Professional Documents
Culture Documents
April 2016
Urban Drainage and Options of Urban
Polder Development for UNESCO
Heritage Kota Lama, Semarang,
Central Java, Indonesia
Supervisor
Prof. Dr. Charlotte de Fraiture, MSc
Mentor
Dr. F.X. Suryadi, MSc
Examination committee
Prof. Dr. Charlotte de Fraiture, MSc (UNESCO-IHE)
Dr. F.X. Suryadi, MSc (UNESCO-IHE)
Ir. Gerard Pichel, MSc
This research is done for the partial fulfilment of requirements for the Master of Science degree at the
UNESCO-IHE Institute for Water Education, Delft, the Netherlands
Delft
April 2016
Although the author and UNESCO-IHE Institute for Water Education have made every effort
to ensure that the information in this thesis was correct at press time, the author and UNESCO-
IHE do not assume and hereby disclaim any liability to any party for any loss, damage, or
disruption caused by errors or omissions, whether such errors or omissions result from
negligence, accident, or any other cause.
iii
iv
Table of Contents
Summary i
Acknowledgements iii
List of Figures ix
Abbreviations xv
Introduction 1
1.1. Background 1
1.2. Problem Identification 3
1.3. Research Questions 4
1.4. Research Objectives 4
Literature Review 5
2.1. Flood Hazard 5
2.2. Sustainable Urban Drainage System 7
2.3. Polder System 8
2.4. Design Rainfall 11
2.5. Unsteady Flow and Precipitation Runoff Model 16
Unsteady Flow 16
Control Structures 18
Precipitation Runoff Module 21
Methodology 23
3.1. Research Methodology 23
3.2. Data Collection 24
3.3. Data Analysis 26
Study Area 29
4.1. Kota Lama as UNESCO Heritage 29
4.2. Kota Lama Area 30
4.3. Kota Lama Sub Drainage System 31
4.4. Administrative Region 32
4.5. Land Use 32
4.6. Population & Employees 33
4.7. Hydrology 33
4.8. Tidal Fluctuation 34
4.9. Inundation Problem 35
v
Review of Drainage System Master Plan 39
5.1. Storm water Drainage Master Plan for the City of Semarang (1976) 39
5.2. Semarang Surakarta Urban Development Project (1991) 39
5.3. Master Plan on Water Resources Development, Flood Control and Urban
Drainage (1993) 40
5.4. Drainage Master Plan for Semarang (2007) 41
5.5. Difference of the Design Rainfall between Master Plans 42
5.6. Existing Drainage System in Semarang 43
Semarang Tengah (Central Semarang) Drainage System 43
East Flood Way (BKT) and West Flood Way (BKB) 44
Banger Polder 45
5.7. Drainage System in Kota Lama Semarang 46
Drainage Master Plan Semarang (2007) 46
Existing Situation 46
Topography Analysis 51
6.1. Coastline 51
6.2. Topography of Semarang 52
6.3. Topography of Kota Lama Sub drainage system 52
6.4. Land Subsidence 53
6.5. Estimation of Future Topography 55
Scenario Analysis 71
8.1. Scenario 1: Cleaning the Canals and Retention Basin 71
8.2. Scenario 2: Full Pump Capacity 74
8.3. Scenario 3: Full Gate Opening Operation at Every Outlets 78
8.4. Scenario 4: Flap Gate Operation at Every Outlets 83
8.5. Scenario 5: Close the Connection with Banger Subsystem Drainage 87
8.6. Scenario 6: Proposed New Pump Capacity 91
8.7. Scenario 7: Full Developed Polder System 93
Determination of Pump Capacity 94
Determination of Dike Height 97
Determination of Control Structures 98
vi
8.8. Selection for the Most Appropriate Scenario 100
Discussion of Scenarios 100
Implementation Phases 102
8.9. Sensitivity Analysis 103
8.10. Application Considerations 104
Environmental and Public Health Aspects 104
Social Aspects 108
Economic Aspects 110
References 113
Appendices 117
Extreme rainfall in order of magnitude for different rainfall duration at
Semarang Rainfall Station 117
Sediment thickness sampling 118
Model Features in DUFLOW for Clean Canals 121
Model Features in DUFLOW for Canals with Sediment 126
Canal Cross Sections, Gates & Pumps in DUFLOW 130
Service Area in DUFLOW 131
vii
viii
List of Figures
Figure 1-1 Layout of Kota Lama in 1787 (atlasofmutualheritage.nl) ..................................................... 2
Figure 1-2 Satellite view of Kota Lama, Semarang (Google Earth, 2016) ............................................. 3
Figure 2-1 The Influence of Urbanization on Different Components of the Water Cycle (APFM, 2008)
......................................................................................................................................................... 6
Figure 2-2 Land Subsidence and Sea Level Rise Rates (Deltares, 2015) ............................................... 6
Figure 2-3 Polder Components (Witteveen+Bos, 2009) ......................................................................... 9
Figure 2-4 Selection of design rainfall for polder components design (Ministry of Public Works and
Housing, 2009) .............................................................................................................................. 10
Figure 2-5 Polder Types (Ministry of Public Works and Housing, 2009) ............................................ 10
Figure 2-6 Grid Points for (a) Explicit and (b) Implicit Scheme (Colin et al, 1976) ............................ 16
Figure 2-7 Volume Control for Continuity Equation (Ministry of Public Works and Housing, 2009) 17
Figure 2-8 The Four Point Preismann Scheme (Stowa, 2006) .............................................................. 18
Figure 2-9 Dependence of Drainage Pump Operation on Upstream Water Level (Stowa, 2006) ........ 18
Figure 2-10 Types of Flow at General Structures (Stowa, 2006).......................................................... 19
Figure 2-11 Sketch (a) and drainage course (b) of quick and slow components (Stowa, 2006) ........... 21
Figure 3-1 Research Methodology ........................................................................................................ 23
Figure 4-1 Blenduk Church at Kota Lama (hotcaramel-s.blogspot.com) ............................................. 29
Figure 4-2 Area of Kota Lama Regional Plan (Regional Regulation of Semarang City No. 8/2003) .. 30
Figure 4-3 Kota Lama Sub Drainage System ........................................................................................ 31
Figure 4-4 Administrative Region of Kota Lama Sub Drainage System .............................................. 32
Figure 4-5 Land Use of Kota Lama Sub Drainage System ................................................................... 33
Figure 4-6 Example Semi Diurnal Tides in Semarang (http://www.ukho.gov.uk/) .............................. 35
Figure 4-7 Tidal Flood in Kota Lama Sub drainage system (Semarang Drainage Master Plan, 2007) 35
Figure 4-8 Local Flood in Kota Lama Sub Drainage System (Semarang Drainage Master Plan, 2007)
....................................................................................................................................................... 36
Figure 4-9 Flood Prone Map in Kota Lama Sub Drainage System (Semarang Drainage Master Plan,
2007) .............................................................................................................................................. 36
Figure 4-10 Rainfall Graph at Simongan Hydrological Station (http://www.tech4water.com) ............ 37
Figure 5-1 Study Area for Urban Drainage Plan (JICA, 1993) ............................................................. 40
Figure 5-2 Planned Drainage System Scheme of Semarang in 2007 (Semarang Planning Board, 2007)
....................................................................................................................................................... 42
Figure 5-3 Semarang Tengah Drainage System (Haryono et.al., 2008)................................................ 43
Figure 5-4 Google Map image of Semarang, East Flood Way (BKT) and West Flood Way (BKB) ... 44
Figure 5-5 Sketch location of Semarang River, Baru River, Asin River and Its Infrastructures .......... 44
Figure 5-6 Condition of Kali Semarang Pump Station and Retention Basin in 16/11/2015 ................. 45
Figure 5-7 Location of Kota Lama and Banger Polder ......................................................................... 45
Figure 5-8 Sketch of Existing Condition of Kota Lama, Semarang ...................................................... 46
Figure 5-9 Situation of Tawang Retention Basin .................................................................................. 47
Figure 5-10 Condition of Baru River Pump Station.............................................................................. 47
Figure 5-11 Condition of Vertical Gates near Berok Bridge................................................................. 48
Figure 5-12 Existing Condition of Drainage Condition at Tawang Street ............................................ 48
Figure 5-13 Existing Condition of Drainage Condition at Letjen Suprapto Street ............................... 48
Figure 5-14 Existing Condition of Drainage Condition at K.H. Agus Salim Street ............................. 49
Figure 5-15 Existing Condition of Drainage Condition at Bandarharjo Street ..................................... 49
Figure 5-16 Existing Condition of Drainage Condition at Merak Street .............................................. 49
Figure 5-17 Location of Sediment Thickness Sampling in Kota Lama ................................................ 50
Figure 6-1 Coastline Change in Semarang (Ministry of Research and Technology, 2009) .................. 51
Figure 6-2 Topography Map of Semarang ............................................................................................ 52
ix
Figure 6-3 Topography Map of Kota Lama .......................................................................................... 53
Figure 6-4 Semarang Land Subsidence Map (Geological Agency, 2008) ............................................ 53
Figure 6-5 Land Subsidence in Kota Lama Sub Drainage System Area............................................... 54
Figure 6-6 Land Subsidence Measurement Points in Kota Lama Sub Drainage System Area ............. 54
Figure 6-7 Land Subsidence Rate at BM16 Point ................................................................................. 55
Figure 6-8 Increasing the number of registered wells and ground water extraction in Semarang
(Murdohardono et al, 2007) ........................................................................................................... 55
Figure 6-9 Land Subsidence Estimation for Bandarharjo-Poncol Trajectory (Sarah et al, 2012) ......... 56
Figure 7-1 IDF Curve of Semarang Rainfall Station............................................................................. 59
Figure 7-2 Outside Service Area of Kota Lama Susbystem Drainage .................................................. 61
Figure 7-3 Land Cover in Kota Lama Susbystem Drainage ................................................................. 62
Figure 7-4 System Schematization of Kota Lama Subsystem Drainage ............................................... 63
Figure 7-5 Assigned Design Rainfall for Existing Condition in DULFOW ......................................... 64
Figure 7-6 Assigned Tidal Fluctuation in DULFOW............................................................................ 65
Figure 7-7 Long section and cross section sketch of the gate ............................................................... 65
Figure 7-8 Tidal Fluctuation Effects at Merak Street for Existing Condition ....................................... 67
Figure 7-9 Water Level Condition on Merak Street until Baru River Pump Station for Existing
Condition ....................................................................................................................................... 68
Figure 7-10 Simulation Result of Existing Condition for Main Drainage of Kota Lama ..................... 68
Figure 7-11 Pump Operation Simulation of Existing Condition ........................................................... 68
Figure 7-12 Simulation Result of Inundated Area for Kota Lama ........................................................ 69
Figure 7-13 Simulation Result of Do Nothing Scenario for Kota Lama ............................................... 70
Figure 8-1 Relationship of Hydraulic Radius and Chezy Coefficient ................................................... 71
Figure 8-2 Tidal Fluctuation Effects at Merak Street for Scenario 1 .................................................... 72
Figure 8-3 Inundation Map of Kota Lama for Scenario 1: Cleaning Canal and Retention Basin ......... 72
Figure 8-4 Tidal Fluctuation Effects at Merak Street for Scenario 2a .................................................. 74
Figure 8-5 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 2a ... 74
Figure 8-6 Pump Operation Simulation of Scenario 2a ........................................................................ 75
Figure 8-7 Inundation Map of Kota Lama for Scenario 2a: Full Pump Capacity and Canal with
Sediment ........................................................................................................................................ 75
Figure 8-8 Tidal Fluctuation Effects at Merak Street for Scenario 2b .................................................. 76
Figure 8-9 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 2b... 76
Figure 8-10 Pump Operation Simulation of Scenario 2b ...................................................................... 77
Figure 8-11 Inundation Map of Kota Lama for Scenario 2b: Full Pump Capacity and Clean Canal.... 77
Figure 8-12 Tidal Fluctuation Effects at Merak Street for Scenario 3a ................................................ 79
Figure 8-13 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 3a . 79
Figure 8-14 Sketch of Water Level Condition at the River Baru outlet for Scenario 3a at 15:55......... 79
Figure 8-15 Inundation Map of Kota Lama for Scenario 3a: Full Gate Opening and Canal with
Sediment ........................................................................................................................................ 80
Figure 8-16 Tidal Fluctuation Effects at Merak Street for Scenario 3b ................................................ 80
Figure 8-17 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 3b. 81
Figure 8-18 Sketch of Water Level Condition at the River Baru outlet for Scenario 3b at 15:55 ........ 81
Figure 8-19 Downstream and Upstream Relations for Scenario 3: Full Gate Opening ........................ 82
Figure 8-20 Tidal Fluctuation Effects at Merak Street for Scenario 4a ................................................ 84
Figure 8-21 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 4a . 84
Figure 8-22 Sketch of Water Level Condition at the River Baru outlet for Scenario 4a at 15:55......... 84
Figure 8-23 Inundation Map of Kota Lama for Scenario 4a: Flap Gate Operation and Canal with
Sediment ........................................................................................................................................ 85
Figure 8-24 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 4b. 85
Figure 8-25 Sketch of Water Level Condition at the River Baru outlet for Scenario 4a at 15:55......... 86
Figure 8-26 Discharge Comparison between Full Gate Opening and Flap Gate Operation ................. 87
x
Figure 8-27 Water Level Condition at Merak Street for Scenario 5a ................................................... 88
Figure 8-28 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 5a . 88
Figure 8-29 Pump Operation Simulation of Scenario 5a ...................................................................... 88
Figure 8-30 Water Level Condition at Merak Street for Scenario 5b ................................................... 89
Figure 8-31 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 5b. 89
Figure 8-32 Pump Operation Simulation of Scenario 5b ...................................................................... 89
Figure 8-33 Pump Operation Simulation of Scenario 5b (In Case of Close Connection to Semarang
River) ............................................................................................................................................. 90
Figure 8-34 Pump Selection for Outside of Kota Lama Polder ............................................................ 91
Figure 8-35 Tidal Fluctuation Effects at Merak Street for Scenario 6 .................................................. 91
Figure 8-36 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 6... 92
Figure 8-37 Pump Operation Simulation of Scenario 6 ........................................................................ 92
Figure 8-38 Boundary Map of Kota Lama Polder................................................................................. 93
Figure 8-39 Water Level Condition at Merak Street with Existing Tawang Pump Capacity ............... 94
Figure 8-40 Water Depth Curve for Inside of Kota Lama Polder with Existing Pump, (a) Return Period
Rainfall & (b) Rainfall ................................................................................................................... 94
Figure 8-41 Rainfall Frequency Curve for Inside of Kota Lama Polder with Existing Pump Capacity 95
Figure 8-42 Water Level Condition at Tawang Street with Existing Baru River Pump Capacity ........ 95
Figure 8-43 Water Depth Curve for Outside of Kota Lama Polder with Existing Pump, (a) Return
Period Rainfall & (b) Rainfall ....................................................................................................... 96
Figure 8-44 Pump Selection for Outside of Kota Lama Polder ............................................................ 96
Figure 8-45 Rainfall Frequency Curve for Outside of Kota Lama Polder with Proposed Pump Capacity
....................................................................................................................................................... 96
Figure 8-46 Water Depth Curve for Outside of Kota Lama Polder with Proposed Pump, (a) Return
Period Rainfall & (b) Rainfall ....................................................................................................... 97
Figure 8-47 Condition of Kota Lama Polder Boundaries ..................................................................... 97
Figure 8-48 Proposed Kota Lama Polder Drainage Scheme ................................................................. 98
Figure 8-49 Water Level Condition on Merak Street and Tawang Street for Scenario 6 ..................... 99
Figure 8-50 Kota Lama Drainage Performance Diagram ................................................................... 101
Figure 8-51 Kota Lama Drainage System Scenarios Performance Assessment ................................. 102
Figure 8-52 Implementation Phases for Kota Lama............................................................................ 103
Figure 8-53 Canals Roughness Effects on Water Depth for Several Pump Capacity within Kota Lama
Polder ........................................................................................................................................... 104
Figure 8-54 Residential Area in Kota Lama........................................................................................ 105
Figure 8-55 Traditional Market, Business Area and Antique Market in Kota Lama .......................... 105
Figure 8-56 Activities of Rukun Karya Bank of Waste, Surabaya (Ministry of Environment and
Forestry, 2012)............................................................................................................................. 106
Figure 8-57 Condition of Water Quality in Kota Lama ...................................................................... 106
Figure 8-58 Operation the Water fountains in Tawang Retention Basin at 2007 (nisa17.blogdetik.com)
..................................................................................................................................................... 106
Figure 8-59 Up Coning Saline Groundwater with Groundwater Extraction (Ministry of Public Works
and Housing, 2009) ...................................................................................................................... 107
Figure 8-60 Jatibarang Reservoir (Ministry of Public Works and Housing, 2015)............................. 107
Figure 8-61 Existing Situation at Tawang Retention Basin ................................................................ 108
