Professional Documents
Culture Documents
Bidding Document
For
Employer:
Nepal Electricity Authority
Ghorahi-Madichaur 132 kV Transmission Line Project
VOLUME-II-B OF III
SECTION-01-PROJECT
SPECIFICATION REQUIREMENT
(PSR)
Contents
SECTION – 1 ................................................................................................................................................. 2
1. GENERAL .............................................................................................................................................. 2
2. SCOPE .................................................................................................................................................... 2
7. SPARES................................................................................................................................................ 10
Note: ............................................................................................................................................................. 14
Annexure - I .................................................................................................................................................. 15
Annexure – II ................................................................................................................................................ 15
Annexure-III ................................................................................................................................................. 18
Annexure-IV ................................................................................................................................................. 31
SECTION – 1
Project Specification Requirement
1. GENERAL
Nepal Electricity Authority (NEA) intend to construct a new 132/33/11 kV substations at
Khungri of Rolpa District along with bay extension of Ghorahi substation at Ghorahi, Dang.
This specification describes the requirements for construction of the substations on a turn-key
basis.
Sites are Greenfield with trees and the Contractor shall be responsible for access and all
necessary utilities. NEA is the Executive Agency.
1.1.1 This specification covers the execution of new substation works that comprise of 132/33/11
kV AIS type (Air Insulated Substation) at Khungri (Rolpa). Above package also include
combination of outdoor 30 MVA, 3-phase, 132/33 kV & 8 MVA, 3-phase, 33/11 kV
Transformers at substation and Bay extension works at Ghorahi Substation, Ghorahi, Dang.
1.1.2 The new substation at Rolpa will connect Rolpa and Dang District with INPS. The Contractor
is requiring designing and constructing the substation as per the site condition based on the
indicative layout drawings provided.
1.1.3 It is the intent of this specification to describe primary features, materials, design &
performance requirements and to establish minimum standards for the work. The specification
is not intended to specify the complete details of various practices of manufactures/ bidders,
but to specify the requirements with regard to performance, durability and satisfactory
operation under the specified site conditions.
2. SCOPE
2.1 The broad scope of this specification covers the following substations along with associated
transformers and other equipments.
12 kV
Local transformer switchgear as
The substations shall
11 kV Switch room 33/0.4 kV, 250 described in
be constructed as fully
Associated control rooms kVA, feed from 11 the
integrated turnkey
& battery room kV outgoing feeder specification
packages.
panel.
(a) 1 (One) number of 30 MVA, ONAN/ONAF, 132/33 kV, 3-phase and 1 (one) number of 6/ 8
MVA ONAN/ONAF, 33/11 kV, 3-phase transformers complete with all materials / fittings /
accessories / Digital RTCC (remote tap changer control) panel /OLTC/MB, Cables including
special cable (if any), etc. The Transformer shall be rated for operation outdoor as per BOQ.
(b) 1 (one) number 250 KVA, 33/0.4 kV LT transformer along with associated equipment.
(d) Complete Relay & Protection System as per of Section - C & R of the Technical
Specifications. The protection to be provided on 132 kV and 33 kV Lines shall be as under;
(e) Complete Substation automation including hardware and software for remote control station
along with associated equipment for following bays including provision of 2 Nos of 132 kV
future bays.
3 11 kV Feeders 2 feeder
The contractor shall also supply necessary BCU for monitoring and control of auxiliary supply
including operation of Isolators associated with Auxiliary transformer.
(f) Digital Protection Coupler (DPC) (2 Nos. at each end- 2 no. of installation should be at
Khungri Substation and remaining 2 no. at Ghorahi Substation) and two number at each end
for far end substations shall be used for protection application. Each DPC shall be equipped
with 4 commands. The above DPC shall have communication port matching to that being
provided in the FO communication SDH panel and all accessories, cabling etc. required to
interface with SDH telecommunication terminal equipment (located in the Control Room) for
its commissioning is in present scope of Project. 48 volt power supply cable, Control Cable
from DPC to relay panel shall be laid as per location of DPC panel. The specification for the
digital protection coupler shall be as per Annexure II.
(h) Complete Fire fighting system suitable for electrical fire for 132 kV Indoor (Control rooms)
and outdoor equipments/ transformers.
(n) 12 (11) kV grade XLPE (Cross-linked polyethylene) Power cabling along with flexible pipe,
cable termination equipment/kits complete accessories and cable trench as required and as
approved as per site condition.
(o) 33 kV grade XLPE Power cables with flexible pipe, sealing end, support insulators with
terminations along with complete accessories and cable trench as required and as approved as
per site condition. The cable shall be buried minimum 1.2 meter below the finished ground
level as per technical spec and drawing. Provision for laying cable in culvert area will be
finalized during detail engineering.
(p) Lattice and pipe structures (galvanized): Gantry, Beams and equipment support structure shall
be provided as per design and drawings to be developed by the contractor. However supply of
support structure for circuit breaker is under scope of CB manufacturer as per their design.
132 kV dead end towers design and drawing and its foundation shall be provided by
employer. The bid shall also cover the cost of take-off gantry and internal gantry structures
for 132 kV future line bays.
(q) Bus Post Insulators, insulator strings and hardware, clamps & connectors, Equipment terminal
connectors, Conductors, Aluminum tubes, Bus bar and earthing materials, Bay marshalling
box, spacers, cable supporting angles/channels, Cable trays & covers, Junction box, buried
cable trenches.
(r) Complete lighting and illumination for the switchyard including street Lightning, Control
Building, Staff quarter, Guard buildings, Parking shade, Playing Court, Transit camp.
(s) Earth mat design & laying the outdoor yard and lightning protection system including top of
control building.
Design, engineering, manufacture, testing, supply on site basis including transportation &
insurance, storage at site of mandatory spares.
2.3.1 Civil Works - The scope of work shall include but shall not be limited to the following based
on design and drawings to be developed by the contractor: -
a) Control Building, Staff quarter, Guard house, Vehicle parking and Badminton court.
b) Marking, Blazing, Cutting and Storage of trees & removing roots as per BOQ.
c) All civil works including foundations associated with SF6 gas insulated Circuit breaker,
Vacuum Circuit Breaker, Dis-connector, Lightning arrestors, Instrument transformers, post
insulators etc.
g) Foundations of Transformers, along with jacking pad and pylon supports, rail track etc
h) Foundation for all equipments supports structures, take off gantry and internal gantry for 132
kV bays (including 2 no. of future 132 Kv take off gantry and internal gantry).
i) Cable trenches along with covers, road/rail crossings, sump pits and cable trench crossings
with roads or drains etc.
k) Antiweed treatment (included in crossed rock surfacing work), Stone spreading in switchyard
area.
l) Design (architectural and structure) and construction Control room all complete in lot basis.
m) Design (architectural and structure) and construction of Staff quarter, Guard and store
buildings, on measurement basis etc.
n) Drains (switchyard cum substation premises) along with drain crossings with cable trenches.
Drain layout shall be developed by the contractor.
r) Survey of substation area and its periphery and Soil investigation including soil resistivity
measurement.
s) Contouring and Site leveling: The leveling in the area under present scope of work inside
substation boundary wall is to be carried out to achieve finished ground level. The leveling
area and finished ground level of switchyard shall be decided during detailed engineering
stage. The leveling area shall be leveled in single or multi level as per topographical
features/contouring details of substation land.
t) Foundation for lighting poles, Bay marshalling box, panels and control cubicles of
equipments wherever required
u) Steel lattice tower foundations for 132 lines as per provided design and drawings.
v) In the Ghorahi Substation tower and equipment structures along with its foundation, cable
trench and crossing, complete drains system including RCC slab cover, concrete of protection
works.
2.4 The bidders are advised to visit the substation sites and acquaint themselves with the
topography, infrastructure and also the design philosophy. Before proceeding with the
construction work of the Sub-stations, the Contractor shall fully familiarize himself with the
site conditions and General arrangements & scheme etc. Though the Employer shall endeavor
to provide the information, it shall not be binding for the Employer to provide the same. The
bidder shall be fully responsible for providing all equipment, materials, system and services
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-7
specified or otherwise which are required to complete the construction and successful
commissioning, operation & maintenance of the substation in all respects. All materials
required for the Civil and construction/ installation work shall be supplied by the Contractor.
The cement and steel shall also be supplied by the Contractor.
The complete design (unless specified otherwise in specification elsewhere) and detailed
engineering shall be done by the Contractor based on conceptual tender drawings. Drawings
for civil works enclosed with tender drawings are for information only. However civil
drawings with design calculation shall be developed by the contractor as per his design.
