Professional Documents
Culture Documents
(LIP 2021)
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
Project : LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Appropriation : (a) Road 301.50
: Barangay Talaan Pantoc, Sariaya, Quezon : (b) Bridge
Project ID : : (c) Others
Location : Sariaya, Quezon Target Start Date :
Station Limits : STA. 0 + 000 - STA. 0 + 301.50 Total Project Duration : 120 C.D.
Appropriation : P 5,000,000.00 No. of Pre-determined :
Source of Fund : LIP 2021 Unworkable Days :
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part A: Facilities for the Engineer 2.05% 78,238.89 2.05% 78,238.89
B: Other General Requirements 8.22% 314,113.63 8.22% 314,113.63
C: Earthworks 7.38% 281,974.15 7.38% 281,974.15
D: Subbase and Base Course 10.19% 389,183.60 10.19% 389,183.60
E: Surface Courses (PLS. SEE FORM POW-2015-01C-00) 72.16% 2,756,448.93 72.16% 2,756,448.93
F: Bridge Construction 0.00% - 0.00% -
G: Drainage and Slope Protection Structures 0.00% - 0.00% -
H: Miscellaneous Structures 0.00% - 0.00% -
I: Provisional Sum 0.00% - 0.00% -
J: Daywork 0.00% - 0.00% -
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
JUMEL B. REYES FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN MA. CHYMBELIN D. IBAL ROGELIO S. CRESPO
Engineer II Chief, Planning & Design Section Chief, Construction Section Assistant District Engineer District Engineer
Construction Section
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP ADJUSTED UNIT
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE COST
PART A FACILITIES FOR THE ENGINEER
As Submitted 2.00% 1.00 l.s. 57,123.05 19,315.84 - 76,438.89 76,438.89 10% 7,643.89 4,204.14 88,286.92 88,286.92
A.1.1(3) Construction of Field Office for the Engineer
As Evaluated 2.00% 1.00 l.s. 57,123.05 19,315.84 - 76,438.89 76,438.89 10% 7,643.89 4,204.14 88,286.92 88,286.92
As Submitted 0.05% 120.00 ea. 1,800.00 - - 15.00 1,800.00 10% 180.00 99.00 2,079.00 17.33
A.1.4(1) Provision of Progress Photographs
As Evaluated 0.05% 120.00 ea. 1,800.00 - - 15.00 1,800.00 10% 180.00 99.00 2,079.00 17.33
As Submitted 2.05% 58,923.05 19,315.84 78,238.89 7,823.89 4,303.14 90,365.92
TOTAL OF PART A
As Evaluated 2.05% 58,923.05 19,315.84 - 78,238.89 7,823.89 4,303.14 90,365.92
PART B OTHER GENERAL REQUIREMENTS
As Submitted 0.28% 2.00 ea. 8,480.00 2,301.28 - 5,390.64 10,781.28 25% 2,695.32 673.83 14,150.43 7,075.22
B.5 Project Billboard / Signboard
As Evaluated 0.28% 2.00 ea. 8,480.00 2,301.28 - 5,390.64 10,781.28 25% 2,695.32 673.83 14,150.43 7,075.22
As Submitted 5.11% 1.00 l.s. 20,536.37 160,800.00 13,718.40 195,054.77 195,054.77 10% 19,505.48 10,728.01 225,288.26 225,288.26
B.7(2) Occupational Safety and Health Program
As Evaluated 5.11% 1.00 l.s. 20,536.37 160,800.00 13,718.40 195,054.77 195,054.77 10% 19,505.48 10,728.01 225,288.26 225,288.26
As Submitted 1.94% 1.00 l.s. 28,509.99 45,491.52 - 74,001.51 74,001.51 10% 7,400.15 4,070.08 85,471.74 85,471.74
B.8(2) Traffic Management
As Evaluated 1.94% 1.00 l.s. 28,509.99 45,491.52 - 74,001.51 74,001.51 10% 7,400.15 4,070.08 85,471.74 85,471.74
As Submitted 0.90% 1.00 l.s. - - 34,276.07 34,276.07 34,276.07 0% - 1,713.80 35,989.87 35,989.87
B.9 Mobilization / Demobilization
As Evaluated 0.90% 1.00 l.s. - - 34,276.07 34,276.07 34,276.07 0% - 1,713.80 35,989.87 35,989.87
As Submitted 8.22% 57,526.36 208,592.80 47,994.47 314,113.63 29,600.95 17,185.72 360,900.30
TOTAL OF PART B
As Evaluated 8.22% 57,526.36 208,592.80 47,994.47 314,113.63 29,600.95 17,185.72 360,900.30
PART C EARTHWORKS
As Submitted 0.91% 1.00 l.s. - 4,602.56 30,030.26 34,632.82 34,632.82 25% 8,658.21 2,164.55 45,455.58 45,455.58
101(1) Removal of Structures and Obstructions
As Evaluated 0.91% 1.00 l.s. - 4,602.56 30,030.26 34,632.82 34,632.82 25% 8,658.21 2,164.55 45,455.58 45,455.58
As Submitted 5.44% 1,838.93 cu.m. - 6,570.20 201,200.27 112.98 207,770.47 25% 51,942.62 12,985.65 272,698.74 148.29
102(2) Surplus Common Excavation
As Evaluated 5.44% 1,838.93 cu.m. - 6,570.20 201,200.27 112.98 207,770.47 25% 51,942.62 12,985.65 272,698.74 148.29
As Submitted 0.07% 12.67 cu.m. - 99.41 2,458.69 201.90 2,558.10 25% 639.53 159.88 3,357.51 265.00
104(1)a Embankment from roadway excavation (Common Soil)
As Evaluated 0.07% 12.67 cu.m. - 99.41 2,458.69 201.90 2,558.10 25% 639.53 159.88 3,357.51 265.00
As Submitted 0.97% 2,291.40 sq.m. - 1,637.36 35,375.40 16.15 37,012.76 25% 9,253.19 2,313.30 48,579.25 21.20
105(1)a Subgrade Preparation (Common Material)
As Evaluated 0.97% 2,291.40 sq.m. - 1,637.36 35,375.40 16.15 37,012.76 25% 9,253.19 2,313.30 48,579.25 21.20
As Submitted 6.47% - 12,909.53 269,064.62 281,974.15 70,493.55 17,623.38 370,091.08
TOTAL OF PART C
As Evaluated 6.47% - 12,909.53 269,064.62 281,974.15 70,493.55 17,623.38 370,091.08
PART D SUBBASE AND BASE COURSE
As Submitted 10.19% 482.40 cu.m 342,430.65 2,068.24 44,684.71 806.77 389,183.60 25% 97,295.90 24,323.98 510,803.48 1,058.88
200(1) Aggregate Subbase Course
As Evaluated 10.19% 482.40 cu.m 342,430.65 2,068.24 44,684.71 806.77 389,183.60 25% 97,295.90 24,323.98 510,803.48 1,058.88
As Submitted 10.19% 342,430.65 2,068.24 44,684.71 389,183.60 97,295.90 24,323.98 510,803.48
TOTAL OF PART D
As Evaluated 10.19% 342,430.65 2,068.24 44,684.71 389,183.60 97,295.90 24,323.98 510,803.48
PART E SURFACE COURSES
As Submitted 72.16% 1,839.16 sq.m. 2,706,322.84 28,168.84 21,957.25 1,498.75 2,756,448.93 25% 689,112.23 172,278.06 3,617,839.22 1,967.11
311(1)c1 Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days
As Evaluated 72.16% 1,839.16 sq.m. 2,706,322.84 28,168.84 21,957.25 1,498.75 2,756,448.93 25% 689,112.23 172,278.06 3,617,839.22 1,967.11
As Submitted 72.16% 2,706,322.84 28,168.84 21,957.25 2,756,448.93 689,112.23 172,278.06 3,617,839.22
TOTAL OF PART E
As Evaluated 72.16% 2,706,322.84 28,168.84 21,957.25 2,756,448.93 689,112.23 172,278.06 3,617,839.22
PART F BRIDGE CONSTRUCTION
As Submitted 0.00% - - - - - - -
TOTAL OF PART F
As Evaluated 0.00% - - - - - - -
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
TOTAL OF PART G As Submitted 0.00% - - - - - - -
As Evaluated 0.00% - - - - - - -
PART H MISCELLANEOUS STRUCTURES
TOTAL OF PART H As Submitted 0.00% - - - - - - -
As Evaluated 0.00% - - - - - - -
PART I PROVISIONAL SUM
TOTAL OF PART I As Submitted 0.00% - - - - - - -
As Evaluated 0.00% - - - - - - -
PART J DAYWORK
TOTAL OF PART J As Submitted 0.00% - - - - - - -
As Evaluated 0.00% - - - - - - -
As Submitted 99.09% 3,165,202.90 271,055.25 383,701.05 3,819,959.20 894,326.52 235,714.28 4,950,000.00
GRAND TOTAL
As Evaluated 99.09% 3,165,202.90 271,055.25 383,701.05 3,819,959.20 894,326.52 235,714.28 4,950,000.00
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS SUBMITTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
PART A FACILITIES FOR THE ENGINEER
A.1.1(3) Construction of Field Office for the Engineer 1.00 1.00 l.s. 76,438.89 76,438.89 76,438.89 76,438.89 88,286.92 88,286.92 2.00% 2.00%
A.1.4(1) Provision of Progress Photographs 120.00 120.00 ea. 1,800.00 1,800.00 15.00 15.00 17.33 17.33 0.05% 0.05%
TOTAL OF PART A 78,238.89 78,238.89
PART B OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard 2.00 2.00 ea. 10,781.28 10,781.28 5,390.64 5,390.64 7,075.22 7,075.22 0.28% 0.28%
B.7(2) Occupational Safety and Health Program 1.00 1.00 l.s. 195,054.77 195,054.77 195,054.77 195,054.77 225,288.26 225,288.26 5.11% 5.11%
B.8(2) Traffic Management 1.00 1.00 l.s. 74,001.51 74,001.51 74,001.51 74,001.51 85,471.74 85,471.74 1.94% 1.94%
B.9 Mobilization / Demobilization 1.00 1.00 l.s. 34,276.07 34,276.07 34,276.07 34,276.07 35,989.87 35,989.87 0.90% 0.90%
TOTAL OF PART B 314,113.63 314,113.63
PART C EARTHWORKS
101(1) Removal of Structures and Obstructions 1.00 1.00 l.s. 34,632.82 34,632.82 34,632.82 34,632.82 45,455.58 45,455.58 0.91% 0.91%
102(2) Surplus Common Excavation 1,838.93 1,838.93 cu.m. 207,770.47 207,770.47 112.98 112.98 148.29 148.29 5.44% 5.44%
104(1)a Embankment from roadway excavation (Common Soil) 12.67 12.67 cu.m. 2,558.10 2,558.10 201.90 201.90 265.00 265.00 0.07% 0.07%
105(1)a Subgrade Preparation (Common Material) 2,291.40 2,291.40 sq.m. 37,012.76 37,012.76 16.15 16.15 21.20 21.20 0.97% 0.97%
TOTAL OF PART C 281,974.15 281,974.15
PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course 482.40 482.40 cu.m 389,183.60 389,183.60 806.77 806.77 1,058.88 1,058.88 10.19% 10.19%
TOTAL OF PART D 389,183.60 389,183.60
PART E SURFACE COURSES
311(1)c1 Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days 1,839.16 1,839.16 sq.m. 2,756,448.93 2,756,448.93 1,498.75 1,498.75 1,967.11 1,967.11 72.16% 72.16%
TOTAL OF PART E 2,756,448.93 2,756,448.93
PART F BRIDGE CONSTRUCTION
TOTAL OF PART F
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
TOTAL OF PART G - -
PART H MISCELLANEOUS STRUCTURES
TOTAL OF PART H - -
PART I PROVISIONAL SUM
TOTAL OF PART I
PART J DAYWORK
TOTAL OF PART J
GRAND TOTAL 3,819,959.20 3,819,959.20 100.00% 100.00%
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
3
1 Backhoe 0.80 m 1 31
2 Dump Truck 12 yd
3
2 32
3 Plate Compactor 5 hp 1 33
4 Concrete Vibrator 5 amp 1 34
5 Water Truck 16,000 L, 360 hp 1 35
6 Concrete Screeder 1 36
7 Low Bed Trailer 1 37
8 Payloader 1 38
9 Motorized Road Grader 1 39
10 Vibratory Roller 1 40
11 Bar Cutter 1 41
12 Concrete Saw 1 42
13 43
14 44
15 45
16 46
17 47
18 48
19 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-TOTAL SUB-TOTAL
13 0
TOTAL 13
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02-00
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
JUMEL B. REYES FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN MA. CHYMBELIN D. IBAL ROGELIO S. CRESPO
Engineer II Chief, Planning & Design Section Chief, Construction Section Assistant District Engineer District Engineer
Construction Section
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
PREPARED BY:
JUMEL B. REYES
Engineer II
BACK UP COMPUTATION
PROJECT : LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc, Sariaya, Quezon
LOCATION : Sariaya, Quezon
ITEM NO. : 102 & 104
DESCRIPTION : Roadway Excavation & Embankment (from borrow)
𝐅𝐈𝐋𝐋
ITEM 102 : CUT − = 1,838.93 cu. m.
