PRE-STRIPPING/DOWN LEVEL TO
RL +35
PLAN Q1SEC1
OB = 313500 BCM
COAL = 5500 MT
SR 57
PRE-STRIPPING/DOWN LEVEL TO
RL +40
DESIGN QUARTER 1 SEQUENCE 2
DOWN LEVEL TO RL +5
PLAN Q1SEC1
OB = 320000 BCM
COAL = 9500 MT
SR 33,7
PRE-STRIPPING/DOWN LEVEL TO
RL +40
DOWN LEVEL TO RL +35
DESIGN QUARTER 1 SEQUENCE 3
PLAN Q1SEC3
OB = 315000 BCM
COAL = 22000 MT
SR 14,3