Professional Documents
Culture Documents
(LIP 2021)
Republic of the Philippines
Department of Public Works and Highways
Quezon II District Engineering Office
Lucena City
EXECUTIVE SUMMARY
Project ID :
PREPARED BY:
SUBMITTED BY:
Project : LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/ Appropriation : P 5,000,000.00
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon Source of Fund : GAA 2021 ( LIP )
Candelaria, Quezon
Project ID : Target Start Date :
Location : Candelaria, Quezon Total Project Duration : 150 CD
Project Description : Multi Purpose Building
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 2.30% 87,825.51 2.30% 87,825.51
Part II Other General Requirements 8.70% 333,031.17 8.70% 333,031.17
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
Part A Earthworks 5.44% 208,465.33 5.44% 208,465.33
Part B Plain and Reinforced Concrete Works (PLS. SEE FORM POW-2015-01C-00) 29.01% 1,110,036.23 29.01% 1,110,036.23
Part C Finishing and Other Civil Works 51.63% 1,975,439.43 51.63% 1,975,439.43
Part D Electrical Works 2.91% 111,254.80 2.91% 111,254.80
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
MARCO BRIAN L. BRITON FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN WILFREDO L. RACELIS MA. CHYMBELIN D. IBAL
Engineer II Chief, Planning & Design Section Chief, Construction Section Engineer III Assistant District Engineer
OIC - Office of the Assistant District Engineer OIC - Office of the District Engineer
B.3 Permits and Clearances 1.00 1.00 l.s. 21,325.00 21,325.00 21,325.00 21,325.00 0% - - 21,325.00 21,325.00 0.56% 0.56%
B.5 Project Billboard / Signboard 1.00 1.00 each 11,310.64 11,310.64 11,310.64 11,310.64 25% 2,827.66 706.92 14,845.22 14,845.22 0.30% 0.30%
B.7 (2) Occupational Safety and Health Program 1.00 1.00 l.s. 263,395.53 263,395.53 263,395.53 263,395.53 10% 26,339.55 14,486.75 304,221.84 304,221.84 6.88% 6.88%
B.9 Mobilization / Demobilization 1.00 1.00 l.s. 37,000.00 37,000.00 37,000.00 37,000.00 0% - 1,850.00 38,850.00 38,850.00 0.97% 0.97%
Project ID
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
801(1) Removal of Structures and Obstructions 1.00 1.00 l.s. 131,753.07 131,753.07 131,753.07 131,753.07 25% 32,938.27 8,234.57 172,925.90 172,925.90 3.44% 3.44%
804 (1)b Embankment ( From Borrow ) 153.00 153.00 m3 61,041.95 61,041.95 398.97 398.97 25% 99.74 24.94 523.64 523.64 1.60% 1.60%
TOTAL OF PART A 208,465.33 208,465.33 5.45% 5.45%
PART B PLAIN AND REINFORCED CONCRETE WORKS
902(1)a Reinforcing Steel (Deformed) Grade 40 2,542.88 2,542.88 kg 127,871.86 127,871.86 50.29 50.29 25% 12.57 3.14 66.00 66.00 3.34% 3.34%
902(1)b Reinforcing Steel (Deformed) Grade 60 3,825.08 3,825.08 kg 196,485.70 196,485.70 51.37 51.37 25% 12.84 3.21 67.42 67.42 5.14% 5.14%
903(2) Formworks and Falseworks 218.31 218.31 m2 169,597.99 169,597.99 776.87 776.87 25% 194.22 48.55 1,019.64 1,019.64 4.43% 7.39%
TOTAL OF PART B 1,110,036.23 1,110,036.23 29.01% 29.01%
PART C FINISHING
C.1. Masonry Works
1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm 79.51 79.51 m2 53,454.53 53,454.53 672.30 672.30 25% 168.07 42.02 882.39 882.39 1.40% 1.40%
1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm 15.00 15.00 m2 14,827.77 14,827.77 988.52 988.52 25% 247.13 61.78 1,297.43 1,297.43 0.39% 0.39%
Sub-Total C.2 68,282.30 68,282.30 1.78% 1.78%
4/55
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QTY. TOTAL MARK-UP % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT 5% VAT
As Submitted As Evaluated As Submitted As Evaluated As Submitted As Evaluated % COST As Submitted As Evaluated As Submitted As Evaluated
1021(1)a Cement Floor Finish ( Plain ) 528.75 528.75 m2 61,186.77 61,186.77 115.72 115.72 25% 28.93 7.23 151.88 151.88 1.60% 1.60%
1027(1) Cement Plaster Finish 189.02 189.02 m2 35,745.72 35,745.72 189.11 189.11 25% 47.28 11.82 248.21 248.21 0.93% 0.93%
Sub-Total C.2 96,932.49 96,932.49 2.53% 2.53%
C.3 Painting Works
1032(1)a Painting Works (Masonry/Concrete) 372.77 372.77 m
2
98,673.99 98,673.99 264.70 264.70 25% 66.18 16.54 347.43 347.43 2.58% 2.58%
1032(5) Textured Finish 526.00 526.00 m2 203,191.05 203,191.05 386.29 386.29 25% 96.57 24.14 507.01 507.01 5.31% 5.31%
1032(1)c Painting Works (Steel) 751.64 751.64 m2 199,669.03 199,669.03 265.64 265.64 25% 66.41 16.60 348.66 348.66 5.22% 5.22%
Sub-Total C.3 501,534.07 501,534.07 13.11% 13.11%
C.4 Roof Framing and Roofing Works
1014 (1) b2 Prepainted Metal Sheets (above 0.427mm) Rib Type Long Span 582.78 582.78 m2 358,046.04 358,046.04 614.38 614.38 25% 153.59 38.40 806.37 806.37 9.36% 9.36%
1047 (1) Structural Steel 1.00 1.00 l.s. 266,068.80 266,068.80 266,068.80 266,068.80 25% 66,517.20 16,629.30 349,215.30 349,215.30 6.95% 6.95%
1047(2)a Structural Steel (Trusses) 4,414.60 4,414.60 kg 344,291.21 344,291.21 77.99 77.99 25% 19.50 4.87 102.36 102.36 9.00% 9.00%
1047(2)b Structural Steel (Purlins) 3,672.57 3,672.57 kg 261,162.08 261,162.08 71.11 71.11 25% 17.78 4.44 93.33 93.33 6.83% 6.83%
1047(3)a Metal Structure Accessories (Bolts) 48.00 48.00 each 6,783.91 6,783.91 141.33 141.33 25% 35.33 8.83 185.50 185.50 0.18% 0.18%
1047(6) Metal Structure Accessories (Steel Plates) 348.90 348.90 kg 29,468.30 29,468.30 84.46 84.46 25% 21.12 5.28 110.85 110.85 0.77% 0.77%
1047(7)b Metal Structure Accessories (Sag Rods) 213.12 213.12 kg 12,647.52 12,647.52 59.34 59.34 25% 14.84 3.71 77.89 77.89 0.33% 0.33%
1047(4) Metal Structure Accessories (Cross Bracing) 347.16 347.16 kg 21,016.31 21,016.31 60.54 60.54 25% 15.13 3.78 79.46 79.46 0.55% 0.55%
1047(3)c Metal Structure Accessories (Turn Buckle) 20.00 20.00 pcs 9,206.40 9,206.40 460.32 460.32 25% 115.08 28.77 604.17 604.17 0.24% 0.24%
Sub-Total C.4 1,308,690.57 1,308,690.57 34.20% 34.20%
TOTAL OF PART C 1,975,439.43 1,975,439.43 51.63% 51.63%
PART D ELECTRICAL
1100(10) Conduits, Boxes & Fittings (Conduit Works/ConduitRough-in) 1.00 1.00 l.s. 17,951.68 17,951.68 17,951.68 17,951.68 25% 4,487.92 1,121.98 23,561.58 23,561.58 0.47% 0.47%
1101(33) Wires and Wiring Devices 1.00 1.00 l.s. 46,627.36 46,627.36 46,627.36 46,627.36 25% 11,656.84 2,914.21 61,198.41 61,198.41 1.22% 1.22%
1102 (1) Panelboard with Main & Branch Breakers 1.00 1.00 l.s. 15,644.95 15,644.95 15,644.95 15,644.95 25% 3,911.24 977.81 20,534.00 20,534.00 0.41% 0.41%
1103(1) Lighting Fixtures and Lamps 1.00 1.00 l.s. 31,030.81 31,030.81 31,030.81 31,030.81 25% 7,757.70 1,939.43 40,727.94 40,727.94 0.81% 0.81%
TOTAL OF PART D 111,254.80 111,254.80 2.91% 2.91%
TOTAL OF PART III 3,405,195.79 3,405,195.79
TOTAL OF (Project ID) 3,826,052.47 3,826,052.47
GRAND TOTAL 3,826,052.47 3,826,052.47 100.0% 100.0%
5/55
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 1.74% 1.00 l.s 55,219.67 19,315.84 - 74,535.51 74,535.51 10% 7,453.55 4,099.45 86,088.51
A.1.1 (3) Construction of Field Office for the Engineer
As Evaluated 1.74% 1.00 l.s 55,219.67 19,315.84 - 74,535.51 74,535.51 10% 7,453.55 4,099.45 86,088.51
Provision of Furnitures/Fixtures, Equipment & Appliances for As Submitted 0.26% 1.00 l.s 11,040.00 - - 11,040.00 11,040.00 10% 1,104.00 607.20 12,751.20
A.1.1(11)
the Field Office for the Engineer As Evaluated 0.26% 1.00 l.s 11,040.00 - - 11,040.00 11,040.00 10% 1,104.00 607.20 12,751.20
As Submitted 0.05% 150.00 each 2,250.00 - - 15.00 2,250.00 10% 225.00 123.75 2,598.75
A.1.4 (1) Provision of Progress Photographs
As Evaluated 0.05% 150.00 each 2,250.00 - - 15.00 2,250.00 10% 225.00 123.75 2,598.75
As Submitted 68,509.67 19,315.84 - 87,825.51 8,782.55 4,830.40 101,438.46
TOTAL OF PART I
As Evaluated 68,509.67 19,315.84 - 87,825.51 8,782.55 4,830.40 101,438.46
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.43% 1.00 l.s. 21,325.00 - - 21,325.00 21,325.00 0% - - 21,325.00
B.3 Permits and Clearances
As Evaluated 0.43% 1.00 l.s. 21,325.00 - - 21,325.00 21,325.00 0% - - 21,325.00
As Submitted 0.30% 1.00 each 10,160.00 1,150.64 - 11,310.64 11,310.64 25% 2,827.66 706.92 14,845.22
B.5 Project Billboard / Signboard
As Evaluated 0.30% 1.00 each 10,160.00 1,150.64 - 11,310.64 11,310.64 25% 2,827.66 706.92 14,845.22
As Submitted 6.15% 1.00 l.s. 87,242.58 159,000.00 17,152.95 263,395.53 263,395.53 10% 26,339.55 14,486.75 304,221.83
B.7 (2) Occupational Safety and Health Program
As Evaluated 6.15% 1.00 l.s. 87,242.58 159,000.00 17,152.95 263,395.53 263,395.53 10% 26,339.55 14,486.75 304,221.83
As Submitted 0.78% 1.00 l.s. - - 37,000.00 37,000.00 37,000.00 0% - 1,850.00 38,850.00
B.9 Mobilization / Demobilization
As Evaluated 0.78% 1.00 l.s. - - 37,000.00 37,000.00 37,000.00 0% - 1,850.00 38,850.00
As Submitted 118,727.58 160,150.64 54,152.95 333,031.17 29,167.21 17,043.67 379,242.05
TOTAL OF PART II
As Evaluated 118,727.58 160,150.64 54,152.95 333,031.17 29,167.21 17,043.67 379,242.05
(Project ID)
(Project Component ID - Description)
PART
CIVIL,
III MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 3.49% 1.00 l.s. - 9,818.70 121,934.37 131,753.07 131,753.07 25% 32,938.27 8,234.57 172,925.91
801(1) Removal of Structures and Obstructions
As Evaluated 3.49% 1.00 l.s. - 9,818.70 121,934.37 131,753.07 131,753.07 25% 32,938.27 8,234.57 172,925.91
As Submitted 0.42% 67.04 m3 - 907.82 14,762.49 233.75 15,670.31 25% 3,917.58 979.39 20,567.28
803(1)a Structure Excavation ( Common soil )
As Evaluated 0.42% 67.04 m3 - 907.82 14,762.49 233.75 15,670.31 25% 3,917.58 979.39 20,567.28
As Submitted 1.62% 153.00 m3 34,488.75 21,287.91 5,265.29 398.97 61,041.95 25% 15,260.49 3,815.12 80,117.56
804 (1)b Embankment ( From Borrow )
As Evaluated 1.62% 153.00 m3 34,488.75 21,287.91 5,265.29 398.97 61,041.95 25% 15,260.49 3,815.12 80,117.56
As Submitted 34,488.75 32,014.43 141,962.15 208,465.33 52,116.34 13,029.08 273,610.75
TOTAL OF PART A
As Evaluated 34,488.75 32,014.43 141,962.15 208,465.33 52,116.34 13,029.08 273,610.75
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 16.34% 91.80 m3 380,373.30 161,115.80 74,591.58 6,711.12 616,080.68 25% 154,020.17 38,505.04 808,605.89
900(1)c1 Structural Concrete (Class A, 28 days)
As Evaluated 16.34% 91.80 m3 380,373.30 161,115.80 74,591.58 6,711.12 616,080.68 25% 154,020.17 38,505.04 808,605.89
As Submitted 3.39% 2542.88 kg 103,329.93 17,707.57 6,834.36 50.29 127,871.86 25% 31,967.97 7,991.99 167,831.82
902(1)a Reinforcing Steel (Deformed) Grade 40
As Evaluated 3.39% 2542.88 kg 103,329.93 17,707.57 6,834.36 50.29 127,871.86 25% 31,967.97 7,991.99 167,831.82
As Submitted 5.21% 3825.08 kg 159,568.95 26,636.29 10,280.46 51.37 196,485.70 25% 49,121.43 12,280.36 257,887.49
902(1)b Reinforcing Steel (Deformed) Grade 60
As Evaluated 5.21% 3825.08 kg 159,568.95 26,636.29 10,280.46 51.37 196,485.70 25% 49,121.43 12,280.36 257,887.49
As Submitted 4.50% 218.31 m2 121,261.82 43,941.97 4,394.20 776.87 169,597.99 25% 42,399.50 10,599.87 222,597.36
903(2) Formworks and Falseworks
As Evaluated 4.50% 218.31 m2 121,261.82 43,941.97 4,394.20 776.87 169,597.99 25% 42,399.50 10,599.87 222,597.36
As Submitted 764,534.00 249,401.63 96,100.60 1,110,036.23 277,509.07 69,377.26 1,456,922.56
TOTAL OF PART B
As Evaluated 764,534.00 249,401.63 96,100.60 1,110,036.23 277,509.07 69,377.26 1,456,922.56
6/55
PART C FINISHINGS AND OTHER CIVIL WORKS
C.1. Masonry Works
As Submitted 1.42% 79.51 m2 40,334.84 8,676.67 4,443.02 672.30 53,454.53 25% 13,363.63 3,340.91 70,159.07
1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm
As Evaluated 1.42% 79.51 m2 40,334.84 8,676.67 4,443.02 672.30 53,454.53 25% 13,363.63 3,340.91 70,159.07
As Submitted 0.39% 15.00 m2 11,850.64 1,968.92 1,008.21 988.52 14,827.77 25% 3,706.94 926.74 19,461.45
1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm
As Evaluated 0.39% 15.00 m2 11,850.64 1,968.92 1,008.21 988.52 14,827.77 25% 3,706.94 926.74 19,461.45
As Submitted 52,185.48 10,645.59 5,451.23 68,282.30 17,070.57 4,267.65 89,620.52
Sub - Total C.1
As Evaluated 52,185.48 10,645.59 5,451.23 68,282.30 17,070.57 4,267.65 89,620.52
C.2 Finishing Works
As Submitted 1.62% 528.75 m2 - 30,580.41 30,606.36 115.72 61,186.77 25% 15,296.69 3,824.17 80,307.63
1021(1)a Cement Floor Finish ( Plain )
As Evaluated 1.62% 528.75 m2 - 30,580.41 30,606.36 115.72 61,186.77 25% 15,296.69 3,824.17 80,307.63
As Submitted 0.95% 189.02 m
2
21,917.22 12,571.36 1,257.14 189.11 35,745.72 25% 8,936.43 2,234.11 46,916.26
1027(1) Cement Plaster Finish
As Evaluated 0.95% 189.02 m
2
21,917.22 12,571.36 1,257.14 189.11 35,745.72 25% 8,936.43 2,234.11 46,916.26
As Submitted 21,917.22 43,151.77 31,863.50 96,932.49 24,233.12 6,058.28 127,223.89
Sub-Total C.2
As Evaluated 21,917.22 43,151.77 31,863.50 96,932.49 24,233.12 6,058.28 127,223.89
C.3 Painting Works
As Submitted 2.62% 372.77 m
2
39,219.13 54,049.87 5,404.99 264.70 98,673.99 25% 24,668.50 6,167.12 129,509.61
1032(1)a Painting Works (Masonry/Concrete)
As Evaluated 2.62% 372.77 m
2
39,219.13 54,049.87 5,404.99 264.70 98,673.99 25% 24,668.50 6,167.12 129,509.61
As Submitted 5.39% 526.00 m
2
119,296.80 76,267.50 7,626.75 386.29 203,191.05 25% 50,797.76 12,699.44 266,688.25
1032(5) Textured Finish
As Evaluated 5.39% 526.00 m
2
119,296.80 76,267.50 7,626.75 386.29 203,191.05 25% 50,797.76 12,699.44 266,688.25
As Submitted 5.29% 751.64 m2 73,792.26 114,433.43 11,443.34 265.64 199,669.03 25% 49,917.26 12,479.31 262,065.60
1032(1)c Painting Works (Steel)
As Evaluated 5.29% 751.64 m2 73,792.26 114,433.43 11,443.34 265.64 199,669.03 25% 49,917.26 12,479.31 262,065.60
As Submitted 232,308.19 244,750.80 24,475.08 501,534.07 125,383.52 31,345.87 658,263.46
Sub-Total C.3
As Evaluated 232,308.19 244,750.80 24,475.08 501,534.07 125,383.52 31,345.87 658,263.46
C.4 Roof Framing and Roofing Works
Prepainted Metal Sheets (above 0.427mm) Rib Type Long As Submitted 9.49% 582.78 m2 269,218.13 80,752.65 8,075.26 614.38 358,046.04 25% 89,511.51 22,377.88 469,935.43
1014 (1) b2
Span As Evaluated 9.49% 582.78 m2 269,218.13 80,752.65 8,075.26 614.38 358,046.04 25% 89,511.51 22,377.88 469,935.43
As Submitted 7.05% 1.00 l.s. 165,188.16 69,490.40 31,390.24 266,068.80 266,068.80 25% 66,517.20 16,629.30 349,215.30
1047 (1) Structural Steel
As Evaluated 7.05% 1.00 l.s. 165,188.16 69,490.40 31,390.24 266,068.80 266,068.80 25% 66,517.20 16,629.30 349,215.30
As Submitted 9.13% 4414.60 kg 296,730.65 28,854.60 18,705.96 77.99 344,291.21 25% 86,072.80 21,518.20 451,882.21
1047(2)a Structural Steel (Trusses)
As Evaluated 9.13% 4414.60 kg 296,730.65 28,854.60 18,705.96 77.99 344,291.21 25% 86,072.80 21,518.20 451,882.21
As Submitted 6.92% 3672.57 kg 202,450.42 24,508.97 34,202.69 71.11 261,162.08 25% 65,290.52 16,322.63 342,775.23
1047(2)b Structural Steel (Purlins)
As Evaluated 6.92% 3672.57 kg 202,450.42 24,508.97 34,202.69 71.11 261,162.08 25% 65,290.52 16,322.63 342,775.23
As Submitted 0.18% 48.00 each 5,040.00 1,585.37 158.54 141.33 6,783.91 25% 1,695.98 423.99 8,903.88
1047(3)a Metal Structure Accessories (Bolts)
As Evaluated 0.18% 48.00 each 5,040.00 1,585.37 158.54 141.33 6,783.91 25% 1,695.98 423.99 8,903.88
As Submitted 0.78% 348.90 kg 22,640.12 6,207.44 620.74 84.46 29,468.30 25% 7,367.08 1,841.77 38,677.15
1047(6) Metal Structure Accessories (Steel Plates)
As Evaluated 0.78% 348.90 kg 22,640.12 6,207.44 620.74 84.46 29,468.30 25% 7,367.08 1,841.77 38,677.15
As Submitted 0.34% 213.12 kg 8,476.63 3,791.72 379.17 59.34 12,647.52 25% 3,161.88 790.47 16,599.87
1047(7)b Metal Structure Accessories (Sag Rods)
As Evaluated 0.34% 213.12 kg 8,476.63 3,791.72 379.17 59.34 12,647.52 25% 3,161.88 790.47 16,599.87
As Submitted 0.56% 347.16 kg 14,222.18 6,176.48 617.65 60.54 21,016.31 25% 5,254.08 1,313.52 27,583.91
1047(4) Metal Structure Accessories (Cross Bracing)
As Evaluated 0.56% 347.16 kg 14,222.18 6,176.48 617.65 60.54 21,016.31 25% 5,254.08 1,313.52 27,583.91
As Submitted 0.24% 20.00 pcs 4,120.00 4,624.00 462.40 460.32 9,206.40 25% 2,301.60 575.40 12,083.40