2.5 The Contractor shall also be responsible for the overall co-ordination with internal / external
agencies, project management, training of Employer’s manpower, loading, unloading, handling,
moving to final destination for successful erection, testing and commissioning of the
substation/switchyard.
2.6 Design of substation and its associated electrical & mechanical auxiliaries systems includes
preparation of single line diagrams and electrical layouts including layout arrangement for
transformers, foundation layout, cable trench layout, earth mat layout, erection key diagrams,
electrical and physical clearance diagrams, design calculations for earthing and lightening
protection system (including Direct Stroke Lighting Protection), control and protection
schematics, wiring and termination schedules, civil designs (as applicable) and drawings, design
of fire fighting system and air conditioning system, indoor / outdoor lighting / illumination,
culvert Bridge and other relevant drawings & documents required for engineering of all
facilities within the fencing to be provided under this contract, are covered under the scope of
the Contractor.
2.7 Employer has standardized its technical specification for various equipments and works for
different voltage levels. Items, which are not applicable for the scope of this package as per
schedule of quantities described in BOQ, the technical specification for such items should not
be referred to.
2.8 The Quantities listed in the Schedule of Prices represent the estimated quantities for Tender
purpose only. The Contractor shall carryout detail design and shall submit final bill of quantity
for approval within 120 days from the signing of contract or 90 days after effective date of
contract. The actually required quantity may vary from the quantity as listed in price schedule.
The Contractor shall agree to make no claim for anticipated profits or for alleged losses because
of any difference between the quantities actually furnished and installed and the estimated
quantities as indicated in the price schedule at the original quoted unit prices within the total
price variations limit of +/- 15% as per the tender conditions.
80 % (max), 20 %(min)
d) The substation locations are lying in the wind speed Zone 4 i.e., 47m/s.
- 0.5g (Horizontal peak acceleration value) for all steel structures and major
equipments.
3.3 The fault level of all equipment to be supplied under present scope shall be as indicated
below:
3 11 kV 25 kA for 3 Sec
The requirement of various items/equipments and civil works are indicated in Bid price
Schedules.
All equipments/items and civil works for which bill of quantity has been indicated in BOQ
(Bill of Quantity) shall be payable on unit rate basis/ quoted rate basis. During actual
execution, any variation in such quantities shall be payable as per relevant clauses
incorporated in Letter of award.
Wherever the quantities of items/works are indicated in LS/Lot/Set, the bidder is required to
estimate the quantity required for entire execution and completion of works and incorporate
their price in respective Bid price schedules. For erection hardware items, Bidders shall
estimate the total requirement of the works and indicate module-wise lump sum price bay
wise and include the same in relevant Bid price schedules. For module identification, Bidder
may refer typical drawings enclosed with the specifications. Any material/works for the
modules not specifically mentioned in the description in BOQ, as may be required shall be
deemed to be included in the module itself.
Bidder should include all such items in the bid proposal sheets, which are not specifically
mentioned but are essential for the execution of the contract. Item which explicitly may not
appear in various schedules and required for successful commissioning of substation shall be
included in the bid price and shall be provided at no extra cost to Employer.
5.1 Single line diagram and general arrangements are enclosed with the bid documents for reference,
which shall be further engineered by the bidder.
5.2 The reference drawings, which form a part of the specifications, are given at Annexure-I. The
bidder shall maintain the overall dimensions of the substation, phase to earth clearance, phase to
phase clearance and sectional clearances. The enclosed drawings give the basic scheme, layout of
substation, substation buildings, associated services etc. In case of any discrepancy between the
drawings and text of specification, the requirements of text shall prevail in general. However, the
Bidder is advised to get these clarified from Employer. Rating of the equipment shall review by
the bidders.
5.3 The auxiliary transformers of rating 250 KVA shall be used to feed the substation auxiliaries.
The 250 KVA, 33/0.4 kV auxiliary transformers shall be located outdoor in a suitable location.
These auxiliary transformers should not be used for construction power supply purpose. The
detailed scheme is shown in the single line diagram.
For the purpose of present scope of work, technical specification shall consist of following
parts and they should be read in conjunction with each other.
3. Section 3: Transformers
4. Section 4: LT Transformer
8. Section 8: Switchgear
In case of any discrepancy between Section 1-PSR, Section 2-GTR and other technical
specifications on scope of works, Section 1 - PSR shall prevail over all other Sections.
In case of any discrepancy between Section 2-GTR and individual Sections for various
equipment, requirement of individual equipment Section shall prevail.
7. SPARES
Mandatory Spares
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-11
The Mandatory Spares shall be included in the bid proposal by the bidder. The prices of
these spares shall be given by the Bidder in the relevant schedule of BOQ and shall be
considered for evaluation of bid. It shall not be binding on the Employer to procure all of
these mandatory spares.
The bidder is clarified that no mandatory spares shall be used during the commissioning of
the equipment. Any spares required for commissioning purpose shall be arranged by the
Contractor. The unutilized spares if any brought for commissioning purpose shall be taken
back by the contractor.
The bidder shall include in his proposal the supply of all special tools and tackles required
for operation and maintenance of equipment. The special tools and tackles shall only cover
items which are specifically required for the equipment offered and are proprietary in nature.
However, a list of all such devices should be indicated in the relevant schedule provided in
the BOQ. In addition to this the Contractor shall also furnish a list of special tools and
tackles for the various equipment in a manner to be referred by the Employer during the
operation of these equipment. The scope of special tools and tackles are to be decided during
detail engineering and the list of special tools and tackles, if any shall be finalized.
9.1 Employer shall make available the auxiliary HT power supply from NEA on chargeable
basis at a single point in the Sub-station. The prevailing energy rates of the state shall be
9.2 Applicable. All further distribution from the same for construction and permanent auxiliary
supply shall be made by the contractor. However, in case of failure of power due to any
unavoidable circumstances, the contractor shall make his own necessary arrangements like
diesel generator sets etc. at his own cost so that progress of work is not affected and
Employer shall in no case be responsible for any delay in works because of non-availability
of power.
9.3 All further distribution for the same shall be made by the Contractor. In case of non-
availability or inadequate availability of water for construction work, the contractor shall
make his own arrangement at his own cost and the Employer shall in no case be responsible
for any delay in works because of non-availability or inadequate availability of water.
9.4 All the cost required for facilities mentioned above shall be borne by contractor.
10.1 The Bidders are advised to visit Sub-stations site and acquaint themselves with existing
facilities, the topography, infrastructure, etc.
10.2 The bidder shall be responsible for safety of human and equipment during the working. It
will be the responsibility of the Contractor to co-ordinate and obtain Electrical Inspector's
clearance before commissioning. Any additional items, modification due to observation of
such statutory authorities shall be provided by the Contractor at no extra cost to the
Employer. The Contractor shall arrange all T&P (such as necessary supports, cranes, ladders,
platforms etc.) for erection, testing & commissioning of the system at his own cost. Further,
all consumables, wastage and damages shall be to the account of contractor.
The details of RTU installed at existing substations and Data acquisition principles (types of
analogue/digital data) for control, monitoring of substation is enclosed at Annexure III. The
existing communication protocol used for SCADA at LDC Kathmandu is IEC 101/104. For
the present scope of work, RTU are not envisaged and the Data for SCADA purpose shall be
obtained from the Substation Automation System (based on IEC 61850) using Gateway port
with communication protocol IEC 104 as per requirement being provided at the substations
under present scope of contract.
The scope of work for supply, installation of Optical Line Termination Equipment, Digital
Multiplexer, hardware accessories etc at Khungri substation for onward transmission of Data
and Voice communication up to LDC Kathmandu is included in the contract.
The existing FO communication link including RTU exists between existing Ghorahi
Substations, Ghorahi, and Dang. Data and voice communications from various substations
and power houses flow to LDC in the direction of between Ghorahi–Syuchatar Substations.
The scope of work for supply, installation of approach optical fibre (as per requirement from
JB to ODF box), Optical Line Termination Equipment, Digital Multiplexer, hardware
accessories etc at Khungri Substation and its integration work (at existing Ghorahi
Substation & LDC Kathmandu) for onward transmission of Data and Voice communication
up to LDC Kathmandu is included in the contract.
10.5 Erection, testing and commissioning of Substation automation system, Control and
protection Panels, Transformer, and communication equipments shall be done by the
contractors under the supervision of respective equipment manufacturers. Charges for the
above supervision shall be included by the bidder in the erection charges for the respective
equipment in the BOQ.
