Professional Documents
Culture Documents
Submitted by
GA Consult
Economic and Corporate Financial Consultants
1. Introduction
The present summary highlights the results of GAC’s financial assessment of
KS/BW’s latest concept design as well as the impact of the recent value engineering
exercise completed by the Construction Division of SO on the Project’s foreseen
development costs and profitability.
BUA
sqm
Phase 1 Phase 2 (A) Phase 2 (B) Phase 3 Total
Apartments 49,120 - - - 49,120
Attached Villas 34,980 22,860 22,140 26,820 106,800
Detached Villas 21,120 24,290 21,220 21,250 87,880
The table below shows the breakdown of the Project’s public BUA (amenities).
2|Page
Construction (hard and soft), residential units 837,635,476 376,535,243 351,337,482 380,100,956 1,945,609,157
3|Page
The table below shows the Project’s foreseen profitability indicators, i.e., foreseen
equity IRR and operating profits as per GAC’s base-case scenario. The Project’s
Equity IRR is foreseen at 12.3%. However, if land value is excluded, foreseen equity
IRR would increase to 16%, i.e., by up to 3.7 percentage points.
Equity IRR, excluding land value 15% 17% 16% 17% 16%
Operating profits
GAC’s base-case infrastructure costs are foreseen at SR593 million while the post-
value-engineering infrastructure costs estimated by SO’s Construction Division
amount to SR452 million, thus resulting in a negative variance of about SR140 million
or 24%.
Based on above figures, GAC’s base-case development costs (excluding land value)
are foreseen at SR2.54 billion while the post-value-engineering development costs
estimated by SO’s Construction Division amount to SR2.42 billion, thus resulting in a
negative variance of about SR115 million or 4.6%.
5|Page
Construction (hard and soft), residential units 850,934,102 380,717,040 354,064,218 384,271,974 1,969,987,334
Equity IRR, excluding land value 17% 18% 17% 19% 18%
Operating profits
6|Page
Hardscape
General Rough Grading (for entire Area) - 6,336,000
LCA1 3,151 6,943,200
LCA2 7,000 2,221,120
LCA3 16,160 15,029,630
LCA4 1,730 1,676,180
LCA5 7,000 7,373,626
LCA6 5,970 2,275,900
LCA7 105,910 23,166,165
LCA8 5,700 8,886,790
LCA9 5,390 1,504,800
Total Hardscape 158,011 75,413,411
Softscape
LCA1 28,359 7,158,357
LCA2 7,000 2,186,800
LCA3 4,040 893,564
LCA4 32,870 4,641,402
LCA5 10,500 2,322,382
LCA6 13,930 3,081,026
LCA7 18,690 4,133,840
LCA8 5,700 1,780,680
LCA9 2,310 583,088
Additional 2,500 974,688
Total Softscape 125,899 27,755,827
Public Amenities
Neighborhood Center 1,186 7,067,168
Shopping 3,000 15,060,600
Indoor Social/Recreational Facilities 7,150 56,686,212
Rose Club 1,500 8,970,000
Medical 200 1,863,000
Pre-School 2,000 11,202,000
Facilities Management 6,600 27,213,450
Security Controls Center 200 2,001,000
Parking 8,750 21,179,450
Total Public Amenities 30,586 151,242,880
Central Plant
Storm Water - 7,350,000
Fire - 1,980,000
Potable Water - 11,536,250
Potable Water Storage - 7,474,500
Grey/ Irrigation Water Piping - 2,087,250
Sanitary Piping - 5,855,438
Waste Water Treatment - 16,851,992
Electric Services - Site Loop / UG - 31,374,200
Infrastructure Facility - Management 3,600 17,988,300
Total Central Plant 3,600 102,497,929
7|Page