OFFICIAL COMPETENCY ASSESSMENT TOOL

Part 1: RATING SHEET FOR DEMONSTRATION

Trainee’s Name Richie Juls Bacalso


Assessor’s Name
Qualification CONSTRUCTION SITE SUPERVISION LEVEL IV
Unit of Competency UOC 4: EVALUATE WORK GROUP
ACCOMPLISHMENTS
Date of Assessment
Time of Assessment
General Instructions
1. Assessor shall provide the Performance Test for UOC4: Evaluate Work
Group Accomplishments for download from the Online Classroom
2. Record yourself while presenting a Construction Progress Report
3. Upload your Video Recording of Construction Progress Report to your
Google Drive and Paste the Link in this Performance Test.
4. Submit the Accomplished Performance Test in PDF Format on the
designated Submission Bin thru the Online Classroom.
Required Resources
1. Internet Connection
2. MS Office Software or Other Similar Software
3. Video Recording Software
4. Recording Device
5. Google Drive
6. Other Relevant Tools and Software in Making a Construction Progress
Report
Criteria To show if evidence
is demonstrated
During the demonstration, did the candidate…✅
Yes No N/A

Clarify tactical strategies in accordance with company


and client’s policies and procedures?
1. Present the 3-Months Look Ahead Schedule?
2. Present issues encountered on site, and
recommended solutions?
Identify key performance criteria in accordance with
company and client’s policies and procedures?
3. Indicate and present the project’s targets?
4. Present a simplified dashboard of Key
Performance Criteria?
Analyze work accomplishment data versus planned
accomplishments in accordance with company and
client’s policies and procedures?
5. Present the Actual Accomplishment vs Planned?
6. Measure the Project’s Completion Rate?

1
OFFICIAL COMPETENCY ASSESSMENT TOOL

Recommend productivity improvement initiatives in


accordance with company and clients policies?
7. Present Action Plans to improve productivity on
Site?
Prepare an accomplishment report in accordance with
company and client’s policies and procedures?
8. Present Construction Progress Report using the
company's standard presentation?
Present reports in accordance with company and client’s
policies and procedures?
9. Present the report following the Presentation
Plan?
The candidate’s demonstration was:
𐄂 Satisfactory 𐄂 Not Satisfactory

2
OFFICIAL COMPETENCY ASSESSMENT TOOL

Part 2: QUESTIONS ABOUT THE DEMONSTRATION


Trainee’s Name Richie Juls Bacalso
Qualification CONSTRUCTION SITE SUPERVISION LEVEL IV
Unit of Competency EVALUATE WORK GROUP ACCOMPLISHMENTS
Satisfactory
QUESTIONS ✅
Responses
Yes No
Targets and Goals Company and the Client
- What are guidelines, targets and requirements
of each stakeholders?
- Who are the Stakeholders in your project?
- How many weeks is your project?
Best Possible Answers: If the answers can be found
in his/her video presentation of report
Key Performance Indicators
- What are your Key Performance Indicators?
- How do you keep your team/employee
satisfaction?
- How do you evaluate your Supplier and
Subcontractor?
Best Possible Answers: If the answers can be found
in his/her video presentation of report
Analyzed the Data
- How do you monitor your progress?
- What Construction data needs to be analyzed?
- How do forecast activities, financial status,
change request histories?
- How do you handle overdue activities?
Best Possible Answers: Presenter must able to
show in the video relevant information like daily
accomplishment reports, action plans, construction
work summary, financial status

3
OFFICIAL COMPETENCY ASSESSMENT TOOL

Recommended Productivity Initiatives


- What are your action plans, instructions,
strategies, changes, observations in achieving
the targets and goals?
Best Possible Answers: If the answers can be found
in his/her video presentation of report
The Trainee’s underpinning knowledge about the demonstration of
tasks was:
𐄂 Satisfactory 𐄂 Not Satisfactory
Feedback to the Trainee:

Overall Performance:
𐄂 Satisfactory 𐄂 Not Satisfactory
Trainee’s Signature: Date:
Richie Juls Bacalso
Assessor’s Signature: Date:

4
OFFICIAL COMPETENCY ASSESSMENT TOOL

Part 3: PERFORMANCE TEST (DEMONSTRATION)

Qualification CONSTRUCTION SITE SUPERVISION LEVEL IV

Unit of Competency EVALUATE WORK GROUP ACCOMPLISHMENTS

Learning Objectives PRESENT CONSTRUCTION REPORTS

SPECIFIC INSTRUCTIONS FOR THE TRAINEE (ANSWER ALL ITEMS)

1. Accomplish the Presentation Plan


2. Trainee shall record himself/herself while reporting a 15-minute
construction progress report containing the following information:

a. Agenda / Objectives of report + Brief Self-Introduction


b. a 3-Months look-ahead schedule
c. Issues encountered on site and recommended solutions
d. Action plans
e. Actual Accomplishment versus Planned
f. Photos from the jobsite
g. Short Recap

3. Trainee shall submit a presentation plan to the assessor that will serve as
his/her guide through-out the report.

4. Trainee shall upload his/her 3-month progress report to Google Drive.

5. Trainee shall provide only the video link for this Performance Test.
Trainee shall NOT send the video itself to the assessor and/or admin.

6. Assessor shall provide feedback based on the submitted video.

7. Assessor shall assess the trainee’s performance based on criteria provided in


the Rating of Demonstration Form.

5
OFFICIAL COMPETENCY ASSESSMENT TOOL

Presentation Plan
Report: WEEKLY PROJECT ACCOMPLISHMENT PROJECT REPORT
Intended Audience: MANAGEMENT AND ENGINEERS
Objective # 1: TO PRESENT THE KPI OF THE PROJECT
Objective # 2: TO DISCUSS ISSUES AND CONCERNS OF THE PROJECT
Slide Required Resources
Timing Topic Activity
No.
3 MINS SELF INTRODUCTION 1-8 SELF INTRO AND
PRESENTATION
AND 40
SECOND ACTUAL
S DISCUSSED THE CURRENT TARGET: 88.57% PROJECT NARRATIVE
KPI OF THE PROJECT REPORT
INHOUSE
TARGET: 88.57% SCURVE UDPATE
OBJECTIVES OF THE CUSTOMER POWER POINT
REPORT TARGET: 86.87% PRESENTATION
Strong
Introduction VARIANCE
PRESENTATION OF THE AGAINST
REPORT INHOUSE:
0.00%
VARIANCE
AGAINST
CUSTOMER:
1.70%

1 MIN ACTIVITIES ON SITE 1.PCCP


MANPOWER, MATERIALS,
ACCOMPLISHED: EQUIPMENT PAYMENT
36.902% FOR SUBCON
9 BALANCE:
0%
2.Surplus Common
Excavation:
9 . MANPOWER,
1 MIN ACTIVITIES ON SITE ACCOMPLISHED: MATERIALS, EQUIPMENT
5.18% PAYMENT FOR SUBCON
BALANCE:
0%
3.Embankment
from roadway
excavation.
. MANPOWER,
The Body 1MIN ACTIVITIES ON SITE 9 ACCOMPLISHED: MATERIALS, EQUIPMENT
4.55% PAYMENT FOR SUBCON
BALANCED:
0%

Payment for
Subcon;
DOCUMENT I.D NUMBER
1 MIN ISSUES AND CONCERS 10 MR. Jaire Uto Alim FOR PAYMENT PROCESS
MR. Jovel GAPATE

FOUR MONTHS IN-HOUSE WEEKLY


FOUR MONTHS LOOK TARGET ACCOMP. TARGET SCHEDULE
1 MIN
AHEAD 11-12
S-CURVE

6
OFFICIAL COMPETENCY ASSESSMENT TOOL

SHOWING ACTUAL
PICTURE
1 MIN PROGRESS PHOTOS 13-16 COMPILATIONS JOBSITE PICTURES

1MIN OVER-ALL ASSESSMENT 17 PROJECT ACTUAL S-CURVE-


OF THE PROJECT TARGET AND
SLIPPAGE IN-HOUSE WEEKLY
Powerful SCHEDULE
Ending

7
OFFICIAL COMPETENCY ASSESSMENT TOOL

Paste your
link here 🡪

https://drive.google.com/file/d/1zEKO485OvxypZg0ihWSGUmvYgD14xNtZ/view?usp=share_link
(Do not email the
MP4 file. Please
submit the video This is to informed that the report used in this presentation was accomplished last August 2022, for the
link from your reason that the project was reported complete last August 30, so I am no longer handling projects as of
Google Drive. today.
Make sure to grant
viewing access to
the assessor/s.

Assessor’s Comments: