Generic Initial Environmental Examination (IEE) Checklist Report Form

Monitoring Parameters/
Possible Preventive/ Mitigating Measures

 Cost of preventive/mitigating as well as monitoring integrated in the construction /operation


Implementation
Environmental/Social Baseline Environment Remarks
Impacts
cost

 
LAND
Consistency with land Current land use w/in 1km See attached proof of compatibility OK


use radius (as per zoning with land use


ordinance):
Limit project activities to what is

 
✔ Residential compatible to the land use



Commercial/ Institutional Others, specify


Industrial NA



Agricultural/ Recreational


Protected Areas
Others, specify
NA

Actual land uses w/in 1km


radius:


✔ Residential



Commercial/ Institutional


Industrial


✔ Agricultural/ Recreational


Protected Areas
Others, specify
NA

Project Name: ___________________________________________ Page 1 of 14


Generic Initial Environmental Examination (IEE) Checklist Report Form

Monitoring Parameters/
Possible Preventive/ Mitigating Measures

 Cost of preventive/mitigating as well as monitoring integrated in the construction /operation


Implementation
Environmental/Social Baseline Environment Remarks
Impacts

  
cost

Land tenure / Identify land tenure/ Obtain the following clearances/ Regularly monitor OK


compatibility issue compatibility issues: permits from concerned agencies: presence/absence of


complaints



CARP NA
Regular coordination with LGU
CADC/ CADT/ CALC/


or appropriate agencies


CALT


Others, specify


ROW


NA
Resettlement Plan prepared


Informal settlers
Provide relocation/disturbance
Ecologically sensitive or


compensation packages


protected area
Ensure participation of IPs in
Others, specify


consultations and dialogues
NA



MOA prepared/signed


Provide adequate buffer
Others, specify
NA



Disturbance to wildlife Existing vegetation in the  Comply with conditions of  Annual inspection of area OK

 
due to vegetation area: DENR/LGU SLUP, Tree Cutting replanted/ re-vegetated

 
clearing Forestland Permit, ROW, PCA Permit Others, specify


Marshland Limit land clearing as much as NA


possible



Grassland
Provide temporary fencing for


Mangrove

vegetation that will be retained


Wetland Promote restoration of damaged or
Others, specify destroyed vegetation where possible


(e.g., tree planting)
Others, specify

Project Name: ___________________________________________ Page 2 of 14


Generic Initial Environmental Examination (IEE) Checklist Report Form

Monitoring Parameters/
Possible Preventive/ Mitigating Measures

 Cost of preventive/mitigating as well as monitoring integrated in the construction /operation


Implementation
Environmental/Social Baseline Environment Remarks
Impacts
cost

NA NA OK

 


Change in surface Slope: Considering the natural hazards and ✔
Regular inspection of slope OK

 
landform/ topography/ ✔
Flat (0-3%) climate projections in the area: protection measures in

 
terrain/slope Gently sloping to rolling

Employ appropriate erosion control erosion-prone areas

 
Soil Erosion (3-18%) and slope protection measures ✔
Regular inspection for new


Steep (>18%)

Designate a spoils storage area, eroded areas near the site
with topsoil set aside for later use Others, specify


Is the project site located in an and allow maximum re-use of spoils
NA


area identified by MGB/PAG- Construct during dry season
ASA/ PHIVOLCS as hazard Stabilize embankment with grasses

 
prone? or other soil cover


Yes ✔
Conduct Engineering Geological and

No Geo-hazard Assessment (EGGA)
and implement corresponding


recommendation
Others, specify
NA

Building of structure and Solid Waste Management  Implement recovery re-use and  Daily inspection of waste OK

 SLF 
improper solid waste Scheme in the area: recycling of waste materials handling including segregation

  MRF 
disposal leading to: in waste/recycling bins
Provide receptacles / bins for solid


Impairment of visual

 Composting

✔ wastes Weekly inspection of waste

 Devaluation of land 
aesthetics

 Regular Collection of Solid 


Composting of Organic Wastes accumulation and disposal
Coordinate with the municipal / city Regular inspection of
values ✔


waste collectors landscaping and other
Wastes
beautification activities
Implement landscaping and other
Project Name: ___________________________________________ Page 3 of 14
Generic Initial Environmental Examination (IEE) Checklist Report Form

Monitoring Parameters/
Possible Preventive/ Mitigating Measures

 Cost of preventive/mitigating as well as monitoring integrated in the construction /operation


Implementation
Environmental/Social Baseline Environment Remarks
Impacts


cost


Presence of visually beautification measures Regular monitoring of buffer OK


significant

Provide adequate buffer zones
landforms/landscape/structure


s?