1047(3)c Metal Structure Accessories (Turn Buckle)
As Evaluated 0.24% 20.00 pcs 4,120.00 4,624.00 462.40 460.32 9,206.40 25% 2,301.60 575.40 12,083.40
As Submitted 988,086.29 225,991.63 94,612.65 1,308,690.57 327,172.65 81,793.16 1,717,656.38
Sub-Total C.4
As Evaluated 988,086.29 225,991.63 94,612.65 1,308,690.57 327,172.65 81,793.16 1,717,656.38
As Submitted 1,294,497.18 524,539.79 156,402.46 1,975,439.43 493,859.86 123,464.96 2,592,764.25
TOTAL OF PART C
As Evaluated 1,294,497.18 524,539.79 156,402.46 1,975,439.43 493,859.86 123,464.96 2,592,764.25
PART D ELECTRICAL
Conduits, Boxes & Fittings (Conduit Works/Conduit As Submitted 0.48% 1.00 l.s. 11,848.00 5,548.80 554.88 17,951.68 17,951.68 25% 4,487.92 1,121.98 23,561.58
1100(10)
Rough-in) As Evaluated 0.48% 1.00 l.s. 11,848.00 5,548.80 554.88 17,951.68 17,951.68 25% 4,487.92 1,121.98 23,561.58
As Submitted 1.24% 1.00 l.s. 34,420.00 11,097.60 1,109.76 46,627.36 46,627.36 25% 11,656.84 2,914.21 61,198.41
1101(33) Wires and Wiring Devices
As Evaluated 1.24% 1.00 l.s. 34,420.00 11,097.60 1,109.76 46,627.36 46,627.36 25% 11,656.84 2,914.21 61,198.41
As Submitted 0.41% 1.00 l.s. 15,000.00 586.32 58.63 15,644.95 15,644.95 25% 3,911.24 977.81 20,534.00
1102 (1) Panelboard with Main & Branch Breakers
As Evaluated 0.41% 1.00 l.s. 15,000.00 586.32 58.63 15,644.95 15,644.95 25% 3,911.24 977.81 20,534.00
As Submitted 0.82% 1.00 l.s. 24,927.13 5,548.80 554.88 31,030.81 31,030.81 25% 7,757.70 1,939.43 40,727.94
1103(1) Lighting Fixtures and Lamps
As Evaluated 0.82% 1.00 l.s. 24,927.13 5,548.80 554.88 31,030.81 31,030.81 25% 7,757.70 1,939.43 40,727.94
As Submitted 86,195.13 22,781.52 2,278.15 111,254.80 27,813.70 6,953.43 146,021.93
TOTAL OF PART D
As Evaluated 86,195.13 22,781.52 2,278.15 111,254.80 27,813.70 6,953.43 146,021.93
As Submitted 2,179,715.06 828,737.37 396,743.36 3,405,195.79 851,298.97 212,824.73 4,469,319.49
TOTAL OF PART III
As Evaluated 2,179,715.06 828,737.37 396,743.36 3,405,195.79 851,298.97 212,824.73 4,469,319.49
As Submitted 2,366,952.31 1,008,203.85 450,896.31 3,826,052.47 889,248.73 234,698.80 4,950,000.00
GRAND TOTAL
As Evaluated 2,366,952.31 1,008,203.85 450,896.31 3,826,052.47 889,248.73 234,698.80 4,950,000.00
7/55
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City FORM ABC-2015-02A-00
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon
(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND
PART III
SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 1.00 l.s. 131,753.07 25% 32,938.27 8,234.57 41,172.84 172,925.91 172,925.90
801(1) Removal of Structures and Obstructions
As Evaluated 1.00 l.s. 131,753.07 25% 32,938.27 8,234.57 41,172.84 172,925.91 172,925.90
As Submitted 67.04 m3 15,670.31 25% 3,917.58 979.39 4,896.97 20,567.28 306.79
803(1)a Structure Excavation ( Common soil )
As Evaluated 67.04 m3 15,670.31 25% 3,917.58 979.39 4,896.97 20,567.28 306.79
As Submitted 153.00 m3 61,041.95 25% 15,260.49 3,815.12 19,075.61 80,117.56 523.64
804 (1)b Embankment ( From Borrow )
As Evaluated 153.00 m3 61,041.95 25% 15,260.49 3,815.12 19,075.61 80,117.56 523.64
As Submitted 208,465.33 52,116.34 13,029.08 65,145.42 273,610.75
TOTAL OF PART A
As Evaluated 208,465.33 52,116.34 13,029.08 65,145.42 273,610.75
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon
PART B FACILITIES
PLAIN AND FOR THE
REINFORCED ENGINEER
CONCRETE WORKS
As Submitted 91.80 m3 616,080.68 25% 154,020.17 38,505.04 192,525.21 808,605.89 8,808.34
900(1)c1 Structural Concrete (Class A, 28 days)
As Evaluated 91.80 m3 616,080.68 25% 154,020.17 38,505.04 192,525.21 808,605.89 8,808.34
As Submitted 2,542.88 kg 127,871.86 25% 31,967.97 7,991.99 39,959.96 167,831.82 66.00
902(1)a Reinforcing Steel (Deformed) Grade 40
As Evaluated 2,542.88 kg 127,871.86 25% 31,967.97 7,991.99 39,959.96 167,831.82 66.00
As Submitted 3,825.08 kg 196,485.70 25% 49,121.43 12,280.36 61,401.79 257,887.49 67.42
902(1)b Reinforcing Steel (Deformed) Grade 60
As Evaluated 3,825.08 kg 196,485.70 25% 49,121.43 12,280.36 61,401.79 257,887.49 67.42
As Submitted 218.31 m2 169,597.99 25% 42,399.50 10,599.87 52,999.37 222,597.36 1,019.64
903(2) Formworks and Falseworks
As Evaluated 218.31 m2 169,597.99 25% 42,399.50 10,599.87 52,999.37 222,597.36 1,019.64
As Submitted 1,110,036.23 277,509.07 69,377.26 346,886.33 1,456,922.56
TOTAL OF PART B
As Evaluated 1,110,036.23 277,509.07 69,377.26 346,886.33 1,456,922.56
PART C FINISHINGS AND OTHER CIVIL WORKS
C.1. Masonry Works
CHB Non-Load Bearing (including Reinforcing Steel), As Submitted 79.51 m2 53,454.53 25% 13,363.63 3,340.91 16,704.54 70,159.07 882.39
1046(2)a1
100mm As Evaluated 79.51 m2 53,454.53 25% 13,363.63 3,340.91 16,704.54 70,159.07 882.39
CHB Non-Load Bearing (including Reinforcing Steel), As Submitted 15.00 m2 14,827.77 25% 3,706.94 926.74 4,633.68 19,461.45 1,297.43
1046(2)a2
150mm As Evaluated 15.00 m2 14,827.77 25% 3,706.94 926.74 4,633.68 19,461.45 1,297.43
As Submitted 68,282.30 17,070.57 4,267.65 21,338.22 89,620.52
Sub - Total C.1
As Evaluated 68,282.30 17,070.57 4,267.65 21,338.22 89,620.52
C.2 Finishing Works
As Submitted 528.75 m2 61,186.77 25% 15,296.69 3,824.17 19,120.86 80,307.63 151.88
1021(1)a Cement Floor Finish ( Plain )
As Evaluated 528.75 m2 61,186.77 25% 15,296.69 3,824.17 19,120.86 80,307.63 151.88
As Submitted 189.02 m2 35,745.72 25% 8,936.43 2,234.11 11,170.54 46,916.26 248.21
1027(1) Cement Plaster Finish
As Evaluated 189.02 m2 35,745.72 25% 8,936.43 2,234.11 11,170.54 46,916.26 248.21
As Submitted 96,932.49 24,233.12 6,058.28 30,291.40 127,223.89
Sub-Total C.2
As Evaluated 96,932.49 24,233.12 6,058.28 30,291.40 127,223.89
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon
Conduits, Boxes & Fittings (Conduit Works/Conduit As Submitted 1.00 l.s. 17,951.68 25% 4,487.92 1,121.98 5,609.90 23,561.58 23,561.58
1100(10)
Rough-in) As Evaluated 1.00 l.s. 17,951.68 25% 4,487.92 1,121.98 5,609.90 23,561.58 23,561.58
As Submitted 1.00 l.s. 46,627.36 25% 11,656.84 2,914.21 14,571.05 61,198.41 61,198.41
1101(33) Wires and Wiring Devices
As Evaluated 1.00 l.s. 46,627.36 25% 11,656.84 2,914.21 14,571.05 61,198.41 61,198.41
As Submitted 1.00 l.s. 15,644.95 25% 3,911.24 977.81 4,889.05 20,534.00 20,534.00
1102 (1) Panelboard with Main & Branch Breakers
As Evaluated 1.00 l.s. 15,644.95 25% 3,911.24 977.81 4,889.05 20,534.00 20,534.00
As Submitted 1.00 l.s. 31,030.81 25% 7,757.70 1,939.43 9,697.13 40,727.94 40,727.94
1103(1) Lighting Fixtures and Lamps
As Evaluated 1.00 l.s. 31,030.81 25% 7,757.70 1,939.43 9,697.13 40,727.94 40,727.94
As Submitted 111,254.80 27,813.70 6,953.43 34,767.13 146,021.93
TOTAL OF PART D
As Evaluated 111,254.80 27,813.70 6,953.43 34,767.13 146,021.93
As Submitted 3,405,195.79 851,298.97 212,824.73 1,064,123.70 4,469,319.49
TOTAL OF PART III
As Evaluated 3,405,195.79 851,298.97 212,824.73 1,064,123.70 4,469,319.49
As Submitted 3,826,052.47 889,248.73 234,698.80 1,123,947.53 4,950,000.00
TOTAL OF (Project ID)
As Evaluated 3,826,052.47 889,248.73 234,698.80 1,123,947.53 4,950,000.00
MARCO BRIAN L. BRITON FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN WILFREDO L. RACELIS MA. CHYMBELIN D. IBAL
Engineer II Chief, Planning & Design Section Chief, Construction Section Engineer III Assistant District Engineer
OIC - Office of the Assistant District Engineer OIC - Office of the District Engineer
13/13
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
No. of Amount
Designation No. of Hour/s Hourly Rate
Person
A.1 Labor
Item no./Description : A.1.1(11) Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the Engineer
Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
A.1 Labor
a. Construction Foreman
b. Skilled Laborers
c. Laborers
Sub - Total for A.1 - As Submitted
A.2 Labor
a. Construction Foreman
b. Skilled Laborers
c. Laborers
Sub - Total for A.2 - As Evaluated
A.1 Labor
Item no./Description : B.7(2) Construction Safety and Health (PPE, Safety Personnel, Disinfection)
Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
Total Man-
Designation No. of Person/s Daily Rate Amount (Php)
days
A.1 Labor
a. Safety Practitioner/Officer (Full Time) 1 1200 62.50 75,000.00
b. Health Personnel (Full Time First Aider) 1 1200 35.00 42,000.00
c. Saniatation Aide 1 1200 35.00 42,000.00
B.1 Equipment
F.1 Materials
Personal Protective Equipment
a. Safety Helmet man-days 944 0.34 323.28
b. Safety Shoes man-days 852 4.11 3,501.36
c. Safety Gloves man-days 944 7.67 7,237.34
d. Vest man-days 944 2.22 2,097.78
e. Rain Coats man-days 228 0.34 76.52
f. Dusk Mask man-days 944 10.00 9,440.00
g. Eye Goggles man-days 944 5.00 4,720.00
h. Ear Muff man-days 52 0.83 43.16
i. Body Harness and Lanyards man-days 80 3.21 256.80
j. Rubber Boots man-days 206 1.39 286.34
Antiseptics
a. Sanitizing Solution lit 110 100.00 11,000.00
b. Ethyl Alcohol lit 36 185.00 6,660.00
c. Disinfectant Spray can 18 1,000.00 18,000.00
d. Liquid Hand Soap lit 18 200.00 3,600.00
Item no./Description : B.7(2) Construction Safety and Health (PPE, Safety Personnel, Disinfection)
Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
a. (Not Exceed 1% of E.D.C. ) as per D.O. 197 Series of 2016 l.s. 1 37,000.00 37,000.00
( Service Truck, Low Bed Trailer )
a. (Not Exceed 1% of E.D.C. ) as per D.O. 197 Series of 2016 l.s. 1 37,000.00 37,000.00
( Service Truck, Low Bed Trailer )
A.1 Labor
B.1 Equipment
F.1 Materials
Part A - Earthworks
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
A.1 Labor
B.1 Equipment
F.1 Materials
Part A - Earthworks
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
A..1 Labor
B.1 Equipment
F.1 Materials
Part A - Earthworks
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
A.1 Labor
B.1 Equipment
F.1 Materials
3
a. Gravel m 1.00 1,262.33 1262.33
b. Sand m3 0.50 1,262.33 631.17
c. Portland Cement bags 9.00 250.00 2,250.00
Item No./Description : 1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm
2
Unit of Measurement : m
Output per hour : 3.825
A.1 Labor
B.1 Equipment
F.1 Materials
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Item No./Description : 1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm
2
Unit of Measurement : m
Output per hour : 3.18
A.1 Labor
B.1 Equipment
F.1 Materials
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
A.1 Labor
B.1 Equipment
F.1 Materials
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
A.1 Labor
B.1 Equipment
F.1 Materials
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Item No./Description : 1014 (1) b2 Prepainted Metal Sheets (above 0.427mm) Rib Type Long Span
2
Unit of Measurement : m
Output per hour : 2.076
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Fabrication
a. Construction Foreman 1 112.00 101.45 11,362.40
b. Skilled Laborer 2 112.00 73.29 16,416.96
c. Unskilled Laborer 2 112.00 56.46 12,647.04
Erection
a. Skilled Laborer 2 112.00 73.29 16,416.96
b. Unskilled Laborer 2 112.00 56.46 12,647.04
Fabrication
a. Construction Foreman 1 112.00 101.45 11362.40
b. Skilled Laborer 2 112.00 73.29 16416.96
c. Unskilled Laborer 2 112.00 56.46 12647.04
Erection
a. Skilled Laborer 2 112.00 73.29 16416.96
b. Unskilled Laborer 2 112.00 56.46 12647.04
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Fabrication
a. Construction Foreman 1 1.00 101.45 101.45
b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 2 1.00 56.46 112.92
Erection
a. Skilled Laborer 3 0.50 73.29 109.94
b. Unskilled Laborer 3 0.50 56.46 84.69
Fabrication
a. Construction Foreman 1 1.00 101.45 101.45
b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 2 1.00 56.46 112.92
Erection
a. Skilled Laborer 3 0.50 73.29 109.94
b. Unskilled Laborer 3 0.50 56.46 84.69
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Item No./Description : 1102 (1) Panelboard with Main & Branch Breakers
Unit of Measurement : l.s.
Output per hour : 1.00
Panelboard with Main & Branch Breakers set 1.00 15,000.00 15,000.00
Panelboard with Main & Branch Breakers set 1.00 15,000.00 15,000.00
A.1.1(11) Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the Engineer
QUANTITY: 1.00 l.s
Stair
Page 24 of 55
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Columns
Beams
Unit Weight
BAR Ø LENGTH QUANTITY PCS. FOR 6m No. Of Footing WEIGHT
(kg/m)
16mm Ø 2.00 8.00 3.00 1.578 12.00 340.85 kg
F-1
16mm Ø 2.00 8.00 3.00 1.578 12.00 340.85 kg
16mm Ø 1.00 5.00 1.00 1.578 2.00 18.94 kg
F-2
16mm Ø 1.00 5.00 1.00 1.578 2.00 18.94 kg
WF-1 (T) 12mm Ø 0.50 18.00 2.00 0.888 1.00 10.66 kg
WF-1 (L) 12mm Ø 5.00 3.00 3.00 0.888 1.00 15.98 kg
Bleacher (T) 10mm Ø 0.50 101.00 9.00 0.616 1.00 33.26 kg
Bleacher (L) 10mm Ø 49.65 5.00 42.00 0.616 1.00 155.23 kg
sub-total: Grade 60 719.58
Grade 40 215.13
COLUMN
Unit Weight
BAR Ø LENGTH QUANTITY PCS. FOR 6m No. of Column WEIGHT
(kg/m)
Vertical Bars 16mm 9 12 18.00 1.578 12 2045.09 kg
C-1
Ties 10mm 1.6 47 13.00 0.616 12 576.58 kg
Vertical Bars 16mm 4.6 4 4.00 1.578 2 75.74 kg
C-2
Ties 10mm 1 33 6.00 0.616 2 44.35 kg
sub-total: Grade 60 2,120.83
Grade 40 620.93
BEAMS & ROOF BEAMS
Unit Weight
BAR Ø NO. OF BARS LENGTH PCS. FOR 6m NO. OF BEAM WEIGHT
(kg/m)
Main Bar 16mm 8 6.9 10.00 1.578 10 946.80 kg
B-1
Stirrups 10mm 47 1.1 9.00 0.616 10 318.47 kg
Main Bar 16mm 4 6 4.00 1.578 1 37.87 kg
B-2
Stirrups 10mm 41 1 7.00 0.616 1 25.26 kg
sub-total: Grade 60 984.67
Grade 40 343.73
Page 25 of 55
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
SLAB ON FILL
COLUMN
QTY. WIDTH (m.) DEPTH(m.) HEIGHT AREA UNIT
C-1 6.00 0.45 0.45 7.10 76.68 sq.m
C-1 6.00 0.45 0.45 6.50 70.20 sq.m
C-2 2.00 0.30 0.30 3.70 8.88 sq.m
sub-total: 155.76 sq.m
BEAMS
QUANTITY LENGTH WIDTH DEPTH AREA UNIT
B-1 1.00 55.5 0.25 0.40 58.28 sq.m
B-2 1.00 5.7 0.15 0.30 4.28 sq.m
sub-total: 62.55 sq.m
AREA
SOF ( Court ) 496.00
SOF ( Stage ) 32.75
TOTAL: 528.75 sq.m.
AREA
4" CHB 159.02
6" CHB 30.00
TOTAL: 189.02 sq.m.
AREA UNIT
WALLS 189.02 sq.m.
COLUMNS 108.00 sq.m.
BEAM 1 72.15 sq.m.
BEAM 2 3.60 sq.m.
TOTAL: 372.77 sq.m.
Page 26 of 55
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
SIZE AREA
SOF (Court) 16 x 31 496.00
SOF (Stage) 6x5 30.00
TOTAL: 526.00 sq.m.
SIZE ( G.I.
LENGTH NO PERIMETER AREA
PIPE )
75Ø x 5.5mm 46.00 6 0.24 66.24 sq.m.
TRUSS 1
25Ø x 3.4mm 46.00 6 0.08 22.08 sq.m.
37.5Ø x 3.7mm 12.00 5 0.12 7.20 sq.m.
STRUT
25Ø x 3.4mm 16.00 5 0.08 6.40 sq.m.
STAGE 100Ø x 6mm 5.50 2 0.32 3.52 sq.m.
C-PURLINS 150x50x25x1.5 1077.00 1 0.60 646.20 sq.m.
TOTAL: 751.64 sq.m.
1014 (1) b2 Prepainted Metal Sheets (above 0.427mm) Rib Type Long Span
QUANTITY: 582.78 sq. m.
SIZE AREA
COURT 17.3 x 31 536.30
STAGE 8.3 x 5.6 46.48
TOTAL: 582.78 sq.m.
SIZE ( Angle
LENGTH NO. OF TRUSS kgs./m WEIGHT
Bar )
75Ø x 5.5mm 46.00 6 11.30 3118.80 kg
TRUSS 1
25Ø x 3.4mm 46.00 6 2.50 690.00 kg
37.5Ø x 3.7mm 12.00 5 4.05 243.00 kg
STRUT
25Ø x 3.4mm 16.00 5 2.50 200.00 kg
STAGE 100Ø x 6mm 5.50 2 14.80 162.80 kg
QUANTITY: 4414.60 kg
Prepared by:
Page 28 of 55
UNIT COST ANALYSIS FOR AGGREGATES (SAND and GRAVEL)
MAP SHOWING DPWH QUEZON II DEO OFFICE TO THE POINT OF REFERENCE (PROJECT SITE) L= 28.9 KM