Professional Documents
Culture Documents
Contract Number
CPSF-ME-SPE-01-CP2017-001-00 Rev A1
CFT/45/20/1006
Nor Syaheera
Ir Danial Zam Zam Shaiful Mahmud
Bt Mohd Riza M. Fadzli
2022.10.28
2022.10.28 08:54:33
+08'00'
2022.10.28 09:29:41 2022.10.31
+08'00'
08:46:07
+08'00'
09:25:36 +08'00'
Table of Contents
1.0 INTRODUCTION 4
1.1 Purpose 5
1.2 Definition of Terms 5
1.3 Abbreviation 5
12.0 GUARANTEE 33
APPENDICES
Appendix A DATASHEETS
Appendix B PROJECT RELATED DOCUMENTS
Appendix C VENDOR DRAWINGS AND REQUIREMENT LIST (VDRL)
Appendix D INSPECTION TEST PLAN MATRIX
Appendix E SPARE PARTS AND INTERCHANGEABILITY RECORD (SPIR) FORM
TECHNICAL SPECIFICATION FOR WATER BATH HEATERS Rev. A1 27.10.22 Page 3 / 40
Doc. No CPSF-ME-SPE-01-CP2017-001-00
1.0 INTRODUCTION
ILK Construction (ILK) was invited by Dragon Oil (Turkmenistan) Ltd (COMPANY), to
execute EPC FOR CPSF DEBOTTLENECKING AND CAPACITY UPGRADE PROJECT
PHASE I.
The production from the LAM and ZHD field are collected at Block-2 manifold platform and further
routed through 30” Pipeline to Central Processing and Storage Facility (CPSF). The CPSF has
a handling capacity of 100,000 bpd oil and 25,000 bpd water along with 200 MMSCFD gas flow.
CPSF has Slug Catchers, Heater Treaters, Gas Scrubbers and Produced Water systems to treat
the oil and thus caters the export gas and oil specification. COMPANY is on a continuous
expansion mode for additional production and processing requirements. COMPANY has carried
out debottlenecking study of CPSF to address existing issues in liquid & vapor streams and
enable the smooth process operations and parallelly upgrading the facility for future production
and to handle increased water.
Phase Oil flow, BOPD Water flow, BLPD Gas flow, MMSCFD
I 80,000 54,000 220
II 100,000 80,000 220
For this purpose, ILK has appointed DAR energy Sdn Bhd (DAR) to execute Engineering scope
for EPC for CPSF Debottlenecking and Capacity Upgrade Project Phase I.
TECHNICAL SPECIFICATION FOR WATER BATH HEATERS Rev. A1 27.10.22 Page 4 / 40
Doc. No CPSF-ME-SPE-01-CP2017-001-00
1.1 Purpose
The purpose is to define the minimum technical requirements for the engineering, design,
fabrication, inspection, testing and supply of Water Bath Heaters (CPSF-21-A-115/ 116/ 117/
118/ 119). This Specification is to be read in conjunction with the referenced Dragon Oil
standards, respective P&IDs, applicable Mechanical Data sheets and all referenced
specifications in this document in which the operating and design Parameters and Technical
requirements of the equipment are stipulated.
Scope of Supply/ Services of the VENDOR shall be as per Section 5 of this Specification and
Mechanical Datasheets. It shall be the responsibility of VENDOR to check that all aspects of the
design, fabrication, inspection and testing are in conformity with the specified documents for all
the items included in the supply.
The absence of any specifications shall imply that the best engineering practices shall prevail,
utilizing state of the art quality workmanship and new materials.
All documents which will use the following words and expression shall have the meanings given:
“CONTRACTOR” The party that carries out all or part of the contract of the Project.
“VENDOR” The company on which the purchase order or contract for supply of
the goods or services is placed.
“VENDOR” covers “Manufacturer/Supplier”
1.3 Abbreviation
For resolution of any conflicting data or other information the following order of precedence shall
apply:
In the event of any conflict, discrepancy, inconsistency or ambiguity amongst documents within
the same level of precedence or between project documents and international codes/standards,
the more stringent requirement shall prevail unless otherwise APPROVED and the same shall
not give rise to any entitlement for cost and/or schedule relief.
The VENDOR’s scope shall include design of Water Bath Heaters as per process requirements,
engineering, procurement, manufacture, assembly, inspection & testing, ASME code stamping,
painting, packing, preservation of water bath heater, supporting system in compliance with this
specification and its attachments, data sheets, COMPANY specifications and the referred
documents.
VENDOR shall be responsible to meet the requirements of this specification with its attachments,
and the documents referred to within, in order to ensure safe and trouble-free operation for the
complete equipment.
2 Material certification as per equipment data sheet 1 Lot for each Included
3 Pipe stress analysis within the skid/ package. 1 Lot for each Included
4 Surface preparation, painting and coating of all 1 Lot for each Included
equipment as per Specification for Painting.
5 VENDOR Documentation as per “Vendor Drawings and 1 Lot for each Included
Data Requirement List”, (Appendix C).
6 Packing, marking, preservation and shipment, as per 1 Lot for each Included
specifications.
7 Inspection and Testing for Water bath heater in 1 Lot for each Included
accordance with Code as specification requirements.
9 Special Tools/ tackles including spreader bar for 1 Lot for each Included
handling the installation. (If required)
10 Lifting Lugs, Earthing lugs, Insulation Cleats 1 Lot for each Included
12 Transportation Saddles & all necessary devices for 1 Lot for each Included
Transport
13 Cathodic Protection System with Sacrificial Anode 1 Lot for each Included
14 Blind flanges for all blinded nozzles with studs, nuts and 1 Lot for each Included
gaskets
16 All fixed & removable internals along with accessories 1 Lot for each Included
for the unit
17 Itemized list of Initial Spare Parts for Ist year of operation 1 Lot for each
on completed SPIR Form.
18 Itemized list of all recommended operational spares for 1 Lot for each
2 years (provide a list in SPIR Form)
19 Priced list of itemized 2-year initial, insurance and 1 Lot for each
operating spares on completed SPIR Form
20 Gussets with pads, platforms, ladders & piping supports 1 Lot for each
(Unit rates to be provided
22 Vendor shall include the supply of PDMS 3D model or 1 Lot for each
3D model STP file that is compatible with PDMS (latest
version) showing all equipment, piping, structures,
operating and safety requirements within the specified
package/ skid limit, comes with PDMS catalogues and
specification.
23 Per diem, rate for VENDOR representative assistance 1 Lot for each Day
for Installation at site.
24 Per diem, rate for VENDOR representative assistance 1 Lot for each Day
for pre-commissioning / commissioning and start-up at
site.
25 Per diem rate for VENDOR Representative for Training 1 Lot for each Day
of COMPANY personnel, (Cost shall include training
materials).
29 Insulation & Fireproofing Supports, Earthing Cleats 1 Lot for each Included
31 Vendor shall provide glycol consumption rate 1 Lot for each Included
Note:
Charges for engineering meetings, pre-commissioning / commissioning supervision, Start-up assistance, Site
Performance/Acceptance Test, Internal Coating, Training etc. shall be furnished in separate schedule. These
rates shall cover categories like Engineer, Technician, Trainer, etc. as necessary.
Water Bath Heater shall be designed for a specified process conditions as described in below
sections.
6.1.3 Rainfall
Annual average: 136 mm
24 hours (Maximum): 68 mm
• Process datasheet
• Mechanical data sheet
8.1 Design
i. The heater shall be a complete factory-assembled, forced draft unit including heat
exchanger, burner equipment, fire tube, blower, gas train, stack, piping connections
including process headers, and steel supports. The heater shall be of complete factory
assembled design, with minimum field bolt-up assembly required.
ii. The heater shall be designed to have two distinctive sections enclosed in one pressure
vessel. The fire tube shall be installed in the lower portion of the shell, immersed in water.