Figure 8-62 Diagram of Realisation Phases ........................................................................................ 108
Figure 8-63 Proposed Organisation Structure of Kota Lama Polder Board ........................................ 109
Figure 8-64 Workflow of the Application of Social Media Based for Inundation Recording and
Emergency Response (Eirlander et al., 2015).............................................................................. 110
xi
xii
List of Tables
Table 2-1 Types and Causes of Floods (Jha et al., 2012) ........................................................................ 5
Table 2-2 Example of Drainage System Sustainability Indicators on Technical and Scientific
Performance (Ellis et al., 2004) ....................................................................................................... 8
Table 2-3 Determination of Variables for General Structures (Stowa, 2006) ....................................... 20
Table 3-1 Data Collection ..................................................................................................................... 25
Table 3-2 Proposed Assessment of Existing Drainage System Sustainability Indicators for Kota Lama
....................................................................................................................................................... 27
Table 4-1 Population in Semarang Tengah and Semarang Utara (Semarang Statistic Bureau, 2014) .. 33
Table 4-2 Semarang Maximum Daily Rainfall of 1981 - 2006............................................................. 34
Table 4-3 Semarang Average Daily Evaporation of 1987-2006 (Witteveen+Bos, 2008)..................... 34
Table 4-4 Semarang Tidal Characteristic (Witteveen+Bos, 2008)........................................................ 35
Table 4-5 Flood Events in Kota Lama Sub drainage system ................................................................ 37
Table 5-1 Design Rainfall 1982 Technical Study (JICA, 1993) ........................................................... 39
Table 5-2 Design Scale 1993 Master Plan (JICA, 1993) ...................................................................... 40
Table 5-3 Design Rainfall at Simongan Rainfall Station (Semarang Planning Board, 2007) ............... 41
Table 5-4 Resume of Design Rainfall between Master Plans ............................................................... 43
Table 7-1 Semarang Rainfall Station’s Maximum rainfall in order of magnitude for different rainfall
duration .......................................................................................................................................... 57
Table 7-2 Rainfall data validation result of Semarang Rainfall Station ................................................ 58
Table 7-3 Design Rainfall of Semarang Rainfall Station ...................................................................... 59
Table 7-4 IDF Table of Semarang Rainfall Station............................................................................... 59
Table 7-5 Hyetograph (3 Hours) of Semarang Rainfall Station ............................................................ 60
Table 7-6 Local Inflow of Kota Lama Sub drainage system................................................................. 60
Table 7-7 Model Features of Kota Lama Subsystem Drainage............................................................. 63
Table 7-8 Boundary Condition of Kota Lama Drainage System .......................................................... 66
Table 7-9 Benchmark for Technical and Scientific Performance Assessment of Existing Kota Lama
Sub drainage system ...................................................................................................................... 66
Table 7-10 Comparison of Simulated and Real Events......................................................................... 67
Table 7-11 Technical and Scientific Performance Assessment of Existing Condition for Kota Lama. 70
Table 8-1 Technical and Scientific Performance Assessment of Scenario 1: Cleaning Canal and
Retention Basin for Kota Lama ..................................................................................................... 73
Table 8-2 Technical and Scientific Performance Assessment of Scenario 2: Full Pump Capacity for
Kota Lama ..................................................................................................................................... 78
Table 8-3 Technical and Scientific Performance Assessment of Scenario 3: Full Gate Opening for
Kota Lama ..................................................................................................................................... 83
Table 8-4 Technical and Scientific Performance Assessment of Scenario 4: Flap Gate Operation at
Every Outlets for Kota Lama ......................................................................................................... 86
Table 8-5 Technical and Scientific Performance Assessment of Scenario 5: Close the Connection with
Banger Sub drainage system .......................................................................................................... 90
Table 8-6 Technical and Scientific Performance Assessment of Scenario 6: Proposed New Pump
Capacity ......................................................................................................................................... 92
Table 8-7 Technical and Scientific Performance Assessment of Scenario 7: Full Developed Polder
System ......................................................................................................................................... 100
Table 8-8 Manning Roughness Coefficients for Concrete Canals (Chow, 1959) ............................... 104
xiii
xiv
Abbreviations
ABM Alternating Block Model
APFM Associated Programme on Flood Management
ArcGIS GIS Software which developed by ESRI
ARF Area Reduction Factor
BKB West Flood Way
BKT East Flood Way
Bappeda Planning Board (local government)
BMKG Meteorology, Geophysics and Climatology Agency
BNPB National Agency for Disaster Management
BPBD Disaster Management Board (local government)
BPS Statistic Bureau
DEM Digital Elevation Model
HELWD Hydraulic Engineering – Land and Water Development
IPCC Intergovernmental Panel on Climate Change
IDF Intensity-Duration-Frequency
IDW Inverse Distance Weighted
ITB Bandung Institute Technology
JICA Japan International Cooperation Agency
MSL Mean Sea Level
MPW Ministry of Public Works and Housing
RTBL Land Use Master Plan
Satker PPLP Drainage and Sanitation Working Unit
SNI Indonesian National Standard
UNDIP Diponegoro University
UNESCO United Nations Educational, Scientific and Cultural Organization
UNISSULA Sultan Agung Islamic University
WGS 84 World Geodetic System 1984
xv
xvi
List of Symbols
A Wetted area of channel (m2)
B Surface width of channel (m)
Bs Storage capacity of open water (hydrology)
Ck Coefficient of kurtosis
Cv Coefficient of variation
Cs Coefficient of skewness
Di Difference of Kxi and Kyi
dk Degree of freedom
dk1 Degree of freedom in group 1
dk2 Degree of freedom in group 2
E Evapotranspiration (mm/day)
Ef Expected frequency in one class
Fcal Calculated F value of F- test
Ftab F value from F value table
g Gravity acceleration (9.81 m/s2)
h Water depth (m)
H Water depth over the sill (m)
Hi Water depth at the upstream (m)
Hj Water depth at the downstream (m)
HO Height of the gate opening (m)
Ii Inflow (mm/day)
I Rainfall intensity (mm/hour)
k Frequency factor depend on the type of distribution
K Number of class in Chi Square test
Ks Seepage (mm/day)
Kxi Rank of each sorted data of Spearman’s rank test
Kyi Rank of sorted data based on original data sequence of Spearman’s rank test
n Life span of structure (years)
N1 Total number of data in group 1
N2 Total number of data in group 2
Of Actual frequency in one class
P Probability
Pr Precipitation (mm/day)
Q Discharge (m3/s)
Qi Incoming flows (mm/day)
Qu Outgoing flows (mm/day)
Qp Pump capacity (m3/s)
ql Lateral flow (m3/s/m)
R Hydraulic radius (m)
Ro Probability of occurrence depends of life span of structure
Rm Total rank data maximum
Rsp Spearman’s rank order coefficient
S Seepage (mm/day)
So Bottom slope
xvii
Sf Energy slope
t Rainfall duration (minutes)
tt Significance for Spearman’s rank order coefficient
T Return period (years)
Tcal Calculated T value of T- test
Ttab T value from T value table
v Velocity (m/s)
W Downward seepage (mm/day)
xave Average of data
xave1 Average of data in group 1
xave2 Average of data in group 2
xH Higher limit of Grubbs-Beck test
xL Lower limit of Grubbs-Beck test
XT Calculated data based on T years return period
Zcal Calculated Z value of Mann Whitney test
Ztab Z value from Z value table
Ztab_bottom Z value lower limit from Z value table
Ztab_top Z value higher limit from Z value table
α Degree of confidence
β Coriolis coefficient (-)
Δcr Critical deviation based on Smirnov Kolmogorov table
Δmax Maximum deviation between observed and theoretical data
ΔH Head difference (m)
μ Loss coefficient (-)
ρ Number of parameter
σ Standard deviation of data
σ1 Standard deviation of data in group 1
σ2 Standard deviation of data in group 2
θ Factor controlling numerical dumping
χ2 Calculated chi square value
χcr2 Critical chi square value based on table
xviii
Chapter 1
Introduction
1.1. Background
Indonesia is an archipelago country with coastline of about 81,000 km with more than
17,500 islands. Indonesian territories is widely spread around the equator, so it is located in
the tropical climate with rainfall distribution from 800 mm/year (dry season) and 4,000
mm/year (rainy season). With these circumstances, Indonesia is a flood prone area. The flood
does not only occur in lowland areas or coastal areas, but also can occur at highland areas.
Based on the National Agency for Disaster Management of the Republic of Indonesia (BNPB),
the floods that occurred in Indonesia from 1990 to 2015 are 31.5% of the total disasters and
61 million of people is living in flood prone areas of moderate and high levels.
The flood events occurred without exception, even in Semarang, Central Java. Semarang is
capital city of Central Java which is located in the northern part of Java Island. Northern part
of Java Island is well known as the lowland areas. According to Suryadi (1996), lowland is
the land which is affected by fluctuating surface water level (e.g. tides and floods).
Lowland can be divided into natural and manmade with human activities such as deep
groundwater extraction, oil and gas exploitation, artificial lands and reclaimed lands.
Lowland also can be described as the land that are either water logged, or temporarily or
permanently covered with a water layer.
Cordero (2012) reported that quantity of drainage system is still the major concern in developing
countries which is contradictory with developed countries. Social and environmental impacts of
drainage in developed countries is getting more attention than quantity and quality. In developing
countries, common factors regarding storm water drainage are:
low investment in urban drainage facilities;
increase of peak flow due to the increase in urbanization;
inadequate management of its land use;
lack of a drainage system capacity and its maintenance in poor areas;
improper design;
overflows from combine sewer systems (storm water and waste water are in the same system);
in separated sewer systems (storm water and waste water are in separate system) part of
the sewage is directed to the storm water drainage network;
lack of control on flows as urbanization increase;
illegal human occupation of flood plains;
lack of law enforcement in flooding areas.
Introduction 1
UNESCO (2015) stated that Semarang was the one of important cities in the colonial era
around 17th century because this port city became part of the trade route in central part of Java
Island. At those period, Dutch was constructed Vijfhoek fort to secure the residents and their
territory. As time goes by, this fort is no longer exist and the area now is known as Kota Lama.
UNESCO also noted that Kota Lama is the best preserved colonial city because this area can
describe about the important historical phases of human civilization (economic, political and
social aspects) in the South East Asia and the World. The layout of Kota Lama in 1787 is
presented in Figure 1-1.
Based on Regional Regulation of Semarang City No. 14/2011 regarding Spatial Planning of
Semarang City, Kota Lama is designated as cultural heritage area. All of cultural heritage is
the nation's cultural wealth that needs to be protected and preserved for awareness, national
identity and national interests (Law No. 5/1992 regarding Cultural Heritage Objects).
This research deals with the drainage system and possibility of polder development in Kota
Lama Area. The result of the research might be used for consideration in updating Heritage
City Management Plan (Rencana Penataan Kota Pusaka) of Semarang, Semarang Drainage
Water Plan and Water Resources Management Strategic Plan (Pola Pengelolaan Sumber Daya
Air) of Jratun Seluna River Basin. This research focuses on three main aspects which are
the existing condition, fully developed polder system for Kota Lama and selecting the most
appropriate scenarios. Several scenarios will be analysed and evaluated for different pump
capacities, drainage scheme and area.
Introduction 2
This thesis consists of nine chapters which are:
Chapter 1: explains about the background of the studies, problem that occurs, research
questions and the objective of the studies.
Chapter 2: focuses on the definition of flood hazards, sustainable urban drainage system,
polder system, design rainfall, unsteady flow and rainfall runoff model.
Chapter 3: defines about research location, methodology, data collection and data analysis.
Chapter 4: describes about the research area, land use, hydrology, tidal fluctuations, and
inundation problems.
Chapter 5: presents about review of past and existing drainage system plan in Semarang.
Chapter 6: describes about land subsidence, past, current and estimate future topography
situation in Semarang.
Chapter 7: analyse design inflow, focuses on past and current drainage system in Kota Lama.
Chapter 8: scenario development and selection for the most appropriate scenario for drainage
system in Kota Lama.
Chapter 9: describes the concluding remarks and recommendation for future outlook.
Figure 1-2 Satellite view of Kota Lama, Semarang (Google Earth, 2016)
Introduction 3
Therefore, the research area will be focussed on Kota Lama, Semarang. The polder type which
is considered is the polder with a pumping station (maximum energy demand) by using
the existing Tawang retention basin. As seen from the satellite imagery research area
(Figure 1-2) is quite congested and it will be very difficult to implement if resettlement should
be carried out.
Introduction 4
Chapter 2
Literature Review
2.1. Flood Hazard
Jha et. al (2012) explained that flood is the most often occurred as natural disaster and
no exception for urban or rural areas. Demographic growth of cities, towns and villages is one
characteristic of urbanization, especially in developing countries. Flood which is happened in
urban area will get worse and if this triggers super imposes with the other factor of flooding in
urban areas such as improper floodplain planning, ageing drainage infrastructures, increasing
of the impermeable surface and lack of flood management programs. Type and causes of floods
can be described briefly in Table 2-1.
Table 2-1 Types and Causes of Floods (Jha et al., 2012)
Literature Review 5
Urbanization has changed the natural ground cover and they become impervious surface (roofs,
roads, and paved areas) which gradually reduce the infiltration rate and increase surface runoff.
The runoff water should be able to infiltrate or runoff slowly, instead of flowing in the channels
or runoff over the paved areas which is resulting in increased the channel discharge.
Those situations change the water balance scheme for the area which roughly can be illustrated
in Figure 2-1.
Figure 2-1 The Influence of Urbanization on Different Components of the Water Cycle (APFM, 2008)
Land subsidence also influence the occurrence of urban flooding (frequency, depth and
duration of inundation). The causes are happened because of more on over exploitation of
ground water rather than tectonics movement. The impacts are more exacerbated by storm
events (short term) and sea level rise (long term). Deltares (2015) based on IPCC scenarios
predicted that mean absolute sea level globally will rise in a range of 3-10 mm/year until 2100
while land subsidence rates are in the range of 6-100 mm/year until 2025 in the coastal mega
cities as shown in Figure 2-2.
Figure 2-2 Land Subsidence and Sea Level Rise Rates (Deltares, 2015)
Literature Review 6
Data which is used for analysing the flood are hydrological, drainage network and topography.
Jha et al. (2012) also recommended that hydrological data can be obtained from land
measurement in hydrology, meteorology stations and satellite imageries which is display real
time or post-flood scenario for enriching the flood analysis. Satellite images can be obtained
from national or international organizations. Digital Elevation Model (DEM) can be obtained
through the remote sensing method which can be generated the high resolution, but the accuracy
of final flood hazard analysis and maps are still affected by the errors from data capture and
data accumulation. One of the public domain for DEM is Shuttle Radar Topography Mission
(SRTM) under supervision of National Aeronautics and Space Administration (NASA) of
the United States. Moreover, it is good that the data is also integrated with population maps,
land price and land cover maps.
Literature Review 7
Table 2-2 Example of Drainage System Sustainability Indicators on Technical and Scientific Performance (Ellis et al., 2004)
The performance assessment is needed in order to define the main cause of under-performance
of drainage system which can lead to the remedial measures for improving the drainage system.
By checking the hydraulic performance of the drainage systems, constraints can be eliminated
and the drainage system can be improved. Smedema et al (2004) discovered several main causes
of under-performance or constraints of drainage system, among others:
poor or faulty construction;
inadequate main drainage;
inadequate maintenance;
faulty design;
inadequate secondary measures;
external constraints.
Literature Review 8
Legend:
1. Closed dike-ring
2. Dike-ring surrounding polder area
3. Pumping station
4. Retention pond
According to the Ministry of Public Works and Housing (2009), polder development types can
be divided into two, among others:
New developed area
Development of new territory is a conversion of an area into urban areas, business or
industry. Peak discharge released from the polder areas are advised not to exceed the
peak discharge before the construction of polder.
Developed Area
Developed area defined as redevelopment of urban areas, business or industry as well
as systems for water management and flood protection. Improvement of water
management needs to be done if the current impervious surface area exceeds the plan
and capacity of the drainage system cannot accommodate the current state (exceeding
the design discharge).
Risk is usually used as a design consideration. For water management in the polder system
is designed with a return period of 25 or 50 years. Meanwhile, the dike should be designed
higher than the water management system. The sketch in Figure 2-4 describes the selection of
design rainfall for polder components design. Polder area can be divided into several sections
based on the different topography or land use. There are three options available to drain water
from the polder area (Figure 2-5), among others:
one pump station serves the entire area of the polder. Energy and pump capacity
required is maximum;
pumping stations with series and drainage system with stages;
polder is equipped by series pump and belt canal which will be pumped out.
