Compliance
Monitoring Report
(CMR)
•CMR: Rule No. 1
CMR is a documentary
requirement prepared by the
proponent to report
performance/ compliance.
•CMR: 3 Level-Reporting
a. Performance against ECC conditions;
b. Performance against the EMP; and
c. Performance against the monitoring of
actual impacts (including residual
impacts) as against predicted impacts in
the EIA Report and as related to current
project operations.
•CMR: Overview of CMR
I. Basic Project Information and Updates
•CMR: Overview of CMR
II. Executive Summary
•CMR: Overview of CMR
III. Results and Discussion
•CMR: Overview of CMR
III. Results and Discussion
•CMR: Overview of CMR
III. Results and Discussion
•CMR: Overview of CMR
III. Results and Discussion
•CMR: Overview of CMR
III. Results and Discussion
•CMR: Overview of CMR
III. Results and Discussion
•CMR: Overview of CMR
III. Results and Discussion
•CMR: Overview of CMR
III. Results and Discussion
•CMR: Overview of CMR
IV. Conclusions & Recommendations
•CMR: Overview of CMR
IV. Conclusions & Recommendations
STEPS ON
CMR ONLINE
SUBMISSION
•CMR: Website Access
Access the website: online.emb.gov.ph/cmr
Click ‘Continue’ to load the login/sign up page.
•CMR: Login Page
Input Username and Password:
• CMR: Account Registration/ Sign Up Page
If not yet registered:
• CMR: Account Registration/ Sign Up Page
Provide Business Information and User Information:
Remember: Don’t leave any blank. Input “Not Applicable” if it does not apply to your
establishment.
• CMR: Account Registration/ Sign Up Page
Attachments: 2 Government IDs, SEC/ DTI Registration, Authorization
Letter (with Downloadable Format click here)
Remember: Always attached a PDF File of the said documents to be attached.
Upload one at a time per row and wait till the label on the
first column turns blue.
• CMR: Log/Sign Out & Password Recovery
• Draft Compliance Monitoring Report (Page 1)
In the course of invalid ECC, click the link here provided on the prompt
message.
Remember:
Don’t leave
any blank,
input Not
Applicable,
if it does not
apply.
• Draft Compliance Monitoring Report (Page 2)
I. Basic Information:
A. Project Area Coordinates
Step 1: Select Project Area and input minimum 4 Geo Coordinates then click Save
button. Saving must be done per row.
Step 2: Select only Project Area 1 if you only have a single project area.
Step 3: To delete, click Trash Bin button.
• Draft Compliance Monitoring Report (Page 2)
I. Basic Information:
B. Project Buffer Zone Coordinates
Step 1: Select Buffer Zone and input minimum 2 Geo Coordinates then click Save
button. Saving must be done per row.
Step 2: Select only Buffer Zone 1 if you only have a single buffer zone area.
Step 3: To delete, click Trash Bin button.
• Draft Compliance Monitoring Report (Page 2)
I. Basic Information:
II. C. Carbon Sink/ GHG Program Area Coordinates
Step 1: Select Pogram Area and input minimum 2 Geo Coordinates then click Save
button. Saving must be done per row.
Step 2: Select only Program Area 1 if you only have a single program area.
Step 3: To delete, click Trash Bin button.
Step 4: Click on Next button to proceed.
Remember: **Project Area Coordinates is required by the system to proceed on the next page. If letters B and C is not
applicable to your firm leave as is and don’t input any but make sure the Project Area Coordinates has an input to avoid
receiving error. **
• Draft Compliance Monitoring Report (Page 3)
II. Executive Summary: A. Summary of Major Findings for the Monitoring Period.
Step 1: Provide information re: Compliance Status to ECC Conditions, EMP
Commitments, Implementation of appropriate & effective env’tal impact remedial
actions in case of exceedances, Complaints Management, Realistic and sufficient
budget for conducting the environmental monitoring and audit activities and
Accountability. Saving must be done per condition.
• Draft Compliance Monitoring Report (Page 4)
III. Results & Discussions:
A. Compliance Monitoring
Project Description
Step 1: Fill up Project Description (based on the issued ECC), choose Yes or No
under Compliant and fill up Remarks, then click Save button.
Saving must be done per condition.
