KURNIA SEHATI MARINE LOGISTIC (M) SDN BHD
THE PROPOSAL FOR THE USED OF GEOTEXTILE AND GEOTUBES
IN THE ISTALLATION OF RIVER ENBANKMENT BUND
ALONG BURIGANGA RIVER IN BANGLADESH
THE
INSTALLATION
OF
(METHOD OF STATEMENT)
CONTENTS
1 Introduction ......................................................................... 3
3 Material ................................................................................10
5 Man Power.......................................................................... 10
This statement is to describe the activities and method which will be used to carry out the
installation of geotextile and geotubes for river embankment and to outline the resources
needed for these operations.
BREAKWATER/GEOTUBES
SAND FILLING/GEOTEXTILE
Preparation
Survey team will prepare and peg the alignment and location for the geofabric tube installation
prior to any geofabric tube installation work. The site area is to be leveled and cleared of
stones, wood, plant, vegetation or other sharp objects to prevent damage or rupture to the
geofabric tube. A layer of geotextile will be laid before the installation of the geofabric tube.
The Installation Procedure For Geotubes
The geofabric tube is tied to iron guide tubes used to guide and make sure the alignment for
the geofabric tube is correct. A flexible pipe is connected to the inlet port of the geofabric tube.
The pipes are connected to a sand pump. Sand slurry is then pumped into the geofabric tube
until the required height. The flexible pipes will be shifted to different part to ensure geofabric
tube is fully filled with in-filling of slurry, mud, sand and other small waste products.
Finishing
To prevent damage due to scour geofabric tube from waves from the sear or waves from the
river, punctured by sharp objects or act of vandalism, the surface of the geofabric tube can be
covered with a concrete matrass if needed.
Typical example of cross-section of works
An open area on land of approximately 500m length x 500m is leveled and prepared for
storage and deployment of the stitched non-woven geotextile. The area should be firm
and stable to accommodate excavators, cleared of large stones, exposed tree root stems
or other protrusions which can damage the non-woven geotextile and geotubes.
The alignment of the non-woven geotextile and geotube will be clearly identified and marked
using steel tubes at 25m interval. The steel tubes are planted into the seabed with sufficient
protrusion above water level.
Approximate
width of works
2.3 Deployment of non-woven geotextile (For Artificial Island and Beach Area works if applicable)
The stitched non-woven geotexile is unrolled and positioned flat on the ground with one end
close to the sea. This end is tie to a boat for towing out to the installation location. The non-
woven geotextile will float and maneuvered between the iron tubes.
Non-woven geotextile
Upon reaching the required location, the non-woven geotextile is tied at the 4 corners to
iron tubes and slowly weight down by sandbags or other suitable means.
2.4 Deployment of Geotube to form bottom tier ( applicable for breakwater, man made island
and beach area) – Note: For Man Made Island, No nonwoven Geotextile, Polyfelt TS009
is install under the Geotube but install over and in between the Geotube bund.
The geotubes are unwrapped and rolled flat on the ground with one end positioned close to
the sea to enable towing rope to be tied to a boat for deployment.
Upon reaching the location, the geotube is tied to the iron tubes.
Geotextile Polyfelt TS 009
under Geotube
Flexible pipes are inserted into the inlet port of the geotube. The pipes are connected to
pumping stations located on land or on float. Sand slurry is then pumped into the geotube
until the required height. The flexible pipes will be shifted to different port to ensure geotube
is fully filled with sand.
For Artificial Island these additional steps are required - The same process is
repeated for 2nd geotube to be placed beside first geotube to form the bottom tier of
perimeter bund.
Except that No Nonwoven Geotextile, Polyfelt TS009 was placed underneath the
geotube but to installed over and in between the Geotube bunds.
After completion of bottom tier geotube # 1 and geotube # 2, the geotube # 3 is deployed
into position beside geotube # 2 and filled.
After installing the 3 nos bottom tier geotubes over the geotube mattress, the deployment
and filling of top tier single geotube will be carried out in the same m a n n e r .
3.0 Material
• TenCate GT750M
• Non-Woven Geotextile Wolfelt TS009 or approved equivalent
The following labour resources shall be deployed to the site for the installation of geotubes
Will work closely with client to ensure safe working condition and environment to carry
out the works.
The following key areas of construction shall be adhered by all site personal working on site.
▪ House keeping
▪ Environment Issues
Temporary drains / sediment pond / silt fence will be constructed and maintained
throughout construction periods to ensure compliance to regulations.
In summation, in order to achieve safe, free risk and healthy working environment that
including loss prevention, every practicable step must be taken by each and every one
engaged in this project site.
-Polyfelt: TS 009
GeoTube
(Geotextile Tube)
Description:
GeoTubes are tubular containment systems made of specialized geosynthetics which prevent
soil and sand from being eroded by waves and currents.
It is a geotextile material filled with soil or sand and it is sewn so that it forms cushions which
are used to replace conventional rocks formation and beach protection.
It is more stable hydraulically and geotechnically because this bag is heavier and wider with
proportion high ratio. It performs well because it is built with integrated units.
Typically, GeoTube are hydraulically filled with a slurry of sand and water but the tubes can
also be filled by a combined mechanical or hydraulic method.
Strengths:
Please refer to the attached documents for more information, references and
applications.
“The information contained herein is to the best of our knowledge accuracy, but since the circumstances and conditions in which
it may be used are beyond our control, we do not accept any liability for any loss or damage, however arising, which results
directly or indirectly from use of such information, nor do we offer warranty or immunity against patent infringement.”
Prepared by : -
Mohamed Damanhure Bin Shamasudin
Group CEO
Mobile : +65-86718198
Bumi Marine Group
Kurnia Sehati Group
17th April 2022