You are on page 1of 69

2ND CONSTRUCTABILITY WORKSHOP - U&O

CRITICAL AREAS

102.380

99.750
97.903

Interconnecting Piperack CWA 128293


Bottom of foundations: 99.750m
2ND CONSTRUCTABILITY WORKSHOP - U&O
CRITICAL AREAS

102.300

97.400 97.966
96.400

Interconnecting Piperack CWA


128295
Bottom of foundations: 96.4m
2ND CONSTRUCTABILITY WORKSHOP - U&O
CRITICAL AREAS

102.300

99.718

97.400 97.966
96.400

Interconnecting Piperack CWA


128295 & 128297
Bottom of foundations: 96.4m
2ND CONSTRUCTABILITY WORKSHOP - U&O
CRITICAL AREAS

102.500

99.400

97.400 97.966
96.400

Interconnecting Piperack CWA


128295
Bottom of foundations: 96.4m
2ND CONSTRUCTABILITY WORKSHOP - U&O
HDPE INSTALLATION METHOD
The installation sequences intended to be adopted for the cooling water and
sea water HDPE UG lines networks are based on the following concepts:

1. Supply of HDPE bars in length of 24 meters.


2. Assembly and welding outside the trench of spools up to 96 meters (4 x
24) when possible.
3. Backfilling of the lines simultaneously along its installation except for the

4. Simultaneous work fronts from both sides.


5. Cleanliness installation approach. Specific procedure/ITP and dedicated
supervision to ensure Cleanliness and its inspection records.
6. Hydrotest philosophy in harmony with commissioning and startup.

RESULTING NETWORK BREAKDOWN


1. General layout divided in 13 groups.
2. 32 lines.
3. 24 test packages/circuits.
2ND CONSTRUCTABILITY WORKSHOP - U&O
HDPE INSTALLATION METHOD 1
Assembly and welding outside the trench of spools up to 96 meters (4 x 24) when possible

HDPE pipe installation requires a certain sequence of installation due to the welding methodology.
As a main approach, pipe lengths will be assembled in a working station (cutting, joining and
welding) creating pipe strings up to 96 m length.
Assembly working stations will be located outside trench as much as possible, especially where
line are single or double in order to keep the trench width as narrow as possible.
2ND CONSTRUCTABILITY WORKSHOP - U&O
HDPE INSTALLATION METHOD 1 - sequences

Once ready, the strings will be positioned inside the trenches by means of multiple cranes.
Use of spreader bar might be required according (to be checked)
2ND CONSTRUCTABILITY WORKSHOP - U&O
HDPE INSTALLATION METHOD 1- sequences
Once the string is positioned inside the trench, backfill will be performed in order to maintain the
line fixed, to protect the line from UV ray and to reduce the dewatering wherever foreseen.
2ND CONSTRUCTABILITY WORKSHOP - U&O
HDPE INSTALLATION METHOD 1- sequences
Then strings will be joined inside the trench up to the required length.
Whenever the trenches are too narrow to access for perform the welding between strings, an
enlarged portion shall be foreseen inside the trench.
2ND CONSTRUCTABILITY WORKSHOP - U&O
HDPE INSTALLATION METHOD 1 - Backfilling
2ND CONSTRUCTABILITY WORKSHOP - U&O
HDPE INSTALLATION METHOD 1 (Summary) - Sequences
2ND CONSTRUCTABILITY WORKSHOP - U&O
HDPE INSTALLATION METHOD 2 - Sequences
2ND CONSTRUCTABILITY WORKSHOP - U&O
HDPE INSTALLATION METHOD 3 - Sequences
2ND CONSTRUCTABILITY WORKSHOP - U&O
HDPE INSTALLATION METHOD 4 - Sequences

Fixed Welding
Station

Piping pulling

Piping enter
welding station
2ND CONSTRUCTABILITY WORKSHOP - U&O
INSTALLATION METHOD
Simultaneous work fronts from both sides
Different work fronts can be considered on the same line where there is a change in direction.
This is feasible without inserting any joint in between.
These points will be called SPLIT POINTS