The heat from the burner will vaporize the water surrounding the fire tube. Above the fire
tube, there will be process piping, which is not immersed in the water bath. Steam
generated by the fire tube will condense on the process coils, transferring heat to the
process.
iii. A heat exchanger principle shall be used such that it will assure uniform heat transfer flux
rates throughout the heat exchanger portion of the heater. As a guard against high flux
rates in one area and low flux rates in another, heat transfer shall be by convection and
condensation. The fuel/air ratio shall be controlled through-out the turndown range
resulting in low oxygen levels at all firing rates.
iv. Process Coil
The material for process coil shall as per datasheet and VENDOR shall calculate the wall
thickness as per respective codes & standards considering the design pressure, design
temperature and corrosion allowance.
Radiographic inspection shall be 100% for the pipe welds.
Tube supports: Process coils shall be adequately supported to prevent sagging and undue
stress on the piping at any operating condition. Pipe supports shall support both the
process coils and the fire tube and shall transfer loads to the vessel shell. Process pipe
support shall not impede thermal expansion of process coils.
v. Insulation
Hot insulation is required for the unit. VENDOR shall include the insulation material of the
vessel.
vi. Burner
Type: The burner shall be a gas-fired, forced-draft, fire tube type burner. The burner shall
be a low emissions burner.
VENDOR shall consider an excess air margin of 10-15% for the design purposes.
VENDOR shall note that emissions such as NOx levels shall be limited to 30 ppm,
corrected to 3% O2, CO levels shall be a maximum of 400 ppm, corrected to 3% O2.
Burners shall be capable of rapid transition from maximum fire to minimum fire to
accommodate sudden process demand changes. Burner shall be designed to operate at
minimum capacity or pilot capacity for longer time to keep the heater at operating
temperatures, even when not in use.
A separate pilot and main burner are acceptable. No provision shall made for manual
ignition of the burner with torches, matches, etc. Ignition of pilot shall utilize an automatic,
electronic spark igniter, controlled by the burner management system.
The burner shall have a turndown capability of 3:1 or better.
The burner-firing rate shall be controlled as follows: The temperature-indicating controller
(TIC) will receive a thermocouple input from the process outlet. This temperature will be
compared with the outlet set point. The TIC has a 4-20 mA output, which is the heater
demand signal. The signals are transmitted to control interface, which shall also include
controls of fuel gas control valve and a combustion air control valve. Each valve shall be
provided with an electronic actuator. These actuators are suitable for use in a Zone 2, IIB,
T3. The actuators position the valves using stepper motors, and therefore can reliably
position the valve to within 0.1°.
vii. Blower
VENDOR to provide motor starter panel on skid for the blower fan motor and shall comply
to Zone 2, IIB, T3 hazardous area classification.
VENDOR shall note that combustion air blower shall be of heavy-duty type sized for (10%)
ten percent excess volume over operation requirements at maximum capacity. The blower
shall be direct drive arrangement. Blower outlet pressure shall be sufficient to maintain a
positive pressure throughout the combustion airline, burner, fire tube, and stack. All
portions of the heater shall be forced draft. No natural or induced draft is acceptable.
All transmitter within the skid /package for connection to the plant Process Control System
(PCS) and Emergency Shutdown (ESD) systems shall be based on 2-wire, 24VDC loop-
powered, 4-20mA DC output signal with HART communication. The transmitters shall be
certified Intrinsically Safe Ex 'i' for hazardous area Zone 2, Gas Group IIA, Temp. class
T3. Transmitters shall be used instead of flow/level/pressure/temperature switches (LSL,
LSH, PSL, PSH, TSL, TSH etc).
All signal cables for connection to the plant PCS and ESD system shall be terminated to
junction boxes located at the edge of the skid/package. Interface cables external of the
skid/package will be under PURCHASER's scope.
Separate junction boxes shall be provided for PCS analog, PCS digital, ESD analog, ESD
digital signal cables. Separate junction boxes shall also be provided for Intrinsically Safe
(I.S.) and Non-intrinsically Safe (Non-I.S.) signal cables.
x. Material of Construction
VENDOR shall note that all materials shall be new and of the highest quality. Refer to the
datasheet for material of construction. The materials shall be tested and comply with
ASME/ ASTM codes or equivalent as per respective codes.
VENDOR shall note that exhaust stack shall be accessible to personnel and shall be
externally insulated with jacketed ceramic fiber for personnel protection.
xi. Local Control Panel
The local control panel shall be IP 55 type with terminal strips for final connections between
controls and heating unit. Panel shall meet NEMA construction standards. Control panel
shall have exterior indicating lights and switches for local control.
Panel space heaters shall be provided to maintain the recommended operating
temperature of components inside the control panel during winter.
All electronic cards shall be suitably coated in accordance with ISA 71.04 to fully protect
the cards from moisture, airborne contaminants, and corrosive gases.
The local control panel shall be designed to interface with the plant Process Control
System (PCS) via fiber optic cable utilising TCP/IP communication protocol. VENDOR
shall provide the necessary fiber optic converter inside the local control panel. VENDOR
shall provide all the required MODBUS data mapping list for incorporation into the PCS.
The local control panel shall be designed to accept a tripping signal from the plant
Emergency Shutdown (ESD) system. The signal from the plant ESD system shall be
based on 24 VDC wet signal (normally energised, de-energise to trip). If Volt-free Contact
signal is required, VENDOR to provide 24VDC interposing relay inside the local control
panel.
xii. The vendor shall provide additional stiffening as required to prevent permanent shell
distortion during fabrication, heat treatment, hydrostatic testing, shipment, and erection
xiii. Design pressure specified shall be at the top of vertical vessel or at the highest point of
horizontal vessel. VENDOR to provide LED lighting fixtures on skid certified to Zone 2, IIB,
T3.
xiv. The design pressure at any lower point shall be determined by adding the maximum
operating liquid head and any pressure gradient within the vessel.
xv. For normal operation, the vessel and its structural supports shall be designed for the
operating load(s) including design pressure, plus static head, plus estimated external
attachment loads (such as exerted by piping) plus wind or earthquake load (whichever is
greater) using the allowable stresses permitted by the Code at the design temperature.
xvi. Design shall also cater to the lifting and transport conditions in addition to operating and
Hydrostatic test conditions.
xvii. All vessels and its structural supports shall be designed for a field hydrostatic test when
the vessel is in the operating position.
xviii. Stiffening rings for external pressure duties shall be external. Internal supports/rings shall
not be considered to contribute to the stiffening ring requirement.
xix. WRC-107 and WRC-297 code shall be used for determining local stress in the vessel
shells and heads.
xx. For Nozzles out of scope of WRC, Finite Element Analysis shall be performed.
xxi. Internal alloy cladding or weld metal overlay cladding shall not be included in the strength
calculations of any of the vessel components
xxii. The design life of the Vessels shall be 30 years as per BED Validation (Mechanical).
xxiii. Each equipment shall be equipped with a minimum of two (2) Earthing lugs.
xxiv. All vessels over 914 mm internal diameter shall have a manhole or at least two hand holes
as per the requirements.
8.2 Internals
i. All removable internals shall be sized for removal through the vessel assesses way(s).
i. The minimum corrosion allowance for carbon steel and low alloy steel shall be 3mm unless
specified otherwise in the data sheets.
ii. Minimum corrosion allowance shall be added to both sides of non-removable carbon
steel/Low alloy steel internals when exposed to corrosive fluid or vapor.
iii. Removable internal parts (with the exception of trays) which are bolted or clamped in
place, shall be provided with extra thickness equal to half the specified corrosion allowance
on each surface exposed to vessel contents.
iv. Full corrosion allowance shall be added to the throat thickness necessary for strength or
sealing in case of fillet and seal welds on internal attachments.
v. Vessels and internals shall have corrosion allowance as specified on the data sheet.
vi. Vessel parts which are subjected to erosion (eg. due to impingement by the process
stream) shall be protected with wear plate or impingement baffles
8.4 FABRICATION
i. VENDOR shall note that Heater Burner and shall be of fabricated welded steel
construction of airtight design.
ii. Stack shall be a stub stack and not be less than 4 ft. above top of heater. The material of
construction shall be carbon steel material or better grade.
iii. Electrical: The control panel, electrical enclosures and conduit shall meet NFPA-70, NEC
requirements for the operating environment of the heater. The electrical assembly and
wiring shall be factory installed and shall be complete.
iv. Piping: Fuel gas and air piping shall be completely shop assembled with control and safety
valves
8.5 Nozzles
i. The tapping for various indications such as level, pressure, temperature etc. shall not be
taken from the bottom but from a height above the bottom. Nozzle load included to the
skid package as attached in Appendix B.
ii. Vessel openings 1-1/4, 2-1/2, 3-1/2, 5 and 7 inch NB shall not be used. Please refer
document no CPSF-PP-DBS-01-CP2017-002-00 Appendix B.
iii. All nozzle attachment welds including ones with reinforcing pad shall be full penetration
type.
iv. Nozzle neck made of elbows, mitered elbows or bends shall not be used unless specified
in vessel specification.
v. Nozzles for drains, vents and relief valves shall be flushed with the inside surface of the
vessel. Other nozzles may protrude inwards to the extent required for internal welds unless
fittings or removal of internals required them to be flushed.
vi. No threaded opening shall be tapped directly into the shell or head plates except for tell-
tale holes in reinforcing pads. Studded type connections shall not be used.
vii. Nozzles, manholes and reinforcing pads shall not penetrate or cover any of the welding
joints of the shell or head.
viii. When bottom head connection of butt-welded construction are brought outside the skirt by
piping, the pipe shall be at least one schedule heavier than that required for the vessel
design conditions plus corrosion allowance. Piping shall be left unrestrained in the skirt
opening
i. Manhole cover shall be provided with a davit and Hand hole cover shall be provided with
handles.
ii. Inside edge of Manholes / Hand holes shall be smooth and rounded off with a minimum
radius of 3 mm.
8.7 Flanges
i. When tongue and groove or male and female faced flanges are used, groove or female
face shall be in nozzle flange. However, when the nozzle is located in the bottom, the
groove or females face shall in the cover.
ii. Dimensions of flanges shall be as per ANSI B16.5 for sizes up to 24” NB (600 mm NB)
and as per ASME B 16.47 series ‘B’ for size greater than 24” NB (600 mm NB).
i. Pad plate for the supports for the vessel supports shall be used same material as vessel.
ii. Horizontal vessel shall be supported in two welded steel saddles, each with a minimum
included angle of 120º.
iii. Saddle bolt holes shall be slotted at sliding saddle of the horizontal vessel/ exchanger to
provide for thermal expansion.
iv. The vessel shall be adequately reinforced to take care of the local loads imposed by the
supports.
i. All bolts / studs shall have ISO threading. Studs shall be threaded to full length.
ii. All internal bolts shall be provided with double nuts.
iii. The fabricator shall supply two sets of gaskets (where the gaskets are under his scope of
supply) other than those used for testing and / or during transportation. Service gaskets
shall be used during hydro-test.
i. Internal pressure piping shall be seamless, to the same specification as the external
connected pipe. However, internal piping for non-pressure piping can be either seamless
or welded type.
ii. Internal flanges for pressure piping shall be forged flanges; however, internal flanges for
non-pressure piping may be fabricated from plate.
i. Each completed vessel shall be provided with a type 316 stainless steel nameplate in
accordance with ASME Sec. VIII, securely attached to the vessel shell, so that it is clearly
visible after installation, preferably near a manhole or inspection opening. Insulated
vessels shall have name plate brackets with enough projection to clear insulation by at
least 25 mm.
ii. The following minimum details shall be marked on the Name plate: -
• The COMPANY equipment tag no.
• Name of Manufacturer
• Order Number
• Date of Manufacture
• Maximum Allowable working Pressure, kg/cm2 at temperature °C
• Hydro test Pressure, kg/cm2
• Date Tested
• Design Pressure, kg/cm2
• Design Temperature, °C
• Erected Weight, kg
• Corrosion Allowance
• Radiography
i. When vessels are to be fireproofed and / or insulated, it shall be indicated on the vessel
data sheets. The fabricator shall provide with the fire proofing and insulation supports
cleats on the vessels.
8.13 Welding
i. Flame cut edges shall be ground by the fabricator as required to remove slag, detrimental
discolorations and non-uniformity of edges.
ii. All pressure bearing butt welds shall be full penetration, double welded joints. When
second side welding is not possible due to inaccessibility, single welded butt joints with
root run by Tungsten Inert Gas Process (TIG) may be used to ensure full penetration.
Backing strip can be used only after obtaining prior approval from Company. For sub-zero
temperature, backing strips shall not be used.
iii. Nozzles and Man ways and their reinforcement pads shall be attached to vessel with full
penetration welds.
iv. Seams in supporting skirt shall be made with full penetration butt welds. Connection
between skirt and vessel head shall be made with a smooth flat-faced weld. Width of the
weld at skit end shall be equal to the skirt thickness and its height shall at least be twice
its width.
v. All main weld seams shall be clear of nozzles, manholes and stiffening rings. Other
attachments like reinforcement pads, internals, tray support rings, cleats etc., shall
preferably be away from the main seams. In case it is unavoidable, the main seam portion
coming under the attachment plus 150mm length on both sides shall be ground flush, fully
radio graphed, and dye penetrate examined before welding or any such attachment.
However, COMPANY approval shall be taken prior to any such welding.
vi. Vendor shall submit welding procedure specification and qualification record to
purchaser’s inspector or authorized representative for approval as per ASME Boiler and
Pressure Vessels Code Section IX.
8.14 Tolerances
i. Vessels shall be post weld heat treated when specified on the datasheet. In no case shall
the post weld heat treatment performed be less than that specified in the code.
ii. Vessels shall be post weld heat treated as a complete unit wherever practicable.
iii. All flanges shall be suitably protected against oxidation during post weld heat treatment.
9.1 General
i. Contractor shall show that an effective system of quality assurance is in operation for both
products and services offered as per this specification.
ii. All lists of documents, in dossier form, shall be retained as evidence that the product or
service supplied complies with the specified requirements.
iii. For the purpose of surveillance, product or service acceptance and QA audit, the
Contractor shall provide access to purchaser or its representative.
iv. Inspection by the purchaser shall not release the Contractor of any guarantees,
responsibilities or obligations to furnish equipment / material in accordance with the
specification and the requisition
i. The Supplier shall prepare a quality plan covering all aspects of design, approval, material
procurement, manufacture, and testing (including work by main sub-Suppliers) and
identifying the points of involvement of Supplier’s and sub-Supplier’s inspectors.
ii. The quality plan shall be submitted to the purchaser at the enquiry stage for review and
agreement. The purchaser will annotate the quality plan with the certifying authority. No
work shall commence without the plan being accepted by the purchaser.
iii. The plan will include the following:
• Observed points – where the work will be offered by the Supplier (7 working days’
notice), but where in the event of non-attendance by purchaser’s inspector, further
work can continue observed by Supplier’s inspector.
• Witnessed where the work will be offered by the Supplier (14 working days’ notice)
and must be witnessed by the purchaser’s inspector before further work can continue.
• The inspection methods.
• Reference to the relevant documents (i.e., procedures, specifications and drawings
which control the specific operations).
iv. The quality characteristics to be verified at each inspection/test point and the acceptance
criteria.
All vessels shall be offered for Inspection to purchaser or his Authorized Inspector.
Inspection shall be carried out both during fabrication and before delivery and also for sub-
ordered material, if any. In addition to final inspection and certification by Inspector, Inspector’s
written approval shall be obtained by the manufacturer at all stages of fabrication including the
following:
10.1 Radiography
i. Contractor shall submit a complete hydrostatic testing procedure including filling and
emptying procedure for COMPANY approval prior to commencement of work.
ii. All necessary precautions shall be taken to guard against the risk of brittle fracture during
hydrostatic test in the shop and at site. The temperature of testing medium shall preferably
not be less than 16°C. Prior to hydrostatic test, all weld spatter, weld stubs, scale, dirt etc.,
shall be removed from vessel
iii. Hydrostatic test shall be conducted at pressure mentioned in datasheet after fabrication,
radiography and post weld heat treatment. After hydrostatic testing, vessel shall be
thoroughly dried by blowing dry air.
iv. Clean potable quality water having chloride content less than 25 ppm shall be used for
hydro test.
v. During hydro test, care shall be taken to avoid local stresses in shell from exceeding 90%
of the yield strength of the material at the temporary saddle supports.
vi. After Hydrostatic testing, Weld metal overlay cladding and attachment welds to weld
overlay or integral cladding shall be 100% liquid Penetrant examined with a water-soluble
liquid Penetrant. Examination and acceptance criteria shall be per ASME Code Section
VIII, Appendix 8 (for Div.1) or Appendix 9 (for Div.2).
TECHNICAL SPECIFICATION FOR WATER BATH HEATERS Rev. A1 27.10.22 Page 28 / 40
Doc. No CPSF-ME-SPE-01-CP2017-001-00
i. All pressure parts material certification shall be traceable with heat numbers, fully
catalogued NDT test records, mechanical test certificates, welding qualification
certificates, heat treatment certificates and hydrostatic test certificates shall be made
available during final inspection. The counter signature by the certification authority and
stored by the contractor for a minimum of 5years after the acceptance of the vessel by the
company, Pressure retaining parts shall be clearly marked to allow verification of
traceability.
i. Surface preparation and painting shall be carried out after satisfactory completion of all
tests including final hydro test. The procedure for sand blasting and coating including
materials shall be submitted for COMPANY’s approval prior to the application.
ii. Surface Cleaning and Painting shall be carried out as per General specification for painting
(CPSF-EQ-SPE-1-0594-11-00) including COMPANY’s standard, Standard Coating and
Painting Procedure shall be carried out as document no. STDS-QA-PCD-1-0001-04-00
and Standard Specification for Painting of Equipments and Piping as document no. STDS-
EQ-SPE-1-0001-01-00.
iii. All completed equipment shall be cleaned and externally to remove scale, dirt, sand, water
and foreign matter.
iv. The surface preparation of outside surface of vessels / columns shall be done by blast
cleaning only.
v. On completion of operation, the blasted surface shall be clean, dry and free from any mill
scale, rust, rust scale and foreign matter. Primer or first coat of paint shall be applied with
spray / brush as pre manufacturer’s recommendations and preferably with 4 hours of
surface preparation. Blast cleaning shall not be done outdoor in bad weather without
adequate protection or when there is dew on the metal surface, which is to be cleaned, or
when humidity exceeds 85%.
vi. Austenitic stainless steel, high alloy steel and non-ferrous material shall be kept free of
paints.
11.2 Markings
i. All loose components such as studs, nuts, washers, gaskets etc., shall be packed in
creates and shall be marked for the project, consignee, job no., item no., order no., gross
and net weight, dimensions etc.
ii. Vessels which have been post weld heat treated or have an applied lining, e.g., lead, glass,
rubber etc., shall have a suitable warning printed on the visible portion on the outside of
vessel.
iii. Specific marking with white paint for slinging shall be provided for all heavy lifts weighing
5 tons and above.
iv. A copy of packing list shall accompany the material enclosed in a water tight envelope
fastened inside a shell connection with an identifying arrow sign “Documents” applied with
indelible paint.
v. If it is necessary to separate the unit into different parts for transportation all components
and subassemblies shall be carefully identified, and match marked to prevent any error in
assembly.
11.3 Packing
i. Vessels, unless provided with their own steel saddles for entire protection, shall be
provided with suitable wooden saddle with steel ties and tension rods. The minimum height
of the saddle shall correspond to the maximum projected length of the connected
attachments, plus an additional clearance of 45 mm. Saddles spacing shall depend on the
length of the equipment.
ii. Large diameter equipment of small thickness shall be provided with an adequate number
of struts positioned inside the equipment to prevent ovalisation effect while being handled.
These struts shall not be removed until the equipments placed in position at job site.
iii. All connections / protrusions shall be suitably protected. Flanges shall be provided with
bolts on metal covers (minimum 5mm thick). Using at least four bolts (Wiring on cover is
not acceptable). For ocean shipment, flanged openings shall be additionally covered with
heavy plastic bags taped to nozzle. All tell-tale holes shall plug with hard grease before
dispatch. Tapped orifice shall have threaded plugs.
iv. Fragile or machined components shall be especially protected against nature during
handling and transit.
v. Temporary stiffeners at each non-supported end shall protect prefabricated sections.
Edges of plates for section to be welded shall also be protected.
11.4 Shipment
i. All dispatches of equipment shall be done in accordance with the relevant terms of the
Purchase Order.
ii. Tray assembly hardware shall be furnished in quantities as required plus the greater of the
following quantities to compensate for possible loss:
• Bolts and nuts – 5 % excess or 10 of each
• Washers – 15 % excess or 10 pieces
• Try clamp – 2% excess or 5 pieces
TECHNICAL SPECIFICATION FOR WATER BATH HEATERS Rev. A1 27.10.22 Page 31 / 40
Doc. No CPSF-ME-SPE-01-CP2017-001-00
11.5 Preservation
Supplier shall state in the proposal his recommendation for long term storage (up to 12 months)
for both indoor and open-air storage in desert sandstorm prone environment.
12.0 GUARANTEE
Manufacturer shall guarantee that all materials used in the equipment are new and have been
submitted to regular acceptance procedure and are free from any defect regarding quality, form
and appearance.
Vessel(s) shall be guaranteed for design, materials and workmanship by the supplier for Two (2)
years after commissioning. Performance guarantee test run for continuous 72 hours shall be
carried out to demonstrate the equipment performance at rated condition as specified
The manufacturer shall be completely responsible for any design work carried out by him.
COMPANY approval of his design will not relieve him of his responsibility to ensure satisfactory
performance of such item.
The following spares shall be provided by manufacturer for all nozzles with blind flanges and for
all bolted joints included in his scope:
2 sets of gaskets
In addition, manufacturer shall provide list of recommended spare parts for two-year normal
operation and spares required for start-up and commissioning as part of his firm scope of supply.
The list of such start-up and commissioning spares shall be furnished to the Company.
Manufacturer shall provide and supply any special tools required for the installation and
maintenance of the equipment.
VENDOR shall include the supply of all documentation to define the equipment/material supplied
for the purposes of:
• Piping GA
• Isometric
• Pipe support drawing
Detailed requirement of VENDOR documents with respective codes are specified in VENDOR
document requirement list (VDRL) attached with this requisition (Appendix C). VENDOR shall
prepare VENDOR document register in accordance with VDRL and submit for
CONTRACTOR/COMPANY approval.
14.3.1 General
It is a condition of any purchase order that all data and drawings (hereinafter called documents)
shall be submitted to the CONTRACTOR/COMPANY in the manner and time period stated. The
purchase order will not be considered complete until all documentation has been submitted and
accepted.
14.3.2 Presentation
All documents shall be full size based on ‘A’ series sizes, i.e. A1, A2, A3 or A4.
All documents shall be checked before submission; unchecked documents may be returned un-
reviewed.
All documents submitted shall be clearly marked with the requisition no., item no, VENDOR’s
Job No., and Part No. (If applicable). In addition, the project title block shall be added by
VENDOR in accordance with engineering procedure
All documents and technical data shall be provided in the English language.
Dimensions and other units of measurement are defined within document and shall be SI and
other units recognized by SI, preferably: mm, °C, bar. Except that pipe and bolt diameters may
be in inches, pipe wall thicknesses may be in pipe schedules, and tube wall thickness in BWG.
A free space 80 mm x 50 mm shall be provided adjacent to the document’s title block for the
purchaser to add his own status review stamp.
All document preparation, photocopying and printing shall be of sufficient clarity and legibility to
ensure satisfactory quality for electronic documentation.
