Activities – On arrow networks

1. i) Draw an on arrow network for the following project data


Task Precedence Duration (Days)

A - 5

B - 4

C A 6

D B 2

E B 5

F C,D 8

ii) What is the duration of the project?

iii) Describe the critical path

2. Draw an on arrow network given the following project data.


Tasks Precedence Time

a - 2 weeks

b - 4 weeks

c - 3 weeks

d a 3 weeks

e a 5 weeks

f c 6 weeks

g c 4 weeks

h d 4 weeks

i d 8 week

j b, e, f, i 2 weeks

k - 4 weeks

l g, k 3 weeks

i) What is the duration of the project


ii) Identify the critical path