10.6 Training: The training shall be provided as per provision of corresponding Section of plant
and equipment. However, if not mentioned in corresponding Section, the traveling and living
expenses of Employer’s personnel for the training programmed conducted shall be borne by
the contractor.
The training shall be provided to Employer’s personnel in the field of erection, testing, operation
and maintenance in abroad as agreed or as specified in corresponding Section as per following.
10.7 The civil construction drawing for above shall be developed by the contractor during detail
engineering. For illumination in switchyard panel room average Lux level at ground level
shall be 350 lux.
10.8 The lighting fixtures for switchyard lighting shall be mounted on LMs wherever LMs are
provided. Where LMs are not available, the fixtures may be mounted on Gantry structures or
on lighting poles to be provided by the contractor. All the lighting fixtures, Air condition,
ceiling Fans etc to be installed at substation shall be energy efficient (low power
consumption).
10.9 The Frequency range for the earthquake spectra shall be as per IEC-62271-300 for Circuit
Breaker.
10.10 Transmission line side insulator String (including Hardware) i.e., tension insulator on the
line side of the take off gantry for 132 and 33 KV lines termination is under the present
scope of specification.
10.11 One number portable fire extinguisher (CO2 type) of 4.5 kg shall be provided for each
switchyard panel room as per Bid proposal sheet (BOQ).
10.12 The Contractor shall provide AC/DC feeders for complete future bays also as per single
line diagram in addition to bays under present scope
10.13 One number each Energy meter for the record and revenue purpose is to be provided for
each 132 kV bays (Bus coupler bays to be excluded) at Substations under present scope of
contract, meeting the requirement as specified at Annexure – IV.
10.14 The reference of IS standard (i.e. Indian Standard) mentioned in the technical specification
shall be read as equivalent EC or BS or equivalent International Standard.
10.15 Non CFC refrigerant shall be utilized for Air conditioning system, offered for buildings is
under the scope of contract.
10.16 The distance protection relays to be supplied for 132 kV lines should have feature of load
encroachment blinder to safeguard the protection trip during heavy load condition.
10.17 Separate protection relay (IED) shall be provided for 132 kV Class Transformer directional
over current and earth fault relay (for both HV & LV side). Inbuilt function in any other
protection IED/BCU (Bay Control Unit) is not acceptable.
10.18 In the Sub-station automation system, each AIS shall be monitored individually per phase
basis. In case it is not possible to monitor in one BCU, the contractor shall supply additional
BCU for the monitoring without any additional cost implication to NEA.
10.19 For supply of SF6 Gas, the contractor shall obtain necessary license from the concerned
statuary authorities in Nepal. The contractor shall comply with all the legal & statuary
requirements as per the local laws for importing, handling & storage of SF6 gas in Nepal.
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-14
For this purpose NEA shall extend necessary assistance (documentation etc) for obtaining
such clearance & licenses, however the complete responsibility for submitting the
application and co-ordination with authorities shall be in the scope of contractor.
As soon as the Facilities covered by these specifications are physically completed in all
respects, the Pre commissioning, Commissioning, Trial-run and Completion of the
Facilities, as mentioned below, shall be attained in accordance with the procedure given in
the Conditions of Contract, Vol.-I of the Bidding Documents.
(ii) Commissioning:
(iii) Trial-run :
Operation of the Facilities or any part thereof by the Contractor immediately after the
Commissioning for a continuous period of 72 (Seventy two) hours continuously. In case
of interruption due to problem / failure in the respective equipment, the contractor shall
rectify the problem and after rectification, continuous 72(Seventy two) hours period start
after such rectification.
(iv) Completion :
‘Guarantee Test(s)’ and/or ‘Functional Guarantees’ are applicable only for Substation
Automation System as specified in Section-‘Substation Automation System.’
Note:
The Contractor shall do the necessary calculations for relay setting required for Pre-
commissioning, Commissioning, Trial-run and Completion for the substations under the
scope of this Contract. All the relay setting calculations required for the substations (in
this scope) with related to Integrated Nepal Power System (INPS) shall be done by the
Contractor.
Supply of all material and equipments shall be done by the contractor according to the
approved supply schedule and this should be the responsibility of the contractor to
submit and get approval of the supply schedule from the employer.
Additional EMP that will be considered necessary by ADB to be implemented during the
project preconstruction and construction stages are attached in the ANNEXTURE VI.
Annexure – II
1.0 Digital protection coupler for protection signalling through optical fibre cable system.
1.1 The Digital protection signalling equipment is required to transfer the trip commands from
one end of the line to the other end in the shortest possible time with adequate security and
dependability. It shall also monitor the healthiness of the link from one end to the other and
give alarms in case of any abnormality. The protection signalling equipment shall have a
proven operating record in similar application over EHV systems and shall operate on 48V
DC (+10%, -10%). It shall provide minimum four commands. These commands shall be
suitable for direct tripping, inter tripping and blocking protection schemes of EHV lines.
The protection signalling equipment shall communicate to the remote end interfacing with
SDH terminal equipment at its 2 Mbps port. It shall provide suitable interfaces for
protective relays, which operate at 110V DC. Power supply points shall be immune to
electromagnetic interface.
Contractor has to utilize the same fibre for communication and digital protection purpose; no
separate fibre shall be provided to the contractor for digital protection. Therefore bidders are
instructed to include all the cost providing necessary equipments/ cards and their installation
in Khungri as well as far end substations (Ghorahi).
During normal operation, protection signalling equipment shall transmit a guard signal/code.
In case Protection signalling equipment is actuated by protective relays for transmission of
commands, it shall interrupt the guard signal/code and shall transmit the command code to
the remote end. The receiver shall recognize the command code and absence of the guard
code and will generate the command to the protective relays.
All signal processing i.e. generation of tripping signal and the evaluation of the signals being
received shall be performed completely digital using Digital Signal Processing techniques.
An automatic loop testing routine shall check the teleprotection channel. It shall also be
possible to initiate a loop test manually at any station by pressing a button on the front of the
equipment. Internal test routine shall continuously monitor the availability of the protection
signalling equipment. Proper tripping signal shall always take the priority over the test
procedure.
The high speed digital protection signalling equipment shall be designed and provided with
following features.
Bidder shall quote for protection signalling equipment suitable for 4 commands with
separate trip counters for transmit and receive. With regard to trip counters alternate
arrangement i.e Laptop along with software & all accessories to download events including
carrier receipt and transmit shall be acceptable. Laptop for the above shall be supplied for
Khungri substation under substation package.
High security and dependability shall be ensured by the manufacturer. Probability of false
tripping and failure to trip shall be minimum. Statistical curves/figures indicating above
mentioned measures shall be submitted along with the bid. The DPC can be either housed in
offered Control & Protection Panel / PLCC Panel or in separate panel.
Reports of the following tests as per clause 9.2 of Section 2-GTR shall be submitted for
approval for protection signalling equipment and relays associated with the protection
signalling equipment and interface unit with protective relay units, if any.
i) General equipment interface tests:
b) Interruptions
c) LF disturbance emission
d) Reverse polarity
iii) Tele-protection system performance tests:
a) Security
b) Dependability
c) Jitter
d) Recovery time
f) Alarm functions
All the above tests at i, ii & iii (except temperature & humidity tests) shall be as per IEC
60834-1 and the standards mentioned therein.
iv) Relays
The input/output interface to the protection equipment shall be achieved by means of relays
and the input/output rack wiring shall be carefully segregated from other shelf/cubicle
wiring. The isolation requirements of the protection interface shall be for 2kV rms.
Propagation delay ≤ 8 ms
Annexure-III
EXISTING RTU BASED SCADA & ITS DATA ACQUISITION
1. GENERAL
1.1 This specification covers the design, manufacture, assembly, shop test, supply, delivery,
installation, field testing and commissioning of SCADA complete with all accessories for
efficient and trouble-free operation as specified hereunder as /if required to meet the requirement
as mentioned in Project Specific Requirement (PSR).
The Integrated Nepal Power System (INPS) is being supervised by Load Dispatch Centre (LDC)
located at Syuchatar, Kathmandu. Computer based SCADA system of Siemens "Power 7" has
been installed in the LDC Master-station for processing the data collected from power stations
and substations spread over the country. The substation contractor shall be fully responsible for
supply, installation, testing and commissioning of all hardware and software including RTU
cards and accessories, necessary for complete operation in regard of implementation of SCADA
system, as required by NEA. A failure of one element of a system must not affect the
availability and the performance of the overall system.
a) Ghorahi Substation:
Necessary adaptation works shall be carried out on existing RTU at Ghorahi substation for data
transmission and remote operation of new 132/33/11 kV bays. This also includes supply of
necessary cards, accessories, cable connectors for the RTU and extension, reorientation and
reconfiguration of the RTU. Data of newly installed 132kV bays shall be integrated into the
Siemens Power 7 of LDC.