Schultz (1986) identified water balance in polder system which is based on the principle of
conservation of mass. The water balance can be described as inflow (Ii) and seepage (S) into
polder is equal to pump capacity (Qp), evapotranspiration (E) and storage capacity of open water
(Bs). Mathematically, it can be expressed as:
+ = + + Equation 2-1
Literature Review 9
Ministry of Public Works and Housing (2009) also has general procedures for calculating
the retention pond capacity inside polder area and then to discharge the water out of the polder.
The procedures are 1-calculating design rainfall, 2-calculating hydrograph of inflow to
the polder, 3-estimate preliminary estimate of system capacity based on steady flow or peak
discharge and outflow, 4-check design capacity and its hydraulic performance.
Probability scale
(ARI)
Building protected in
major design flood
Main dikes Main dikes 1,000 years
Major System
Drainage system 25 years
Minor system
Road trafficable in
minor design flood
Figure 2-4 Selection of design rainfall for polder components design (Ministry of Public Works and Housing, 2009)
Figure 2-5 Polder Types (Ministry of Public Works and Housing, 2009)
Literature Review 10
Control structures or pump station can be used to discharge the water. Flap gate is usually used
for automatic operation which is operated based on the difference in water pressure.
When the water pressure inside the polder is bigger than outside, the gate will be opened and
water flow out. Then, the gate will close if water pressure outside is bigger than inside.
Incase a sluice gate is used, sluice gate also can be operated manually and it needs operator to
monitor water level or computer can be programed to make the gate operate automatically.
Flow capacity of control structure can be calculated based on desired water level inside polder,
water level outside polder and design rainfall. In any case, pump capacity is determined by the
capacity of the retention basin in order to create a balance to the extreme rainfall. The greater
the capacity of the pump the less area of retention pond and vice versa. Optimum combination
should be determined economically.
Design water level is formulated based on desired water level inside polder, duration of
inundation (if it is allowed) and return period. For indicative water level, Ministry of Public
Works and Housing (2009) has some value which are:
desired water level in drainage is 1 meter below the surface,
once in 2.5 years inundation in the street is allowed,
once in 5-10 years drainage system is allowed in bankfull condition,
indicative discharge of secondary or tertiary open channel is 150 l/day/ha.
Sensitivity analysis is needed if the system is new developed or no supported data with changing
the key parameters with the percentage so it is known changes to the output of the model.
{ − (( × )/2}
= .
Equation 2-2
{(1/12) × ( × ×( + + 1)))}
Literature Review 11
Where:
= × + ( /2) × ( + 1) − Equation 2-3
= × − Equation 2-4
Rm : total rank data maximum
N1 : total number of data in group 1
N2 : total number of data in group 2
Ztab value can be defined by the table of Z value with degree of confidence (α) is 5 %.
Conclusion that data is consistent can be known if Ztab_top < Zcal < Ztab_bottom and
if Ztab_top > Zcal > Ztab_bottom, data is inconsistent.
Wald-Wolfowitz test.
Triola (2009) stated that if the number of data is less than 40, the small sample method
of Wald-Wolfowitz method can be done. First thing is determined the n1 and n2
which are the value of data is less or more than average. Then, counting the number of
runs (G) and compare it to the two critical values of number of runs in the table
(Gtab_bottom and Gtab_top). Data can be accepted as independence data if G is between
Gtab_bottom and Gtab_top.
Grubbs-Beck test.
This test is determined two limits which are higher limit (xH) and lower limit (xL). Those
two limits can be calculated by the following equations:
( )
= Equation 2-5
( )
= Equation 2-6
Where:
xave : average of data
σ : standard deviation of data
/ / /
= −3.62201 + 6.28446 − 2.49835 + 0.491436 − 0.037911 Equation 2-7
Data is lower than value of xL classified as lower outliers and data on higher than value
xH classified as high outlier. The data is discarded if there is a lower outlier data.
However, proven high outlier data can still be used if the data is stationary (no trend,
variance consistent and average consistent)
Spearman’s rank test.
The data should be sorted from the smallest to largest (y), give the rank for each sorted
data (Kxi) and also give the rank of sorted data based on the original data sequence (Kyi).
Di value is the difference of Kxi and Kyi. Spearman’s rank-order coefficient (Rsp)
calculation can be calculated as:
6∑
=1− Equation 2-8
( − 1)
Literature Review 12
Significance for Spearman’s rank-order coefficient (tt) is computed with:
√ −2
= Equation 2-9
1−
Calculated tt value has to be compared to the two tailed invers of student’s t distribution
with degree of confidence (α) is 5 % and v value is
= −2 Equation 2-10
The rainfall data is accepted if the data is proven that is no trend or tt value is between
the critical values of two tailed two tailed invers of student’s t distribution.
F-test.
Fcal value can be calculated based on the following equation:
{ × ×( − 1)}
= Equation 2-11
{ × ×( − 1)}
Where:
1 : standard deviation of data in group 1
2 : standard deviation of data in group 2
Ftab value is defined by the table of F value with degree of confidence (α) is 5 % and
degree of freedom (dk) are
= −1 Equation 2-12
= −1 Equation 2-13
Then, calculated and table base F value should be compared. If Fcal is more than Ftab,
the rainfall data is in consistent condition (stable variance). The rainfall data is not in
consistent condition (unstable variance), if Fcal is less than Ftab.
T-test.
The equation to calculate Tcal are presented as follows:
| − |
= .
{∝ [(1/ ) + (1/ )] } Equation 2-14
{ × + × } Equation 2-15
∝=
( + − 2)
Similar as the method before, Ttab value can be defined by the table of T value with
degree of confidence (α) is 5 % and degree of freedom (dk) is
= + −2 Equation 2-16
Literature Review 13
Where:
xave1 : average of data in group 1
xave2 : average of data in group 2
The result of Tcal and Ttab should be compared. If Tcal is less than Ttab, the rainfall data
is in consistent condition. Then, if Tcal is more than Ttab the rainfall data is not in
consistent condition.
Ministry of Public Works and Housing (2011) stated that if the validation process indicates of
inconsistency and non-homogeneity, so the data need to be checked with document of measured
data, comparing to the nearest station or check the rainfall station condition.
Reoccurrence interval or return period has to be known. Return period is defined as the average
interval of time T within which a flood (or any other extreme event) of given magnitude will
be equalled or exceeded at least one (Patra, 2008). Return period (T) can be calculated, if the
percentage of probability (P) is known, then = 1 . Probability of occurrence (Ro) also
depends on the life span of the structure (n) and can be expressed as
1
= 1− 1− Equation 2-17
Hydrological and meteorological data show no random behaviour. It can be analysed by some
statistical methods based on frequency analysis of precipitation. Mahdavi (2010) stated that
statistical distribution can be employed for studies such as the design of water structure,
the management of water resource and watershed and the determination of effective factors
about hydrologic cycle. Chow et al. (1988) suggested general equation for hydrologic frequency
analysis as:
= + Equation 2-18
Where:
XT : calculated data based on T years return period
k : frequency factor depend on the type of distribution
Basically, standard deviation (σ), coefficient of kurtosis (Ck), coefficient of variation (Cv) and
coefficient of skewness (Cs) are calculated based on the equation in general. Calculation method
for mean (xave) is using arithmetic mean method because Patra (2008) proposed this method for
flat area and assumed the rainfall is in uniform distribution. Log transferred series value is
converted from the series value. Afterwards, normal, log normal, log Pearson type III and
gumbel distributions are suggested for frequency analysis of precipitation by Mahdavi (2010).
Frequency factors (k) are different for each distributions and its own table of distribution factor.
Good fit test also need to be done with Chi square test and Smirnov Kolmogorov test which can
be expressed as (Triatmodjo, 2008):
Literature Review 14
Chi square test.
Chi square test is generated from χ2 equation which is presented as follows:
( − )
= Equation 2-19
Where:
χ2 : calculated chi square value
K : number of class (should be more than or equal to 5)
Ef : expected frequency in one class
Of : actual frequency in one class
χ2 value should be less than χcr2 (using chi square critic table) value for a degree of
confidence which 0.05 is usually used and number of parameter (ρ) for Chi-Square is 2.
Then, degree of freedom (dk) can be calculated as
= − ( + 1) Equation 2-20
= 60 × Equation 2-21
Where:
I : rainfall intensity (mm/hour)
t : rainfall duration (minutes)
Triatmodjo (2008) also suggested to make hyetograph modelling if the there is no hourly rainfall
distribution. Alternating Block Model (ABM) is the simple method to make hyetograph from IDF
curve which is introduced by Chow (1988). Rainfall in IDF is multiplied by the rainfall duration,
then the difference in the calculation between rainfall time and the percentage based on total
rainfall are calculated. The maximum rainfall of this calculation was in the middle of series of
time and the rest of data are arranged in descending order on the right and left of the middle block.
Smedema, et al (1986) proposed that the area reduction factor (ARF) value for small area (equal
or less than 1,000 ha) is 1.0. ARF is usually used for decreasing of discharge in a basin due to
non-uniformity of rainfall coverage of large basin and dynamic storage in drainage system.
Literature Review 15
2.5. Unsteady Flow and Precipitation Runoff Model
Duflow is the software which will be used for hydraulic mathematical modelling. Duflow is
based on the implicit scheme and one-dimensional partial differential equation that describes
non-stationary flow in open channels (Abbott, 1979; Donkers, 1964 cited by Stowa, 2006).
The software also simulates the flow and includes the structures (pumps, gates weirs, etc.) in
the canals. Duflow is also coupled with precipitation runoff module or RAM (Dutch: Regen
Avfoer Module).
Unsteady Flow
Unsteady flow defines as the flow condition changes at any point of fluid and any time.
Principle of continuity and mass equations are needed to formulate the unsteady flow which are
known as the St. Venant Equation. According to Suryadi (2015), calculation of unsteady flow
can be conducted with explicit and implicit scheme. Explicit scheme is calculated the variable
time t+1 based on the value at time t but this scheme becomes unstable when the courant number
is more than 1. Courant number is a dimensionless number which is calculated by the velocity
times the time step and divided by length interval. Implicit scheme provide more stable
calculation that uses the approximation for both time and spaces derivatives in terms of the
dependent variable on the unknown level x+1 and t+1. Grid points for explicit and implicit
scheme can be seen in Figure 2-6. Thus, the upstream and downstream boundary condition and
initial condition (time zero) are needed for the numerical calculation.
Figure 2-6 Grid Points for (a) Explicit and (b) Implicit Scheme (Colin et al, 1976)
Yevjevich (1975) and Chaudhry (1993), cited by Ministry of Public Works and Housing (2009),
describes some assumption to derive the equation which are 1-shallow flow so the vertical flow
velocity can be neglected, 2-channel slope is small and 3-channel bottom is stable. Unsteady
flow can be assumed as one dimensional calculation which can make simplification as
perpendicular flow velocity can be neglected, average shear stress of channel wall can be
applied to all cross sections and Manning or Chezy equation can be used for evaluating shear
stress of canal’s bottom. The equations with lateral inflow effects can be shown as follows:
Literature Review 16
Continuity equation
Figure 2-7 Volume Control for Continuity Equation (Ministry of Public Works and Housing, 2009)
+ = Equation 2-22
+ = Equation 2-23
Momentum equation
Changing of momentum in one time in the channel with in compressible liquid can be
written as:
Or if the side flow is zero, another form of momentum equation can be expressed as:
ℎ | |
+ ( )+ ( )+ =0 Equation 2-25
Where:
Q : discharge (m3/s)
ql : lateral flow (m3/s/m)
v : velocity (m/s)
A : wetted area (m2)
h : water depth (m)
B : surface width of channel (m)
R : hydraulic radius (m)
β : coriolis coefficient (-)
g : gravity acceleration (9.81 m/s2)
So : bottom slope (-)
Sf : energy slope (-)
Literature Review 17
At Duflow, the implicit four point Preismann scheme is usually used to discretize in space and
time. Defining a section ∆xi from node xi to node xi+1 and a time interval ∆t from time t = tn to
time t = tn+1, the discretization of the water level H can be expressed as:
Those expressions approximate the derivatives at the point of references (xi 1/2, tn+θ) as shown
in figure below.
The factor controlling numerical dumping (θ) influences the precision and stability of
calculation, because less θ is more precise but less stable of calculation and vice versa.
Control Structures
1. Pumps
Pumps are operated in full capacity operation for assessing the hydraulic performance of
drainage system. Pump operation is controlled by the water level at the upstream of the pump.
Drainage pump type is used for this study which carried the water from the upstream to
the downstream of the pump. The pump starts to operate when the water level is above the start
level and the pump stops when the water level drops below the stop level. The discharge of
the pump is set based on the pump capacity when the pump works and zero when the pump
stops. Illustration of drainage pump operation can be seen in Figure 2-9.
Figure 2-9 Dependence of Drainage Pump Operation on Upstream Water Level (Stowa, 2006)
Literature Review 18
2. General Structures (Gates)
Gates and weirs in Duflow are operated under the general structures. The flow over
the weirs or through the gates depends on the upstream and downstream water level which
is determined whether its weir flow, free flow or submerged flow. Duflow divided
the flow into 6 categories of flow. Types of flow through general structures are presented
in Figure 2-10.
Literature Review 19
The general equation for general structures can expressed as follows:
= 2 ∆ Equation 2-28
Where:
Q : discharge through general structures (m3/s)
μ : loss coefficient (-)
H : water depth over the sill (m)
ΔH : head difference (m)
g : gravity acceleration (9.81 m/s2)
The loss coefficient, water depth over the sill and the head difference which are working
depends on its type of flow. These variables are determined based on Table 2-3.
Table 2-3 Determination of Variables for General Structures (Stowa, 2006)
= +2 −1 ( − ) Equation 2-29
Literature Review 20
Precipitation Runoff Module
Hydrologic cycle of catchment area is reflected by its water balance. Stowa (2004) described
that Water balance is a balance between incoming water and outgoing water which can be
expressed by the equation below.
+ + = + + +∆ Equation 2-30
Where:
P : precipitation (mm/day)
Qi : incoming flows (mm/day)
Qu : outgoing flows (mm/day)
K : seepage (mm/day)
E : evapotranspiration (mm/day)
W : downward seepage (mm/day)
ΔS : Change in storage in the catchment basin for the reflected time interval (mm/day)
Duflow is using linear reservoir method and effective precipitation for the input. Soil moisture
also take a role in this process, so that the selection of the type of land cover also defines the
runoff that occurs.
The effective precipitation at open water surface is determined by the reduction of evaporation.
Kota Lama is still not using sewage treatment plant and there are not any greenhouses, so
the paved surface for rural areas is applied that causes the precipitation is discharging directly
to drainage canals. The runoff process for unpaved surface are consist of infiltration to
unsaturated zone, percolation into saturated zone and ground water discharge into the drainage
system. Delayed discharge which is drained to the canals is happened because of the resistance
in the soil and the opening. Two parallel Nash-cascades model is selected to describe this
phenomenon by using quick and slow components of linear reservoir methods.
Quick components are the surface runoff, interflow and precipitation to open water. The remaining
effective precipitation which is resulted of unsaturated and saturated zone is the slow components.
Sketch and drainage course of quick and slow components can be seen in Figure 2-11.
Figure 2-11 Sketch (a) and drainage course (b) of quick and slow components (Stowa, 2006)
Literature Review 21
Literature Review 22
Chapter 3
Methodology
3.1. Research Methodology
This research will only analyse and discuss the problems and solutions based on hydraulic
aspects then water quality, social and economic aspects are not going to be considered. The
methodology is divided by several steps which are 1-data collection, 2-first analysis, 3-second
analysis, 4-final analysis and 5-output which is described briefly in Figure 3-1.
Research Methodology
Collection
Data
Design Rainfall
Exisiting Existing Drainage Design Local
Topography Performance Inflow
Fulfill Desired
Second Analysis
Performance?
Estimating the Future
Topography
No
Scenario
Development
Yes
Polder System Clean Canal Full Pump Cap. Full Gate Opening Flap Gate Close Connection New Pump Cap.
Scenario Scenario Scenario Scenario Scenario Scenario Scenario
Final Analysis
The Most
Test Selected Scenario
Appropriate
with Sensitivity Analysis Scenario
Output
Methodology 23
3.2. Data Collection
Data and information that has been obtained through field observation and collection from local
government offices, universities, seminars and workshops in the form of published reports,
studies, scientific papers, proceedings and maps. The following are the explanation of data and
information which were collected:
- Hydrological data
Rainfall data that was collected from Semarang Climatological Station from 1981 to 2006
which is useful for the design rainfall analysis. This station also recorded climatology data
from 1987 to 2006 which is used for analysis in DUFLOW. Hydrological network is used
to locate the nearest hydrological station from Kota Lama. Tidal fluctuation data was
collected from Water Resources Research and Development Center’s reports which are
useful for the analysis in DUFLOW.