WORK FRONT SPLIT POINT


2ND CONSTRUCTABILITY WORKSHOP - U&O
INSTALLATION METHOD
Simultaneous work fronts from both sides

SPLIT
POINT

Line backfill
Backfill can be completely done
except for the portion near by
the split joint in order to
position and operate the
welding machines.
Line will be fixed during the
entire welding operation

Line backfill
Backfill can be completely
done except the last portion
of approx. 20 m to allow the
line movement while welding
machines is working.
Line movement will be
supported by means of sliding
points/cranes.
2ND CONSTRUCTABILITY WORKSHOP - U&O
INSTALLATION METHOD
Clean installation approach
A Clean installation method shall be adopted during the HDPE line erection in
order to avoid any dirt or foreign objects inside the line.
Every single pipe length or component will be inspected by all parties prior the
installation and signed records will be implemented during all phases of
installation.
Clean installation method will
foresee:
Dedicated procedure to be approved by
company and endorsed by HDPE subcontractor
Training to subcontractor personnel
Dedicated hold point on the ITP which will
involve subcontractor, Tecnimont and
Company
Blinding device to ensure that no dirt can get
inside while the lines are not attended
Full time contractor inspector to ensure Clean
methodology is applied and maintained
2ND CONSTRUCTABILITY WORKSHOP - U&O
INSTALLATION METHOD
Hydrotest philosophy
Line hydrotest will be mainly performed once the line is totally completed end to end
point. At that moment, the line will be entirely backfilled to guarantee also stability
while filling and pressurizing.
Test will be performed essentially in 4 steps:

- Step 1 Filling and venting


- Step 2 Pressurization up to operational pressure
- Step 3 Pressurization up to test pressure
- Step 4 De-pressurization up to operational pressure (test result evidence)
X

1.3
2ND CONSTRUCTABILITY WORKSHOP - U&O
INSTALLATION METHOD
Hydrotest philosophy

Wherever possible (line conformation), water can be maintained inside the


line after hydrotest, ready for the following flushing activities.
This approach will increase benefit for precommissiong during the flushing
activities reducing time and having also positive ecological impact avoiding
disposal of thousands of water cubic meters
2ND CONSTRUCTABILITY WORKSHOP - U&O
INSTALLATION METHOD
Use of couplings

The concept of the analysis focuses on ZERO breaking points.


Nevertheless, couplings or flanges might be considered the volume of water is
too important for performing the hydrotest.

Coupling or flanges will allow testing of already installed line up to the


selected break up point.

Anyhow, we identified that possible coupling might be used only for lines lower
than Ø1200mm.

Coupling or flanges might be direct buried after installation provided that


service test is completed to ensure no leakages are present
From Sea Water
2ND CONSTRUCTABILITY WORKSHOP - U&O Intake
CWA 600181
UG LINES GROUPING
From
SWI
CWA
600081
From Sea Water
2ND CONSTRUCTABILITY WORKSHOP - U&O Intake
CWA 600181
UG LINES GROUPING
Sea Water Intake
CWA 600081

To cooling towers
CWA 610280-610281-
610282
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT DEFINITION

discharge
CIRCUIT LINES total length total volume water Proposed test media
required
1 Line 1 group 3 791 621 No Potable water
2 Line 2 group 3 663 341 Yes Potable water
3 Line 1 group 7 855 905 Yes Potable water
4 Line 1 group 8 (portion) 35 89 Yes Potable water
5 Line 1 group 8 155 394 Yes Potable water
6 Line 1 group 2A 574 1305 Yes Potable water
7 Line 2 group 8 166 422 Yes Potable water
8 Line 2 group 2A 572 1455 Yes Potable water
9 Line 3 group 8 166 334 Yes Potable water
10 Line 1 group 2B 731 1126 Yes Potable water
11 Line 4 group 8 211 424 Yes Potable water
12 Line 2 group 2B 720 1114 Yes Potable water
13 Line 1 group 1B 490 985 Yes Potable water
14 Line 2 group 1B 490 985 Yes Potable water
15 Line 3 group 1B 490 985 Yes Potable water
16 Line 1 group 1C 332 668 Yes Potable water
17 Line 2 group 1C 332 668 Yes Potable water
18 Line 3 group 1C 332 668 Yes Potable water
19 Line 2 group 1A +Line 2 Group 4 1099 1015 Yes sea water
20 Line 2 group 5A+ Line 2 group 5B 2222 1745 Yes sea water
21 Line 2 group 6A+ Line 2 group 6B 2860 2246 Yes sea water
Line 1 group 1A + Line1 group 4 + Line 1
22 3983 4467 Yes sea water
group 6A + Line 1 group 6B
Line 3 group 1A + Line 3 group 4 + Line 3
23 3311 3723 Yes sea water
group 5A+ Line 3 group 5B
24 Line 4 group 4 58 37 Yes Potable water
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT DEFINITION
2ND CONSTRUCTABILITY WORKSHOP - U&O Flanged Ends

