Professional Documents
Culture Documents
QC:
INTER-DEPARTMENTAL PROCEDURE - OPERATIONS – DUKHAN FIELDS
PERMIT TO WORK SYSTEM – DUKHAN FIELDS IP-OPS-015
Rev Rev
Revision Description Page No. Approved by
No. Date
A1 July 2002 Original Issue - OM(D), DO
Remarks :
CONTENT LIST
1.0 INTRODUCTION 1
8.8 Cross-referencing 12
9.4 Radiography 17
13.10 Firewatcher 26
ATTACHMENTS
1.0 INTRODUCTION
The management of Qatar Petroleum (QP) requires that the health and safety of all
employees and other persons who may be affected directly or indirectly by their
activities, and the protection of its assets is ensured.
To ensure the PTW System is effective, DO NOT DEVIATE FROM IT. The system
is designed to ensure personal and environmental safety, and the integrity of plant
and equipment.
This PTW Procedure is a formal written system that uses Work Permits to control
work by means of potential hazard identification and risk assessment.
These work permits are also means of communication between plant management,
plant supervisors, technicians who prepare and carry out the work.
THE ISSUE OF A WORK PERMIT DOES NOT, BY ITSELF, MAKE A JOB SAFE.
SAFETY CAN ONLY BE ACHIEVED BY THOSE PREPARING THE WORK AND
THOSE CARRYING OUT THE WORK.
The work permit is not simply permission to carry out a job. It is the cornerstone of a
safe system of work that determines how that job can be carried out safely. A work
permit must not be regarded as a means of avoiding the need to eliminate hazards
or reduce risks, nor just an exercise in form filling. It does not remove individual
responsibility, as your signature means you are responsible.
Work Permits are not mandatory for aboveground civil infrastructure works inside
the Green Fields Areas of Dukhan Concession Area of QP.
The Respective Asset Holder is responsible for ensuring that an effective PTW
system is established and maintained. He shall also ensure that the system is
monitored, audited and reviewed as required. As a minimum the system shall be
reviewed every three years and amended as necessary.
The Asset Manager or his authorized representative has complete authority for the
operation and administration of the system, and shall appoint Permit Authorities as
required.
Permit Authorities are the area supervisor for Operations - Dukhan Fields on all
matters related to the PTW system.
These supervisors are responsible for ensuring the workforce (with PTW
responsibility) under their authority, inclusive of contractors, are adequately trained
in the operation of the PTW system.
Administration of the PTW system shall be conducted in English and all personnel
who have responsibilities within the system shall be able to read and write in English
and fully understand the requirements applicable to their role.
Note: If the above emergency procedure is used, it shall be recorded in the Plant
Permit Logbook and signed and dated by the Permit Controller. The
ensuing Incident Report shall also show how this work was carried out.
An essential requirement for safe and efficient administration of the PTW system is
comprehensive forward planning. A weekly work permit meeting shall be held to
discuss the proposed Hot Work permits for hazardous / operational areas.
Note: Breakdown and priority unplanned work may necessitate immediate action.
Note: A Spading / Blinding List (see Attachment L) is mandatory for all vessel or
tank entry activities, however the Spading / Blinding List is not classed as a
certificate.
All identified work shall be authorized and planned prior to work permit application.
The Permit Applicant shall raise the appropriate work permit and should use the leg
chart as a means of deciding the type of permit required. Included in Box 1 of the
permit shall be a full description of:
• location of work
• applicant telephone number
• work order / contract number
• equipment to be worked on and identification number
• exact nature and scope of the work
• speciality tools and/or equipment that may impact on safety at the worksite
• need for daily Permit endorsement by the Permit Applicant, by ticking the
relevant box
The Permit Applicant shall liaise with the Permit Controller to complete the relevant
sections of the work permit to the best of his knowledge, and any additional work
permits and supporting certificates as required.
The Permit Applicant or his representative shall present the work permit and any
supporting documentation to the Permit Authority for review and authorization.
