You are on page 1of 4

CONSTRUCTION CREW OF FIVE (5) FOR A TWO (2) STOREY RESIDENTIAL

General Requirements

1. Schedule lot stake out – 50 sqm = 10 sqm/man-day = 1 day/s


2. Stake lot – 50 sqm = 10 sqm/man-day = 1 day/s
3. Post lot Identification – 140 sqm = 28 sqm/man-day = 1 day/s
4. Install construction entrance – 24 m = 4.8 m/man-day = 1 day/s
5. Install sediment controls – 24 m = 2.4 m /man-day = 2 day/s

Site Work

6. Clearing – 140 sqm = 50 sqm/man-day = 3 day/s


7. Stake lot for excavation – 50 sqm = 10 sqm/man-day = 1 day/s
8. Excavate for foundation – 50 sqm = 5 sqm/man-day = 2 day/s

Foundation and Column

9. Layout footings – 50 sqm = 10 sqm/man-day = 1 day/s


10. Dig footings & install reinforcement – 50 sqm = 10 sqm/man-day = 1 day/s
11. Installation of rebar and wires of columns – 50 sqm = 10 sqm/man-day = 0 day/s
12. Pour footings – 50 sqm = 10 sqm/man-day = 1 day/s
13. Installation Column Formworks – 50 sqm = 10 sqm/man-day = 1 day/s
14. Pour Columns with concrete – 50 sqm = 10 sqm/man-day = 1 day/s
15. Installation Column Formworks – 50 sqm = 5 sqm/man-day = 2 day/s
16. Pour Columns with concrete – 50 sqm = 10 sqm/man-day = 1 day/s

Ground Floor

17. Ground Floor Slab Framing – 50 sqm = 2.5 sqm/man-day = 4 day/s


18. Pour Ground Floor Slab – 50 sqm = 10 sqm/man-day = 1 day/s
19. Ground Floor Wall Framing – 50 sqm = 2.5 sqm/man-day = 4 day/s
Second Floor

20. 2nd Floor Slab Framing – 50 sqm = 5 sqm/man-day = 2 day/s


21. Pour 2nd Floor Slab – 50 sqm = 10 sqm/man-day = 1 day/s
22. 2nd Floor Wall Framing – 50 sqm = 3.33 sqm/man-day = 3 day/s

Roofing

23. Set Roof Trusses – 50 sqm = 5 sqm/man-day = 2 day/s


24. Frame Roof – 50 sqm = 1.42 sqm/man-day = 7 day/s
25. Install Roof Plywood – 50 sqm = 1 sqm/man-day = 5 day/s
26. Install Windows & Doors – 50 sqm = 5 sqm/man-day = 2 day/s

HVAC

27. HVAC Layout & Measure – 50 sqm = 10 sqm/man-day = 1 day/s


28. HVAC Rough-in – 50 sqm = 10 sqm/man-day = 5 day/s
29. HVAC Set Indoor Units – 50 sqm = 5 sqm/man-day = 2 day/s

Plumbing Rough-in

30. Plumbing Sub-slab – 50 sqm = 10 sqm/man-day = 2 day/s


31. Plumbing Layout – 50 sqm = 10 sqm/man-day = 1 day/s
32. Plumbing rough-in – 50 sqm = 10 sqm/man-day = 5 day/s

Electric Rough-in

33. Set Electric Boxes – 2 pcs = 1 pc/man-day = 2 day/s


34. Install Electric Service Panel – 50 sqm = 5 sqm/man-day = 2 day/s
35. Electrical Walk-through – 50 sqm = 10 sqm/man-day = 1 day/s
36. Electrical Rough-wire – 50 sqm = 0.71 sqm/man-day = 14 day/s

Exterior Finishes

37. Siding – 50 sqm = 3.33 sqm/man-day = 3 day/s


38. Exterior Trim – 50 sqm = 1.42 sqm/man-day = 7 day/s
39. Brick Veneer – 50 sqm = 0.22 sqm/man-day = 45 day/s
40. Ceramic Tile – 50 sqm = 0.66 sqm/man-day = 15 day/s
Paint

41. Prep Drywall for Prime Coat – 100 sqm = 10 sqm/man-day = 2 day/s
42. Prime Trim – 100 sqm = 10 sqm/man-day = 2 day/s
43. Finish Coat Trim – 100 sqm = 1 sqm/man-day = 10 day/s
44. Finish Coat Drywall – 100 sqm = 1.42 sqm/man-day = 14 day/s
45. Caulk Exterior Windows & Doors – 50 sqm = 5 sqm/man-day = 2 day/s
46. Finish Coat Exterior Trim & Siding – 50 sqm = 5 sqm/man-day = 2 day/s

Interior Trim

47. Install Interior Doors – 10 pcs = 2 pcs/man-day = 5 day/s


48. Install Cabinetry – 10 pcs = 1 pcs/man-day = 5 day/s
49. Install Appliances – 10 pcs = 10 pcs/man-day = 1 day/s
50. 1st Punch-out Interior Trim – 50 sqm = 5 sqm/man-day = 2 day/s

HVAC Trim

51. Install Grills & Registers for Paint – 50 sqm = 10 sqm/man-day = 1 day/s
52. Set Outdoor Units – 50 sqm = 10 sqm/man-day = 1 day/s

Plumbing Trim

53. Set Fixtures – 6 pcs = 1 pcs/man-day = 1 day/s


54. Connect Appliances – 6 pcs = 1 pcs/man-day = 1 day/s
55. County Final Plumbing Inspection – 0 sqm = 0 sqm/man-day = 0 day/s

Electrical Final Trim

56. Switch & Plug – 20 pcs = 2 pcs/man-day = 2 day/s


57. Install Fixtures – 6 pcs = 1 pcs/man-day = 1 day/s
58. Connect Appliances – 6 pcs = 1 pcs/man-day = 1 day/s

Hardware

59. Door Hardware – 10 pcs = 5 pcs/man-day = 2 day/s


60. Bath Hardware – 1 pcs = 1 pc/man-day = 2 day/s
61. Mirrors – 3 pcs = 3 pcs/man-day = 1 day/s
62. Shower Doors – 3 pcs = 1 pcs/man-day = 10 day/s
63. Draw #8 (Prime paint, cabinets, doors) – 50 sqm = 10 sqm/man-day = 0 day/s
64. Draw #9 (Trim, furnace, hard wood, tile, rails) – 50 sqm = 0 sqm/man-day = 2
day/s
65. Draw #10 (Plumbing & elec. trim, final paint) – 50 sqm = 0 sqm/man-day = 2
day/s
66. Final Building Inspection – 0 sqm = 0 sqm/man-day = 0 day/s

Final Punch-out

67. Punch Out Walk-thru List – 140 sqm = 35 sqm/man-day = 4 day/s


68. Paint Touch-up – 100 sqm = 33.3 sqm/man-day = 3 day/s

Cleaning

69. Windows – 100 sqm = 33.3 sqm/man-day = 3 day/s


70. Rough Clean – 100 sqm = 33.3 sqm/man-day = 3 day/s
71. Final Clean – 140 sqm = 70 sqm/man-day = 2 day/s
72. Final Walk-through – 0 sqm = 0 sqm/man-day = 0 day/s

You might also like