9. We will submit Seven (7) sets of our Final Report stating our
observations and findings.
10. Will issue yearly a Certificate of Structural Stability as required by LGU within
the 15-year liability period
11. Since the loads were analyzed as it was found in the time of Inspection, in the
event that a change of load was imposed, vendor will check if the area is still
adequate to cater the load.
Exclusions:
1. Soil Boring test
2. Chipping works and restoration concrete coring shall not form part of this
scope.