The Permit Authority, together with the Permit Applicant, shall review the work
permit and any supporting documentation and, if satisfied, authorize the Permit
Controller to process the work permit, ensuring that equipment preparation and
safety precautions are put in place.
The Permit Authority shall specify the validity of the work permit after discussion with
the Permit Applicant. However it shall not exceed the limits stated in Section 8.1. A
new permit shall be processed for work extending beyond the validity of a permit.
On being authorized, the Permit Controller shall review the work permit and any
supporting documentation and shall complete the appropriate sections. He shall
arrange for equipment preparation, e.g. depressurizing, draining, flushing, purging,
and any process, mechanical, safety, or electrical isolations required.
When he is satisfied that the worksite has been safely prepared (see Section 10 of
this procedure) and lock-off keys for process / electrical isolations are secure in the
Lockout Box(es), the work permit details shall be recorded in the Work Permit
Register. Only when this is complete will the work permit and the relevant
equipment be released to the Permit Applicant, after the Permit Controller has
signed.
The Worksite Supervisor assigned by the Permit Applicant shall collect the prepared
work permit from the Permit Controller and sign the permit to acknowledge he
understands it and accepts the associated worksite responsibilities.
The Worksite Supervisor shall then obtain the first endorsement from the Permit
Controller for the work to proceed. He shall then proceed to the worksite to
commence the work.
If a work permit has all the endorsements complete but the isolations and work are
to continue, a new work permit shall be raised. The new work permit shall then be
applied for and authorized using the normal procedure.
Each work permit endorsement from the Permit Controller is only valid for a
maximum of one shift. The oncoming Permit Controller shall endorse work
extension into the next shift. If the work permit endorsement boxes have all been
completed, a new work permit shall be raised.
If work has not been completed within the validity of a permit, a new permit shall be
issued for the remaining work. The Serial Number of the new permit shall be
struck-off and the Serial Number of the old permit shall be written in its place. All
work permits and certificates associated with the same work shall be cross-
referenced by inserting the certificate number in the box provided on each
document. Additional certification raised during the validity of an issued permit shall
also be cross-referenced on all copies of the ‘live’ work permit. There will not be
any limit to the number of new permits issued for completion of ongoing work.
OSP/4 Owner - OPERATIONS – DUKHAN FIELDS Revision A4.1 Feb15
INTER-DEPARTMENTAL PROCEDURE - OPERATIONS – DUKHAN FIELDS
PERMIT TO WORK SYSTEM – DUKHAN FIELDS IP-OPS-015
Page 12 of 47
Permit Authority - If the position holder changes, all work permits shall
be presented to the new Permit Authority
immediately after the change occurs.
Permit Controller - All work permits shall be presented for transfer of
authority immediately to the oncoming Permit
Controller as he arrives on site.
Permit Applicant - All work permits shall be presented for transfer of
authority immediately to the oncoming Permit
Applicant as he arrives on site.
Worksite Supervisor - Work shall stop if he leaves the site for shift change.
The new Worksite Supervisor shall sign the ‘Transfer
of Responsibility’ part of the permit in the presence
of the Permit Controller.
If the work is being performed on more than one shift
per day and the Worksite Supervisor changes during
these shifts, the oncoming shift Worksite Supervisor
shall endorse the work and permit declaration with
his name, timing of the shifts, and signatures on the
attached sheet.
Radiation Protection - Work shall stop if he leaves the site for shift change.
Officer (RPO) The new RPO shall sign the “Transfer of Responsibility”
part of the permit in the presence of Permit Controller.
If the work being performed is more than one shift per
day and the RPO changes during this shift, the
incoming shift RPO shall endorse the work permit
declaration with his name, timing of the shift and
signature on the attached sheet.
8.8 Cross-referencing
All work permits and certificates associated with the same work shall be cross-
referenced by inserting the work permit / certificate number in the box provided on
each document. Additional certification raised during the validity of an issued
permit shall also be cross-referenced on all copies of the ‘live’ primary work permit.
If a general alarm activates all work shall stop immediately. Work shall not
recommence until cleared to do so by the Permit Controller or by announcement
from the Control Room, and the permits shall be stamped and initialed accordingly.
The Permit Controller, Permit Applicant or Safety Officer are authorized to stop work
in the event of work permit violation or unsafe acts.
OSP/4 Owner - OPERATIONS – DUKHAN FIELDS Revision A4.1 Feb15
INTER-DEPARTMENTAL PROCEDURE - OPERATIONS – DUKHAN FIELDS
PERMIT TO WORK SYSTEM – DUKHAN FIELDS IP-OPS-015
Page 13 of 47
All other personnel may stop the work if they observe any hazardous or potentially
hazardous condition. They shall immediately inform the Permit Controller, Permit
Applicant or Safety Officer. If on investigation it is determined the work permit is to
be suspended, the Permit Authority shall be informed immediately.
If Hot Work is suspended for operational reasons, e.g. due to sampling, the Control
Room shall advise the Permit Applicant / Worksite Supervisor if other work permits
are to be suspended or withdrawn. The Permit Controller shall retrieve all relevant
work permits. Work shall not resume until the Permit Controller declares it is safe to
do so.
A work permit can only be suspended for a maximum of five days or until the expiry
of its validity period (whichever is sooner), when it shall be cancelled and signed off.
Thereafter a new work permit shall be raised or the system / equipment shall be
placed in long term isolation as appropriate.
On completion of the work, the Worksite Supervisor shall check the worksite and
ensure that all tools and equipment have been removed and the area cleaned.
When all activities have ceased, he shall return the work permit to the Permit
Controller for his endorsement.
The Worksite Supervisor shall then inform the Permit Applicant, who shall sign the
work permit signifying handing back of the equipment. Responsibility for the
satisfactory handing back of the worksite is the Permit Applicant’s.
Note: For Confined Space Entry Certificates, it is mandatory that the Permit
Controller visits the site and checks the confined space is clear prior to
closure of the certificate.
The Permit Controller shall ensure the area is acceptable prior to signing for
acceptance of handing back of the area / equipment. The Permit Controller can
then allow de-isolation of the equipment.
The Permit Controller shall ensure that all isolations are removed before closing the
work permit, and associated work permits and/or certificates as appropriate, and
allowing the equipment to be reinstated.
The original (top copy) of the work permit, and top copy of any associated
certificates, shall be held on site for one month or an appropriate time as determined
by the Permit Authority, prior to being archived.
If an incident occurs associated with a work permit, the original copy of the work
permit and the original copy of any associated certificate(s) shall be attached to the
Incident Report. Copies of these originals shall be retained on file.
It is the responsibility of the Permit Authority to ensure the safe preparation of the
worksite. He may assign the application for process isolations to a nominated
person, but he still retains overall responsibility.
When the Permit Authority decides it is necessary, the Permit Applicant shall
prepare formal plant or equipment preparation procedures / method statement. This
will be completed prior to the work commencing and reference should be made to
any Simultaneous Operations procedures when necessary.
The Permit Controller shall provide copies of marked-up P&IDs, spade lists and/or
isolation procedures to the Permit Applicant (mandatory for all vessel entry and
process isolations).
Based upon the detailed description of the work to be performed, hazards shall be
assessed regarding the materials to be handled and the prevailing conditions.
The possible impact of the work on the surrounding area shall be assessed and care
taken not to issue a work permit that could impact on the safety conditions of other
work permits in the area.
The Permit Controller can introduce additional precautions if necessary based on his
assessment. Based on the assessment of the hazards involved, the precautions to
be taken to enable the work to proceed safely shall be indicated by the Permit
Authority on the work permit. Based on the residual risks associated with the job,
the permit/JSA to be escalated to higher management approval. Refer procedure
QPR-DKN-25 on Job Safety Analysis for further details.
The performance of cold work shall require, but is not limited to, the following
precautions:
a) The Permit Authority shall specify if the Permit Controller and Permit Applicant
are required to make a site visit during the shift.
b) If a gas test is required, it shall be carried out immediately prior to the
commencement of work and, if the work party has left the worksite, immediately
prior to resumption of work.
Prior to any hot work being authorized, the Permit Authority shall consider the
following points:
• could the work be removed to a safer location?
• is it essential for safety or process reasons to perform the work during
normal operations, or could the work be deferred until a total or partial
shutdown?
• has the workscope and potential hazards been discussed by the Permit
Applicant, Safety Officer and Permit Controller?
• another hot work permit will NOT be issued for an area where a confined
space entry certificate for work permits associated with this activity are in
force
• the performance of hot work is NOT permitted in the same area as work
involving paint spraying or hand painting
• cold work that is likely to release hydrocarbons near to the site of hot work
shall be suspended
• gas test is required; it shall be carried out immediately prior to the
commencement of work and, if the work party has left the worksite,
immediately prior to resumption of work
• the Worksite Supervisor shall remain at the worksite during the performance
of the work as defined by the Permit Authority on the permit
• the number of hot work permits to be issued in any one area will be
determined by the Permit Authority, based upon the availability of manpower
and equipment to control and make safe for the work to be carried out
The Permit Controller and Permit Applicant shall make regular visits to the
worksite during the work activity.
Total isolation from flammable or toxic gas / liquids shall be achieved in one of
the following ways:
• physical disconnection
• blinding using correctly rated blinds
• spading using correctly rated spades
• double block and bleed
• any combination of the above as deemed necessary by the Permit
Authority / Permit Controller
Note: It may be necessary to raise a Cold Work permit for this preparatory work.
The Permit Authority shall assess this after discussion with the Permit
Controller.
• depressurized
• drained
• vented
• purged and flushed
• or any of the above as required to allow hot work to commence
All hot work sites shall be free of hydrocarbons and combustible materials, e.g.
sludge, scale, deposits etc.
The worksite shall be gas tested by an Authorized Gas Tester and certified as
being flammable / toxic gas free. A certified gas detector shall be active on site
throughout the hot work. The maximum LEL permissible for authorized hot work
is 0% LEL.
During the work, all sparks and splatter shall be suitably contained. If the work is
above access or walkways, precautions shall be taken to ensure that no sparks
or splatter falls below. The area beneath the worksite shall be barricaded off
and warning notices posted in English and Arabic. All drains in the vicinity shall
be covered.
Preparation for entry into confined spaces shall be performed in accordance with the
approved procedure IP-OPS-031, which will be provided by the Permit Controller.
The precautions are mandatory and apply even when a person’s head is inserted
into the space for a quick inspection. The following requirements are applicable to
all process and utility systems, irrespective of service:
• the Permit Controller and Permit Applicant shall make regular visits to the
worksite during the work activity
• the confined space shall be positively isolated from all process and utility
systems by disconnection, blinding and/or spading, using the correctly rated
spades / blinds (where disconnection is employed as the means of isolation,
both sides of the disconnected lines will be blinded)
• isolations shall be achieved as close to the confined space as possible (a
Cold Work permit will be required for the isolation work)
Where the Permit Controller is one of the persons entering the confined space, the
Permit Authority shall endorse the certificate. Where the Permit Authority decides to
enter, the Permit Controller shall endorse the certificate. Under no circumstances
shall the Permit Authority and the Permit Controller be permitted to enter the
confined space at the same time.
9.4 Radiography
At the discretion of the AEP, an Electrical Work Certificate may be issued for
work on a low voltage system, e.g. work on the busbars of a 415V switchboard.
The safety rules for work on high voltage systems shall apply to this work. This
certificate can be transferred between AEPs.
After discussion with the Permit Applicant, the requirement for electrical isolation
shall be specified by the Permit Controller at permit application.
The PRC can be issued to a CEP for the isolation of low voltage equipment only,
i.e. equipment not exceeding 1000V AC or 1500V DC. A PRC for high voltage,
i.e. exceeding 1000V AC or 1500V DC, can only be issued to and performed by
an AEP.
At the discretion of the AEP, this certificate may be issued to allow work to be
carried out in the vicinity of such overhead lines.
Excavation work shall be carried out under the control of an ‘Excavation Certificate’
(see Attachment J), which will be supplemented by a primary work permit for
excavation work only authorized by the Permit Authority and the Permit Controller.
A drawing or sketch of the proposed excavation work and site shall be prepared by
the sponsoring department and submitted along with the certificate. This will enable
any affected disciplines to identify hazards and specify precautions to be taken
when signing for approval.
Considering the criticality of excavation or its proximity to live facilities, if the Permit
Controller stipulates that the presence of the Permit Applicant / QP Representative
is required, then the relevant box will be ticked on the Excavation Certificate.
A matrix for identifying the respective authority for each area is included as
Attachment Q.
Notes: I. The cancelled certificate shall be attached to the new certificate during
processing and retained by the Permit Controller until all work has been
completed and the permit / certificate closed.
The Worksite Supervisor shall examine the worksite each time the ‘Excavation
Certificate’ is endorsed to ensure it is safe to continue work. All excavation
worksites shall be barricaded off, with warning notices written in English and
Arabic clearly visible. Flashing warning lights are mandatory during periods of
poor visibility, e.g. during the hours of darkness, during foggy weather or
sandstorms.
Isolation, lock off and tag is an integral part of the PTW System. If plant or
equipment is specified as requiring isolation as a condition of the work permit, a
‘Preparation / Reinstatement Certificate (PRC) shall be issued and becomes part of
the work permit to which it is referenced.
Personal isolations are only permitted to be carried out by a CEP or AEP (for
electrical, instrument and telecommunications) as defined in ES.E.50. When such
isolations are used, this shall be identified by the Permit Authority on the
appropriate section of the work permit as a condition of the work to be performed.
Personal isolations can only be used for a period of one shift.
The method of isolation shall be detailed on the PRC and the isolation shall only be
carried out by the nominated authorized person. If isolations require ‘locking off’,
official QP padlocks, clearly stamped with an individual ID number, should be used.
If padlocks cannot be installed, other approved immobilizing devices as specified by
the Permit Controller shall be used.
Isolation padlock keys and, where other forms of immobilizing devices are used, the
‘tear off’ section of the isolation tags shall be locked in a Lockout Box (see
Attachment M). Each isolation point and any vent / drain point that has been
opened or closed shall have an isolation tag attached, clearly noted and referenced
to the PRC.
The type of isolation used shall depend on the level of risk associated with the work
to be performed. For further information, refer to IP-OPS-029.
It is the responsibility of the Permit Controller to ensure that marked-up P&IDs and
an approved spade list are issued to the Permit Applicant for use.
• blind flanges, plugs, pipe joints or any other equipment removed or loosened
shall be tagged and noted
When the lockout box finally contains all the relevant isolation information, the
number of the lockout box shall be recorded on the PRC.
The Permit Controller shall issue one lockout box key to the Worksite Supervisor,
record the issue on the PRC, and obtain the relevant signature.
If an isolation is in force under a work permit and an additional work permit is raised
which requires exactly the same isolation, no additional isolation needs to be
carried out. To ensure isolation control, an additional key is removed from the
lockout box holding the appropriate isolation records and is handed over to the
second Worksite Supervisor under signature.
The original and all copies of the PRC will be amended to reflect the issue of the
second key, and both permits shall be cross-referenced to each other and the PRC.
A control system (issue and return) for the lockout box keys shall be developed by
the Permit Authority and any local rules approved by management. This may reflect
either a ‘2-key’ or ‘3-key’ system, dependent on the requirements of the user
department.
The ‘C’ (Control) key from a lockout box shall not be issued to a Worksite
Supervisor. This key can be cascaded from work permit to work permit by being
placed in an unused lockout box, providing additional Worksite Supervisors with
lockout keys. This allows multiple work permits to be issued without jeopardising
the integrity of the original isolation.
When the work associated with a work permit is completed, the Worksite Supervisor
returns the work permit, suitably signed off by the Permit Applicant, along with the
lockout box key to the Permit Controller.
The Permit Controller and the Worksite Supervisor shall sign the ‘lockout box key’
section on the PRC to record the return of the key.
If isolations need to remain in force, this shall be reflected on the work permit when
closed, along with all associated work permits / certificates.
The original PRC shall be stamped with the letters ‘LTI’ (Long Term Isolation), and
the padlock keys, tags, and PRC shall be placed in the Long Term Isolation Lockout
Box and recorded in the LTI Register.
The Permit Controller, in liaison with the Permit Applicant, shall specify the
requirement for an electrical isolation.
Following discussion with the Permit Controller and the Permit Applicant, an
appropriate AEP or CEP shall complete the ‘electrical isolation’ section of the PRC.
The isolation will be carried out using a padlock and key supplied by the Permit
Controller. Once the isolation is effected, the AEP / CEP shall place the padlock
key(s) in the lockout box allocated by the Permit Controller and record the
number(s) on the PRC.
The lockout box Key ‘A’ will then be issued to the Worksite Supervisor in charge of
the work.
When the work requiring the electrical isolation is completed, the Worksite
Supervisor shall return his signed-off permit, with PRC attached, and lockout box
Key ‘A’ to the Permit Controller, who shall arrange for de-isolation by the
AEP / CEP, provided it is safe to do so.
If the isolation needs to remain in force, this shall be reflected on the work permit
when closed, along with all associated work permits / certificates.
The original PRC shall be stamped with the letters ‘LTI’ (Long Term Isolation), and
the padlock keys, tags, and PRC shall be placed in the Long Term Isolation Lockout
Box and recorded in the LTI Register.
If work is completed or suspended beyond the work permit’s period of validity, but
the worksite requires the continued protection of an electrical, mechanical, safety or
emergency system isolation, the following shall apply:
a) Sign off to close the original work permit.
b) Stamp the original PRC with the letters ‘LTI’.
c) Retain the original copy of the PRC, with the original work permit attached, in the
Long Term Isolation file, and give a copy to the Permit Applicant for his record.
The details of the LTI shall be recorded by the Permit Controller.
d) The Permit Controller shall retain the lockout box control key and one other key
shall be retained by the Permit Authority.
c) The Permit Controller shall then transpose the original details from the LTI PRC
onto a new PRC, noting the name of the person who verified the isolations as the
‘isolator’.
d) The Permit Controller shall draw 2 lines across the original LTI PRC, write
cancelled and discard it. The new PRC shall be attached to the work permit.
The work can then be completed under normal PTW conditions. When the work is
complete, the Permit Controller shall cancel all work permits, associated certificates,
and remove the isolations.
All work to be carried out at a height above 2 metres shall be accomplished from a
certified scaffold, secured ladder or purpose-built platform.
Three audits per week shall be carried out on specific work permits as follows:
• the Permit Authority shall audit 1 live work permit
• the Permit Controller shall audit 1 completed work permit
• a senior supervisor shall audit 1 completed work permit
The Permit Authority may, at his discretion, request other supervisors to carry out
audits.
A ‘Permit Compliance Checklist’ shall be completed for each audited work permit
(see Attachment O). The Permit Authority shall endorse the audit findings and, if
deficiencies are found, may put corrective actions in place immediately or make
recommendation for amendment to the PTW System (see Attachment P).
All completed audit reports shall be forwarded to the HSE Department for
independent review.
PTW position holders are required to have completed the appropriate training and
be certified accordingly. Certification shall be the responsibility of the respective
Department Head and, where appropriate, the Permit Authority.
He is responsible for raising all work permits and supporting certification for
electrical equipment, and can isolate / de-isolate electrical equipment up to and
including high voltage equipment.
Note: A CEP cannot issue a work permit or associated certificate of any type. He
can endorse the relevant section on a PRC. CEPs from the Instrument
section can raise a work permit specific to their discipline.
The RPO shall understand the necessary precautions to be taken for the work to be
performed, and the extent to which these precautions restrict exposure.
He shall monitor the work of the Radiation Workers and shall remains at the
worksite during performance of the work. The RPO may either be an addition
to the radiographic crew or be a part of the radiography team.
More than one RPO may be appointed and the name(s) shall be posted.
All personnel engaged in radiography work shall wear a personal monitoring badge
(Thermal Luminescence Dosimeter TLD Badge), and should carry a personal
radiation (Dosimeter) at all times during the performance of work.
Note: All personnel engaged in radiography shall carry their license with them all
the time during the performance of their work and produce it if requested by
the Permit Authority, Permit Controller, QP RPC or Safety Inspector.
Personnel not in possession of valid license shall be prohibited from using
radio active material and/or entering the controlled area.
13.10 Firewatcher
He shall monitor the work area while Fire and Gas Detection systems are inhibited,
or as required by the Permit Controller during Hot Work.
Work Party members shall understand the principles of the PTW system and be
technically competent to carry out the tasks assigned to them by the Worksite
Supervisor.
PTW WORKFLOW
PERMIT CLOSE-OUT BY
Maintain Permit Register
PERMIT CONTROLLER
IP-OPS-015, Att.A
YES
Does the work create a source of ignition?
Does the work involve naked flame?
Does the work involve electric welding?
Does the work involve electric induction pre-heating / stress relieving?
Does the work involve grinding?
Does the work involve explosives?
Does the work involve the operation of protected portable diesel engines?
Does the work involve non-intrinsically safe equipment?
Does the work involve non-certified electrical / electronic equipment?
Does the work involve cameras equipped with batteries in restricted areas?
Does the work involve removing covers and exposing live electric / instrument
connections to atmosphere?
Does the work involve removing covers and exposing non-intrinsically safe
instrumentation / circuits to atmosphere?
Does the work involve air / hydraulic powered tools / equipment?
Soil testing by nuclear gauge involving radioactive sources less than 100 mCi (milli Curies)
YES
YES
IF YOU ARE IN ANY DOUBT AS TO WHICH TYPE OF PERMIT YOU REQUIRE, CONTACT EITHER THE
PERMIT CONTROLLER OR THE PERMIT AUTHORITY.
The Vessel / Tank / Confined Space preparations have been completed. The 'Prior to Entry' testing has been completed and is within
limits. Continuous Monitoring Tests to be carried out at hour interval(s) and recorded in Box 5.
I confirm that it is now safe for personnel to enter the above confined space and carry out the work as described, provided that all
requirements in Section 3 remain in effect and the gas monitoring levels remain below the acceptable safe limits.
Print Name: Signature: Time: Date:
4. WORKSITE SUPERVISOR DECLARATION
I understand my responsibilities and will ensure that personnel under my supervision are fully briefed. I will ensure that all preparations
are complete and that all protective and rescue equipment are in place at all times while personnel are in the confined space. The
nominated Standby man has been fully briefed on his duties and responsibilities.
Worksite Supervisor Name: Signature: Date:
5. RECORD OF GAS TESTS (To be used to record any additional gas tests required during validity of Certificate)
Time
Oxygen
Hydrogen Sulphide
Flammable Gas
Other:
Initial
6. COMPLETION AND CERTIFICATE CLOSE OUT
The Confined Space is ready to close left open for re-entry For Re-Entry, a new Certificate must be applied for.
The vessel has been left in a safe condition with all tools and equipment removed barricaded off, and left open for re-entry
Worksite Supervisor Name: Signature: Date:
Permit Controller Name: Signature: Date:
Original: With Original of Work Permit 1st Copy: With 1st Copy of Work Permit 2nd Copy: With 2nd Copy of Work Permit Feb. 2013
INTER-DEPARTMENTAL PROCEDURE - OPERATIONS – DUKHAN FIELDS
PERMIT TO WORK SYSTEM – DUKHAN FIELDS IP-OPS-015
Page 36 of 47
STANDBY MAN:
Print Name: Signature: Date:
PART 3 - RECEIPT:
I hereby declare that I will ensure that all equipment will be kept at a safe distance from 33KV Overhead lines.
Signature: being the designated person of the Performing Authority
Date: Time:
PART 4 - CANCELLATION:
SHEET 1 OF 3
DUKHAN FIELDS PERMIT TO WORK SYSTEM
PERMIT No:
PERM IT COMPLIANCE AUDIT CHECKLIST
FACILITY: COLD HOT
PERMIT AUDITOR NAME: JOB TITLE:
Checklist t:
Section SPECIFICATION OF WORK Max. Points Score Total
1 1.1 Is the work description information full and accurate? 5
1.2 Is the correct permit category identified and used as stated 5
in procedure IP-OPS-015?
6.3 Are you satisfied that the Worksite Supv. is fully aw are of 10
w here the isolations are and understands the precautions?
9 9.1 Did the Permit Controller inspect the worksite prior to work 10
commencing?
9.2 Are you satisfied that the Permit Controller accepts 5
responsibility for the precautions / isolations as stated?
9.3 If there has been a transfer of control, has the oncoming 5
Permit Controller fully complied with IP-OPS-015?
SHIFT CHANGES
10 10.1 Are you satisfied that the oncoming Permit Controller is 10
f ully aw are of the work, precautions and isolations f or which
he has signed?
HANDBACK OF EQUIPMENT BY PERMIT APPLICANT
11 11.1 Are you satisfied that the worksite w as properly inspected by 10
the appropriate personnel in compliance with IP-OPS-015? (If
NO, award no points and move to next section)
11.2 Were all tools removed and w as the area properly cleaned? 5
11.3 If not, is the work continuing on another permit?
11.4 If a Long Term Isolation is required, has the appropriate 5
action been taken to raise the documentation?
AUDITOR'S RECOMMENDATIONS:
ORIGINATOR TO COMPLETE
Section No: Revision:
Title:
Attach a photocopy of the relevant documentation highlighting the part(s) requiring amendment.
Originator
Print Name: Signature: Date:
Department / Group:
Supervisor, Group Leader, Manager - Verification
Print Name: Signature: Date:
Permit Authority - Approval / Rejection
Print Name: Signature: Date:
Reason for Rejection:
Manager Signature
Print Name: Signature: Date:
OSC/3 TO COMPLETE
Print Name: Signature: Date Received:
IP-OPS-015, Att. P July, 2005
OSP/4
Responsibility
I E M C T S W I E M C T S W I E M C T S W I E M C
FSU
FSU/1
FSU/2
FSU/3
FSU/4
FSE
FST
FSM
IFM
PDD/RGD/NGD
Dukhan Township & QPAA Jabel Tank Farm Production Stations Dukhan Field (Outside Prod. Stns)
Responsibility
I E M C T S W I E M C T S W I E M C T S W I E M C
FSU
FSU/1
FSU/2
FSU/3 2 2
FSU/4 2 2
PERMIT TO WORK SYSTEM – DUKHAN FIELDS
FSE 1
FST
FSM 3
IFM 1 2 2 2 2
LEGEND
I - Instrument
E - Electrical (Operations & Distribution)
M - Mechanical (Oil & Gas Pipelines)
C - Civil
T - Telecommunication
S - Sewage (Collection & Drainage)
W - Water
IMPORTANT NOTE:
Drawings for proposed new pipes/cables/facilities routes & existing route of underground pipes/cables/facilities shall be
INTER-DEPARTMENTAL PROCEDURE - OPERATIONS – DUKHAN FIELDS
1 : FSE Shall be involved in Civil Excavation Clearance when activities come near FS assets such as Electrical Sub-Stations, Water & Sewage Pumping Stations inside Township & QPAA.
Page 46 of 47
Rating
0 - No/Not Available/Poor 1 - Partially Available/Not satisfactory
2 - Yes/Available/Good NA- Not Applicable
Rating
15. Is the workforce aware about the nearby jobs being carried out
by another QP/Contractor?
16. Do the QP/Contractor take care of the necessary safety
measures while doing the job that prevents damage to people/QP
asset?
17. Is confined space entry procedures / precautions being
followed?
Additional observation/comments.
>90 %
70-90 %
Rvn-23.05.2012