Firefighting Pump Installation Method Statement
SEARCH
Follow the manufacturer’s instructions while installing the pump. Pump shall be stored on a flat
surface in well-ventilated storage area. Inlet and outlet flange blanks shall not be removed until
ready for connection to pipe work. Manufacturer’s instructions shall be strictly followed as
Subscribe for New applicable.
Methodstatements Preparation Works
Enter your email address to subscribe and
receive notifications when new documents are The foundations designed to meet the vibration and
released. sound control requirements shall be provided by Main
contractor. Check and ensure that the shop drawings
Email Address used are latest and approved for
construction. Concrete, (reinforced as necessary or
required) is most widely used for the foundation of fire
SUBSCRIBE pumps. In sufficient mass, it provides rigid support,
which minimizes deflection and vibration. It may be
Join 4,219 other subscribers
located on soil, structural steel or building floors,
provided the combined weight of the pumping unit.
Like & Follow on Facebook MEP contractor will co-ordinate the location of
foundation as per approved shop drawings. The foundation surface shall be flat and level and
smoothly finished top surface.
Check the piping support locations and cable tray routing locations in co-ordination with pump and
piping layout and ensure these are not obstructing the space around pump. Ensure easy access and
sufficient clearance for servicing and maintenance i.e. for replacement of pump, motor.
Select a location for the pumping unit (pump, base plate, coupling and driver) that will be clean,
well ventilated, properly drained and provide accessibility for inspection and maintenance (see
outline drawing for dimension) Outdoor installations may require protection from the elements
particularly freezing.
Browse By Topics The suction supply system must provide the pump i.e. the suction tank location with its base or
Aluminium & Glass Work Methods (10) above the same elevation of the pump.
HVAC Method Statements (100) Remove the end caps fixed on the inlet flange.
Method Statement for Civil Works (118)
Install the electrical control panel and power connections as per approved drawings. Incoming and
p p p pp g g
Method Statements (373) outgoing cables to be insulation resistance/continuity tested. Provide earth wiring as per approved
Occupational Health and Safety (42) drawings/manufacturers instruction.
Piping Method Statements (28)
After completion and pump installation and piping connections, the same shall be checked and
Piping Works (31)
certified by the pump supplier. Request for Inspection’ shall be raised for Consultants inspection
Plumbing Downloads (26) and approval.
Plumbing Method Statements (61)
Firefighting Pumps and drivers mounted on a common base plate are accurately aligned before
Pedestrian Glazed Repair of
Walkway Partitioning Painting shipment. Realignment is necessary after the complete unit has been leveled on the foundation
Concreting Method Works on and again after the grout has set and foundation bolts have been tightened. The alignment must
– Broom Statement Beam, be checked after the unit is piped and rechecked periodically. To facilitate accurate field
Finish for Glass Column, alignment, do not dowel the pumps or drivers on the base plates before shipment.
Concrete Office Slabs, and
Partitions Wall
Firefighting Pump Alignment
Reliable, trouble‐free, and efficient operation of a pumping unit requires correct alignment of
pump and driver shafts. Misalignment may be the cause of:
Make such changes only after it is certain alignment cannot be obtained by shifting of the wedges.
If wedges are shifted or shims changed a substantial amount to obtain proper alignment, recheck
the piping alignment and level of the shafts.
The suction and discharge piping should be arranged for the simplest, most direct layout, to be of
sufficient size and be internally free of foreign material. The piping must never be pulled into
position by the flange bolts. It must be independently fixed and arranged. The suction piping, if not
installed properly, is a potential source of faulty operation. To achieve best performance:
the suction lines ,when operation must be kept absolutely free from air leaks.
A strainer should be installed in suction line . The screen must be checked and cleaned
periodically. The opening in the screen must smaller than the sphere size allotted fro the impeller.
Piping should be cleaned mechanically and chemically , and flushed prior to installing the pump.
A large number of pump packing , mechanical seal and seizure troubles are due to improperly
cleaned systems.
c ea ed syste s.
The Pump should also be inspected internally for foreign matter that may have entered the pump.
Meta The suction pipe shall be sized such that pump capacity and minimum distance to be maintained
from suction pump flange.
Log in
Entries feed
Comments feed Waukesha Parts Supplier
WordPress.org View Our Parts Catalog Online
New Genuine, OEM, Replacement, and Remanufactured Waukesha Parts. Contact Us!
mcgillindustries.com OPEN
Share this:
Twitter Facebook
Related
Method Statement for Installation of Testing & Commissioning Of Fire Chilled Water Pump Installation
Sump Pump Pumps Alignment and Balancing Method
September 1, 2018 November 4, 2013 Statement
In "Method Statements" In "Method Statements" April 28, 2013
In "Construction Method Statements"
Previous Next
All Right Reserved. MethodstatementHQ Serving the Construction Industry Since 11 Years.