- Topography and land subsidence
Spot height data in 2010 was collected which should be converted to topography map for
analysing. Land subsidence rate from 2009 to 2012 was gained for future topography
analysis and tidal influence.
- Base map
Administration and land use map are included in this type of information. The information
is useful for analysing the design local inflow and possibility of development to improve
the water management in Kota Lama.
- Drainage system information
Drainage canal cross sections and network information of Kota Lama were collected
for year 1998, there is no latest information about Kota Lama sub drainage system.
The thickness of sediment and solid waste in drainage canals were collected by sampling
for several drainage canals in Kota Lama area. Retention basin and pumps information was
quoted from the working report of Semarang Water Resources Management, Energy and
Mineral Resources Agency (Dinas PSDA & ESDM Kota Semarang). The data were used
in the making of drainage model and its Duflow network.
- Flood hazards and events
Several flood events in Kota Lama from 2013 to 2015 were quoted from several local web
news that gave the information of inundation depth and locations. Flood hazard map from
Semarang Drainage Master Plan was also collected. The data is useful for analysing the
performance of Kota Lama drainage system.
- Supporting information
Kota Lama land use master plan (RTBL) and Semarang in Figures 2012, 2013 and 2014
were used for the future development analysis for Kota Lama.
Methodology 24
Table 3-1 presents the summary of the data and information which were collected.
Table 3-1 Data Collection
Hydrological Data
1 Rainfall Semarang Meteorology, Geophysics and
Climatology Agency (BMKG Semarang)
2 Climatology Water Resources Research and Center
(Puslitbang SDA)
3 Hydrological network map Water Resources Research and Center
(Puslitbang SDA)
4 Tidal Fluctuation Water Resources Research and Center
(Puslitbang SDA)
Topography and Land Subsidence
5 Land subsidence Bandung Institute Technology (ITB)
6 Spot Height Diponegoro University (UNDIP)
Base Map
7 Administration map Diponegoro University (UNDIP)
8 Land use map Diponegoro University (UNDIP)
Drainage System Information
9 Kota Semarang drainage master plan Diponegoro University (UNDIP)
10 Kota Lama drainage network Semarang Water Resources Management,
Energy and Mineral Resources Agency
(Dinas PSDA & ESDM Kota Semarang)
11 Kota Lama drainage technical information Semarang Water Resources Management,
Energy and Mineral Resources Agency
(Dinas PSDA & ESDM Kota Semarang)
Flood Hazard and Events
12 Flood hazard map of Kota Lama Semarang Drainage Master Plan 2007
13 Number of flood event in Kota Lama Local Web News from 2013 to 2015
Supporting Information
14 Kota Lama land use master plan (RTBL) Semarang Planning Board
(Bappeda Kota Semarang)
15 Semarang in Figures of 2012, 2013 and Semarang Statistics Bureau
2014 (BPS Kota Semarang)
Methodology 25
3.3. Data Analysis
First analysis
First analysis is made based on the collected data which will be used for the next phase of
analysis. The analysis which will be done in this phase are:
a. Existing topography
The spot height data is converted to topography with ArcGIS. World Geodetic System
1984 (WGS 84) UTM zone 49S is used for the reference coordinate for this study.
The topography map is adjusted only for Kota Lama area.
b. Design rainfall
Rainfall data is verified with homogeneity with Mann-Whitney test, independence
with Wald-Wolfowitz test, outlier with Grubbs-Beck test, trend with Spearman’s rank
test, variance consistency with F-test and average consistency with T-test. Then,
verified rainfall data is used for calculating design rainfall with frequency analysis
based on the return period. Normal, log normal, gumbel and log Pearson type III
distribution which are suggested by Mahdavi (2010) are calculated. The suitable
distribution is selected based on Chi Square and Smirnov Kolomogorov test.
The selected design rainfall distribution is converted to the Intensity-Duration-
Frequency (IDF) curve. Then, hyetograph is calculated to have the hourly rainfall
distribution by using Alternating Block Model (ABM) method.
c. Design local inflow
Local inflow of the drainage is calculated based on the design standard in Indonesia
(SNI-03-7065-2005) which is calculated based on 80% of water demand. This step should
be done because Kota Lama sub drainage system is still mixed drainage system.
d. Existing drainage performance
Duflow software is used to analyse existing hydraulic drainage performance and also its
rainfall runoff model. The analysis is performed with the existing drainage scheme,
drainage dimensions based on the observed condition and design rainfall that has been
done before. From this analysis, the causes of flooding in Kota Lama should be noticed
whether coming from land subsidence, sea level rise, the channel capacity and lack of
maintenance or combination of these factors.
Rainfall runoff simulation is run based on the type of land cover which is paved, unpaved
or open water area. The open water area is considered as directly connected to
the drainage system. The precipitation on paved area which is discharge to the canals is
calculated based on evaporation, infiltration and direct runoff to the canals. The rainfall
runoff in unpaved area is calculated based on evaporation and Nash-cascade model for
the infiltration and runoff. The rainfall runoff is also run with Duflow.
Assessment of drainage system sustainability on technical and scientific performance
is also done in this phase. The indicator which will be used are referred to the Minister
of Public Works and Housing Regulation No. 14/2010 regarding Minimum Service
Standards, No. 12/2014 regarding Urban Drainage System, Guideline of Drainage
Network Assessment and Semarang Drainage Master Plan 2007 were described in
Table 3-2. After the assessment, it is clear that the main causes of the flood is the poor-
performance of the drainage system.
Methodology 26
Table 3-2 Proposed Assessment of Existing Drainage System Sustainability Indicators for Kota Lama
Second analysis
The next phase of the analysis is analysis in estimating the future topography and scenario
development which can be described as follows:
a. Estimating the future topography
The future topography is estimated based on the occurrence of land subsidence
phenomena. This is done because of the effects of land subsidence that occurred in the
study area.
b. Scenario development
Some scenarios are developed based on the causes in study area which are cleaning
the canals and retention basin, using several pump capacities or hydraulic structures,
simulating the effects from development of Banger Polder and developing polder
system for Kota Lama.
Final analysis
The final analysis will be conducted by doing:
a. Selecting the most appropriate scenario
The scenario that has been developed is assessed with the same indicator which is used
to assess the existing drainage system. The most appropriate scenario is chosen with
the highest score of the assessment. The implementation phases may also be done
through this analysis.
b. Sensitivity analysis
The analysis is be done to know the uncertainties of canal roughness for the selected
scenario. Three different canal roughness is used for calculating which are minimum,
normal and maximum of roughness coefficient for the same canal material in
the study area.
27
28
Chapter 4
Study Area
4.1. Kota Lama as UNESCO Heritage
Semarang has now developed into a modern city with a population of around 1.5 million
inhabitants. However on the other hand, Kota Lama has been a witness to the history of
Semarang City which has been maintaining the continuity of European-style colonial buildings.
Unfortunately, Kota Lama is the home of 105 old buildings are not all well maintained but there
are at least 50 buildings are still well maintained.
Actually, the government has established regulations to preserve the historical area such as Kota
Lama Semarang from deterioration due to aging and the current situation of the development.
The government with some foundations has been tried to attract the attention of the world and
revive Kota Lama. Moreover, they also took the initiative to nominate Kota Lama as one of the
UNESCO heritage site. Justifications for becoming UNESCO heritage are:
Kota Lama Semarang was grown as multicultural and international trade city in
Indonesia’s colonial age;
Kota Lama Semarang reflects the mixture of influence that can be seen from the
uniqueness of the building architecture, cultural mixing and landscape of the region.
According to UNESCO (2015), until these days, Kota Lama has been transformed into a laboratory
of urban development for the world and deserve to be preserved because the unchanged of urban
lay out, rich in architectural masterpiece and its adaptability to the technology.
Study Area 29
4.2. Kota Lama Area
Kota Lama is located in two districts which are Semarang Utara and Semarang Tengah.
From the sea shore, the distance to Kota Lama is only about 1.5 km. Based on Regional
Regulation of Semarang City No. 8/2003 regarding Spatial and Environment Planning of Kota
Lama, the total area of Kota Lama Regional Plan is about 40 ha which consists of 31 ha of Kota
Lama area and 9 ha of influenced area. Boundaries of Kota Lama Regional Plan are:
1. Tawang Railway Station and the northern rail line (North);
2. Haji Agus Salim Street (South);
3. Kolonel Sugiyono Street up to Mpu Tantular Street and Semarang River (West);
4. Ronggowarsito Street, Permasan Village and Grogolan Vilage (East).
However, the boundaries for Kota Lama are:
1. Merak Street (North);
2. Sendowo Street (South);
3. Semarang River and Sleko Region (West);
4. Cendrawasih Street (East).
Then, the boundary for influenced area is boundary outside the boundary for Kota Lama until
the boundary for Kota Lama Regional Plan, see Figure 4-2.
Figure 4-2 Area of Kota Lama Regional Plan (Regional Regulation of Semarang City No. 8/2003)
Study Area 30
The area of Kota Lama which was measured using ArcGIS with Open Street Map as base map,
Google Earth and the area in Regional Regulation of Semarang City No. 8/2003 shows
difference of area whereas the boundaries that is used to measure has followed the regional
regulation. Open Street Map and Google Earth showed that the area of Kota Lama is 23.8 ha
where there is a difference of 7.2 ha with the regional regulation. Based on the discussion with
the local authority, Kota Lama with the area of 23.8 ha will be used in this study.
Study Area 31
4.4. Administrative Region
According to Semarang Drainage Master Plan 2007, Kota Lama and Kota Lama sub drainage
system are in two sub regencies, namely Semarang Tengah and Semarang Utara. Semarang
Utara area is 57.9% of the total area of Kota Lama sub drainage system. The administrative
division of the area can be seen in Figure 4-4.
Study Area 32
Figure 4-5 Land Use of Kota Lama Sub Drainage System
Population Density
Sub Regency Employees
(Inhabitants/km2)
Semarang Tengah 11,596 49,125
Semarang Utara 11,671 69,364
4.7. Hydrology
Kota Lama is in tropical climate area and the rainy season occurs during December – May and
June – November for dry season. Based on the Semarang Rainfall Station from 1981 to 2006,
the maximum rainfall that is occurred is 245 mm/day which occurs in February. Based on
Witteveen+Bos (2008), cited by Ministry of Public Works and Housing (2009), the average
daily evaporation is 4.5 mm/day. The hydrological characteristic of the area is presented in
Table 4-2 and Table 4-3.
Study Area 33
Table 4-2 Semarang Maximum Daily Rainfall of 1981 - 2006
Month Evaporation
(mm/day)
January 3.6
February 3.8
March 4.0
April 4.2
May 4.2
June 4.2
July 4.9
August 5.5
September 6.0
October 5.6
November 4.5
December 3.8
Study Area 34
Figure 4-6 Example Semi Diurnal Tides in Semarang (http://www.ukho.gov.uk/)
Figure 4-7 Tidal Flood in Kota Lama Sub drainage system (Semarang Drainage Master Plan, 2007)
Study Area 35
The master plan also noted that local flood which is occurred as a result of high rainfall intensity
also happens. The result of the study stated that there are two large areas of inundation which
are 4.0 ha at residential area near Tawang Railway Station and 3.3 ha near Bubakan roundabout.
Inundation depth usually occurred about 20-75 cm at several places in Kota Lama with 2 hours
to 24 hours of duration. Local flood map of Kota Lama sub drainage system can be seen in
Figure 4-8. From those flood events (tidal and local flood), Semarang Drainage Master Plan
2007 provided flood prone map also which is presented in Figure 4-9.
Figure 4-8 Local Flood in Kota Lama Sub Drainage System (Semarang Drainage Master Plan, 2007)
Figure 4-9 Flood Prone Map in Kota Lama Sub Drainage System (Semarang Drainage Master Plan, 2007)
Study Area 36
However, it is unfortunate absence of a complete recording flood events regarding
rainfall intensity, extensive flooding and water level when flooding in Kota Lama. Rainfall
which was recorded by Simongan Hydrological Station in 12 February 2015 was 161 mm/day
(see Figure 4-10). This event affected Merak Street and Tawang Street for 20 cm and 40cm of
inundation as reported by the local web news. Unfortunately, the inundation area and duration
of each events was not recorded. The flood events in Kota Lama sub drainage system were
quoted from local web news in Table 4-5.
Table 4-5 Flood Events in Kota Lama Sub drainage system
Inundation Time of
Location Sources
Depth (m) Occurrence
Inside Kota Lama
Merak Street 0.2 12 February 2015 http://www.antaranews.com
Letjen Suprapto Street 0.6 03 March 2013 http://beta.mediaindonesia.com
Mpu Tantular Street 0.3 04 January 2015 http://daerah.sindonews.com
Ronggowarsito Street 0.3 04 January 2015 http://daerah.sindonews.com
Tawang Street 0.4 12 February 2015 http://www.antaranews.com
Outside Kota Lama
MT Haryono Street 0.3 23 January 2014 http://www.antaranews.com
KH Agus Salim Street 0.5 12 February 2015 http://www.antaranews.com
Bubakan Roundabout 0.7 23 January 2014 http://www.antaranews.com
Study Area 37
Study Area 38
Chapter 5
Figure 5-1 Study Area for Urban Drainage Plan (JICA, 1993)
Design scale for urban drainage based on JICA (2013) is presented in Table 5-2. According to
this table, there were 7 canals with 10-year return period and 12 canals with 5-year return
period. Semarang River which is located on the western part of Kota Lama was design for 10-
year return period. Design of primary drainage canals is 10-year return period. 5-year return
period suggested for secondary drainage canals. Design of pumps is using 12 hours rainfall with
5-year return period.
Table 5-2 Design Scale 1993 Master Plan (JICA, 1993)
=( . ) .
for t 2 hours
Equation 5-1
=( . ) .
for t 2 hours
Equation 5-3
=( . ) .
for t 2 hours
Equation 5-5
Where:
I : point rainfall intensity (mm/hour)
t : rainfall duration time (minutes)
K.Mangkang Wetan
K.Plumbon
K.Bringin
K.
K.Baru
K.Banger
Te
K.Siangker
ng
K.Randu Garut
Madukoro
K.Sringin
K. ga
K.Karang Anyar
ng
K.Asin
Si
K.Semarang
ak
K.Tapak
K.Tugu Rejo
K.Babon
K.Buntu
K.Jumbleng
Karangayu
Ronggolawe
K.Tambakharjo
Bendung Simongan
Saluran Sabuk
Bendung Pucanggading
Legend:
Keterangan :
Bendungan Jatibarang Bendungan Garang Rivers
Sungai Bendungan Babon
River’s
TanggulDike
Sungai
Bendungan Kripik
Coastal’s Dike
Tanggul Laut
Belt Canal
Saluran Sabuk
Polder
Sistem System
Polder
Bendungan Mundingan
Reservoirs
Embung / Waduk
Figure 5-2 Planned Drainage System Scheme of Semarang in 2007 (Semarang Planning Board, 2007)
BKB BKT
Figure 5-4 Google Map image of Semarang, East Flood Way (BKT) and West Flood Way (BKB)
Figure 5-5 Sketch location of Semarang River, Baru River, Asin River and Its Infrastructures
Figure 5-6 Condition of Kali Semarang Pump Station and Retention Basin in 16/11/2015
Banger Polder
Banger Polder is located on the west side of Kota Lama subsystem (Figure 5-7). Covering
an area of 527 ha and approximately 84,000 residents served by this polder. However, this
polder system has not been fully developed. All the planned pumps has been arrived but still
not tested and operated. Banger retention pond and western ring dike have not been constructed.
Tawang Retention Basin Tawang Retention Basin Inlet Tawang Retention Basin Outlet
Since 2012, the new drainage scheme for Central Semarang drainage system has been
developed, Kota Lama does not connect to tidal fluctuation any more from Semarang River
because all the outlets of Semarang River that connected to the sea has been closed. National
road on the north of Kota Lama has also been raised by 1 m to prevent tide of the sea comes
through the mainland. However, Kota Lama drainage system is still connected to Banger sub
drainage system which is connected to Banger River and the tidal fluctuation still happens in
Banger system and might influences Kota Lama as well.
There are seven outlets of Kota Lama sub drainage system which are Baru River pumps,
two outlets (vertical gate and free outlet) in Kota Lama and other four outlets outside
Kota Lama (a vertical gate and 4 free outlets).
