Professional Documents
Culture Documents
38.00
Bollard 100t/20 m +4.40
3
+4.00 1
-2.00
3.00
Tie rod
0
Ro
2.0
ckfi
Concrete fill C35/45 ll fr
om
Ro 50
ckfi to 7
ll fr 0k 6.50
om N
Coating to -6.00 l.m.m. Anchor wall 5 to
10 -7.50
Backfill kN
8.00
Dredging
27.00
38.00
-20.00
Final dredge level
Combined wall
- Pipe Ø2060 x 26 mm (L = 38 m)
- Reinforcement plates from -4.50 m to -25.00 m l.m.m.
- Intermediary sheet piles AZ 28-700 (L = 29 m)
Silty sand
-28.00
-30.00
-37.00
Sandy clay
East Quay
Port of Piombino - Livorno | Italy
Project owner Autorità Portuale di Piombino
Design engineer dott. eng. Antonio Riccardi
Contractor JV CMC / Sales SpA
Tubes
Ø 2060 x 26 mm 38.0 m S 420 MH 5501 t
Sheet Piles
AZ 28-700 29.0 m S 430 GP 702 t
Clutches
C9 29.0 m S 355 GP 61 t
Reinforcement plates
600 x 26 mm 20.5 m S 420 M 559 t
Total 6823 tonnes
350.00
Tie rod ø120 Steel tube Concrete
interval 3.53 m interval 3.53 m capping beam
ø 2060 mm +4.00 3.26 x 6.0 mm +4.00
39.30 Joint 38.83 Joint 38.83 Joint 38.83 Joint 38.83 Joint 38.83 Joint 38.83 Joint 38.83 Joint 38.89
344.90
304.10
46.50
38.40
24.40
48.39 Joint 49.42 Joint 49.42 Joint 49.42 Joint 49.42 Joint 49.42 Joint 49.42 Joint
+4.50
+7.20 Concrete protection wall against wave action +8.50
The combined wall was planned to be anchored at to the tube’s longitudinal axis. They are placed in
-0.50 m below l.m.m. with steel tie rods Ø 120 mm, the positions of the highest stresses: 90° from the
one each primary element, to a reinforced concrete clutches from elevation -4.50 m to -25.00 m below
beam positioned in the vicinity of the breakwater at l.m.m. The intermediary sheet pile section selected was
the sea-side of the quay platform (see «Typical cross an AZ 28-700 in S430 GP,TIPO
SEZIONE with
“C” an elastic modulus of
section»). The distance between the main wall and the 3’865 cm3/double element
anchor beam was approximately 38 m. The actual tie rod position was raised from level
In order to provide a more economical solution and -0.50 m to +0.50 m above water level, outside the
a faster delivery, ArcelorMittal, in collaboration with usual tidal movements, in order to lower the corrosion
CMC, proposed an alternative design using spirally influence. The rise in the anchoring level causes a
welded tubes with a constant wall thickness of 26 mm different distribution of the acting forces, causing Driving frame
(locally reinforced when needed), a higher anchoring a modest increase in the stresses on the tube at a
level and a more economical intermediary sheet pile. slightly higher elevation, while reducing the anchoring Due to the soil conditions, consisting of an upper
The alternative solution consisted of steel tubular piles, forces. This reduction in the forces acting on the medium-dense silty sand layer (ϕ =30°~34°) up to
Ø 2060 mm, reinforced with two internal stiffener tie rod prolongs its service live while maintaining its -30.00 m below l.m.m, and a lower sandy clay layer
steel plates (600 x 26 mm), shaped to fit the tube diameter (Ø 120 mm). The higher stresses in the (cu=110-150 kPa) up to -50.00 m below l.m.m, a
curvature, welded both parallel and perpendicular tubular pile, however, are countered by the positioning normal frequency vibratory hammer could be used
of the reinforcement plates inside. for the installation. Also, as a part of ArcelorMittal’s
The design of this tube combined wall was performed services, a complete custom-made driving template
Stiff. plate
according to Eurocode 3 (Part 4 and Part 5) and was delivered to the jobsite to enable the accurate
11.2016 - CS 022 - Piombino East Quay - GB
Eurocode 8 (seismic design). driving of the 111 tubular piles. The driving was
The minimum quay wall design life time is 100 years, carried out between June and October 2014.
without considering the additional measures that can The Piombino Port project showcases perfectly the
extend the design life time up to 300 years, which are: advantages of collaborating with ArcelorMittal’s
Clutch 1 Clutch 2 technical services. Thanks to this collaboration among
0° 180°
• steel stress verification performed assuming a
corrosion loss for 100 years; designers, contractors and supplier, a more simplified
• coating over the 7 upper meters of the combined and cost efficient solution has been installed. The
wall; different technical modifications explained resulted
in an easier execution and significant savings in steel
• cathodic protection (the anchoring system, the
weight (the installed intermediary piles are 20% lighter
combined wall and the concrete reinforcement);
than the tendered ones).
Stiff. plate • filling of the steel tubes with concrete and jet
C o a ti n g grouting (this also helps to avoid ovalisation and
increase the pile inertia).
ArcelorMittal Commercial RPS S.à r.l. | Sheet Piling | 66, rue de Luxembourg | L-4221 Esch-sur-Alzette | Luxembourg
T (+352) 5313 3105 | sheetpiling@arcelormittal.com | sheetpiling.arcelormittal.com
Projects Europe | Mannesmannweg 5 | 4794 SL Heijningen | The Netherlands
T (+31) 88 0083 700 | projects.europe@arcelormittal.com | www.arcelormittal.com/foundationsolutions