Professional Documents
Culture Documents
Helwan Plant
Focus Group:
1- Eng.Mohamed Fathy .
2- Eng. Mohamed Atef.
3- Eng. Mahmoud Tammam .
4- Eng.islam Roushdy.
Supervisor
Dr. Attia Gomaa
Contents
Equipment specifications
A raw mill is the equipment used to grind raw materials into "raw mix"
during the manufacture of cement. Raw mix is then fed to a cement
kiln, which transforms it into clinker, which is then ground to make
cement in the cement mill.
SD70 HA8 -
BBC
500 V
raw meal
3 Collecting belt conveyor F.L.S 1982 800mm 240 T/h 35 kw
transportation
width
raw meal
4 Collecting belt conveyor F.L.S 1982 1000mm 240 T/h 7.5 kw
transportation
width
5 Clay belt conveyor T.O. 2001 800 mm 120t/hr Clay transportion 30 kw
Equipment Specifications
n1 = 990 r.p.m
X100
n2 = 623 r.p.m
965 r.p.m
315/335
f 3350
Raw Mills
Inside diameter of the mill (Other dimension) 4.42 m dia., (L=6.6 m)
•change worn out crusher grates •Change worn-out mill plates •Change hammers of crusher
•Change worn-out mill plates •Change worn-out mill plates •complete crusher grates •Complete grates crusher
•change worn out crusher grates •Change worn-out mill plates •Change hammers of crusher
1 2 3 4 5 6 7 8 9 10 11 12
M M M M M M M M M M M M
Q Q Q Q
A
Note:
• The Raw Mills system consists for two main Equipment ( Raw Mill & 3&4 ).
and they stopped alternately for example in week 1 raw Mill 3 stopped and raw Mill 4 will
be on operation .
• We don’t have any semiannually activities .
• We will work based on 52 week in the calendar .
• All the activities during stopped phase (weekly – Monthly – quarterly – annually ).
Annual Maintenance schedule ( Maintenance Matrix )
R.M# 3
1 2 3 4 5 6 7 8 9 10 11 12 13
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
X W X M X W X M X W X Q X W X M X W X M X W X Q X W X M X W X M X W X Q X W X M X W X M X W X A X W X W
M M M M M M M M M M M M
Q Q Q Q
R.M# 4 1 2 3 4 5 6 7 8 9 10 11 12 13
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
W X W X M X W X M X W X Q X W X M X W X M X W X X W X M X W X M X W X Q X W X M X W X M X W X A X W X
S
M M M M M M M M M M M M
Q Q Q Q
Cost of of weekly PM 3*5 2*5 2*5 2*5 2*5 2*5 2*5 2*5 2*5 2*5 2*5 2*5 3*5
Cost of of Monthly PM 1*30 2*30 1*30 1*30 2*30 1*30 1*30 2*30 1*30 1*30 2*30 1*30 1*30
•Change worn-out mill plates •Change worn-out mill plates •complete crusher grates •Complete grates crusher
•change worn out crusher grates •Change worn-out mill plates •Change hammers of crusher
No. of C.M 5 3 8 3
• Standard working hours / line = 8760 hrs X 2running / 2 Total = 8760 hrs
MTBF :-
MTBF(for the line) = Total operating Time / No. (CMS + PMs).
For sub Equipment stoppage
MTBM MTBF
item
(Mean Time between maintenance ) (Mean Time between Failure )
Fans Tripped = (8760 / (5 CM+ 2 PM) = 1251 Hrs./failure. (8760 / (5 CM )=1752 Hrs./failure.
Mills Internal = (8760 / (3 CM+ 42 PM) = 195 Hrs. /failure. (8760 / (3 CM) = 2920 Hrs. /failure.
Hazemag Crushers = (8760 /(8 CM+22 PM) = 292Hrs. / failure. (8760 /(8 CM) = 1095Hrs. / failure.
Filters Problems = ( 8760/ ( 3 CM+ 2 PM) = 1752Hrs. /failure . ( 8760/ ( 3 CM) = 2920Hrs. /failure .
Case Study:- Maintenance Control
Hazemag Filter
Item Target Fan tripped Mill internal
crusher problems
CM/PM 20% 5/2=250% 3/42= 8% 8/22= 37% 3/2=150%
Recommendations RCFA Update PM RCFA
Case Study:- Maintenance Control
PM Efficiency : PM % on Time
Maintenance type •Stopped •Stopped •Stopped •Stopped
Assumption :-
Waiting Time /year = 550 Hrs. for Raw Mills (3,4).
100.00%
80.00%
60.00% Acutal
Target
40.00%
20.00%
0.00%
Availability Reliability Utilization Performance Quality OEE
Case Study:- Supporting documents
• Planner
NO Yes
Standing order
(Minor & Non
critical Jobs Only)
Yes
not
available
available
Do the planning & preparation
•Maintenan Manpower +resources+spares
CRTD-IPRE • All departments
ce /MCC
manager
do the job
WO prepared and
ready for
execution
Close Notification status REL-WFPA
Assign to project CRTD-RTLA
or close
• Planner
Execute the job • Execution
• MCC Planner
Close WO- TECO
Close Notification
Equipment History
Inspection , Notification, Work order & Feed back:-
Inspection , Notification, Work order & Feed back:-