RATE ANALYSIS
REMOVAL OF FIBER SHED
Removal of existing fiber shed with minimum damage of original structure as per site requirement including carriage to the storage /
disposal area at designated place, complete in all respect and as per instruction of Engineer Incharge

Unit Per Sft 100 Sft


Sr.
MRS Input Sheet Detail Unit Rate Per 100 Sft.
No.
Qty Rate Per Amount (Rs.)
Unit (Rs.)
A MATERIAL
-
Total (A) -
B TRANSPORTATION
Manual Labour will be used
Total (B) -
C LABOUR
1 LB-024 Skilled 1.00 No. 634 Per day 634
2 LB-015 Un-Skilled 1.00 No. 558 Per day 558
1,192
Sundries 10 % 119
Total (C) 1,311

Total (A+B+C) 1,311


Contractor's Profit + Overheads 15 % Total (D) 197
Total (A+B+C+D) 1,508
Income Tax 7.5 % 113

Total 1,620.97
ITEM RATE
Composite Rate Per Sft. 1620.97/100 Rs. 16.21

Say 20.00

Page 1 of 1