CIRCUIT 1
Line 1 Group 3

Flanged End Split point


Split point
Line 2 group 1A

WF Work front available

Assembled string limits

Consideration for HYT:


1000 mm Main line diameter Line tested alone, flanges are present in both side.
Not require drainage after test.
791 m Line length Line ready for flushing.

621 m³ Water volume for HYT


2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 2
Line 2 Group 3

Flanged End

Split point Split point


Line 1 group 1A
Flanged End
Line 1 group 1A

Flanged
End
WF Work front available Flanged
End
Assembled string limits

710 mm Main line diameter

Consideration for HYT:


663m Line length - Line tested alone: whole line is flanged, north part
required valves, therefore line shall be discharged.
341m³ Water volume for HYT
2ND CONSTRUCTABILITY WORKSHOP - U&O
No flange
CIRCUIT 3
Line 1 Group 7
Split point
Flanged End Flanged End

Split
point

WF Work front available

Assembled string limits

Consideration for HYT:


1200 mm Main line diameter Line tested alone, flanges are present in one side
only.
855 m Line length Line end point in basin has no flanges. Temporary cap
shall be foreseen.
After test line shall be discharged.
905 m³ Water volume for HYT
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 4 & 5 Flanged End Consideration for HYT (top):
Line tested alone: line is flanged in
Line 1 Group 8 both side. Line shall be discharged
after test

Line 1 group 2A

Flanged End

WF Work front available

Assembled string limits


Flanged End
1800 mm Main line diameter
Consideration for HYT (bottom):
190 m Line length - Both sides are flanged.
Line tested alone: both side flanged. Line
shall be discharged after test
483 m³ Water volume for HYT
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 6
Line 1 Group 2A

Split point

Flanged End

Flanged
End

WF Work front available

Assembled string limits


Line 1 group 8 Consideration for HYT (top):
1800 mm Main line diameter - Line tested alone: line is flanged in
both side and all branches.
574 m Line length Line shall be discharged after test

1305 m³ Water volume for HYT


2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 7 Flanged End
Line 2 Group 8

Line 2 group 2A

WF Work front available


Split
Assembled string limits
point
1800 mm Main line diameter
Flanged End
166 m Line length Consideration for HYT
Line tested alone: line is flanged in both
side. Line shall be discharged after test
422 m³ Water volume for HYT
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 8
Line 2 Group 2A

Split point
Flanged
End

Flanged
End

WF Work front available

Assembled string limits

Line 2 group
1800 mm Main line diameter Consideration for HYT (top):
8
- Line tested alone: line is flanged in
571.6 m Line length both side and all branches.
Line shall be discharged after test

1454 m³ Water volume for HYT


2ND CONSTRUCTABILITY WORKSHOP - U&O
Flanged End
CIRCUIT 9
Line 3 Group 8

Line 1 group 2B

WF Work front available


Split point
Assembled string limits

1600 mm Main line diameter


Flanged End
Consideration for HYT
166 m Line length - Line tested alone: line is flanged in both
side.
Line shall be discharged after test
334 m³ Water volume for HYT
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 10
Line 1 Group 2B

Split
Flanged point
End

Flanged
End

WF Work front available

Assembled string limits

1600 mm Main line diameter


Flanged End Consideration for HYT (top):
731 m Line length - Line tested alone: line is flanged in
both side and all branches.
Line 3 group 8 Line shall be discharged after test
1126 m³ Water volume for HYT
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 11
Line 4 Group 8 Flanged End

Line 2 group
2B

WF Work front available


Split
Assembled string limits
point
1600 mm Main line diameter
Flanged End
211 m Line length
Consideration for HYT
- Line tested alone: line is flanged in both
424 m³ Water volume for HYT side.
Line shall be discharged after test
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 12
Line 2 Group 2B
Split
point
Flanged End

Flanged End

WF Work front available

Assembled string limits

1600 mm Main line diameter


Flanged End Consideration for HYT (top):
720.4 m Line length - Line tested alone: line is flanged in
both side and all branches.
Line 4 group 8 Line shall be discharged after test
1114 m³ Water volume for HYT
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 13
Line 1 Group 1B Split
point
Flanged
End

Split
point

WF Work front available


Flanged
Assembled string limits End

1600 mm Main line diameter

490 m Line length Consideration for HYT:


Line tested alone: line is flanged in both side and
985 m³ Water volume for HYT all branches.
Line shall be discharged after test
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 14
Line 2 Group 1B Flanged Split point
End

Split point

WF Work front available

Assembled string limits Flanged


End
1600 mm Main line diameter

490 m Line length Consideration for HYT:


Line tested alone: line is flanged in both side and
985 m³ Water volume for HYT all branches.
Line shall be discharged after test
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 15
Line 3 Group 1B
Flanged Split point
End

Split point

Flanged
WF Work front available
End
Assembled string limits

1600 mm Main line diameter

490 m Line length Consideration for HYT:


Line tested alone: line is flanged in both side and
985 m³ Water volume for HYT all branches.
Line shall be discharged after test
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 16
Line 1 Group 1C
Flanged
End Split
Split point
point

Flanged
WF Work front available
End
Assembled string limits

1600 mm Main line diameter

332 m Line length Consideration for HYT:


Line tested alone: line is flanged in both side and
668 m³ Water volume for HYT all branches.
Line shall be discharged after test
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 17
Line 2 Group 1C
Flanged
End
Split point
Split point

Flanged
WF Work front available
End
Assembled string limits

1600 mm Main line diameter

332 m Line length Consideration for HYT:


Line tested alone: line is flanged in both side and
668 m³ Water volume for HYT all branches.
Line shall be discharged after test
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 18
Line 3 Group 1C
Flanged
End Split
point

Split
point

WF Work front available Flanged


End
Assembled string limits

1600 mm Main line diameter

332 m Line length Consideration for HYT:


Line tested alone: line is flanged in both side and
668 m³ Water volume for HYT all branches.
Line shall be discharged after test
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 19 Split
Line 2 Group 1A point

Line 2 group 4
No flange

Split point

Flanged
End
WF Work front available

Assembled string limits

Line 1 group 3
1200 mm Main line diameter
Consideration for HYT:
439 m Line length Since line has one flanged connection south and no
flanged connection north part it has to be tested with
the next part of the pipe until next flanged end
496 m³ Water volume for HYT available. Therefore test shall consider line 2 group 4
+ Line 2 Group 1A.
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 19 Line 2 group 5A
Line 2 Group 4
Line 2 group 6A

Flanged
Ends

WF Work front available


Consideration for HYT:
Assembled string limits Since line has two flanged connection on
the north and no flanged connection
Line 2 group
south it has to be tested with the next
1200 mm Main line diameter 1A
part of the pipe until next flanged end
available. Therefore test shall consider
676 m Line length No flange line 2 group 4 + Line 2 Group 1A.

743 m³ Water volume for HYT


2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 20
Line 2 Group 5A
Line 2 group 5B

No flange

Flanged
Split End
point

Line 2 group 4

WF Work front available

Assembled string limits Consideration for HYT:


Since line has one flanged connection south
and no flanged connection north part it has
1000 mm Main line diameter to be tested with the next part of the pipe
until next flanged end available. Therefore
1097 m* test shall consider Line 2 group 5A + Line 2
Line length
group 5B.

862 m³* Water volume for HYT


*For overall circuit length and water volume for
HYT refer to circuit definition table
2ND CONSTRUCTABILITY WORKSHOP - U&O
Flanged End
CIRCUIT 20
Line 2 Group 5B
Split point Consideration for HYT (top):
- Both sides are flanged.
Flanged Line tested alone. Line shall be
discharged after test
Ends

Split point

WF Work front available


Split point
Assembled string limits
Consideration for HYT (bottom):
1000 mm Main line diameter Line 2 group 5A Since line has one flanged connection
north and no flanged connection south, it
has to be tested with the next part of the
1125 m * Line length pipe until next flanged end available.
No flange Therefore test shall consider Line 2 group
5A + Line 2 group 5B.
883 m³ * Water volume for HYT
*For overall circuit length and water volume for
HYT refer to circuit definition table
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 21
Line 2 Group 6A
Line 2 group 6B No flange
Split point

Flanged End

Line 2 group 4
WF Work front available

Assembled string limits


Consideration for HYT:
1000 mm Main line diameter Since line has one flanged connection
south and no flanged connection north it
has to be tested with the next part of the
937 m * Line length pipe until next flanged end available.
Therefore test shall consider Line 2 group
736 m³ * Water volume for HYT 6A + Line 2 group 6B.

*For overall circuit length and water volume for


HYT refer to circuit definition table
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 21
Line 2 Group 6B

Split point
No flange
Flanged End

Line 2 group
6A

WF Work front available

Assembled string limits

1000 mm Main line diameter Consideration for HYT (bottom):


Since line has one flanged connection
north and no flanged connection south it
1923 m * Line length has to be tested with the next part of the
pipe until next flanged end available.
1510 m³ * Water volume for HYT Therefore test shall consider Line 2 group
6A + Line 2 group 6B.
*For overall circuit length and water volume for
HYT refer to circuit definition table
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 22
Line 1 Group 1A Split point
Line 1 group 4

Split No flange
point

Flanged
End
WF Work front available

Assembled string limits

1200 mm Main line diameter Line 2 group 3

413 m * Line length Consideration for HYT:


Since line has one flanged connection south and no flanged connection north
467 m³ * Water volume for HYT it has to be tested with the next part of the pipe until next flanged end
available. Therefore test shall consider Line 1 group 1A + Line1 group 4 +
*For overall circuit length and water volume for Line 1 group 6A + Line 1 group 6B
HYT refer to circuit definition table
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 22 Line 1 group 6A
Line 1 Group 4
Split point

No flange

Split point

Consideration for HYT:


WF Work front available Since line has no flanged connection has
to be tested with the next part of the
pipe until next flanged end available.
Assembled string limits
Therefore, test shall consider Line 1
group 1A + Line1 group 4 + Line 1 group
1200 mm Main line diameter Line 1 group 1A 6A + Line 1 group 6B

710 m * Line length


No flange
Split
765 m³ * Water volume for HYT
point
*For overall circuit length and water volume for
HYT refer to circuit definition table
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 22 No flange
Line 1 Group 6A Line 1 group 6B

Split point

No
flange

Line 1 group 4
WF Work front available

Assembled string limits Consideration for HYT:


Since line has no flanged connection has
to be tested with the next part of the
1200 mm Main line diameter
pipe until next flanged end available.
Therefore, test shall consider Line 1
937 m * Line length group 1A + Line1 group 4 + Line 1 group
6A + Line 1 group 6B
1060 m³ * Water volume for HYT
*For overall circuit length and water volume for
HYT refer to circuit definition table
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 22
Line 1 Group 6B

Split point
No flange
Flanged End

Line 1 group 6A

WF Work front available

Assembled string limits


Consideration for HYT:
Since line has a flanged end on the
1200 mm Main line diameter north part, has to be tested with the
next part of the pipe until next
1923 m Line length flanged end available. Therefore test
shall consider Line 1 group 1A + Line1
group 4 + Line 1 group 6A + Line 1
2175 m³ Water volume for HYT group 6B
*For overall circuit length and water volume for
HYT refer to circuit definition table
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 23
Line 3 Group 1A
Split point
Line 3 group 4

No flange
Split point

WF Work front available


Flanged
Assembled string limits End + valve
Line 2 group
1200 mm Main line diameter 3