Compensate adjacent property Regular monitoring for


owners presence/absence of



Yes complaints from adjacent
Others, please specify


No property owners
NA
Others, specify
NA

 Soil/Land contamination Existing soil/land type in the ✔


Secondary containment (pls specify) ✔
Regular inspection for leakage OK

 
due to materials leakage expansion area: of materials that can cause
GRAVEL, SAND AND BOULDERS

 
Depletion of soil nutrient sandy land/soil contamination.


content/soil clay ✔
Monitoring of soil physical and


productivity/Change in chemical properties



sandy-loam
acidity/alkalinity of soil


concrete/cement Engage third party company for


Others, specify waste collection
Others, specify


Soil acidity/alkalinity
NA


acidic

basic
Conduct of soil test/analysis
for the following parameters
relevant to the potential
source of contamination:
WATER

Project Name: ___________________________________________ Page 4 of 14


Generic Initial Environmental Examination (IEE) Checklist Report Form

Monitoring Parameters/
Possible Preventive/ Mitigating Measures

 Cost of preventive/mitigating as well as monitoring integrated in the construction /operation


Implementation
Environmental/Social Baseline Environment Remarks
Impacts

 
cost


Increased siltation due to Specify nearest/receiving Set up proper and adequate sanitary Regular (ocular) inspection of: OK

  
project activities water body facilities ✔
Drainage / canal systems
SURFACE WATER (RIVER BED)
Water quality Ensure strict observance of proper ✔
Wastewater treatment facility


degradation waste handling and disposal and (i.e., grease trap, septic tank,
proper sanitation including by the etc.)
Others, specify


contractors and its workers (if any)
Provide wastewater treatment facility Monitoring of ambient water for
(e.g., septic tank, oil and water the following:


Distance to nearest/receiving separator, etc.)

  pH  Annual
water body: Parameter Frequency
Set up silt trap/stilling ponds to

   Semi-annual
0 to less than 0.5 km minimize downstream siltation ✔

  Quarterly
0.5 to 1 km ✔
Provide three-chambered septic ✔

  TSS  Annual
tank for domestic sewage

More than 1 km

 Semi-annual

Provide ring canals around fuelling ✔

Classification of nearest water tanks/ motorpool/ maintenance

 Quarterly
concentration



areas

 Freshwater  Marine/
body:

 BOD  Annual
Others, specify

 Semi-annual

 AA 
NA
coastal water

 Quarterly

A 
✔ ✔ SA

 Color  Annual
B   Semi-annual
SB ✔

C   Quarterly
SC ✔

D  Oil and  Annual


SD

 Semi-annual

 Quarterly
Grease ✔

 Fishery  Total Coliform  Annual


Current Water Use:

 Tourist Zone / Park  Semi-annual


 Recreational  Quarterly

 Industrial

 Agricultural

 Others, specify:

Project Name: ___________________________________________ Page 5 of 14


Generic Initial Environmental Examination (IEE) Checklist Report Form

Monitoring Parameters/
Possible Preventive/ Mitigating Measures

 Cost of preventive/mitigating as well as monitoring integrated in the construction /operation


Implementation
Environmental/Social Baseline Environment Remarks
Impacts

 Heavy  Annual
cost

 Semi-annual

NA OK

 Quarterly
metals: ✔

 Others:  Annual
 Semi-annual

 Quarterly

Distance of project area to the


nearest well used:


0 to less than 0.5 km


0.5 to 1 km
✔ More than 1 km


Use of the nearest well:


Drinking/Domestic



Industrial



Agricultural
Others:
NA

  

Competition in water use Size of population using the ✔
Implement rainwater harvesting and Regular monitoring for OK
source/s of water for the similar measures as an alternative presence/absence of


Depletion of water

 
project: source of water complaints
resources



≤ 1,000 persons ✔
Observe water conservation Regular coordination with

 
>1,000 and ≤ 5,000 measures; concerned agencies


persons ✔
Carefully select project site to avoid Regular monitoring for


>5,000 persons disruption of traditional water uses occurrences of water


shortages


Obtain Water Permit from NWRB
Available/nearest water Others, specify


source. Improve efficiency of water supply
and distribution system

Deepwell

Project Name: ___________________________________________ Page 6 of 14


Generic Initial Environmental Examination (IEE) Checklist Report Form

Monitoring Parameters/
Possible Preventive/ Mitigating Measures

 Cost of preventive/mitigating as well as monitoring integrated in the construction /operation


Implementation
Environmental/Social Baseline Environment Remarks
Impacts

 
cost



Water district/LGU Increase storage capacities of water NA
OK (SURFACE WATER)



Surface water supply structures for resilience to
greater climate variations and


Others, specify extremes
SURFACE WATER (RIVER BED) Others, specify
NA

 Increased occurrence of Is the project site located in an


area identified by MGB/PAG-
✔
Use appropriate design for project  Regular monitoring for OK
flooding facilities including appropriate presence/absence of

 
ASA as flood prone? drainage mechanism considering complaints

 
Yes the existing local drainage system. Regular coordination with



No ✔
Regularly remove debris and other concerned agencies
materials that may obstruct water Regular monitoring for

 
flow increased frequency of flooding
Use appropriate technology (e.g., Others, specify
raised hand-pumps) to protect NA
drinking water from flood


contamination
Others, specify
NA

AIR / NOISE

Project Name: ___________________________________________ Page 7 of 14


Generic Initial Environmental Examination (IEE) Checklist Report Form

Monitoring Parameters/
Possible Preventive/ Mitigating Measures

 Cost of preventive/mitigating as well as monitoring integrated in the construction /operation


Implementation
Environmental/Social Baseline Environment Remarks
Impacts

 Impact on air quality  


cost

 Nuisance due to
Distance to nearest ✔
Properly operate and maintain all Regular monitoring for


OK
community: emission sources (e.g., vehicles, presence/absence of

 
generation of obnoxious/ 0 to less than 0.5 km pumps, generator, etc.) complaints

 Absence of white or black


Regular (ocular) inspection of:


unpleasant odor 0.5 to 1 km ✔
Install appropriate air pollution



More than 1 km control device/s
smoke from vehicles, heavy

Strictly enforce good housekeeping

 Presence of truck cover during


equipment and generator


Is the wind direction blowing practices
towards the nearest Control vehicle speed to lessen


deliveries


community most of the year? suspension of road dust
Monitoring of ambient air for the


Yes Conduct water spraying to suppress following:
✔ No dust sources and minimize

  PM10  Annual
discomfort to nearby residents Parameter Frequency

 Semi-annual

Use covered vehicles to deliver ✔


materials that may generate dust

 Quarterly

Others, specify

 TSP  Annual
 Semi-annual

 Quarterly

 NO2  Annual
 Semi-annual

 Quarterly

 SO2  Annual
 Semi-annual

 Quarterly

 Trace  Annual
 Semi-annual

 Quarterly
metals: ✔

 Others:  Annual
 Semi-annual

Project Name: ___________________________________________ Page 8 of 14


Generic Initial Environmental Examination (IEE) Checklist Report Form

Monitoring Parameters/
Possible Preventive/ Mitigating Measures

 Cost of preventive/mitigating as well as monitoring integrated in the construction /operation


Implementation
Environmental/Social Baseline Environment Remarks
Impacts


cost

Quarterly OK

 Nuisance due to noise Distance to nearest ✔


Properly operate and maintain all  Regularly monitor


OK
generation community: noise sources (e.g. vehicles, pumps, presence/absence of

