You are on page 1of 42

TYPES OF RCC SLABS

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Floor Slab is important part of framing. It ties together all columns.
It also gives stiffness to the frame which do not deflect excessively in case
of horizontal loads.

GOOD FRAMING BAD FRAMING

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Free end cantilevers are dangerous in case of EQ.
Code also do not allow Floating Column.

GOOD FRAMING BAD FRAMING

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Ferrocement slab by Pier Luigi Nervi

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Beam reinf band

Punching Shear
Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
•It is done for the span of 6 to 8 m.
•Supported directly on columns or load bearing walls.
•The principal feature of the flat plate floor is a uniform or near-uniform
thickness with a flat soffit which requires only simple formwork and is easy to
construct.
•The span 'L' of a reinforced concrete flat-plate is approximately D x 28 for
simply supported, D x 30 for an end span of a continuous system, to D x 32
for internal continuous spans.

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
•Span of 6 to 10 m.
•A reinforced concrete slab supported directly by concrete columns without
the use of Beams.
•It may have a column head and/or a drop panel to take care of shear.
•When a drop panel or column head is not provided it is also referred to as
flat plate.
•Simple formwork and easy construction.

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Column Drop panel

Prestressed duct alignment

L/3
Slab

Drop panel

Reduced punching shear Column head

Welded reinf mesh for slab by resistance welding

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Post Tensioned Method :

tendons
ELEVATION In conduit

Strands
Helical Reinforcement
Sheathing or conduit
Split conical pins
Anchor Plate
PLAN Wedge Plate Anchorage Details

END SECTION MID SECTION


Post tensioned Flat Slab :

G.I Duct

Bursting Reinf

Anchorage

Prestressing
Strands

Hogging due to P
P
P

Deflection curve
Post tensioned Flat Slab :

Advantages :

Dis advantages :

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Reinf steel is of smaller dia as compared to
Regular slab – beam

Concrete needs to be more workable as it


Has got more surface to covers ( More Fines
In mix )

De-shuttering is done by compressed air


Which is fast.

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
L/30
Two way slab

Concrete on Tension side removed

L/25

Reinf steel readjusted

Max span = 12m for 450 mm depth

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
L/25
One way slab

L/20
Band beam

Band Beam and Slab

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Band Beam and Slab

• This system consists of a series of parallel, wide, shallow beams with the floor
slab spanning transversely between the bands.
• The floor slab is designed as a continuous slab, with the shallow band beams
carrying all loads from the slab.
• A two-way slab system and are not treated as beams, except for shear.
• Commonly used for longer span structures often with the bands post-tensioned
and the slabs reinforced

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Max span = 11 m

L/D = 30 to 35

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Similar to ribbed slab.

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Maximum permissible span is 3.5m to 10m for 1.2 mm thick

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
SOME SITE CASE STUDIES

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
INDIAN INSTITUTE OF TROPICAL
METROLOGY, PUNE

RADIANT Cooling pipes of 19 mm dia


PEX pipes

FOR THE SLAB OF ROOM FOR


SUPER COMPUTER.

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
FLAME UNIVERSITY, PUNE
– LIBRARY BLDG

TRIANGULAR SKYLIGHTS IN SLAB

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
STEPPED SLOPING SLAB

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
FLAME UNIVERSITY

INDOOR SPORT COMPLEX

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
OLD TEXTILE MILL SLAB

Third year B.Arch Subject TOS V Prof Hemant Joshi & Asst Prof Sudhir Deshpande
Precast India Infrastructure P. Ltd, Pune

HALF CAST PRECAST SLAB

Cummins Ltd
Campus, Balewadi.

You might also like