You are on page 1of 3

Republic of the Philippines

Deparment of Education
Region XI
TAGUM CITY NATIONAL HIGH SCHOOL
Mangga, Visayan Village, Tagum City
INDIVIDUAL PROGRAM OF WORKS

1. Date: October 21, 2021


2. Name of Project: 3. Location: 4. Type of Project:
Tagum City National High School ( ) Building
WATER RESERVOIR SYSTEM REPAIR Mangga, Visayan Village ( ) Waterworks
( ) Others
5. Project Description: 6. Category
Plumbing Supplies Buildings Waterworks Building
5.1 Dimension : ( ) 1 Room ( ) Level 1 ( ) Econimics
5.2 Floor Area : ( ) 2 Room ( ) Level 2 ( ) Others
7. Calendar days to complete ( ) 3 Room ( ) Level 3
3 weeks / 15 days ( ) 4 Room ( ) Level 4
8. Source of Funds: MOOE
9. Implementation Scheme: ( ) By Administration ( ) By Contract
10. Summary of Estimated Cost: 10.1 Materials 11. Direct Cost
SUMMARY OF ITEMS % of Total QTY Unit U.C. Amount
PE Hose 3/4 20 Mtrs. -
PE Coupling 1-3/4 6 Pcs. -
PE Coupling 3/4-1/2 6 Pcs. -
PE "Tee" Connector 3/4-1/2 4 Pcs. -
PE "Tee" Connector 3/4 4 Pcs. -
PE Elbow 3/4 10 Pcs. -
PE Elbow 1/2 10 Pcs. -
PE Coupling 1/2 10 Pcs -
PE Coupling 3/4 10 Pcs -
GI Tank Floater #2 w/ Elbow 1/2 5 Pcs. -
3/4 Teflon Tape 6 Pcs -
Ball Valve #1/2 w/ #1/2 Connector 3 Pcs. -
1/2 PE Hose 1 Roll -
3/4 x 1/2 PE Connector 4 Pcs. -
1/2 PE Connector 4 Pcs. -
1/2 PE Tee 6 Pcs. -
-
-
-
-
-
-
-
Php -
12. Labor Cost
13. Contingencies
14. Other Materials shall be Charge to other sources/canteen, PTA and LGU
TOTAL PROJECT COST 0.35 Php -
Prepared by: Recommending Approval:

ROGER L. YECYEC, LPT.,MAED ROLANDO F. GAYAS


School Engineering Facilities Coordinator School Property Custodian/Supply Officer

Approved by:

JEFFREY C. VILLAROSA, PHD


Principal IV
Republic of the Philippines
Deparment of Education
Region XI
TAGUM CITY NATIONAL HIGH SCHOOL
Mangga, Visayan Village, Tagum City
INDIVIDUAL PROGRAM OF WORKS

1. Date: November 23, 2022


2. Name of Project: 3. Location: 4. Type of Project:
Tagum City National High School ( ) Building
Floor Tiling of SHS Building Mangga, Visayan Village ( ) Waterworks
( ) Others
5. Project Description: 6. Category
Buildings Waterworks Building
5.1 Dimension : ( ) 1 Room ( ) Level 1 ( ) Econimics
5.2 Floor Area : ( ) 2 Room ( ) Level 2 ( ) Others
7. Calendar days to complete ( ) 3 Room ( ) Level 3
1 week ( ) 4 Room ( ) Level 4
8. Source of Funds: MOOE
9. Implementation Scheme: ( ) By Administration ( ) By Contract
10. Summary of Estimated Cost: 10.1 Materials 11. Direct Cost
SUMMARY OF ITEMS % of Total QTY Unit U.C. Amount
60 x 60 Tiles 180 pcs 180.00 32,400.00
Tile Adhesive 30 bags 300.00 9,000.00
Wash Sand 1 load 2,000.00 2,000.00
Cement 30 bags 300.00 9,000.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Php 52,400.00
12. Labor Cost Php 18,340.00
13. Contingencies
14. Other Materials shall be Charge to other sources/canteen, PTA and LGU
TOTAL PROJECT COST 0.35 Php 70,740.00
Prepared by: Recommending Approval:

ERNIE L. BALBUENA ROLANDO F. GAYAS


Grade 11 Head School Property Custodian/Supply Officer

Approved by:

JEFFREY C. VILLAROSA, PHD


Principal IV