𝟎.𝟖𝟎
PROJECT : LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road,
Barangay Talaan Pantoc, Sariaya, Quezon
LOCATION : Sariaya, Quezon
ITEM NO. : 311(1)c1
DESCRIPTION : Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
Structural Concrete:
Volume:
L W H Q
Footing 0.6 0.6 0.2 4 0.288 Cement 37 bags
Column 0.2 0.2 1.6 4 0.256 Sand 2 cu.m.
WF 0.35 10.4 0.15 1 0.546 Gravel 3 cu.m.
Slab 4 4 0.1 1 1.6
CHB Mortar Cement 9.00 Sand 0.52
CHB Plaster Cement 3.00 Sand 0.19
2.69
Reinforcing Steel Bar:
w/m
Footing x 10 mmØ 0.6165 0.6 4 4 5.92
Footing y 10 mmØ 0.6165 0.6 4 4 5.92
Column 12 mmØ 0.8878 2 4 4 28.41
Stirrups 10 mmØ 0.6165 0.58 9 4 12.87
WF 10 mmØ 0.6165 10.4 1 1 6.41
Slab 10 mmØ 0.6165 7 1 1 4.32
10 mmØ 0.6165 7 1 1 4.32
Hor. Vert.
For CHB 10 mmØ 0.6165 25.714 19.136 27.65
95.82 kgs.
100mm Thk. Concrete Hollow Blocks
Ht. L
Area: 1.15 10.4 11.96 sq.m.
150 pcs.
Good Lumber
L cu.in. bd.ft.
2x2 2 2 5043.31 144 140.09
2x3 2 3 661.42 144 27.56
2x4 2 4 673.23 144 37.40
2x5 2 5 696.85 144 48.39
3x5 3 5 236.22 144 24.61
4x4 4 4 283.46 144 31.50
309.55 bd.ft.
1 x 20 watts FLF
Quantity: 1 set
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
DURATION: 120
a. Safety Officer (Full Time) 1 960.00 62.50 60,000.00
b. Health Personnel (Full Time First Aider) 1 960.00 35.00 33,600.00
c. Sanitation Aide 2 960.00 35.00 67,200.00
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
Rental Basis (Based on D.O. 13 Series of 2018) Unit Cost for 120 C.D.
g. Roadwork 1km Ahead ea. 1.00 1314.17 1,314.17
h. Lane Status ea. 1.00 1553.92 1,553.92
i. Road Work ea. 1.00 464.44 464.44
j. Speed Restriction ea. 1.00 567.13 567.13
k. Workmen Ahead ea. 1.00 676.72 676.72
l. Temporary Hazard Maker (Chevron) ea. 2.00 961.05 1,922.10
m. End Speed Restriction ea. 2.00 666.42 1,332.83
n. End Road Work ea. 2.00 1314.17 2,628.34
Rental Basis (Based on D.O. 13 Series of 2018) Unit Cost for 120 C.D.
g. Roadwork 1km Ahead ea. 1.00 1,314.17 1,314.17
h. Lane Status ea. 1.00 1,553.92 1,553.92
i. Road Work ea. 1.00 464.44 464.44
j. Speed Restriction ea. 1.00 567.13 567.13
k. Workmen Ahead ea. 1.00 676.72 676.72
l. Temporary Hazard Maker (Chevron) ea. 2.00 961.05 1,922.10
m. End Speed Restriction ea. 2.00 666.42 1,332.83
n. End Road Work ea. 2.00 1,314.17 2,628.34
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
Prepared
`1`1by: Checked/Reviewed by:
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
Item no./Description : 311(1)c1 Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days
Unit of Measurement : sq.m.
Output per hour - As Submitted : 70.00
Output per hour - As Evaluated : 70.00
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor