Job Title 3453 LPM CE 47/2014 Originator SCC Revised by
Date 11/11/2016 Date
Section Pipe capicity Design (Under Hing Keng Shek Road) Checker YKF Re-checked by
Assume the pipe is 2/3( 100 %) full with respect to the height of pipe
q d= 1.5 m
2/3d = 1.50 m
a = 90 o
Q= v A
= 26.718 m3/s
= 26718 L/s
= 2E+06 L/min >45600 L/min OK!
JACOBS CALCULATION SHEET
Rev No
Job Title 3453 LPM CE 47/2014 Originator SCC Revised by
Date 11/11/2016 Date
Section Pipe capicity Design (Under Hing Keng Shek Road) Checker YKF Re-checked by
INLET OUTLET
GL FROM DIA(mm) IL(Mpd) TO DIA(mm) IL(Mpd) LENGTH (m) GRADIENT(1IN)
CP-C-1 76.57 - 225 UC 76.98 CP1 225 UC/600 UC 76.35 17.5 39
CP1 76.50 CP-C-1 600 UC 75.90 CP2 600 UC 75.80 42.5 25
CP2 74.69 CP1 600 UC 74.09 CP3 600 UC 73.99 20 5
CP3 70.15 CP2 600 UC 69.55 CP4 600 UC 69.45 23.5 67
CP4 69.70 CP3 600 UC 69.10 CP5 450 D 69.00 20 11
CP5 67.70 CP4 450 D 67.25 CP6 600 UC 67.20 12.5 83
CP6 67.70 CP5 600 UC 67.05 - 450 D 66.95 -
JACOBS CALCULATION SHEET
Rev No
Job Title 3380 LPM CE 30/2012 Originator YYL Revised by
Date 3/8/2016 Date
Section Feature No. Checker YKF Re-checked by
1. Introduction
The Stability analysis will be carried out for the feature no.
7SE-D/C27
2. Method of Analysis
g' = 18 kN/m³
g' = 18 kN/m³
For purpose of the stability assessment, the deisgn groundwater table has been
assumed to be approximately one-third of the slope height.
JACOBS CALCULATION SHEET
Rev No
Job Title 3380 LPM CE 30/2012 Originator YYL Revised by
Date 3/8/2016 Date
Section Feature No. Checker YKF Re-checked by
Rev No
Job Title 3380 LPM CE 30/2012 Originator YYL Revised by
Date 3/8/2016 Date
Section Feature No. Checker YKF Re-checked by
1.1 Introduction
1.2 Methodology
1.3.2 High yield bars complied with BS 4449 are used for soil nails,
which are hot dip galvanized are required in BS 729.
A reduction of 2mm radius as sacrificial thickness for steel corrosion is allowed.
Diameter of Bar= 25 mm
1.3.5 The effect of shear and bending of nails across the critical surface
is considered insignificant and is neglected in the design.
1.3.6 The soil nails are bonded behind the Design Slip of FOS > 1.40 after upgrading.
1.3.9 With reference to GEO Technical Guidance Note No. 15 (TGN 15), slips scarps within
a crest influence zone (D) of two times the feature height (H) (i.e., D = 2H) are checked
in the stability assessment.
Rev No
Job Title 3380 LPM CE 30/2012 Originator YYL Revised by
Date 3/8/2016 Date
Section Feature No. Checker YKF Re-checked by
ft = 500 N/mm²
= 500.0 N/mm²
JACOBS CALCULATION SHEET
Rev No
Job Title 3380 LPM CE 30/2012 Originator YYL Revised by
Date 3/8/2016 Date
Section Feature No. Checker YKF Re-checked by
= 115.45 kN
The following soil parameters are selected in the soil nail analysis:
Rev No
Job Title 3380 LPM CE 30/2012 Originator YYL Revised by
Date 3/8/2016 Date
Section Feature No. Checker YKF Re-checked by
Rev No
Job Title 3380 LPM CE 30/2012 Originator YYL Revised by
Date 3/8/2016 Date
Section Feature No. Checker YKF Re-checked by
where η1 = coefficient related to the quality of the bond condition and the position of the bar
during concreting in accordance with Clause 8.4.2 of BS EN 1992-1-1:2004
(BSI, 2004)
η2 = coefficient related to the bar diameter in accordance with Clause 8.4.2. of
BS EN 1992-1-1:2004 (BSI, 2004)
fctd = the design value of concrete tensile strength in accordance with Clause 3.1.6(2)P
of BS EN 1992-1-1:2004 (BSI, 2004) and NA to BS EN 1992-1:2004 (BSI, 2005)
Pr = effective perimeter of the soil-nail reinforcement
L = bond length of the soil-nail reinforcement in the passive zone
FGR = factor of safety against pullout failure at grout-reinforcement interface
η1 = 1.0 Pr = ( 25 - 2 x 2) x p
η2 = 1.0 = 65.97 mm
fctd = αct fctk,0.05 /γc
= 1.2 FGR = 2.0
Rev No
Job Title 3380 LPM CE 30/2012 Originator YYL Revised by
Date 3/8/2016 Date
Section Feature No. Checker YKF Re-checked by
Rev No
Job Title 3380 LPM CE 30/2012 Originator YYL Revised by
Date 3/8/2016 Date
Section Feature No. Checker YKF Re-checked by
c' = 1 kPa
q = 40 o to 55 o
Bar Dia. = 25 mm
Soil Head Size
800 x 800 (mm)
Tp = 362 Ta = 9
Section 2-2
Row lb H1 Hw sv' Tf TSG T1 T2 Elevation
T2 2.00 3.80 0.80 60 18.81 9.4047 13 26 181.5
JACOBS CALCULATION SHEET
Rev No
Job Title 3380 LPM CE 30/2012 Originator YYL Revised by
Date 3/8/2016 Date
Section Feature No. Checker YKF Re-checked by