 Kg/Cm2 Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
12 Altas Copco 2 New Utility Hub Air 9 Kg/Cm2 Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
13 Sanco VS-20 1 Utility Roof Air 9 Kg/Cm2 10.2 Bar Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
14 Sanco VS-20 2 Utility Roof Air 9 Kg/Cm2 10.1 Bar Planned January Planned Planned Planned
14 Sanco VS-20 2 Utility Roof Air 9 Kg/Cm2 10.1 Bar
Actual Actual Actual Actual
February March April May June July August September October November
15 Process Water Supply Outer Area Water 5 Kg/Cm2 Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
16 Fire Fighting Header Outer Area Water 8 Kg/Cm2 Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
17 DCM Open Kettle DCM Steam 5 Kg/Cm2 3.6 Bar Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
18 Autoclave DCM Steam 8 Kg/Cm2 3 Bar Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
19 HFO Circuit Fuel Line Outer Area Fuel 6 Kg/Cm2 Circuit Off Planned January Planned Planned Planned
Actual Actual Actual Actual
February March April May June July August September October November
20 CPR Main Header Outer Area Steam 9 Kg/Cm2 Circuit Off Planned January Planned Planned Planned
Actual Actual Actual Actual
edule of PSVs Planned Inspection 2019
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
UPFL Planned Maintenance Schedule of PSVs Planned Inspection 2019
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
December
UPFL Planned Maintenance Schedule of PSVs Planned Inspection 2019
January February March April May June July August September October November December
1 Main Office Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
2 Canteen Kitchen Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
3 Worker's Facility Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
4 New Worker's Facility 1 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
4 New Worker's Facility 2 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
5 Dining Hall Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
Dry Mix Hand Washing Planned Planned Planned Planned
6
Area
Actual Actual Actual Actual
January February March April May June July August September October November December
7 Conveyor 1 Dry Mix Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
8 Dry Mix to Warehouse Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
9 Soup Area to Warehouse Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
10 Mayo to Warehouse 1 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
10 Mayo to Warehouse 2 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
11 Mayo Area Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
12 Ketchup GF 1 Planned Planned Planned Planned
12 Ketchup GF 1
Actual Actual Actual Actual
January February March April May June July August September October November December
12 Ketchup GF 2 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
13 Ketchup FF Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
14 DCM 1 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
14 DCM 2 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
15 AutoClave Room 1 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
15 AutoClave Room 2 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
16 Egg Reception 1 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
16 Egg Reception 2 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
17 Main Warehouse Door 1 #1 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
17 Main Warehouse Door 1 #2 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
18 Main Warehouse Door 2 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
Main Warehouse Planned Planned Planned Planned
19 Emergency Door
Actual Actual Actual Actual
January February March April May June July August September October November December
Noodle to Noodle Planned Planned Planned Planned
20
Warehouse 1 #1
Actual Actual Actual Actual
January February March April May June July August September October November December
Noodle to Noodle Planned Planned Planned Planned
20
Warehouse 1 #2
Actual Actual Actual Actual
January February March April May June July August September October November December
Noodle to Noodle Planned Planned Planned Planned
21 Warehouse 2
Actual Actual Actual Actual
January February March April May June July August September October November December
Noodle 600 Line Flour
22
Warehouse 1
22 Noodle 600 Line Flour Planned Planned Planned Planned
Warehouse 1
Actual Actual Actual Actual
January February March April May June July August September October November December
22 Noodle 600 Line Flour Planned Planned Planned Planned
Warehouse 2
Actual Actual Actual Actual
January February March April May June July August September October November December
22 Noodle 600 Line Flour Planned Planned Planned Planned
Warehouse 3
Actual Actual Actual Actual
January February March April May June July August September October November December
23 Noodle 300 Line Flour Planned Planned Planned Planned
Warehouse
Actual Actual Actual Actual
January February March April May June July August September October November December
24 Noodle Main Entrance 1 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
24 Noodle Main Entrance 2 Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
25 Noodle 800 Line Entrance Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
26 RM Store Planned Planned Planned Planned
Actual Actual Actual Actual
January February March April May June July August September October November December
27 Canteen Planned Planned Planned Planned