Baru River Pump consists of 6 units of submersible pump with a capacity of 400 l/s for each
unit, 1 unit axial pump of 100 l/s and also equipped with 2 units of vertical gate with 1.5 m for
each gate. There is no water level measurement at the pump station. Based on the interview to
the pump operator, the operator has lost his flood manual and he only operates the pump based
on his previous experiences. Only 3 pumps start when water reached the upper black marked
(marked of high water level) in the canal or about 50 cm below the surface and stop when water
reached the lower black marked about 80 cm below the surface (see Figure 5-10). Vertical gate
near Berok Bridge is consisted of 2 units of vertical gate which is a new structure. There is no
water level measurement at the gate (Figure 5-11).
Pump Start
Pump Stop
Existing hydraulic performance of drainage canals of Kota Lama is low which can be seen
from the accumulation of solid waste and sedimentation in the canals, drainage canals are higher
than the streets and blocked inlet to the canals (see Figure 5-12, Figure 5-13, Figure 5-14,
Figure 5-15 and Figure 5-16).
±45 cm ±95 cm
In fact, some measurements were done by using the simple gauge into the drainage canal, average
sediment thickness in the drainage canal is about 34.2% of canal capacity. The detail and
calculation of sediment thickness sampling is presented in Appendix B and location of sample
points can be seen in Figure 5-17. The impression for Kota Lama drainage are:
1. all the canals’ in Kota Lama are concrete canals,
2. solid waste and sediments fulfilled part of the drainage canals’ capacity,
3. the houses are below the road elevation in some places.
Topography Analysis
6.1. Coastline
Ministry of Research and Technology (2009), cited by Abidin et al. (2013) discovered that due
to the coastal sedimentation the coastline of Semarang has gone forward 1.64 km from 1741 to
2007. These changes roughly can be said that the coastline has moved forward for 6.2 m/year
because of sedimentation and land reclamation. Kota Lama has been established in 1705 which
was marked by the construction of Vijfhoek Fort. Land subsidence phenomena that occurred in
Kota Lama is most probably not derived from natural consolidation of young alluvium soil but
due to over exploitation of deep ground water.
1.64 km
Kota Lama
Figure 6-1 Coastline Change in Semarang (Ministry of Research and Technology, 2009)
Topography Analysis 51
6.2. Topography of Semarang
There is some data available concerning Digital Elevation Model (DEM) which is provided by
United States Geological Survey (USGS). USGS provides elevation data with worldwide coverage
at high resolution dataset of 1 arc-second (30 meters) or 30 x 30 m2 per grid. SRTM 1 arc-second
data set was released starting on 24 September 2014. Overview of topographical conditions of
Semarang is made with Semarang area which is obtained from Ministry of Public Works and Public
Housing in 2010. The topographical condition of Semarang is presented in Figure 6-2 and it is
known that Kota Lama is laying on about 0.00 m+Mean Sea Level (MSL).
Topography Analysis 52
Figure 6-3 Topography Map of Kota Lama
Kota Lama
Topography Analysis 53
Impacts of land subsidence can also be seen in Kota Lama drainage system area which
is presented in Figure 6-5. There is an observation point for land subsidence measurement in
the area which was conducted by Bandung Institute Technology from 2009 to 2012 (Figure 6-6).
Figure 6-5 Land Subsidence in Kota Lama Sub Drainage System Area
Figure 6-6 Land Subsidence Measurement Points in Kota Lama Sub Drainage System Area
Log and log relation between amount of land subsidence and years of BM16 point is presented
in Figure 6-7. The result shows that the land subsidence has a tendency to increase in time.
If there is not any measure in 50 years, the land subsidence might be occurred about 2.7 m.
Topography Analysis 54
Figure 6-7 Land Subsidence Rate at BM16 Point
Figure 6-8 Increasing the number of registered wells and ground water extraction in Semarang (Murdohardono et al, 2007)
Topography Analysis 55
Figure 6-9 Land Subsidence Estimation for Bandarharjo-Poncol Trajectory (Sarah et al, 2012)
Sarah et al. (2012) simulated three scenarios which is representing some conditions such as
a) only the natural consolidation scenario, b) decreased ground water level and c) decreased
ground water level and building loads. It was explained that before 2020 the land subsidence is
more dominated by decreased groundwater level of 85%-95% and building loads of 5-16%,
then the natural consolidation will start to dominate at 2020-2060. Then, with the calibrated
data of 2002-2007, the natural consolidation process will be stopped in range year of
5448-11065 which are all the pore water pressure has been dissipated. Land subsidence will be
occurred until the end of consolidation period which is dominated by natural consolidation of
64-78%, decreased groundwater level of 22-27% and building loads of 2-8%.
If the ground water extraction is not regulated strictly and the domestic, municipal and industrial
water provision is not supplied and people of Semarang still use the ground water to fulfil their
demand, the occurred land subsidence will be deeper (scenario B). The difference between
scenarios shows large difference of land subsidence occurrence in the future years. The graph
of land subsidence estimation is shown in Figure 6-9.
56
Chapter 7
Stationarity
Rainfall
Homogeneity Independence Outlier
Duration Variance Average
Trend
Consistency Consistency
Independent Consistent -
5 Minutes Homogen Ok Trend Consistent
(Random) Stable Variance
Independent Consistent -
10 Minutes Homogen Ok No Trend Consistent
(Random) Stable Variance
Independent High Consistent -
15 Minutes Homogen No Trend Consistent
(Random) Outlier Stable Variance
Independent Consistent -
30 Minutes Homogen Ok No Trend Consistent
(Random) Stable Variance
Independent Consistent -
45 Minutes Homogen Ok No Trend Consistent
(Random) Stable Variance
Independent Consistent -
1 Hour Homogen Ok No Trend Consistent
(Random) Stable Variance
Independent Consistent -
2 Hours Homogen Ok No Trend Consistent
(Random) Stable Variance
Independent Consistent -
3 Hours Homogen Ok No Trend Consistent
(Random) Stable Variance
Independent Consistent -
6 Hours Homogen Ok No Trend Consistent
(Random) Stable Variance
Independent Consistent -
12 Hours Homogen Ok No Trend Inconsistent
(Random) Stable Variance
There are some data that are not valid such as 5 minutes duration and 12 hours duration.
The data of 5 minutes duration is declared invalid because the data is following particular trend.
Average inconsistency is found in 12 hours duration data, so that this data will not be used.
High outlier is also found in 15 minutes duration data. However, 15 minutes duration data is
still used as the data is stationary.
Frequency Analysis
Frequency analysis is useful to determine the design of hydraulic structures. This analysis is
conducted to determine the probability of occurrence of maximum rainfall events on a certain
length of time. This maximum rainfall usually calls as design rainfall. The probability
of occurrence (P) is always associated with a return period (T) in which a certain amount
of rain will be surpassed. This does not mean that the rainfall with a specific return period will
only happen once, but the rainfall can be exceeded once in a period which is determined.
Probability of occurrence in accordance with a lifetime of hydraulic structure (R) also can be
known from this analysis.
Intensity-Duration-Frequency (IDF)
Table 7-4 is showing the result of IDF calculation and its regression formula for each return
period. IDF calculation graph can be seen in Figure 7-1. Power regression is selected because
it has got the best value of R2. Therefore, the intensity of certain minutes besides the existing
duration can be calculated based on the regression formula.
Table 7-4 IDF Table of Semarang Rainfall Station
Wastewater
Water
Population Average Peak
Land Use Consumption
(capita) 3 Peak 3
(l/c/day) (l/c/day) (l/day) (m /s) (l/c/day) (l/day) (m /s)
Factor
Semarang Tengah
Residential 4579 120 96 439578 0.0051 1.5 144 659366 0.0076
Offices 1368 50 40 54720 0.0006 1.5 60 82080 0.0010
Semarang Utara
Residential 4260 120 96 408968 0.0047 1.5 144 613452 0.0071
Offices 469 50 40 18779 0.0002 1.5 60 28169 0.0003
Total 922045 0.0107 1383067 0.0160
The result shows that total of average and peak wastewater discharge consecutively are
0.0107 m3/s (1.1 mm/day) and 0.016 m3/s (1.6 mm/day). Average and peak wastewater
discharge are less than 1% compare to rainfall in 3 hours of 25 years return period which is
166 mm/day. The local inflow for modelling only input for node which have not got are
precedence sections.
Number of
Features
Features
Nodes 24
Sections 27
Cross Sections 50
Types of Canal 28
Area 14
Vertical Gates 3
Pumps 2
1 /
= Equation 7-1
Where:
C : Chezy roughness coefficients (m1/2/s)
n : Manning roughness coefficients (-)
R : hydraulic radius (m)
c) Service Area, Rainfall and Tidal Fluctuation Settings
Service area is defined by using the flow direction on the drainage system map.
Land cover which has been defined in the previous sections is set in this step. Land cover
distinction for every service area is presented in Appendix F.
Rainfall intensity is assigned based on the 3 hours hyetograph for several return period
(10 years, 25 years, 50 years, 100 years and 200 years). For existing condition, assigned
rainfall is 166 mm/day which is 25 years return period and rainfall starts at 14.00 to 16.00.
Evaporation is set constant for 3.8 mm/day or the same month of the highest rainfall.
Assigned design rainfall in Duflow is presented in Figure 7-5.
HHWS and LLWS of Semarang is on +0.5 m+MSL and -0.5 m+MSL with semidiurnal type
of tides. In Duflow, the highest high water level of spring tide occurs is set at 03.00 and
15.00. Assigned tidal fluctuation in Duflow can be seen in Figure 7-6.
Cross Section
A-A Sliding Gate
A
Gate level Surface level Surface level Gate level
Flow Height of
Height of Whirlpool
Whirlpool
Canal’s bottom level Canal’s
bottom level
A Gate Width
Figure 7-7 Long section and cross section sketch of the gate
f) Calculation Settings
The model is set for calculating in a day. Time step of computation flow is done for every
1 second and the output is every 5 minutes. Damped is selected for calculation of advection
term. The Froude term is considered by selecting “damped”, but its absolute value will not
exceed the friction term. The factor controlling numerical dumping (θ) of the model is 0.85,
so it is expected to have enough precision and stable calculation, because less theta is more
precise but less stable of calculation and vice versa.
g) Benchmark and Score Determination
Technical and scientific performance is one of the categories in sustainable urban
drainage system. Benchmarks which are used based on the Indonesian National Standard
and several literatures that are provided by the Government. The benchmarks can be
seen in Table 7-9.
Table 7-9 Benchmark for Technical and Scientific Performance Assessment of Existing Kota Lama Sub drainage system
Figure 7-8 Tidal Fluctuation Effects at Merak Street for Existing Condition
The highest water level on Merak and Cendrawasih Street Cross Section is 0.51 m+MSL or
0.22 m above the surface at 15.50 which happens after spring tide and heavy rainfall. According
to the simulation, the inundation is occurred for 0.22 m during the 2 hours and 50 minutes. If it is
compared to the flood event in 12 February 2015 which was 0.2 m of inundation for 161 mm/day
of rainfall, the simulation shows 10% difference which is still acceptable. This is showing that
the assumptions that are used may described the situation on the field. The comparison is
presented in Table 7-10 and the condition of the water level in the main drainage is presented in
Figure 7-9 and Figure 7-10.
Table 7-10 Comparison of Simulated and Real Events
Flood
No Flood
Figure 7-10 Simulation Result of Existing Condition for Main Drainage of Kota Lama
The pump at Baru River pump station must work to draw water outside the area as a consequence
of the closed gate due to high water level at Baru River (boundary water level). Figure 7-11 shows
pump operation simulation for Kota Lama. For the high rainfall intensity and high tides, the pump
operates from 11:20 to 8:45 in the next day or operates for 21 hours and 25 minutes which is
shown in yellow section. The green section is the pump response to the initial water level.
The pump operation for the hydraulic response and the next high tides can be seen in blue section.
Operating hours of pump becomes longer or not only during the rainfall because of the tidal
fluctuation effects from Banger sub drainage system.
According to the simple survey that has been conducted the average sediment depth in the canals
are 34.2% of canal capacity. The Drainage system in Kota Lama is on the flat area, so it is possible
that the height of the sediment in canals are also the same in the retention basin. The existing volume
of retention basin is 13,943 m3 or less than the 15,000 m3 of effective volume.
Review of drainage system master plan which is discussed in the previous chapter shows that
the existing design period is still for 5 years return period or less than the recommended design
in Semarang Drainage Master Plan 2010 which is 10 years return period. The highest maximum
velocity in the drainage system is 0.25 m/s which is still accepted due to the concrete canal
construction with maximum velocity of 3.0 m/s. In the other side, the lowest velocity is not
expected to occur in the system which is 0.08 m/s or less than 0.6 m/s. It shows that the canal
is very susceptible to the occurrence of sediment.
According to the simple survey that has been conducted the average sediment depth in the canals
are 34.2% of canal capacity. The Drainage system in Kota Lama is on the flat area, so it is possible
that the height of the sediment in canals are also the same in the retention basin. The existing volume
of retention basin is 13,943 m3 or less than the 15,000 m3 of effective volume.
Based on those analysis, the existing condition of Kota Lama drainage is at low performance.
The drainage system only meets two from nine criteria of good technical and scientific
performance. Therefore, the score of existing condition is 15. The resume of technical and
scientific performance assessment of existing condition is presented in Table 7-11.
65.8% of canal
Canal capacity 80% of canal capacity 1
capacity
Total 15
If the assumed situations are remain the same and no measures taken, Kota Lama will be remain
inundated when the water level at the boundary condition is high and highest high water level
of tidal occurs through Banger sub drainage system. Even for the rain with 2 years return period,
this system cannot control. The graph relationship between water level at Merak Street drainage
and rainfall intensity of “do nothing scenario” is presented in Figure 7-13.
Scenario Analysis
Kota Lama needs several measures to improve the performance of existing condition.
In accordance with the assessment that has been discussed, there are several measures that
will be simulated which are full pump capacity, cleaning the canal and retention basin, flap gate
operation at every outlets, restricting incoming water from Banger sub drainage system and
propose new pump capacity for Baru River Pump. The other simulation that should be done
what if the polder system for Kota Lama is fully developed.
8.1. Scenario 1: Cleaning the Canals and Retention Basin
The first scenario is cleaning all the canals and retention basin in Kota Lama. Several
assumptions and drainage scheme are the same as the simulation of existing condition.
The difference are on the canals’ condition due to sediment removal in the canals, so that
the canals become deeper. The canals’ roughness also become smoother because the absence
of sediment at the bottom and wild plants at the cracking spots. It is assumed that the canals
condition are unpolished concrete canals with manning coefficient of 0.017. The converting
calculation of manning to Chezy coefficient can be seen in Appendix E.
Clean canals impact the increasing of discharge capacity and flow velocity. Theoretically,
a comparison can be made by using chezy formula flow velocity for the existing condition and
clean canal scenario. If the relationship between hydraulic radius and Chezy coefficient is
graphed (Figure 8-1), it is shown that cleaning scenario indicates additional discharge capacity
and flow velocity for the same canals' bottom slope. The calculation results, this scenario
provides additional flow velocity with average of 30.7% and 52.8% for discharge capacity.
Scenario Analysis 71
Cleaning the canal can accelerate tidal to reach the center of Kota Lama. As in Merak Street
main drainage, tidal reaching is faster up to 20 minutes compared to the existing conditions.
The highest water level which is occurred due to high tide and rainfall also reduced by 0.04 m.
However, the highest water level is occurred at 15:50 and the water level is 0.47 m+MSL at
Merak Street or inundated of 0.18 m. Tidal fluctuation effects at Merak Street main drainage
can be seen in Figure 8-2.
For the same rainfall (25 years return period), the inundation area is only reduced 0.6 ha
compared to the existing condition. Total of inundation area is 20.6 ha with maximum
inundation of 0.21 m at the cross section of Tawang and Merak Street. This cross section also
the connection point of drainage from Kota Lama and northern side of Kota Lama sub drainage
system. However, this scenario can reduce the inundation depth above 0.2 m from 30% to 3%.
Inundation duration is 3 hours or only better 10 minutes from the existing condition.
The inundation map for this scenario is presented in Figure 8-3.
Figure 8-3 Inundation Map of Kota Lama for Scenario 1: Cleaning Canal and Retention Basin
Scenario Analysis 72
The working hours of pump also increase to 24 hours which can be operated alternately with
the other 3 pumps of 1.2 m3/s. The addition of working hours of pump due to the water can
reach the pumping station rapidly but the outflow of the pump cannot overcome the inflow
discharge, so the water is stored in the drainage network and inundated the area. This is in
accordance with the principle of water balance with the following equation.
