Professional Documents
Culture Documents
Activity: Project Environmental Risk Assessment Assessment Purpose: (Preparation/Supplementary to method statement/following incident, etc.)
Preparation
Cause of
People/ Adverse Effect / Type
L1 S1 Ctrl L2 S2 Legal and Other
Job / Task Environment/ Adverse Effect / of Environmental RFN ** Mitigating Controls RRN * Assessment
Type Requirements Reference
Property at Risk Impact
Environmental Aspect
EL -
S -
EL No Burning of vegetation
S -
All workers,
Low, temporary,
Local Increased emissions
Vegetation E Composting/use by local community where possible, reversible and
Community, Vegetation Burning of hydrocarbons, CO2 2 2 4 1 2 2 EPA 1986, rule 14
Clearance residual impact is
Local and particulate
neutral.
Environment.
A -
P -
EL -
S -
EL -
Activity: Project Environmental Risk Assessment Assessment Purpose: (Preparation/Supplementary to method statement/following incident, etc.)
Preparation
Cause of
People/ Adverse Effect / Type
L1 S1 Ctrl L2 S2 Legal and Other
Job / Task Environment/ Adverse Effect / of Environmental RFN ** Mitigating Controls RRN * Assessment
Type Requirements Reference
Property at Risk Impact
Environmental Aspect
S
Installation of Bag filters/ESP/Catalic reactor and for
dust or emission control device.
Use of silo for cement feeding.
Enclosure of cement, aggregates and sand feeding
conveyors.
Construction of wind walls across the aggregate and
E sand bins.
Local Development of green belt around the batching plant. The Air Prevention and control of
Batching plant Increased SPM and Low & Temporary
Community, Increased dust from batching plant. 3 3 9 2 2 4 Pollution) Act 1981 & Rules 1983 -
operation RSPM Impact
and all workers. Screening to be used against as per wind direction S.21/ R.9
EL -
S -
Provision of dust screen for every floor and sprinkling
E
High rise Local provision The Air Prevention and control of
Increased SPM and Low & Temporary
construction Community, Dust Emission 3 2 6 2 2 4 Pollution) Act 1981 & Rules 1983 -
RSPM Impact
activities. and all workers. A Good housekeeping. S.21/ R.9
EL -
S -
Enclosure of the area where possible.
E
Demolition & Local Water sprinkling and alternate working schedule The Air Prevention and control of
Increased SPM and Low & Temporary
Breaking Community, Dust Emission 3 2 6 2 2 4 Pollution) Act 1981 & Rules 1983 -
RSPM Impact
activities and all workers. S.21/ R.9
A Good housekeeping.
Activity: Project Environmental Risk Assessment Assessment Purpose: (Preparation/Supplementary to method statement/following incident, etc.)
Preparation
Cause of
People/ Adverse Effect / Type
L1 S1 Ctrl L2 S2 Legal and Other
Job / Task Environment/ Adverse Effect / of Environmental RFN ** Mitigating Controls RRN * Assessment
Type Requirements Reference
Property at Risk Impact
Environmental Aspect
EL
S -
P -
Soil & Ground Water- Environmental Aspects and Impacts.
EL -
S -
Damage to soil quality
Building Local Compacting of soil from increased or encourage water E Construction of ditches if required. And Stabilization Low & Temporary
2 2 4 1 2 2 -
foundations. Environment heavy weight traffic on track logging in susceptible Impact
areas. A -
P -
Activity: Project Environmental Risk Assessment Assessment Purpose: (Preparation/Supplementary to method statement/following incident, etc.)
Preparation
Cause of
People/ Adverse Effect / Type
L1 S1 Ctrl L2 S2 Legal and Other
Job / Task Environment/ Adverse Effect / of Environmental RFN ** Mitigating Controls RRN * Assessment
Type Requirements Reference
Property at Risk Impact
Environmental Aspect
EL -
S -
Building
foundations and
other Soil and crop Restrict working width to safe minimum, excavations
Local Clearing topsoil along foundation should be backfilled with original soil wherever Low & Temporary
foundations for disturbance, exposure 3 2 6 E 2 2 4 -
Environment excavation possible and compacted to ensure sinking does not Impact
batching plant to erosion
and debagging occur later.
unit.
A -
P -
EL -
S -
Building Local foundation excavation, grading, Erosion & Implement drainage and erosion control measures, Low & Temporary
3 2 6 E 2 2 4 -
foundations Environment backfilling sedimentation Stabilization Impact
A -
P -
EL -
Soil and groundwater S Reuse former trench materials where possible
Local
Excavation disturbance, E Use minimum quantities possible,
Environment, Extraction of soil for backfilling 3 3 9 2 2 4 - -
Backfilling landscape and
Ground water A Use only legitimate quarry source,
topology change
P -
EL -
S -
Soil and ground water
contamination by All welding buds must be collected and disposed off
Fabrication and Local Disposal of welding buds, metal E
lead, & heavy metals 2 3 6 safely. 2 2 4 - -
other activities Environment, scraps.
in soil and ground
water. Sell or reuse as scrap metal with limited use e.g.
A
construction.
P -
Activity: Project Environmental Risk Assessment Assessment Purpose: (Preparation/Supplementary to method statement/following incident, etc.)
Preparation
Cause of
People/ Adverse Effect / Type
L1 S1 Ctrl L2 S2 Legal and Other
Job / Task Environment/ Adverse Effect / of Environmental RFN ** Mitigating Controls RRN * Assessment
Type Requirements Reference
Property at Risk Impact
Environmental Aspect
No excessive storage of fuel and chemical more than
EL
prescribed limit.