The contractor shall make necessary studies and investigations of the existing SCADA
systems in order to design and supply of appropriate equipment.
b) Khungri Substation:
Data of newly installed 132/33/11 kV bays shall be integrated into the Siemens Power 7 of LDC.
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-19
The contractor shall make necessary studies and investigations of the existing SCADA
systems in order to design and supply of appropriate equipment.
2.1 The Contractor shall be fully responsible for full-functioning and compatible interfacing of data
and tele protection schemes between the existing SCADA and communication system of NEA
and the new system to be commissioned under the scope of this Tender.
2.2 Compatible interfacing shall be for all aspects, including software and hardware. In addition to
other necessary compatibilities and interfacing, the Contractor shall be fully responsible for
the integration of the SCADA data associated with the scope in this tender in the Siemens
Power 7 SCADA system -the processing software of the Load Dispatch Centre. This
integration requires modification, addition and parameterization in the software for the
following main activities:
a) SCADA data entry: this includes data entry of different components of the substations, lines
and other relevant components.
b) Creating Graphics: this includes creating graphics for substations, lines and other relevant
components, network map creation and integration with existing system, etc.
d) Testing and commissioning of the newly integrated SCADA system for its full functioning;
and
The above activities shall be carried out, as appropriate, in Ghorahi substation and the Load
Dispatch Centre.
For these purposes, the Contractor shall carry out necessary studies / investigations of the
existing system carefully, in full coordination with the Load Dispatch Centre, and design /
propose, install and integrate a suitable scheme/system to fulfil the specified scope of works for
teleprotection, SCADA etc., as required by NEA (Load Dispatch Centre).
For Ghorahi substation, SCADA related connections shall preferably be provided separately in
the control and relay panels.
2.4 WIRING
2.4.1. Secondary control wiring, windings, coils and resistors shall be insulated for 600 volts and shall
withstand 1500 volts, one (1) minute dielectric test. All circuits shall terminate on adequately
marked approved screw type terminal blocks mounted in accessible locations in the mechanism
housing. Not more than two terminations to a single terminal point will be permitted.
2.4.2 The diameter of the control wiring shall not be smaller than 0.5 mm. All wiring shall be tinned,
standard copper, 600-volt insulation. Both ends of all wires and all terminal block points shall
be clearly marked with the designation shown on manufacturer's wiring diagram.
2.4.4 Adequate space shall be allowed in terminal boxes for the pulling, bending and proper grouping
of all external power and control cables and a suitable removable drilling plate shall be
provided for external conduits or cables. All external conduits and cables shall be furnished and
installed by the Contractor.
2.4.5 All internal wiring shall be connected to terminal blocks in a manner to allow the external cables
to be terminated on consecutive points of the blocks.
All design tests, if required, and production tests shall be conducted in the presence of an
authorized representative of the Employer, unless waived in writing by him. The Contractor shall
notify the Employer at least fifteen (15) days in advance as to the date of the tests, and the place
at which the tests are to be conducted so that arrangements may be made for his representative to
be present. Prior to shipment of the equipment, the Contractor shall furnish the Employer five (5)
certified copies of all design and production test reports.
The equipment to be supplied under the Contract shall be fully equipped for the actual amount
of data to be acquired and commands to be executed, plus a spare capacity of 20% for each type
of data.
The Contractor shall be responsible for the complete design, installation, wiring, testing,
commissioning and documentation of the RTU extension works,, including any required new
or parallel connections to NEA’s field equipment as described in this Specification, including
synchronization with the existing SCADA equipment.
3.1.3 The equipment to be furnished shall strictly be in accordance with the specifications and the
Price Schedule.
Remote control
remote control of selected 33 kV circuit breakers (off-control only for load curtailment)
status indication of all 33 kV line feeders, as specified under “Remote Control” above, to be
used for load shedding from the LDC
Alarms
one grouped alarm summarizing all causes that prevent operation of a circuit breaker (Circuit
Breaker Fault Alarm, CBF)
one grouped alarm summarizing all faults not affecting operation of a circuit breaker (Bay
Fault Alarm, BFA)
single indication for operation of auto re-closure relay for 132 kV transmission lines (ARO)
transformer alarms:
"general alarm" (all other alarms except the above as one grouped alarm)
"general trip" (all other alarms except the above as one grouped alarm)
A table summarizing the alarms to be acquired by LDC from each type of bay in the 132/33/11 kV
network is shown in Table 9.1
Total 5 10 4 1 5
Measurements
Busbar voltages (separate for each busbar and section) of all 132 kV busbars.
all 132/33/11 kV transformers feeding into the distribution networks (at secondary side)
Single phase current measurements for all 33 kV/11 kV lines participating in the load
shedding scheme.
The Contractor shall supply and install all equipment and material including transducers,
meters and auxiliary relays, cables, wiring, terminal blocks, test switches, isolation
devices, conduits, cable trays/trenches and any other equipment required to interface the
RTUs with the substation equipment.
The field instrumentation, devices, connections shall not affect the current operation of the
existing substation equipment.
The Contractor shall be responsible to perform any necessary modification to the existing
substation facilities to accommodate RTU extension works.
The new equipment shall be adapted to site conditions with the following:
Bidders shall propose the new RTU cards, equipment, accessories, etc. required for
extension works, so as to incorporate the following functional requirements.
RTUs to be installed under the project shall provide at least the following functions:
regulation command outputs e.g. raise/lower command outputs for transformer tap
changer control
Sequential Event Recording (SER) with time stamping of events at the RTU
self-testing and diagnostic functions for detection and reporting of any error
3.2.1 Telecontrols
The RTUs shall have the capability for the SCADA system master station to select and
control specified power system devices. The following power system devices will be
controlled by the RTU:
The RTUs shall ensure that only the correct output is selected for two state devices before
command execution.
The SCADA system shall transmit a command message addressing the proper
RTU and the control point within the RTU, and indicate the control action
desired.
The RTU shall initialize its control logic, reassemble the command message, and
transmit the reassembled message to the SCADA system. The message sent to the
SCADA system shall be generated by the RTU's point selection logic.
The SCADA system shall check the returned message for validity and, if valid,
shall issue an execute command to the RTU.
The RTU shall operate the control point selected only after the execute command
has been received.
The impedance of the output circuit shall be measured to detect jammed contacts.
The point selection logic for the control output shall be designed to preclude operation of
an unselected output under single component failure conditions. That is, no single
component shall be capable of selecting and operating an output point by itself.
In no case, any unwanted telecommand shall be given to the process in case of an RTU
power failure.
A test command (dummy breaker) shall be provided for the purpose of ensuring that the
telecommand function is working correctly. The test command shall correspond to circuit
breaker close/open command with back-indications on/off.
The RTU communications protocol shall also support "immediate execute" contact outputs
(where an operation can be commanded without the validity check and execute message
exchange) for control output types such as On Load Tap Changer (OLTC) raise / lower
command outputs.
3.2.3 Teleindications
The RTU shall report teleindications by exception but shall also allow the SCADA system
to demand - scan status data even if the data has not changed.
The status (open / closed) of two state devices such as circuit breakers, isolators or earthing
switches shall be acquired by using suitable designs. These may, for example, be acquired
by 2 independent, potential - free contacts or by 2 interposing relays, one for each position.
Position indications shall be checked for validity and undefined states like open and closed
(1 | 1) or neither open nor closed (0 | 0) shall be alarmed. The RTU shall provide for run-
time-monitoring, adjustable to the HV equipment operation parameters, to avoid alarming
of undefined states while the equipment (e.g. isolator) is operating.
3.2.3.2 ALARMS
Alarms shall be acquired as single indications by appropriate designs via potential - free
contacts.
Telemeasurements
In analogue measurands the information to the RTU is given in the form of an analogue
current supplied by the output of an analog measuring transducer. The analog signals
shall be converted to digital mode by an analog-to-digital converter, to which the inputs are
connected. All inputs of a module shall be measured within one cycle, regardless of the
number of inputs in use. Thus new points can be added to the RTU without
reprogramming.
Analog measurements shall be transmitted to the master station with 16 bits or 15 bits +
sign bit.
