Caticlan Airport Development Project

Summary Cost of the Amount In Details of the Project


Project
Total Budget of the Php.2.506 Billion Implementing Agency
Project Civil Aviation Authority of the Philippines
(CAAP)
Total Cost of the Project Php.1.35 Billion Status of the Project
As of October 2021, construction still stands
54.19% complete.
Procurement Mode
Unsolicited

Phases of the Project

Phase 1A

1. Improvement/ upgrading of existing terminal

2. Upgrading of airport facilities

3. Reducing slope of adjacent hill to 4 degrees

Phase 1B

1. Extension of the runway to 1.95 km

2. Construction of landslide facilities to include new terminal building

3. Installation of navigational and air traffic control aids

Phase 2:

1. Extension of runway towards the sea by 150 m

Status

Phase 1A - completed and operational


Phase 1B and 2 - ongoing construction