Professional Documents
Culture Documents
CONSTRUCTION
PROJECT
SCHEDULING
Gülben ÇALIŞ, Ph.D.
Associate Professor
CONSTRUCTION PROJECT MANAGEMENT
OUTLINE
CONSTRUCTION SCHEDULES
TIME MANAGEMENT
BAR CHARTS
PRECEDENCE DIAGRAMMING
INTRODUCTION
A schedule is the tool most commonly used to
plan the project step by step.
Project manager can build the project on paper
before committing resources to it by analyzing
each activity and its relationship to the ones that
come before and after it.
A schedule could be a simple timetable or a
complex network diagram.
Schedules are not unique to construction but are
found in many industries whenever people,
equipment, materials, and organizations are
brought together and directed toward a common
goal.
4/12/2022 02. Time Management 3
CONSTRUCTION PROJECT MANAGEMENT
CONSTRUCTION
SCHEDULES
Used in construction since 1950s
Once formalized schedules were used
on only the largest of projects with
early computer technology
Today with the help of personal
computers more people use network
schedules at many levels.
Both used in planning and control
stages,
4/12/2022 02. Time Management 4
CONSTRUCTION PROJECT MANAGEMENT
TIME MANAGEMENT
INTRODUCTION
Major processes in developing project time
schedule
– Activity Definition—identifying the specific activities
that must be performed to produce the various
project deliverables.
– Activity Sequencing—identifying and documenting
interactivity dependencies.
– Activity Duration Estimating — estimating the
number of work periods that will be needed to
complete individual activities.
– Schedule Development—analyzing activity
sequences, activity durations, and resource
requirements to create the project schedule.
– Schedule Control—controlling changes to the project
schedule.
4/12/2022 02. Time Management 7
CONSTRUCTION PROJECT MANAGEMENT
Introduction (Cont.)
► Project tasks represent the necessary framework
to permit scheduling of activities, along with
estimating the resources required by the
individual work tasks, and any necessary
precedences or required sequence among the
tasks.
► An activity is any subdivision of project tasks.
► The time required to perform an activity is called
the duration of the activity.
► The beginning and the end of activities are
signposts or milestones, indicating the progress
of the project.
4/12/2022 02. Time Management 8
CONSTRUCTION PROJECT MANAGEMENT
ACTIVITY DEFINITION
Identifying and documenting the specific activities that must be
performed to produce the deliverables and subdeliverables
identified in WBS.
The definition of appropriate work tasks can be a laborious and
tedious process; no computer help
ACTIVITY SEQUENCING
Identifying and documenting interactivity logical
relationships. Activities must be sequenced accurately
to support later development of a realistic and
achievable schedule.
Dependencies (Input)
Mandatory dependencies often involve physical
limitations. (On a construction project, it is
impossible to erect the superstructure until after
the foundation has been built) AKA hard logic.
Discretionary dependencies are usually defined
based on knowledge of: “Best practices” within a
particular application area. AKA soft logic.
External dependencies involve a relationship
between project activities and non-project
activities. E.g. environmental hearings may need to
be held before site preparation can begin on a
construction project.
Network Templates
Example:
Precedence relationships
There are four types of dependencies
Finish-to-start
Finish-to-finish
Start-to-start
Start-to-finish