SPECIFICATION C08
STEEL STRUCTURE AND CLADDING
GENERAL
MATERIALS
WORKMANSHIP
Cladding
Steel Frames
-C08/ -
Reinforcement of AlSharqia Transmission System
Volume 2 – SPECIFICATIONS (Book 8 of 8)
General Specifications - Civil
SPECIFICATION C08
STEEL STRUCTURE AND CLADDING
GENERAL
The pertinent DIN norms and the specifications given in the following section are
valid for all steel structures. The specifications take precedence over the DIN
norms.
The DB-contractor alone is responsible for seeing that the strength of the
materials used is within the allowable limits.
The origin of the individual materials is to be made known to the Engineer before
work commencement and in the event of any changes. The QA/QC plan shall
follow the requirements described in the relevant section of the Specifications
for General Requirements.
The DB-contractor is to make certificates available to the Engineer on the
results of material tests performed as per EN ..
The Engineer reserves the right to have the DB-contractor perform additional
material tests at his own expense at any time. The DB-contractor is to provide the
workers, machines, equipment and all other things necessary for testing as well as
the completed test pieces and is to afford the Engineer the opportunity to
participate in the testing.
The DB-contractor is to prepare all necessary workshop drawings, assembly
drawings, erection drawings etc. and all calculations for the works and is to
submit all documents to the Engineer for approval. This approval does not relieve
the DB-contractor of his responsibility for the construction works.
Before commencement of work, the DB-contractor is to submit a certified
documentation confirming that he is in possession of the "full welding certificate"
for steel structures.
The latest edition of the following standards is valid for the construction of steel
structures. The following list does not claim to be complete.
-C08/ -
Reinforcement of AlSharqia Transmission System
Volume 2 – SPECIFICATIONS (Book 8 of 8)
General Specifications - Civil
Contractor shall supply two sets of all standards and codes referred in this
specification and elsewhere in the project for the client and the consultant prior to the
commencement of the contract.
-C08/ -
Reinforcement of AlSharqia Transmission System
Volume 2 – SPECIFICATIONS (Book 8 of 8)
General Specifications - Civil
Definitions:
“Client” means Public Authority for Electricity and Water
“Engineer” means the engineering company entrusted with the project
management and construction supervision of the project.
“DB Contractor“ means the company or group of companies enthrusted by the
client with the Engineering, Procurement and Construction of
the project(s)
MATERIALS
The steel qualities for the individual construction elements are to be chosen in
accordance with UBC, chapter , structural steel. The steel quality is to be
verified by the manufacturer's certificate.
Other types of steel may only be used after thorough tests of the technological
properties and acceptance by the Engineer.
Cranes shall be designed according to the relevant chapters of UBC as well as
the AISC standards.
Insulated metal roof and wall panels and accessories: Products to be considered
equal to those specified below must be approved in writing by the Engineer.
Panels shall have a nominal width of m and a thickness of min. cm. The
panel length shall be the maximum possible. The panels shall present a fluted
surface externally and a flat surface internally.
Physical properties:
Steel skin: min. , mm of galvanized steel conforming to ASTM-A - ,
Grade A, structural quality with hot dipped commercial galvanized coating,
designation G- ( g/m ).
Insulation: expanded polyiscyanurate / polyurethane foam with a minimum of
% closed cell structure. The K value of the insulated panels shall be less than
W/m ,°C. As far as possible, heat bridges shall be avoi ded.
Density: min. 37 kg/m (ASTM D 1622-
-C08/ -
Reinforcement of AlSharqia Transmission System
Volume 2 – SPECIFICATIONS (Book 8 of 8)
General Specifications - Civil
Colour Coating: The exterior face of the panels and exterior flashings shall
Receive a factory applied paint finish having a colour to be
selected at the choice of the Client.
Metal Flashings and Trims: Shall be factory formed from the same material and
finish as the exterior skin of the panels.
Fire Performance: Panels shall be rated and carry the following listings:
-C08/ -
Reinforcement of AlSharqia Transmission System
Volume 2 – SPECIFICATIONS (Book 8 of 8)
General Specifications - Civil
Weather Tightness: Panels shall meet the Air Infiltration test when tested by the
recognized independent laboratories in accordance with ASTM
E- (Test of rate of air leakage), with a static pressure
difference of p.s.f. to p.s.f. Panels should also meet the
water penetration test as conducted in accordance with ASTM
E- “Test of Water Penetration” with a static pressure
difference of p.s.f. to p.s.f.
Color Coating Testing: Panel coating shall meet all performances as listed in the
appropriate specifications for the selected coating system.
All materials and components to be supplied by the DB-contractor and incorporated in
the structure shall be unused and new. The quality shall conform with the standard
regulations and be in accordance to the described requirements. Proof of the
quality is to be submitted to the Engineer by presentation of the certificates of quality.
The protective coating system of the external skin of the different roof and wall
constructions shall be a –
Multi-layered protected metal, comprising a galvanized steel
substrate, heavy epoxy barrier base coat and an exterior
weathering coat.
which must perform to the minimum test results described in the table below. The
coating for the roof and wall cladding shall be as follows:
-C08/ -
Reinforcement of AlSharqia Transmission System
Volume 2 – SPECIFICATIONS (Book 8 of 8)
General Specifications - Civil
Specification by Performance:
The selected coating system for the roof and wall cladding profiles must meet or
exceed the following performance criteria:
-C08/ -
Reinforcement of AlSharqia Transmission System
Volume 2 – SPECIFICATIONS (Book 8 of 8)
General Specifications - Civil
-C08/ -
Reinforcement of AlSharqia Transmission System
Volume 2 – SPECIFICATIONS (Book 8 of 8)
General Specifications - Civil
WORKMANSHIP
. Drawings
All necessary drawings for the manufacture and erection must be prepared in
accordance to the general time schedule and approved prior to commencement
of work.
