ENGINEER’s RESPONSE

Project Construction of Mumbai-Ahmedabad High Speed Rail (MAHSR) Package P1B


Ref. No. MGCPL/SITE/HSR-PKG1B/2022-23/1545 Revision 0
Received 02-10-
Title QAP of Fabrication of Launching Nose for Package-PKG-P1(B)
on 2022
Reviewed 04-10-
Review Code Notice of No Objection with Comments (NONOC)
on 2022
Other Ref. COR0000003147

Quality Drawing /
Components/
Clause check Document Characteristics Observations / Comments
Operations
Point No./IS Code
Incoming IS 2062- Number of test Sample shall be 2/cast/heat and a class of
1.4 Raw 2011 Chemical test steel product irrespective of cast/heat size and test shall be
Material Steel plate & Clause-08 conducted at an approved lab
Structural Mechanical test
IS 2062- Number of test Sample shall be 2/cast/heat and a class of
Sections Like ( UTS,YS ,%EI &
angels, 2011 Clause- steel product irrespective of cast/heat size and test shall be
Channels and 10 Bend test) conducted at an approved lab
1.5
Beam etc. IS 2062-
Impact test One test Sample shall be taken from thickest Product per
2011 Clause-
Cast/Heat and test shall be conducted at an approved lab
12
1.6 a) HSFG Bolt Standard test for Test on at least three Specimen shall be conducted at an
b) HSFG Nuts IS 4000
evaluation of Slip approved lab
c) HSFG Annex B
factor
washer IS Storage Care shall be Taken that bolts, Nuts and washers are stored in
4000:2003 such a way that they do not Deteriorate.
Clause-4.2
IS Bolts Nuts and washer which on visual inspection show any
4000:2003 Visual inspection evidence of physical defects shall be removed and replaced by
Clause-08 new one
Baking of Visual check of Electrodes that have absorbed an excessive amount of
Welding
3 Electrode, IRS B1-2001 electrode & Beating moisture should be re-baked in an oven
Process
Flux

Click or tap here to enter text.

____________________________________

[Reviewed by] [Endorsed by]


Note: Notwithstanding Engineer’s comments, responsibility of ensuring conformity to contractual, technical, and functional requirements lies with the
Contractor. Any non-compliances on the part of the Contractor in the preparation, submission or resubmission of Contractor’s Documents shall not constitute
a Variation.