Professional Documents
Culture Documents
TNEB wanted to know as to how many engineers they should post for this project.
Ezhumathur engineers and consultants estimated the requirement of engineers to manage
each of the activities as per Table 3 given below.
Table: 3
(1,2) Survey 1
(2,3) Estimate and Sanction 3
(2,4) Tree Cutting Schedule 2
(3,5) Procure Stubs and Tower Parts 3
(3,6) Award Contract for Stub Setting 2
(3,7) Award Contract for Tower Erection 2
(4,7) Stub Cutting 1
(6,7) Tree Setting 1
(7,8) Tower Erection and Stringing 3
(8,9) Energizing 3
An assumption, such as the above, is not always valid unless the activity is totally and
singly dependent on that particular resource. Taking (2,3) itself, the activity involves
1*
For all these assume that activities cannot be ‘split’, i.e. they cannot be stopped once started. Also assume that
the activities can neither be expedited nor delayed by giving additional engineers or reducing the number of
engineers.
‘sanction’, which cannot be speeded up by increases in the number of engineers to carry
out the activity, because the ‘sanction’ is to be given by somebody else.
Let us, for a moment, assume that such assumptions are valid. Now, if four engineers are
given for this project, and if the activities cannot be split find.