OGL320.Updated Project Plan.MFv1.1.

23FEB21

### OGL - 320 PROJECT PLAN

Delivery Planned Start Planned End Re-Planned Re-Planned Planned time Actual Start Actual time Planned vs. Actual
Product Tasks Subtasks PM Strengths to Complete Tasks and Subtasks Actual End Date
Due Date Date Date Start Date End Date to invest (hrs.) Date invested Time Invested

Read the ASU Student Academic Policy and then enter


Log in to Canvas and access the module page, locate the assignment
the date you read it to indicate your agreement to abide
by it. Click on the hyperlink in canvas and read the entire document
Acknowledge reading the Academic policy by submitting Name and Date
Complete acknowledgment in Canvas
in to Canvas Schedule time to complete the reading of the policy and
1 Agreement to Adhere to the Academic Integrity Rules 12-Jan-21 10-Jan-21 10-Jan-21 N/A N/A 0.5 10-Jan-21 10-Jan-21 0.5 0
ensure submission is delivered on time.

Log into Canvas to access modules and click the link to access Perusall
Access reading of Course Structure Conversation
Contributions Read document Provide detailed responses that relates to and support
Ensure to read all the instructor's comments
other PM questions based on my experience can help
14-Jan-21 Enter annotations before the deadline
2 Course Structure Conversation Contributions support the other PMs. Schedule time to enter any 13-Jan-21 14-Jan-21 N/A N/A 1 10-Jan-21 10-Jan-21 1.5 0.5
Verify earned score is updated and reflected in Canvas
questions on reading early to obtain any timely
Ensure assignment is completed in Perusall Download comments entered in Perusall as part of contingency plan for
responses from other PMs or the Client.
back up, then save to computer hardrive

Log into Canvas to access modules and click the link to access Perusall
Complete reading on Scrappy Project Management, Ch.1
Read document and provide thoughtful comments, questions and to the
& Ch.2
conversation. Provide detailed responses that relates to and support
other PM questions based on my experience can help
Submissions that demonstrate engagement with the concepts in Wiefling
3 14-Jan-21 Enter annotations before the deadline Verify earned score is updated and reflected in Canvas support the other PMs. Schedule time to enter any 13-Jan-21 14-Jan-21 N/A N/A 3 14-Jan-21 14-Jan-21 2.5 -0.5
(2007) Kickoff, Ch. 1 & Ch. 2
Download provided comments from Perusall as part of contingency plan questions on reading early to obtain any timely
Ensure assignment is completed in Perusall
for back up, then save to computer hardrive responses from other PMs or the Client.

Watch assigned video on Concepts in Conversation and Begin video within the Canvas module, respond and answer quiz questions
respond to quiz questions within the video to complete
Ensure assignment is complete and points are recorded Download question responses and answers and save to computer hardrive
in Canvas for back up
Submissions that demonstrate understanding of concepts in Answer questions with integrity and provide written
4 14-Jan-21 13-Jan-21 14-Jan-21 N/A N/A 1 14-Jan-21 14-Jan-21 1 0
Conversation with a PM - Part 1 Video Quiz responses to support that supports the content.
Module 1a & 1b

Log into Canvas to access modules and click the link to access Perusall
Complete reading on, What You Need to Know About
Project Management Read document and provide thoughtful comments, questions and to the Provide detailed responses that relates to and support
conversation. other PM questions based on my experience that can
Enter annotations before the deadline help support the other PMs questions and comments.
Submissions that demonstrate engagement with the concepts in
5 16-Jan-21 Verify earned score is updated and reflected in Canvas 15-Jan-21 16-Jan-21 N/A N/A 3 16-Jan-21 16-Jan-21 2.5 -0.5
O'Connell (2011) Intro, Ch. 1 & Ch. 2
Ensure assignment is completed in Perusall Download provided comments from Perusall as part of contingency plan Schedule time to enter any questions on reading early to
for back up, then save to computer hardrive obtain any timely responses from other PMs or the
Client.