• Draft Compliance Monitoring Report (Page 4)
III. Results & Discussions:
A. Compliance Monitoring
ECC Conditions
Step 1: Input all ECC Conditions stipulated in the issued ECC, choose Yes or No
under Compliant and fill up Remarks, then click Save button.
Saving must be done per condition.
Step 2: Always fill up Condition No. corresponding to the Description.
• Draft Compliance Monitoring Report (Page 4)
III. Results & Discussions:
A. Compliance Monitoring
EMP Commitments
Step 1: Input all EMP Commitments stipulated in the issued ECC/ Submitted
Documents, choose Yes or No under Compliant and fill up Remarks, then click
Save button.
Saving must be done per condition.
Step 2: Always fill up Impacts corresponding to the Mitigating Measures.
• Draft Compliance Monitoring Report (Page 4)
III. Results & Discussions:
A. Compliance Monitoring
Annex B of ECC
Step 1: Fill up Requirements with corresponding Description, choose Yes or No
under Compliant and fill up Remarks, then click Save button.
Saving must be done per condition.
• Draft Compliance Monitoring Report (Page 4)
III. Results & Discussions:
A. Compliance Monitoring
Social Development Plan
Step 1: Fill up Requirements with corresponding Description, choose Yes or No
under Compliant and fill up Remarks, then click Save button.
Saving must be done per condition.
• Draft Compliance Monitoring Report (Page 4)
III. Results & Discussions:
A. Compliance Monitoring
Information Education Communication (IEC)
Step 1: Fill up Requirements with corresponding Description, choose Yes or No
under Compliant and fill up Remarks, then click Save button.
Saving must be done per condition.
• Draft Compliance Monitoring Report (Page 4)
III. Results & Discussions:
A. Compliance Monitoring
Contingency/ Emergency Response Plan or Equivalent Risk Management Plan
Step 1: Fill up Requirements with corresponding Description, choose Yes or No
under Compliant and fill up Remarks, then click Save button.
Saving must be done per condition.
Remember:
If there were no actions made or a condition has not been applicable for the Monitoring Period
input ‘Not Applicable’ or state the reason why. Leave no blanks.
Attaching files: Files should be in PDF version, attach file then click save button.
Click Next button to proceed to the next page.
• Draft Compliance Monitoring Report (Page 5)
III. Results & Discussions:
B. Impact Monitoring
Step 1: Fill up Findings/Issues, Recommendations and Action Plan.
Step 2: If there were no actions made or a condition has not been applicable for the Monitoring
Period input ‘Not Applicable’, and Click save. Saving must be done per condition.
Step 3: Click Next button to proceed to the next page.
• Draft Compliance Monitoring Report (Page 6)
III. Results & Discussions:
B. Impact Monitoring
Current Monitoring Results and Findings (Water Quality)
Step 1: Fill up letter A before proceeding to letter B. Same with letters C and D.
Step 2: Click save button. Saving must be done per row.
• Draft Compliance Monitoring Report (Page 6)
III. Results & Discussions:
B. Impact Monitoring
Current Monitoring Results and Findings (Water Quality)
Step 3: If the above letters (A,B,C, & D) does not apply, leave as is don’t input any and proceed
to the ‘Over all Remarks on Water Quality Monitoring’. Fill out the box with corresponding
remarks.
Step 4: Click Next button to proceed to the next page.
• Draft Compliance Monitoring Report (Page 7)
III. Results & Discussions:
B. Impact Monitoring
Current Monitoring Results and Findings (Air Quality)
Step 1: Fill up letter A before proceeding to letter B. Same with letters C and D.
Step 2: Click save button. Saving must be done per row.
• Draft Compliance Monitoring Report (Page 7)
III. Results & Discussions:
B. Impact Monitoring
Current Monitoring Results and Findings (Air Quality)
Step 3: If the above letters (A,B,C, & D) does not apply, leave as is don’t input any and proceed
to the ‘Over all Remarks on Water Quality Monitoring’. Fill out the box with corresponding
remarks.
Note: The corresponding link provided will expire within 5 days. Click on the link and input the ‘One-
time-Password’ provided and click
‘GO’ to proceed.
• Draft Compliance Monitoring Report (Page 11)
After reviewing, click on ‘Approve and Submit to EMB’. If found insufficient or with missing data
click on ‘Disapprove and Return’.