The shop drawings shall clearly indicate all different items with respect to the
erection work.
A separate material recognition list shall be prepared for each building.
The item numbers in these lists must be identical to those shown in the shop
drawings.
The DB-contractor shall allow for deformation due to permanent loads and the
process and sequence of fabrication, erection and construction such that
steelwork is completed to be within the specified tolerances.
Braces (wind braces and gable walls) which resist live loads and assure stability
of the building are to be used for buildings.
Connection design shall provide adequate access for welding and inspection
(SPECIFICATION C08 – Steel Structure and Cladding)
-C08/ -
Reinforcement of AlSharqia Transmission System
Volume 2 – SPECIFICATIONS (Book 8 of 8)
General Specifications - Civil
during fabrication. The profile of the joint shall enable satisfactory non-destructive
testing to be carried out.
Special attention is drawn to the deflection limitations of the steel structure as well
as the crane way girders (please refer to the relevant standards).
The maximum deflection of trusses, floor beams and girders may not exceed
1/300 of the span. For trusses the deflection due to dead load may be
compensated by superelevation. The maximum deflection of rafters and spars
must be less than 1/400 of the span. The limit of deflection for crane beams in
both horizontal and vertical direction is 1/1000 of the span. The allowable
horizontal deflection of the columns under horizontal wheel pressure shall not
exceed 1/300 of the height of the crane beam bracing or 2.5 cm.
The design loads for buildings are to be taken from SBC and AISC standards. A
velocity of 45 m/sec is to be assumed for calculation of wind loads.
Additional to wind loads a vertical live load for roofs is to be calculated with 1
kN/m2. Live loads for flat roofs have to be chosen according to the purpose of
use.
. Erection Programme
Before starting the execution of the works, the DB-contractor shall furnish a
detailed programme according to the general time schedule. Each month the
DB-contractor shall provide a progress report in duplicate to the Engineer,
indicating the progress of work.
The DB-contractor shall be solely responsible for the accuracy of all relevant
dimensions of the structure.
. Manufacturer’s Instruction
All work at site, i.e. handling, storage and erection shall be carried out strictly in
accordance with the manufacturer’s instructions and recommendations.
Cladding
. Drawings
All necessary drawings for the manufacture and erection must be prepared in
accordance to the general time schedule and approved prior to commencement
of work.
The shop drawings shall clearly indicate all different items with respect to the
erection work.
A separate material recognition list shall be prepared for each building.
The item numbers in these lists must be identical to those shown in the shop
drawings.
-C08/ -
Reinforcement of AlSharqia Transmission System
Volume 2 – SPECIFICATIONS (Book 8 of 8)
General Specifications - Civil
. Erection Programme
Before starting the execution of the works, the DB-contractor shall furnish a
detailed programme according to the general time schedule. Each month the
DB-contractor shall provide a progress report in duplicate to the Engineer,
indicating the progress of work.
. Manufacturer’s Instructions
All work at site, i.e. handling, storage and erection shall be carried out strictly in
accordance with the manufacturer’s instructions and recommendations.
. Auxiliary Works
. Ancilliary Provisions
Ancilliary provisions include but not be limited to the following:
After completion of the erection work the following must be undertaken before
handover:
. Ancilliary Products
END LAPS : External weathering sheet:
Where the angles of the roofs are ° or below, the end laps
shall be a minimum of 0mm. On roof slopes in excess of °,
the end laps shall be a minimum of mm.
On vertical areas the end laps shall be a minimum of mm
Internal Liner Sheets:
End laps shall be 5mm on trapezoidal internal liner sheets
SEALANTS: Where required and to suit the cladding supplier’s
recommendations the cladding shall be sealed with a non-
(SPECIFICATION C08 – Steel Structure and Cladding)
-C08/ -
Reinforcement of AlSharqia Transmission System
Volume 2 – SPECIFICATIONS (Book 8 of 8)
General Specifications - Civil
Steel Frames
All frames – for edgeless or rebated door leaves – shall be offered with sealing
groove and sealing, prepared for two strong cylindrical hinges per door leaf, for
single-wing doors in a left-right type. Before production or delivery of the frames,
the contractor has to find out about the definitive number, size and type (edgeless
and rebated door leaves) and to search approval from the Employer. The same
applies for door leaves and their opening direction. In case of double-wing doors,
attention has to be paid to ensuring that the position of the upper covering of the
bolt opening corresponds to the actual width of the dead wing. The contractor
who installs and adjusts the door leaves is responsible for drilling the bolt
opening.
Surface galvanized, colour of coating to be chosen.
The sealing profiles must all be of elastomer materials (e.g. APTK) or equal
materials.
The calculation and execution of steel radio antenna towers shall be performed in
(SPECIFICATION C08 – Steel Structure and Cladding)
-C08/ -
Reinforcement of AlSharqia Transmission System
Volume 2 – SPECIFICATIONS (Book 8 of 8)
General Specifications - Civil
-C08/ -