All document prints larger than A4 shall be folded to A4 size with identification data visible at the
bottom right.
14.3.3 Submission
Documents required for submission are indicated in the “With Quote” or “For Review” columns
of this VDRL
Documents required to form part of the final documentation which will not be submitted for
individual review are indicated in the data book column only.
Any revision to a document after its first submission shall be clearly identified on the document
in the revision box. Once issued, a document number shall not be changed or re-used.
All documents shall be sent under cover of a transmittal using the standard project format (to
follow).
Certified final submissions shall be made within 7 calendar days of receipt of document with
CONTRACTOR/COMPANY review status of “No Comments”.
Drawings showing overall dimensions of equipment and other details will be considered fixed
and final regarding these details, once they have been acceptably reviewed and returned. No
alteration to these documents will be accepted when they have achieved this status.
The VENDOR shall list all documents and their document number on the VDI. The COMPANY
documents numbers will be added at the first review of the VDI by the VENDOR. All documents
subsequently submitted shall be identified with their relevant COMPANY document number. Any
urgent documents submitted with, or prior to, the VDI will be marked with a COMPANY document
number as part of the review comments.
These numbers shall be identified on the originals by the VENDOR for their next submission.
14.3.7 Manufacturing Record Book (MRB) and Vendor Data Book (VDB)
The Manufacturing Record Book (MRB) is a compilation of production record documents and
VENDOR Data Book (VDB) is a compilation of VENDOR’s instructions for installation, operation
and maintenance cross sectional drawings as identified in the VENDOR document requirements
list (VDRL). All data books must have a Table of contents detailing all sections and total number
of pages. A separate MRB & VDB shall be supplied for each tagged item.
All pages within the MRB and VDB must be clearly marked on both front and spine with:
Manufacturing record book and VENDOR data book shall be prepared in accordance with project
procedure/specification & VDRL. All prior approved documents must show the signed
acceptance stamp of the CONTRACTOR.
The manufacturing record book and VENDOR data book shall be complete for final inspection
and submitted to the inspector prior to material dispatch. Following inspector’s acceptance, the
VENDOR shall dispatch one complete hard copy set of the manufacturing record book and
VENDOR data book with the goods and the remaining copies shall be dispatched to
CONTRACTOR.
Signed Inspection and Test Plan (ITP) shall be attached with MRB.
VENDOR shall revise and reissue immediately the certified final documents to show any agreed
concessions or corrective actions.
All native files for drawings and documents shall be submitted along with final dossier.
APPENDIX A
DATASHEETS
APPENDIX A (i)
MECHANICAL DATASHEETS
(3 Pages)
Medium Water
[kg/m3] VTC
Density (Liquid / Gas)
[cP] VTC
Viscosity (Liquid/Gas)
[kJ/kgK] VTC
Specific heat(Liquid/Gas)
Refer to Process Datasheet VTC
Compressibility
CPSF-PR-DAT-01-CP2017-004-00 VTC
Molecular Weight
[BLPD] VTC
Cp/Cv(Liquid/Gas)
[W/mK] VTC
Thermal conductivity (Liquid/Gas)
VTC
Operating temperature [°C]
Operating pressure [barg] VTC
Design temp (Max/Min) [°C] Tube side : -29/85 Shell side : 120
Design pressure [barg] Tube side :25 Shell side:5 (VTC)
Coil Bundle: Single
Coil Split: No
Coil Working Pressure [barg] VTC
Painting required Yes (CPSF-EQ-SPE-1-0594-11-00_A2)
Regulatory requirements API 12K (Note-6, 1)
Coil Connections Flanged: Yes Threaded: No
Companion Flange Bolted On (CFBO): Yes, Bore: VTC
Skid Mounted Yes
Lifting Lugs Yes
Insulation 25mm Thk, Hot Insulation (Note-7)
Shell Lifting Lugs Yes
Intake Flame Arrestor Yes
Stack Flame Arrestor Yes
Stack Spark Arrestor Yes
Stack Down Draft Diverter Yes
Stack Rain Shield Yes
Stack Gas Sample Connection Yes
Fuel Gas Scrubber Yes
Electric Spark Ignitor Yes
Pilot Flame Failure Shutdown Yes
Telltale Holes Yes
Fuel Gas Regulator Yes
Water Bath Additive Yes
Controls Yes as per Mfg. Standard
NACE MR 0175 No
ASME U stamp Yes
TBC - To Be Confirmed Later VTA - VENDOR To Advise VTC- VENDOR To confirm
CPSF-ME-DAT-01-CP2017-001-00
CLIENT: Requisition No. : CPSF-ME-SPE-01-CP2017-001-00
Project No. : CFT/45/20/1006
MECHANICAL DATASHEET Document No. :
WATER BATH HEATER PACKAGE CPSF-ME-DAT-01-CP2017-001-00
Sheet No. : 3 OF 4
Rev. No. : A1
ENG BY: CPSF-21-A-
Item Tag No. :
115/116/117/118/119
EPC FOR CPSF DEBOTTLENECKING AND CAPACITY UPGRADE PROJECT PHASE-I Water Bath Heater
Service : Package
CPSF-ME-DAT-01-CP2017-001-00
CLIENT: Requisition No. : CPSF-ME-SPE-01-CP2017-001-00
Project No. : CFT/45/20/1006
MECHANICAL DATASHEET Document No. :
WATER BATH HEATER PACKAGE CPSF-ME-DAT-01-CP2017-001-00
Sheet No. : 4 OF 4
Rev. No. : A1
ENG BY: CPSF-21-A-
Item Tag No. :
115/116/117/118/119
EPC FOR CPSF DEBOTTLENECKING AND CAPACITY UPGRADE PROJECT PHASE-I Water Bath Heater
Service : Package
General Notes:
1. Water Bath Heater Package shall comply API 12K requirements however API12 K monogram is not mandatory.
2. Refer to Technical Specificaion for Water Bath Heater (CPSF-ME-SPE-01-CP2017-001-00) for unit requirements such as scope of works,
fabrication and testing requiremets.
3. Hazardous area for the package shall be complied with Zone2, IIA, T3.
4. Refer to Technical Specification for Water Bath Heater (CPSF-ME-SPE-01-CP2017-001-00) for unit requirements such as scope of works,
fabrication and testing requiremets.
5. Vendor shall provide all utility requirements for eg. fuel gas requirement, make-up water requirement,Instrument air, Electrical
consumption, glycol and etc.
6. All valves shall be Fire safe design as per API 607
7. Water bath outer surface and chimney to be properly insulated with mineral wool or equivalent
8. Coil size of water bath heaters shall be selected for minimum velocity to prevent sand settling and wax deposition with minimum
pressure.
9. Burner Design margin shall be 15%
10. Vendor shall confirm transportation feasibility for the size of water bath heater package considering Turkmenistan location.
If necessary moudlarization possibility to be considered.
11. For sand distribution properties refer note-12.
CPSF-ME-DAT-01-CP2017-001-00
Doc. No CPSF-ME-SPE-01-CP2017-001-00
APPENDIX A (ii)
PROCESS DATASHEETS
(38 Pages)
PROCESS DATA
ADDITIONAL DATA
CORROSION ALLOWANCE mm 3
INSULATION - YES
INSULATION THICKNESS mm 25
INSULATION TYPE - H
SAND QUANTITY - (NOTE-2)
WAX CONTENT %wt 8 - 12 (NOTE-2)
WAX APPEARANCE TEMPERATURE °C 20.0 - 38.0
UTILITIES AVAILABLE
NOTES
1. VENDOR SHALL DESIGN WATER BATH HEATER PACKAGE AS PER PROCESS DATA PROVIDED ABOVE WHICH INCLUDES ALL ASSOCIATED EQUIPMENT AND
INSTRUMENTS (REFER APPENDIX A - P&ID NO.: CPSF-PR-PID-01-CP2017-014/015/016/017/018-001).
2. TABLE BELOW SHOWS THE CHARACTERISTICS OF SAND [REF.1]:
DENSITY @ 20°C : 2.053 g/cm3
WATER CONTENT : 16.50 %wt. /wt
ORGANIC MATTER (TOLUENE SOLUBLE) : 0.44 %wt/wt
INORGANIC PART : 83.06 %wt/wt
SALT CONTENT : 3 % wt./wt.
SAND QUANTITY : BASED ON LATEST COMPANY SUPPLIED DATA, SAND CONTENT SHALL BE 0.1 WT% OF TOTAL
FLOWING LIQUID (@MAXIMUM CONDITIONS) TO BE CONSIDERED IN THE DESIGN.
PARTICLE SIZE DISTRIBUTION : REFER TABLE-1
BELOW ARE THE PARTICLE SIZE DISTRIBUTION DETAILS OF TESTED SAND:
TABLE 1: SAND PROPERTIES
SIZE OF PARTICLES FOR INORGANIC PART (wt./wt.%) FOR BASE SAMPLE (wt/wt%)
d > 0.40mm 8.8 7.31
0.40 mm > d >0.30mm 1.2 1
0.30 mm > d >0. 20mm 42.3 35.13
0.20 mm > d >0.16mm 19.8 16.45
0.16 mm > d >0.10mm 25.6 21.26
0.10 mm > d >0.08mm 1.4 1.16
d < 0.08mm 0.9 0.75
TOTAL 100 83.06
NEW WATER BATH HEATERS TUBES SHALL BE ADEQUATELY SIZED TO HANDLE SAND / WAX FLOW WITHOUT BLOCKING THE TUBES WITH SOLIDS.
NOTES - CONTINUE
3. COIL SIZE OF WATER BATH HEATERS SHALL BE SELECTED FOR MINIMUM VELOCITY TO PREVENT SAND SETTING AND WAX DEPOSITION WITH MINIMUM PRESSURE
DROP.
4. ALL INSTRUMENTS, EQUIPMENT AND PIPING SHOWN INSIDE THE BATTERY LIMIT ARE TO BE SUPPLIED BY VENDOR.
5. STACK EMISSION SHALL NOT EXCEED LOCAL REGULATION [REF.2].
6. VENDOR TO PROVIDE THE PERFORMANCE GAURANTEE AS STATED IN TECHNICAL SPECIFICATION OF WATER BATH HEATER, DOC NO. CPSF-ME-SPE-01-CP2017
-0001-00 REV. A1.
7. DESIGN CAPACITY INCLUDES 10% MARGIN ON FLOWRATE. VENDOR TO ADVISE ON MINIMUM TURNDOWN FLOWRATE FOR THE PROCESS FLUID FOR EACH WATER
BATH HEATER.
8. REFER TO ATTACHED P&ID IN APPENDIX A. THE P&ID IS TYPICAL FOR ALL FIVE (5) WATER BATH HEATER PACKAGES.
9. WATER BATH OUTER SURFACE & CHIMNEY TO BE PROPERLY INSULATED WITH MINERAL WOOL OR EQUIVALENT.
10. FIRE TUBES SHALL BE REMOVABLE TYPE FOR EASY MAINTENANCE AND REPLACEMENT.
11. VENDOR TO SUPPLY LOCAL CONTROL PANEL ALONG WITH THE NECESSARY INTERFACE SIGNALS AS SHOWN IN P&ID (REFER APPENDIX A).
12. BURNER SYSTEM TO BE PROVIDED AS AN ASSEMBLY INCLUDING ALL NECESSARY ACCESSORIES LIKE, FORCED DRAFT FAN, BMS,
PILOT, FLAME ARRESTOR, FLAME OUT SENSOR, FUEL GAS CONDITIONING SYSTEM (INCLUDING BUT NOT LIMITED TO KNOCK-OUT DRUM, FILTERS, LIQUID TRAP)
AND ETC.
13. ALL PRESSURE RELIEF DEVICE DISCHARGE PIPING FOR HYDROCARBON SERVICE WITHIN THE PACKAGE SHALL BE ROUTED TO EXISTING CPSF FLARE HEADER.
VENDOR SHALL ENSURE THE RELIEF DEVICE LOCATION, ELEVATION AND ORIENTATION TO MEET THE RELIEF DEVICE DISCHARGE PIPING SLOPING
REQUIREMENTS (WITHOUT POCKET) CONSIDERING SUPERIMPOSED BACKPRESSURE WHICH WILL BE ADVISED BY COMPANY.
14. REFER APPENDIX C FOR CRUDE OIL AND EMULSION PROPERTIES [REF.1].
15. VENDOR SHALL ADVISE ON THE REQUIREMENT OF GLYCOL OR ANY ADDITIVE TO BE ADDED DURING WINTER FOR LOWERING THE FREEZING POINT OF THE
WATER.
16. REFER APPENDIX D FOR PRODUCED WATER CHARACTERISTICS [REF.1].
17. GAS MAY CONTAIN UP TO 12 ppmv H2S (INCLUDING FUEL GAS).
SKETCH (TYPICAL)
REFERENCES
ST
1. PROCESS DESIGN BASIS, CPSF-PR-DBS-01-CP2017-001-00, 21 SEPTEMBER 2022, REV. A1.
2. SAFETY DESIGN PHILOSOPHY FOR ONSHORE FACILITIES, STDS-IN-PHL-01-00002-002-00, 24TH SEPTEMBER 2018.
3. PROCESS DATA SHEET OF WATER BATH HEATER PACKAGE, CPSF-PR-DAT-01-TR1901A-003-001, 30TH JUNE 2020, REV. 1.
4. ELECTRICAL DESIGN BASIS, CPSF-EL-DBS-01-CP2017-001-00, 14TH SEPTEMBER 2022, REV. A1.
APPENDIX A
PIPING & INSTRUMENTATION DIAGRAM
WATER BATH HEATER PACKAGES
STOP
PI
TI
FROM LCP DRAIN LAL
TI PI TAH TAH
PT TE+TT VENT TI
PI
LO LSL LAL LO
TI TE+TT
TT TAH TT TAH
TSHH TAHH
01 01
FLUID INLET INSUL
TAHH LI
01 01
TO WATER
BATH HEATER
PI
CPSF-21-A-115
WATER BATH HEATER
PI
PT FROM WATER
BATH HEATER
TE+TT TE+TT TI
FIRE TUBE
FIRE TUBE x2
TAL
NOTE 5 NOTE 5
TAL
DRAIN
INSUL
INSUL
PAL PSH
INSUL
INSUL
LCP
INSUL
PI PCV PI PSL SSOV SSOV SSOV
PSH RCV
INSUL
INSUL
LO
FT-100 INSUL
PAL
PI PAH FROM TIC
LO PI PSL
AFCV
INSUL
DPT DPI MOV
LO
FROM
FUEL GAS LCP
LI KOD (V-1) INSUL (TYP) SSOV SSOV
PI PCV PI SSOV FROM FROM
LCP LCP
INSUL
ADT
INSUL
WATER BATH HEATER CPSF-21-A-116 EXPANSION TANK (NOTE 5 ) FUEL GAS KOD (NOTE 5 ) BURNER ASSEMBLY
CAPACITY : 40,000 BLPD (NOTE 5) OPERATIN GPR. : OPERATING PR. :
HEAT DUTY : (NOTE 5 )
OPERATING PR : 3 - 6.5 barg OPERATING TEMP. : OPERATING TEMP. :
OPERATING TEMP : 42° (OUTLET) DESIGN PR. : DESIGN PR. :
DESIGN PR : 25 barg DESIGN TEMP. : DESIGN TEMP. : TIME
SIZE : SIZE : FAIL TO COMMON UNIT SYNCHRONISATION
DESIGN TEMP : -29/85 ° C SHUTDOWN FROM PCS
START START STOP RUN FAULT
SIZE : (NOTE 5)
STOP
PI
TI
FROM LCP DRAIN LAL
TI PI TAH TAH
PI PT TE+TT VENT TI
LO LSL LAL LO
TI TE+TT
TT TAH TT TAH
TSHH TAHH
FLUID INLET INSUL
TAHH LI
TO WATER
BATH HEATER
PI
CPSF-21-A-116
WATER BATH HEATER
PI
PT FROM WATER
BATH HEATER
TE+TT TE+TT TI
FIRE TUBE
FIRE TUBE x2
TAL
NOTE 5 NOTE 5
TAL
DRAIN
FROM LCP
FROM LCP RCV
PSV FROM LCP SSOV
FROM
INSUL
INSUL
PAL PSH
INSUL
INSUL
LCP
INSUL
PI PCV PI PSL SSOV SSOV SSOV
PSH RCV
INSUL
INSUL
LO
FT-100
INSUL
PAL
PI PAH FROM TIC
LO PI PSL
AFCV
INSUL
DPT DPI MOV
LO
FROM
FUEL GAS LCP
LI KOD (V-1) INSUL (TYP) SSOV SSOV
PI PCV PI SSOV FROM FROM
LCP LCP
INSUL
ADT
INSUL
WATER BATH HEATER CPSF-21-A-117 EXPANSIONTANK (NOTE 5 ) FUELGASKOD (NOTE 5 ) BURNER ASSEMBLY
CAPACITY : 40,000 BLPD (NOTE 5) OPERATIN GPR. : OPERATING PR. :
HEAT DUTY : (NOTE 5 )
OPERATING PR : 3 - 6.5 barg OPERATING TEMP. : OPERATING TEMP. :
OPERATING TEMP : 42° (OUTLET) DESIGN PR. : DESIGN PR. :
DESIGN PR : 25 barg DESIGN TEMP. : DESIGN TEMP. : TIME
SIZE : SIZE : FAIL TO COMMON UNIT SYNCHRONISATION
DESIGN TEMP : -29/85 ° C SHUTDOWN FROM PCS
START START STOP RUN FAULT
SIZE : (NOTE 5)
STOP
PI
TI
FROM LCP DRAIN LAL
TI PI TAH TAH
PT TE+TT VENT TI
PI
LO LSL LAL LO
TI TE+TT
TT TAH TT TAH
TSHH TAHH
FLUID INLET INSUL
TAHH LI
TO WATER
BATH HEATER
PI
CPSF-21-A-117
WATER BATH HEATER
PI
PT FROM WATER
BATH HEATER
TE+TT TE+TT TI
FIRE TUBE
FIRE TUBE x2
TAL
NOTE 5 NOTE 5
TAL
DRAIN
INSUL
INSUL
PAL PSH
INSUL
INSUL
LCP
INSUL
PI PCV PI PSL SSOV SSOV SSOV
PSH RCV
INSUL
INSUL
LO
FT-100 INSUL
PAL
PI PAH FROM TIC
LO PI PSL
AFCV
INSUL
DPT DPI MOV
LO
FROM
FUEL GAS LCP
LI KOD (V-1) INSUL (TYP) SSOV SSOV
PI PCV PI SSOV FROM FROM
LCP LCP
INSUL
ADT
INSUL
WATER BATH HEATER CPSF-21-A-118 EXPANSIONTANK (NOTE 5 ) FUELGASKOD (NOTE 5 ) BURNER ASSEMBLY
CAPACITY : 40,000 BLPD (NOTE 5) OPERATIN GPR. : OPERATING PR. :
HEAT DUTY : (NOTE 5 )
OPERATING PR : 3 - 6.5 barg OPERATING TEMP. : OPERATING TEMP. :
OPERATING TEMP : 42° (OUTLET) DESIGN PR. : DESIGN PR. :
DESIGN PR : 25 barg DESIGN TEMP. : DESIGN TEMP. : TIME
SIZE : SIZE : FAIL TO COMMON UNIT SYNCHRONISATION
DESIGN TEMP : -29/85 ° C SHUTDOWN FROM PCS
START START STOP RUN FAULT
SIZE : (NOTE 5)
STOP
VENT
Set Pr. 25 barg
PSV MH LAL
MAKE UP
WATER
FLAME FLAME
LAL ARRESTOR ARRESTOR
STACK-1 STACK-2
EXPANSION LI
TANK LT
PI
TI
FROM LCP DRAIN LAL
TI PI TAH TAH
PT TE+TT VENT TI
PI
LO LSL LAL LO
TI TE+TT
TT TAH TT TAH
TSHH TAHH
FLUID INLET INSUL
TAHH LI
TO WATER
BATH HEATER
PI
CPSF-21-A-118
WATER BATH HEATER
PI
PT FROM WATER
BATH HEATER
TE+TT TE+TT TI
FIRE TUBE
FIRE TUBE x2
TAL
NOTE 5 NOTE 5
TAL
DRAIN
INSUL
INSUL
PAL PSH
INSUL
INSUL
LCP
INSUL
PI PCV PI PSL SSOV SSOV SSOV
PSH RCV
INSUL
INSUL
LO
FT-100 INSUL
PAL
PI PAH FROM TIC
LO PI PSL
AFCV
INSUL
DPT DPI MOV
LO
FROM
FUEL GAS LCP
LI KOD (V-1) INSUL (TYP) SSOV SSOV
PI PCV PI SSOV FROM FROM
LCP LCP
INSUL
ADT
INSUL
WATER BATH HEATER CPSF-21-A-119 EXPANSIONTANK (NOTE 5 ) FUELGASKOD (NOTE 5 ) BURNER ASSEMBLY
CAPACITY : 40,000 BLPD (NOTE 5) OPERATIN GPR. : OPERATING PR. :
HEAT DUTY : (NOTE 5 )
OPERATING PR : 3 - 6.5 barg OPERATING TEMP. : OPERATING TEMP. :
OPERATING TEMP : 42° (OUTLET) DESIGN PR. : DESIGN PR. :
DESIGN PR : 25 barg DESIGN TEMP. : DESIGN TEMP. : TIME
SIZE : SIZE : FAIL TO COMMON UNIT SYNCHRONISATION
DESIGN TEMP : -29/85 ° C SHUTDOWN FROM PCS
START START STOP RUN FAULT
SIZE : (NOTE 5)
STOP
VENT
Set Pr. 25 barg
PSV MH LAL
MAKE UP
WATER
FLAME FLAME
LAL ARRESTOR ARRESTOR
STACK-1 STACK-2
EXPANSION LI
TANK LSL
PI
TI
FROM LCP DRAIN LAL
TI PI TAH TAH
PI PT TE+TT VENT TI
LO LSL LAL LO
TI TE+TT
ESDV
TT TAH TT TAH
930
TSHH TAHH
FLUID INLET INSUL FC
FBTSO
TAHH LI
TO WATER
BATH HEATER
PI
CPSF-21-A-119
WATER BATH HEATER
PI
02 PT FROM WATER
BATH HEATER
TE+TT TE+TT TI
FIRE TUBE
FIRE TUBE X2
TAL
TAL
DRAIN
FROM LCP
Set Pr. 7 barg FROM LCP RCV
PSV FROM LCP SSOV
FROM
INSUL
INSUL
PAL PSH
INSUL
INSUL
LCP
INSUL
PI PCV PI PSL SSOV SSOV SSOV
PSH RCV
INSUL
INSUL
LO
INSUL
PAL
PI
PAH FROM TIC
PI PSL
AFCV
FROM
FUEL GAS LCP
LI KOD (V-1) INSUL (TYP) SSOV SSOV
PI PCV PI SSOV FROM FROM
LCP LCP
INSUL
ADT
INSUL
CLIENT: Requisition No : CFT/45/20/1006
Project No. : P-1042
PROCESS DATASHEET Document No. :
WATER BATH HEATER PACKAGE CPSF-PR-DAT-01-CP2017-004-00
Sheet No. : APPENDIX B
Rev. No. : A1
ENG BY: Item Tag No. : CPSF-21-A-
115/116/117/118/119
EPC FOR CPSF DEBOTTLENECKING AND CAPACITY UPGRADE PROJECT PHASE-I Service : WATER BATH HEATER
PACKAGE
APPENDIX B
FUEL GAS COMPOSITION
APPENDIX C
CRUDE OIL CHARACTERISTICS
AND EMULSION PROPERTIES
2 API - 37- 40
Page 18 /
PROCESS DESIGN BASIS Rev. A1 21.09.22
51
THIS DOCUMENT IS EXTRACTED FROM
PROCESS DESIGN BASIS REV. A1 Doc. No CPSF-PR-DBS-01-CP2017-001-00
Based on latest COMPANY supplied data, the following emulsion properties shall be considered
from two (2) sources considering conservative assumption on the emulsion viscosity considering
results of (1) SLB and (2) fresh test by CPSF Lab.
