You are on page 1of 55

Republic of the Philippines

Department of Public Works and Highways


QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Dalahican Road, Lucena City

LOCAL PROGRAM, Local Infrastructure


Program, Buildings and Other Structures,
Multipurpose / Facilities, Construction of Multi-
Purpose Building (Covered Court), Barangay
Masin Norte, Candelaria, Quezon

(LIP 2021)
Republic of the Philippines
Department of Public Works and Highways
Quezon II District Engineering Office
Lucena City

Date: November 17, 2020

EXECUTIVE SUMMARY

For : THE DISTRICT ENGINEER

Project ID :

LOCAL PROGRAM, Local Infrastructure Program, Buildings


and Other Structures, Multipurpose / Facilities,
Project Name :
Construction of Multi-Purpose Building (Covered Court),
Barangay Masin Norte, Candelaria, Quezon

Location of Project : Candelaria, Quezon


2. Project Category : Multi-Purpose Building
3. Source of Fund : LIP 2021
4. Action Recommended : For Approval
5. Implementing Office : DPWH Quezon II District Engineering Office
6. Reviewing Offices : DPWH Quezon II District Engineering Office
7. Appropriation : ₱ 5,000,000.00
8. ABC : ₱ 4,950,000.00
9. Project Duration : 150 C.D.
10. Mode Implementation : By Contract

PREPARED BY:

MARCO BRIAN L. BRITON


Engineer II

SUBMITTED BY:

FAUSTINO MARK ANTHONY S. DE LA CRUZ


Chief, Planning and Design Section
Republic of the Philippines
Department of Public Works and Highways ANNEX A
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City FORM POW-2015-01-00

PROGRAM OF WORKS/BUDGET COST

Project : LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/ Appropriation : P 5,000,000.00
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon Source of Fund : GAA 2021 ( LIP )
Candelaria, Quezon
Project ID : Target Start Date :
Location : Candelaria, Quezon Total Project Duration : 150 CD
Project Description : Multi Purpose Building

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 2.30% 87,825.51 2.30% 87,825.51
Part II Other General Requirements 8.70% 333,031.17 8.70% 333,031.17
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
Part A Earthworks 5.44% 208,465.33 5.44% 208,465.33
Part B Plain and Reinforced Concrete Works (PLS. SEE FORM POW-2015-01C-00) 29.01% 1,110,036.23 29.01% 1,110,036.23
Part C Finishing and Other Civil Works 51.63% 1,975,439.43 51.63% 1,975,439.43
Part D Electrical Works 2.91% 111,254.80 2.91% 111,254.80

Total 100.00% 3,826,052.47 100.00% 3,826,052.47

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 1,008,203.85 1,008,203.85 A. Total Direct Cost 3,826,052.47 3,826,052.47
2. Materials 2,366,952.31 2,366,952.31 B. OCM and Profit 889,248.73 889,248.73
3. Rental of Equipment 450,896.31 450,896.31 C. Value Added Tax (5%) 234,698.80 234,698.80
4. Provisional Sum / Daywork D. Total Construction Cost 4,950,000.00 4,950,000.00
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 889,248.73 889,248.73 E. Eng'g & Administrative Overhead, 1.0 % 50,000.00 50,000.00
6. Value Added Tax (5%) 234,698.80 234,698.80 F. RROW Acquisition
7. EAO, 1.0 % 50,000.00 50,000.00 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 5,000,000.00 5,000,000.00 H. TOTAL ESTIMATED COST 5,000,000.00 5,000,000.00
Note: 1. Prices of Materials were based on CMPD 2020 3rd Quarter and Labor based on June 2020 rates in Region IV-A.

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

MARCO BRIAN L. BRITON FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN WILFREDO L. RACELIS MA. CHYMBELIN D. IBAL
Engineer II Chief, Planning & Design Section Chief, Construction Section Engineer III Assistant District Engineer
OIC - Office of the Assistant District Engineer OIC - Office of the District Engineer

Date: November 17, 2020 3/55


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QTY. TOTAL MARK-UP % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT 5% VAT
As Submitted As Evaluated As Submitted As Evaluated As Submitted As Evaluated % COST As Submitted As Evaluated As Submitted As Evaluated

PART I FACILITIES FOR THE ENGINEER


I.1.1 Offices and Laboratory for the Engineer
A.1.1 (3) Construction of Field Office for the Engineer 1.00 1.00 l.s 74,535.51 74,535.51 74,535.51 74,535.51 10% 7,453.55 4,099.45 86,088.51 86,088.51 1.95% 1.95%
Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the
A.1.1(11) 1.00 1.00 l.s 11,040.00 11,040.00 11,040.00 11,040.00 10% 1,104.00 607.20 12,751.20 12,751.20 0.29% 0.29%
Engineer
A.1.4 (1) Provision of Progress Photographs 150.00 150.00 each 2,250.00 2,250.00 15.00 15.00 10% 1.50 0.83 17.33 17.33 0.06% 0.06%
TOTAL OF PART I 87,825.51 87,825.51 2.30% 2.30%
PART II OTHER GENERAL REQUIREMENTS

B.3 Permits and Clearances 1.00 1.00 l.s. 21,325.00 21,325.00 21,325.00 21,325.00 0% - - 21,325.00 21,325.00 0.56% 0.56%

B.5 Project Billboard / Signboard 1.00 1.00 each 11,310.64 11,310.64 11,310.64 11,310.64 25% 2,827.66 706.92 14,845.22 14,845.22 0.30% 0.30%

B.7 (2) Occupational Safety and Health Program 1.00 1.00 l.s. 263,395.53 263,395.53 263,395.53 263,395.53 10% 26,339.55 14,486.75 304,221.84 304,221.84 6.88% 6.88%

B.9 Mobilization / Demobilization 1.00 1.00 l.s. 37,000.00 37,000.00 37,000.00 37,000.00 0% - 1,850.00 38,850.00 38,850.00 0.97% 0.97%

TOTAL OF PART II 333,031.17 333,031.17 8.71% 8.71%

Project ID
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS

801(1) Removal of Structures and Obstructions 1.00 1.00 l.s. 131,753.07 131,753.07 131,753.07 131,753.07 25% 32,938.27 8,234.57 172,925.90 172,925.90 3.44% 3.44%

803(1)a Structure Excavation ( Common soil ) 67.04 67.04 m


3
15,670.31 15,670.31 233.75 233.75 25% 58.44 14.61 306.79 306.79 0.41% 0.41%

804 (1)b Embankment ( From Borrow ) 153.00 153.00 m3 61,041.95 61,041.95 398.97 398.97 25% 99.74 24.94 523.64 523.64 1.60% 1.60%
TOTAL OF PART A 208,465.33 208,465.33 5.45% 5.45%
PART B PLAIN AND REINFORCED CONCRETE WORKS

900(1)c1 Structural Concrete (Class A, 28 days) 91.80 91.80 m


3
616,080.68 616,080.68 6,711.12 6,711.12 25% 1,677.78 419.44 8,808.34 8,808.34 16.10% 16.10%

902(1)a Reinforcing Steel (Deformed) Grade 40 2,542.88 2,542.88 kg 127,871.86 127,871.86 50.29 50.29 25% 12.57 3.14 66.00 66.00 3.34% 3.34%

902(1)b Reinforcing Steel (Deformed) Grade 60 3,825.08 3,825.08 kg 196,485.70 196,485.70 51.37 51.37 25% 12.84 3.21 67.42 67.42 5.14% 5.14%

903(2) Formworks and Falseworks 218.31 218.31 m2 169,597.99 169,597.99 776.87 776.87 25% 194.22 48.55 1,019.64 1,019.64 4.43% 7.39%
TOTAL OF PART B 1,110,036.23 1,110,036.23 29.01% 29.01%
PART C FINISHING
C.1. Masonry Works
1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm 79.51 79.51 m2 53,454.53 53,454.53 672.30 672.30 25% 168.07 42.02 882.39 882.39 1.40% 1.40%

1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm 15.00 15.00 m2 14,827.77 14,827.77 988.52 988.52 25% 247.13 61.78 1,297.43 1,297.43 0.39% 0.39%
Sub-Total C.2 68,282.30 68,282.30 1.78% 1.78%

4/55
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QTY. TOTAL MARK-UP % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT 5% VAT
As Submitted As Evaluated As Submitted As Evaluated As Submitted As Evaluated % COST As Submitted As Evaluated As Submitted As Evaluated

C.2 Finishing Works FACILITIES FOR THE ENGINEER

1021(1)a Cement Floor Finish ( Plain ) 528.75 528.75 m2 61,186.77 61,186.77 115.72 115.72 25% 28.93 7.23 151.88 151.88 1.60% 1.60%

1027(1) Cement Plaster Finish 189.02 189.02 m2 35,745.72 35,745.72 189.11 189.11 25% 47.28 11.82 248.21 248.21 0.93% 0.93%
Sub-Total C.2 96,932.49 96,932.49 2.53% 2.53%
C.3 Painting Works
1032(1)a Painting Works (Masonry/Concrete) 372.77 372.77 m
2
98,673.99 98,673.99 264.70 264.70 25% 66.18 16.54 347.43 347.43 2.58% 2.58%

1032(5) Textured Finish 526.00 526.00 m2 203,191.05 203,191.05 386.29 386.29 25% 96.57 24.14 507.01 507.01 5.31% 5.31%

1032(1)c Painting Works (Steel) 751.64 751.64 m2 199,669.03 199,669.03 265.64 265.64 25% 66.41 16.60 348.66 348.66 5.22% 5.22%
Sub-Total C.3 501,534.07 501,534.07 13.11% 13.11%
C.4 Roof Framing and Roofing Works
1014 (1) b2 Prepainted Metal Sheets (above 0.427mm) Rib Type Long Span 582.78 582.78 m2 358,046.04 358,046.04 614.38 614.38 25% 153.59 38.40 806.37 806.37 9.36% 9.36%

1047 (1) Structural Steel 1.00 1.00 l.s. 266,068.80 266,068.80 266,068.80 266,068.80 25% 66,517.20 16,629.30 349,215.30 349,215.30 6.95% 6.95%

1047(2)a Structural Steel (Trusses) 4,414.60 4,414.60 kg 344,291.21 344,291.21 77.99 77.99 25% 19.50 4.87 102.36 102.36 9.00% 9.00%

1047(2)b Structural Steel (Purlins) 3,672.57 3,672.57 kg 261,162.08 261,162.08 71.11 71.11 25% 17.78 4.44 93.33 93.33 6.83% 6.83%

1047(3)a Metal Structure Accessories (Bolts) 48.00 48.00 each 6,783.91 6,783.91 141.33 141.33 25% 35.33 8.83 185.50 185.50 0.18% 0.18%

1047(6) Metal Structure Accessories (Steel Plates) 348.90 348.90 kg 29,468.30 29,468.30 84.46 84.46 25% 21.12 5.28 110.85 110.85 0.77% 0.77%

1047(7)b Metal Structure Accessories (Sag Rods) 213.12 213.12 kg 12,647.52 12,647.52 59.34 59.34 25% 14.84 3.71 77.89 77.89 0.33% 0.33%

1047(4) Metal Structure Accessories (Cross Bracing) 347.16 347.16 kg 21,016.31 21,016.31 60.54 60.54 25% 15.13 3.78 79.46 79.46 0.55% 0.55%

1047(3)c Metal Structure Accessories (Turn Buckle) 20.00 20.00 pcs 9,206.40 9,206.40 460.32 460.32 25% 115.08 28.77 604.17 604.17 0.24% 0.24%
Sub-Total C.4 1,308,690.57 1,308,690.57 34.20% 34.20%
TOTAL OF PART C 1,975,439.43 1,975,439.43 51.63% 51.63%
PART D ELECTRICAL

1100(10) Conduits, Boxes & Fittings (Conduit Works/ConduitRough-in) 1.00 1.00 l.s. 17,951.68 17,951.68 17,951.68 17,951.68 25% 4,487.92 1,121.98 23,561.58 23,561.58 0.47% 0.47%

1101(33) Wires and Wiring Devices 1.00 1.00 l.s. 46,627.36 46,627.36 46,627.36 46,627.36 25% 11,656.84 2,914.21 61,198.41 61,198.41 1.22% 1.22%

1102 (1) Panelboard with Main & Branch Breakers 1.00 1.00 l.s. 15,644.95 15,644.95 15,644.95 15,644.95 25% 3,911.24 977.81 20,534.00 20,534.00 0.41% 0.41%

1103(1) Lighting Fixtures and Lamps 1.00 1.00 l.s. 31,030.81 31,030.81 31,030.81 31,030.81 25% 7,757.70 1,939.43 40,727.94 40,727.94 0.81% 0.81%
TOTAL OF PART D 111,254.80 111,254.80 2.91% 2.91%
TOTAL OF PART III 3,405,195.79 3,405,195.79
TOTAL OF (Project ID) 3,826,052.47 3,826,052.47
GRAND TOTAL 3,826,052.47 3,826,052.47 100.0% 100.0%

5/55
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 1.74% 1.00 l.s 55,219.67 19,315.84 - 74,535.51 74,535.51 10% 7,453.55 4,099.45 86,088.51
A.1.1 (3) Construction of Field Office for the Engineer
As Evaluated 1.74% 1.00 l.s 55,219.67 19,315.84 - 74,535.51 74,535.51 10% 7,453.55 4,099.45 86,088.51
Provision of Furnitures/Fixtures, Equipment & Appliances for As Submitted 0.26% 1.00 l.s 11,040.00 - - 11,040.00 11,040.00 10% 1,104.00 607.20 12,751.20
A.1.1(11)
the Field Office for the Engineer As Evaluated 0.26% 1.00 l.s 11,040.00 - - 11,040.00 11,040.00 10% 1,104.00 607.20 12,751.20
As Submitted 0.05% 150.00 each 2,250.00 - - 15.00 2,250.00 10% 225.00 123.75 2,598.75
A.1.4 (1) Provision of Progress Photographs
As Evaluated 0.05% 150.00 each 2,250.00 - - 15.00 2,250.00 10% 225.00 123.75 2,598.75
As Submitted 68,509.67 19,315.84 - 87,825.51 8,782.55 4,830.40 101,438.46
TOTAL OF PART I
As Evaluated 68,509.67 19,315.84 - 87,825.51 8,782.55 4,830.40 101,438.46
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.43% 1.00 l.s. 21,325.00 - - 21,325.00 21,325.00 0% - - 21,325.00
B.3 Permits and Clearances
As Evaluated 0.43% 1.00 l.s. 21,325.00 - - 21,325.00 21,325.00 0% - - 21,325.00
As Submitted 0.30% 1.00 each 10,160.00 1,150.64 - 11,310.64 11,310.64 25% 2,827.66 706.92 14,845.22
B.5 Project Billboard / Signboard
As Evaluated 0.30% 1.00 each 10,160.00 1,150.64 - 11,310.64 11,310.64 25% 2,827.66 706.92 14,845.22
As Submitted 6.15% 1.00 l.s. 87,242.58 159,000.00 17,152.95 263,395.53 263,395.53 10% 26,339.55 14,486.75 304,221.83
B.7 (2) Occupational Safety and Health Program
As Evaluated 6.15% 1.00 l.s. 87,242.58 159,000.00 17,152.95 263,395.53 263,395.53 10% 26,339.55 14,486.75 304,221.83
As Submitted 0.78% 1.00 l.s. - - 37,000.00 37,000.00 37,000.00 0% - 1,850.00 38,850.00
B.9 Mobilization / Demobilization
As Evaluated 0.78% 1.00 l.s. - - 37,000.00 37,000.00 37,000.00 0% - 1,850.00 38,850.00
As Submitted 118,727.58 160,150.64 54,152.95 333,031.17 29,167.21 17,043.67 379,242.05
TOTAL OF PART II
As Evaluated 118,727.58 160,150.64 54,152.95 333,031.17 29,167.21 17,043.67 379,242.05

(Project ID)
(Project Component ID - Description)
PART
CIVIL,
III MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 3.49% 1.00 l.s. - 9,818.70 121,934.37 131,753.07 131,753.07 25% 32,938.27 8,234.57 172,925.91
801(1) Removal of Structures and Obstructions
As Evaluated 3.49% 1.00 l.s. - 9,818.70 121,934.37 131,753.07 131,753.07 25% 32,938.27 8,234.57 172,925.91
As Submitted 0.42% 67.04 m3 - 907.82 14,762.49 233.75 15,670.31 25% 3,917.58 979.39 20,567.28
803(1)a Structure Excavation ( Common soil )
As Evaluated 0.42% 67.04 m3 - 907.82 14,762.49 233.75 15,670.31 25% 3,917.58 979.39 20,567.28
As Submitted 1.62% 153.00 m3 34,488.75 21,287.91 5,265.29 398.97 61,041.95 25% 15,260.49 3,815.12 80,117.56
804 (1)b Embankment ( From Borrow )
As Evaluated 1.62% 153.00 m3 34,488.75 21,287.91 5,265.29 398.97 61,041.95 25% 15,260.49 3,815.12 80,117.56
As Submitted 34,488.75 32,014.43 141,962.15 208,465.33 52,116.34 13,029.08 273,610.75
TOTAL OF PART A
As Evaluated 34,488.75 32,014.43 141,962.15 208,465.33 52,116.34 13,029.08 273,610.75
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 16.34% 91.80 m3 380,373.30 161,115.80 74,591.58 6,711.12 616,080.68 25% 154,020.17 38,505.04 808,605.89
900(1)c1 Structural Concrete (Class A, 28 days)
As Evaluated 16.34% 91.80 m3 380,373.30 161,115.80 74,591.58 6,711.12 616,080.68 25% 154,020.17 38,505.04 808,605.89
As Submitted 3.39% 2542.88 kg 103,329.93 17,707.57 6,834.36 50.29 127,871.86 25% 31,967.97 7,991.99 167,831.82
902(1)a Reinforcing Steel (Deformed) Grade 40
As Evaluated 3.39% 2542.88 kg 103,329.93 17,707.57 6,834.36 50.29 127,871.86 25% 31,967.97 7,991.99 167,831.82
As Submitted 5.21% 3825.08 kg 159,568.95 26,636.29 10,280.46 51.37 196,485.70 25% 49,121.43 12,280.36 257,887.49
902(1)b Reinforcing Steel (Deformed) Grade 60
As Evaluated 5.21% 3825.08 kg 159,568.95 26,636.29 10,280.46 51.37 196,485.70 25% 49,121.43 12,280.36 257,887.49
As Submitted 4.50% 218.31 m2 121,261.82 43,941.97 4,394.20 776.87 169,597.99 25% 42,399.50 10,599.87 222,597.36
903(2) Formworks and Falseworks
As Evaluated 4.50% 218.31 m2 121,261.82 43,941.97 4,394.20 776.87 169,597.99 25% 42,399.50 10,599.87 222,597.36
As Submitted 764,534.00 249,401.63 96,100.60 1,110,036.23 277,509.07 69,377.26 1,456,922.56
TOTAL OF PART B
As Evaluated 764,534.00 249,401.63 96,100.60 1,110,036.23 277,509.07 69,377.26 1,456,922.56

6/55
PART C FINISHINGS AND OTHER CIVIL WORKS
C.1. Masonry Works
As Submitted 1.42% 79.51 m2 40,334.84 8,676.67 4,443.02 672.30 53,454.53 25% 13,363.63 3,340.91 70,159.07
1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm
As Evaluated 1.42% 79.51 m2 40,334.84 8,676.67 4,443.02 672.30 53,454.53 25% 13,363.63 3,340.91 70,159.07
As Submitted 0.39% 15.00 m2 11,850.64 1,968.92 1,008.21 988.52 14,827.77 25% 3,706.94 926.74 19,461.45
1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm
As Evaluated 0.39% 15.00 m2 11,850.64 1,968.92 1,008.21 988.52 14,827.77 25% 3,706.94 926.74 19,461.45
As Submitted 52,185.48 10,645.59 5,451.23 68,282.30 17,070.57 4,267.65 89,620.52
Sub - Total C.1
As Evaluated 52,185.48 10,645.59 5,451.23 68,282.30 17,070.57 4,267.65 89,620.52
C.2 Finishing Works
As Submitted 1.62% 528.75 m2 - 30,580.41 30,606.36 115.72 61,186.77 25% 15,296.69 3,824.17 80,307.63
1021(1)a Cement Floor Finish ( Plain )
As Evaluated 1.62% 528.75 m2 - 30,580.41 30,606.36 115.72 61,186.77 25% 15,296.69 3,824.17 80,307.63
As Submitted 0.95% 189.02 m
2
21,917.22 12,571.36 1,257.14 189.11 35,745.72 25% 8,936.43 2,234.11 46,916.26
1027(1) Cement Plaster Finish
As Evaluated 0.95% 189.02 m
2
21,917.22 12,571.36 1,257.14 189.11 35,745.72 25% 8,936.43 2,234.11 46,916.26
As Submitted 21,917.22 43,151.77 31,863.50 96,932.49 24,233.12 6,058.28 127,223.89
Sub-Total C.2
As Evaluated 21,917.22 43,151.77 31,863.50 96,932.49 24,233.12 6,058.28 127,223.89
C.3 Painting Works
As Submitted 2.62% 372.77 m
2
39,219.13 54,049.87 5,404.99 264.70 98,673.99 25% 24,668.50 6,167.12 129,509.61
1032(1)a Painting Works (Masonry/Concrete)
As Evaluated 2.62% 372.77 m
2
39,219.13 54,049.87 5,404.99 264.70 98,673.99 25% 24,668.50 6,167.12 129,509.61
As Submitted 5.39% 526.00 m
2
119,296.80 76,267.50 7,626.75 386.29 203,191.05 25% 50,797.76 12,699.44 266,688.25
1032(5) Textured Finish
As Evaluated 5.39% 526.00 m
2
119,296.80 76,267.50 7,626.75 386.29 203,191.05 25% 50,797.76 12,699.44 266,688.25
As Submitted 5.29% 751.64 m2 73,792.26 114,433.43 11,443.34 265.64 199,669.03 25% 49,917.26 12,479.31 262,065.60
1032(1)c Painting Works (Steel)
As Evaluated 5.29% 751.64 m2 73,792.26 114,433.43 11,443.34 265.64 199,669.03 25% 49,917.26 12,479.31 262,065.60
As Submitted 232,308.19 244,750.80 24,475.08 501,534.07 125,383.52 31,345.87 658,263.46
Sub-Total C.3
As Evaluated 232,308.19 244,750.80 24,475.08 501,534.07 125,383.52 31,345.87 658,263.46
C.4 Roof Framing and Roofing Works
Prepainted Metal Sheets (above 0.427mm) Rib Type Long As Submitted 9.49% 582.78 m2 269,218.13 80,752.65 8,075.26 614.38 358,046.04 25% 89,511.51 22,377.88 469,935.43
1014 (1) b2
Span As Evaluated 9.49% 582.78 m2 269,218.13 80,752.65 8,075.26 614.38 358,046.04 25% 89,511.51 22,377.88 469,935.43
As Submitted 7.05% 1.00 l.s. 165,188.16 69,490.40 31,390.24 266,068.80 266,068.80 25% 66,517.20 16,629.30 349,215.30
1047 (1) Structural Steel
As Evaluated 7.05% 1.00 l.s. 165,188.16 69,490.40 31,390.24 266,068.80 266,068.80 25% 66,517.20 16,629.30 349,215.30
As Submitted 9.13% 4414.60 kg 296,730.65 28,854.60 18,705.96 77.99 344,291.21 25% 86,072.80 21,518.20 451,882.21
1047(2)a Structural Steel (Trusses)
As Evaluated 9.13% 4414.60 kg 296,730.65 28,854.60 18,705.96 77.99 344,291.21 25% 86,072.80 21,518.20 451,882.21
As Submitted 6.92% 3672.57 kg 202,450.42 24,508.97 34,202.69 71.11 261,162.08 25% 65,290.52 16,322.63 342,775.23
1047(2)b Structural Steel (Purlins)
As Evaluated 6.92% 3672.57 kg 202,450.42 24,508.97 34,202.69 71.11 261,162.08 25% 65,290.52 16,322.63 342,775.23
As Submitted 0.18% 48.00 each 5,040.00 1,585.37 158.54 141.33 6,783.91 25% 1,695.98 423.99 8,903.88
1047(3)a Metal Structure Accessories (Bolts)
As Evaluated 0.18% 48.00 each 5,040.00 1,585.37 158.54 141.33 6,783.91 25% 1,695.98 423.99 8,903.88
As Submitted 0.78% 348.90 kg 22,640.12 6,207.44 620.74 84.46 29,468.30 25% 7,367.08 1,841.77 38,677.15
1047(6) Metal Structure Accessories (Steel Plates)
As Evaluated 0.78% 348.90 kg 22,640.12 6,207.44 620.74 84.46 29,468.30 25% 7,367.08 1,841.77 38,677.15
As Submitted 0.34% 213.12 kg 8,476.63 3,791.72 379.17 59.34 12,647.52 25% 3,161.88 790.47 16,599.87
1047(7)b Metal Structure Accessories (Sag Rods)
As Evaluated 0.34% 213.12 kg 8,476.63 3,791.72 379.17 59.34 12,647.52 25% 3,161.88 790.47 16,599.87
As Submitted 0.56% 347.16 kg 14,222.18 6,176.48 617.65 60.54 21,016.31 25% 5,254.08 1,313.52 27,583.91
1047(4) Metal Structure Accessories (Cross Bracing)
As Evaluated 0.56% 347.16 kg 14,222.18 6,176.48 617.65 60.54 21,016.31 25% 5,254.08 1,313.52 27,583.91
As Submitted 0.24% 20.00 pcs 4,120.00 4,624.00 462.40 460.32 9,206.40 25% 2,301.60 575.40 12,083.40
1047(3)c Metal Structure Accessories (Turn Buckle)
As Evaluated 0.24% 20.00 pcs 4,120.00 4,624.00 462.40 460.32 9,206.40 25% 2,301.60 575.40 12,083.40
As Submitted 988,086.29 225,991.63 94,612.65 1,308,690.57 327,172.65 81,793.16 1,717,656.38
Sub-Total C.4
As Evaluated 988,086.29 225,991.63 94,612.65 1,308,690.57 327,172.65 81,793.16 1,717,656.38
As Submitted 1,294,497.18 524,539.79 156,402.46 1,975,439.43 493,859.86 123,464.96 2,592,764.25
TOTAL OF PART C
As Evaluated 1,294,497.18 524,539.79 156,402.46 1,975,439.43 493,859.86 123,464.96 2,592,764.25
PART D ELECTRICAL
Conduits, Boxes & Fittings (Conduit Works/Conduit As Submitted 0.48% 1.00 l.s. 11,848.00 5,548.80 554.88 17,951.68 17,951.68 25% 4,487.92 1,121.98 23,561.58
1100(10)
Rough-in) As Evaluated 0.48% 1.00 l.s. 11,848.00 5,548.80 554.88 17,951.68 17,951.68 25% 4,487.92 1,121.98 23,561.58
As Submitted 1.24% 1.00 l.s. 34,420.00 11,097.60 1,109.76 46,627.36 46,627.36 25% 11,656.84 2,914.21 61,198.41
1101(33) Wires and Wiring Devices
As Evaluated 1.24% 1.00 l.s. 34,420.00 11,097.60 1,109.76 46,627.36 46,627.36 25% 11,656.84 2,914.21 61,198.41
As Submitted 0.41% 1.00 l.s. 15,000.00 586.32 58.63 15,644.95 15,644.95 25% 3,911.24 977.81 20,534.00
1102 (1) Panelboard with Main & Branch Breakers
As Evaluated 0.41% 1.00 l.s. 15,000.00 586.32 58.63 15,644.95 15,644.95 25% 3,911.24 977.81 20,534.00
As Submitted 0.82% 1.00 l.s. 24,927.13 5,548.80 554.88 31,030.81 31,030.81 25% 7,757.70 1,939.43 40,727.94
1103(1) Lighting Fixtures and Lamps
As Evaluated 0.82% 1.00 l.s. 24,927.13 5,548.80 554.88 31,030.81 31,030.81 25% 7,757.70 1,939.43 40,727.94
As Submitted 86,195.13 22,781.52 2,278.15 111,254.80 27,813.70 6,953.43 146,021.93
TOTAL OF PART D
As Evaluated 86,195.13 22,781.52 2,278.15 111,254.80 27,813.70 6,953.43 146,021.93
As Submitted 2,179,715.06 828,737.37 396,743.36 3,405,195.79 851,298.97 212,824.73 4,469,319.49
TOTAL OF PART III
As Evaluated 2,179,715.06 828,737.37 396,743.36 3,405,195.79 851,298.97 212,824.73 4,469,319.49
As Submitted 2,366,952.31 1,008,203.85 450,896.31 3,826,052.47 889,248.73 234,698.80 4,950,000.00
GRAND TOTAL
As Evaluated 2,366,952.31 1,008,203.85 450,896.31 3,826,052.47 889,248.73 234,698.80 4,950,000.00

7/55
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City FORM ABC-2015-02A-00

LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 150 CD
TOTAL MARK-UP
ESTIMATED TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
DIRECT COST % VALUE COST

PART I FACILITIES FOR THE ENGINEER


As Submitted 1.00 l.s. 74,535.51 10% 7,453.55 4,099.45 11,553.00 86,088.51 86,088.51
A.1.1 (3) Construction of Field Office for the Engineer
As Evaluated 1.00 l.s. 74,535.51 10% 7,453.55 4,099.45 11,553.00 86,088.51 86,088.51
Provision of Furnitures/Fixtures, Equipment & As Submitted 1.00 l.s. 11,040.00 10% 1,104.00 607.20 1,711.20 12,751.20 12,751.20
A.1.1(11)
Appliances for the Field Office for the Engineer As Evaluated 1.00 l.s. 11,040.00 10% 1,104.00 607.20 1,711.20 12,751.20 12,751.20
As Submitted 150.00 each 2,250.00 10% 225.00 123.75 348.75 2,598.75 17.33
A.1.4 (1) Provision of Progress Photographs
As Evaluated 150.00 each 2,250.00 10% 225.00 123.75 348.75 2,598.75 17.33
As Submitted 87,825.51 8,782.55 4,830.40 13,612.95 101,438.46
TOTAL OF PART I
As Evaluated 87,825.51 8,782.55 4,830.40 13,612.95 101,438.46
PART II OTHER GENERAL REQUIREMENTS
As Submitted 1.00 l.s. 21,325.00 0% - - - 21,325.00 21,325.00
B.3 Permits and Clearances
As Evaluated 1.00 l.s. 21,325.00 0% - - - 21,325.00 21,325.00
As Submitted 1.00 each 11,310.64 25% 2,827.66 706.92 3,534.58 14,845.22 14,845.22
B.5 Project Billboard / Signboard
As Evaluated 1.00 each 11,310.64 25% 2,827.66 706.92 3,534.58 14,845.22 14,845.22
As Submitted 1.00 l.s. 263,395.53 10% 26,339.55 14,486.75 40,826.30 304,221.83 304,221.84
B.7 (2) Occupational Safety and Health Program
As Evaluated 1.00 l.s. 263,395.53 10% 26,339.55 14,486.75 40,826.30 304,221.83 304,221.84
As Submitted 1.00 l.s. 37,000.00 0% - 1,850.00 1,850.00 38,850.00 38,850.00
B.9 Mobilization / Demobilization
As Evaluated 1.00 l.s. 37,000.00 0% - 1,850.00 1,850.00 38,850.00 38,850.00
As Submitted 333,031.17 29,167.21 17,043.67 46,210.88 379,242.05
TOTAL OF PART II
As Evaluated 333,031.17 29,167.21 17,043.67 46,210.88 379,242.05

(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND
PART III
SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 1.00 l.s. 131,753.07 25% 32,938.27 8,234.57 41,172.84 172,925.91 172,925.90
801(1) Removal of Structures and Obstructions
As Evaluated 1.00 l.s. 131,753.07 25% 32,938.27 8,234.57 41,172.84 172,925.91 172,925.90
As Submitted 67.04 m3 15,670.31 25% 3,917.58 979.39 4,896.97 20,567.28 306.79
803(1)a Structure Excavation ( Common soil )
As Evaluated 67.04 m3 15,670.31 25% 3,917.58 979.39 4,896.97 20,567.28 306.79
As Submitted 153.00 m3 61,041.95 25% 15,260.49 3,815.12 19,075.61 80,117.56 523.64
804 (1)b Embankment ( From Borrow )
As Evaluated 153.00 m3 61,041.95 25% 15,260.49 3,815.12 19,075.61 80,117.56 523.64
As Submitted 208,465.33 52,116.34 13,029.08 65,145.42 273,610.75
TOTAL OF PART A
As Evaluated 208,465.33 52,116.34 13,029.08 65,145.42 273,610.75

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost

MARCO BRIAN L. BRITON FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Engineer II Chief, Planning & Design Section Chief, Construction Section

Date: November 17, 2020 Page 8 of 55


Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City FORM ABC-2015-02A-00

LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 150 CD
TOTAL MARK-UP
ESTIMATED TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
DIRECT COST % VALUE COST

PART B FACILITIES
PLAIN AND FOR THE
REINFORCED ENGINEER
CONCRETE WORKS
As Submitted 91.80 m3 616,080.68 25% 154,020.17 38,505.04 192,525.21 808,605.89 8,808.34
900(1)c1 Structural Concrete (Class A, 28 days)
As Evaluated 91.80 m3 616,080.68 25% 154,020.17 38,505.04 192,525.21 808,605.89 8,808.34
As Submitted 2,542.88 kg 127,871.86 25% 31,967.97 7,991.99 39,959.96 167,831.82 66.00
902(1)a Reinforcing Steel (Deformed) Grade 40
As Evaluated 2,542.88 kg 127,871.86 25% 31,967.97 7,991.99 39,959.96 167,831.82 66.00
As Submitted 3,825.08 kg 196,485.70 25% 49,121.43 12,280.36 61,401.79 257,887.49 67.42
902(1)b Reinforcing Steel (Deformed) Grade 60
As Evaluated 3,825.08 kg 196,485.70 25% 49,121.43 12,280.36 61,401.79 257,887.49 67.42
As Submitted 218.31 m2 169,597.99 25% 42,399.50 10,599.87 52,999.37 222,597.36 1,019.64
903(2) Formworks and Falseworks
As Evaluated 218.31 m2 169,597.99 25% 42,399.50 10,599.87 52,999.37 222,597.36 1,019.64
As Submitted 1,110,036.23 277,509.07 69,377.26 346,886.33 1,456,922.56
TOTAL OF PART B
As Evaluated 1,110,036.23 277,509.07 69,377.26 346,886.33 1,456,922.56
PART C FINISHINGS AND OTHER CIVIL WORKS
C.1. Masonry Works
CHB Non-Load Bearing (including Reinforcing Steel), As Submitted 79.51 m2 53,454.53 25% 13,363.63 3,340.91 16,704.54 70,159.07 882.39
1046(2)a1
100mm As Evaluated 79.51 m2 53,454.53 25% 13,363.63 3,340.91 16,704.54 70,159.07 882.39
CHB Non-Load Bearing (including Reinforcing Steel), As Submitted 15.00 m2 14,827.77 25% 3,706.94 926.74 4,633.68 19,461.45 1,297.43
1046(2)a2
150mm As Evaluated 15.00 m2 14,827.77 25% 3,706.94 926.74 4,633.68 19,461.45 1,297.43
As Submitted 68,282.30 17,070.57 4,267.65 21,338.22 89,620.52
Sub - Total C.1
As Evaluated 68,282.30 17,070.57 4,267.65 21,338.22 89,620.52
C.2 Finishing Works
As Submitted 528.75 m2 61,186.77 25% 15,296.69 3,824.17 19,120.86 80,307.63 151.88
1021(1)a Cement Floor Finish ( Plain )
As Evaluated 528.75 m2 61,186.77 25% 15,296.69 3,824.17 19,120.86 80,307.63 151.88
As Submitted 189.02 m2 35,745.72 25% 8,936.43 2,234.11 11,170.54 46,916.26 248.21
1027(1) Cement Plaster Finish
As Evaluated 189.02 m2 35,745.72 25% 8,936.43 2,234.11 11,170.54 46,916.26 248.21
As Submitted 96,932.49 24,233.12 6,058.28 30,291.40 127,223.89
Sub-Total C.2
As Evaluated 96,932.49 24,233.12 6,058.28 30,291.40 127,223.89

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost

MARCO BRIAN L. BRITON FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Engineer II Chief, Planning & Design Section Chief, Construction Section

Date: November 17, 2020 Page 9 of 55


Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City FORM ABC-2015-02A-00

LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 150 CD
TOTAL MARK-UP
ESTIMATED TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
DIRECT COST % VALUE COST

FACILITIES FOR THE ENGINEER


C.3 Painting Works
As Submitted 372.77 m2 98,673.99 25% 24,668.50 6,167.12 30,835.62 129,509.61 347.43
1032(1)a Painting Works (Masonry/Concrete)
As Evaluated 372.77 m2 98,673.99 25% 24,668.50 6,167.12 30,835.62 129,509.61 347.43
As Submitted 526.00 m2 203,191.05 25% 50,797.76 12,699.44 63,497.20 266,688.25 507.01
1032(5) Textured Finish
As Evaluated 526.00 m2 203,191.05 25% 50,797.76 12,699.44 63,497.20 266,688.25 507.01
As Submitted 751.64 m2 199,669.03 25% 49,917.26 12,479.31 62,396.57 262,065.60 348.66
1032(1)c Painting Works (Steel)
As Evaluated 751.64 m2 199,669.03 25% 49,917.26 12,479.31 62,396.57 262,065.60 348.66
As Submitted 501,534.07 125,383.52 31,345.87 156,729.39 658,263.46
Sub-Total C.3
As Evaluated 501,534.07 125,383.52 31,345.87 156,729.39 658,263.46
C.4 Roof Framing and Roofing Works
Prepainted Metal Sheets (above 0.427mm) Rib Type As Submitted 582.78 m2 358,046.04 25% 89,511.51 22,377.88 111,889.39 469,935.43 806.37
1014 (1) b2
Long Span As Evaluated 582.78 m2 358,046.04 25% 89,511.51 22,377.88 111,889.39 469,935.43 806.37
As Submitted 1.00 l.s. 266,068.80 25% 66,517.20 16,629.30 83,146.50 349,215.30 349,215.30
1047 (1) Structural Steel
As Evaluated 1.00 l.s. 266,068.80 25% 66,517.20 16,629.30 83,146.50 349,215.30 349,215.30
As Submitted 4,414.60 kg 344,291.21 25% 86,072.80 21,518.20 107,591.00 451,882.21 102.36
1047(2)a Structural Steel (Trusses)
As Evaluated 4,414.60 kg 344,291.21 25% 86,072.80 21,518.20 107,591.00 451,882.21 102.36
As Submitted 3,672.57 kg 261,162.08 25% 65,290.52 16,322.63 81,613.15 342,775.23 93.33
1047(2)b Structural Steel (Purlins)
As Evaluated 3,672.57 kg 261,162.08 25% 65,290.52 16,322.63 81,613.15 342,775.23 93.33
As Submitted 48.00 each 6,783.91 25% 1,695.98 423.99 2,119.97 8,903.88 185.50
1047(3)a Metal Structure Accessories (Bolts)
As Evaluated 48.00 each 6,783.91 25% 1,695.98 423.99 2,119.97 8,903.88 185.50
As Submitted 348.90 kg 29,468.30 25% 7,367.08 1,841.77 9,208.85 38,677.15 110.85
1047(6) Metal Structure Accessories (Steel Plates)
As Evaluated 348.90 kg 29,468.30 25% 7,367.08 1,841.77 9,208.85 38,677.15 110.85
As Submitted 213.12 kg 12,647.52 25% 3,161.88 790.47 3,952.35 16,599.87 77.89
1047(7)b Metal Structure Accessories (Sag Rods)
As Evaluated 213.12 kg 12,647.52 25% 3,161.88 790.47 3,952.35 16,599.87 77.89
As Submitted 347.16 kg 21,016.31 25% 5,254.08 1,313.52 6,567.60 27,583.91 79.46
1047(4) Metal Structure Accessories (Cross Bracing)
As Evaluated 347.16 kg 21,016.31 25% 5,254.08 1,313.52 6,567.60 27,583.91 79.46
As Submitted 20.00 pcs 9,206.40 25% 2,301.60 575.40 2,877.00 12,083.40 604.17
1047(3)c Metal Structure Accessories (Turn Buckle)
As Evaluated 20.00 pcs 9,206.40 25% 2,301.60 575.40 2,877.00 12,083.40 604.17
As Submitted 1,308,690.57 327,172.65 81,793.16 408,965.81 1,717,656.38
Sub-Total C.4
As Evaluated 1,308,690.57 327,172.65 81,793.16 408,965.81 1,717,656.38
As Submitted 1,975,439.43 493,859.86 123,464.96 617,324.82 2,592,764.25
TOTAL OF PART C
As Evaluated 1,975,439.43 493,859.86 123,464.96 617,324.82 2,592,764.25

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost

MARCO BRIAN L. BRITON FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Engineer II Chief, Planning & Design Section Chief, Construction Section

Date: November 17, 2020 Page 10 of 55


Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City FORM ABC-2015-02A-00

LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 150 CD
TOTAL MARK-UP
ESTIMATED TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
DIRECT COST % VALUE COST

FACILITIES FOR THE ENGINEER


PART D ELECTRICAL WORKS

Conduits, Boxes & Fittings (Conduit Works/Conduit As Submitted 1.00 l.s. 17,951.68 25% 4,487.92 1,121.98 5,609.90 23,561.58 23,561.58
1100(10)
Rough-in) As Evaluated 1.00 l.s. 17,951.68 25% 4,487.92 1,121.98 5,609.90 23,561.58 23,561.58
As Submitted 1.00 l.s. 46,627.36 25% 11,656.84 2,914.21 14,571.05 61,198.41 61,198.41
1101(33) Wires and Wiring Devices
As Evaluated 1.00 l.s. 46,627.36 25% 11,656.84 2,914.21 14,571.05 61,198.41 61,198.41
As Submitted 1.00 l.s. 15,644.95 25% 3,911.24 977.81 4,889.05 20,534.00 20,534.00
1102 (1) Panelboard with Main & Branch Breakers
As Evaluated 1.00 l.s. 15,644.95 25% 3,911.24 977.81 4,889.05 20,534.00 20,534.00
As Submitted 1.00 l.s. 31,030.81 25% 7,757.70 1,939.43 9,697.13 40,727.94 40,727.94
1103(1) Lighting Fixtures and Lamps
As Evaluated 1.00 l.s. 31,030.81 25% 7,757.70 1,939.43 9,697.13 40,727.94 40,727.94
As Submitted 111,254.80 27,813.70 6,953.43 34,767.13 146,021.93
TOTAL OF PART D
As Evaluated 111,254.80 27,813.70 6,953.43 34,767.13 146,021.93
As Submitted 3,405,195.79 851,298.97 212,824.73 1,064,123.70 4,469,319.49
TOTAL OF PART III
As Evaluated 3,405,195.79 851,298.97 212,824.73 1,064,123.70 4,469,319.49
As Submitted 3,826,052.47 889,248.73 234,698.80 1,123,947.53 4,950,000.00
TOTAL OF (Project ID)
As Evaluated 3,826,052.47 889,248.73 234,698.80 1,123,947.53 4,950,000.00

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost

MARCO BRIAN L. BRITON FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Engineer II Chief, Planning & Design Section Chief, Construction Section

Date: November 17, 2020 Page 11 of 55


Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City FORM ABC-2015-02-00
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon

SUMMARY OF APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 150 CD
TOTAL MARK-UP
ITEM NO. DESCRIPTION ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST
% VALUE
As Evaluated 87,825.51 10.00% 8,782.55 4,830.40 13,612.95 101,438.46
PART I FACILITIES FOR THE ENGINEER
As Submitted 87,825.51 10.00% 8,782.55 4,830.40 13,612.95 101,438.46
As Evaluated 333,031.17 8.76% 29,167.21 17,043.67 46,210.88 379,242.05
PART II OTHER GENERAL REQUIREMENTS
As Submitted 333,031.17 8.76% 29,167.21 17,043.67 46,210.88 379,242.05
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING
PART III
WORKS
As Submitted 208,465.33 25.00% 52,116.34 13,029.08 65,145.42 273,610.75
PART A EARTHWORKS
As Evaluated 208,465.33 25.00% 52,116.34 13,029.08 65,145.42 273,610.75
As Submitted 1,110,036.23 25.00% 277,509.07 69,377.26 346,886.33 1,456,922.56
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Evaluated 1,110,036.23 25.00% 277,509.07 69,377.26 346,886.33 1,456,922.56
As Submitted 1,975,439.43 25.00% 493,859.86 123,464.96 617,324.82 2,592,764.25
PART C FINISHINGS AND OTHER CIVIL WORKS
As Evaluated 1,975,439.43 25.00% 493,859.86 123,464.96 617,324.82 2,592,764.25
As Submitted 111,254.80 25.00% 27,813.70 6,953.43 34,767.13 146,021.93
PART D ELECTRICAL WORKS
As Evaluated 111,254.80 25.00% 27,813.70 6,953.43 34,767.13 146,021.93
As Submitted 3,405,195.79 851,298.97 212,824.73 1,064,123.70 4,469,319.49
Total of Part III
As Evaluated 3,405,195.79 851,298.97 212,824.73 1,064,123.70 4,469,319.49
As Submitted 3,826,052.47 889,248.73 234,698.80 1,123,947.53 4,950,000.00
TOTAL OF (Project ID)
As Evaluated 3,826,052.47 889,248.73 234,698.80 1,123,947.53 4,950,000.00
As Submitted 3,826,052.47 889,248.73 234,698.80 1,123,947.53 4,950,000.00
TOTAL
As Evaluated 3,826,052.47 889,248.73 234,698.80 1,123,947.53 4,950,000.00

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Evaluated by: Recommending Approval: Approved:

MARCO BRIAN L. BRITON FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN WILFREDO L. RACELIS MA. CHYMBELIN D. IBAL
Engineer II Chief, Planning & Design Section Chief, Construction Section Engineer III Assistant District Engineer
OIC - Office of the Assistant District Engineer OIC - Office of the District Engineer

Date: November 17, 2020 12/55


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon
Candelaria, Quezon
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Plate Compactor ( 400-500 Gasoline Engine) 5 Hp 1 31
2 One Bagger Mixer 4-6 ft3/min 1 32
3 Bar Bender (25 mm Maximum Rebar Ø) Three Phase 1 33
4 Bar Cutter (25 mm Maximum Rebar Ø (Grade 40), Single Phase 1 34
5 Welding Machine (Electric Driven/DC Output) 500Amp 1 35
6 Cutting outfit 1 36
7 Self loading truck 1 37
8 Backhoe with breaker 1 38
9 Dump truck 2 39
10 40
11 41
12 42
13 43
14 44
15 45
16 46
17 47
18 48
19 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-TOTAL 10 SUB-TOTAL
TOTAL 10

13/13
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item no./Description : A.1.1(3) Construction of Field Office for the Engineer


Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of Amount
Designation No. of Hour/s Hourly Rate
Person
A.1 Labor

a. Construction Foreman 1 32.00 101.45 3,246.40


b. Skilled Laborers 3 32.00 73.29 7,035.84
c. Laborers 5 32.00 56.46 9,033.60

Sub - Total for A.1 - As Submitted 19,315.84


A.2 Labor

a. Construction Foreman 1 32.00 101.45 3,246.40


b. Skilled Laborers 3 32.00 73.29 7,035.84
c. Laborers 5 32.00 56.46 9,033.60

Sub - Total for A.2 - As Evaluated 19,315.84


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

Sub - Total for B.1 - As Submitted


B.2 Equipment

Sub - Total for B.2 - As Evaluated


C.1 Total (A.1 + B.1) - As Submitted 19,315.84
C.2 Total (A.2 + B.2) - As Evaluated 19,315.84
D.1 Output per hour - As Submitted = 1.00 l.s.
D.2 Output per hour - As Evaluated = 1.00 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 19,315.84
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 19,315.84
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. 1/4 x 4 x 8 Marine Plywood pc. 15.00 500.00 7,500.00


b. Coco Lumber bd.ft. 309.55 35.00 10,834.25
c. Corrugated Roofing, Gauge 26 sq.m. 13.00 255.00 3,315.00
d. 2" x 4" Door Hinges pc. 3.00 70.00 210.00
e. 2" x 3" Window Hinges pc. 8.00 41.00 328.00
f. Portland Cement bag 37.00 250.00 9,250.00
g. Gravel 3/4 cu.m. 3.00 1,262.33 3,787.00
h. Sand cu.m. 2.00 1,262.33 2,524.67
i. Reinforcing Steel Bars Grade 40 kg. 95.82 37.50 3,593.25
j. CHB Ordinary 4" pcs. 150.00 15.00 2,250.00
k. Fascia Board ( 1/2 x 12" Marine Plywood ) l.m. 8.40 93.75 787.50
l. Ridge Roll l.m. 4.20 100.00 420.00
m. 20Watts Flourescent LF set 1.00 255.00 255.00
n. Duplex Convenience Outlet set 2.00 130.00 260.00
o. One Gang Switch set 1.00 95.00 95.00
p. Panel Board & cabinet set 1.00 1,650.00 1,650.00
q. #16 G.I Tie Wires kgs. 2.00 80.00 160.00
r. Miscellaneous (CWN, Drainage & Electrical Works) lot 1.00 8,000.00 8,000.00

Sub - Total for F.1 - As Submitted 55,219.67


F.2 Materials

a. 1/4 x 4 x 8 Marine Plywood pc. 15.00 500.00 7500.00


b. Coco Lumber bd.ft. 309.55 35.00 10834.25
c. Corrugated Roofing, Gauge 26 sq.m. 13.00 255.00 3315.00
d. 2" x 4" Door Hinges pc. 3.00 70.00 210.00
e. 2" x 3" Window Hinges pc. 8.00 41.00 328.00
f. Portland Cement bag 37.00 250.00 9250.00
g. Gravel 3/4 cu.m. 3.00 1262.33 3787.00
h. Sand cu.m. 2.00 1262.33 2524.67
i. Reinforcing Steel Bars Grade 40 kg. 95.82 37.50 3593.25
j. CHB Ordinary 4" pcs. 150.00 15.00 2250.00
k. Fascia Board ( 1/2 x 12" Marine Plywood ) l.m. 8.40 93.75 787.50
l. Ridge Roll l.m. 4.20 100.00 420.00
m. 20Watts Flourescent LF set 1.00 255.00 255.00
n. Duplex Convenience Outlet set 2.00 130.00 260.00
o. One Gang Switch set 1.00 95.00 95.00
p. Panel Board & cabinet set 1.00 1650.00 1650.00
q. #16 G.I Tie Wires kgs. 2.00 80.00 160.00
r. Miscellaneous (CWN, Drainage & Electrical Works) lot 1.00 8000.00 8000.00

Sub - Total for F.2 - As Evaluated 55,219.67


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 74,535.51
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 74,535.51
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 7,453.55
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 7,453.55
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 4,099.45
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 4,099.45
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 86,088.51
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 86,088.51

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART I - Facilities for the Engineer


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item no./Description : A.1.1(11) Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the Engineer
Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor

Sub - Total for A.1 - As Submitted 0.00


A.2 Labor

Sub - Total for A.2 - As Evaluated 0.00


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

Sub - Total for B.1 - As Submitted


B.2 Equipment

Sub - Total for B.2 - As Evaluated


C.1 Total (A.1 + B.1) - As Submitted 0.00
C.2 Total (A.2 + B.2) - As Evaluated 0.00
D.1 Output per hour - As Submitted = 1.00 l.s.
D.2 Output per hour - As Evaluated = 1.00 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 0.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 0.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. Monoblock Table pc. 1.00 1600.00 1,600.00


b. Monoblock Chair pcs. 4.00 450.00 1,800.00
c. Bulletin/Cork Board pc. 2.00 320.00 640.00
d. Miscellaneous Office Supplies lot 1.00 7000.00 7,000.00

Sub - Total for F.1 - As Submitted 11,040.00


F.2 Materials

a. Monoblock Table pc. 1.00 1600.00 1600.00


b. Monoblock Chair pcs. 4.00 450.00 1800.00
c. Bulletin/Cork Board pc. 2.00 320.00 640.00
d. Miscellaneous Office Supplies lot 1.00 7000.00 7000.00

Sub - Total for F.2 - As Evaluated 11,040.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 11,040.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 11,040.00
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 1,104.00
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 1,104.00
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 607.20
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 607.20
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 12,751.20
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 12,751.20

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART I - Facilities for the Engineer


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item no./Description : A.1.4(1) Provision of Progress Photographs


Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor

Sub - Total for A.1 - As Submitted


A.2 Labor

Sub - Total for A.2 - As Evaluated


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

Sub - Total for B.1 - As Submitted


B.2 Equipment

Sub - Total for B.2 - As Submitted


C.1 Total (A.1 + B.1) - As Submitted 0.00
C.2 Total (A.2 + B.2) - As Evaluated 0.00
D.1 Output per hour - As Submitted = 1.00 each
D.2 Output per hour - As Evaluated = 1.00 each
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 0.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 0.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. Developing pc. 1.00 15.00 15.00

Sub - Total for F.1 - As Submitted 15.00


F.2 Materials

a. Developing pc. 1.00 15.00 15.00

Sub - Total for F.2 - As Evaluated 15.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 15.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 15.00
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 1.50
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 1.50
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 0.83
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 0.83
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 17.33
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 17.33

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART I - Facilities for the Engineer


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item no./Description : B.3 Permits and Clearances


Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

Designation No. of Person No. of Hour/s Hourly Rate Amount

A.1 Labor

a. Construction Foreman
b. Skilled Laborers
c. Laborers
Sub - Total for A.1 - As Submitted
A.2 Labor

a. Construction Foreman
b. Skilled Laborers
c. Laborers
Sub - Total for A.2 - As Evaluated

Name and Capacity No of Units No. of Hour/s Hourly Rate Amount


B.1 Equipment

Sub - Total for B.1 - As Submitted


B.2 Equipment

Sub - Total for B.2 - As Submitted


C.1 Total (A.1 + B.1) - As Submitted 0.00
C.2 Total (A.2 + B.2) - As Evaluated 0.00
D.1 Output per hour - As Submitted = 1.00 l.s.
D.2 Output per hour - As Evaluated = 1.00 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 0.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 0.00

Name and Specification Unit Quantity Unit Cost Amount


F.1 Materials

a. Fire Safety Evaluation Clearance Fee l.s. 1.00 14,700.00 14,700.00


b. Brgy. Clearance for construction fee l.s. 1.00 500.00 500.00
c. Professional fee l.s. 1.00 4500.00 4,500.00
d. Blue Print 20"x30" sheet 65.00 25.00 1,625.00

Sub - Total for F.1 - As Submitted 21,325.00


F.2 Materials

a. Fire Safety Evaluation Clearance Fee l.s. 1.00 14,700.00 14,700.00


b. Brgy. Clearance for construction fee l.s. 1.00 500.00 500.00
c. Professional fee l.s. 1.00 4,500.00 4,500.00
d. Blue Print 20"x30" sheet 65.00 25.00 1,625.00

Sub - Total for F.2 - As Evaluated 21,325.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 21,325.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 21,325.00
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 0% of G.1 0.00
I.2 Contractor's Profit (CP) - As Evaluated 0% of G.2 0.00
J.1 Value Added Tax (VAT) - As Submitted 0% of (G.1 + H.1 + I.1) 0.00
J.2 Value Added Tax (VAT) - As Evaluated 0% of (G.2 + H.2 + I.2) 0.00
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 21,325.00
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 21,325.00

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART II - Other General Requirements


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item no./Description : B.5 Project Billboard / Signboard


Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

Designation No. of Person No. of Hour/s Hourly Rate Amount

A.1 Labor

a. Construction Foreman 1 4.00 101.45 405.80


b. Skilled Laborers 1 4.00 73.29 293.16
c. Laborers 2 4.00 56.46 451.68
Sub - Total for A.1 - As Submitted 1,150.64
A.2 Labor

a. Construction Foreman 1 4.00 101.45 405.80


b. Skilled Laborers 1 4.00 73.29 293.16
c. Laborers 2 4.00 56.46 451.68
Sub - Total for A.2 - As Evaluated 1,150.64

Name and Capacity No of Units No. of Hour/s Hourly Rate Amount


B.1 Equipment

Sub - Total for B.1 - As Submitted


B.2 Equipment

Sub - Total for B.2 - As Submitted


C.1 Total (A.1 + B.1) - As Submitted 1,150.64
C.2 Total (A.2 + B.2) - As Evaluated 1,150.64
D.1 Output per hour - As Submitted = 1.00 each
D.2 Output per hour - As Evaluated = 1.00 each
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,150.64
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 1,150.64

Name and Specification Unit Quantity Unit Cost Amount


F.1 Materials

a. 1/2 x 4 x 8' marine plywood pc. 1.00 900.00 900.00


b. Good Lumber bd.ft. 41.00 60.00 2,460.00
c. Project Sign (Tarpaulin) sq.ft. 32.00 25.00 800.00
d. Miscelleaneous Items ( CWN ) lot 1 6000.00 6000.00

Sub - Total for F.1 - As Submitted 10160.00


F.2 Materials

a. 1/2 x 4 x 8' marine plywood pc. 1.00 900.00 900.00


b. Good Lumber bd.ft. 41.00 60.00 2460.00
c. Project Sign (Tarpaulin) sq.ft. 32.00 25.00 800.00
d. Miscelleaneous Items lot 1.00 6000.00 6000.00

Sub - Total for F.2 - As Evaluated 10160.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 11,310.64
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 11,310.64
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 1,696.60
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 1,696.60
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 1,131.06
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 1,131.06
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 706.92
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 706.92
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 14,845.22
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 14,845.22

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART II - Other General Requirements


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : B.7(2) Construction Safety and Health (PPE, Safety Personnel, Disinfection)
Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

Total Man-
Designation No. of Person/s Daily Rate Amount (Php)
days
A.1 Labor
a. Safety Practitioner/Officer (Full Time) 1 1200 62.50 75,000.00
b. Health Personnel (Full Time First Aider) 1 1200 35.00 42,000.00
c. Saniatation Aide 1 1200 35.00 42,000.00

Sub - Total for A.1 - As Submitted 159,000.00


A.2 Labor
a. Safety Practitioner/Officer (Full Time) 1 1200 62.50 75,000.00
b. Health Personnel (Full Time First Aider) 1 1200 35.00 42,000.00
c. Saniatation Aide 1 1200 35.00 42,000.00

Sub - Total for A.2 - As Evaluated 159,000.00


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)

B.1 Equipment

Rental Basis of the ff:

a. Portable Mist-Based Sanitation Tent 1 1200 9.79 11,753.42


b. Thermal Scanner (w/rechargeable battery) 1 1200 1.03 1,232.86
c. Power Sprayer w/ complete accessories 1 1200 3.47 4,166.67

Sub - Total for B.1 - As Submitted 17,152.95


B.2 Equipment

Rental Basis of the ff:

a. Portable Mist-Based Sanitation Tent 1 1200 9.79 11,753.42


b. Thermal Scanner (w/rechargeable battery) 1 1200 1.03 1,232.86
c. Power Sprayer w/ complete accessories 1 1200 3.47 4,166.67

Sub - Total for B.2 - As Evaluated 17,152.95


C.1 Total (A.1 + B.1) - As Submitted 176,152.95
C.2 Total (A.2 + B.2) - As Evaluated 176,152.95
D.1 Output per hour - As Submitted = 1.00 l.s. 1.00
D.2 Output per hour - As Evaluated = 1.00 l.s. 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 176,152.95
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 176,152.95
Name and Specification Unit Quantity Unit Cost Amount

F.1 Materials
Personal Protective Equipment
a. Safety Helmet man-days 944 0.34 323.28
b. Safety Shoes man-days 852 4.11 3,501.36
c. Safety Gloves man-days 944 7.67 7,237.34
d. Vest man-days 944 2.22 2,097.78
e. Rain Coats man-days 228 0.34 76.52
f. Dusk Mask man-days 944 10.00 9,440.00
g. Eye Goggles man-days 944 5.00 4,720.00
h. Ear Muff man-days 52 0.83 43.16
i. Body Harness and Lanyards man-days 80 3.21 256.80
j. Rubber Boots man-days 206 1.39 286.34

Antiseptics
a. Sanitizing Solution lit 110 100.00 11,000.00
b. Ethyl Alcohol lit 36 185.00 6,660.00
c. Disinfectant Spray can 18 1,000.00 18,000.00
d. Liquid Hand Soap lit 18 200.00 3,600.00

COVID-19 Rapid Antibody Test each 20 1,000.00 20,000.00

Sub - Total for F.1 - As Submitted 87,242.58

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART II - Other General Requirements


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : B.7(2) Construction Safety and Health (PPE, Safety Personnel, Disinfection)
Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

Name and Specification Unit Quantity Unit Cost Amount


F.2 Materials
Personal Protective Equipment
a. Safety Helmet man-days 944 0.34 323.28
b. Safety Shoes man-days 852 4.11 3,501.36
c. Safety Gloves man-days 944 7.67 7,237.34
d. Vest man-days 944 2.22 2,097.78
e. Rain Coats man-days 228 0.34 76.52
f. Dusk Mask man-days 944 10.00 9,440.00
g. Eye Goggles man-days 944 5.00 4,720.00
h. Ear Muff man-days 52 0.83 43.16
i. Body Harness and Lanyards man-days 80 3.21 256.80
j. Rubber Boots man-days 206 1.39 286.34
0.00
Antiseptics 0.00
a. Sanitizing Solution lit 110 100.00 11,000.00
b. Ethyl Alcohol lit 36 185.00 6,660.00
c. Disinfectant Spray can 18 1,000.00 18,000.00
d. Liquid Hand Soap lit 18 200.00 3,600.00

COVID-19 Rapid Antibody Test each 20 1,000.00 20,000.00

Sub - Total for F.2 - As Evaluated 87,242.58


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 263,395.53
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 263,395.53
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 26,339.55
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 26,339.55
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 14,486.75
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 14,486.75
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 304,221.83
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 304,221.83

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART II - Other General Requirements


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item no./Description : B.9 Mobilization / Demobilization


Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor

Sub - Total for A.1 - As Submitted


A.2 Labor

Sub - Total for A.2 - As Evaluated


Name and Capacity No of Units No. of Hour/s Hourly Rate Amount
B.1 Equipment

a. (Not Exceed 1% of E.D.C. ) as per D.O. 197 Series of 2016 l.s. 1 37,000.00 37,000.00
( Service Truck, Low Bed Trailer )

Sub - Total for B.1 - As Submitted 37,000.00


B.2 Equipment

a. (Not Exceed 1% of E.D.C. ) as per D.O. 197 Series of 2016 l.s. 1 37,000.00 37,000.00
( Service Truck, Low Bed Trailer )

Sub - Total for B.2 - As Submitted 37,000.00


C.1 Total (A.1 + B.1) - As Submitted 37,000.00
C.2 Total (A.2 + B.2) - As Evaluated 37,000.00
D.1 Output per hour - As Submitted = 1.00 l.s.
D.2 Output per hour - As Evaluated = 1.00 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 37,000.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 37,000.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

Sub - Total for F.1 - As Submitted


F.2 Materials

Sub - Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 37,000.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 37,000.00
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0 of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0 of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 0 of G.1 0.00
I.2 Contractor's Profit (CP) - As Evaluated 0 of G.2 0.00
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1,850.00
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 1,850.00
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 38,850.00
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 38,850.00

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART II - Other General Requirements


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 801(1) Removal of Structures and Obstruction


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A.1 Labor

a. Construction Foreman 1 30.00 101.45 3,043.50


c. Unskilled Laborer 4 30.00 56.46 6,775.20

Sub - Total for A.1 - As Submitted 9,818.70


A.2 Labor

a. Construction Foreman 1 30.00 101.45 3,043.50


c. Unskilled Laborer 4 30.00 56.46 6,775.20

Sub - Total for A.2 - As Evaluated 9,818.70


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B.1 Equipment

Backhoe with breaker 1 25.00 1,998.10 49,952.50


Dump Truck 2 25.00 1,420.00 71,000.00
Minor Tools (10% of Labor Cost) 981.87

Sub - Total for B.1 - As Submitted 121,934.37


B.2 Equipment

Backhoe with breaker 1 25.00 1,998.10 49,952.50


Dump Truck 2 25.00 1,420.00 71,000.00
Minor Tools (10% of Labor Cost) 981.87

Sub - Total for B.2 - As Evaluated 121,934.37


C.1 Total (A.1 + B.1) - As Submitted 131,753.07
C.2 Total (A.2 + B.2) - As Evaluated 131,753.07
D.1 Output per hour - As Submitted = 1.00 l.s.
D.2 Output per hour - As Evaluated = 1.00 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 131,753.07
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 131,753.07
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F.1 Materials

Sub - Total for F.1 - As Submitted


F.2 Materials

Sub - Total for F.2 - As Submitted


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 131,753.07
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 131,753.07
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 19,762.96
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 19,762.96
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 13,175.31
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 13,175.31
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 8,234.57
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 8,234.57
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 172,925.90
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 172,925.90
Note: 1. Additional labor and/or equipment may be added for disposal of surplus excavated material.

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

Part A - Earthworks
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 803(1)a Structure Excavation ( Common soil )


3
Unit of Measurement : m
Output per hour : 20.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A.1 - As Submitted 270.83


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A.2 - As Evaluated 270.83


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B.1 Equipment

Backhoe ( 0.80 cu.m. ) 1 1.00 1,537.00 1,537.00


Dump Truck ( 12 cu.yd. ) 2 1.00 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 27.08

Sub - Total for B.1 - As Submitted 4,404.08


B.2 Equipment

Backhoe ( 0.80 cu.m. ) 2 1.00 1,420.00 2,840.00


Dump Truck ( 12 cu.yd. ) 1 1.00 1,537.00 1,537.00
Minor Tools (10% of Labor Cost) 27.08

Sub - Total for B.2 - As Submitted 4,404.08


C.1 Total (A.1 + B.1) - As Submitted 4,674.91
C.2 Total (A.2 + B.2) - As Evaluated 4,674.91
D.1 Output per hour - As Submitted = 20.00 cu.m.
D.2 Output per hour - As Evaluated = 20.00 cu.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 233.75
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 233.75
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F.1 Materials

Sub - Total for F.1 - As Submitted


F.2 Materials

Sub - Total for F.2 - As Submitted


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 233.75
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 233.75
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 35.06
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 35.06
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 23.37
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 23.37
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 14.61
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 14.61
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 306.79
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 306.79
Note: 1. Additional labor and/or equipment may be added for dispossal of surplus excavated material.

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

Part A - Earthworks
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 804 (1)b Embankment ( From Borrow )


3
Unit of Measurement : m
Output per hour : 3.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A..1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A.1 - As Submitted 417.41


A..2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A.2 - As Evaluated 417.41


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B.1 Equipment

a. Plate Compactor 1 0.50 123.00 61.50


Minor Tools (10% of Labor Cost) 41.74

Sub - Total for B.1 - As Submitted 103.24


B.2 Equipment

a. Plate Compactor 1 0.50 123.00 61.50


Minor Tools (10% of Labor Cost) 41.74

Sub - Total for B.2 - As Evaluated 103.24


C.1 Total (A.1 + B.1) - As Submitted 520.65
C.2 Total (A.2 + B.2) - As Evaluated 520.65
D.1 Output per hour - As Submitted = 3.00 cu.m.
D.2 Output per hour - As Evaluated = 3.00 cu.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 173.55
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 173.55
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F.1 Materials

a. Embankment Materials m3 1.25 180.33 225.42


(w/ 25% Shrinkage Factor)

Sub - Total for B.1 - As Submitted 225.42


F.2 Materials

a. Embankment Materials m3 1.25 180.33 225.42


(w/ 25% Shrinkage Factor)

Sub - Total for B.2 - As Evaluated 225.42


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 398.97
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 398.97
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 59.85
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 59.85
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 39.90
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 39.90
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 24.94
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 24.94
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 523.64
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 523.64

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

Part A - Earthworks
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 900(1)c1 Structural Concrete (Class A, 28 days)


3
Unit of Measurement : m
Output per hour : 0.27

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
b. Unskilled Laborer 4 1.00 56.46 225.84

Sub - Total for A.1 - As Submitted 473.87


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
b. Unskilled Laborer 4 1.00 56.46 225.84

Sub - Total for A.2 - As Evaluated 473.87


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B.1 Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


Minor Tools (10% of Labor Cost) 47.39

Sub - Total for B.1 - As Submitted 219.39


B.1 Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


Minor Tools (10% of Labor Cost) 47.39

Sub - Total for B.2 - As Evaluated 219.39


C.1 Total (A.1 + B.1) - As Submitted 693.26
C.2 Total (A.2 + B.2) - As Evaluated 693.26
D.1 Output per hour - As Submitted
= 0.27 cu.m.
D.2 Output per hour - As Evaluated
= 0.27 cu.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 2,567.62
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 2,567.62
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F.1 Materials

3
a. Gravel m 1.00 1,262.33 1262.33
b. Sand m3 0.50 1,262.33 631.17
c. Portland Cement bags 9.00 250.00 2,250.00

Sub - Total for F.1 - As Submitted 4,143.50


F.2 Materials

a. Gravel m3 1.00 1,262.33 1262.33


b. Sand m3 0.50 1,262.33 631.17
c. Portland Cement bags 9.00 250.00 2,250.00

Sub - Total for F.2 - As Submitted 4,143.50


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,711.12
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 6,711.12
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 1,006.67
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 1,006.67
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 671.11
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 671.11
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 419.44
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 419.44
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 8,808.34
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 8,808.34

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART B - Plain and Reinforced Concrete Works


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 902(1)a Reinforcing Steel (Deformed) Grade 40


Unit of Measurement : kg
Output per hour : 143.44 kg

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 3 1.00 73.29 219.87
c. Unskilled Laborer 12 1.00 56.46 677.52

Sub - Total for A.1 - As Submitted 998.84


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 3 1.00 73.29 219.87
c. Unskilled Laborer 12 1.00 56.46 677.52

Sub - Total for A.2 - As Evaluated 998.84


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor Cost) 99.88

Sub - Total for B.1 - As Submitted 385.51


B.2 Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor Cost) 99.88

Sub - Total for B.2 - As Evaluated 385.51


C.1 Total (A.1 + B.1) - As Submitted 1,384.35
C.2 Total (A.2 + B.2) - As Evaluated 1,384.35
D.1 Output per hour - As Submitted = 143.44 kg
D.2 Output per hour - As Evaluated = 143.44 kg
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 9.65
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 9.65
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. Deformed Reinforcing Steel kg 1.00 37.50 37.50


b. #16 Galvanized Iron Wire kg 0.015 80.00 1.20
c. Consumables (5% of Materials Cost) 1.94

Sub - Total for F.1 - As Submitted 40.64


F.2 Materials

a. Deformed Reinforcing Steel kg 1.00 37.50 37.50


b. #16 Galvanized Iron Wire kg 0.015 80.00 1.20
c. Consumables (5% of Materials Cost) 1.94

Sub - Total for F.2 - As Evaluated 40.64


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 50.29
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 50.29
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 7.54
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 7.54
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 5.03
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 5.03
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 3.14
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 3.14
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 66.00
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 66.00

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART B - Plain and Reinforced Concrete Works


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 902(1)b Reinforcing Steel (Deformed) Grade 60


Unit of Measurement : kg
Output per hour : 143.44 kg

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 3 1.00 73.29 219.87
c. Unskilled Laborer 12 1.00 56.46 677.52

Sub - Total for A.1 - As Submitted 998.84


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 3 1.00 73.29 219.87
c. Unskilled Laborer 12 1.00 56.46 677.52

Sub - Total for A.2 - As Evaluated 998.84


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor Cost) 99.88

Sub - Total for B.1 - As Submitted 385.51


B.2 Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor Cost) 99.88

Sub - Total for B.2 - As Evaluated 385.51


C.1 Total (A.1 + B.1) - As Submitted 1,384.35
C.2 Total (A.2 + B.2) - As Evaluated 1,384.35
D.1 Output per hour - As Submitted = 143.44 kg
D.2 Output per hour - As Evaluated = 143.44 kg
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 9.65
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 9.65
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. Deformed Reinforcing Steel kg 1.00 38.53 38.53


b. #16 Galvanized Iron Wire kg 0.015 80.00 1.20
c. Consumables (5% of Materials Cost) 1.99

Sub - Total for F.1 - As Submitted 41.72


F.2 Materials

a. Deformed Reinforcing Steel kg 1.00 38.53 38.53


b. #16 Galvanized Iron Wire kg 0.015 80.00 1.20
c. Consumables (5% of Materials Cost) 1.99

Sub - Total for F.2 - As Evaluated 41.72


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 51.37
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 51.37
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 7.71
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 7.71
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 5.14
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 5.14
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 3.21
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 3.21
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 67.42
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 67.42

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART B - Plain and Reinforced Concrete Works


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 903(2) Formworks and Falseworks


2
Unit of Measurement : m
Output per hour : 3.24

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor
Installation
a. Construction Foreman 1 1.00 101.45 101.45
b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 4 1.00 56.46 225.84
Stripping
a. Construction Foreman 1 0.41 101.45 41.09
b. Unskilled Laborer 6 0.41 56.46 137.20

Sub - Total for A.1 - As Submitted 652.16


A.2 Labor
Installation
a. Construction Foreman 1 1.00 101.45 101.45
b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 4 1.00 56.46 225.84
Stripping
a. Construction Foreman 1 0.41 101.45 41.09
b. Unskilled Laborer 6 0.41 56.46 137.20

Sub - Total for A.2 - As Evaluated 652.16


Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)
B.1 Equipment

Minor Tools (10 % of Labor Cost) 65.22

Sub - Total for A.1 - As Submitted 65.22


B.2 Equipment

Minor Tools (10 % of Labor Cost) 65.22

Sub - Total for B.2 - As Evaluated 65.22


C.1 Total (A.1 + B.1) - As Submitted 717.37
C.2 Total (A.2 + B.2) - As Evaluated 717.37
D.1 Output per hour - As Submitted = 3.24 cu.m.
D.2 Output per hour - As Evaluated = 3.24 cu.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 221.41
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 221.41
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. Ordinary Plywood - 3 uses pcs 0.347 700.00 80.97


b. Good Lumber - 3 uses bd ft 7.190 60.00 431.40
c. Assorted Common Wire Nails kg 0.21 80.00 16.64
d. Consumables (5% of Materials Cost) 26.45

Sub - Total for F.1 - As Submitted 555.46


F.2 Materials

a. Ordinary Plywood - 3 uses pcs 0.347 700.00 80.97


b. Good Lumber - 3 uses bd ft 7.190 60.00 431.40
c. Assorted Common Wire Nails kg 0.208 80.00 16.64
d. Consumables (5% of Materials Cost) 26.45

Sub - Total for F.2 - As Evaluated 555.46


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 776.87
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 776.87
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 116.53
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 116.53
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 77.69
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 77.69
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 48.55
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 48.55
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,019.64
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 1,019.64

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART B - Plain and Reinforced Concrete Works


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm
2
Unit of Measurement : m
Output per hour : 3.825

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A.1 - As Submitted 417.41


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A.2 - As Evaluated 417.41


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B.1 Equipment

a. One-bagger mixer 1.00 1.00 172.00 172.00


Minor Tools (10% of Labor Cost) 41.74

Sub - Total for B.1 - As Submitted 213.74


B.2 Equipment

a. One-bagger mixer 1.00 1.00 172.00 172.00


Minor Tools (10% of Labor Cost) 41.74

Sub - Total for B.2 - As Evaluated 213.74


C.1 Total (A.1 + B.1) - As Submitted 631.15
C.2 Total (A.2 + B.2) - As Evaluated 631.15
D.1 Output per hour - As Submitted = 3.825 sq.m.
D.2 Output per hour - As Evaluated = 3.825 sq.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 165.01
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 165.01
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F.1 Materials

a. 100 mm thk CHB (Non-Load Bearing) pc 13.00 15.00 195.00


b. Cement bag 0.53 250.00 131.25
c. Sand cu.m 0.04 1,262.33 55.54
d. Reinforcing Steel kg 3.24 37.50 121.50
e. #16 Tie wire kg 0.05 80.00 4.00

Sub - Total for F.1 - As Submitted 507.29


F.2 Materials

a. 100 mm thk CHB (Non-Load Bearing) pc 13.00 15.00 195.00


b. Cement bag 0.53 250.00 131.25
c. Sand cu.m 0.04 1,262.33 55.54
d. Reinforcing Steel kg 3.24 37.50 121.50
e. #16 Tie wire kg 0.05 80.00 4.00

Sub - Total for F.2 - As Evaluated 507.29


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 672.30
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 672.30
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 100.84
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 100.84
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 67.23
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 67.23
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 42.02
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 42.02
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 882.39
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 882.39

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm
2
Unit of Measurement : m
Output per hour : 3.18

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A.1 - As Submitted 417.41


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A.2 - As Evaluated 417.41


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B.1 Equipment

a. One-bagger mixer 1 1.00 172.00 172.00


Minor Tools (10% of Labor Cost) 41.74

Sub - Total for B.1 - As Submitted 213.74


B.2 Equipment

a. One-bagger mixer 1 1.00 172.00 172.00


Minor Tools (10% of Labor Cost) 41.74

Sub - Total for B.2 - As Evaluated 213.74


C.1 Total (A.1 + B.1) - As Submitted 631.15
C.2 Total (A.2 + B.2) - As Evaluated 631.15
D.1 Output per hour - As Submitted = 3.18 sq.m.
D.2 Output per hour - As Evaluated = 3.18 sq.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 198.48
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 198.48
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F.1 Materials

a. 150 mm thk CHB (Non load Bearing) pc 13.00 18.00 234.00


b. Cement bag 1.500 250.00 375.00
c. Sand cu.m 0.04 1262.33 55.54
d. Reinforcing Steel kg 3.24 37.50 121.50
e. #16 Tie wire kg 0.05 80.00 4.00

Sub - Total for F.1 - As Submitted 790.04


F.2 Materials

a. 150 mm thk CHB (Non load Bearing) pc 13.00 18.00 234.00


b. Cement bag 1.50 250.00 375.00
c. Sand cu.m 0.04 1262.33 55.54
d. Reinforcing Steel kg 3.24 37.50 121.50
e. #16 Tie wire kg 0.05 80.00 4.00

Sub - Total for F.2 - As Submitted 790.04


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 988.52
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 988.52
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 148.28
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 148.28
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 98.85
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 98.85
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 61.78
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 61.78
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,297.43
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 1,297.43

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1021(1)a Cement Floor Finish ( Plain )


2
Unit of Measurement : m
Output per hour : 5.95

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A.1 - As Submitted 344.12


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A.2 - As Evaluated 344.12


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B.1 Equipment

Power Throwel 1 1.00 310.00 310.00


Minor Tools (10% of Labor Cost) 34.41

Sub - Total for B.1 - As Submitted 344.41


B.2 Equipment

Power Throwel 1 1.00 310.00 310.00


Minor Tools (10% of Labor Cost) 34.41

Sub - Total for B.2 - As Evaluated 344.41


C.1 Total (A.1 + B.1) - As Submitted 688.53
C.2 Total (A.2 + B.2) - As Evaluated 688.53
D.1 Output per hour - As Submitted = 5.95 sq.m.
D.2 Output per hour - As Evaluated = 5.95 sq.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 115.72
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 115.72
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F.1 Materials

Sub - Total for F.1 - As Submitted 0.00


F.2 Materials

Sub - Total for F.2 - As Evaluated 0.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 115.72
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 115.72
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 17.36
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 17.36
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 11.57
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 11.57
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 7.23
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 7.23
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 151.88
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 151.88

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1027(1) Cement Plaster Finish


Unit of Measurement : m2
Output per hour : 7.125

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 4 1.00 56.46 225.84

Sub - Total for A.1 - As Submitted 473.87


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 4 1.00 56.46 225.84

Sub - Total for A.2 - As Evaluated 473.87


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

Minor Tools (10% of Labor Cost) 47.39

Sub - Total for B.1 - As Submitted 47.39


B.2 Equipment

Minor Tools (10% of Labor Cost) 47.39

Sub - Total for B.2 - As Evaluated 47.39


C.1 Total (A.1 + B.1) - As Submitted 521.26
C.2 Total (A.2 + B.2) - As Evaluated 521.26
D.1 Output per hour - As Submitted
= 7.125 sq.m.
D.2 Output per hour - As Evaluated
= 7.125 sq.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 73.16
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 73.16
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. Cement bag 0.330 250.00 82.50


b. Sand cu.m 0.027 1,262.33 33.45

Sub - Total for F.1 - As Submitted 115.95


F.2 Materials

a. Cement bag 0.330 250.00 82.50


b. Sand cu.m 0.027 1,262.33 33.45

Sub - Total for F.2 - As Evaluated 115.95


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 189.11
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 189.11
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 28.37
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 28.37
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 18.91
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 18.91
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 11.82
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 11.82
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 248.21
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 248.21

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1032(1)a Painting Works (Masonry/Concrete)


2
Unit of Measurement : m
Output per hour : 2.1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.1 - As Submitted 304.49


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.2 - As Evaluated 304.49


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

Minor Tools (10% of Labor Cost) 30.45

Sub - Total for B.1 - As Submitted 30.45


B.2 Equipment

Minor Tools (10% of Labor Cost) 30.45

Sub - Total for B.2 - As Evaluated 30.45


C.1 Total (A.1 + B.1) - As Submitted 334.94
C.2 Total (A.2 + B.2) - As Evaluated 334.94
D.1 Output per hour - As Submitted
= 2.1 sq.m.
D.2 Output per hour - As Evaluated
= 2.1 sq.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 159.49
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 159.49
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. Concrete Neutralizer l 0.02 135.00 2.70


b. Concrete Sealer/Primer gal 0.04 490.00 19.60
c. Patching Compound gal 0.05 550.00 27.50
d. Semi Gloss Latex (two coats) gal 0.08 630.00 50.40
e. Consumables (5% of Materials Cost) 5.01

Sub - Total for F.1 - As Submitted 105.21


F.1 Materials

a. Concrete Neutralizer l 0.02 135.00 2.70


b. Concrete Sealer/Primer gal 0.04 490.00 19.60
c. Patching Compound gal 0.05 550.00 27.50
d. Semi Gloss Latex (two coats) gal 0.08 630.00 50.40
e. Consumables (5% of Materials Cost) 5.01

Sub - Total for F.2 - As Evaluated 105.21


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 264.70
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 264.70
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 39.71
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 39.71
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 26.47
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 26.47
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 16.54
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 16.54
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 347.43
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 347.43

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1032 (5) Textured Finish


2
Unit of Measurement : m
Output per hour : 2.1

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.1 - As Submitted 304.49


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.2 - As Evaluated 304.49


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

Minor Tools (10% of Labor Cost) 30.45

Sub - Total for B.1 - As Submitted 30.45


B.2 Equipment

Minor Tools (10% of Labor Cost) 30.45

Sub - Total for B.2 - As Evaluated 30.45


C.1 Total (A.1 + B.1) - As Submitted 334.94
C.2 Total (A.2 + B.2) - As Evaluated 334.94
D.1 Output per hour - As Submitted
= 2.1 sq.m.
D.2 Output per hour - As Evaluated
= 2.1 sq.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 159.49
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 159.49
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. Rubberized floor paint gal 0.18 1,200.00 216.00


b. Consumables (5% of Materials Cost) 10.80

Sub - Total for F.1 - As Submitted 226.80


F.1 Materials

a. Rubberized floor paint gal 0.18 1,200.00 216.00


b. Consumables (5% of Materials Cost) 10.80

Sub - Total for F.2 - As Evaluated 226.80


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 386.29
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 386.29
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 57.94
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 57.94
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 38.63
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 38.63
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 24.14
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 24.14
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 507.01
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 507.01

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1032(1)c Painting Works (Steel)


2
Unit of Measurement : m
Output per hour : 2.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.1 - As Submitted 304.49


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.2 - As Evaluated 304.49


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B.1 Equipment

Minor Tools (10% of Labor Cost) 30.45

Sub - Total for B.1 - As Submitted 30.45


B.2 Equipment

Minor Tools (10% of Labor Cost) 30.45

Sub - Total for B.2 - As Evaluated 30.45


C.1 Total (A.1 + B.1) - As Submitted 334.94
C.2 Total (A.2 + B.2) - As Evaluated 334.94
D.1 Output per hour - As Submitted
= 2.00 sq.m.
D.2 Output per hour - As Evaluated
= 2.00 sq.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 167.47
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 167.47
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F.1 Materials

a. Red Oxide Primer gal 0.04 490.00 19.60


b. Enamel Paint gal 0.10 600.00 60.00
c. Paint thinner L 0.04 280.00 11.20
d. Tinting Color (Optional) pint 0.01 270.00 2.70
e. Consumables (5% of Materials Cost) 4.68

Sub - Total for F.1 - As Submitted 98.18


F.2 Materials

a. Red Oxide Primer gal 0.04 490.00 19.60


b. Enamel Paint gal 0.10 600.00 60.00
c. Paint thinner L 0.04 280.00 11.20
d. Tinting Color (Optional) pint 0.01 270.00 2.70
e. Consumables (5% of Materials Cost) 4.68

Sub - Total for F.2 - As Evaluated 98.18


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 265.64
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 265.64
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 39.85
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 39.85
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 26.56
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 26.56
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 16.60
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 16.60
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 348.66
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 348.66

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1014 (1) b2 Prepainted Metal Sheets (above 0.427mm) Rib Type Long Span
2
Unit of Measurement : m
Output per hour : 2.076

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 2 1.00 56.46 112.92

Sub - Total for A.1 - As Submitted 287.66


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 2 1.00 56.46 112.92

Sub - Total for A.2 - As Evaluated 287.66


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

Minor Tools (10% of Labor Cost) 28.77

Sub - Total for B.1 - As Submitted 28.77


B.2 Equipment

Minor Tools (10% of Labor Cost) 28.77

Sub - Total for B.1 - As Evaluated 28.77


C.1 Total (A.1 + B.1) - As Submitted 316.43
C.2 Total (A.2 + B.2) - As Evaluated 316.43
D.1 Output per hour - As Submitted = 2.076 sq.m.
D.2 Output per hour - As Evaluated = 2.076 sq.m.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 152.42
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 152.42
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. Curva type color roof, ga. 26x0.915m m2 1.05 370.00 388.50


b. Tekscrew pcs 10 6.00 60.00
c. Consumables (3% of Materials Cost) 13.46

Sub - Total for F.1 - As Submitted 461.96


F.2 Materials

a. Curva type color roof, ga. 26x0.915m m2 1.05 370.00 388.50


b. Tekscrew pcs 10 6.00 60.00
c. Consumables (3% of Materials Cost) 13.46

Sub - Total for F.2 - As Evaluated 461.96


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 614.38
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 614.38
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 92.16
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 92.16
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 61.44
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 61.44
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 38.40
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 38.40
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 806.37
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 806.37

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1047 (1) Structural Steel


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

Fabrication
a. Construction Foreman 1 112.00 101.45 11,362.40
b. Skilled Laborer 2 112.00 73.29 16,416.96
c. Unskilled Laborer 2 112.00 56.46 12,647.04
Erection
a. Skilled Laborer 2 112.00 73.29 16,416.96
b. Unskilled Laborer 2 112.00 56.46 12,647.04

Sub - Total for A.1 - As Submitted 69,490.40


A.2 Labor

Fabrication
a. Construction Foreman 1 112.00 101.45 11362.40
b. Skilled Laborer 2 112.00 73.29 16416.96
c. Unskilled Laborer 2 112.00 56.46 12647.04
Erection
a. Skilled Laborer 2 112.00 73.29 16416.96
b. Unskilled Laborer 2 112.00 56.46 12647.04

Sub - Total for A.2 - As Evaluated 69,490.40


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

a. Welding Machine 1 56.00 391.00 21,896.00


b. Cutting Outfit 1 56.00 45.45 2,545.20
Minor Tools (10 % of Labor Cost) 6,949.04

Sub - Total for B.1 - As Submitted 31,390.24


B.2 Equipment

a. Welding Machine 1 56.00 391.00 21,896.00


b. Cutting Outfit 1 56.00 45.45 2,545.20
Minor Tools (10 % of Labor Cost) 6,949.04

Sub - Total for B.2 - As Evaluated 31,390.24


C.1 Total (A.1 + B.1) - As Submitted 100,880.64
C.2 Total (A.2 + B.2) - As Evaluated 100,880.64
D.1 Output per hour - As Submitted = 1.00 l.s.
D.2 Output per hour - As Evaluated = 1.00 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 100,880.64
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 100,880.64
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials
Side Cover (Court)
100x50x15x1.5mm C-Purlins kg 665.55 60.00 39,933.00
Prepainted Metal Sheet, Ga. 26, Rib Type sq.m. 111.00 295.00 32,745.00
Teckscrew pc. 1,101.00 3.00 3,303.00
Goal
G.I. Pipe 4" Sch. 40 kg 289.80 60.00 17388.00
G.I. Pipe 2" Sch. 40 kg 68.88 60.00 4132.80
ANGLE BAR 2"x2"x4.5mm kg 80.88 60.00 4852.80
ANGLE BAR 1.5"x1.5"x4.5mm kg 59.76 60.00 3585.60
FRP Baketball Goal and Ring sets 2.00 20,000.00 40000.00
Miscellanoues, Paints, Wheels, Padding lot 1.000 15,000.00 15000.00
Consumables (5% of Materials Cost) 4247.96

Sub - Total for F.1 - As Submitted 165,188.16


F.2 Materials
Side Cover (Court) kg 665.55 60.00 39933.00
100x50x15x1.5mm C-Purlins sq.m. 111.00 295.00 32745.00
Prepainted Metal Sheet, Ga. 26, Rib Type pc. 1101.00 3.00 3303.00
Teckscrew
Goal kg 289.80 60.00 17388.00
G.I. Pipe 4" Sch. 40 kg 68.88 60.00 4132.80
G.I. Pipe 2" Sch. 40 kg 80.88 60.00 4852.80
ANGLE BAR 2"x2"x4.5mm kg 59.76 60.00 3585.60
ANGLE BAR 1.5"x1.5"x4.5mm sets 2.00 20000.00 40000.00
FRP Baketball Goal and Ring lot 1.00 15000.00 15000.00
Miscellanoues, Paints, Wheels, Padding 4247.96
Consumables (5% of Materials Cost)

Sub - Total for F.1 - As Submitted 165,188.16


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 266,068.80
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 266,068.80
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 39,910.32
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 39,910.32
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 26,606.88
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 26,606.88
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 16,629.30
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 16,629.30
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 349,215.30
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 349,215.30

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1047(2)a Structural Steel (Trusses)


Unit of Measurement : kg
Output per hour : 85.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

Fabrication
a. Construction Foreman 1 1.00 101.45 101.45
b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 2 1.00 56.46 112.92
Erection
a. Skilled Laborer 3 0.50 73.29 109.94
b. Unskilled Laborer 3 0.50 56.46 84.69

Sub - Total for A.1 - As Submitted 555.58


A.2 Labor

Fabrication
a. Construction Foreman 1 1.00 101.45 101.45
b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 2 1.00 56.46 112.92
Erection
a. Skilled Laborer 3 0.50 73.29 109.94
b. Unskilled Laborer 3 0.50 56.46 84.69

Sub - Total for A.2 - As Evaluated 555.58


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

a. Welding Machine 1 0.75 391.00 293.25


b. Cutting Outfit 1 0.25 45.45 11.36
Minor Tools (10 % of Labor Cost) 55.56

Sub - Total for B.1 - As Submitted 360.17


B.2 Equipment

a. Welding Machine 1 0.75 391.00 293.25


b. Cutting Outfit 1 0.25 45.45 11.36
Minor Tools (10 % of Labor Cost) 55.56

Sub - Total for B.2 - As Evaluated 360.17


C.1 Total (A.1 + B.1) - As Submitted 915.75
C.2 Total (A.2 + B.2) - As Evaluated 915.75
D.1 Output per hour - As Submitted = 85.00 kg
D.2 Output per hour - As Evaluated = 85.00 kg
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 10.77
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 10.77
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials
a. Structural Steel Truss kg 1.00 60.00 60.00
b. Acetylene kg 0.011 65.00 0.72
c. Oxygen kg 0.022 50.00 1.10
d. Welding Rod kg 0.020 110.00 2.20
e. Consumables (5% of Materials Cost) 3.20

Sub - Total for F.1 - As Submitted 67.22


F.2 Materials
a. Structural Steel Truss kg 1.00 60.00 60.00
b. Acetylene kg 0.01 65.00 0.72
c. Oxygen kg 0.02 50.00 1.10
d. Welding Rod kg 0.02 110.00 2.20
e. Consumables (5% of Materials Cost) 3.20

Sub - Total for F.2 - As Evaluated 67.22


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 77.99
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 77.99
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 11.70
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 11.70
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 7.80
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 7.80
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 4.87
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 4.87
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 102.36
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 102.36

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1047(2)b Structural Steel (Purlins)


Unit of Measurement : kg
Output per hour : 90.45

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 3 1.00 73.29 219.87
c. Unskilled Laborer 5 1.00 56.46 282.30

Sub - Total for A.1 - As Submitted 603.62


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 3 1.00 73.29 219.87
c. Unskilled Laborer 5 1.00 56.46 282.30

Sub - Total for A.2 - As Evaluated 603.62


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

a. Welding Machine 2 1.00 391.00 782.00


Minor Tools (10% of Labor Cost) 60.36

Sub - Total for B.1 - As Submitted 842.36


B.2 Equipment

a. Welding Machine 2 1.00 391.00 782.00


Minor Tools (10% of Labor Cost) 60.36

Sub - Total for B.2 - As Evaluated 842.36


C.1 Total (A.1 + B.1) - As Submitted 1,445.98
C.2 Total (A.2 + B.2) - As Evaluated 1,445.98
D.1 Output per hour - As Submitted = 90.45 kg
D.2 Output per hour - As Evaluated = 90.45 kg
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 15.99
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 15.99
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. Structural Steel Purlins kg 1.05 50.00 52.50


b. Consumables (5% of Materials Cost) 2.63

Sub - Total for F.1 - As Submitted 55.13


F.2 Materials

a. Structural Steel Purlins kg 1.05 50.00 52.50


b. Consumables (5% of Materials Cost) 2.63

Sub - Total for F.2 - As Submitted 55.13


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 71.11
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 71.11
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 10.67
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 10.67
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 7.11
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 7.11
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 4.44
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 4.44
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 93.33
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 93.33

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1047(3)a Metal Structure Accessories (Bolts)


Unit of Measurement : each
Output per hour : 7.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.1 - As Submitted 231.20


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.2 - As Evaluated 231.20


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for A.1 - As Submitted 23.12


B.2 Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for A.2 - As Evaluated 23.12


C.1 Total (A.1 + B.1) - As Submitted 254.32
C.2 Total (A.2 + B.2) - As Evaluated 254.32
D.1 Output per hour - As Submitted
= 7.00 each
D.2 Output per hour - As Evaluated
= 7.00 each
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 36.33
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 36.33
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. Bolts pc 1.00 105.00 105.00

Sub - Total for F.1 - As Submitted 105.00


F.2 Materials

a. Bolts pc 1.00 105.00 105.00

Sub - Total for F.2 - As Evaluated 105.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 141.33
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 141.33
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 21.20
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 21.20
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 14.13
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 14.13
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 8.83
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 8.83
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 185.50
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 185.50

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1047(6) Metal Structure Accessories (Steel Plates)


Unit of Measurement : kg
Output per hour : 12.995

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.1 - As Submitted 231.20


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.2 - As Evaluated 231.20


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B.1 - As Submitted 23.12


B.1 Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B.2 - As Evaluated 23.12


C.1 Total (A.1 + B.1) - As Submitted 254.32
C.2 Total (A.2 + B.2) - As Evaluated 254.32
D.1 Output per hour - As Submitted = 12.995 kg
D.2 Output per hour - As Evaluated = 12.995 kg
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 19.57
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 19.57
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. Steel Plates kg 1.05 60.00 63.00


b. Consumables (3% of Materials Cost) 1.89

Sub - Total for F.1 - As Submitted 64.89


F.2 Materials

a. Steel Plates kg 1.05 60.00 63.00


b. Consumables (3% of Materials Cost) 1.89

Sub - Total for F.2 - As Evaluated 64.89


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 84.46
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 84.46
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 12.67
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 12.67
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 8.45
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 8.45
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 5.28
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 5.28
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 110.85
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 110.85

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1047(7)b Metal Structure Accessories (Sag Rods)


Unit of Measurement : kg
Output per hour : 12.995

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.1 - As Submitted 231.20


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.2 - As Evaluated 231.20


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B.1 - As Submitted 23.12


B.1 Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B.2 - As Evaluated 23.12


C.1 Total (A.1 + B.1) - As Submitted 254.32
C.2 Total (A.2 + B.2) - As Evaluated 254.32
D.1 Output per hour - As Submitted = 12.995 kg
D.2 Output per hour - As Evaluated = 12.995 kg
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 19.57
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 19.57
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. 12mm dia x 6m-sag rod kg 1.05 37.88 39.77

Sub - Total for F.1 - As Submitted 39.77


F.2 Materials

a. 12mm dia x 6m-sag rod kg 1.05 37.88 39.77

Sub - Total for F.2 - As Evaluated 39.77


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 59.34
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 59.34
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 8.90
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 8.90
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 5.93
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 5.93
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 3.71
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 3.71
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 77.89
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 77.89

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1047(4) Metal Structure Accessories (Cross Bracing)


Unit of Measurement : kg
Output : 12.995

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.1 - As Submitted 231.20


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.2 - As Evaluated 231.20


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B.1 - As Submitted 23.12


B.2 Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B.2 - As Evaluated 23.12


C.1 Total (A.1 + B.1) - As Submitted 254.32
C.2 Total (A.2 + B.2) - As Evaluated 254.32
D.1 Output per hour - As Submitted
= 12.995 kg
D.2 Output per hour - As Evaluated
= 12.995 kg
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 19.57
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 19.57
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. 16mmx12m Plain rod-cross bracing kg 1.05 37.88 39.77


b. Consumables (3% of Materials Cost) 1.19

Sub - Total for F.1 - As Submitted 40.97


F.2 Materials

a. 16mmx12m Plain rod-cross bracing kg 1.05 37.88 39.77


b. Consumables (3% of Materials Cost) 1.19

Sub - Total for F.2 - As Evaluated 40.97


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 60.54
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 60.54
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 9.08
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 9.08
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 6.05
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 6.05
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 3.78
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 3.78
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 79.46
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 79.46

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1047(3)c Metal Structure Accessories (Turn Buckle)


Unit of Measurement : each
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.1 - As Submitted 231.20


A.2 Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A.2 - As Evaluated 231.20


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B.1 - As Submitted 23.12


B.2 Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B.2 - As Evaluated 23.12


C.1 Total (A.1 + B.1) - As Submitted 254.32
C.2 Total (A.2 + B.2) - As Evaluated 254.32
D.1 Output per hour - As Submitted
= 1.00 each
D.2 Output per hour - As Evaluated
= 1.00 each
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 254.32
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 254.32
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. 16mm Ø turn buckles pc. 1.00 200.00 200.00


b. Consumables (3% of Materials Cost) 6.00

Sub - Total for F.1 - As Submitted 206.00


F.2 Materials

a. 16mm Ø turn buckles pc. 1.00 200.00 200.00


b. Consumables (3% of Materials Cost) 6.00

Sub - Total for F.2 - As Evaluated 206.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 460.32
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 460.32
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 69.05
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 69.05
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 46.03
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 46.03
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 28.77
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 28.77
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 604.17
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 604.17

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART C - Finishing
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1100(10) Conduits, Boxes & Fittings (Conduit Works/ConduitRough-in)


Unit of Measurement : l.s
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 24.00 101.45 2,434.80


b. Skilled Laborer 1 24.00 73.29 1,758.96
c. Unskilled Laborer 1 24.00 56.46 1,355.04

Sub - Total for A.1 - As Submitted 5,548.80


A.2 Labor

a. Construction Foreman 1 24.00 101.45 2,434.80


b. Skilled Laborer 1 24.00 73.29 1,758.96
c. Unskilled Laborer 1 24.00 56.46 1,355.04

Sub - Total for A.2 - As Evaluated 5,548.80


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

Minor Tools (10% of Labor Cost) 554.88

Sub - Total for B.1 - As Submitted 554.88


B.2 Equipment

Minor Tools (10% of Labor Cost) 554.88

Sub - Total for B.2 - As Evaluated 554.88


C.1 Total (A.1 + B.1) - As Submitted 6,103.68
C.2 Total (A.2 + B.2) - As Evaluated 6,103.68
D.1 Output per hour - As Submitted = 1.00 l.s.
D.2 Output per hour - As Evaluated = 1.00 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 6,103.68
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 6,103.68
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

a. 20mmØ PVC conduit length 60.00 98.00 5,880.00


b. 25mmØ RSC conduit length 2.00 125.00 250.00
c. 20mmØ PVC adapter pc 121.00 15.00 1,815.00
d. 15mmØ locknut & bushing pr 121.00 8.00 968.00
e. 20mmØ locknut & bushing pr 4.00 10.00 40.00
f. utility box, deep type pc 1.00 35.00 35.00
g. junction box, deep type pc 14.00 29.00 406.00
h. 20mmØ entrance cap pc 1.00 54.00 54.00
i. 20mmØX2.4m ground rod pc 2.00 1,200.00 2,400.00

Sub - Total for B.1 - As Submitted 11,848.00


F.2 Materials

a. 20mmØ PVC conduit length 60.00 98.00 5,880.00


b. 25mmØ RSC conduit length 2.00 125.00 250.00
c. 20mmØ PVC adapter pc 121.00 15.00 1,815.00
d. 15mmØ locknut & bushing pr 121.00 8.00 968.00
e. 20mmØ locknut & bushing pr 4.00 10.00 40.00
f. utility box, deep type pc 1.00 35.00 35.00
g. junction box, deep type pc 14.00 29.00 406.00
h. 20mmØ entrance cap pc 1.00 54.00 54.00
i. 20mmØX2.4m ground rod pc 2.00 1,200.00 2,400.00

Sub - Total for B.1 - As Submitted 11,848.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 17,951.68
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 17,951.68
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 2,692.75
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 2,692.75
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 1,795.17
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 1,795.17
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1,121.98
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 1,121.98
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 23,561.58
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 23,561.58

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART D - Electrical Works


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102 (1) Panelboard with Main & Branch Breakers
Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Skilled Laborer 1 8.00 73.29 586.32

Sub - Total for A.1 - As Submitted 586.32


A.2 Labor

a. Skilled Laborer 1 8.00 73.29 586.32

Sub - Total for A.2 - As Evaluated 586.32


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

Minor Tools (10% of Labor Cost) 58.63

Sub - Total for B.1 - As Submitted 58.63


B.2 Equipment

Minor Tools (10% of Labor Cost) 58.63

Sub - Total for B.2 - As Evaluated 58.63


C.1 Total (A.1 + B.1) - As Submitted 644.95
C.2 Total (A.2 + B.2) - As Evaluated 644.95
D.1 Output per hour - As Submitted = 1.00 l.s.
D.2 Output per hour - As Evaluated = 1.00 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 644.95
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 644.95
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

Panelboard with Main & Branch Breakers set 1.00 15,000.00 15,000.00

Br.: 1-15AT,SP, 240V, 3-30AT,50AF,2P,240V


1-60AT,100AF,2P,240V

Sub - Total for F.1 - As Submitted 15,000.00


F.2 Materials

Panelboard with Main & Branch Breakers set 1.00 15,000.00 15,000.00

Br.: 1-15AT,SP, 240V, 3-30AT,50AF,2P,240V


1-60AT,100AF,2P,240V

Sub - Total for F.2 - As Evaluated 15,000.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 15,644.95
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 15,644.95
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 2,346.74
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 2,346.74
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 1,564.50
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 1,564.50
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 977.81
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 977.81
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 20,534.00
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 20,534.00

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART D - Electrical Works


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00

Item No./Description : 1101(33) Wires and Wiring Devices


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 48.00 101.45 4,869.60


b. Skilled Laborer 1 48.00 73.29 3,517.92
c. Unskilled Laborer 1 48.00 56.46 2,710.08

Sub - Total for A.1 - As Submitted 11,097.60


A.2 Labor

a. Construction Foreman 1 48.00 101.45 4869.60


b. Skilled Laborer 1 48.00 73.29 3517.92
c. Unskilled Laborer 1 48.00 56.46 2710.08

Sub - Total for A.2 - As Evaluated 11,097.60


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

Minor Tools (10% of Labor Cost) 1,109.76

Sub - Total for B.1 - As Submitted 1,109.76


B.2 Equipment

Minor Tools (10% of Labor Cost) 1,109.76

Sub - Total for B.2 - As Evaluated 1,109.76


C.1 Total (A.1 + B.1) - As Submitted 12,207.36
C.2 Total (A.2 + B.2) - As Evaluated 12,207.36
D.1 Output per hour - As Submitted = 1.00 l.s.
D.2 Output per hour - As Evaluated = 1.00 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 12,207.36
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 12,207.36
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

ELECTRIC WIRES 2.0 sq.mm., THW m 30.00 22.00 660.00


ELECTRIC WIRES 3.5 sq.mm., THW m 300.00 32.00 9,600.00
ELECTRIC WIRES 5.5 sq.mm., THW m 30.00 45.00 1,350.00
ELECTRIC WIRES 8.0 sq.mm., THW m 60.00 60.00 3,600.00
Two gang switch set 1.00 130.00 130.00
duplex C.O. grounding type, 15A, 230V set 14.00 420.00 5,880.00
KWHR meter round with base set 1.00 2,200.00 2,200.00
tape, bolts & nuts, mica tube, terminal lugs, JB cover, lot 1.00 3,000.00 3,000.00
clamps, screws and anchors
Consumables lot 1.00 8,000.00 8,000.00

Sub - Total for F.1 - As Submitted 34,420.00


F.2 Materials

ELECTRIC WIRES 2.0 sq.mm., THW m 30.00 22.00 660.00


ELECTRIC WIRES 3.5 sq.mm., THW m 300.00 32.00 9,600.00
ELECTRIC WIRES 5.5 sq.mm., THW m 30.00 45.00 1,350.00
ELECTRIC WIRES 8.0 sq.mm., THW m 60.00 60.00 3,600.00
Two gang switch set 1.00 130.00 130.00
duplex C.O. grounding type, 15A, 230V set 14.00 420.00 5,880.00
KWHR meter round with base set 1.00 2,200.00 2,200.00
tape, bolts & nuts, mica tube, terminal lugs, JB cover, lot 1.00 3,000.00 3,000.00
clamps, screws and anchors
Consumables lot 1.00 8,000.00 8,000.00

Sub - Total for F.2 - As Evaluated 34,420.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 46,627.36
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 46,627.36
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 6,994.10
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 6,994.10
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 4,662.74
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 4,662.74
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 2,914.21
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 2,914.21
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 61,198.41
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 61,198.41

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART D - Electrical Works


LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures and Lamps


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

a. Construction Foreman 1 24.00 101.45 2,434.80


b. Skilled Laborer 1 24.00 73.29 1,758.96
c. Unskilled Laborer 1 24.00 56.46 1,355.04

Sub - Total for A.1 - As Submitted 5,548.80


A.2 Labor

a. Construction Foreman 1 24.00 101.45 2434.80


b. Skilled Laborer 1 24.00 73.29 1758.96
c. Unskilled Laborer 1 24.00 56.46 1355.04

Sub - Total for A.2 - As Evaluated 5,548.80


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment

Minor Tools (10% of Labor Cost) 554.88

Sub - Total for B.1 - As Submitted 554.88


B.2 Equipment

Minor Tools (10% of Labor Cost) 554.88

Sub - Total for B.2 - As Evaluated 554.88


C.1 Total (A.1 + B.1) - As Submitted 6,103.68
C.2 Total (A.2 + B.2) - As Evaluated 6,103.68
D.1 Output per hour - As Submitted
= 1.00 l.s.
D.2 Output per hour - As Evaluated
= 1.00 l.s.
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 6,103.68
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 6,103.68
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials

50W Flood light set 12.00 1,320.00 15,840.00


18watts downlight LED set 2.00 900.00 1,800.00
consumables lot 1.00 7,287 7,287

Sub - Total for F.1 - As Submitted 24,927


F.2 Materials

50W Flood light set 12.00 1,320.00 15,840.00


18watts downlight LED set 2.00 900.00 1,800.00
consumables lot 1.00 7,287 7,287

Sub - Total for F.2 - As Evaluated 24,927


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 31,030.81
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 31,030.81
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.1 4,654.62
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.2 4,654.62
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 3,103.08
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 3,103.08
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1,939.43
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) 1,939.43
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 40,727.94
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 40,727.94

Prepared by: Checked/Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

PART D - Electrical Works


BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

A 1.1 (3) Construction of Field Office for the Engineer


QUANTITY: 1.00 l.s

A.1.1(11) Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the Engineer
QUANTITY: 1.00 l.s

A.1.4(1) Provision of Progress Photographs


QUANTITY: 150.00 each

B.3 Permits and Clearances


QUANTITY: 1.00 l.s.

B.5 Project Billboard / Signboard


QUANTITY: 1.00 each

B.7(2) Occupational Safety and Health Program


QUANTITY: 1.00 l.s.

B.9 Mobilization / Demobilization

QUANTITY: 1.00 l.s.

801(1) Removal of Structures and Obstructions

QUANTITY: 1.00 l.s.

803(1)a Structure Excavation ( Common soil )

QUANTITY: 67.04 cu.m.

LENGTH WIDTH DEPTH QUANTITY VOLUME UNIT


F-1 1.50 1.50 1.80 6.00 24.30 cu.m.
F-1 1.50 1.50 2.40 6.00 32.40 cu.m.
F-2 1.00 1.00 1.30 2.00 2.60 cu.m.
WF-1 5.00 0.50 0.60 1.00 1.50 cu.m.
WF-2 5.10 0.30 0.60 1.00 0.92 cu.m.
Bleacher Footing 50.70 0.70 0.15 1.00 5.32 cu.m.
TOTAL: 67.04 cu.m.

804 (1)b Embankment ( From Borrow )


QUANTITY: 153.00 cu.m.

LENGTH WIDTH THICKNESS QUANTITY VOLUME


Stage stair 2.10 1.00 1.00 2.00 4.20 cu.m.
Court 31.00 16.00 0.30 1.00 148.80 cu.m.
TOTAL: 153.00 cu.m.

900(1)c1 Structural Concrete (Class A, 28 days)

QUANTITY: 91.80 cu.m.

Stair

LENGTH AREA NO. OF STEPS QTY VOLUME UNIT


Stair 0.8 0.03 3 2 0.14 cu.m.
Landing 0.8 0.09 1 2 0.14 cu.m.
sub-total: 0.28 cu.m.

Page 24 of 55
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

Footing and Slab on Fill

LENGTH (m.) WIDTH (m.) THICKNESS (m.) QTY VOLUME UNIT


F-1 1.50 1.50 0.40 12.00 10.80 cu.m.
F-2 1.00 1.00 0.30 2.00 0.60 cu.m.
WF-1 5.00 0.50 0.20 1.00 0.50 cu.m.
WF-2 5.10 0.30 0.20 1.00 0.31 cu.m.
Slab on Fill (court) 31.00 16.00 0.10 1.00 49.60 cu.m.
Bleacher 49.65 0.60 0.05 1.00 1.49 cu.m.
Bleacher Footing 49.65 0.70 0.15 1.00 5.21 cu.m.
total: 68.51 cu.m.

Columns

WIDTH DEPTH LENGTH QUANTITY VOLUME UNIT


C-1 0.45 0.45 7.1 6.00 8.63 cu.m.
C-1 0.45 0.45 6.5 6.00 7.90 cu.m.
C-2 0.3 0.3 3.7 2.00 0.67 cu.m.
sub-total: 17.20 cu.m.

Beams

WIDTH DEPTH LENGTH QUANTITY VOLUME UNIT


B-1 0.25 0.4 5.55 10 5.55 cu.m.
B-2 0.15 0.3 5.7 1 0.26 cu.m.
sub-total: 5.81 cu.m.

902(1)a Reinforcing Steel (Deformed) Grade 40

TOTAL QUANTITY: 2,542.88 kg

902(1)b Reinforcing Steel (Deformed) Grade 60

TOTAL QUANTITY: 3,825.08 kg

COLUMN FOOTING AND WALL FOOTING

Unit Weight
BAR Ø LENGTH QUANTITY PCS. FOR 6m No. Of Footing WEIGHT
(kg/m)
16mm Ø 2.00 8.00 3.00 1.578 12.00 340.85 kg
F-1
16mm Ø 2.00 8.00 3.00 1.578 12.00 340.85 kg
16mm Ø 1.00 5.00 1.00 1.578 2.00 18.94 kg
F-2
16mm Ø 1.00 5.00 1.00 1.578 2.00 18.94 kg
WF-1 (T) 12mm Ø 0.50 18.00 2.00 0.888 1.00 10.66 kg
WF-1 (L) 12mm Ø 5.00 3.00 3.00 0.888 1.00 15.98 kg
Bleacher (T) 10mm Ø 0.50 101.00 9.00 0.616 1.00 33.26 kg
Bleacher (L) 10mm Ø 49.65 5.00 42.00 0.616 1.00 155.23 kg
sub-total: Grade 60 719.58
Grade 40 215.13
COLUMN

Unit Weight
BAR Ø LENGTH QUANTITY PCS. FOR 6m No. of Column WEIGHT
(kg/m)
Vertical Bars 16mm 9 12 18.00 1.578 12 2045.09 kg
C-1
Ties 10mm 1.6 47 13.00 0.616 12 576.58 kg
Vertical Bars 16mm 4.6 4 4.00 1.578 2 75.74 kg
C-2
Ties 10mm 1 33 6.00 0.616 2 44.35 kg
sub-total: Grade 60 2,120.83
Grade 40 620.93
BEAMS & ROOF BEAMS

Unit Weight
BAR Ø NO. OF BARS LENGTH PCS. FOR 6m NO. OF BEAM WEIGHT
(kg/m)
Main Bar 16mm 8 6.9 10.00 1.578 10 946.80 kg
B-1
Stirrups 10mm 47 1.1 9.00 0.616 10 318.47 kg
Main Bar 16mm 4 6 4.00 1.578 1 37.87 kg
B-2
Stirrups 10mm 41 1 7.00 0.616 1 25.26 kg
sub-total: Grade 60 984.67
Grade 40 343.73

Page 25 of 55
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

SLAB ON FILL

LENGTH Unit Weight


BAR Ø NO. OF BARS PCS. FOR 6m Quantity WEIGHT
(including (kg/m)
Short Direction 10mm 28 splicing)
36 168.00 0.616 1 620.93 kg
SOF ( court )
Long Direction 10mm 53 18.45 163.00 0.616 1 602.36 kg
Short Direction 10mm 126 0.6 13.00 0.616 1 48.05 kg
Bleacher
Long Direction 10mm 3.00 49.65 25.00 0.616 1 91.75 kg
sub-total: Grade 40 1,363.09

903(2) Formworks and Falseworks

QUANTITY: 218.31 sq.m

COLUMN
QTY. WIDTH (m.) DEPTH(m.) HEIGHT AREA UNIT
C-1 6.00 0.45 0.45 7.10 76.68 sq.m
C-1 6.00 0.45 0.45 6.50 70.20 sq.m
C-2 2.00 0.30 0.30 3.70 8.88 sq.m
sub-total: 155.76 sq.m

BEAMS
QUANTITY LENGTH WIDTH DEPTH AREA UNIT
B-1 1.00 55.5 0.25 0.40 58.28 sq.m
B-2 1.00 5.7 0.15 0.30 4.28 sq.m
sub-total: 62.55 sq.m

1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm

QUANTITY: 79.51 sq.m.

LENGTH HEIGHT QUANTITY AREA UNIT


Stage stair 5.00 1.00 2.00 10.00 sq.m.
Bleacher 49.65 0.60 2.00 59.58 sq.m.
Bleacher 49.65 0.20 1.00 9.93 sq.m.
79.51 sq.m.

1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm

QUANTITY: 15.00 sq.m.

LENGTH HEIGHT QUANTITY AREA UNIT


Stage 6.00 2.50 1.00 15.00 sq.m.
15.00 sq.m.

1021(1)a Cement Floor Finish ( Plain )


QUANTITY: 528.75 sq.m.

AREA
SOF ( Court ) 496.00
SOF ( Stage ) 32.75
TOTAL: 528.75 sq.m.

1027(1) Cement Plaster Finish


QUANTITY: 189.02 sq.m.

AREA
4" CHB 159.02
6" CHB 30.00
TOTAL: 189.02 sq.m.

1032(1)a Painting Works (Masonry/Concrete)


QUANTITY: 372.77 sq.m.

AREA UNIT
WALLS 189.02 sq.m.
COLUMNS 108.00 sq.m.
BEAM 1 72.15 sq.m.
BEAM 2 3.60 sq.m.
TOTAL: 372.77 sq.m.

Page 26 of 55
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

1032(5) Textured Finish


QUANTITY: 526.00 sq.m.

SIZE AREA
SOF (Court) 16 x 31 496.00
SOF (Stage) 6x5 30.00
TOTAL: 526.00 sq.m.

1032(1)c Painting Works (Steel)


QUANTITY: 751.64 sq.m.

SIZE ( G.I.
LENGTH NO PERIMETER AREA
PIPE )
75Ø x 5.5mm 46.00 6 0.24 66.24 sq.m.
TRUSS 1
25Ø x 3.4mm 46.00 6 0.08 22.08 sq.m.
37.5Ø x 3.7mm 12.00 5 0.12 7.20 sq.m.
STRUT
25Ø x 3.4mm 16.00 5 0.08 6.40 sq.m.
STAGE 100Ø x 6mm 5.50 2 0.32 3.52 sq.m.
C-PURLINS 150x50x25x1.5 1077.00 1 0.60 646.20 sq.m.
TOTAL: 751.64 sq.m.

1014 (1) b2 Prepainted Metal Sheets (above 0.427mm) Rib Type Long Span
QUANTITY: 582.78 sq. m.

SIZE AREA
COURT 17.3 x 31 536.30
STAGE 8.3 x 5.6 46.48
TOTAL: 582.78 sq.m.

1047(2)a Structural Steel (Trusses)


QUANTITY: 4,414.60 kg

SIZE ( Angle
LENGTH NO. OF TRUSS kgs./m WEIGHT
Bar )
75Ø x 5.5mm 46.00 6 11.30 3118.80 kg
TRUSS 1
25Ø x 3.4mm 46.00 6 2.50 690.00 kg
37.5Ø x 3.7mm 12.00 5 4.05 243.00 kg
STRUT
25Ø x 3.4mm 16.00 5 2.50 200.00 kg
STAGE 100Ø x 6mm 5.50 2 14.80 162.80 kg
QUANTITY: 4414.60 kg

1047(2)b Structural Steel (Purlins)


QUANTITY: 3,672.57 kg LENGTH

SIZE LENGTH kgs./m WEIGHT UNIT


150x50x25x1.5mm C-Purlins 992.00 3.41 3382.72 kg
150x50x25x1.5mm C-Purlins 85.00 3.41 289.85 kg
QUANTITY: 3,672.57 kg

1047(3)a Metal Structure Accessories (Bolts)


QUANTITY: 48.00 each

1047(6) Metal Structure Accessories (Steel Plates)


QUANTITY: 348.90 kg

SIZE SETS QTY WEIGHT PER PC. UNIT


Gusset Plates 6mm thk
Truss 1 1 12.00 1.12 13.44 kg
Truss 2 ( stage ) 1 8.00 2.24 17.92 kg
Base Plate 400x400x20mm ( court ) 1 12.00 25.12 301.44 kg
Base Plate 250x250x10mm ( Stage ) 1 2.00 4.91 9.82 kg
Base Plate 200x200x10mm ( Stage ) 1 2.00 3.14 6.28 kg
TOTAL 348.90 kg

1047(7)b Metal Structure Accessories (Sag Rods)


QUANTITY: 213.12 kg
kg
SIZE LENGTH kgs./m WEIGHT UNIT
12mm diameter Sagrod 240.00 0.888 213.12 kg
QUANTITY: 213.12 kg
Page 27 of 55
BACK UP COMPUTATION
LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte, Candelaria, Quezon

1047(4) Metal Structure Accessories (Cross Bracing)


QUANTITY: 347.16 kg

SIZE LENGTH kgs./m WEIGHT UNIT


16mm diameter Cross bracing 220.00 1.578 347.16 kg
QUANTITY: 347.16 kg

1047(3)c Metal Structure Accessories (Turn Buckle)


QUANTITY: 20.00 pcs

1100(10) Conduits, Boxes & Fittings (Conduit Works/ConduitRough-in)


QUANTITY: 1.00 l.s.

1101(33) Wires and Wiring Devices


QUANTITY: 1.00 l.s.

1102 (1) Panelboard


Power Loadwith
Center
Main
Switchgear
& Branch Breakers
and Panelboards
QUANTITY: 1.00 l.s.

1103(1) Lighting Fixtures and Lamps


QUANTITY: 1.00 l.s.

Prepared by:

MARCO BRIAN L. BRITON


Engineer II

Page 28 of 55
UNIT COST ANALYSIS FOR AGGREGATES (SAND and GRAVEL)

Item Description : Aggregates


Assumed Quantity : 100.00 cu.m.
Source : Sariaya quarry
Project : LOCAL PROGRAM, Local Infrastructure Program, Buildings and Other Structures, Multipurpose/
Facilities, Construction of Multi-Purpose Building (Covered Court), Barangay Masin Norte,
Candelaria, Quezon
Candelaria Sta. K107+000.00 (POBLACION)
D
9.20 km
Terrain Condition : **With 5km free hauling distance
Flat/ Rolling, Paved : 4.20 km **From Source of Material to Point of Reference
Flat/ Rolling, Paved : 0.00 km **From Point of Reference to Project Site if Applicable
(Note: Distance established was based on Google Earth)
Working Hours : 8.00 hours

TIME MOTION ANALYSIS :

Flat/ Rolling, Paved :


Speed when Loaded = 32.5 kph
Speed when empty = 47.5 kph
4.20 km x 60 mins/hr
Time when loaded = = 7.75 mins
32.5 kph
4.20 km x 60 mins/hr
Time when empty = = 5.31 mins
47.5 kph

Flat/ Rolling, Paved :


Speed when Loaded = 32.5 kph
Speed when empty = 47.5 kph
0.00 km x 60 mins/hr
Time when loaded = = 0.00 mins
32.5 kph
0.00 km x 60 mins/hr
Time when empty = = 0.00 mins
47.5 kph

Loading Time = 3 mins


Unloading Time = 2 mins
Allowance for Delay:
10% of Total Time = 1.81 mins
TOTAL CYCLE TIME = 19.87 mins/trip

No. of Dumptrucks Used: 1 Dumptruck


Capacity of Dumptruck : 10 cu.m
No. of trips for DT per 8.00 hr/day x 60 mins/hr
= = 24.00 trips/day
day 19.87 mins/trip
Dumptruck Daily Output = 10 cu.m/trip x 24.00 trips/day = 240.00 cu.m./day
No. of Dump Trucks Used = 1 DT x 240.00 cu.m./day = 240.00 cu.m./day
No. of Days of 100 cu.m.
= = 0.42 days
Dumptruck 240.00 cu.m./day
Equipment Used
(Rates per Day) (Days)
1 Dumptruck = 11360 x 0.42 = 4,733.33 Php
Sub Total = 4,733.33 Php
Hauling Cost 4,733.33 Php
= = 47.33 Php/ cu.m.
per cu.m. 100 cu.m.

Baranggay Municipal Total Cost up to Project


ITEM Pick Up Price Hauling Cost
Passway Passway Site
3/4 1,200.00 5.00 10.00 47.33 1,262.33
G-1 1,150.00 5.00 10.00 47.33 1,212.33
Filler Materials 515.00 5.00 10.00 47.33 577.33
Sand 1,200.00 5.00 10.00 47.33 1,262.33
Boulder 400.00 5.00 10.00 47.33 462.33
Common
118.00 5.00 10.00 47.33 180.33
Borrow

Prepared by: Checked/ Reviewed by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II
MAP SHOWING THE SOURCE OF MATERIAL TO THE POINT OF REFERENCE (PROJECT SITE) L= 9.20 KM

MAP SHOWING DPWH QUEZON II DEO OFFICE TO THE POINT OF REFERENCE (PROJECT SITE) L= 28.9 KM

Prepared by: Checked by:

MARCO BRIAN L. BRITON JUMEL B. REYES


Engineer II Engineer II

You might also like