Watch assigned video on Concepts in Project


Management and respond to quiz questions within the Begin video within the Canvas module, respond and answer quiz questions
video to complete
Ensure assignment is complete and points are recorded Download question responses and answers and save to computer hardrive
in Canvas for back up
Submissions that demonstrate understanding of concepts in Project Answer questions with integrity and provide written
6 16-Jan-21 15-Jan-21 16-Jan-21 N/A N/A 1 16-Jan-21 16-Jan-21 1 0
Management Terminology Video Quiz responses to support that supports the content.

Use personal computer to record an apx. 4 minute in length video


Provide a video describing a baseline assessment that is
following the instructions provided in Canvas
about you and your experience that relates to being a
Include existing competencies and abilities that relate to your project
project manager.
management experience
Provide candid and personal information that relates to
Follow criteria provided in Canvas to properly upload and embed video file
Upload video to Canvas to submit product my experience. Be transparent and ensure client
7 Baseline Assessment 19-Jan-21 in the Rich Content Editor in Canvas 17-Jan-21 19-Jan-21 N/A N/A 3 19-Jan-21 19-Jan-21 4 1
understands that communication and feedback are
important.

Watch assigned video on Baseline Assessment and Begin video within the Canvas module, respond and answer quiz questions
respond to quiz questions within the video to complete
Ensure assignment is complete and points are recorded Download question responses and answers and save to computer hardrive
in Canvas for back up
Submissions that demonstrate understanding of concepts in Baseline Answer questions with integrity and provide written
8 21-Jan-21 20-Jan-21 21-Jan-21 N/A N/A 1 21-Jan-21 21-Jan-21 1 0
Assessment Video Quiz responses to support that supports the content.

Page 1 of 6
OGL320.Updated Project Plan.MFv1.1. 23FEB21

Delivery Planned Start Planned End Re-Planned Re-Planned Planned time Actual Start Actual time Planned vs. Actual
Product Tasks Subtasks PM Strengths to Complete Tasks and Subtasks Actual End Date
Due Date Date Date Start Date End Date to invest (hrs.) Date invested Time Invested

Log into Canvas to access modules and click the link to access Perusall
Complete reading of Scrappy Project Management,
Ch.10 & Ch. 11 Read document and provide thoughtful comments, questions and to the Provide detailed responses that relates to and support
conversation. other PM questions based on my experience that can
Enter annotations before the deadline help support the other PMs questions and comments.
Submissions that demonstrate engagement with the concepts in Wiefling
9 21-Jan-21 Verify earned score is updated and reflected in Canvas 20-Jan-21 21-Jan-21 N/A N/A 3 21-Jan-21 21-Jan-21 2 -1
(2007) Chapters 10 and 11
Ensure assignment is completed in Perusall Download provided comments from Perusall as part of contingency plan Schedule time to enter any questions on reading early to
for back up, then save to computer hardrive obtain any timely responses from other PMs or the
Client.

Watch assigned video on Concepts in Rubrics and Begin video within the Canvas module, respond and answer quiz questions
respond to quiz questions within the video to complete
Ensure assignment is complete and points are recorded Download question responses and answers and save to computer hardrive
in Canvas for back up
Submissions that demonstrate understanding of concepts in Rubrics Answer questions with integrity and provide written
10 21-Jan-21 20-Jan-21 21-Jan-21 N/A N/A 1 21-Jan-21 21-Jan-21 1 0
Video Quiz responses to support that supports the content.
Module 1a & 1b

Log into Canvas to access modules and click the link to access Perusall
Complete reading of What is Quality Assurance
Read document and provide thoughtful comments, questions and to the Provide detailed responses that relates to and support
conversation. other PM questions based on my experience that can
Enter annotations before the deadline help support the other PMs questions and comments.
Submissions that demonstrate engagement with the concepts in What is
11 23-Jan-21 Verify earned score is updated and reflected in Canvas 22-Jan-21 23-Jan-21 N/A N/A 2 23-Jan-21 23-Jan-21 2 0
Quality Assurance?
Ensure assignment is completed in Perusall Download provided comments from Perusall as part of contingency plan Schedule time to enter any questions on reading early to
for back up, then save to computer hardrive obtain any timely responses from other PMs or the
Client.

