You are on page 1of 28

Republic of the Philippines

Department of Public Works and Highways


QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Dalahican Road, Lucena City

LOCAL PROGRAM, Local Infrastructure


Program, Local Roads and Bridges, Local
Roads, Construction of Road, Barangay
Talaan Pantoc,
Sariaya, Quezon

(LIP 2021)
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Appropriation : (a) Road 301.50
: Barangay Talaan Pantoc, Sariaya, Quezon : (b) Bridge
Project ID : : (c) Others
Location : Sariaya, Quezon Target Start Date :
Station Limits : STA. 0 + 000 - STA. 0 + 301.50 Total Project Duration : 120 C.D.
Appropriation : P 5,000,000.00 No. of Pre-determined :
Source of Fund : LIP 2021 Unworkable Days :

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part A: Facilities for the Engineer 2.05% 78,238.89 2.05% 78,238.89
B: Other General Requirements 8.22% 314,113.63 8.22% 314,113.63
C: Earthworks 7.38% 281,974.15 7.38% 281,974.15
D: Subbase and Base Course 10.19% 389,183.60 10.19% 389,183.60
E: Surface Courses (PLS. SEE FORM POW-2015-01C-00) 72.16% 2,756,448.93 72.16% 2,756,448.93
F: Bridge Construction 0.00% - 0.00% -
G: Drainage and Slope Protection Structures 0.00% - 0.00% -
H: Miscellaneous Structures 0.00% - 0.00% -
I: Provisional Sum 0.00% - 0.00% -
J: Daywork 0.00% - 0.00% -

Total 100.00% 3,819,959.20 100.00% 3,819,959.20

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 271,055.25 271,055.25 A. Total Direct Cost 3,819,959.20 3,819,959.20
2. Materials 3,165,202.90 3,165,202.90 B. OCM and Profit 894,326.52 894,326.52
3. Rental of Equipment 383,701.05 383,701.05 C. Value Added Tax 235,714.28 235,714.28
4. Provisional Sum / Daywork D. Total Construction Cost 4,950,000.00 4,950,000.00
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 894,326.52 894,326.52 E. Eng'g & Administrative Overhead, 1% 50,000.00 50,000.00
6. Value Added Tax (5%) 235,714.28 235,714.28 F. RROW Acquisition
7. EAO, 1% 50,000.00 50,000.00 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 5,000,000.00 5,000,000.00 H. TOTAL ESTIMATED COST 5,000,000.00 5,000,000.00

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

JUMEL B. REYES FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN MA. CHYMBELIN D. IBAL ROGELIO S. CRESPO
Engineer II Chief, Planning & Design Section Chief, Construction Section Assistant District Engineer District Engineer
Construction Section
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP ADJUSTED UNIT
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE COST
PART A FACILITIES FOR THE ENGINEER
As Submitted 2.00% 1.00 l.s. 57,123.05 19,315.84 - 76,438.89 76,438.89 10% 7,643.89 4,204.14 88,286.92 88,286.92
A.1.1(3) Construction of Field Office for the Engineer
As Evaluated 2.00% 1.00 l.s. 57,123.05 19,315.84 - 76,438.89 76,438.89 10% 7,643.89 4,204.14 88,286.92 88,286.92
As Submitted 0.05% 120.00 ea. 1,800.00 - - 15.00 1,800.00 10% 180.00 99.00 2,079.00 17.33
A.1.4(1) Provision of Progress Photographs
As Evaluated 0.05% 120.00 ea. 1,800.00 - - 15.00 1,800.00 10% 180.00 99.00 2,079.00 17.33
As Submitted 2.05% 58,923.05 19,315.84 78,238.89 7,823.89 4,303.14 90,365.92
TOTAL OF PART A
As Evaluated 2.05% 58,923.05 19,315.84 - 78,238.89 7,823.89 4,303.14 90,365.92
PART B OTHER GENERAL REQUIREMENTS
As Submitted 0.28% 2.00 ea. 8,480.00 2,301.28 - 5,390.64 10,781.28 25% 2,695.32 673.83 14,150.43 7,075.22
B.5 Project Billboard / Signboard
As Evaluated 0.28% 2.00 ea. 8,480.00 2,301.28 - 5,390.64 10,781.28 25% 2,695.32 673.83 14,150.43 7,075.22
As Submitted 5.11% 1.00 l.s. 20,536.37 160,800.00 13,718.40 195,054.77 195,054.77 10% 19,505.48 10,728.01 225,288.26 225,288.26
B.7(2) Occupational Safety and Health Program
As Evaluated 5.11% 1.00 l.s. 20,536.37 160,800.00 13,718.40 195,054.77 195,054.77 10% 19,505.48 10,728.01 225,288.26 225,288.26
As Submitted 1.94% 1.00 l.s. 28,509.99 45,491.52 - 74,001.51 74,001.51 10% 7,400.15 4,070.08 85,471.74 85,471.74
B.8(2) Traffic Management
As Evaluated 1.94% 1.00 l.s. 28,509.99 45,491.52 - 74,001.51 74,001.51 10% 7,400.15 4,070.08 85,471.74 85,471.74
As Submitted 0.90% 1.00 l.s. - - 34,276.07 34,276.07 34,276.07 0% - 1,713.80 35,989.87 35,989.87
B.9 Mobilization / Demobilization
As Evaluated 0.90% 1.00 l.s. - - 34,276.07 34,276.07 34,276.07 0% - 1,713.80 35,989.87 35,989.87
As Submitted 8.22% 57,526.36 208,592.80 47,994.47 314,113.63 29,600.95 17,185.72 360,900.30
TOTAL OF PART B
As Evaluated 8.22% 57,526.36 208,592.80 47,994.47 314,113.63 29,600.95 17,185.72 360,900.30
PART C EARTHWORKS
As Submitted 0.91% 1.00 l.s. - 4,602.56 30,030.26 34,632.82 34,632.82 25% 8,658.21 2,164.55 45,455.58 45,455.58
101(1) Removal of Structures and Obstructions
As Evaluated 0.91% 1.00 l.s. - 4,602.56 30,030.26 34,632.82 34,632.82 25% 8,658.21 2,164.55 45,455.58 45,455.58
As Submitted 5.44% 1,838.93 cu.m. - 6,570.20 201,200.27 112.98 207,770.47 25% 51,942.62 12,985.65 272,698.74 148.29
102(2) Surplus Common Excavation
As Evaluated 5.44% 1,838.93 cu.m. - 6,570.20 201,200.27 112.98 207,770.47 25% 51,942.62 12,985.65 272,698.74 148.29
As Submitted 0.07% 12.67 cu.m. - 99.41 2,458.69 201.90 2,558.10 25% 639.53 159.88 3,357.51 265.00
104(1)a Embankment from roadway excavation (Common Soil)
As Evaluated 0.07% 12.67 cu.m. - 99.41 2,458.69 201.90 2,558.10 25% 639.53 159.88 3,357.51 265.00
As Submitted 0.97% 2,291.40 sq.m. - 1,637.36 35,375.40 16.15 37,012.76 25% 9,253.19 2,313.30 48,579.25 21.20
105(1)a Subgrade Preparation (Common Material)
As Evaluated 0.97% 2,291.40 sq.m. - 1,637.36 35,375.40 16.15 37,012.76 25% 9,253.19 2,313.30 48,579.25 21.20
As Submitted 6.47% - 12,909.53 269,064.62 281,974.15 70,493.55 17,623.38 370,091.08
TOTAL OF PART C
As Evaluated 6.47% - 12,909.53 269,064.62 281,974.15 70,493.55 17,623.38 370,091.08
PART D SUBBASE AND BASE COURSE
As Submitted 10.19% 482.40 cu.m 342,430.65 2,068.24 44,684.71 806.77 389,183.60 25% 97,295.90 24,323.98 510,803.48 1,058.88
200(1) Aggregate Subbase Course
As Evaluated 10.19% 482.40 cu.m 342,430.65 2,068.24 44,684.71 806.77 389,183.60 25% 97,295.90 24,323.98 510,803.48 1,058.88
As Submitted 10.19% 342,430.65 2,068.24 44,684.71 389,183.60 97,295.90 24,323.98 510,803.48
TOTAL OF PART D
As Evaluated 10.19% 342,430.65 2,068.24 44,684.71 389,183.60 97,295.90 24,323.98 510,803.48
PART E SURFACE COURSES
As Submitted 72.16% 1,839.16 sq.m. 2,706,322.84 28,168.84 21,957.25 1,498.75 2,756,448.93 25% 689,112.23 172,278.06 3,617,839.22 1,967.11
311(1)c1 Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days
As Evaluated 72.16% 1,839.16 sq.m. 2,706,322.84 28,168.84 21,957.25 1,498.75 2,756,448.93 25% 689,112.23 172,278.06 3,617,839.22 1,967.11
As Submitted 72.16% 2,706,322.84 28,168.84 21,957.25 2,756,448.93 689,112.23 172,278.06 3,617,839.22
TOTAL OF PART E
As Evaluated 72.16% 2,706,322.84 28,168.84 21,957.25 2,756,448.93 689,112.23 172,278.06 3,617,839.22
PART F BRIDGE CONSTRUCTION
As Submitted 0.00% - - - - - - -
TOTAL OF PART F
As Evaluated 0.00% - - - - - - -
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
TOTAL OF PART G As Submitted 0.00% - - - - - - -
As Evaluated 0.00% - - - - - - -
PART H MISCELLANEOUS STRUCTURES
TOTAL OF PART H As Submitted 0.00% - - - - - - -
As Evaluated 0.00% - - - - - - -
PART I PROVISIONAL SUM
TOTAL OF PART I As Submitted 0.00% - - - - - - -
As Evaluated 0.00% - - - - - - -
PART J DAYWORK
TOTAL OF PART J As Submitted 0.00% - - - - - - -
As Evaluated 0.00% - - - - - - -
As Submitted 99.09% 3,165,202.90 271,055.25 383,701.05 3,819,959.20 894,326.52 235,714.28 4,950,000.00
GRAND TOTAL
As Evaluated 99.09% 3,165,202.90 271,055.25 383,701.05 3,819,959.20 894,326.52 235,714.28 4,950,000.00
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon

FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS SUBMITTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
PART A FACILITIES FOR THE ENGINEER

A.1.1(3) Construction of Field Office for the Engineer 1.00 1.00 l.s. 76,438.89 76,438.89 76,438.89 76,438.89 88,286.92 88,286.92 2.00% 2.00%
A.1.4(1) Provision of Progress Photographs 120.00 120.00 ea. 1,800.00 1,800.00 15.00 15.00 17.33 17.33 0.05% 0.05%
TOTAL OF PART A 78,238.89 78,238.89
PART B OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard 2.00 2.00 ea. 10,781.28 10,781.28 5,390.64 5,390.64 7,075.22 7,075.22 0.28% 0.28%
B.7(2) Occupational Safety and Health Program 1.00 1.00 l.s. 195,054.77 195,054.77 195,054.77 195,054.77 225,288.26 225,288.26 5.11% 5.11%
B.8(2) Traffic Management 1.00 1.00 l.s. 74,001.51 74,001.51 74,001.51 74,001.51 85,471.74 85,471.74 1.94% 1.94%
B.9 Mobilization / Demobilization 1.00 1.00 l.s. 34,276.07 34,276.07 34,276.07 34,276.07 35,989.87 35,989.87 0.90% 0.90%
TOTAL OF PART B 314,113.63 314,113.63
PART C EARTHWORKS

101(1) Removal of Structures and Obstructions 1.00 1.00 l.s. 34,632.82 34,632.82 34,632.82 34,632.82 45,455.58 45,455.58 0.91% 0.91%
102(2) Surplus Common Excavation 1,838.93 1,838.93 cu.m. 207,770.47 207,770.47 112.98 112.98 148.29 148.29 5.44% 5.44%
104(1)a Embankment from roadway excavation (Common Soil) 12.67 12.67 cu.m. 2,558.10 2,558.10 201.90 201.90 265.00 265.00 0.07% 0.07%
105(1)a Subgrade Preparation (Common Material) 2,291.40 2,291.40 sq.m. 37,012.76 37,012.76 16.15 16.15 21.20 21.20 0.97% 0.97%
TOTAL OF PART C 281,974.15 281,974.15
PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course 482.40 482.40 cu.m 389,183.60 389,183.60 806.77 806.77 1,058.88 1,058.88 10.19% 10.19%
TOTAL OF PART D 389,183.60 389,183.60
PART E SURFACE COURSES
311(1)c1 Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days 1,839.16 1,839.16 sq.m. 2,756,448.93 2,756,448.93 1,498.75 1,498.75 1,967.11 1,967.11 72.16% 72.16%
TOTAL OF PART E 2,756,448.93 2,756,448.93
PART F BRIDGE CONSTRUCTION
TOTAL OF PART F
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
TOTAL OF PART G - -
PART H MISCELLANEOUS STRUCTURES
TOTAL OF PART H - -
PART I PROVISIONAL SUM
TOTAL OF PART I
PART J DAYWORK
TOTAL OF PART J
GRAND TOTAL 3,819,959.20 3,819,959.20 100.00% 100.00%
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
3
1 Backhoe 0.80 m 1 31
2 Dump Truck 12 yd
3
2 32
3 Plate Compactor 5 hp 1 33
4 Concrete Vibrator 5 amp 1 34
5 Water Truck 16,000 L, 360 hp 1 35
6 Concrete Screeder 1 36
7 Low Bed Trailer 1 37
8 Payloader 1 38
9 Motorized Road Grader 1 39
10 Vibratory Roller 1 40
11 Bar Cutter 1 41
12 Concrete Saw 1 42
13 43
14 44
15 45
16 46
17 47
18 48
19 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60

SUB-TOTAL SUB-TOTAL
13 0
TOTAL 13
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02-00

LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon

SUMMARY OF APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 120
TOTAL MARK-UP
ITEM NO. DESCRIPTION ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST
% VALUE
AS SUBMITTED 78,238.89 10.00% 7,823.89 4,303.14 12,127.03 90,365.92
PART A FACILITIES FOR THE ENGINEER
AS EVALUATED 78,238.89 10.00% 7,823.89 4,303.14 12,127.03 90,365.92
AS SUBMITTED 314,113.63 9.42% 29,600.95 17,185.72 46,786.67 360,900.30
PART B OTHER GENERAL REQUIREMENTS
AS EVALUATED 314,113.63 9.42% 29,600.95 17,185.72 46,786.67 360,900.30
AS SUBMITTED 281,974.15 25.00% 70,493.55 17,623.38 88,116.93 370,091.08
PART C EARTHWORKS
AS EVALUATED 281,974.15 25.00% 70,493.55 17,623.38 88,116.93 370,091.08
AS SUBMITTED 389,183.60 25.00% 97,295.90 24,323.98 121,619.88 510,803.48
PART D SUBBASE AND BASE COURSE
AS EVALUATED 389,183.60 25.00% 97,295.90 24,323.98 121,619.88 510,803.48
AS SUBMITTED 2,756,448.93 25.00% 689,112.23 172,278.06 861,390.29 3,617,839.22
PART E SURFACE COURSES
AS EVALUATED 2,756,448.93 25.00% 689,112.23 172,278.06 861,390.29 3,617,839.22
AS SUBMITTED
PART F BRIDGE CONSTRUCTION
AS EVALUATED
AS SUBMITTED - - - - -
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
AS EVALUATED - - - - -
AS SUBMITTED - - - - -
PART H MISCELLANEOUS STRUCTURES
AS EVALUATED - - - - -
AS SUBMITTED
PART I PROVISIONAL SUM
AS EVALUATED
AS SUBMITTED
PART J DAYWORK
AS EVALUATED
AS SUBMITTED 3,819,959.20 894,326.52 235,714.28 1,130,040.80 4,950,000.00
TOTAL
AS EVALUATED 3,819,959.20 894,326.52 235,714.28 1,130,040.80 4,950,000.00

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Evaluated by: Recommending Approval: Approved:

JUMEL B. REYES FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN MA. CHYMBELIN D. IBAL ROGELIO S. CRESPO
Engineer II Chief, Planning & Design Section Chief, Construction Section Assistant District Engineer District Engineer
Construction Section
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 120

ESTIMATED DIRECT TOTAL MARK-UP


ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL INDIRECT COST TOTAL COST UNIT COST
COST % VALUE
PART A FACILITIES FOR THE ENGINEER
AS SUBMITTED 1.00 l.s. 76,438.89 10% 7,643.89 4,204.14 11,848.03 88,286.92 88,286.92
A.1.1(3) Construction of Field Office for the Engineer
AS EVALUATED 1.00 l.s. 76,438.89 10% 7,643.89 4,204.14 11,848.03 88,286.92 88,286.92
AS SUBMITTED 120.00 ea. 1,800.00 10% 180.00 99.00 279.00 2,079.00 17.33
A.1.4(1) Provision of Progress Photographs
AS EVALUATED 120.00 ea. 1,800.00 10% 180.00 99.00 279.00 2,079.00 17.33
AS SUBMITTED 78,238.89 7,823.89 4,303.14 12,127.03 90,365.92
TOTAL OF PART A
AS EVALUATED 78,238.89 7,823.89 4,303.14 12,127.03 90,365.92
PART B OTHER GENERAL REQUIREMENTS
AS SUBMITTED 2.00 ea. 10,781.28 25% 2,695.32 673.83 3,369.15 14,150.43 7,075.22
B.5 Project Billboard / Signboard
AS EVALUATED 2.00 ea. 10,781.28 25% 2,695.32 673.83 3,369.15 14,150.43 7,075.22
AS SUBMITTED 1.00 l.s. 195,054.77 10% 19,505.48 10,728.01 30,233.49 225,288.26 225,288.26
B.7(2) Occupational Safety and Health Program
AS EVALUATED 1.00 l.s. 195,054.77 10% 19,505.48 10,728.01 30,233.49 225,288.26 225,288.26
AS SUBMITTED 1.00 l.s. 74,001.51 10% 7,400.15 4,070.08 11,470.23 85,471.74 85,471.74
B.8(2) Traffic Management
AS EVALUATED 1.00 l.s. 74,001.51 10% 7,400.15 4,070.08 11,470.23 85,471.74 85,471.74
AS SUBMITTED 1.00 l.s. 34,276.07 0% - 1,713.80 1,713.80 35,989.87 35,989.87
B.9 Mobilization / Demobilization
AS EVALUATED 1.00 l.s. 34,276.07 0% - 1,713.80 1,713.80 35,989.87 35,989.87
AS SUBMITTED 314,113.63 29,600.95 17,185.72 46,786.67 360,900.30
TOTAL OF PART B
AS EVALUATED 314,113.63 29,600.95 17,185.72 46,786.67 360,900.30

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

JUMEL B. REYES FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Engineer II Chief, Planning & Design Section Chief, Construction Section
Construction Section
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 120

ESTIMATED DIRECT TOTAL MARK-UP


ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL INDIRECT COST TOTAL COST UNIT COST
COST % VALUE
PART C EARTHWORKS
FACILITIES FOR THE ENGINEER
AS SUBMITTED 1.00 l.s. 34,632.82 25% 8,658.21 2,164.55 10,822.76 45,455.58 45,455.58
101(1) Removal of Structures and Obstructions
AS EVALUATED 1.00 l.s. 34,632.82 25% 8,658.21 2,164.55 10,822.76 45,455.58 45,455.58
AS SUBMITTED 1,838.93 cu.m. 207,770.47 25% 51,942.62 12,985.65 64,928.27 272,698.74 148.29
102(2) Surplus Common Excavation
AS EVALUATED 1,838.93 cu.m. 207,770.47 25% 51,942.62 12,985.65 64,928.27 272,698.74 148.29
AS SUBMITTED 12.67 cu.m. 2,558.10 25% 639.53 159.88 799.41 3,357.51 265.00
104(1)a Embankment from roadway excavation (Common Soil)
AS EVALUATED 12.67 cu.m. 2,558.10 25% 639.53 159.88 799.41 3,357.51 265.00
AS SUBMITTED 2,291.40 sq.m. 37,012.76 25% 9,253.19 2,313.30 11,566.49 48,579.25 21.20
105(1)a Subgrade Preparation (Common Material) AS EVALUATED 2,291.40 sq.m. 37,012.76 25% 9,253.19 2,313.30 11,566.49 48,579.25 21.20
TOTAL OF PART C
AS SUBMITTED 281,974.15 70,493.55 17,623.38 88,116.93 370,091.08
AS EVALUATED 281,974.15 70,493.55 17,623.38 88,116.93 370,091.08
PART D SUBBASE AND BASE COURSE
AS SUBMITTED 482.40 cu.m. 389,183.60 25% 97,295.90 24,323.98 121,619.88 510,803.48 1,058.88
200(1) Aggregate Subbase Course AS EVALUATED 482.40 cu.m. 389,183.60 25% 97,295.90 24,323.98 121,619.88 510,803.48 1,058.88
TOTAL OF PART D
AS SUBMITTED 389,183.60 97,295.90 24,323.98 121,619.88 510,803.48
AS EVALUATED 389,183.60 97,295.90 24,323.98 121,619.88 510,803.48
PART E SURFACE COURSES
Portland Cement Concrete Pavement (Unreinforced) - 0.23 m AS SUBMITTED 1,839.16 sq.m. 2,756,448.93 25% 689,112.23 172,278.06 861,390.29 3,617,839.22 1,967.11
311(1)c1
thick, 14 days AS EVALUATED 1,839.16 sq.m. 2,756,448.93 25% 689,112.23 172,278.06 861,390.29 3,617,839.22 1,967.11
TOTAL OF PART E
AS SUBMITTED 2,756,448.93 689,112.23 172,278.06 861,390.29 3,617,839.22
AS EVALUATED 2,756,448.93 689,112.23 172,278.06 861,390.29 3,617,839.22
PART F BRIDGE CONSTRUCTION
TOTAL OF PART F AS SUBMITTED - - - - -
AS EVALUATED
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
AS SUBMITTED - - - - -
TOTAL OF PART G AS EVALUATED - - - - -
PART H MISCELLANEOUS STRUCTURES
TOTAL OF PART H AS SUBMITTED - - - - -
AS EVALUATED - - - - -
PART I PROVISIONAL SUM
TOTAL OF PART I AS SUBMITTED - - - - -
AS EVALUATED
PART J DAYWORK
TOTAL OF PART J AS SUBMITTED - - - - -
AS EVALUATED
AS SUBMITTED 3,819,959.20 894,326.52 235,714.28 1,130,040.80 4,950,000.00
GRAND TOTAL
AS EVALUATED 3,819,959.20 894,326.52 235,714.28 1,130,040.80 4,950,000.00
Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

JUMEL B. REYES FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Engineer II Chief, Planning & Design Section Chief, Construction Section
Construction Section
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc, Sariaya, Quezon
ITEM NO. DESCRIPTION QUANTITY UNIT REMARKS

PART A FACILITIES FOR THE ENGINEER


A.1.1(3) Construction of Field Office for the Engineer 1.00 l.s.

A.1.4(1) Provision of Progress Photographs 120.00 ea.


PART B OTHER GENERAL REQUIREMENTS
B.5 Project Billboard/ Signboard 2.00 ea.

B.7(2) Occupational Safety and Health Program 1.00 l.s.

B.8(2) Traffic Management 1.00 l.s.

B.9 Mobilization / Demobilization 1.00 l.s.


PART C EARTHWORKS
101(1) Removal of Structures and Obstructions 1.00 l.s.

102(2) Surplus Common Excavation 1838.93 cu.m.

104(1)a Embankment from Roadway Excavation (Common Soil) 12.67 cu.m.

105(1)a Subgrade Preparation (Common Material) 2291.40 sq.m.


PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course 482.40 cu.m. COMPACTED VOLUME

PART E SURFACE COURSES


311(1)c1 Portland Cement Concrete Pavement (Unreinforced, 023m thick, 14 days) 1839.16 sq.m.
BACK-UP COMPUTATION

A.1.1(3) Construction of Field Office for the Engineer


QUANTITY : 1.00 l.s.

A.1.4(1) Provision of Progress Photographs


QUANTITY : 120.00 ea.

B.5 Project Billboard / Signboard


QUANTITY : 2.00 ea.

B.7(2) Occupational Safety and Health Program


QUANTITY : 1.00 l.s.

B.8(2) Traffic Management


QUANTITY : 1.00 l.s.

B.9 Mobilization / Demobilization


QUANTITY : 1.00 l.s.

101(1) Removal of Structures and Obstructions


QUANTITY : 1.00 l.s.
( SEE QUANTITY SHEET )

102(2) Surplus Common Excavation


QUANTITY : 1,838.93 cu.m.
( SEE QUANTITY SHEET )

104(1)a Embankment from roadway excavation (Common Soil)


QUANTITY : 12.67 cu.m.
( SEE QUANTITY SHEET )

105(1)a Subgrade Preparation (Common Material)


QUANTITY : 2,291.40 sq.m.
( SEE QUANTITY SHEET )

200(1) Aggregate Subbase Course


QUANTITY : 482.40 cu.m.

AREA: 1.60 sq.m.


LENGTH : 301.50 m

Vol: AREA x LENGTH


Vol: 482.40 cu.m.

311(1)c1 Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days


QUANTITY : 1,839.16 sq.m.
( SEE QUANTITY SHEET )

PREPARED BY:

JUMEL B. REYES
Engineer II
BACK UP COMPUTATION
PROJECT : LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc, Sariaya, Quezon
LOCATION : Sariaya, Quezon
ITEM NO. : 102 & 104
DESCRIPTION : Roadway Excavation & Embankment (from borrow)

AREA (sq.m.) VOLUME


STATION CUT FILL CUT FILL
LEFT RIGHT DIST.(M) LEFT RIGHT DIST.(M) LEFT RIGHT LEFT RIGHT

0 + 0.00 3.168 1.428 - 0.0570


20.00 20.00 65.09 41.76 - 0.57
0 + 20.00 3.341 2.748 - -
20.00 20.00 67.66 62.43 - -
0 + 40.00 3.425 3.495 - -
20.00 20.00 68.40 75.13 - -
0 + 60.00 3.415 4.018 - -
20.00 20.00 64.51 75.05 - -
0 + 80.00 3.036 3.487 - -
20.00 20.00 60.43 63.40 - -
0 + 100.00 3.007 2.853 - -
20.00 20.00 60.96 50.67 0.22 0.15
0 + 120.00 3.089 2.214 0.022 0.0150
20.00 20.00 64.38 37.38 1.27 1.63
0 + 140.00 3.349 1.524 0.105 0.1480
20.00 20.00 61.60 33.27 2.97 2.33
0 + 160.00 2.811 1.803 0.192 0.0850
20.00 20.00 49.68 55.66 2.30 0.85
0 + 180.00 2.157 3.763 0.038 -
20.00 20.00 42.48 93.90 0.38 -
0 + 200.00 2.091 5.627 - -
20.00 20.00 50.38 100.81 - -
0 + 220.00 2.947 4.454 - -
20.00 20.00 52.51 70.60 - -
0 + 240.00 2.304 2.606 - -
20.00 20.00 47.15 55.73 - -
0 + 260.00 2.411 2.967 - -
20.00 20.00 48.21 80.33 - -
0 + 280.00 2.410 5.066
20.00 20.00 51.77 92.98 - -
0 + 300.00 2.767 4.232
1.50 1.50 4.42 6.04 - -
0 + 301.50 3.127 3.816

859.63 995.14 7.14 5.53


1854.77 12.67

TOTAL CUT : 1854.77 cu. m.


TOTAL FILL : 12.67 cu. m.

𝐅𝐈𝐋𝐋
ITEM 102 : CUT − = 1,838.93 cu. m.
𝟎.𝟖𝟎

ITEM 104 : FILL = 12.67 cu. m.


BACK UP COMPUTATION

PROJECT : LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road,
Barangay Talaan Pantoc, Sariaya, Quezon
LOCATION : Sariaya, Quezon
ITEM NO. : 311(1)c1
DESCRIPTION : Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days

WIDTH AREA [311(1)e1] AREA [105(1)a]


STATION DIST.(M)
LEFT RIGHT LEFT RIGHT LEFT RIGHT
0 + 0.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 20.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 40.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 60.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 80.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 100.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 120.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 140.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 160.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 180.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 200.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 220.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 240.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 260.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 280.00 3.05 3.05
20.00 61.00 61.00 76.00 76.00
0 + 300.00 3.05 3.05
1.50 4.58 4.58 5.70 5.70
0 + 301.50 3.05 3.05

SUB-TOTAL 919.58 919.58 1,145.70 1,145.70


TOTAL 1,839.16 2,291.40
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : A.1.1(3) Construction of Field Office for the Engineer


Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor

a. Construction Foreman 1 32.00 101.45 3,246.40


b. Skilled Laborers 3 32.00 73.29 7,035.84
c. Laborers 5 32.00 56.46 9,033.60

Sub - Total for A.1 - As Submitted 19,315.84


A.2 Labor

a. Construction Foreman 1 32.00 101.45 3,246.40


b. Skilled Laborers 3 32.00 73.29 7,035.84
c. Laborers 5 32.00 56.46 9,033.60

Sub - Total for A.2 - As Evaluated 19,315.84


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

Sub - Total for B.1 - As Submitted


B.2 Equipment

Sub - Total for B.2 - As Submitted


C.1 Total (A.1 + B.1) - As Submitted 19,315.84
C.2 Total (A.2 + B.2) - As Evaluated 19,315.84
D.1 Output per hour - As Submitted = 1 l.s.
D.2 Output per hour - As Evaluated = 1 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 19,315.84
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 19,315.84
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. 1/4 x 4 x 8 Marine Plywood pc. 15.00 500.00 7,500.00


b. Good Lumber bd.ft. 309.55 60.00 18,573.00
c. Corrugated Roofing, Gauge 26 sq.m. 21.00 255.00 5,355.00
d. 2" x 4" Door Hinges pc. 3.00 70.00 210.00
e. 2" x 3" Window Hinges pc. 8.00 41.00 328.00
f. Portland Cement bag 37.00 250.00 9,250.00
g. Gravel 3/4 cu.m. 3.00 1,217.26 3,651.78
h. Sand cu.m. 2.00 1,217.26 2,434.52
i. Reinforcing Steel Bar Grade 40 kg. 95.82 37.50 3,593.25
j. CHB Ordinary 4" pcs. 150.00 15.00 2,250.00
k. Fascia Board (1/2 x 12" Marine Plywood) l.m. 8.40 93.75 787.50
l. Ridge Roll l.m. 4.20 100.00 420.00
m. 20 watts Flourescent LF set 1.00 255.00 255.00
n. Duplex Convenience Outlet set 2.00 130.00 260.00
o.One Gang Switch set 1.00 95.00 95.00
p. Panel Board & Cabinet set 1.00 500.00 500.00
q. #16 G.I. Tie Wires kgs. 2.00 80.00 160.00
r. Miscellaneous (Forms, CWN, Bolts, Electrical Wires etc.) lot 1.00 1,500.00 1,500.00

Sub - Total for F.1 - As Submitted 57,123.05


F.2 Materials

a. 1/4 x 4 x 8 Marine Plywood pc. 15.00 500.00 7,500.00


b. Good Lumber bd.ft. 309.55 60.00 18,573.00
c. Corrugated Roofing, Gauge 26 sq.m. 21.00 255.00 5,355.00
d. 2" x 4" Door Hinges pc. 3.00 70.00 210.00
e. 2" x 3" Window Hinges pc. 8.00 41.00 328.00
f. Portland Cement bag 37.00 250.00 9,250.00
g. Gravel 3/4 cu.m. 3.00 1,217.26 3,651.78
h. Sand cu.m. 2.00 1,217.26 2,434.52
i. Reinforcing Steel Bar Grade 40 kg. 95.82 37.50 3,593.25
j. CHB Ordinary 4" pcs. 150.00 15.00 2,250.00
k. Fascia Board (1/2 x 12" Marine Plywood) l.m. 8.40 93.75 787.50
l. Ridge Roll l.m. 4.20 100.00 420.00
m. 20 watts Flourescent LF set 1.00 255.00 255.00
n. Duplex Convenience Outlet set 2.00 130.00 260.00
o.One Gang Switch set 1.00 95.00 95.00
p. Panel Board & Cabinet set 1.00 500.00 500.00
q. #16 G.I. Tie Wires kgs. 2.00 80.00 160.00
r. Miscellaneous (Forms, CWN, Bolts, Electrical Wires etc.) lot 1.00 1,500.00 1,500.00

Sub - Total for F.2 - As Evaluated 57,123.05


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 76,438.89
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 76,438.89
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 7,643.89
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 7,643.89
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 4,204.14
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 4,204.14
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 88,286.92
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 88,286.92

Prepared by: Checked/Reviewed by:

JUMEL B. REYES CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
DETAILED CALCULATIONS OF FIELD OFFICE

Structural Concrete:
Volume:
L W H Q
Footing 0.6 0.6 0.2 4 0.288 Cement 37 bags
Column 0.2 0.2 1.6 4 0.256 Sand 2 cu.m.
WF 0.35 10.4 0.15 1 0.546 Gravel 3 cu.m.
Slab 4 4 0.1 1 1.6
CHB Mortar Cement 9.00 Sand 0.52
CHB Plaster Cement 3.00 Sand 0.19
2.69
Reinforcing Steel Bar:
w/m
Footing x 10 mmØ 0.6165 0.6 4 4 5.92
Footing y 10 mmØ 0.6165 0.6 4 4 5.92
Column 12 mmØ 0.8878 2 4 4 28.41
Stirrups 10 mmØ 0.6165 0.58 9 4 12.87
WF 10 mmØ 0.6165 10.4 1 1 6.41
Slab 10 mmØ 0.6165 7 1 1 4.32
10 mmØ 0.6165 7 1 1 4.32
Hor. Vert.
For CHB 10 mmØ 0.6165 25.714 19.136 27.65
95.82 kgs.
100mm Thk. Concrete Hollow Blocks
Ht. L
Area: 1.15 10.4 11.96 sq.m.
150 pcs.

Corrugated Roofing Sheet #26 Ridge Roll:


Wdth L Length: 4.2 m.
Area: 5 4.2 21 sq.m.

Fascia Board (1/2 x 12" HardiFlex)


Length: 8.4 m.

1/4" x 4 x 8 Marine Plywood


Door Openings:
Area: 0.9 2.1 1 1.89 sq.m. Door 1.08
Window 3.6
Window 4.68 sq.m.
Area: 1.2 1.2 2 2.88 sq.m. Hinge
1.2 0.6 1 0.72 sq.m. 2 x 4 Door Hinge 3 pcs.
2 x 3 Window Hinge 8 pcs.
Wall (Double) Ht L
Area: 1.8 12 21.6 sq.m.
0.3 6 1.8 sq.m. 1.2 1.4
23.4 15.00 pcs.
Less openings: 18.72 sq.m. Size:
Total Area: 24.21 sq.m. Quantity:

Good Lumber
L cu.in. bd.ft.
2x2 2 2 5043.31 144 140.09
2x3 2 3 661.42 144 27.56
2x4 2 4 673.23 144 37.40
2x5 2 5 696.85 144 48.39
3x5 3 5 236.22 144 24.61
4x4 4 4 283.46 144 31.50
309.55 bd.ft.

1 x 20 watts FLF
Quantity: 1 set

Duplex Convenience Outlet


Quantity: 2 set

One Gang Switch


Quantity: 1 set

Panel Board & Cabinet


Quantity: 1 set
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : A.1.4(1) Provision of Progress Photographs


Unit of Measurement : ea.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor

Sub - Total for A.1 - As Submitted


A.2 Labor

Sub - Total for A.2 - As Evaluated


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

Sub - Total for B.1 - As Submitted


B.2 Equipment

Sub - Total for B.2 - As Submitted


C.1 Total (A.1 + B.1) - As Submitted 0.00
C.2 Total (A.2 + B.2) - As Evaluated 0.00
D.1 Output per hour - As Submitted = 1 mo.
D.2 Output per hour - As Evaluated = 1 mo.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 0.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 0.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. Developing pc. 1.00 15.00 15.00

Sub - Total for F.1 - As Submitted 15.00


F.2 Materials

a. Developing pc. 1.00 15.00 15.00

Sub - Total for F.2 - As Evaluated 15.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 15.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 15.00
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 1.50
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 1.50
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 0.83
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 0.83
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 17.33
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 17.33

Prepared by: Checked/Reviewed by:

JUMEL B. REYES CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : B.5 Project Billboard / Signboard


Unit of Measurement : ea.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

Designation No. of Person No. of Hour/s Hourly Rate Amount


A.1 Labor

a. Construction Foreman 1 4.00 101.45 405.80


b. Skilled Laborers 1 4.00 73.29 293.16
c. Laborers 2 4.00 56.46 451.68

Sub - Total for A.1 - As Submitted 1,150.64


A.2 Labor

a. Construction Foreman 1 4.00 101.45 405.80


b. Skilled Laborers 1 4.00 73.29 293.16
c. Laborers 2 4.00 56.46 451.68

Sub - Total for A.2 - As Evaluated 1,150.64


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

Sub - Total for B.1 - As Submitted


B.2 Equipment

Sub - Total for B.2 - As Submitted


C.1 Total (A.1 + B.1) - As Submitted 1,150.64
C.2 Total (A.2 + B.2) - As Evaluated 1,150.64
D.1 Output per hour - As Submitted = 1 ea.
D.2 Output per hour - As Evaluated = 1 ea.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,150.64
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 1,150.64
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. 1/2 x 4 x 8' marine plywood pc. 1.00 900.00 900.00


b. Good Lumber bd.ft. 41.00 60.00 2,460.00
c. Project Sign (Tarpaulin) sq.ft. 32.00 25.00 800.00
d. Assorted Common Nails kgs. 1 80 80.00

Sub - Total for F.1 - As Submitted 4,240.00


F.2 Materials

a. 1/2 x 4 x 8' marine plywood pc. 1.00 900.00 900.00


b. Good Lumber bd.ft. 41.00 60.00 2,460.00
c. Project Sign (Tarpaulin) sq.ft. 32.00 25.00 800.00
d. Assorted Common Nails kgs. 1.00 80.00 80.00

Sub - Total for F.2 - As Evaluated 4,240.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 5,390.64
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 5,390.64
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 808.60
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 808.60
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 539.06
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 539.06
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 336.92
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 336.92
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 7,075.22
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 7,075.22

Prepared by: Checked/Reviewed by:

JUMEL B. REYES CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : B.7(2) Occupational Safety and Health Program


Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
DURATION: 120
a. Safety Officer (Full Time) 1 960.00 62.50 60,000.00
b. Health Personnel (Full Time First Aider) 1 960.00 35.00 33,600.00
c. Sanitation Aide 2 960.00 35.00 67,200.00

Sub - Total for A.1 - As Submitted 160,800.00


A.2 Labor

a. Safety Officer (Full Time) 1 960.00 62.50 60,000.00


b. Health Personnel (Full Time First Aider) 1 960.00 35.00 33,600.00
c. Sanitation Aide 2 960.00 35.00 67,200.00

Sub - Total for A.2 - As Evaluated 160,800.00


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

a. Portable Mask-Based Sanitation Tent 1 960 9.79 9,398.40


b. Thermal Scanner (w/ rechargable battery) 1 960 1.03 988.80
c. Power Sprayer w/ Complete Accessories 1 960 3.47 3,331.20

Sub - Total for B.1 - As Submitted 13,718.40


B.2 Equipment

a. Portable Mask-Based Sanitation Tent 1 960 9.79 9,398.40


b. Thermal Scanner (w/ rechargable battery) 1 960 1.03 988.80
c. Power Sprayer w/ Complete Accessories 1 960 3.47 3,331.20

Sub - Total for B.2 - As Submitted 13,718.40


C.1 Total (A.1 + B.1) - As Submitted 174,518.40
C.2 Total (A.2 + B.2) - As Evaluated 174,518.40
D.1 Output per hour - As Submitted = 1 l.s.
D.2 Output per hour - As Evaluated = 1 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 174,518.40
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 174,518.40
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
Personal Protective Equipment (PPE)
a. Safety Helmet m-day 73.82 0.34 25.28
b. Working Gloves m-day 73.82 7.67 565.95
c. Safety Shoes m-day 73.82 4.11 303.37
d. Safety Vest m-day 73.82 2.22 164.04
e. Face Mask (Surgical/Cloth) m-day 73.82 10.00 738.20
f. Rubber Boots m-day 55.76 1.39 77.30
g. Eye Googles m-day 73.82 6.00 442.92

Antiseptics and Disinfectant


h. Sanitizing Solution lit 53.37 100.00 5,336.55
i. Ethyl Alcohol lit 11.76 185.00 2,175.32
j. Disinfectant Spray can 5.88 1,000.00 5,879.25
k. Liquid hand Soap lit 11.76 200.00 2,351.70
l. Miscellaneous (Medicine) lot 1.00 2476.48 2,476.48

Sub - Total for F.1 - As Submitted 20,536.37


F.2 Materials
Personal Protective Equipment (PPE)
a. Safety Helmet m-day 73.82 0.34 25.28
b. Working Gloves m-day 73.82 7.67 565.95
c. Safety Shoes m-day 73.82 4.11 303.37
d. Safety Vest m-day 73.82 2.22 164.04
e. Face Mask (Surgical/Cloth) m-day 73.82 10.00 738.20
f. Rubber Boots m-day 55.76 1.39 77.30
g. Eye Googles m-day 73.82 6.00 442.92

Antiseptics and Disinfectant


h. Sanitizing Solution lit 53.37 100.00 5,336.55
i. Ethyl Alcohol lit 11.76 185.00 2,175.32
j. Disinfectant Spray can 5.88 1,000.00 5,879.25
k. Liquid hand Soap lit 11.76 200.00 2,351.70
l. Miscellaneous (Medicine) lot 1.00 2,476.48 2,476.48

Sub - Total for F.2 - As Evaluated 20,536.37


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 195,054.77
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 195,054.77
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 19,505.48
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 19,505.48
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 10,728.01
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 10,728.01
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 225,288.26
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 225,288.26

Prepared by: Checked/Reviewed by:

JUMEL B. REYES CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
NO. OF
OUTPUT SAFETY SAFETY SAFETY WORKING RAIN FACE BODY RUBBER EYE FACE TOTAL
ITEM NO./DESCRPTION QUANTITY WORKERS PERSONNE DAYS MAN-DAYS EAR MUFF LANYARD
PER HOUR HELMET SHOES VEST GLOVES COATS MASKS HARNESS BOOTS GOOGLES SHIELD COST
L
Surplus Common Excavation Foreman 1 3.83 3.83 3.83 3.83 3.83 3.83 3.83 3.83
102(2) 1,838.93 60.00 Skilled Laborer - 3.83 - - - - - - -
Unskilled Laborer 2 3.83 7.66 7.66 7.66 7.66 7.66 7.66 7.66
Embankment from roadway excavation Foreman 1 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
104(1)a (Common Soil) 12.67 50.00 Skilled Laborer - 0.03 - - - - - - -
Unskilled Laborer 2 0.03 0.06 0.06 0.06 0.06 0.06 0.06 0.06
Subgrade Preparation (Common Foreman 1 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95
105(1)a Material) 2,291.40 300.00 Skilled Laborer - 0.95 - - - - - - -
Unskilled Laborer 2 0.95 1.90 1.90 1.90 1.90 1.90 1.90 1.90
Aggregate Subbase Course Foreman 1 1.21 1.21 1.21 1.21 1.21 1.21 1.21 1.21
200(1) 482.40 50.00 Skilled Laborer - 1.21 - - - - - - -
Unskilled Laborer 2 1.21 2.42 2.42 2.42 2.42 2.42 2.42 2.42
Portland Cement Concrete Pavement Foreman 1 3.28 3.28 3.28 3.28 3.28 3.28 3.28 3.28 3.28
311(1)c1 (Unreinforced) - 0.23 m thick, 14 days 1,839.16 70.00 Skilled Laborer 4 3.28 13.12 13.12 13.12 13.12 13.12 13.12 13.12 13.12
Unskilled Laborer 12 3.28 39.36 39.36 39.36 39.36 39.36 39.36 39.36 39.36
A. TOTAL PERSONNEL/MAN-DAYS 29 73.82 73.82 73.82 73.82 73.82 - 73.82 - - - 55.76 73.82 -
B. SERVICE LIFE, DAYS 730.00 365.00 180.00 3.00 730.00 0.50 730.00 730.00 730.00 365.00 50.00 60.00
C. PURCHASE COST, PPh 250.00 1,500.00 400.00 23.00 245.00 5.00 602.60 1,263.85 1,083.30 506.00 300.00 500.00
D. UNIT COST/MAN-DAY(C/B) 0.34 4.11 2.22 7.67 0.34 10.00 0.83 1.73 1.48 1.39 6.00 8.33
E. DIRECT COST FOR PPE's (D*A(Man-days)) 25.28 303.37 164.04 565.95 - 738.20 - - - 77.30 442.92 - 1,058.65
F. SAFETY OFFICER/PRACTITIONER(PART TIME) @ P15,000.00/MONTH (AS PER D.O. 56,S2005, consider at least 4hours per week) -
G. HEALTH PERSONNEL ( FULL TIME) @ P8,400.00/MONTH (AS PER D.O. 56,s2005) -
H. TOTAL DIRECT COSTM(E+F+G) 1,058.65
I. OCM (0% of E) -
J. PROFIT (10% of H) 105.87
K. VAT (5% of (H+I+J)) 58.23
L. TOTAL COST (H+I+J+K) 1,222.75
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : B.8(2) Traffic Management


Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor

a. Construction Foreman 1 96.00 101.45 9,739.20


b. Skilled Laborers 2 96.00 73.29 14,071.68
c. Laborers 4 96.00 56.46 21,680.64

Sub - Total for A.1 - As Submitted 45,491.52


A.2 Labor

a. Construction Foreman 1 96.00 101.45 9,739.20


b. Skilled Laborers 2 96.00 73.29 14,071.68
c. Laborers 4 96.00 56.46 21,680.64

Sub - Total for A.2 - As Evaluated 45,491.52


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

Sub - Total for B.1 - As Submitted


B.2 Equipment

Sub - Total for B.2 - As Submitted


C.1 Total (A.1 + B.1) - As Submitted 45,491.52
C.2 Total (A.2 + B.2) - As Evaluated 45,491.52
D.1 Output per hour - As Submitted = 1 l.s.
D.2 Output per hour - As Evaluated = 1 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 45,491.52
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 45,491.52
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. Weather Receptacle pc. 10.00 30.00 300.00


b. Incandescent Bulb pc. 10.00 35.00 350.00
c. Electrical Wire #14 ln.m. 70.00 23.00 1,610.00
d. Bollards (G.I. Pipe 3" dia.) ea. 28.00 350.00 9,800.00
e. High Intensity Prismatic White Reflectorized Sticker cu. m. 0.72 2750.00 1,980.00
f. Misc. Items (CWN, Spray Paint, etc.) lot 1.00 4010.34 4,010.34