3.2.4 Telemetering
The RTU shall be capable of Sequence-of-Events (SER) data collection at a time resolution
less than the operating speeds of the power system devices. Any digital input points in the
RTU may be assigned, programmable as an SER data point. In general, a breaker position
change and any alarm from a protection device that has initiated a trip signal is defined as
an event for SER. Multiple transitions of a device, such as the tripping and subsequent
reclosing of a breaker, shall be considered as a series of separate events. Each time an
event is detected, the RTU shall time-tag the event and store it together with the time-tag of
the event for transmission to the SCADA system with the next scan. The buffer shall be
sized to store, as a minimum, a number of events equal to three times the number of SER
points implemented in the RTU.
The time-tag recorded with each event shall be generated from a clock internal to
the RTU.
Separating capability
Time resolution
The internal clock of each RTU shall be synchronized either from an internal, Contractor
supplied and installed time synchronization source, such as a Global Positioning
System (GPS) or an omega synchronizing signal receiver or through the telecommunication
network from a master clock installed at the LDC.
The synchronization shall be done periodically such that the time-tags in each RTU shall be
within five milliseconds (5 ms) accuracy between all RTUs.
Bidders shall clearly indicate the method used for time synchronization and describe in
detail how the required accuracy is achieved.
In the RTU there shall be a digital output from which time synchronization messages can
be forwarded to external devices. The frequency of the activation of the message shall be
adjustable.
Data transmission
The data transmission network shall consist of dedicated data channels utilizing Fibre optic
transmission media. The RTUs shall be capable of utilizing different protocols on separate
RTU communication ports. Communication protocols shall be implemented by modifiable
firmware in the RTU. Reconfiguration of the RTU database may be necessary when an
RTU's communications protocol is changed due to the difference in the functions
supported by the protocol.
The Contractor shall provide and implement a version of the standard IEC 60870-5-
101/104 communications protocol which shall support all the functions specified in this
document. The RTU protocol shall be non-proprietary for use within NEA. NEA shall be
authorized to disclose the RTU protocol to third party suppliers.
3.11 Interconnections
All connections between the RTU's termination facilities and signal wiring shall be
through barrier-terminal blocks with knife-switch isolation, mounted in the RTU panel or
an adjacent marshalling cabinet. Terminal blocks shall be screw-type, with full depth
insulating barriers.
The digital inputs shall be opto-isolated, signal voltage 48 V DC. Other lower voltages
shall also be possible by changing the matching resistor in the input circuit.
Contact bouncing of the interposing relays shall be filtered. The bounce filtering time
shall be 7 ms. Input circuits with selectable bounce filtering time setting are preferred.
The indications shall preserve the chronological order of events inside the RTU.
The resolution time requirement is 10 ms.
Oscillating inputs as a result of, e.g. a faulty relay chattering, shall be blocked locally at
the RTU.
In analogue measurements, the information to the analog input modules of the RTU is
given in the form of analog current supplied by the output of measuring transducers.
In analog input modules, the following current input ranges shall be available:
It shall be possible to change the input range for each individual input, preferably by
software means, instead of changing the input resistor. The analog input circuit shall have
a precise DC impedance less than 200 ohms for current inputs. This impedance must not
vary more than half of the accuracy of the Analog to Digital Converter (ADC) with
influence values such as temperature, etc. In the input circuit, galvanic isolation shall be
provided from mechanical earth and electrical earth, and, preferably, between different
inputs. The circuits of the analog input module shall be protected against disturbances
caused by switching transients and against disturbances at power and RF frequencies
present at outstations.
The scanning of each input shall not introduce any error on the analog information.
For each input it must be possible, without disturbing the other inputs,
to isolate the input from the ADC and close the analog circuit,
to measure the analog input value without disturbing the measurement (addition
of an mA meter over a link which is then disconnected).
The analog information shall be converted into digital value by the ADC which can be
common for all inputs. Analog measurements shall be transmitted to the master station
with at least 11 bits + sign bit.
The input circuits must withstand a permanent overload of 30% without any damage.
The maximum value that is possible to code (with the correct sign).
3.14 Pulse inputs
The counter register shall be 16 bit. The maximum input frequency shall be 25 Hz.
In practice, the pulses will be dimensioned in a way that max. Frequency is less than 5 Hz.
Interposing relays will not be used.
For telecommands:
Coil voltage shall be 48 V DC. Coil voltage variation shall be +10% and -20%.
Signal voltage on the contact circuit shall be 110V DC depending on the station.
The rated contact current shall be minimum 10 A making / breaking at 110 V DC.
For teleindications:
Coil voltage shall be 110 V DC. Coil voltage variation shall be +10% and -20%.
Relays with two (2) normally open and two (2) normally closed contacts shall be
provided. Contact bounce shall be less than 8 ms and contact age shall be 106 operations
Dielectric strength shall be 2 kV, 50 Hz-1 min between one circuit and the earthing point
and between independent circuits, 1 kV, 50 Hz during 1 min between two terminals of the
same circuit. Impulse test voltage: 5 kV (IEC 60255-5)
Plug - in type relays and sockets shall be used with sockets directly mounted on a DIN
rail.
All necessary arrangements must be made so that the plugging - in and out are easy and
performed without any risk of damaging of relay parts.
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-30
The relays shall be fitted with a visual operation indicator (either mechanical or LED).
3.17 Transducers
Transducers shall be of the latest state-of- the art solid state technology, not requiring
frequent calibration and preventive maintenance and shall be free from electro-magnetic
interference and noise. They shall use electronic surface components and all of its internal
parts are protected by a tropicalization varnish. Transducers shall comply to the latest
international standards and, mandatorily, to the IEC 60688 publication. Transducers shall
in general be installed in the control or protection board of the switchgear equipment.
Accuracy of the measurements for MW, MVAR, voltages shall be better than
0.5% of full scale over a temperature of 0 to 50 °C.
Response time to 99% of final value and shall not exceed 0.5 sec.
The analogue outputs of the transducers as inputs to the RTU shall be isolated,
unipolar or bipolar, 2 - wire load independent DC current of 0 to 10 mA or ±10
mA.
Active and re-active power measurements shall be made 3 phases - 3 wires for unbalanced
load. A single phase-to-phase voltage shall be acquired for each measurement point.
Voltage transducer shall provide for expanded scale of +/- 20% of the rated voltage.
3.18 Cables
The instrumentation cables from the RTU electronics cabinet, to the interface terminals at
the substation control / switchgear shall be supplied by the Contractor.
The outer PVC sheath shall conform to flame test requirements of IEC 60323-3
category C. Manufacturer’s name, manufacturer’s type, core quantity and cross-
section, year and month of manufacturing shall be indicated.
Pair-twisted cores, each pair and the whole core surrounded by protective screen
shall be used for connection of transducer secondaries to the RTUs.
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-31
For connection of controls, status indications and alarms, cables with protective
screen surrounding the whole core are acceptable.
In the design made by the Contractor the following shall be taken into account:
Short-term spare parts that shall be necessary for two (2) years of operation
Long-term spare parts that shall be necessary for ten (10) years of operation.
3.3.2 Portable testing equipment
The Contractor shall supply 1 (one) portable RTU testing equipment sets for testing RTU
operation and functioning without any cost to NEA. No separate payment shall be made
for it. Each testing set shall be capable of emulating communications from both the
SCADA system and the RTUs. These testing sets shall also be capable of passively
monitoring all communication traffic on a channel without interfering with channel
operation.
Annexure-IV
Specification for Revenue Meter & Metering (Instrument) Transformer
General
The units shall be suitable for operating in Outdoor environment and shall be
manufactured by International Reputed ISO 9001 Company.
Energy Meter
The Energy Meter shall be programmable in site and shall have the following minimum
requirement
Frequency 50Hz
Load Profile Memory Storage At Least 60 days of storage using 4 channels at 15 min Intervals
Other to be included
ANNEXTURE –V
LIST OF PREFERED (SHORTLISTED) MAKE
It is preferred that the following equipment be supplied from the manufacturers listed hereunder:
1) Main Protection Relays, Control &Relay panel, Substation Automation System from: ABB,
AREVA / ALSTOM, SIEMENS, Fuji, Reyrolle, Toshiba, Mitsubishi, GE or equivalent.
3) SF6 Circuit Breakers from: ABB, AREVA/ ALSTOM, Hitachi, Siemens, Toshiba / Mitsubishi,
LG, Fuji, GE or equivalent.