Watch assigned video on Concepts in Product


Specifications and respond to quiz questions within the Begin video within the Canvas module, respond and answer quiz questions
video to complete
Ensure assignment is complete and points are recorded Download question responses and answers and save to computer hardrive
in Canvas for back up
Submissions that demonstrate understanding of concepts in Product Answer questions with integrity and provide written
12 23-Jan-21 22-Jan-21 23-Jan-21 N/A N/A 1 23-Jan-21 23-Jan-21 1 0
Specifications and Quality Criteria Video Quiz responses to support that supports the content.

Log into Canvas to access modules and click the link to access Perusall
Complete reading of Effective Project Planning
Read document and provide thoughtful comments, questions and to the Provide detailed responses that relates to and support
conversation. other PM questions based on my experience that can
Enter annotations before the deadline help support the other PMs questions and comments.
Submissions that demonstrate engagement with the concepts in De
13 26-Jan-21 Verify earned score is updated and reflected in Canvas 24-Jan-21 26-Jan-21 N/A N/A 2 26-Jan-21 26-Jan-21 2 0
Reyck (2010) - Effective Project Planning
Ensure assignment is completed in Perusall Download provided comments from Perusall as part of contingency plan Schedule time to enter any questions on reading early to
for back up, then save to computer hardrive obtain any timely responses from other PMs or the
Client.

Watch assigned video on Concepts in Planning and Begin video within the Canvas module, respond and answer quiz questions
respond to quiz questions within the video to complete
Ensure assignment is complete and points are recorded Download question responses and answers and save to computer hardrive
in Canvas for back up
Submissions that demonstrate understanding of Concepts in Planning for Answer questions with integrity and provide written
14 26-Jan-21 25-Jan-21 26-Jan-21 N/A N/A 1 26-Jan-21 26-Jan-21 1 0
Contingencies Video Quiz responses to support that supports the content.
Module 2

Document product in a word document on computer prior to entering in


Outline a product that I create often to canvas to ensure editing and format are appropriate

Create product tasks and sub tasks using the outline format, in a bulleted Demonstrate ability to outline and produce a product
15 Products, Tasks, and Subtasks 28-Jan-21 list and sub list. Save file once complete with written instructions to detail how I can produce a 27-Jan-21 28-Jan-21 N/A N/A 1.5 28-Jan-21 28-Jan-21 1.5 0
product with task and subtask described.
Cut and paste list from word file to Canvas and ensure format is correct,
Submit product description in to Canvas then submit assignment.

Log into Canvas to access modules and click the link to access Perusall
Complete reading on WBS
Read document and provide 7 thoughtful comments Dedicate time to provide clear input to plan, provide
Enter annotations before the deadline
video submission even though being on camera is
Submissions that demonstrate engagement with the concepts in Work Verify earned score is updated and reflected in Canvas
16 28-Jan-21 uncomfortable, double check all entries to ensure 27-Jan-21 28-Jan-21 N/A N/A 2 28-Jan-21 29-Jan-21 2 0
Break Down Structure (WBS) Ensure assignment is completed in Perusall Download comments entered in Perusall as part of contingency plan for
accuracy, make it easy to understand and display well to
back up, then save to computer hardrive
the client.