Rental Basis (Based on D.O. 13 Series of 2018) Unit Cost for 120 C.D.
g. Roadwork 1km Ahead ea. 1.00 1314.17 1,314.17
h. Lane Status ea. 1.00 1553.92 1,553.92
i. Road Work ea. 1.00 464.44 464.44
j. Speed Restriction ea. 1.00 567.13 567.13
k. Workmen Ahead ea. 1.00 676.72 676.72
l. Temporary Hazard Maker (Chevron) ea. 2.00 961.05 1,922.10
m. End Speed Restriction ea. 2.00 666.42 1,332.83
n. End Road Work ea. 2.00 1314.17 2,628.34

Sub - Total for F.1 - As Submitted 28,509.99


F.2 Materials

a. Weather Receptacle pc. 10.00 30.00 300.00


b. Incandescent Bulb pc. 10.00 35.00 350.00
c. Electrical Wire #14 ln.m. 70.00 23.00 1,610.00
d. Bollards (G.I. Pipe 3" dia.) ea. 28.00 350.00 9,800.00
e. High Intensity Prismatic White Reflectorized Sticker cu. m. 0.72 2,750.00 1,980.00
f. Misc. Items (CWN, Spray Paint, etc.) lot 1.00 4,010.34 4,010.34

Rental Basis (Based on D.O. 13 Series of 2018) Unit Cost for 120 C.D.
g. Roadwork 1km Ahead ea. 1.00 1,314.17 1,314.17
h. Lane Status ea. 1.00 1,553.92 1,553.92
i. Road Work ea. 1.00 464.44 464.44
j. Speed Restriction ea. 1.00 567.13 567.13
k. Workmen Ahead ea. 1.00 676.72 676.72
l. Temporary Hazard Maker (Chevron) ea. 2.00 961.05 1,922.10
m. End Speed Restriction ea. 2.00 666.42 1,332.83
n. End Road Work ea. 2.00 1,314.17 2,628.34

Sub - Total for F.2 - As Evaluated 28,509.99


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 74,001.51
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 74,001.51
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 7,400.15
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 7,400.15
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 4,070.08
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 4,070.08
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 85,471.74
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 85,471.74

Prepared by: Checked/Reviewed by:

JUMEL B. REYES CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
DETAILED CALCULATIONS ON COST OF TRAFFIC MANAGEMENT
Materials (Rental Basis Based on DO13) Price For 3 years span Unit Cost per day Calendar Days
Roadwork 1 km Ahead 11,991.80 10.95 120.00
Lane Status 14,179.56 12.95 120.00
Road Work 4,238.04 3.87 120.00
Speed Restriction 5,175.04 4.73 120.00
Workmen Ahead 6,175.04 5.64 120.00
Temporary Hazard Maker (Chervon) 8,769.56 8.01 120.00
End Speed Restriction 6,081.04 5.55 120.00
End RoadWork 11,991.80 10.95 120.00
NAGEMENT
Total Unit Cost
1,314.17
1,553.92
464.44
567.13
676.72
961.05
666.42
1,314.17
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : B.9 Mobilization / Demobilization


Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor

Sub - Total for A.1 - As Submitted


A.2 Labor

Sub - Total for A.2 - As Evaluated


Name and Capacity No of Units No. of Trips Hourly Rate Amount
B.1 Equipment

Low Bed Trailer 34,276.07


For Transporting by Low Bed Trailer:
Backhoe, Road Roller, Payloader, Grader
Note: Use 1% of Civil Works

Sub - Total for B.1 - As Submitted 34,276.07


B.2 Equipment

Low Bed Trailer 34,276.07


For Transporting by Low Bed Trailer:
Backhoe, Road Roller, Payloader, Grader
Note: Use 1% of Civil Works

Sub - Total for B.2 - As Submitted 34,276.07


C.1 Total (A.1 + B.1) - As Submitted 34,276.07
C.2 Total (A.2 + B.2) - As Evaluated 34,276.07
D.1 Output per hour - As Submitted = 1 l.s.
D.2 Output per hour - As Evaluated = 1 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 34,276.07
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 34,276.07
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

Sub - Total for F.1 - As Submitted


F.2 Materials

Sub - Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 34,276.07
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 34,276.07
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 0% of G.1 0.00
I.2 Contractor's Profit (CP) - As Evaluated 0% of G.2 0.00
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1,713.80
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 1,713.80
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 35,989.87
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 35,989.87

Prepared by: Checked/Reviewed by:

JUMEL B. REYES CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : 101(1) Removal of Structures and Obstructions


Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor

a. Construction Foreman 1 16.00 101.45 1,623.20


b. Skilled Laborers 1 16.00 73.29 1,172.64
c. Laborers 2 16.00 56.46 1,806.72

Sub - Total for A.1 - As Submitted 4,602.56


A.2 Labor

a. Construction Foreman 1 16.00 101.45 1,623.20


b. Skilled Laborers 1 16.00 73.29 1,172.64
c. Laborers 2 16.00 56.46 1,806.72

Sub - Total for A.2 - As Evaluated 4,602.56


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

a. Backhoe (0.80 cu.m.) 1 10.00 1,537.00 15,370.00


b. Dump Truck (10 cu.m.) 1 10.00 1,420.00 14,200.00
Minor Tools (10% of Labor Cost) 460.26 460.26

Sub - Total for B.1 - As Submitted 30,030.26


B.2 Equipment

a. Backhoe (0.80 cu.m.) 1 10.00 1,537.00 15,370.00


b. Dump Truck (10 cu.m.) 1 10.00 1,420.00 14,200.00
Minor Tools (10% of Labor Cost) 460.26 460.26

Sub - Total for B.2 - As Submitted 30,030.26


C.1 Total (A.1 + B.1) - As Submitted 34,632.82
C.2 Total (A.2 + B.2) - As Evaluated 34,632.82
D.1 Output per hour - As Submitted = 1 l.s.
D.2 Output per hour - As Evaluated = 1 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 34,632.82
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 34,632.82
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

Sub - Total for F.1 - As Submitted


F.2 Materials

Sub - Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 34,632.82
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 34,632.82
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 5,194.92
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 5,194.92
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 3,463.28
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 3,463.28
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 2,164.55
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 2,164.55
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 45,455.57
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 45,455.57

Prepared by: Checked/Reviewed by:

JUMEL B. REYES CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : 102(2) Surplus Common Excavation


Unit of Measurement : cu.m.
Output per hour - As Submitted : 60.00
Output per hour - As Evaluated : 60.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Laborers 2 1.00 56.46 112.92

Sub - Total for A.1 - As Submitted 214.37


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Laborers 2 1.00 56.46 112.92

Sub - Total for A.2 - As Evaluated 214.37


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

a. Backhoe 1 1.00 1,537.00 1,537.00


b. Payloader (1.50 cu.m.) 1 1.00 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) at disposal site 1 0.25 1,733.00 433.25
d. Dump Truck (10 cu.m.) 2 1 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 21.44
(Hauling Distance - within three (3) km.)

Sub - Total for B.1 - As Submitted 6,564.69


B.2 Equipment

a. Backhoe 1 1.00 1,537.00 1,537.00


b. Payloader (1.50 cu.m.) 1 1.00 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) at disposal site 1 0.25 1,733.00 433.25
d. Dump Truck (10 cu.m.) 2 1.00 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 21.44
(Hauling Distance - within three (3) km.)

Sub - Total for B.2 - As Submitted 6,564.69


C.1 Total (A.1 + B.1) - As Submitted 6,779.06
C.2 Total (A.2 + B.2) - As Evaluated 6,779.06
D.1 Output per hour - As Submitted = 60 cu.m.
D.2 Output per hour - As Evaluated = 60 cu.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 112.98
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 112.98
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

Sub - Total for F.1 - As Submitted


F.2 Materials

Sub - Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 112.98
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 112.98
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 16.95
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 16.95
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 11.30
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 11.30
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 7.06
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 7.06
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 148.29
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 148.29

Prepared
`1`1by: Checked/Reviewed by:

JUMEL B. REYES CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : 104(1)a Embankment from roadway excavation (Common Soil)


Unit of Measurement : cu.m.
Output per hour - As Submitted : 50.00
Output per hour - As Evaluated : 50.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor

a. Construction Foreman 1 0.83 101.45 84.20


b. Laborers 2 0.83 56.46 93.72

Labor for spreading and compaction


a. Construction Foreman 1 1 101.45 101.45
b. Laborers 2 1 56.46 112.92

Sub - Total for A.1 - As Submitted 392.30


A.2 Labor

a. Construction Foreman 1 0.83 101.45 84.20


b. Laborers 2 0.83 56.46 93.72

Labor for spreading and compaction


a. Construction Foreman 1 1.00 101.45 101.45
b. Laborers 2 1.00 56.46 112.92

Sub - Total for A.2 - As Evaluated 392.30


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

a. Backhoe 1 0.83 1,537.00 1,275.71


b. Payloader 1 0.83 1,733.00 1,438.39
c. Dumptruck 2 0.83 1,420.00 2,357.20

Equipment for spreading and compaction


a. Motorized Road Grader, G710A ( 140 HP ) 1 1.00 2,173.00 2,173.00
b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck (16000 lit.) 1 0.25 2,450.00 612.50

Sub - Total for B.1 - As Submitted 9,702.80


B.2 Equipment

a. Backhoe 1 0.83 1,537.00 1,275.71


b. Payloader 1 0.83 1,733.00 1,438.39
c. Dumptruck 2 0.83 1,420.00 2,357.20

Equipment for spreading and compaction


a. Motorized Road Grader, G710A ( 140 HP ) 1 1.00 2,173.00 2,173.00
b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck (16000 lit.) 1 0.25 2,450.00 612.50

Sub - Total for B.2 - As Submitted 9,702.80


C.1 Total (A.1 + B.1) - As Submitted 10,095.10
C.2 Total (A.2 + B.2) - As Evaluated 10,095.10
D.1 Output per hour - As Submitted = 50 cu.m.
D.2 Output per hour - As Evaluated = 50 cu.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 201.90
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 201.90
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

Sub - Total for F.1 - As Submitted


F.2 Materials

Sub - Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 201.90
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 201.90
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 30.29
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 30.29
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 20.19
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 20.19
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 12.62
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 12.62
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 265.00
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 265.00

Prepared by: Checked/Reviewed by:

JUMEL B. REYES CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : 105(1)a Subgrade Preparation (Common Material)


Unit of Measurement : sq.m.
Output per hour - As Submitted : 300.00
Output per hour - As Evaluated : 300.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Laborers 2 1.00 56.46 112.92

Sub - Total for A.1 - As Submitted 214.37


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Laborers 2 1.00 56.46 112.92

Sub - Total for A.2 - As Evaluated 214.37


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

a. Motorized Road Grader, 140 HP 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck (16,000 lit.) 1 0.25 2,450.00 612.50

Sub - Total for B.1 - As Submitted 4,631.50


B.2 Equipment

a. Motorized Road Grader, 140 HP 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck (16,000 lit.) 1 0.25 2,450.00 612.50

Sub - Total for B.2 - As Submitted 4,631.50


C.1 Total (A.1 + B.1) - As Submitted 4,845.87
C.2 Total (A.2 + B.2) - As Evaluated 4,845.87
D.1 Output per hour - As Submitted = 300 sq.m.
D.2 Output per hour - As Evaluated = 300 sq.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 16.15
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 16.15
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

Sub - Total for F.1 - As Submitted


F.2 Materials

Sub - Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 16.15
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 16.15
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 2.42
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 2.42
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 1.62
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 1.62
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1.01
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 1.01
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 21.20
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 21.20

Prepared by: Checked/Reviewed by:

JUMEL B. REYES CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : 200(1) Aggregate Subbase Course


Unit of Measurement : cu.m
Output per hour - As Submitted : 50.00
Output per hour - As Evaluated : 50.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Laborers 2 1.00 56.46 112.92

Sub - Total for A.1 - As Submitted 214.37


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Laborers 2 1.00 56.46 112.92

Sub - Total for A.2 - As Evaluated 214.37


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

a. Motorized Road Grader, G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck (16,000 lit.) 1 0.25 2,450.00 612.50

Sub - Total for B.1 - As Submitted 4,631.50


B.2 Equipment

a. Motorized Road Grader, G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck (16,000 lit.) 1 0.25 2,450.00 612.50

Sub - Total for B.2 - As Submitted 4,631.50


C.1 Total (A.1 + B.1) - As Submitted 4,845.87
C.2 Total (A.2 + B.2) - As Evaluated 4,845.87
D.1 Output per hour - As Submitted = 50 cu.m
D.2 Output per hour - As Evaluated = 50 cu.m
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 96.92
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 96.92
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. Aggregate Subbase Course cu.m. 1.15 617.26 709.85


(w/ 15% Shrinkage Factor)

Sub - Total for F.1 - As Submitted 709.85


F.2 Materials

a. Aggregate Subbase Course cu.m. 1.15 617.26 709.85


(w/ 15% Shrinkage Factor)

Sub - Total for F.2 - As Evaluated 709.85


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 806.77
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 806.77
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 121.01
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 121.01
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 80.68
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 80.68
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 50.42
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 50.42
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,058.88
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 1,058.88

Prepared by: Checked/Reviewed by:

JUMEL B. REYES CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II
LOCAL PROGRAM, Local Infrastructure Program, Local Roads and Bridges, Local Roads, Construction of Road, Barangay Talaan Pantoc,
Sariaya, Quezon
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00

Item no./Description : 311(1)c1 Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days
Unit of Measurement : sq.m.
Output per hour - As Submitted : 70.00
Output per hour - As Evaluated : 70.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor

a. Construction Foreman 1.00 1.00 101.45 101.45


b. Skilled Laborers 4.00 1.00 73.29 293.16
c. Laborers 12.00 1.00 56.46 677.52

Sub - Total for A.1 - As Submitted 1,072.13


A.2 Labor

a. Construction Foreman 1.00 1.00 101.45 101.45


b. Skilled Laborers 4.00 1.00 73.29 293.16
c. Laborers 12.00 1.00 56.46 677.52

Sub - Total for A.2 - As Evaluated 1,072.13


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase, 25 mm. 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 53.61

Sub - Total for B.1 - As Submitted 835.71


B.2 Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase, 25 mm. 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 53.61

Sub - Total for B.2 - As Submitted 835.71


C.1 Total (A.1 + B.1) - As Submitted 1,907.84
C.2 Total (A.2 + B.2) - As Evaluated 1,907.84
D.1 Output per hour - As Submitted = 70 sq.m.
D.2 Output per hour - As Evaluated = 70 sq.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 27.25
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 27.25
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. Reinforcing Steel Bar (Grade 40) kg. 0.43 37.50 16.13


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.12 44.00 5.28
d. Steel Forms, 230mm width l.m. 0.46 105.00 48.30
e. Readymix concrete (3500 psi @ 14 days concrete) cu.m. 0.23 6,050.00 1,391.50
f. Concrete Saw (diamond blade 14") pc 0.00015 8,000.00 1.20
h. Grease/Tar lit. 0.0087 112.00 0.97

Sub - Total for F.1 - As Submitted 1,471.50


F.2 Materials

a. Reinforcing Steel Bar (Grade 40) kg. 0.43 37.50 16.13


b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.12 44.00 5.28
d. Steel Forms, 230mm width l.m. 0.46 105.00 48.30
e. Readymix concrete (3500 psi @ 14 days concrete) cu.m. 0.23 6,050.00 1,391.50
f. Concrete Saw (diamond blade 14") pc 0.00015 8,000.00 1.20
h. Grease/Tar lit. 0.0087 112.00 0.97

Sub - Total for F.2 - As Evaluated 1,471.50


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,498.75
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 1,498.75
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 224.81
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 224.81
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 149.88
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 149.88
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 93.67
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 93.67
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,967.11
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 1,967.11

Prepared by: Checked/Reviewed by:

JUMEL B. REYES CHARLOTTE KAYE A. CONSTANTINO


Engineer II Engineer II

You might also like