∆ =∑ −∑ Equation 8-1
Where:
S : storage capacity (m3/s)
O : total outflow (m3/s)
I : total inflow (m3/s)
This scenario meet four of nine criteria and the score is increasing 8 points or become 23
although the inundation still occurs. The addition score due to the increasing of the canals and
retention basin capacity. The resume for this scenario can be seen in Table 8-1.
Table 8-1 Technical and Scientific Performance Assessment of Scenario 1: Cleaning Canal and Retention Basin for Kota Lama
100% of canal
Canal capacity 80% of canal capacity 5
capacity
Inundation
Less than 2 hours 3 Hours 1
Duration
Performance Design return 10 years (for
System reliability 5 years 1
reliability failures period secondary canals)
Maximum flow
Canal strength 3.0 m/s (concrete) 0.19 m/s 5
velocity
System durability
Canal Minimum flow
0.6 m/s 0.11 m/s 1
sedimentation velocity
Total 23
Scenario Analysis 73
8.2. Scenario 2: Full Pump Capacity
Full pump capacity scenario is intended to use the pumps with planned capacity of 2.5 m3/s.
The other assumptions also remain the same. This scenario is also simulated in two conditions
which are canals with sediment and clean canals.
a. Canals with sediment and waste (Scenario 2a)
Duration of tidal reaching Kota Lama is longer than the existing condition, the lag time is
up to 3 hour. Full pump capacity also can reduce the high water level due to tidal fluctuation
and rainfall. For instance, the high water level at 16:10 on Merak Street reduces to
0.36 m+MSL. However, the inundation is still occurred of 0.07 m for this scenario. Tidal
fluctuation effects at Merak Street for this scenario is shown in Figure 8-4.
If it is compared to the existing condition, the scenario can reduce inundation depth up to
42% on Merak Street until Baru River Pump Station (see Figure 8-5). This happens because
the pump provides greater outflow thus providing larger storage before high tide and
rainfall occurs.
Figure 8-5 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 2a
Scenario Analysis 74
working for 4 hours and 50 minutes which is 77% faster than the existing condition.
The pump operation simulation and inundation map for scenario 2a are shown in
Figure 8-6 and Figure 8-7.
Figure 8-7 Inundation Map of Kota Lama for Scenario 2a: Full Pump Capacity and Canal with Sediment
Scenario Analysis 75
Figure 8-8 Tidal Fluctuation Effects at Merak Street for Scenario 2b
Water level on Merak Street until Baru River Pump Station shows that there is
no inundation in Kota Lama. However, drainage in Kota Lama has not got free board or
in full bank condition so that the drainage system does not give the flexibility aspect and also
drainage canals between Kota Lama and Baru River Pump Station (B-C) is inundated up to
4 cm. Figure 8-9 is showing water level on Merak Street until Baru River Pump Station.
Figure 8-9 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 2b
No inundation area reduce significantly for this scenario which is 19.5 ha (82%).
The highest inundation depth is 0.4 m at the cross section of Tawang and Merak
Street. Inundation that happens is 10 minutes longer than scenario 2a or occur of 1 hour
and 35 minutes. The pump is working for 9 hours which is 58% faster than the existing
condition. The scenario is still better than the existing condition because it can reduce
the inundation duration by 50%. The pump operation simulation and inundation map for
scenario 2b can be seen in Figure 8-10 and Figure 8-11.
Scenario Analysis 76
Figure 8-10 Pump Operation Simulation of Scenario 2b
Figure 8-11 Inundation Map of Kota Lama for Scenario 2b: Full Pump Capacity and Clean Canal
The pump is working almost twice longer than scenario 2a or working for 9 hours.
This happens because the water level which is coming from high tides reach Baru River
Pump Station is faster so that the pump also works earlier. With pump capacity greater than
Scenario 1, it has an impact on storage for drainage system is also larger and can reduce high
water levels that occur during high tides and rainfall. Even though, the capacity of the pump
is not enough of removing the excess water from the system when it is in high tide and rain
fall in the same time which can be seen with the inundation before pumping station
Scenario Analysis 77
According to those conditions, the full pump capacity with clean canals has bigger score with
27 (6 of 9 criteria) and 19 for the canals with sediment (4 of 9 criteria). Although, the full pump
capacity with clean canals scenario gives smaller area of inundation, this scenario has
a weakness for longer pump working. The resume for Scenario 2: Full Pump Capacity can be
seen in Table 8-2.
Table 8-2 Technical and Scientific Performance Assessment of Scenario 2: Full Pump Capacity for Kota Lama
Total 19 27
Scenario Analysis 78
Figure 8-12 Tidal Fluctuation Effects at Merak Street for Scenario 3a
Longitudinal section from Merak Street until Baru River Pump Station (Gate) shows a draw
down curve (see Figure 8-13). This occurs because the flow is act as weir flow which the
gates does not influence the discharge. When viewed in more detail in Figure 8-14, it is
shown that the upstream water level (Kota Lama drainage) is -0.03 m+MSL which is higher
than the downstream water level (boundary condition, Baru river) of -0.12 m+MSL.
Duflow read this situation on the condition IV where the downstream water depth is higher
than 2/3 of upstream water depth.
Figure 8-13 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 3a
gate
-1.12 m+MSL
(floor level)
Upstream Downstream
Kota Lama drainage Baru River
Figure 8-14 Sketch of Water Level Condition at the River Baru outlet for Scenario 3a at 15:55
Scenario Analysis 79
Almost the entire area (99%) of Kota Lama can be free from inundation. The highest
inundated depth is only 0.02 m which is lasted for 40 minutes. The inundation map for
scenario 3a is presented in Figure 8-15.
Figure 8-15 Inundation Map of Kota Lama for Scenario 3a: Full Gate Opening and Canal with Sediment
Scenario Analysis 80
With full gate opening, the flow is act as weir flow and it also gives a draw down curve
flow based on the longitudinal section from Merak Street until Baru River Pump Station
(Gate) which is presented in Figure 8-17. The condition is included as condition IV
in Duflow where the downstream water depth (boundary condition, Baru river) of
1 m is higher than 2/3 of upstream water depth (Kota Lama drainage) of 0.7 m. The sketch
of water level condition at the gate can be seen in Figure 8-18.
This scenario can cope the inundation problem in Kota Lama for rainfall of 25 years
return period and even could give freeboard in the canal. Freeboard which is provide is
up to 0.25 m below surface level or more deep within 5 cm of the freeboard that is required
by the government.
Figure 8-17 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 3b
gate
-1.82 m+MSL
(floor level)
Upstream Downstream
Kota Lama drainage Baru River
Figure 8-18 Sketch of Water Level Condition at the River Baru outlet for Scenario 3b at 15:55
Scenario 3a and 3b are only limited with the water level of boundary condition (Semarang and
Baru River) which is regulated at 0.3 m below the surface. Some simulations are also done for
several different water level of boundary condition (0.1, 0.2, 0.3 and 0.5 m below the surface)
to know how the water level at boundary condition affects water level in Kota Lama. The result
of simulation or downstream and upstream relations can be seen in Figure 8-19.
Scenario Analysis 81
Referring to the graph, it can be seen that the full gate open and clean canal scenario can provide
Kota Lama for free of inundation even when the water level at boundary is only 0.1 m below
the surface. However, full gate open and canal with sediment shows that Kota Lama starts to
inundate or drainage canal is in full bank condition when the water level at boundary is 0.3 m.
Figure 8-19 Downstream and Upstream Relations for Scenario 3: Full Gate Opening
The highest velocity is happened just before the gate. Maximum velocity at scenario 3b
is lower than scenario 3a, whereas 3b scenario is a clean canal scenario. The highest water level
at the outlet of both scenarios are in the weir flow condition IV with the following equation.
= 2 ∆ Equation 8-2
Where:
μ : discharge coefficient
B : gate width (m)
H : water depth at gate (m)
g : gravity acceleration (m/s2)
ΔH : difference upstream and downstream head (m)
Discharge coefficient is assumed as 1 or there is no loss for this simulations. Gate width and
opening for both scenario are the same and the only difference is the difference of upstream and
downstream head. According to the calculation, discharge of scenario 3a (4.4 m3/s) is smaller
than scenario 3b (5.2 m3/s). However, the wetted area of scenario 3b is bigger than scenario 3a
which generates the flow velocity of scenario 3a (1.1 m/s) is faster than scenario 3b (0.9 m/s).
According to the analysis and simulations, full gate open and canal with sediment gives a good
performance, but unfortunately this scenario cannot provide freeboard as required and drainage
canal on the fullbank state. This scenario can meet 4 of 9 criteria with a score of 19, because it
does not give Kota Lama are completely free from inundation. Full gate open with clean canal
can provide Kota Lama free of inundation and also provide freeboard in the canals as required.
Therefore, this scenario can satisfy 7 of 9 criteria with a score of 37. The scoring result for
Scenario 3: Full Gate Opening is shown in Table 8-3.
Scenario Analysis 82
Table 8-3 Technical and Scientific Performance Assessment of Scenario 3: Full Gate Opening for Kota Lama
Total 19 37
Scenario Analysis 83
Figure 8-20 Tidal Fluctuation Effects at Merak Street for Scenario 4a
Figure 8-21 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 4a
Flap gate
(surface level)
0.18 m+MSL
-0.01 m+MSL (downstream wl and gate level)
(upstream wl) -0.12 m+MSL
-1.12 m+MSL
Upstream Downstream (floor level)
Kota Lama drainage Baru River
Figure 8-22 Sketch of Water Level Condition at the River Baru outlet for Scenario 4a at 15:55
0.4 ha area of Kota Lama is inundated and the highest inundation depth is only 0.03 m.
This scenario can reduce 98% the inundation area. Kota Lama is inundated for 50 minutes
or 10 minutes longer than full gate opening scenario. The inundation map for scenario 4a
can be seen in Figure 8-23.
Scenario Analysis 84
Figure 8-23 Inundation Map of Kota Lama for Scenario 4a: Flap Gate Operation and Canal with Sediment
Figure 8-24 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 4b
The flow at the flap gate for this scenario is free flow or condition V in Duflow which
means discharge at the gate depends on the gate opening, the upstream water level and
the contraction coefficient. This can be seen the 2/3 of upstream water depth (1.17 m) is
lower than gate opening height (1.7 m) and downstream water depth (1.7 m). Other
consideration to determine is 2/3 of upstream water depth (1.13 m) is lower than the
downstream water depth. The sketch of water level at the flap gate is presented Figure 8-25.
Scenario Analysis 85
Flap gate
(surface level)
0.18 m+MSL
-0.07 m+MSL (downstream wl and gate level)
(upstream wl) -0.12 m+MSL
-1.82 m+MSL
Upstream Downstream (floor level)
Kota Lama drainage Baru River
Figure 8-25 Sketch of Water Level Condition at the River Baru outlet for Scenario 4a at 15:55
The ability of the channel increased after cleaning thus providing additional capacity and
flow velocity of the canals. In addition, the installation of flap gate also provides the
capability of water outside the system cannot enter into the system if the water outside is
higher than that within the system. Therefore, the inflow from high tides and rainfall of
25 years return period still can be overcome and provide adequate freeboard meets
the requirements.
The score of flap gate and canals with sediment scenario is 19 that meets 4 of 9 criteria.
If the same scenario is applied to the clean canals, the scenario generates larger score (37) and
meets 7 of 9 criteria. Scenario 4a has got the larger score because this scenario provide free of
inundation condition for Kota Lama and meets the requirements. The resume for Scenario 4:
Flap Gate Operation at Every Outlet is shown in Table 8-4.
Table 8-4 Technical and Scientific Performance Assessment of Scenario 4: Flap Gate Operation at Every Outlets for Kota Lama
Total 19 37
Scenario Analysis 86
Comparison of maximum discharge which is through both gates (full gate opening and flap
gate) shows both gates has almost the same capacities of each other. The flow type for both
gate are different but the determinant variable for both flow type are the same which are
upstream water depth and difference between upstream and downstream water depth. Cleaning
the canals is shown of increasing the discharge passing through the gate of 31%. This has an
impact on the availability of capacity in the drainage system. Graph of discharge comparison at
high water level (14:00 to 19:00) is presented in Figure 8-26.
Figure 8-26 Discharge Comparison between Full Gate Opening and Flap Gate Operation
Scenario Analysis 87
Figure 8-27 Water Level Condition at Merak Street for Scenario 5a
Figure 8-28 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 5a
Scenario Analysis 88
Figure 8-30 Water Level Condition at Merak Street for Scenario 5b
Kota Lama area is free of inundation but some of the canals between Merak Street drainage
and Baru River Pump Station cannot provide the required freeboard due to the backwater
curve. This condition can be seen in Figure 8-31. The pump operation simulation is
presented in Figure 8-32.
Figure 8-31 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 5b
Figure 8-32 shows that the pump still does not stop working after the second day. This is
because the two boundaries’ water level in Semarang River are set constant, so the water
still enters into the system even though the rain has stopped. If the connections to Semarang
River at both boundaries are closed, the pump operated for 20 hours which can be seen in
Figure 8-33.
Scenario Analysis 89
Figure 8-33 Pump Operation Simulation of Scenario 5b (In Case of Close Connection to Semarang River)
Both scenario can provide Kota Lama of inundation free condition. Score of Scenario 5a
(close connection and canals with sediment) is good enough of 29 which meets 5 of 9 criteria,
but this scenario cannot give the expected canal capacity. Scenario 5b (close connection and
clean canals) get better score of 33 and unfortunately, this scenario can meet the freeboard
requirement. So, the scenario 5b only meets 6 of 9 criteria. The resume of the scoring for these
scenario is presented in Table 8-5.
Table 8-5 Technical and Scientific Performance Assessment of Scenario 5: Close the Connection with Banger Sub drainage system
Total 29 33
Scenario Analysis 90
8.6. Scenario 6: Proposed New Pump Capacity
According to Scenario 2, the existing full pump capacity is not enough to handle the high tide
and rainfall of 25 years return period. It is better to add the capacity of the pump at clean canal
condition when the gate cannot be used due to the high water level at Semarang and Baru River.
Ministry of Public Works and Housing (2009) suggested that the design pump should cope
the 50 years return period rainfall with canal’s full bank condition. The result of simulations
based on several pump capacity show that the pump capacity of 3 m3/s is suitable for Baru River
pump. The graph between the highest water level and pump capacity to determine the proposed
pump capacity is presented in Figure 8-34.
Water level in Kota Lama with the proposed pump is lower than the existing condition because
the pump can drain the water to Baru River before the high tides become too high to handle.
The highest water level of 0.17 m+MSL is occurred at 16:35 on Merak Street drainage.
The tidal fluctuation effects at Merak Street main drainage for scenario 6 can be seen in Figure 8-35.
Rainfall of 25 years return period can be handle with the proposed pump, even though the free
board in the canal is less than 0.2 cm. As the type of flow of using pump in other scenarios,
this scenario is also backwater curve. The pump is working for 8 hours and 10 minutes.
The pump operation simulation and the longitudinal section from Merak Street until Baru River
Pump Station are presented in Figure 8-36 and Figure 8-37.
Although scenario 6 can overcome the inundation at Kota Lama for 25 years return period
rainfall, the score of this scenario is 33. The highest freeboard of this scenario is 0.12 m which
is occur in Merak Street drainage which is less than the required by the government. The score
for Scenario 6: Proposed New Pump Capacity is shown in Table 8-6.
Scenario Analysis 91
Figure 8-36 Water Level Condition on Merak Street until Baru River Pump Station for Scenario 6
Table 8-6 Technical and Scientific Performance Assessment of Scenario 6: Proposed New Pump Capacity
Scenario 6: Proposed
New Pump Capacity
Primary Se condary
Benchmarks and Clean Canal
Criteria Criteria
Scenario
Results Scores
80% of canal 100% of canal
Canal capacity 5
capacity capacity
Retention pond 3 3
Storage 15,000 m 20,150 m 5
capacity
System Pumping/gate Reduce inundation
None 5
performance capacity less than 2 hours
Inundation
Flooding Less than 0.3 m None 5
Depth
Inundation
Less than 2 hours None 5
Duration
Performance Design return 10 years (for
System reliability 5 years 1
reliability failures period secondary canals)
Maximum flow
Canal strength 3.0 m/s (concrete) 0.51 m/s 5
velocity
System durability
Canal Minimum flow
0.6 m/s 0.2 m/s 1
sedimentation velocity
System flexibility Capacity for Design free-
0.2 m 0.12 m 1
and adaptability change board
Total 33
Scenario Analysis 92
8.7. Scenario 7: Full Developed Polder System
Polder system for Kota Lama has not been fully developed because there are only 3 of 4 main
polder components which are drainage system, retention basin and pumping station. Kota Lama
has not got any ring dike as the boundary area of the polder system and protection of tidal flood
that used to happen. Kota Lama also has not formed its own hydrological system because
Kota Lama still connected to the upstream Kota Lama drainage scheme, partly of Simpang
Lima and partly Banger sub drainage system. So that, there is a miss understanding about polder
system for Kota Lama in public and government.