Page 2 of 6
OGL320.Updated Project Plan.MFv1.1. 23FEB21

Delivery Planned Start Planned End Re-Planned Re-Planned Planned time Actual Start Actual time Planned vs. Actual
Product Tasks Subtasks PM Strengths to Complete Tasks and Subtasks Actual End Date
Due Date Date Date Start Date End Date to invest (hrs.) Date invested Time Invested
Choose format (e.g. Table or Outline format) that is best to display your
plan
Create and deliver the Initial Project Plan
Build table format in excel to begin inputting data for initial project plan
Include Product Names(exact), due dates and provided instruction as Dedicate time to provide clear input to plan, provide
written in Canvas modules. video submission even though being on camera is
17 Initial Project Plan 30-Jan-21 Check with Rubric as project plan is in progress and verify information is uncomfortable, double check all entries to ensure 17-Jan-21 30-Jan-21 2-Feb-21 2-Feb-21 20 20-Jan-21 30-Jan-21 20 0
Evaluate the Project Plan you created using the rubric
accurately reflected per client's requirements accuracy, make it easy to understand and display well to
Ensure format for document is readable by Canvas to allow client to read the client.
Submit Project plan in Canvas
within the Canvas tool

Evaluate other's projects plans against Rubric provided in Canvas


*Fully Proficient - *Attempt Made - *Missing
Module 2

Review 4 colleagues' Project Plans


Provide comments on aspects of the Project Plan that are only addressed
by the rubric provided in Canvas
Review each submission, provide candid feedback to
18 Peer Reviews of Colleagues' Project Plans 2-Feb-21 support the other PMs to be successful upon their next 31-Jan-21 2-Feb-21 2-Feb-21 2-Feb-21 4 1-Feb-21 2-Feb-21 3 -1
revision of their plan.

Watch assigned video on Concepts on Feedback and Begin video within the Canvas module, respond and answer quiz questions
respond to quiz questions within the video to complete
Ensure assignment is complete and points are recorded Download question responses and answers and save to computer hardrive
in Canvas for back up
Submissions that demonstrate understanding of the concepts in the Provide examples of how I have received feedback, and
19 4-Feb-21 3-Feb-21 4-Feb-21 N/A N/A 1 4-Feb-21 4-Feb-21 1 0
Feedback Video Quiz how to seek out feedback for this class.

Watch assigned video on Concepts in Habits and respond Begin video within the Canvas module, respond and answer quiz questions
to quiz questions within the video to complete
Ensure assignment is complete and points are recorded Download question responses and answers and save to computer hardrive
in Canvas for back up
Submissions that demonstrate understanding of Concepts in Habits Video Answer questions with integrity and provide written
20 6-Feb-21 5-Feb-21 6-Feb-21 N/A N/A 1 6-Feb-21 6-Feb-21 0.5 -0.5
Quiz responses to support that supports the content.

Log into Canvas to access modules and click the link to access Perusall
Complete reading of Beyond Bias Read document, prioritize the client's comments and review each one.
Provide detailed responses that relates to and support
Respond to, answer, and provide additional comments to other PMs input
other PM questions based on my experience that can
Module 3

to the reading.
help support the other PMs questions and comments.
Submissions that demonstrate engagement with the concepts in Enter annotations before the deadline
21 9-Feb-21 7-Feb-21 9-Feb-21 N/A N/A 3 9-Feb-21 9-Feb-21 2 -1
Halvorson and Rock (2015) and with Desjardins (2018) Verify earned score is updated and reflected in Canvas
Schedule time to enter any questions on reading early to
Ensure assignment is completed in Perusall Download comments entered in Perusall as part of contingency plan for
obtain any timely responses from other PMs or the
back up, then save to computer hardrive
Client.

Watch assigned video on Biases and respond to quiz Begin video within the Canvas module, respond and answer quiz questions
questions within the video to complete
Ensure assignment is complete and points are recorded Download question responses and answers and save to computer hardrive
in Canvas for back up
Submissions that demonstrate understanding of concepts in Biases Video Answer questions with integrity and provide written
22 9-Feb-21 10-Feb-21 9-Feb-21 N/A N/A 1 9-Feb-21 9-Feb-21 0.75 -0.25
Quiz responses to support that supports the content.