4) VCB Switchgear from: ABB, AREVA/ ALSTOM, Hitachi, Siemens, Toshiba/ Mitsubishi, LG,
Fuji, GE, Schneider Electric or equivalent.
5) On-Load Tap Changer: The on-load tap-changer (OLTC) to be equipped on the power
transformers and associated control equipment shall be from MR Germany or ABB Sweden or
equivalent.
6) AVR: The AVR to be equipped on the RTCC shall be from MR Germany or ABB Sweden or
equivalent.
8) Air Insulated Substation: ABB, AREVA/ ALSTOM, SIEMENS, Toshiba / Mitsubishi, GE,
HYOSUNG, Hyundai, Hitachi or equivalent.
ANNEXTURE VI
EGMP AF EMP
Project Impact or risk to be Mitigation measure(s) Performance Institutional responsibilities Budget/source
component or mitigated indicators (including implementation, supervision, and
activity monitoring)
PMD PSC Contractor /
Subcontractor
Project-wide EMP
Detailed design and pre-construction preparations
General
Compliance Environment, health, and NEA and Contractor to ensure compliance with No breaches of PMD to comply PSC to Contractor to NEA counterpart
with national safety impacts and risks national and international regulatory framework national regulations with requirements supervise, comply with funds
regulations and of the project in general as set out in Section II of the IEE, including ADB and/or international throughout project monitor, and requirements
international Safeguard Policy Statement (2009), IFC EHS good practice implementation. assist PMD in throughout Part of PSC
good practice General Guidelines (April 2007), and IFC EHS guidelines. PMD supervise ensuring their contract budget
guidelines. Guidelines for Electric Power Transmission and and monitor own implementation.
Distribution (April 2007) plus other applicable contractor to compliance Part of contract
environment, health and safety laws and ensure their and assist with cost, include costs
regulations in force during project compliance with supervision of implementing
implementation, in addition to any further delegated and EMP as BOQ line
mitigation measures set out in this EMP. requirements. monitoring of
the contractor.
Grievance Environment, health, and NEA with support of Contractor to establish multi- GRM PMD to comply PSC to Contractor to NEA counterpart
Redress safety impacts and risks level GRM as per Section VII of IEE, including operationalized with requirements supervise, comply with funds
Mechanism of the project on affected identification of GRM Officers at all GRM levels upon loan throughout project monitor, and requirements
(GRM). persons; including and Grievance Redress Committee members. effectiveness, implementation. assist PMD in throughout Part of PSC
construction workers and NEA and Contractor to carry out community affected persons are PMD to supervise ensuring their contract budget
affected local awareness raising during community meetings aware of its and monitor own implementation.
communities and one-to-one discussions about the GRM with existence and are contractor to compliance Part of contract
directly affected persons before the actively using GRM ensure their and assist with cost, include costs
commencement of works including details of how to raise their compliance with supervision of implementing
to submit a grievance to either NEA and/or the grievances. delegated and GRM as BOQ line
Contractor, consultations are to be documented. requirements. monitoring of
NEA and Contractor to disseminate GRM contact 100% of grievances the contractor.
details verbally and by SMS as well as through received are
distribution of leaflets, and prominently posting resolved in a timely
GRM arrangements on noticeboards located at manner by NEA and
the project sites and at local NEA offices, project Contractor.
substations, community centers etc.
Contractor to carry out awareness raising Details of GRM
amongst workers about the GRM at the start of operationalization
Obtain national Environment, health, and NEA to ensure all national EIA/IEE required are National EIA/IEE PMD to comply PSC to Contractor to NEA counterpart
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-8
Update and Environment, health, and NEA to update the IEE to reflect additional Updated IEE cleared PMD to comply PSC to Contractor to NEA counterpart
disclose IEE safety impacts and risks meaningful consultation and national and disclosed by with requirements supervise, immediately funds, including
prior to of the project in general environmental clearance conditions for ADB ADB prior to prior to issue of monitor, and inform NEA if costs of printing
contract award, clearance and disclosure prior to contract award. contract award. bidding assist PMD in any
update as NEA to review the final IEE following the documents and ensuring their unanticipated Part of PSC
required to completion of the detailed designs and update it, IEE updated, as before the own impacts are budget
reflect detailed as required, to reflect the detailed design for all required, to reflect commencement of compliance. identified at any
designs. project components, and obtain ADB’s clearance the detailed design works. PSC to point and make Part of contract
before the commencement of any works, for all project support PMD a copy of the cost, include costs
including enabling works. components prior to PMD to supervise in finalizing latest IEE of implementing
If a change in project scope or design occurs the start of any and monitor and updating available at the EMP as BOQ line
during project implementation or if unanticipated works. contractor to IEE/EMP project sites.
impacts are identified at any point during project ensure their documentation
implementation NEA to inform ADB and, if Final IEE, any compliance with .
deemed appropriate, NEA will update the IEE for subsequent updates delegated
clearance and disclosure by ADB. Project to it, and other requirements.
components having associated facility unable to environmental
avoid significant irreversible impacts post- safeguards
mitigation on protected areas, natural and critical documentation are
habitat do not qualify for financing under this locally disclosed.
project. NEA will ensure all associated facility of
the project comply with national laws and
regulations, and are consistent with SPS
requirements by requiring them to comply with
this EMP.
NEA to locally disclose in a timely manner the
final IEE, any subsequent updates to it, and other
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-9
Trainings and Environment, health, and NEA with the support of the PSC to prepare Detailed training PMD to comply PSC to Contractor to NEA counterpart
awareness safety impacts and risks detailed training plan upon loan effectiveness plan reflecting final with requirements supervise, comply with funds
raising of the project in general. elaborating how training and awareness raising EMP requirements throughout project monitor, and requirements
activities. activities required by the final EMP will be developed upon implementation, assist PMD in throughout Part of PSC
conducted. loan effectiveness. including ensuring their contract budget
conducting own implementation,
EHS management: Trainings and training sessions compliance including Part of contract
NEA with support of the PSC to conduct training awareness raising and ensuring and assist with conducting cost, include costs
sessions on EMP implementation for all those delivered in relevant staff supervision training sessions of implementing
with management responsibilities under it to accordance with the attendance. and and ensuring EMP as BOQ line
clarify national and ADB SPS (2009) plan. monitoring of relevant staff
requirements, requirements at each stage of the PMD supervise the contractor. attendance. Indicative costs for
project, roles and responsibilities, and, record Contractor and and monitor PSC to trainings and
keeping and reporting requirements. construction workers contractor to develop awareness raising
NEA with support PSC to conduct training fully aware of their ensure their training are included in the
sessions on GRM operationalization for all those responsibilities compliance with materials for EMP budget table
with responsibilities under it, including the under EMP through delegated NEA, act as
nominated PMD Community Engagement/GRM training. requirements. resource
Officer, and all members of the grievance redress person to
committee. Details of training deliver them,
Contractor to ensure all members of its project and awareness and ensure
management team, environment safeguards raising sessions, relevant
team, design team, construction management including photos and specialists’
team, and community engagement/GRM officers records of attendance.
attend NEA trainings. participants
Training of all PMD and O&M staff on the climate (including gender)
change impact of SF6, alternatives, H&S risks documented and
during O&M due to presence of toxic byproducts, included in
leakage minimization, and environmentally sound monitoring reports.
and safe disposal of old equipment with SF6
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-11
Construction workers:
Contractor to conduct training for construction
management and provide all workers and visitors
on-site, irrespective of them being formally or
informally employed by contractor, subcontractor
or third-party with an environmental, health and
safety induction before being allowed on-site
including do's and don’ts in relation to
construction site, temporary workers camps, local
communities, protected areas, etc.
Contractor to ensure topics covered by training
and induction will include but not be limited to:
good housekeeping at all times; environmentally
sound waste management practices; hygiene
and communicable disease prevention including
COVID-19 and HIV/AIDS; snake and rodent bites
and precautionary measures for avoidance i.e.
avoid work after rain, flood, and in the crop
ripening seasons, caution while putting hands in
holes; sexual exploitation, abuse and harassment
prevention; culturally acceptable practices;
biodiversity conservation awareness; fire safety
prevention; prohibition on firewood and NTFPs
collection by workers; prohibition on fishing,
hunting, or poaching by workers; heritage
conservation awareness; chance find
procedures; OHS, including use of PPE; etc.
Contractor to conduct training for construction
management and regular drills involving workers
irrespective of them being formally or informally
employed by contractor, subcontractor or third-
party on emergency preparedness and response
procedures in case of an environmental or health
and safety incident including spillage, fire, natural
disaster, disease outbreak etc. Training for
construction management will include modules
on first aid and fire safety including include
training on how to use first aid and firefighting
equipment provided on-site and the scenario of
potential or confirmed COVID-19 infection on-
site.
Contractor to continue to deliver short
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-12
Community awareness:
Contractor to undertake construction safety
community awareness raising activities in local
affected communities within 500m of substations
and transmission lines prior to construction.
NEA to undertake electrical safety community
awareness raising activities in local affected
communities within 500m of substations and
transmission lines prior to construction,
awareness raising activities to be repeated on
completion of construction; to include
electrocution risks, EMF, corona noise, etc.
Detailed Environment, health, and NEA and Contractor to address all site-specific NEA approved PMD to comply PSC to Contractor to NEA counterpart
design. safety impacts and risks measures detailed in this EMP with regards detailed designs with requirements supervise, comply with funds
of the project in general biodiversity and physical cultural resources as minimize impacts prior approval of monitor, and requirements
well as other sensitive receptors during the and risks on detailed design. assist PMD in prior to approval Part of PSC
detailed design, as well as ensuring the detailed environment, health ensuring their of detailed budget
designs reflect international engineering best and safety during PMD to supervise own design.
practice/ good EHS practices. construction and and monitor compliance Part of contract
Contractor’s detailed designs will be reviewed by operation & contractor to and assist with cost, include costs
the PSC to confirm that all measures required by maintenance ensure their supervision of implementing
the final EMP have been adequately incorporated stages. compliance with and EMP as BOQ line
and that they reflect international engineering delegated monitoring of
best practice/good EHS practice before they are requirements. the contractor.
approved by NEA. PSC to review
detailed
Disaster risk management: design and
During detailed route survey identify presence of confirm in
any floodplain, waterlogged or unstable land, accordance
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-13
Biodiversity management:
Contractor to strictly locate all temporary
construction facilities outside of forest areas, all
temporary workers camps unless within
substation boundaries are to be located at least
500 m for forest areas. Location of related project
facilities is to be identified by contractor, PSC
international biodiversity expert to review if
locations are suitable prior to NEA approval.
Include in CEMP or site-specific BMP emergency
fauna rescue and handling procedure, including
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-21
Traffic management:
NEA and the Contractor to consult with and seek
the agreement of the irrigation authority to use
the existing irrigation access roads for the
purposes of construction.
For all works on or adjacent to public roads, the
Contractor will prepare for NEA approval a
Construction Traffic Management Plan (CTMP)
appropriate to the pedestrian and vehicular traffic
flows on the road as part of the CEMP in
consultation with relevant local authorities/traffic
police to ensure proper execution of traffic
controls including where temporary blockage of
the road during installation is required for health
and safety purposes and ensure that highly
visible guides, advance warning signs or flag
persons are in place to direct pedestrian and
vehicular traffic.
On-site enabling works, construction works, testing and commissioning of project components
Biological Environment
On-site pre- Impacts on biodiversity Comply with CEMP during construction works Compliance with PMD to comply PSC to Contractor to NEA counterpart
construction including Chure Ensure clear demarcation of the working area national laws and with requirements supervise, comply with funds
and Conservation Area and avoid encroachment outside the agreed regulations. during monitor, and requirements
construction corridor of impact. construction. assist PMD in throughout Part of PSC
activities Trees are to be cleared during non-bird breeding Mitigation measures ensuring their construction budget
season, if this not possible due to weather successfully PMD to supervise own
restrictions on access, trees cleared during implemented by and monitor compliance Part of contract
breeding season to be checked by field ecologist NEA and Contractor contractor to and assist with cost, include costs
for nests prior to clearance, if present harvesting as determined ensure their supervision of implementing
to be postponed until the young have fledged. through regular site compliance with and EMP as BOQ line
Unnecessary use of machinery to be avoided to checks, delegated monitoring of
minimize disturbance to fauna. photographic record requirements. the contractor. Indicative costs for
Revegetate any disturbed areas beyond footprint etc. purchase of bird
of substation and tower foundations to at least divertors
original condition through revegetation using No outstanding (excluding their
biodiversity-related installation) and
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-30
No outstanding
topography/ terrain
related grievances
from local
communities.
On-site pre- Changes in ambient air • Comply with CEMP, CPPP, and the IFC EHS Compliance with PMD to comply PSC to Contractor to NEA counterpart
construction quality - dust and General Guidelines in relation to air quality and national laws and with requirements supervise, comply with funds
and suspended particulate avoid the occurrence of pollution incidents as far regulations. during monitor, and requirements
construction matter from earthworks, as practicable construction. assist PMD in throughout Part of PSC
activities and other pollutants from • Require construction equipment and vehicles to Mitigation measures ensuring their construction, budget
vehicular emissions, may meet national emissions standards, see successfully PMD to supervise own keep required
affect ambient air quality Appendix 2 of IEE. implemented by and monitor compliance maintenance Part of contract
with impacts on the • Perform regular checks, upkeep, and NEA and Contractor contractor to and assist with records and cost, include costs
health of workers and maintenance of construction equipment and as determined ensure their supervision undertake of implementing
community. vehicles to keep them in good working order as through regular site compliance with and ambient air EMP as BOQ line
per the manufacturer's specifications to meet checks, delegated monitoring of quality
emission standards. Keep log of maintenance photographic record requirements. the contractor. monitoring in
undertaken. etc. accordance with
• Sprinkle water during earthworks to avoid dust the EMoP
being dispersed by wind, cover with materials like Monitoring confirms
gravel to minimize re-suspension of dust. ambient air quality
• Stockpiles of spoil and other dust generating within national
materials to be kept to a minimum necessary to standards or no
undertake works for the day worsening of the
• Cover stockpiles with tarpaulin. Locate stockpiles baseline situation if
at least 500m from residential property to avoid already exceeded.
inconvenience to avoid inconvenience from
fugitive dust and ensure they are enclosed by a No outstanding air
fence or similar to minimize windblown dust. quality-related
Minimize double handling and drop loads. grievances from
• Trucks importing loose raw materials or removing local communities or
spoil to local approved disposal sites must be workers.
covered with tarpaulin to reduce dust generation,
all trucks used are to be serviced and meet
Nepal emission standards and belching of black
smoke prohibited.
• Position any stationary emission sources (e.g.,
water pumps, diesel generators, compressors,
etc.) as far as practical from sensitive receptors
(houses, schools, clinics, temples, touristic areas
etc.)
