Professional Documents
Culture Documents
Contract Management
Lecture No. 05
Tender
Prerequisites for Invitation to Tender
Preparation of Tender Documents
PEC Bidding Documents
What is a Tender?
What is a Bid?
Tender
Tender
"Tender" means the Contractor's priced offer to the Employer for the
execution and completion of the Works and the remedying of any defects
therein in accordance with the provisions of the Contract, as accepted by the
Letter of Acceptance. – FIDIC
Types of Tender
Open Tender
Limited / Restricted / Selective Tender
Single Tender
Negotiated Tender
Item Rate Tender
Percentage Rate Tender
D. ARRANGEMENT OF FINANCES
− Local & Foreign Exchange Components
E. Land Acquisition
F. Prequalification of Contractors
Dr.-Ing Abdur Rehman Nasir
Assistant Professor of Construction Engineering and Management 03.10.2018
NIT (SCEE), NUST H-12, Islamabad 11
CE-898
Contract Management
This is the general notice issued by the client inviting tenders from the
prospective construction firms. This signifies the intention of the client to get
work executed by contract.
The purpose of this is to get competitive offer. A condensed text of N.I.T.
covering key features is advertised in newspaper. This condensed text is known
as “Tender Notice” or “Press Tender Notice”.
Dr.-Ing Abdur Rehman Nasir
Assistant Professor of Construction Engineering and Management 03.10.2018
NIT (SCEE), NUST H-12, Islamabad 13
CE-898
Contract Management
The amount of Bid Security should be a lump sum figure ranging from 1% to
3% of the likely cost of the Works or a percentage ranging from 1 % to 3 % of
the Bid Price.
Bid Preparation
Bidders’ Responses to the Invitation to Tender
Whatever time is allowed for bidders to prepare quotations to meet the
closing date, it never seems quite enough.
In the frenzied activity of estimating, the bidder sometimes overlooks the
inconsistencies and pitfalls introduced by the client, not by design, but as a
result of haste or carelessness in the composition of the bid package.
Most bidders are confident that they have read the bid package from cover to
cover before submitting their tenders but in reviewing the contract proper, it is
important not only to understand what is written therein but also to be aware
of what is left unwritten.
Dr.-Ing Abdur Rehman Nasir
Assistant Professor of Construction Engineering and Management 03.10.2018
NIT (SCEE), NUST H-12, Islamabad 34
CE-898
Contract Management
Unfortunately, some contractors are willing to accept this view and skip over
the articles in review as something to be accepted without question.
Indeed, most of the articles are reasonable, practical, and inserted for
purposes that few bidders would contest. On occasions, however, clients’
lawyers will slip in some clause that could be unfair to the contractor or, at
best, biased in favor of the owner.
Dr.-Ing Abdur Rehman Nasir
Assistant Professor of Construction Engineering and Management 03.10.2018
NIT (SCEE), NUST H-12, Islamabad 35
CE-898
Contract Management
i. Contractor shall comply with all applicable laws and regulations of all
governmental and other authorities having jurisdiction, including but not
limited to, laws and regulations regarding labor, taxes, and safety.
The bidder might inquire who pays extra taxes, and so forth, if these laws are revised during
the life of the contract. Probably the “other” authorities having jurisdiction should be listed.
Most articles are silent on any suggestion regarding the contractor’s right to terminate, but if
the bidder accepts this it may be worthwhile looking closely at the compensation to determine
if, when the contract is halted through no fault of the contractor, the amounts offered are
sufficient. The same applies to the suspension clause that may be actuated solely at the
convenience of the client.
Dr.-Ing Abdur Rehman Nasir
Assistant Professor of Construction Engineering and Management 03.10.2018
NIT (SCEE), NUST H-12, Islamabad 37
CE-898
Contract Management
Don’t be afraid to challenge the Articles of Agreement if you think they may be
weighted against you.
Finally, it should be mentioned that, because the articles are frequently taken
from a “model” contract, one or two clauses might creep in to the bid package
and be completely irrelevant to the work. On discovery, the client will usually
be quite willing to alter or delete them.
Scope of Work
Changes in Scope of Work
Materials
Specifications and Drawings
Alternate Proposals
Tendering Process
The tendering process, which leads towards the award of a main or prime
contract to the main contractor, is complex and generally follows four distinct
stages.