Log into Canvas to access modules and click the link to access Perusall
Complete Reading on Critical Thinking Read document, prioritize the client's comments and review each one.
Provide detailed responses that relates to and support
Respond to, answer, and provide additional comments to other PMs input
other PM questions based on my experience that can
to the reading.
help support the other PMs questions and comments.
Submissions that demonstrate engagement with the concepts in Cottrell Enter annotations before the deadline
23 11-Feb-21 10-Feb-21 11-Feb-21 N/A N/A 3 11-Feb-21 11-Feb-21 3 0
(2011) - Critical Thinking Verify earned score is updated and reflected in Canvas
Schedule time to enter any questions on reading early to
Ensure assignment is completed in Perusall Download comments entered in Perusall as part of contingency plan for
obtain any timely responses from other PMs or the
back up, then save to computer hardrive
Client.
Module 4

Watch assigned video on Critical Thinking and respond Begin video within the Canvas module, respond and answer quiz questions
to quiz questions within the video to complete
Ensure assignment is complete and points are recorded Download question responses and answers and save to computer hardrive
in Canvas for back up
Submissions that demonstrate understanding of concepts in Critical Answer questions with integrity and provide written
24 11-Feb-21 12-Feb-21 11-Feb-21 N/A N/A 1 11-Feb-21 11-Feb-21 0.5 -0.5
Thinking Video Quiz responses to support that supports the content.

Page 3 of 6
OGL320.Updated Project Plan.MFv1.1. 23FEB21

Delivery Planned Start Planned End Re-Planned Re-Planned Planned time Actual Start Actual time Planned vs. Actual
Product Tasks Subtasks PM Strengths to Complete Tasks and Subtasks Actual End Date
Due Date Date Date Start Date End Date to invest (hrs.) Date invested Time Invested

Log into Canvas to access modules and click the link to access Perusall
Complete reading on Scrappy Project Management, Ch.
Read document, prioritize the client's comments and review each one.
7 & Ch.8 for Prioritizing and Change. Provide detailed responses that relates to and support
Respond to, answer, and provide additional comments to other PMs input
other PM questions based on my experience that can
to the reading.
help support the other PMs questions and comments.
Submissions that demonstrate engagement with the concepts in Wiefling Enter annotations before the deadline
25 13-Feb-21 12-Feb-21 13-Feb-21 N/A N/A 3 13-Feb-21 13-Feb-21 2 -1
(2007) Ch. 7 & 8 Verify earned score is updated and reflected in Canvas
Schedule time to enter any questions on reading early to
Ensure assignment is completed in Perusall Download comments entered in Perusall as part of contingency plan for
obtain any timely responses from other PMs or the
back up, then save to computer hardrive
Client.

Re-watch Baseline Assessment


Analyze what you did for the project you described that you managed in
your Baseline Assessment.
Copy the table provided in Canvas and fill in the third column. Provide
Provide key actions associated with the project I
Module 4

either :
Complete the table based on Fulfilling PM Principals described and how they are related to the principals and
(1) the actions you did to fulfill the specified principles
26 Fulfilling PM Principles 16-Feb-21 reference area. 14-Feb-21 16-Feb-21 N/A N/A 2 16-Feb-21 16-Feb-21 2.5 0.5
(2) the actions you could have completed to fulfill the specified principles.
Read the other entries from the members in your group and discuss them.
Ask questions, make comments, and look for familiarities.

Read the Job Description provided in Canvas Use gained understanding to best relate the job
Analyze a real Project Manager Job Description focusing Analyze each sentence that is highlighted blue
descriptions and qualifications to the PMBOK Principals
on the PMBOK Project Management Principles Copy the table provided in Canvas and place each highlighted blue
in the table.
sentence in the cell that you feel it best fits
27 PM Principles at Work 18-Feb-21 17-Feb-21 18-Feb-21 N/A N/A 2 18-Feb-21 18-Feb-21 2.25 0.25
Read the other entries from the members in your group and discuss them.
Review other PMs analyses and see how others use the
Ask questions, make comments, look for similarities
job descriptions to expand on the principals in multiple
principal areas as well.