This scenario aims to provide advice and analysis when fully developed polder system will be
applied in Kota Lama. Kota Lama Polder is designated in this scenario for referring polder
system for Kota Lama. Proposed area of Kota Lama Polder is 26 ha. Boundaries of Kota Lama
Polder are the same as defined in the Regional Regulation of Semarang City No. 8/2003
regarding Spatial Planning and Environment of Kota Lama, but the northern boundary is
extended partly to Tawang Street that includes Tawang Retention Basin. Boundary map of
proposed Kota Lama Polder is presented in Figure 8-38. Gravity driven polder is chosen due to
the limitation of land availability to implement different types of polders. This type of polder
has minimum construction cost but requires high energy, if it compares to belt canal or separate
polder system.
Kota Lama Polder is still the part of Kota Lama sub drainage system. Thus, to implement this
system some adjustments need to implement. Changes in drainage scheme needs to be done because
there is main drainage canal (Merak Street drainage) which is passing through Kota Lama.
Besides that, the existing control structures still will be used and add several control structures.
Scenario Analysis 93
Determination of Pump Capacity
a. Pump within Kota Lama Polder
Gravity driven polder is suitable for Kota Lama Polder due to its limited land availability
and using the existing condition. Capacity of Tawang pump is 0.45 m3/s. Now, this pump
is designed for service area of 26 ha. The simulation is done with the 25 years return period
rainfall. Only the pump is worked (no flow from gates) due to the high water level outside
the polder, the pump should be overcome the rainfall. Based on the simulation, the highest
water level at Merak Street drainage is +0.02 m+MSL and it is not causing inundation.
The water level at Merak Street drainage can be seen in Figure 8-39.
Figure 8-39 Water Level Condition at Merak Street with Existing Tawang Pump Capacity
The simulation is also done for several rainfall return period which are 10, 25, 50, 100, 200
and 1000 years. The inundation starts to occur when the rainfall is more than 100 years
return period rainfall or more precisely the pump can cope with rainfall of 208 mm/day.
If the canal must have a freeboard of 0.2 m below the surface as required, the results show
that the existing pump can serve up to 25 years rainfall return period or 175 mm/day
accurately. Water depth curve for inside Kota Lama Polder is presented in Figure 8-40.
Figure 8-40 Water Depth Curve for Inside of Kota Lama Polder with Existing Pump, (a) Return Period Rainfall & (b) Rainfall
As discussed previously in chapter 2 that the major design flood should be designed for
50 years rainfall return period at full bank condition. Therefore, the existing pump capacity
still meets the criteria. The rainfall frequency curve is shown in Figure 8-41.
Scenario Analysis 94
Figure 8-41 Rainfall Frequency Curve for Inside of Kota Lama Polder with Existing Pump Capacity
Figure 8-42 Water Level Condition at Tawang Street with Existing Baru River Pump Capacity
According to the water depth curve which can be seen in Figure 8-43, the difference
between water depth of 10 years and 1000 years return period rainfall is only 0.07 m.
The existing pump capacity cannot overcome even for the rainfall of 10 years return period,
so the bigger capacity of the pump is needed. Addition or have larger area of open water is
not possible because of the polder is in the heritage site.
Scenario Analysis 95
Figure 8-43 Water Depth Curve for Outside of Kota Lama Polder with Existing Pump, (a) Return Period Rainfall & (b) Rainfall
The selection pump capacity is based on the 50 years return period rainfall. According to
Figure 8-44, the results of pump selection simulation shows that the pump capacity of
3.5 m3/s can cope with the 50 years return period rainfall.
The proposed pump capacity can handle rainfall up to 189 mm/day accurately or it is better
than the existing pump because it can provide additional design rainfall of 149 mm/day.
The rainfall frequency curve is shown in Figure 8-45.
Figure 8-45 Rainfall Frequency Curve for Outside of Kota Lama Polder with Proposed Pump Capacity
Scenario Analysis 96
Determination of Dike Height
Ministry of Public Works and Housing (2009) recommended that design of dike height is
1000 years return period rainfall at the outside of polder area. The simulation is run
with the proposed pump capacity. The inundation depth of 1000 years return period rainfall is
0.13 m. Water depth curve for outside of Kota Lama Polder can be seen in Figure 8-46.
Figure 8-46 Water Depth Curve for Outside of Kota Lama Polder with Proposed Pump, (a) Return Period Rainfall & (b) Rainfall
Kota Lama Polder will be the protection for UNESCO-Heritage site. Flood is the main factor
of polder development but the effect of land subsidence and tidal fluctuation effects should be
considered. Considering the occurrence of land subsidence with the “do nothing” scenario in
15 years, the estimated land subsidence is 0.8 m. The highest high water level for Semarang is
+0.5 m+MSL. Therefore, it is recommended that the dike height is 1.0 m. Polder’s ring dike
suggested by elevating the road so it does not diminish the aesthetic values of colonial buildings.
This is possible because the average width of the road as the boundary is 12 m, if it is viewed
the existing conditions of Kota Lama (see Figure 8-47).
Scenario Analysis 97
Determination of Control Structures
The first proposed adjustment is the two outlets at Semarang River are controlled with vertical
gates (existing) and flap gate (new), so there are not the free outlet anymore to prevent high
water level in Semarang River enter Kota Lama. Main drainage canal that is passing through
Merak Street is diverted to drainage Tawang with canals’ dimension of 4.8 m2 and parallel
to it. Main drainage at Merat Street will be converted its functions as an additional long storage
for Kota Lama because of its connection with the main drainage has been restricted by using
control structures. The western connection of Kota Lama and main drainage also will be
equipped by a flap gate. The eastern connection canal of Kota Lama and main drainage should
be the same as the western connection canal to prevent blockage. Main outlet of Kota Lama
polder are a pump next to Tawang Retention Basin (existing) and vertical gate at main drainage
(new) to control water level inside the polder when the outside water level is low. A flap gate
is proposed to install at the eastern part of Merak Street drainage to prevent the high water level
from upstream Kota Lama drainage system.
The proposed situation of Kota Lama can be seen in Figure 8-48. Resume of proposed control
structures and pumps for Kota Lama Polder and its surrounding, among others:
Inside Kota Lama Polder
a) Tawang pump station (existing, 0.45 m3/s of pumping capacity),
b) vertical gates for inlet and outlet at Retention Basin (existing, four vertical gates of
1.5 m for inlet and two vertical gates of 1.5 m for outlet),
c) vertical gate at first outlet of Semarang River (existing, two vertical gates of 1 m for each gate),
d) flap gate at second outlet of Semarang River (proposed, width of 0.6 m),
e) flap gate at western part of Merak Street drainage (proposed, width of 3.5 m),
f) flap gate at eastern part of Merak Street drainage (proposed, width of 3.5 m),
g) flap gate at the western connection of Kota Lama and main drainage (proposed, width of 2 m)
h) enlargement of the western canal connection (proposed, dimension of 2.6 m2)
Scenario Analysis 98
Outside Kota Lama Polder
a) Baru River pump station for Kota Lama sub drainage system (proposed, 3.5 m3/s of
pumping capacity and two vertical gates of 1.5 m for each gate),
b) connection canal from Merak Street drainage to Tawang Street drainage (proposed,
dimension of 4.8 m2)
The simulation is done by using the rainfall of 25 years return period. The proposed drainage
scheme of Kota Lama Polder is created by the previous description. The canals are in clean
condition. The start and stop interval for Tawang pump and Baru River pump are changed to
0.3 m-surface level for start and stop at 0.50 m-surface level.
Water level inside and outside of Kota Lama Polder is increase after 14:00 because of the addition
of inflow from rainfall. Outside the polder has got higher water level due to it has a larger service
area and tidal fluctuation effects. The highest water level in Kota Lama is occurred at 20:40 of
+0.02 m+MSL or 0.27 m-surface level. Then, for the highest water level outside the polder is
+0.26 m+MSL or 0.04 m-surface level. It is proved that the polder system can keep Kota Lama
from inundation. The water level inside and outside Kota Lama can be seen in Figure 8-49.
Figure 8-49 Water Level Condition on Merak Street and Tawang Street for Scenario 6
Scenario 7: Full Developed Polder System achieves score of 37 for Kota Lama and 28 for
outside drainage the polder. The minimum velocity of both condition (inside and outside the
polder) is no velocity because the water is stored before its pumped. The outside polder also get
the lower score because it does not design with the retention basin and has a little freeboard
left. The scoring for scenario 7 can be seen in Table 8-7.
Scenario Analysis 99
Table 8-7 Technical and Scientific Performance Assessment of Scenario 7: Full Developed Polder System
Storage
Retention 3 3
15,000 m 20,150 m 5
pond capacity
System
performance
Pumping/ gate Reduce inundation
None 5 None 5
capacity less than 2 hours
Inundation
Flooding Less than 0.3 m None 5 None 5
Depth
Inundation
Less than 2 hours None 5 None 5
Duration
Performance
System Design return 10 years (for
reliability None
5 years 1 None
5 years 1
reliability period secondary canals)
failures
Maximum flow
Canal strength 3.0 m/s (concrete) 0.11 m/s 5 0.75 m/s 5
velocity
System
durability
Canal Minimum flow
0.6 m/s 00.02
m/sm/s 1 00.12
m/sm/s 1
sedimentation velocity
System
Capacity for Design free-
flexibility and 0.2 m 0.27 m 5 0.02 m 1
change board
adaptability
Total 37 28
Score for each of the scenarios are summarized and sorted on Figure 8-51. All scenarios have
got the same score for the design return period criteria because canals and retention basin
are still using the existing condition which is rainfall of 5 years return period. The minimum
flow velocity for all scenarios are not more than 0.6 m/s. Almost all scenarios of the canals with
sediment and waste has got score less than 20.
Clean canal with the existing pump operation and full pump capacity has almost the same score
because the inundation still occurs, although it is still less than 20 cm. The difference is clean
canal with the existing pump operation cannot meet the requirement of pumping capacity and
inundation duration because the inundation is occurred more than 2 hours.
Close connection with Banger sub drainage system for canals with sediment and clean canals
consecutively is 29 and 33. Actually, these scenarios provide Kota Lama which is free form
inundation. Canals with sediment scenario cannot meet canals and retention basin capacity criteria.
The clean canals for this scenario can provide the opposite, but cannot give freeboard as required.
The new pump capacity is determined by the 50 years return period rainfall at full bank
condition. The score of proposed new pump capacity is 33. Inundation free condition is
provided but the freeboard criteria cannot be met by this scenario.
The lowest score is the Existing Scenario with 15. There are 3 scenarios with the highest score
of 37 which are scenario 3b: full gate open and clean canal scenario, scenario 4b: flap gate and
clean canal scenario and scenario 7: full developed polder system scenario
From those scenarios, it can be known that main causes of inundation in Kota Lama are
1) high rainfall intensity, 2) sediments and waste inside the canals and retention basin,
3) tidal fluctuation effects and 4) lack of pump capacity.
Implementation Phases
Those scenarios can actually be used as the reference of implementation phases to reduce
inundation in Kota Lama. Then, according to Figure 8-19, the clean canal curve shows that
Kota Lama start to inundate when the boundary condition is at 0.18 m+MSL. For fulfilling
the flexibility criteria, the vertical gates can be operated if the water level in boundary condition
is -0.05 m+MSL. So, it can be divided into two cases, namely normal case and critical case.
Normal case is applied when the gate operation can be used as an outlet regulator and the water
level on the boundary condition is less than -0.05 m+MSL. The condition when only pump can
be operated due to the high water level at boundary condition (more than -0.05 m+MSL) can
be categorised as critical case.
Cleaning all the canals is an activity that must be done at least once a year before the rainy
season. If the canal cleaning is not done regularly, the drainage system of Kota Lama cannot
provide the best service with the score of the performance is less than 20 either with pump or
All drainage canals in Kota Lama are concrete canals. According to Chow (1959), the range of
Manning roughness coefficients for concrete canals is 0.011 to 0.025. Manning coefficient for
clean canal is assumed as unfinished concrete canal with value of 0.017. Those three
coefficients is observed its effects on water depth for several pump capacities. According to
Figure 8-53, the minor effects of canals roughness are occurred for different pump capacity
within Kota Lama Polder.
Figure 8-53 Canals Roughness Effects on Water Depth for Several Pump Capacity within Kota Lama Polder
Residential Area at Empu Tantular St. Residential Area at Branjangan St. Residential Area at Cendrawasih 1 St.
b. Solid Waste
Solid waste management is also noteworthy because Kota Lama is one of the trade centers,
tourism, residential and there is still a traditional market. Accumulation of solid waste lead
to unpleasant smells, water pollution, decreasing canal and retention basin capacity and
increasing of pest. Collecting recycled solid waste can be one form of community-based
solutions. Condition of markets in Kota Lama is shown in Figure 8-55.
Kota Lama Traditional Market Kepodang Street Kota Lama Antique Market
Kota Lama
Figure 8-55 Traditional Market, Business Area and Antique Market in Kota Lama
World Bank (2013) explained the existence the bank of waste in Indonesia. Bank of waste
is a place for recycling organic and inorganic waste which has similar works to commercial
banks. Each residents can register themselves by opening the account. They can fill up their
savings by providing the waste with the agreed price and they can draw their savings at any
time. The basic principles of the bank of waste in Indonesia are recycle waste into goods
with economic values, change the public attitudes and maintain the cleanliness.
Ministry of Environment and Forestry (2012) recorded some good results in the
implementation of waste bank. Waste bank concept is just implemented in several cities in
Indonesia. One of the waste bank is in Surabaya City (Rukun Karya Waste Bank) which
was established in 2010 and in 2010 it has got 178 members. This waste bank can process
the waste up to 1000 kg/month, produce organic fertilizer and recycle inorganic waste with
a turnover up to $190/month. The activities of the waste bank can be seen in Figure 8-56.
c. Water Quality
Visually, water in canals and retention basin of Kota Lama showed poor water quality
which is known from the high turbidity water and unpleasant smells. The condition of water
quality in Kota Lama can be seen in Figure 8-57.
Condition of Water Quality in Merak Street Drainage Condition of Water Quality in Tawang Retention Basin
Aeration may be an easy way to improve water quality. Some time ago, Tawang Retention
basin had got some water fountains, but the fountains are no longer in operation now.
Reoperation of the fountains in Kota Lama may be able to do to improve water quality and
become the tourist attraction. Operation water fountains in Tawang Retention Basin at 2007
can be seen in Figure 8-58.
Figure 8-58 Operation the Water fountains in Tawang Retention Basin at 2007 (nisa17.blogdetik.com)
Figure 8-59 Up Coning Saline Groundwater with Groundwater Extraction (Ministry of Public Works and Housing, 2009)
Jatibarang Reservoir has begun its operation since May 2015 (see Figure 8-60). Besides for
controlling floods and micro-hydro power plants, this reservoir is also used for supplying water
for Semarang through Tirta Moedal Water Utility Company. Jatibarang Reservoir is expected
to provide the certainty of supplying the water, then the water utility company can expand their
network. It is believed this solution can solve the problem of the quality of drinking water.
Figure 8-60 Jatibarang Reservoir (Ministry of Public Works and Housing, 2015)
e. Ecology
Trend of major cities in the world are to have more open space. Regulations on green space in
Indonesia also recommends this concept which is the ministerial regulation of home affairs
No. 1/2007 regarding the green space area for urban area. Green space area can be used as a
recreation area and a source of oxygen. Availability of green space area may also be misused
in the future as for the storage of trash or slums. As the prevention, policies that support and
community participation are needed. The surrounding area at Tawang Retention Basin may be
rearranged by reducing the use of paving blocks, relocate the street food vendors and illegal
parking. Existing situation around Tawang Retention Basin is presented in Figure 8-61.
Social Aspects
a. Realisation Phases
In establishing the water management plan in Indonesia, several phases should be done according
to the Minister Regulation of Public Works and Housing No. 10/2015 regarding The Strategic
Plan and Implementation Plan of Water Resources Management. The study must be completed
with the basic study and pre-feasibilities of technical and non-technical aspects. Afterwards, the
drainage plan will be consulted with the technical team from the institution which is responsible
for water management, in this case is Semarang Water Resources Management, Energy and
Mineral Resources Agency (Dinas PSDA & ESDM Kota Semarang).
The public hearing sessions should be carried out for the next phase to introduce the study
results and the implementation plan. This meeting also aims to have feedback, comments,
corrections and clarifications according to the stakeholders’ expectation for later organised into
a collective agreement. After the plan is enriched with the ideas from the stakeholders, the plan
is announced to the public to see the reactions from the stakeholders. The establishing team
should review or clarified the objections, if there are some objections. If there are not any
objections from the stakeholders, the plan can be implemented. The realisation phases is
illustrated in Figure 8-62.
Figure 8-64 Workflow of the Application of Social Media Based for Inundation Recording and Emergency Response (Eirlander et
al., 2015)
Economic Aspects
The series of activities in a project are survey, investigation, design, land acquisition,
construction and maintenance. The cost for each of these activities must be prepared in order
to produce the expected results. Land acquisition for Kota Lama Polder is minimized because
the existing network (canals and retention basin) is still used (canal widening or new drainage
network), Tawang Pumping Station is also still in good condition and the construction of ring
dike is suggested by raising the existing roads. Direct and indirect costs should be reckoned for
survey, investigation, design and construction. Direct costs include expenses that are used to
provide materials, equipment rental and salary workers. Whereas, the indirect costs are related
to the permit cost, tax and project office needs.
Costs of operation and maintenance can be divided into two which are routine operation and
maintenance and large maintenance. Routine operation and maintenance is an activity that must
be done every year such as the payment of staff salaries, energy costs, canals cleaning and
maintenance dike and pump. Large maintenance is done in a certain period of time that includes
pump replacement, ring dike heightening and retention basin dredging.
9.2. Recommendation
To improve the operation, maintenance, studies and plannings in relation with Kota Lama
drainage system, several things may be considered, such as:
1. Determination of Kota Lama and Kota Lama sub drainage system area should be
remeasured because the measurement by using ArcGIS with Open Street Map as
based map and Google Earth has got the difference of 23% (7.2 ha) to the area in Regional
Regulation of Semarang City No. 8/2003 regarding Spatial and Environment Planning of
Kota Lama, although the measurement has been done with the same boundaries with the
regional regulation.
2. Inventaritation of canal’s dimension should be done to update the existing data of Kota
Lama sub drainage system.
3. Water level or discharge measurement devices should be installed in every outlet of Kota
Lama Sub drainage system, so the operator can be operated the gates or pumps precisely
based on the flood manual. Studies about flood and drainage system can also be improved
with these data.
4. Availability of flood manual in every outlet (pumps and gates) at operator level should be
checked at least a once a year before rainy season. Therefore the operator can be operated
as the design.
5. Recording of flood events, inundation area and inundation depth by the official institutions
are needed for further studies about flood and drainage system.
6. Land subsidence measurement and study should be conducted continuously to have better
understanding of land subsidence behaviour in Semarang.
7. Supply of raw water for Semarang should be done, especially for Kota Lama and its
surroundings, to control decreasing of ground water level. It is intended to have the life
span as planned for ring dike of Kota Lama Polder, control seawater instruction and provide
good quality of drinking water.
8. Environmental, public health, social and economic aspects should be studied
comprehensively to have a sustainable drainage system.
References 113
Kurniawan, A., Dewi, N.A. 2015. Planning of Domestic Wastewater Sewerage in Bogor City
Using Rainwater for Flushing Flowrate. Jurnal Manusia dan Lingkungan Vol. 22 No. 1
Mahdavi, M., Osati, K., Sadeghi, S.A.N., Karimi, B., Mobaraki, J. 2010. Determining Suitable
Probability Distribution Models for Annual Precipitation Data (A Case Study of
Mazandaran and Golestan Provinces). Journal of Sustainable Development Vol. 3
No. 1, March. Toronto: The Canadian Center of Science and Education (CCSE)
Ministry of Environment. 2012. Profil Bank Sampah. Rapat Kerja Nasional Bank Sampah.
2-4 November, Malang, East Java, Indonesia
Ministry of Public Works and Housing. 2009. Prosedur and Instruksi Kerja Validasi Data
Hidrologi. Jakarta: Directorate General of Water Resources
Ministry of Public Works and Housing. 2009. Urban Polder Drainage: General Aspects.
Bandung: Water Resources Research Development Centre
Ministry of Public Works and Housing. 2009. Urban Polder Drainage: Institutional Aspects.
Bandung: Water Resources Research Development Centre
Ministry of Public Works and Housing. 2009. Urban Polder Drainage: Technical Aspects.
Bandung: Water Resources Research Development Centre
Ministry of Public Works and Housing. 2009. Urban Polder Drainage: Case Study Banger
Polder Semarang. Bandung: Water Resources Research Development Centre
Ministry of Public Works and Housing. 2011. Pengumpulan dan Pengolahan Data Hidrologi.
Bandung: Water Resources Research Development Centre
Murdohardono, D., Tobing, T.M.H.L., Sayekti, A. 2007. Over Pumping of Groundwater as
One of Causes of Sea Water Inundation in Semarang City. International Symposium and
Workshop on Current Problems in Groundwater Management and Related Water
Resources Issues, 3 – 8 December, Kuta, Indonesia
Patra, K.C. 2008. Hydrology and Water Resources Engineering. Oxford: Alpha Science
International Ltd.
Rizal, R., Ikhwan, Y., Fauzi, M. 2014. Analisis Tata Kelola Sistem Drainase yang
Berkelanjutan Berbasis Partisipasi Masyarakat (Studi Kasus di Perumahan Duta Green
City Kota Pekanbaru Provinsi Riau). Pekanbaru: Pusat Penelitian Lingkungan Hidup
Universitas Riau
Sarah, D., Soebowo, E., Syahbana, A.J., Murdohardono, D., Setiawan, T., Mulyono, A.,
Satriyo, N.A. 2012. Perhitungan Penurunan Tanah Lintasan Bandarharjo-Poncol, Kota
Semarang Berdasarkan Permodelan 2 Dimensi. Prosiding Pemaparan Hasil Penelitian
Pusat Penelitian Geoteknologi LIPI
Sasongko, L.A. 2006. Kontribusi Air Limbah Domestik Penduduk di Sekitar Sungai Tuk
Terhadap Kualitas Air Sungai Kaligarang Serta Upaya Penanganannya. MSc Thesis.
Semarang: Universitas Diponegoro
Schultz, E., Severs, G., Ven, G.A. 1986. Design Study Main Drainage System Markerwaard.
Proceeding of the 2nd International Conference, April, Southampton, United Kingdom
Schultz, B. 2015. Report of the International Workshop on Drainage System Plan in Semarang
Old City. Semarang
References 114
Semarang Planning Board. 2007. Penyusunan Dokumen Master Plan Drainase Kota Semarang.
Semarang: Semarang Planning Board
Semarang Statistic Bureau. 2007. Penyusunan Dokumen Master Plan Drainase Kota
Semarang. Semarang: Semarang Planning Board
Sheskin, D.J. 2007. Handbook of Parametric and Nonparametric Statistical Procedures.
Danvers: Chapman & Hall/CRC
Smedema, L.K., Mooren, J.H.M., Veraa, C.J.F.M. 1986. Area Reduction Factors for Land
Drainage Design in Flat Basins in Moderate Temperate Climate. Proceeding of the 2nd
International Conference, April, Southampton, United Kingdom
Smedema, L.K., Vlotman, W.F., Rycroft, D.W. 2004. Modern Land Drainage. Leiden: A.A.
Balkema Publishers
Stowa. 2004. RAM Manual Precipitation Runoff Module
Stowa. 2006. Duflow Modelling Studio Users’ Guide.
Stowa. 2006. Duflow Modelling Studio Manual.
Suryadi, F.X. 1996. Soil and Water Management Strategies for Tidal Lowlands in Indonesia.
PhD Thesis. Delft University of Technology – IHE Delft. Rotterdam: A.A. Balkema
Suryadi, F.X. 2015. Unsteady Flow. Lecture Note. Delft: UNESCO-IHE
Triatmodjo, B. 2008. Hidrologi Terapan. Yogyakarta: Beta Offset
Triola, M. F. 2009. Elementary Statistics. Boston: Addison-Wesley
UNESCO. 2015. Semarang Old Town. Jakarta: Indonesia National Commission for UNESCO
Van Duijl, B. 2015. Sewer Design and Layout: Part I. Lecture Note. Delft: UNESCO-IHE
World Bank. 2013. Bank Sampah di Indonesia: Menabung, Merubah Perilaku
http://blogs.worldbank.org/eastasiapacific/id/bank-sampah-di-indonesia-menabung-
mengubah-perilaku. retrieved on 19th March 2016.
Yuwono, B.D., Abidin H.Z., Hilmi, M. 2013. Analisa Geospasial Penyebab Penurunan Muka
Tanah di Kota Semarang. Semarang: Prosiding SNST ke-4 Fakultas Teknik Universitas
Wahid Hasyim
References 115
References 116
Appendices
Extreme rainfall in order of magnitude for
different rainfall duration at Semarang Rainfall Station
Rainfall Station : BMKG Semarang
Max Rainfall (mm) Day of Max
Day of
Year Rain Daily
5 10 15 30 45 12 Rain
1 Hour 2 Hours 3 Hours 6 Hours > 10 mm Rainfall
Minutes Minutes Minutes Minutes Minutes Hours
1981 20 40 50 65 70 80 113 133 189 212 27 19 235
1982 10 20 29 48 60 70 81 100 133 133 27 13 158
1983 15 30 45 60 76 77 77 78 80 80 22 11 80
1984 15 25 30 40 60 66 77 79 81 82 23 13 82
1985 15 25 35 50 65 88 111 111 145 245 18 11 245
1986 30 45 60 70 84 97 102 116 126 126 27 14 126
1987 13 21 30 60 85 88 93 93 96 138 26 9 138
1988 15 25 35 50 70 80 101 101 117 174 24 11 174
1989 20 26 41 51 55 95 125 126 141 144 23 25 144
1990 10 20 30 50 95 58 66 70 82 100 27 12 115
1991 10 20 30 40 48 49 70 82 125 132 25 15 132
1992 16 42 30 55 75 80 88 94 98 99 19 7 99
1993 20 30 36 60 76 86 161 185 193 193 27 13 193
1994 20 30 36 55 66 68 79 79 86 90 24 14 90
1995 15 22 35 60 67 79 100 100 100 100 22 12 124
1996 25 37 66 66 85 110 114 116 117 117 25 15 117
1997 20 30 36 60 76 86 161 185 193 193 27 13 193
1998 20 27 32 46 49 58 98 99 101 102 22 9 102
1999 18 20 30 56 65 70 80 85 93 93 27 11 93
2000 20 20 30 41 60 70 138 145 170 175 25 11 175
2001 20 30 40 50 70 90 100 108 111 111 23 9 111
2002 10 20 30 44 52 85 97 98 98 98 23 14 98
2003 10 20 27 40 48 48 90 97 97 97 23 15 97
2004 20 24 30 60 77 80 82 82 82 82 21 12 82
2005 10 20 30 50 55 78 85 88 88 89 23 8 89
2006 10 20 26 40 54 70 89 89 90 107 26 13 112
Appendices 117
Sediment thickness sampling
Measurement
Depth of Canal's % of
(cm)
Streets Sediment Height Sediment Photos
(m) (m) in Canal
1st 2nd
Appendices 118
Measurement
Depth of Canal's % of
(cm)
Streets Sediment Height Sediment Photos
st nd (m) (m) in Canal
1 2
Appendices 119
Measurement
Depth of Canal's % of
(cm)
Streets Sediment Height Sediment Photos
st nd (m) (m) in Canal
1 2
Average 34.2%
Appendices 120
Model Features in DUFLOW for Clean Canals
Clean Canals
Main Drainage
NOD00000 0.00 0.29
SEC00000 165
CSC00000 Type 1 10.00 10.00 0.29 -1.71
CSC00001 Type 1 155.00 155.00 0.27 -1.73
NOD00001 165.00 0.27
SEC00001 34
CSC00002 Type 1 10.00 175.00 0.27 -1.73
CSC00003 Type 1 24.00 189.00 0.27 -1.73
NOD00002 199.00 0.27
SEC00002 113
CSC00004 Type 1 10.00 209.00 0.27 -1.73
CSC00005 Type 1 103.00 302.00 0.26 -1.74
ARE00000 5814 56.50 255.50
NOD00003 312.00 0.26
SEC00003 48
CSC00006 Type 1 10.00 322.00 0.26 -1.74
CSC00007 Type 1 38.00 350.00 0.25 -1.75
NOD00004 360.00 0.25
SEC00004 70
CSC00008 Type 1 10.00 370.00 0.25 -1.75
CSC00009 Small RB 60.00 420.00 0.25 -1.75
ARE00001 128597 35.00 395.00
NOD00005 430.00 0.25
SEC00005 482
CSC00010 Type 1 10.00 440.00 0.25 -1.75
CSC00011 Type 1 472.00 902.00 0.18 -1.82
ARE00002 63955 241.00 671.00
NOD00006 912.00 0.18
Main Drainage - Baru River Pump
NOD00006 912.00 0.18
SEC00006 20
CSC00012 Type 1 10.00 922.00 0.18 -1.82
Appendices 121
Dimension Section Area (m2) / Surface Bottom
Code Position Distance (m)
Type Length (m) Pump (m3/s) (m+MSL) (m+MSL)
Appendices 122
2
Dimension Section Area (m ) / Surface Bottom
Code Position Distance (m)
Type Length (m) Pump (m3/s) (m+MSL) (m+MSL)
Appendices 123
Dimension Section Area (m2) / Surface Bottom
Code Position Distance (m)
Type Length (m) Pump (m3/s) (m+MSL) (m+MSL)
Appendices 124
Model Feature Changing - In Case of Polder
Tawang Street
NOD00022 0.00 0.30
SEC00028 130.00
CSC00051 Type 27 10.00 10.00 0.30 -1.70
CSC00052 Type 27 120.00 120.00 0.30 -1.70
ARE00015 693108 10.00 10.00
NOD00025 130.00 0.30
SEC00029 347.00
CSC00053 Type 27 10.00 140.00 0.30 -1.70
CSC00054 Type 27 337.00 467.00 0.25 -1.75
ARE00016 31320 173.50 303.50
NOD00004 477.00 0.25
Main Drainage - Inlet
NOD00022 0.00 0.30
SEC00024 35.00
CSC00046 Type 1 17.50 17.50 0.30 -1.71
Appendices 125
Model Features in DUFLOW for Canals with
Sediment
Main Drainage
NOD00000 0.00 0.29
SEC00000 165
CSC00000 Type 1 10.00 10.00 0.29 -1.01
CSC00001 Type 1 155.00 155.00 0.27 -1.03
NOD00001 165.00 0.27
SEC00001 34
CSC00002 Type 1 10.00 175.00 0.27 -1.03
CSC00003 Type 1 24.00 189.00 0.27 -1.03
NOD00002 199.00 0.27
SEC00002 113
CSC00004 Type 1 10.00 209.00 0.27 -1.03
CSC00005 Type 1 103.00 302.00 0.26 -1.04
ARE00000 5814 56.50 255.50
NOD00003 312.00 0.26
SEC00003 48
CSC00006 Type 1 10.00 322.00 0.26 -1.04
CSC00007 Type 1 38.00 350.00 0.25 -1.05
NOD00004 360.00 0.25
SEC00004 70
CSC00008 Type 1 10.00 370.00 0.25 -1.05
CSC00009 Small RB 60.00 420.00 0.25 -1.05
ARE00001 128597 35.00 395.00
NOD00005 430.00 0.25
SEC00005 482
CSC00010 Type 1 10.00 440.00 0.25 -1.05
CSC00011 Type 1 472.00 902.00 0.18 -1.12
ARE00002 63955 241.00 671.00
NOD00006 912.00 0.18
Main Drainage - Baru River Pump
NOD00006 912.00 0.18
SEC00006 20
CSC00012 Type 1 10.00 922.00 0.18 -1.12
Appendices 126
Dimension Section Area (m2) / Surface Bottom
Code Position Distance (m)
Type Length (m) Pump (m3/s) (m+MSL) (m+MSL)
Appendices 127
2
Dimension Section Area (m ) / Surface Bottom
Code Position Distance (m)
Type Length (m) Pump (m3/s) (m+MSL) (m+MSL)
Appendices 128
Dimension Section Area (m2) / Surface Bottom
Code Position Distance (m)
Type Length (m) Pump (m3/s) (m+MSL) (m+MSL)
Appendices 129
Canal Cross Sections, Gates & Pumps in
DUFLOW
manning coefficient, n: 0.017 0.022
Clean Canals Canals with Sediment
Dimension
B1 (m) B2 (m) 1/2 1/2
Type H (m) C (m /s) H (m) C (m /s)
Appendices 130
Service Area in DUFLOW
Existing Condition
2
Code Section Area (m ) Paved Unpaved Open Water
In case of Polder
2
Code Section Area (m ) Paved Unpaved Open Water
Appendices 131