Stage 1
Subcontractors and suppliers of materials prepare bid prices and quotations to
be used by main (general) contractors.
Subcontractors and suppliers will be invited by bidding main contractors to
supply bid prices for specific project activities and materials.
Tendering Process
Stage 1
A structure of the bill of quantities facilitates a relatively easy break-up of the
bill into specific trade sections for use by bidding subcontractors. The bill of
quantities is also highly suitable for use by suppliers of materials.
Tendering Process
Stage 2
A main contractor compiles a tender either from the real subcontractors’ bids
or from target costs allowed for different trade items, or from both. Material
costs, preliminaries and the markup costs are then added. Some contractors
prefer to develop their own estimates of subcontract work.
A main contractor combines the best subcontract and supply bid prices with
an estimate of preliminaries and mark-up to form a competitive bid price.
Tendering Process
Stage 2
It is interesting to note that on building projects, the bids of subcontractors
and suppliers generally amount to at least two-thirds of a contractor’s tender
price (assuming that preliminaries range between 10 and 15 per cent, and the
mark-up between 15 and 20 per cent).
Tendering Process
Stage 2
The total tender price is then a function of the main contractor’s preliminaries,
subcontractors’ and suppliers’ bid prices, the main contractor’s mark-up, and
the magnitude of the risk allowance. It can be expressed by the following
equation:
TTP = f((GCP + SUM SCB + SUM SB) + GCMP + RA)
where:
- TTP = total tender price - GCP = main contractor’s preliminaries
- SCB = subcontractors’ bid prices - SB = suppliers’ bid prices
- GCMP = main contractor’s mark-up - RA = risk allowance
Dr.-Ing Abdur Rehman Nasir
Assistant Professor of Construction Engineering and Management 03.10.2018
NIT (SCEE), NUST H-12, Islamabad 44
CE-898
Contract Management
Tendering Process
Stage 2
It would be too simple when analyzing a tender price to consider the main
contractor’s risks only. Subcontractors and suppliers are also exposed to risks
and will make appropriate allowances for such risks in their bid prices.
Tendering Process
Stage 3
In the evaluation of submitted tenders, the ‘best tender’ is selected and the
contract is awarded to the respective main contractor.
General contracts and subcontracts are usually awarded to the best tenderer.
How the term ‘best tender’ is interpreted undoubtedly, depends on the
perception of risk.
Where the project risks are seen as insignificant, the ‘best tender’ will most
likely be the lowest priced tender, provided it is within an acceptable margin
from the principal’s/engineer’s estimate.
Tendering Process
Stage 3
In the presence of a moderate to high risk, however, the term ‘best tender’ will
commonly be a bid in the range between the lowest and the mean tender
prices. The selection of the lowest tender on high-risk projects would normally
be regarded as a risky decision.
Tendering is similar to auctions and requires knowledge of the construction
industry, application of common sense, and a feel for the market. It is a
complex process that brings together a number of bidders, each with only one
objective in mind i.e. to win a job.
Tendering Process
Stage 3
Despite its complexity, competitive tendering ultimately leads to the selection
of a successful bidder.
But until the winning tenderer is announced, the tendering process is riddled
with uncertainty.
Tenderers do not know how accurate, complete and competitive their bids are,
whether they are free of mistakes, how good or bad various assumptions will
be, or whether the tendering process will be conducted ethically.
Tendering Process
Stage 3
The evaluator(s) may also not be sure how accurate tender prices are and to
what extent they cover the project risk. Nevertheless, the outcome of this
stage should be the selection of the best tender.
Tendering Process
Stage 4
After the award of the contract, the successful main contractor will select
subcontractors and suppliers on the basis of meeting or bettering the real or
target cost provisions for different trades made in the tender.
Tendering Process
Stage 4
Such events are almost always linked to unrealistically low subcontract prices
and the presence of difficult subcontract conditions. Problems in executing just
one subcontract may cause overruns in project cost and time.
Industry Practices
Second Stage:
After agreement between the procuring agency and the bidders on the
technical requirements, bidders who are willing to conform to the
revised technical specifications and whose bids have not already been
rejected shall submit a revised technical proposal and supplementary
financial proposal, according to the technical requirement.
The revised technical proposal along with the original financial proposal
and supplementary financial proposal shall be opened at a date, time
and venue announced in advance by the procuring agency.
Thank You!
Any queries??