Log into Canvas to access modules and click the link to access Perusall
Complete reading on What You Need to Know About
Read document, prioritize the client's comments and review each one.
Project Management, Ch. 4, 5 & 6 Provide detailed responses that relates to and support
Respond to, answer, and provide additional comments to other PMs input
other PM questions based on my experience that can
to the reading.
help support the other PMs questions and comments.
Submissions that demonstrate engagement with the concepts in Enter annotations before the deadline
28 20-Feb-21 19-Feb-21 20-Feb-21 N/A N/A 3 20-Feb-21 20-Feb-21 2 -1
O'Connell (2011) Ch. 4, 5, & 6 Verify earned score is updated and reflected in Canvas
Schedule time to enter any questions on reading early to
Ensure assignment is completed in Perusall Download comments entered in Perusall as part of contingency plan for
obtain any timely responses from other PMs or the
back up, then save to computer hardrive
Client.

Post Updated and Improved Project Plan to solicit peer Upload recent project plan to Canvas for peer review
feedback before the product is due. Post comments and provide feedback to other's Projects Plans to earn Had planned to complete early and submit for peer
credit. review.
Pre Peer Feedback on UPDATED Project Plans
29 22-Feb-21 21-Feb-21 22-Feb-21 N/A N/A 4 N/A N/A 0 -4
(Optional / Extra Credit) Elected not to take optional/extra credit submission due
to project being on track and work load for previous
week being greater than planned.
Module 5

1 - Conduct a Quality Control (QC) evaluation of the Initial Project Plan you
created using the rubric provided
Maintain entries as work is completed and allow for
2 - Update and improve the Project Plan based on your QC evaluation and
minimal impact to time spent and maximize efficiency in
based on your evaluation of the peer feedback it received
planning.
Update Project Plan & perform the following 5 steps to 3- Conduct a Quality Control (QC) evaluation of the Updated and
13-Feb-21 23-Feb-21 23-Feb-21 23-Feb-21 20 2-Feb-21 23-Feb-21 6.5 13.5
your project plan Improved Project Plan you created using the rubric provided
Update entries based on QC evaluation and update as
4 - Describe the Active Planning you have been doing for the last several
needed.
30 Updated and Improved Project Plan 23-Feb-21 weeks
5 - Then you will evaluate the Updated and Improved Project Plans
created and delivered by four of your colleagues using the same rubric you
used to evaluate your product.
Describe in three paragraphs the active planning you
have been doing Prepare in word format in a separate file. Complete action planning for remaining of project
Deliver by uploading both Updated and Improved Project Plan and Active timeline and utilize information to develop word 15-Feb-21 16-Feb-21 N/A N/A 2 23-Feb-21 23-Feb-21 2 0
Submit files to Canvas Planning document to Canvas. summary.

Evaluate other's projects plans against Rubric provided in Canvas


*Fully Proficient - *Attempt Made - *Missing
Review 4 colleagues' Project Plans
Provide comments on aspects of the Project Plan that are only addressed
by the rubric provided in Canvas
Review each submission, provide candid feedback to
0 - estimate based on
31 Peer Reviews of Colleagues' Updated Project Plans 25-Feb-21 support the other PMs to be successful for the updated 24-Feb-21 25-Feb-21 N/A N/A 4 24-Feb-21 25-Feb-21 4
adjustments
project plans and project completion.