• Impose speed limits on construction vehicles to
minimize exhaust and dust emissions along
areas where sensitive receptors are located
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-33
On-site pre- Occupational health and • Comply with CHSMP and with IFC EHS General Compliance with PMD to comply PSC to Contractor to NEA counterpart
construction safety of workers at risk Guidelines in relation to occupational H&S. national laws and with requirements supervise, comply with funds
and due to the hazards • Ensure health and safety supervisor is on site at regulations. during monitor, and requirements
construction created during the all times (implies an alternate off on leave or on construction. assist PMD in throughout Part of PSC
activities construction period, e.g. sick). Mitigation measures ensuring their construction, budget
movement of heavy • Require subcontractors and workers to confirm successfully PMD to supervise own maintain records
equipment, vehicles, and they have seen and understood the requirements implemented by and monitor compliance of health and Part of contract
machineries, working of the CHSMP before proceeding with their work. NEA and Contractor contractor to and assist with safety incidents cost, include costs
conditions, etc. • Provide worker training on H&S and daily/weekly as determined ensure their supervision per the EMoP of implementing
briefings led by site-appointed Health and Safety through regular site compliance with and and maintain EMP as BOQ line
Workers may be exposed Officer. checks, delegated monitoring of copies of
to occupational health • PPE to be provided for all workers (regardless photographic record requirements. the contractor. training records. Budget for
risks and safety hazards, formal and informal, directly contracted or etc. PSC compensation
regarding site clearance subcontracted) in accordance with Table 2.7.1. international included in
for pre-construction and Summary of Recommended Personal Protective No outstanding OHS health and Resettlement Plan
during construction Equipment According to Hazard in IFC EHS related grievances safety expert and Indigenous
relating to working with Guidelines on OHS. to work closely People
electricity and working at • Enforce disciplinary system (e.g. immediate No fatalities or lost with PMD
height, as well as from removal from site) for non-compliance with PPE time incidents, if health and
handling PCBs or requirements and other H&S measures (e.g. they do occur to be safety staff to
asbestos in upgrade social distancing for COVID-19). reported to NEA ensure
works at existing • Check health condition of workers on daily basis, board and knowledge
substations. for example, use of self-certification forms and management within transfer and
temperature checks before being allowed on the 24h and to ADB development
construction site with more thorough monthly within 48h. of
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-41
On-site pre- Community health and • Comply with CHSMP and with IFC EHS General Compliance with PMD to comply PSC to Contractor to NEA counterpart
construction safety - at increased H&S Guidelines in relation to community H&S. national laws and with requirements supervise, comply with funds
and risk from communicable • Installation of barriers (a temporary fence ideally regulations. during monitor, and requirements
construction diseases as workers solid fence) at construction areas with hazard construction. assist PMD in throughout Part of PSC
activities coming from elsewhere, warning signs to deter people from accessing the Mitigation measures ensuring their construction, budget
including COVID-19, construction site successfully PMD to supervise own maintain records
social disturbances implemented by and monitor compliance of health and Part of contract
related to workers camps, • Do not leave hazardous conditions (e.g. NEA and Contractor contractor to and assist with safety incidents cost, include costs
traffic, electricity unfenced and unlit open excavations without as determined ensure their supervision per the EMoP. of implementing
infrastructure etc. means of escape) overnight unless no access by through regular site compliance with and EMP as BOQ line
public can be ensured checks, delegated monitoring of
• Define construction schedule for sections along photographic record requirements. the contractor. Budget for
or crossing roads in coordination with local etc. PSC compensation
authorities/traffic police particularly where road international included in
closures required. No outstanding CHS health and Resettlement Plan
• Implement CTMP during construction works with related grievances safety expert and Indigenous
advance warning signs or flag persons to ensure to work closely People
traffic safety of construction workers and road No project-related with PMD
users, in coordination with traffic police. accident reported health and
• Road safety and warning signs must be posted at within community - safety staff to
500m, 100m, and immediately in advance of the if they do occur to ensure
works at least two weeks prior to the works be reported to NEA knowledge
commencing to inform the public of the board and transfer and
temporary blockage. management within development
24h and to ADB of
• Access to the construction site will be under within 48h. knowledgeabl
traffic controls when trucks enter and exit. e health and
100% of H&S safety team at
• Require all project drivers to abide by Nepal road incidents including NEA.
safety regulations at all times. near miss recorded,
• Use of scaffold and bamboo frames to support immediately
stringing to protect structures, roads, irrigation investigated, and
canals, utilities etc. as well as pedestrians, corrective action
vehicles, and the conductor itself. taken to prevent
repeat
On-site pre- Loss of physical cultural • Comply with CEMP and chance find procedure; Compliance with PMD to comply PSC to Contractor to NEA counterpart
construction resources (PCR) - implement as soon as any monuments or national laws and with requirements supervise, comply with funds
and chance find procedures artefacts encountered during construction regulations. during monitor, and requirements
construction will be implemented in activities. construction. assist PMD in throughout Part of PSC
activities case of chance find • Strictly ensure no chance finds are tampered Mitigation measures ensuring their construction. budget
(including fossils). with. successfully PMD to supervise own
• Brief workers on chance find protocol and on implemented by and monitor compliance Part of contract
apply penalties applying for tempering with them. NEA and Contractor contractor to and assist with cost, include costs
• Contractor to declare a chance find to DOA and as determined ensure their supervision of implementing
NEA within 24h of find. through regular site compliance with and EMP as BOQ line
• PMD to report on any chance find having checks, delegated monitoring of
occurred within 48h to ADB. photographic record requirements. the contractor. Budget for
etc. compensation
included in
No outstanding PCR Resettlement Plan
related grievances
100% of chance
finds were reported
to DOA and dealt
with in accordance
with chance find
procedure
Physical Environment
AIS Climate change from • Keep record of all gas insulated switchgear and Compliance with PMD to implement n/a n/a NEA’s operational
substations fugitive emission of SF6 gas insulated transformers, including presence, if national laws and EMP in budget.
any, and quantity of SF6 in these. regulations. collaboration with
• Provide SF6 leakage detection kit at each NEA operation &
substation. Mitigation measures maintenance
• NEA to monitor SF6 emissions through inventory successfully teams on site.
control and accounting per the requirements set implemented by
out in the EMoP. NEA as determined
• Proper handling and storage procedures to be through regular site
implemented in accordance with equipment checks,
suppliers’ specifications and best practices. photographic record
Check for SF6 gas leakage in every shift of the etc.
operation.
• Maintain SF6 leakage records in every substation SF6 leakage below
and report in periodic monitoring reports to ADB. 0.1% per annum
• Define a safe SF6 retrieval arrangement, with
appropriate handling, storage, disposal process
for end of life equipment in accordance
international good practice.
EMF:
• Monitor electromagnetic field strength workers
are exposed to and ensure occupational
exposures are within the limits of the International
Commission on Non-Ionizing Radiation
Protection (ICNIRP) reference level. If EMF
limits are often reached, provide workers with
personal radiation monitors that shall set off an
alarm when exposure limits are reached.
• Monitor electromagnetic field strength where
regularly occupied properties are in the ROW and
ensure public exposures are within the reference
levels of the International Commission on Non-
Ionizing Radiation Protection (ICNIRP)
Housekeeping:
• Keep the substation neat and tidy at all times.
• Remove any trip hazards on the ground, e.g.
open channels, materials, equipment, trash
laying around.
• Carry out regular pest control where pests are a
risk; favor natural pest control measures when
possible.
• Display clear emergency exits signs (in working
order, if light signs, ensure works) and keep exits
clear of any blockage.
• Visually inspect for any standing water on site,
and when identified, remove or provide
appropriate drainage to remove in timely manner;
ensure drainage system is not blocked and fully
operational.
• Maintain all lights in working order.
• Ensure all vents are free of blockages and
regularly maintained.
Emergency situations:
• Ensure a recent, full, first aid kit and adequate
firefighting equipment is available on site at all
times, stored in clearly labelled and easily
accessible area.
• Replace the first aid equipment timely as
required to keep all equipment within its expiry
date.
• Service the firefighting equipment timely as
required to keep all equipment in date
• Provide first aid and firefighting training to select,
volunteer staff; at least one staff having recently
carried out first aid and firefighting training must
be present on site at all times. Refreshers are to
be provided once a year.
• Hang posters showing first aid procedures
especially for electrocution, and fire procedures,
as well as listing all emergency contacts. Display
the emergency phone number and location of
doctor and hospital in a clear and easily
accessible location.
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-52
Site-specific EMP
Contract Impact on locally • NEA and Contractor to plan to minimize the Compliance with PMD to comply PSC to Contractor to NEA counterpart
Ghorahi- important physical cumulative impacts they may cause to the local national laws and with requirements supervise, comply with funds
Madichaur cultural resources community. regulations. during detailed monitor, and requirements
TLP • Transport equipment only during non-rush hours design, assist PMD in throughout Part of PSC
i.e., avoid the hours of 6 am to 8 am and 4 pm to Mitigation measures preconstruction, ensuring their detailed design, budget
6 pm. successfully construction, and own preconstruction,
implemented by operation & compliance construction. Part of contract
• Local communities will be informed will in NEA and Contractor maintenance. and assist with cost, include costs
advance of the construction schedule for noisy as determined supervision of implementing
activities. through regular site PMD to supervise and EMP as BOQ line
• Use drilling as opposed to open trench checks, and monitor monitoring of
construction within the built-up area for photographic record contractor to the contractor.
underground cabling to minimize dust generation. etc. ensure their
• Contractor to carry out detailed line route survey compliance with
of alignment of Ghorahi-Madichaur TLP, No outstanding site delegated
including undertaking detailed pre-construction specific-related requirements.
structural survey and photographic record of all grievances from
property adjacent to the road, in case of any local communities.
damages claim during laying of cable works.
Paying particular attention to weak and sensitive
structures along the alignment determine the
level of risk and whether such buildings may
require the installation of vibration monitors
during construction to monitor movement.
• Do not allow the use of oil or bentonite clay as a
drilling fluid, if water is used any excess must be
disposed of to an adjacent defined area of
ground for percolation, or to waiting tanker trucks
for proper disposal, it must not be disposed of to
surface water.
• NEA to deliver awareness raising on bird
electrocution and collision with power lines and
adopting international good practice for “bird
OCB No. PMD/EGMP/GKTLSS-078/79-01 Procurement of Plant Single-Stage: Two-Envelope
Turnkey Bidding Documents
Ghorahi-Madichaur 132 kV TLP 1-53