  
0 to less than 0.5 km generator, etc) complaints


0.5 to 1 km Install appropriate noise control ✔
Regular monitoring of buffer


device/s (e.g., mufflers, silencer, zones

More than 1 km


sound barriers, etc.) Quarterly monitoring of noise



Implement appropriate operating level


hours Others, specify
Provide adequate buffer and/or NA


planting of trees
Others, specify
NA

PEOPLE

 Displacement of residents Size of population of host  Provide relocation/disturbance  Regular monitoring for OK

including indigenous barangay/s: compensation packages presence/absence of


Project Name: ___________________________________________ Page 9 of 14
Generic Initial Environmental Examination (IEE) Checklist Report Form

Monitoring Parameters/
Possible Preventive/ Mitigating Measures

 Cost of preventive/mitigating as well as monitoring integrated in the construction /operation


Implementation
Environmental/Social Baseline Environment Remarks
Impacts

 
cost

 
people in the project site ≤ 1,000 persons Prioritize local residents for complaints

 Enhanced employment
OK

 
and within its vicinity employment Regular coordination with LGU
>1,000 and ≤



5,000persons Promptly pay local taxes and other Others, specify


and/or livelihood financial obligations

 Reduced employment 
opportunities

>5,000person NA


Regular coordination with LGU

Indigenous People Size:
Conduct prior consultation and
and/or livelihood 500
coordination to minimize disruption

 Increased revenues for


opportunities


of daily domestic activities

Ensure participation of IPs in

 Disruption/Competition in
LGU
consultations and dialogues &
consider IP rights and cultural
delivery of public services Classification of host practices in the provision of


(e.g., education, peace barangay: relocation/disturbance compensation

  
and order, etc.) Urban packages

Enhanced delivery of ✔
Rural Provide appropriate traffic/warning


public services (e.g., signs, lighting, etc
education, peace and Employment/Livelihood Others, specify


order, etc.) Opportunity Rate in the host NA


Increase in traffic volume Municipality:


and worsening of traffic ✔ High
flow
Low
Description:
NA

Available services within/near

 Schools (e.g. elementary,


the host barangay:

 Health facilities (e.g.,


high school, college)

clinics, hospitals, etc.)


Project Name: ___________________________________________ Page 10 of 14
Generic Initial Environmental Examination (IEE) Checklist Report Form

Monitoring Parameters/
Possible Preventive/ Mitigating Measures

 Cost of preventive/mitigating as well as monitoring integrated in the construction /operation


Implementation
Environmental/Social Baseline Environment Remarks
Impacts

 Peace and order (e.g.,


cost

OK
police outpost, Brgy.

 Recreation and sports


Tanod, etc.)

 Others, specify
facilities

NA

  

Impacts on community Source of risks (please Regular coordination with LGU Regular monitoring for


OK
health and safety specify) presence/absence of

Provide appropriate warning signs,

 Regular monitoring of buffer



Explosives : lighting and barricades, whenever complaints

 
Safety Risks NA practicable

  
Fire Observe proper housekeeping zones

 
Explosion ✔
Provide on-site medical services for Regular coordination with LGU


Release of toxic any emergency. Regular submission of reports

  
materials to concerned agency

Participate in public awareness


Structural failure ✔
Flammable substances: programs on health and safety Others, specify
NA ✔
Implement appropriate safety NA
programs for both community and


workers
Strictly comply with fire, safety and


similar regulatory requirements

✔
Toxic substances:
Strictly comply with requirements of


RA 6969
NA
Others, specify
NA

 Others, specify

Project Name: ___________________________________________ Page 11 of 14


Generic Initial Environmental Examination (IEE) Checklist Report Form

Monitoring Parameters/
Possible Preventive/ Mitigating Measures

 Cost of preventive/mitigating as well as monitoring integrated in the construction /operation


Implementation
Environmental/Social Baseline Environment Remarks
Impacts
cost
SURFACE WATER (RIVER BED) OK

Project Name: ___________________________________________ Page 12 of 14