Professional Documents
Culture Documents
Task
Mode
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Task Name
Duration
PHASE-1
65 days
EXPECTED CHASSIS ARRIVAL
30 days
CHASSIS ALLOTMENT
1 day
CABIN WORK SKELETON
7 days
SUBFRAME TAG WELD
7 days
SUPERSTRUCTURE TAG WELD
5 days
FIRST STAGE INSPECTION
15 days
PHASE 1 MILESTONE
0 days
PHASE- 2
134 days
CABIN WORK INTER STAGE
5 days
SUPERSTRUCTURE FINAL WELD 6 days
SUBFRAME FINAL WELD
5 days
SHEET METAL WORK
10 days
PROPELLOR SHAFTS
10 days
PREPARATION
15
16
17
18
19
PHASE -2 MILESTONE
20
PHASE -3
21
PTO INSTALLATION
22
5 days
5 days
30 days
30 days
0 days
95 days
5 days
5 days
Start
Qtr 4, 2016
Nov
Dec
Thu 15-12-16
Thu 15-12-16
Thu 26-01-17
Fri 27-01-17
Tue 07-02-17
Thu 16-02-17
Thu 23-02-17
Thu 16-03-17
Fri 17-03-17
Fri 17-03-17
Fri 24-03-17
Mon 03-04-17
Mon 10-04-17
Mon 24-04-17
Qtr 1, 2017
Jan
Feb
Mar
Qtr 2, 2017
Apr
May
Jun
Qtr 3, 2017
Jul
Aug
Sep
Qtr 4, 2017
Oct
Nov
Dec
Jan
PURCHASE TEAM
WORKSHOP TEAM - N
QA/QC TEAM ,WORKSHOP TEAM - N
DESIGN TEAM ,QA/QC TEAM ,WORKSHOP TEAM - N
WORKSHOP TEAM - N
QA/QC TEAM
16-03
WORKSHOP TEAM - R
WORKSHOP TEAM - N
WORKSHOP TEAM - R
WORKSHOP TEAM - R
WORKSHOP TEAM - N
WORKSHOP TEAM - N
Fri 12-05-17
Fri 19-05-17
Fri 26-05-17
Fri 07-07-17
Thu 27-04-17
Thu 27-04-17
Fri 05-05-17
Thu 27-04-17
WORKSHOP TEAM - N
WORKSHOP TEAM - N
WORKSHOP TEAM - N
27-04
WORKSHOP TEAM - R
WORKSHOP TEAM - N
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 1
ID
Task
Mode
Task Name
Duration
Start
Qtr 4, 2016
Nov
Dec
Qtr 1, 2017
Jan
Feb
Mar
Qtr 2, 2017
Apr
May
Jun
Qtr 3, 2017
Jul
Aug
WORKSHOP TEAM - R
Sep
23
6 days
Thu 27-04-17
24
TANK INSTALLATION
TANK PAINTING
26
27
28
29
PUMP INSTALLATION +
PLUMBING WORKS
Fri 05-05-17
Wed 30-08-17
Mon 15-05-17
Mon 15-05-17
Wed 24-05-17
Wed 14-06-17
WORKSHOP TEAM - N
25
6 days
6 days
7 days
7 days
15 days
10 days
30
PHASE-3 MILESTONE
0 days
50 days
Wed 28-06-17
Wed 28-06-17
28-06
31
PHASE-4
Qtr 4, 2017
Oct
Nov
Dec
WORKSHOP TEAM - N
WORKSHOP TEAM - R
WORKSHOP TEAM - N
QA/QC TEAM
WORKSHOP TEAM - R
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 2
Jan