1st November 2022 Pre production Initial sketches 1st November N

1st November 2022 Pre production Mood boards 1st November N

6th November Pre production Planning of models 8th November N

7th November Production Basic Layout 14th November N


Production
8th November Creation of the island 9th November
Production
8th November Creation of the island texture 9th November
Production
9th November Choosing the specific colour of the island 9th November
Production
9th November Setting the water level 9th November
Production
10th November Animating the water 11th November
Production
12th November Choosing the colour of the water 12th November

15th November Production Learning how to create palm trees 15th November N

19th November Production Choosing the colour of the palm trees 19th November
Cloning the palm trees and placing them around
22nd November Production 23rd November N
the islands.
6th December Production Create an SOS “Help” sign 7th December N

10th December Production Add lighting for the level 10th November

13th December Production Render a tour of my level 16th December N