Page 4 of 6
OGL320.Updated Project Plan.MFv1.1. 23FEB21

Delivery Planned Start Planned End Re-Planned Re-Planned Planned time Actual Start Actual time Planned vs. Actual
Product Tasks Subtasks PM Strengths to Complete Tasks and Subtasks Actual End Date
Due Date Date Date Start Date End Date to invest (hrs.) Date invested Time Invested

Log into Canvas to access modules and click the link to access Perusall
Complete reading on Why People Fail to Recognized
Read document, prioritize the client's comments and review each one.
Their Own Incompetence Provide detailed responses that relates to and support
Respond to, answer, and provide additional comments to other PMs input
other PM questions based on my experience that can
to the reading.
help support the other PMs questions and comments.
Submissions that demonstrate engagement with the concepts in Why Enter annotations before the deadline 0 - estimate based on
32 27-Feb-21 26-Feb-21 27-Feb-21 N/A N/A 3 25-Feb 27-Feb-21 3
People Fail to Recognize their own Incompetence Verify earned score is updated and reflected in Canvas adjustments
Schedule time to enter any questions on reading early to
Ensure assignment is completed in Perusall Download comments entered in Perusall as part of contingency plan for
obtain any timely responses from other PMs or the
back up, then save to computer hardrive
Client.

Watch assigned video on Concepts in Conversation with Begin video within the Canvas module, respond and answer quiz questions
a PM Part 2, and respond to quiz questions within the to complete
video
Module 6

Ensure assignment is complete and points are recorded Download question responses and answers and save to computer hardrive
in Canvas for back up
Submissions that demonstrate understanding of concepts in Answer questions with integrity and provide written 0 - estimate based on
33 27-Feb-21 25-Feb-21 27-Feb-21 N/A N/A 1 25-Feb-21 27-Feb-21 1
Conversation with a PM - Part 2 Video Quiz responses to support that supports the content. adjustments

Rewatch Baseline Assessment and review PM Principals documented on


Baseline Assessment.
Document in word document. Compare and contrast in essay form
Describe how I started planning the project
Capture all the relevant information through the course,
Describe how I feel about it at this time
Deliver a Detailed Personal Performance Review to the reviewing comments and submissions to provide best 0 - estimate based on
34 Culminating Project Management Performance Review 2-Mar-21 Which techniques did I use and not use and how do I draw on my unique 25-Feb-21 2-Mar-21 N/A N/A 4 26-Feb-21 27-Feb-21 4
client and accurate detail as possible back to the client on my adjustments
strengths as a PM.
performance as a PM for this project.
How did I interact with the client and your relationship?

Discuss in detail, expand on strengths and abilities learned on this project.

Page 5 of 6
OGL320.Updated Project Plan.MFv1.1. 23FEB216

OGL -320 PROJECT PLAN


Contingencies Planning Risk Planning
Computer Hardware Failure. Back up copies of all files on my laptop, Kid's School Work and Conflicts with Delivery of Products. I am
1 desktop, and USB drive 1 managing both closely to ensure work loads do not impact my ability to
deliver my products on time.
Personal Emergency. My wife has access to my project documents, Loss of Interest to Complete Work. Find ways to relate
2 clients contact information, and understands how to contact the client 2 information to work, life, home to connect interests.
incase of incident
Technology Disruption. Allocated second location to upload and Procrastination to Complete Work onTtime. Manage
3 submit products, incase of outage or disruption at home to support 3 work/life/school balance to make sure product delivery is of high
getting products delivered on time. priority since it is for a limited time.
Becoming Ill. Trying to go to sleep at a regular time and ensure rest to Loss of Internet Service. Internet bill was set to automatic
support not getting ill. As well, taking regular vitamin supplement to payments to ensure I do not forget to pay the bill (again:))
4 4
help with diet. Limiting any contact or exposure outside the house
that is not absolutely necessary.
Media Upload Failure. For any media submission, have written notes Work/School/Life not Balanced. Impacts of being furloughed and
or transcript saved as back up. Communciate with Client upon any looking for work, along with making sure bills can be paid. Trying
5 5
descreptancies. my best to balance all this and life is surprising very busy and
school can fall behind.
Called Back to Work. Sudden change in prioritizing to ensure project
products can still be delivered on time with quality. I will make all the
6 necessary notifications to the client to inform her of my recent 6
changes and abilities. We will discuss impacts and how to still deliver
the required products.
7 7
8 8
9 9
10 10

Page 6 of 6