Professional Documents
Culture Documents
TIAONG, QUEZON
BIP 2022
Republic of the Philippines
Department of Public Works and Highways
Quezon II District Engineering Office
Lucena City
EXECUTIVE SUMMARY
Project ID :
Convergence and Special Support Program: Basic Infrastructure
Project Name : Program (BIP) - Access Roads and/or Bridges from the National
Road/s leading to Major/ Strategic Public Buildings/ Facilities,
Construction of Bridge with box culvert, Brgy. San Isidro to Brgy.
San Jose, Tiaong, Quezon
Location of Project : TIAONG, QUEZON
2. Project Category : Construction of Bridge with Box Culvert
3. Source of Fund : BIP 2022
4. Action Recommended: For Approval
5. Implementing Office : DPWH Quezon II District Engineering Office
6. Reviewing Offices : DPWH Quezon II District Engineering Office
7. Appropriation : ₱ 5,000,000.00
8. ABC : ₱ 4,950,000.00
9. Project Duration : 120 C.D.
10. Mode Implementation: By Contract
PREPARED BY:
SUBMITTED BY:
Project : Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Appropriation : (a) Road 49.7 m
Major/ Strategic Public Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong, Quezon : (b) Bridge 30.3 m
Project ID : : (c) Others
Location : TIAONG, QUEZON Target Start Date :
Station Limits : SECTION I : STA. 0+000.00 - STA. 0+033.85, BRIDGE : STA. 0+33.85 - STA. 0+064.15, SECTION II : STA. 0+064.15 - STA. 0+080.00 Total Project Duration : 120 C.D.
Appropriation : 5,000,000.00 No. of Pre-determined : 90 C.D.
Source of Fund : BIP 2022 Unworkable Days : 30 C.D.
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part A: Facilities for the Engineer 5.06% 193,660.92 5.06% 193,660.92
B: Other General Requirements 13.09% 501,258.22 13.09% 501,258.22
C: Earthworks 23.30% 892,445.04 23.30% 892,445.04
D: Subbase and Base Course 1.21% 46,490.05 1.21% 46,490.05
E: Surface Courses 9.72% 372,700.09 9.72% 372,700.09
F: Bridge Construction (PLS. SEE FORM POW-2015-01C-00) 39.96% 1,530,197.48 39.96% 1,530,197.48
G: Drainage and Slope Protection Structures 7.65% 292,912.39 7.65% 292,912.39
H: Miscellaneous Structures - - - -
I: Provisional Sum - - - -
J: Daywork - - - -
- - -
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
DAN LESTER T. LAGSIT FAUSTINO MARK ANTHONY S. DE LA CRUZ CHARLOTTE KAYE A. CONSTANTINO WILFREDO L. RACELIS DEL ROASARIO C. NACA
Engineer II Chief, Planning & Design Section Engineer II Assistant District Engineer Officer - In - Charge
Planning & Design Section Planning & Design Section Office of the District Engineer
DATE: Feb. 08, 2022
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong, Quezon
TIAONG, QUEZON
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST
TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED
A.1.1(3) Construction of Field Office for the Engineer 1.00 1.00 l.s. 105,633.56 105,633.56 105,633.56 105,633.56 138,644.05 138,644.05 2.76% 2.76%
A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the Engineer 4.00 4.00 mo. 86,227.36 86,227.36 21,556.84 21,556.84 24,898.15 24,898.15 2.25% 2.25%
A.1.4(1) Provision of Progress Photographs 120.00 120.00 each 1,800.00 1,800.00 15.00 15.00 17.33 17.33 0.05% 0.05%
B.5 Project Billboard / Signboard 2.00 2.00 ea. 10,439.60 10,439.60 5,219.80 5,219.80 6,850.99 6,850.99 0.27% 0.27%
B.7(2) Occupational Safety and Health Program 1.00 1.00 ls 164,919.71 164,919.71 164,919.71 164,919.71 190,482.26 190,482.26 4.31% 4.31%
B.8(2) Traffic Management 1.00 1.00 l.s 169,016.48 169,016.48 169,016.48 169,016.48 195,214.04 195,214.04 4.41% 4.41%
B.9 Mobilization / Demobilization 1.00 1.00 l.s. 38,000.00 38,000.00 38,000.00 38,000.00 39,900.00 39,900.00 0.99% 0.99%
B.17 Temporary Diversion of Waterway 1.00 1.00 l.s. 118,882.43 118,882.43 118,882.43 118,882.43 156,033.19 156,033.19 3.10% 3.10%
PART C EARTHWORKS
101(1) Removal of Structures and Obstructions 1.00 1.00 l.s. 62,075.57 62,075.57 62,075.57 62,075.57 81,474.18 81,474.18 1.62% 1.62%
104(1)b Embankment from Borrow 2,014.38 2,014.38 cu.m. 825,099.75 825,099.75 409.60 409.60 537.61 537.61 21.54% 21.54%
105(1)a Subgrade Preparation (Common Material) 326.00 326.00 sq.m. 5,269.72 5,269.72 16.16 16.16 21.22 21.22 0.14% 0.14%
200(1) Aggregate Subbase Course 79.20 79.20 cu.m 46,490.05 46,490.05 587.00 587.00 770.43 770.43 1.21% 1.21%
311(1)c1 Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days 250.76 250.76 cu.m 372,700.09 372,700.09 1,486.28 1,486.28 1,950.75 1,950.75 9.73% 9.73%
404(1)a Reinforcing Steel (Deformed, Grade 40) 4,465.61 4,465.61 kg 266,501.28 266,501.28 59.68 59.68 78.33 78.33 6.96% 6.96%
404(1)b Reinforcing Steel (Deformed, Grade 60) 3,982.95 3,982.95 kg 241,878.74 241,878.74 60.73 60.73 79.71 79.71 6.32% 6.32%
405(1)a3 Structural Concrete (20.68 MPa, Class A, 28 days) 98.43 98.43 cu.m 882,958.37 882,958.37 8,970.87 8,970.87 11,774.27 11,774.27 23.06% 23.06%
407(8) Lean Concrete, Class B (16.5 Mpa) 10.87 10.87 cu.m 138,859.09 138,859.09 12,772.76 12,772.76 16,764.25 16,764.25 3.63% 3.63%
505(2)a Grouted Riprap (Class A) 106.34 106.34 cu.m 292,912.39 292,912.39 2,754.55 2,754.55 3,615.35 3,615.35 7.65% 7.65%
TOTAL OF PART H - -
PART J DAYWORK
TOTAL OF PART J
DAN LESTER T. LAGSIT FAUSTINO MARK ANTHONY S. DE LA CRUZ CHARLOTTE KAYE A. CONSTANTINO
Engineer II Chief, Planning & Design Section Engineer II
Planning & Design Section Planning & Design Section
DATE: Feb. 08, 2022
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities,
Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong, Quezon
TIAONG, QUEZON
DAN LESTER T. LAGSIT FAUSTINO MARK ANTHONY S. DE LA CRUZ CHARLOTTE KAYE A. CONSTANTINO
Engineer II Chief, Planning & Design Section Engineer II
Planning & Design Section Planning & Design Section
DATE: Feb. 08, 2022
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities,
Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong, Quezon
TIAONG, QUEZON
PART J DAYWORK
AS SUBMITTED - - - - -
TOTAL OF PART J
AS EVALUATED
AS SUBMITTED 3,829,664.19 884,621.52 235,714.29 1,120,335.81 4,950,000.00
GRAND TOTAL
AS EVALUATED 3,829,664.19 884,621.52 235,714.29 1,120,335.81 4,950,000.00
DAN LESTER T. LAGSIT FAUSTINO MARK ANTHONY S. DE LA CRUZ CHARLOTTE KAYE A. CONSTANTINO
Engineer II Chief, Planning & Design Section Engineer II
Planning & Design Section Planning & Design Section
DATE: Feb. 08, 2022
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02-00
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public
Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong, Quezon
TIAONG, QUEZON
DAN LESTER T. LAGSIT FAUSTINO MARK ANTHONY S. DE LA CRUZ CHARLOTTE KAYE A. CONSTANTINO WILFREDO L. RACELIS DEL ROASARIO C. NACA
Engineer II Chief, Planning & Design Section Engineer II Assistant District Engineer Officer - In - Charge
Planning & Design Section Office of the District Engineer
DATE: Feb. 08, 2022
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to
Major/ Strategic Public Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong, Quezon
TIAONG, QUEZON
BACK-UP COMPUTATIONS
A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the Engineer
PART C EARTHWORKS
101(1) Removal of Structures and Obstructions
RCBC RSB
DESCRIPTION Size (mm) BAR MARK Ø GRADE SP BAR SHAPE A B C LENGTH UNIT WEIGHTNUMBER OF BARS' TOTAL WEIGHT UNIT
RCBC BAR 1 20 60 300 A 1000 3500 1000 5.500 2.466 8.00 726.95 kg.
NO. OF BARREL 2 BAR 2 16 60 200 A 200 3500 200 3.900 1.578 10.00 412.32 kg.
HEIGHT 3000 BAR 3 20 60 300 B 1000 1000 0 2.000 2.466 16.00 528.70 kg.
SPAN 3000 BAR 4 20 60 300 B 200 6800 200 7.200 2.466 8.00 951.67 kg.
Thk 300 BAR 5 20 60 300 C 0 1800 0 1.800 2.466 16.00 475.90 kg.
CC 50 BAR 6 25 60 170 A 0 1800 0 1.800 3.853 12.00 557.57 kg.
LENGTH 6700 BAR 7 16 60 300 D 200 3500 200 3.900 1.578 8.00 329.84 kg.
BAR 8 12 40 200 D 0 1800 0 1.800 0.888 20.00 214.20 kg.
BAR 9 12 40 250 D 0 1000 0 1.000 0.888 184.00 1094.71 kg.
WINGWALL W1 12 40 300 A 0 7050 0 7.050 0.888 14.00 350.60 kg.
NO. OF WING WALL 4 W2 12 40 250 B 250 600 1950 5.050 0.888 29.00 520.20 kg.
HEIGHT 1 3300 150 1950 150
HEIGHT 2 600 W3 12 40 250 C 150 1000 150 1.300 0.888 29.00 133.92 kg.
SPAN 7100 W4 12 40 300 A 0.00 7050 0 7.050 0.888 4.00 100.16 kg.
APRON A1 12 40 300 A 0 3000 100 3.100 0.888 56.00 308.32 kg.
NO. OF APRON 2 A2 12 40 300 A 0 11900 0 11.900 0.888 20.00 422.68 kg.
BREADTH 6000 H1 12 40 200 A 600 900 100 2.600 0.888 170.00 785.00 kg.
WIDTH 1 6900 900 100
WIDTH 2 16900
DESCRIPTION Size (mm) LENGTH Ø GRADE SP TYPE B D HOOK LENGTH UNIT WEIGHTNUMBER OF BARS' TOTAL WEIGHT UNIT
CRIB RIPRAP 6900 16 40 MAIN 300 400 80 6.900 1.578 16.00 174.21 kg.
1800 16 40 MIAN 300 400 80 1.800 1.578 16.00 45.45 kg.
6900 12 40 200 TIES 300 400 60 4.140 0.888 70.00 257.34 kg.
1500 12 40 200 TIES 300 400 60 4.140 0.888 16.00 58.82 kg.
RCBC CONCRETE
DESCRIPTION OUTSIDE AREA INSIDE AREA CONCRETE AREA LENGTH TOTAL VOLUME UNIT
RCBC 24.84 18.00 7 6700.00 45.83 cu.m.
DESCRIPTION LOC W1 W2 HEIGHT SPAN TOTAL VOLUME UNIT
WINGWALL FOOTING 1200 800 400 7100 11.36 cu.m.
WINGWALL WING WALL 400 250 3300 7100 30.46 cu.m.
ARPON SLAB 6900 3300 150 6000 4.59 cu.m.
APRON HEEL 1000 1000 200 16900 3.38 cu.m.
DESCRIPTION NO OF BLOCKS WIDTH HEIGHT SPAN TOTAL VOLUME UNIT
PARAPET L/R 0 200 500 500 0.00 cu.m.
DESCRIPTION NO OF BLOCKS WIDTH HEIGHT SPAN TOTAL VOLUME UNIT
CRIB RIPRAP L/R 2 300 400 6900 1.66 cu.m.
CRIB RIPRAP L/R 6 300 400 1600 1.15 cu.m.
SUB-TOTAL VOLUME 98.43 cu.m.
RCBC CONCRETE
DESCRIPTION WIDTH LENGTH THINKNESS QUANTITY TOTAL VOLUME UNIT
RCBC 6900.00 6700.00 50.00 1.00 2.31 cu.m.
DESCRIPTION WIDTH LENGTH THINKNESS QUANTITY TOTAL VOLUME UNIT
WINGWALL FOUNDATION 1000.00 7100.00 50.00 4.00 1.42 cu.m.
APRON 11900.00 6000.00 50.00 2.00 7.14 cu.m.
SUB-TOTAL LEAN 10.87 cu.m.
Project : Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s
leading to Major/ Strategic Public Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong,
Location : TIAONG, QUEZON
Item No. : 104 - 1 & 102
Description : Roadway Excavation & Embankment (from borrow)
PROJECT : Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public
Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong, Quezon
LOCATION : TIAONG, QUEZON
ITEM NO. : 105(1)a, 200(1), 311(1)c1
Maps showing the source of material to the point of reference (project site) L=19.7 km
Maps showing DPWH Quezon II DEO to the point of reference (project site) L=10.4 km
Prepared by:
PROJECT : Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads
and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities,
Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong, Quezon
AMOUNT: P 5,000,000.00
Calendar Days = [(given ref amount x ref duration per km. of road)/estimated amount per km. of road] +
[ duration of mob./demob. On the given ref amount]
CD = 90.00 days
SAY 90 days
Prepared by:
SUNDAYS 4 4 4 4 16
NATIONAL HOLIDAYS 3 1 0 1 5
RAINY DAYS 0 1 3 5 9
TOTAL NON-WORKING
7 6 7 10 30
DAYS
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
Structural Concrete:
Volume:
L W H Q
Footing 0.6 0.6 0.2 6 0.432 Cement 43 bags
Column 0.2 0.2 1.6 6 0.384 Sand 2 cu.m.
WF 0.35 10.4 0.15 1 0.546 Gravel 4 cu.m.
Slab 6 3 0.1 1 1.8
CHB Mortar Cement 10.00 Sand 0.57
CHB Plaster Cement 4.00 Sand 0.21
3.162
Reinforcing Steel Bar (Grade 40):
w/m
Footing x 10 mmØ 0.6165 0.6 4 6 8.88
Footing y 10 mmØ 0.6165 0.6 4 6 8.88
Column 12 mmØ 0.8878 2 4 6 42.62
Stirrups 10 mmØ 0.6165 0.58 9 6 19.31
WF 10 mmØ 0.6165 10.4 1 1 6.41
Slab 10 mmØ 0.6165 10 3 1 18.50
10 mmØ 0.6165 5 6 1 18.50
Hor. Vert.
For CHB 10 mmØ 0.6165 27.95 20.8 30.06
153.14 kgs.
100mm Thk. Concrete Hollow Blocks
Ht. L
Area: 1.25 10.4 13 sq.m.
163 pcs.
Good Lumber
L cu.in. bd.ft.
2x2 2 2 3996.06 144 111.00
2x3 2 3 2267.72 144 94.49
2x4 2 4 1381.89 144 76.77
2x5 2 5 1161.42 144 80.65
3x5 3 5 472.44 144 49.21
4x4 4 4 425.20 144 47.24
459.37 bd.ft.
1 x 20 watts FLF
Quantity: 3 set
Item No./Description : A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the Engineer
Unit of Measurement : mo.
Output per Hour - As Evaluated : 1.00
Output per Hour - As Submitted : 1.00
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
101(1) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.039 0.039
1.00 1.00
Removal of Structures and Obstructions Unskilled Laborer 2 0.13 0.26 0.26 0.26 0.26 0.26 0.078 0.078 0.13
104(1)b Construction Foreman 1 5.04 5.04 5.04 5.04 5.04 1.512 1.512
2014.38 50.00
Embankment from Borrow Unskilled Laborer 2 5.04 10.08 10.08 10.08 10.08 10.08 3.024 3.024 5.04
105(1)a Construction Foreman 1 0.14 0.14 0.14 0.14 0.14 0.042 0.042
326.00 300.00
Subgrade Preparation (Common Material) Unskilled Laborer 2 0.14 0.28 0.28 0.28 0.28 0.28 0.084 0.084 0.14
200(1) Construction Foreman 1 0.2 0.2 0.2 0.2 0.2 0.06 0.06
79.20 50.00
Aggregate Subbase Course Unskilled Laborer 2 0.2 0.4 0.4 0.4 0.4 0.4 0.12 0.12 0.2
311(1)c1 Construction Foreman 1 0.45 0.45 0.45 0.45 0.45 0.135 0.135
Portland Cement Concrete Pavement 250.76 70.00 Skilled Laborer 4 0.45 1.8 1.8 1.8 1.8 0.54 0.54 0.45
(Unreinforced) - 0.23 m thick, 14 days Unskilled Laborer 12 0.45 5.4 5.4 5.4 5.4 5.4 1.62 1.62 0.45
404(1)a Construction Foreman 1 3.1 3.1 3.1 3.1 3.1 0.93 0.93
4465.61 180.00 Skilled Laborer 2 3.1 6.2 6.2 6.2 6.2 1.86 1.86
Reinforcing Steel (Deformed, Grade 40)
Unskilled Laborer 8 3.1 24.8 24.8 24.8 24.8 24.8 7.44 7.44
404(1)b Construction Foreman 1 2.77 2.77 2.77 2.77 2.77 0.831 0.831
3982.95 180.00 Skilled Laborer 2 2.77 5.54 5.54 5.54 5.54 1.662 1.662
Reinforcing Steel (Deformed, Grade 60)
Unskilled Laborer 8 2.77 22.16 22.16 22.16 22.16 22.16 6.648 6.648
405(1)a3 Construction Foreman 1 1.23 1.23 1.23 1.23 1.23 0.369 0.369
Skilled Laborer 4 1.23 4.92 4.92 4.92 4.92 1.476 1.476 1.23
Unskilled Laborer 8 1.23 9.84 9.84 9.84 9.84 9.84 2.952 2.952 1.23
Structural Concrete (20.68 MPa, Class A, 28 98.43 10.00
Construction Foreman 1 1.23 1.23 1.23 1.23 1.23 0.369 0.369
days)
Skilled Laborer 4 1.23 4.92 4.92 4.92 4.92 1.476 1.476 1.23
Unskilled Laborer 8 1.23 9.84 9.84 9.84 9.84 9.84 2.952 2.952 1.23
407(8) Construction Foreman 1 7.15 7.15 7.15 7.15 7.15 2.145 2.145
10.87 0.19 Skilled Laborer 2 7.15 14.3 14.3 14.3 14.3 4.29 4.29 7.15
Lean Concrete, Class B (16.5 Mpa)
Unskilled Laborer 6 7.15 42.9 42.9 42.9 42.9 42.9 12.87 12.87 7.15
505(2) Construction Foreman 1 #N/A #N/A #N/A #N/A #N/A #N/A #N/A
#N/A #REF! Skilled Laborer 4 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
#REF!
Unskilled Laborer 8 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
A. TOTAL PERSONNEL/MAN-DAYS 17 #N/A #N/A #N/A #N/A #N/A #N/A 0 0 0 #N/A #N/A
A. TOTAL PERSONNEL/MAN-DAYS 29 24.18 24.18 22.38 24.18 18.22 7.254 0 7.254 6.41
B. SERVICE LIFE, DAYS 730 365 180 3 730 1 0.5 730 730 365 60
C. PURCHASE COST, PPh 250.00 1,500.00 400.00 23.00 245.00 602.60 500.00 1,263.85 5.00 506.00 300.00
D. UNIT COST/MAN-DAY(C/B) 0.34 4.11 2.22 7.67 0.34 5 10 1.39
E. DIRECT COST FOR PPE's (D*A(Man-days)) 8.22 91.98 53.68 139.75 2.43 - - - 72.54 8.91 - 377.51
F. SAFETY OFFICER/PRACTITIONER(PART TIME) @ P15,000.00/MONTH (AS PER D.O. 56,S2005, consider at least 4hours per week) -
G. HEALTH PERSONNEL ( FULL TIME) @ P8,400.00/MONTH (AS PER D.O. 56,s2005) -
H. TOTAL DIRECT COSTM(E+F+G) 377.51
I. OCM (0% of E) -
J. PROFIT (8% of H) 30.20
K. VAT (5% of (H+I+J)) 20.39
L. TOTAL COST (H+I+J+K) 428.10
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading
to Major/ Strategic Public Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong, Quezon
TIAONG, QUEZON
DETAILED UNIT PRICE ANALYSIS (DUPA)
Rental Basis (Based on D.O 13 series of 2018) Unit Cost for 120 C.D.
Roadword Ahead (T1-1) each 2 11,991.80 23,983.60
Detour Ahead (T1-6) each 4 7,165.04 28,660.16
Detour (Left or Right) (T5-1) each 8 5,251.04 42,008.32
Detour Marker (T5-6 each 6 3,565.04 21,390.24
Local Traffic Only (G9-40-2 each 1 6,175.04 6,175.04
Road Closed (T2-4) each 2 6,074.56 12,149.12
End Detour (T2-23) each 2 7,165.04 14,330.08
Rental Basis (Based on D.O 13 series of 2018) Unit Cost for 120 C.D.
Roadword Ahead (T1-1) each 2.00 11,991.80 23,983.60
Detour Ahead (T1-6) each 4.00 7,165.04 28,660.16
Detour (Left or Right) (T5-1) each 8.00 5,251.04 42,008.32
Detour Marker (T5-6 each 6.00 3,565.04 21,390.24
Local Traffic Only (G9-40-2 each 1.00 6,175.04 6,175.04
Road Closed (T2-4) each 2.00 6,074.56 12,149.12
End Detour (T2-23) each 2.00 7,165.04 14,330.08
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
a Aggregate Subbase Course Material w/ 15% shrinkage factor cu.m 1.15 426.09 490.01
a Aggregate Subbase Course Material w/ 15% shrinkage factor cu.m 1.15 426.09 490.01
Item No./Description : 311(1)c1 Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days
Unit of Measurement : cu.m
Output per Hour - As Evaluated : 70.00
Output per Hour - As Submitted : 70.00
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
a Deformed Reinforcing Steel (G40) (w/ 5% wastage) kg. 1.050 49.00 51.45
b #16 Galvanized Iron Wire 2% of rsb kg. 0.021 80.00 1.68
a Deformed Reinforcing Steel (G40) (w/ 5% wastage) kg. 1.050 49.00 51.45
b #16 Galvanized Iron Wire 2% of rsb kg. 0.021 80.00 1.68
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
a Deformed Reinforcing Steel (G60) (w/ 5% wastage) kg. 1.050 50.00 52.50
b #16 Galvanized Iron Wire 2% of rsb kg. 0.021 80.00 1.68
a Deformed Reinforcing Steel (G60) (w/ 5% wastage) kg. 1.050 50.00 52.50
b #16 Galvanized Iron Wire 2% of rsb kg. 0.021 80.00 1.68
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
a Ready Mix Concrete, Lean Concrete, 28days cu.m 1.05 5,450.00 5,722.50
a Ready Mix Concrete, Lean Concrete, 28days cu.m 1.05 5450.00 5,722.50
No. of
Designation No. of Hr/s Hourly Rate Amount (PhP)
Person/s
A1. Labor
AGGREGATES
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s
leading to Major/ Strategic Public Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong,
Quezon
TIAONG, QUEZON
AGGREGATES
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s
leading to Major/ Strategic Public Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong,
Quezon
TIAONG, QUEZON
AGGREGATES
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s
leading to Major/ Strategic Public Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong,
Quezon
TIAONG, QUEZON
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s
leading to Major/ Strategic Public Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong,
Quezon
TIAONG, QUEZON
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s
leading to Major/ Strategic Public Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong,
Quezon
TIAONG, QUEZON
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s
leading to Major/ Strategic Public Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong,
Quezon
TIAONG, QUEZON
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s
leading to Major/ Strategic Public Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong,
Quezon
TIAONG, QUEZON
Convergence and Special Support Program: Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s
leading to Major/ Strategic Public Buildings/ Facilities, Construction of Bridge with box culvert, Brgy. San Isidro to Brgy. San Jose, Tiaong,
Quezon
TIAONG, QUEZON