- Survey the vessel 1 Day - Ask Kelly for status survey 1 Day - Ask operation for drawing and history docking 1 Day - Send email to Docking Manager
- Ask to procurement for vendor Engine and Electrical
- Ask approval to Docking Manager for give DRL to
shipyard so that they make prepare the material for repair the vessel 2 Docking - Check and survey with vendor (Shipyard, Mechanic M/E & A/E, Mechanic Electrical) 5 Day - List what the vendor finding at vessel (hull, engine, electrical) 1 Day - Make document amprahan 1 Day
- If vendor late give the result after their survey, send
document amprahan with Berita Acara and evindence 1 Day - Ask the crew for what they need it during dock for prepare before sail again 2 Day - Follow up to Docking Manager and kelly for done or not (approval) 1 Day