S -
P -
Surface Water- Environmental Aspects and Impacts.
EL -
S -
Interruption of surface
Civil Local water and Drainage and erosion control measures, Reconstruct
E Low, negative,
construction Environment, Clearing & Excavation groundwater, 3 3 9 the drains, reconstruction of the road banks, 2 2 4 -
temporary
works (Soil & Water) particularly swamp
area and road drains
A Work should be done within contract period.
P -
Terrestrial Construction - Environmental Aspects and Impacts.
EL -
S Only required vegetation to be removed.
Construction Local Vegetation removal and clearance
Vegetation Clearance 2 3 6 E - 2 2 4 Low -
Activity Environment along the foundation route.
A -
P -
Activity: Project Environmental Risk Assessment Assessment Purpose: (Preparation/Supplementary to method statement/following incident, etc.)
Preparation
Cause of
People/ Adverse Effect / Type
L1 S1 Ctrl L2 S2 Legal and Other
Job / Task Environment/ Adverse Effect / of Environmental RFN ** Mitigating Controls RRN * Assessment
Type Requirements Reference
Property at Risk Impact
Environmental Aspect
P -
Material Consumption - Environmental Aspects and Impacts.
EL -
Use of pre mixed concrete curing agents to reduces
S
water consumption.
P -
EL -
P -
Activity: Project Environmental Risk Assessment Assessment Purpose: (Preparation/Supplementary to method statement/following incident, etc.)
Preparation
Cause of
People/ Adverse Effect / Type
L1 S1 Ctrl L2 S2 Legal and Other
Job / Task Environment/ Adverse Effect / of Environmental RFN ** Mitigating Controls RRN * Assessment
Type Requirements Reference
Property at Risk Impact
Environmental Aspect
EL -
Use of fly ash in the design mix to reduce the
S
consumption of cement.
Consumption of Increased mining Low and temporary Fly ash Notification September
Environment. Excessive consumption of cement 2 2 4 E Monitoring with plant Efficiency consumption rate 1 2 2
Cement activities impact 1999.
A -
P -
EL -
S -
EL -
S -
P -
Activity: Project Environmental Risk Assessment Assessment Purpose: (Preparation/Supplementary to method statement/following incident, etc.)
Preparation
Cause of
People/ Adverse Effect / Type
L1 S1 Ctrl L2 S2 Legal and Other
Job / Task Environment/ Adverse Effect / of Environmental RFN ** Mitigating Controls RRN * Assessment
Type Requirements Reference
Property at Risk Impact
Environmental Aspect
EL -
S -
P -
EL -
S -
Hazardous
waste / Hazardous waste must be collected and stored in Hazardous waste management
Improper handling or management of Impact on local E Low and temporary
Biomedical Environment. 2 3 6 designated, weather protect areas. With MSDS 1 3 3 handling and trans boundary act-
waste community impact
Waste / 2010
Electronic waste To be disposed off only to authorised, licensed
A
agency only.
P -
EL
EL -
Activity: Project Environmental Risk Assessment Assessment Purpose: (Preparation/Supplementary to method statement/following incident, etc.)
Preparation
Cause of
People/ Adverse Effect / Type
L1 S1 Ctrl L2 S2 Legal and Other
Job / Task Environment/ Adverse Effect / of Environmental RFN ** Mitigating Controls RRN * Assessment
Type Requirements Reference
Property at Risk Impact
Environmental Aspect
S -
P -
EL
S
NGT
Order/Supreme E
court order In Project Obtaining necessary legal permits Impact on project 1 2 2 To liaise with client. NGT Act-2010
dated
17.04.2015 All applicable legal requirements to be identified and
A
necessary Obligation to be obtained and complied.
Prepared By: Niladri S Mitra Reviewed By: Shaik Khadarvali Approved By: Richard Squire
Frequency Severity Risk Factor Number (RFN) Residual Risk Number (RRN) * Prepare Job Safety Analysis and Safety Verification
1: Unlikely/Improbable 1: Negligible 1-2: Trivial/Acceptable 1-2: Trivial/Acceptable Checklist when RRN is > 6
2: Remote 2: Slight 3-5: Tolerable 3-5: Tolerable ** Prepare Safety Verification Checklist when RFN is > 6.
3: Quite Possible/Occasional 3: Moderate 6-9: Moderate/Acceptable with Review 6-9: Moderate/Acceptable with Review L1 Likelihood as is
4: Likely/Probable 4: Critical/High 10-15: Substantial 10-15: Substantial L2 Likelihood with mitigating controls in place
5: Very Likely/Frequent 5: Catastrophic/Very High 16-25: Intolerable/Unacceptable 16-25: Intolerable/Unacceptable S1 Severity as is
S2 Severity with mitigating controls in place
Mitigating Controls Control Type Hierarchy
Select controls based on the Control Type Hierarchy. EL - Elimination BEST
Remember: Multiple controls will provide assurance S - Substitution
for best results. E - Engineering
A - Administrative
Activity: Project Environmental Risk Assessment Assessment Purpose: (Preparation/Supplementary to method statement/following incident, etc.)
Preparation
Cause of
People/ Adverse Effect / Type
L1 S1 Ctrl L2 S2 Legal and Other
Job / Task Environment/ Adverse Effect / of Environmental RFN ** Mitigating Controls RRN * Assessment
Type Requirements Reference
Property at Risk Impact
Environmental Aspect
P - PPE WORST