Name of work :- Construction of 40.

00 mtr effective span box girder bridge over Jabothi Khad on Bahi Sulpur jahu road km 0/0 to 2/750(Sh:- construction of Sub Structure , Super Structure and
approaches )under SCSP
As per agreement As per Substitution Differences Remarks
S.No./DNIT Description of item Unit Qty. Rate Amount Description of item Unit Qty. Rate Amount (+) (-)
No.

1/3. Plain/Reinforced cement concrete in sub- Cum 146.90 9500 1395550 Plain / RCC in M-30 in substructure Cum 146.90 14405 2116139 720589
structure complete as per drawing and complete as per drawing and
Technical Specifications (using concrete Technical Specifications (using
mixer) height upto 5.0 meter including all concrete mixer) height upto 5.0 meter As per
leads , lifts of material and incidenals including all leads , lifts of material Drawing
and incidentals specifica
tion
Subsitiut
e
1395550 2116139 720589

Execitve Engineer
B&R Division ,HPPWD
Sarkaghat
Financial implication statement
Name of Work:-Construction of 40.00 mtr span PCC box girder Bridge over jabothi Khad on bahi Sulpur Jahu road km
0/0 to 2/750 (SH:- Construction of Sub structure, Super structure and approaches ) under SCSP.

Sr.No. Description
Remarks
1 Sanction cost 217.94

2 Awarded amount 189.50

3 Financial implication involved 23.03% above

4 Precentage on awarded amount 13.05% below

5 Total Amount (awarded+Financial implication i.e 2+3 233.15

Execitve Engineer
B&R Division ,HPPWD
Sarkaghat.

Financial implication statement


Name of Work:-Construction of 40.00 mtr span PCC box girder Bridge over jabothi Khad on bahi Sulpur Jahu road km
0/0 to 2/750 (SH:- Construction of Sub structure, Super structure and approaches ) under SCSP.

Sr.No. Description Remarks


1 Sanction cost 217.94

2 Awarded amount 189.50


3 Financial implication involved 23.03% above
4 Precentage on awarded amount 13.05% below

5 Total Amount (awarded+Financial implication i.e 2+3 233.15

Execitve Engineer
B&R Division ,HPPWD
Sarkaghat.
Financial Implication Statement
Name of Work:-Construction of stadium at Govt. Degree college Sarkaghat Distt. Mandi H.P.
(Sh:- Construction of boundary wall) under Deposit

Sr.No. Description
Remarks
1 Sanction cost 5000000.00 Deposit work

2 Awarded amount 2,640,950.00

3 Financial implication / Extra item involved 219,751.40

4 Precentage on awarded amount 5.92% below

5 Total Amount (awarded+Financial implication i.e 2+3 2,836,718.38

6 Total Expenditure
2,200,000

Execitve Engineer
B&R Division ,HPPWD
Sarkaghat.
DEVIATION STATEMENT

1 Name of Work :- Landscaping and beautification of old bus stand Sarkaghat, Dist.
Mandi (H.P.)

2 Name of Contractor :- Shri Surender Kumar, Govt. Contractor

3 Agreement No. 632 for the year 202-21

4 A/A & E/S amount revised, if any 2135175/-

5 Awarded amount Rs.27,58,386/- only


6 Date of Award No:-PW-SKT-CB-EA I- award/Tender/2020- 22025-35dated 03-03-
2021.
7 Stipulated time 4 Months.
8 Stipulated date of completion 8/14/2021
9 Actual date of completion 09-02-2022.
10 Extension of time i) 14-04-2022 to 09-02-2022.

LIABILITY
(a) Gross amount of Bill paid to contractor in Last Rs. 8,96,754/-
R/Bill :-

(b) Gross amount of Final bill :- Rs.20,07,268/-

( c) Gross amount yet payable to Contractor :- Rs.11,10,514/-

Budgetary Provision :-
Budget for currrent financial year

or
1 Amount of balance deposit available with
department

(C) Necessary Certificate :-


(i) The nature of the work is such that it is not
possible to get the extra quantity executed -
through any other agency.

(ii) The rate of the Contractor was comparable with


the prevailing market rate at the time of
-
execution.

(iii) There is no other agency to execute the extra


quantity at the rate lower than the agreement
rate. -

(iv) The present contractor is not willing to execute


the quantity at rates lower than the agreement -
rate.

(v) Aftr deviation in executing this quantity the


position of the lower tender remain un-changed. -
(vi) The actual quantity is not more than the quantity
-
contained in the statement.
(vii) The quantity depicted in the deviation is as per
-
MB's.
8 Completion Certificate :- Certified that the work has been completed on 09-02-2022.

EXTRA ITEMS & SUBSTITUTE ITEMS :


Extra Items Substitute items
No. Amount No. Amount
-

Executive Engineer
B&R Division, HPPWD
Sarkaghat