413 m Line length Consideration for HYT:


Since line has a flanged connection on the south part, has to be tested with
467 m³ the next part of the pipe until next flanged end available. Therefore test
Water volume for HYT
shall consider Line 3 group 1A + Line 3 group 4 + line 3 group 5A + Line 3
*For overall circuit length and water volume for group 5B
HYT refer to circuit definition table
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 23 Split
Line 3 Group 4 point
Line 3 group
6A

Split
point

No flange

Consideration for HYT:


Since line has no flanged connection, it
WF Work front available has to be tested with the next part of the
pipe until next flanged end available.
Assembled string limits Therefore test shall consider Line 3 group
1A + Line 3 group 4 + line 3 group 5A +
Line 3 group 5B
1200 mm Main line diameter Line 3 group
1A
676 m Line length
Split
743 m³ Water volume for HYT
point
*For overall circuit length and water volume for
HYT refer to circuit definition table
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 23
Line 3 Group 5A
Line 3 group 5B

Split point

No flange
No flange

Split point

Line 3 group 4

WF Work front available

Assembled string limits


Consideration for HYT:
Since line has no flanged connection, it
1200 mm Main line diameter has to be tested with the next part of the
pipe until next flanged end available.
1067 m * Line length Therefore test shall consider Line 3 group
1A + Line 3 group 4 + line 3 group 5A +
Line 3 group 5B
1241 m³ * Water volume for HYT
*For overall circuit length and water volume for
HYT refer to circuit definition table
2ND CONSTRUCTABILITY WORKSHOP - U&O
Flanged End
CIRCUIT 23
Line 3 Group 5B
Split
point Consideration for HYT (top):
Flanged - Both sides are flanged.
Line tested alone
Ends

Split
point

WF Work front available Split


point
Assembled string limits
Consideration for HYT:
Since line has a flanged connection
1200 mm Main line diameter on the north part, it has to be
Line 3 group tested with the next part of the
5A pipe until next flanged end
1125 m * Line length
available. Therefore test shall
consider Line 3 group 1A + Line 3
1272 m³ * Water volume for HYT group 4 + line 3 group 5A + Line 3
group 5B
*For overall circuit length and water volume for
HYT refer to circuit definition table
2ND CONSTRUCTABILITY WORKSHOP - U&O
CIRCUIT 24
Line 4 Group 4

Flanged End Flanged


Ends

Line 3 group 4

Line 1 group 4

WF Work front available

Assembled string limits

900 mm Main line diameter Consideration for HYT:


Line tested alone, flanges are present in both sides.
Required drainage after test.
58 m Line length Line tested together with line 1 group 4 and line 3 group
4
37 m³ Water volume for HYT Required drainage after test.
2ND CONSTRUCTABILITY WORKSHOP - U&O
HDPE LINES ERECTION IMPROVEMENT
U&O plant is set on different elevation (+105.000 / +102.000)
HDPE lines across this elevation change in several points (13 lines)
2ND CONSTRUCTABILITY WORKSHOP - U&O
Cooling Water + HDPE:
FOCUS ON HDPE ERECTION EXECUTION STRATEGY

2
3
2 3
43

7
5
6 6 6
KEYPLAN
2ND CONSTRUCTABILITY WORKSHOP - U&O
11) CRITICAL POINT SEA WATER BASIN B2 (CWA 600081)

A) SEA WATER MAKEUP B) NEW PIT


A
PUMPS 60-PC-2842
A/B/C

C) EXISTING SEA WATER BASIN D) 600081-RP003A


PIT FOR DEWATERING AND
B PIPING SUPORTS

D
KEYPLAN
2ND CONSTRUCTABILITY WORKSHOP - U&O
11) CRITICAL POINT SEA WATER BASIN B2 (CWA 600081)
D) 600081-RP003A
Depth: 5.00m
PIT FOR DEWATERING AND
PIPING SUPPORTS
KEYPLAN
2ND CONSTRUCTABILITY WORKSHOP - U&O
22) CRITICAL POINT HDPE LINE ROAD CROSSING

Installation of pipe sleeve (by Pipe Jacking)


The crane will lower the welding machine into the trench and position
Generator will place nearer to the location
Load the pipe unto both side of welding machine with the end of the
pipe will be in the clamps of welding machine.
Attach the clamps & tight on the pipeline. Load pipe into the welding
machine in the trench and weld. After the required length for NDRC
achieved, remove the welding machine and generator and shift to
another place.
After welding completed, the welded pipeline will be tow by excavator
until nearest to the NDRC.
KEYPLAN
2ND CONSTRUCTABILITY WORKSHOP - U&O
22) CRITICAL POINT HDPE LINE ROAD CROSSING

Place the wire rope that coming from other side of NDRC. And start pulling and full length of pipeline
will be inside the sleeve. The pipeline can be push also by excavator depends on requirement.
Pulling or pushing the pipeline can be execute by excavator assisted by crane.
Hydro testing will be done before the pipeline will pull or push into NDRC [pipe sleeve]
And continue the welding on either both sides until weld reach on elbow or change direction of pipeline.
After completed the welding on the whole straight pipeline, shift the equipment on the other side.
KEYPLAN
2ND CONSTRUCTABILITY WORKSHOP - U&O
32) CRITICAL POINT HDPE LINE UNDER PIPELINE

PLACING SLEEVE PIPE BELOW EXISTING PIPELINE (BY PIPING JACK)

A stablished thrust wall (concrete)


for jacking equipment will lean.
Steel rail will also place for guide of
pipe steel.

The hydraulic jack and the steel


pipe will be placed as sleeve,
jacking until the steel pipe
penetrates completely the soil.
KEYPLAN
2ND CONSTRUCTABILITY WORKSHOP - U&O
32) CRITICAL POINT HDPE LINE UNDER PIPELINE

PIPE TO PIPE WELDING FOR NDRC [PIPE SLEEVE]

Procedure for HDPE line before and


after pipeline cross:
The crane lowers the welding
machine and the pipe into the
trench. The pipe will be in the
clamps into welding machine.
The clamps will be attached and
tighten on the pipeline. The pipe
will be loaded into the welding
machine in the trench and weld.
After the required length for
NDRC (sleeve) achieved, the
welding machine will be
removed.
After welding completed, the
welded pipeline will be tow or
push by excavator until will be
fully inserted into NDRC. If the
pipe will be pull, the wire rope
will be placed passing into NDRC
until it will be inside the sleeve.
KEYPLAN
2ND CONSTRUCTABILITY WORKSHOP - U&O
CRITICAL AREAS: Microtunneling Jacking for HDD
KEYPLAN
2ND CONSTRUCTABILITY WORKSHOP - U&O
4 FOCUS ON HDPE ERECTION EXECUTION STRATEGY

PIPERACK FOUNDATION UNDER HDPE


LINE FOR INTERCONNECTING
PIPERACKS CWA 128295-128297

HDPE Depth (bottom): 4.3m


Foundations Depth (bottom): 6.5m
KEYPLAN
2ND CONSTRUCTABILITY WORKSHOP - U&O
5 FOCUS ON HDPE ERECTION EXECUTION STRATEGY

COOLING WATER LINES PIT


BETWEEN U&O AND PO
CWA: 128U02

HDPE level is above Storm water lines


according to Company comments (to
facilitate maintenance in case of a
broken line).
To be checked and defined by
engineering.
KEYPLAN
2ND CONSTRUCTABILITY WORKSHOP - U&O
6 FOCUS ON HDPE ERECTION EXECUTION STRATEGY

PRIORITY ON HDPE LINE


UNDER INTERCONNECTING
PIPERACK 128291-IR003

Issues found on interface between


Piperack foundation and HDPE
line to EU4.
Is not possible to lower the
foundation of the Piperack due
the position of the HDPE lines/
To be studied by engineering.
KEYPLAN
2ND CONSTRUCTABILITY WORKSHOP - U&O
7 FOCUS ON HDPE ERECTION EXECUTION STRATEGY

COOLING WATER LINES PIT


BETWEEN U&O AND PO
CWA: 128U02

Pit dimensions: ENG ON HOLD

You might also like