1. The following test was done by SLB (fluid was taken from inlet FTSC)
Page 19 /
PROCESS DESIGN BASIS Rev. A1 21.09.22
51
THIS DOCUMENT IS EXTRACTED FROM Doc. No CPSF-PR-DBS-01-CP2017-001-00
PROCESS DESIGN BASIS REV. A1
2. The following test was done by CPSF lab (fluid was taken from B2 riser)
Page 20 /
PROCESS DESIGN BASIS Rev. A1 21.09.22
51
THIS DOCUMENT IS EXTRACTED FROM Doc. No CPSF-PR-DBS-01-CP2017-001-00
PROCESS DESIGN BASIS REV. A1
7.3 Crude Oil Composition at Battery Limit
Page 21 /
PROCESS DESIGN BASIS Rev. A1 21.09.22
51
THIS DOCUMENT IS EXTRACTED FROM
PROCESS DESIGN BASIS REV. A1 Doc. No CPSF-PR-DBS-01-CP2017-001-00
Recombined
Flashed Gas Flashed Liquid
Component Separator Oil
mole % mole % mole %
C14 0 4.09 3.63
C15 0 3.95 3.5
C16 0 3.04 2.69
C17 0 2.81 2.49
C18 0 2.75 2.44
C19 0 2.53 2.25
C20 0 1.94 1.72
C21 0 1.72 1.53
C22 0 1.55 1.38
C23 0 1.4 1.24
C24 0 1.23 1.09
C25 0 1.11 0.98
C26 0 0.99 0.88
C27 0 0.94 0.84
C28 0 0.9 0.8
C29 0 0.85 0.76
C30 0 0.85 0.75
C31 0 0.76 0.67
C32 0 0.66 0.59
C33 0 0.53 0.47
C34 0 0.52 0.46
C35 0 0.45 0.4
C36+ 0 1.92 1.7
Total 100 100 100
Page 22 /
PROCESS DESIGN BASIS Rev. A1 21.09.22
51
THIS DOCUMENT IS EXTRACTED FROM
PROCESS DESIGN BASIS REV. A1 Doc. No CPSF-PR-DBS-01-CP2017-001-00
Page 23 /
PROCESS DESIGN BASIS Rev. A1 21.09.22
51
THIS DOCUMENT IS EXTRACTED FROM
PROCESS DESIGN BASIS REV. A1 Doc. No CPSF-PR-DBS-01-CP2017-001-00
Page 24 /
PROCESS DESIGN BASIS Rev. A1 21.09.22
51
CLIENT: Requisition No : CFT/45/20/1006
Project No. : P-1042
PROCESS DATASHEET Document No. :
WATER BATH HEATER PACKAGE CPSF-PR-DAT-01-CP2017-004-00
Sheet No. : APPENDIX D
Rev. No. : A1
ENG BY: Item Tag No. : CPSF-21-A-
115/116/117/118/119
EPC FOR CPSF DEBOTTLENECKING AND CAPACITY UPGRADE PROJECT PHASE-I Service : WATER BATH HEATER
PACKAGE
APPENDIX D
PRODUCED WATER
CHARACTERISTICS
Page 24 /
PROCESS DESIGN BASIS Rev. A1 21.09.22
51
THIS DOCUMENT IS EXTRACTED FROM
PROCESS DESIGN BASIS REV. A1 Doc. No CPSF-PR-DBS-01-CP2017-001-00
pH - 6.98
The characteristics of fuel gas are provided in the below tables (Refer Appendix B for details)
with following Operating Conditions:
Pressure: 3 – 8 Barg
Temperature: 2 – 32°C
Page 25 /
PROCESS DESIGN BASIS Rev. A1 21.09.22
51
Doc. No CPSF-ME-SPE-01-CP2017-001-00
APPENDIX B
PROJECT RELATED DOCUMENTS
(3 Pages)
Allow. Allow.
Allow. Allow. Allow. Allow.
Moments Moments
Forces (N) Forces (N) Forces (N) Moments (Nm)
Pipe ND (in) (Nm) (Nm)
Note 1. The specified maximum boundary shall apply in conjunction with design pressure, design
temperature and other applicable loads.
Note 2. Specified forces and moments shall be expected to apply in both positive and negative
direction and act simultaneously in the most conservative combination.
Note 3. All forces and moment act at flange facing.
LETTER OF COMPLIANCE
The offered equipment is in strict compliance with Material requisition, Specification and Data
Sheets without any deviations / with deviations as identified in Vendor Deviation form
……..…………………………………….
(Seal & Signature of VENDOR)
VENDOR
Paragrap Specification Exception,
No Specification No. Purchaser Decision
h No. Requirement Deviation and
Clarification
Notes:
In case of no deviations, VENDOR shall state “NO DEVIATIONS” with stamp and sign
1
below.
Deviations listed elsewhere in VENDOR’s offer shall not be considered. VENDOR shall be
2
responsible to comply at his own cost and time.
3 Offers that do not include signed and stamped Deviation List shall be liable for rejection.
AUTHORISED
VENDOR VENDOR
VENDOR NAME SIGNATORY DATE
STAMP SIGNATURE
NAME
APPENDIX C
VENDOR DOCUMENT REQUIREMENTS LIST (VDRL)
(3 Pages)
After Order
Sl. Final
No. Along First Issue
Description Issue
with Bid
Issue Date Quantity Quantity
Purpose
* Type Type
After Order
Sl. Final
No. Along First Issue
Description Issue
with Bid
Issue Date Quantity Quantity
Purpose
* Type Type
After Order
Sl. Final
No. Along First Issue
Description Issue
with Bid
Issue Date Quantity Quantity
Purpose
* Type Type
ABBREVIATION USED:
(*) - From P.O Date
W - Weeks
M - Months
C - Copy
E - Electronics (Hard Disk / Flash Drive)
APPENDIX D
INSPECTION AND TEST PLAN (ITP)
(2 Pages)
2 During Manufacturing
2.1 Check correct assignment of material and relevant certificates V H H
2.2 Shell, Flanges, Pipes Thickness V W W
2.3 Weld repairs (if any) V W W
2.4 Intermediate N.D.E V W S
2.5 External and Internal visual V W S
2.6 PWHT V W W
2.7 Final NDE V W W
2.8 Hardness Tests of Weld V W W
2 Certificates / Documents
2.1 Material Certificates to EN10204 (3.1 for Pressure Parts and 2.2 for Non V R R
Pressure Parts
2.1 NDT test certificates V R R
2.2 Certificate of Compliance with purchase order, specifications & drawings V R R
2.3 Material Traceability V R R
2.4 Manufacturer Data Book V R R
APPENDIX E
SPARE PARTS AND INTERCHANGEABILITY RECORD (SPIR) FORM
(1 Page)
Bidder’s
SL. No. Description Confirmation
(Yes/No)
1. Bidder to confirm that Scope of Supply and services has been considered as
per Specification and Material Requisition
2. Bidder to confirm that ‘List of Deviation’ has been provided in the Bid
5. Bidder to confirm that Weight Data required has been provided in the Bid
7. Bidder to confirm that List of Special tools and tackles is included in the Bid
8. Bidder to confirm that 2 years spares quoted and list furnished in the Bid
9. Bidder to furnish List of Past supply reference has been included in the Bid