You are on page 1of 1

Activities – Precedence networks

1. Draw a precedence network given the following project data.


Tasks Precedence Time

a - 2 weeks

b - 4 weeks

c - 3 weeks

d a 3 weeks

e a 5 weeks

f c 6 weeks

g c 4 weeks

h d 4 weeks

i d 8 week

j b, e, f, i 2 weeks

k - 4 weeks

l g, k 3 weeks

i) What is the duration of the project


ii) Identify the critical path

You might also like