SIPL/EPC-06/HW/41 Dismantling of existing BT surface BT Scr 77+220 78+000 BHS 3/13/2020 3/14/2020

SIPL/EPC-06/HW/43 Dismantling of existing BT surface BT Scr 78+740 79+060 BHS 3/14/2020 3/15/2020

SIPL/EPC-06/HW/45 Dismantling of existing BT surface BT Scr 78+000 78+740 BHS 3/15/2020 3/16/2020

SIPL/EPC-06/HW/49 Dismantling of existing BT surface BT Scr 79+060 79+650 BHS 3/17/2020 3/18/2020

SIPL/EPC-06/HW/61 Earthwork in excavation for SG Top Excavation 78+740 79+060 LHS 4/10/2020 4/11/2020

SIPL/EPC-06/HW/67 Level & FDD Checking of Subgrade Top layer SG Top 79+060 79+140 LHS 4/11/2020 4/12/2020

SIPL/EPC-06/HW/70 Level & FDD Checking of Subgrade Top layer SG Top 78+000 78+740 Rhs 4/12/2020 4/13/2020 Not Done

SIPL/EPC-06/HW/71 Level & FDD Checking of Subgrade Top layer SG Top 78+350 78+740 LHS 4/12/2020 4/13/2020

SIPL/EPC-06/HW/78 Level & FDD Checking of Subgrade Top layer SG Top 79+060 79+140 RHS 4/15/2020 4/16/2020

SIPL/EPC-06/HW/79 Level & FDD Checking of Subgrade Top layer SG Top 78+000 78+350 LHS 4/15/2020 4/16/2020

SIPL/EPC-06/HW/86 Level & FDD Checking of Subgrade Top layer SG Top 78+000 78+740 Rhs 4/17/2020 4/18/2020

SIPL/EPC-06/HW/87 Earthwork in excavation for SG Top Excavation 78+740 79+060 Rhs 4/17/2020 4/18/2020

SIPL/EPC-06/HW/92 Level & FDD Checking of Subgrade Top layer SG Top 77+630 78+000 LHS 4/18/2020 4/19/2020

SIPL/EPC-06/HW/96 Level & FDD Checking of Subgrade Top layer SG Top 79+140 79+640 LHS 4/19/2020 4/20/2020

SIPL/EPC-06/HW/98 Level & FDD Checking of Subgrade Top layer SG Top 78+350 78+740 RHS 4/19/2020 4/20/2020

SIPL/EPC-06/HW/100 Level & FDD Checking of Subgrade Top layer SG Top 77+300 77+630 LHS 4/20/2020 4/21/2020

SIPL/EPC-06/HW/102 Level & FDD Checking of Subgrade Top layer SG Top 78+000 78+350 RHS 4/21/2020 4/22/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

SIPL/EPC-06/HW/106 Level & FDD Checking of Subgrade Top layer SG Top 79+140 79+640 RHS 4/22/2020 4/23/2020

SIPL/EPC-06/HW/112 Level & FDD Checking of Subgrade Top layer SG Top 77+630 78+000 RHS 4/27/2020 4/28/2020

SIPL/EPC-06/HW/113 Dismantling of existing BT surface BT Scr 79+650 79+960 BHS 4/27/2020 4/28/2020

SIPL/EPC-06/HW/120 Level & FDD Checking of Subgrade Top layer SG Top 77+300 77+630 RHS 4/30/2020 5/1/2020

SIPL/EPC-06/HW/131 FDD Checking of Sub grade 1st layer SG 1st 79+700 79+960 LHS 5/3/2020 5/4/2020

SIPL/EPC-06/HW/134 Level & FDD Checking of Subgrade Top layer SG Top 79+700 79+960 LHS 5/4/2020 5/5/2020

SIPL/EPC-06/HW/170 FDD Checking of Embt Top EMB 79+700 79+960 RHS 5/17/2020 5/18/2020

SIPL/EPC-06/HW/176 FDD Checking of Sub grade 1st layer SG 1st 79+700 79+960 RHS 5/18/2020 5/19/2020

SIPL/EPC-06/HW/179 Level & FDD Checking of Subgrade Top layer SG Top 79+700 79+960 RHS 5/19/2020 5/20/2020

SIPL/EPC-06/HW/182 Dismantling of existing BT surface BT Scr 79+960 80+220 BHS 5/19/2020 5/20/2020

SIPL/EPC-06/HW/209 Level & FDD Checking of Subgrade Top layer SG Top 80+000 80+220 RHS 5/26/2020 5/27/2020

SIPL/EPC-06/HW/210 Level & FDD Checking For GSB layer GSB 78+300 78+740 RHS 5/26/2020 5/27/2020

SIPL/EPC-06/HW/239 Level & FDD Checking of Subgrade Top layer SG Top 80+000 80+220 LHS 6/2/2020 6/3/2020

SIPL/EPC-06/HW/242 Dismantling of existing BT surface BT Scr 80+220 80+460 BHS 6/3/2020 6/4/2020

SIPL/EPC-06/HW/257 Level & FDD Checking of Subgrade Top layer SG Top 80+220 80+440 LHS 6/7/2020 6/8/2020

SIPL/EPC-06/HW/272 Level & FDD Checking of Subgrade Top layer SG Top 80+220 80+460 Rhs 6/10/2020 6/11/2020

SIPL/EPC-06/HW/275 Level & FDD Checking For GSB layer GSB 78+740 79+000 RHS 6/10/2020 6/11/2020

SIPL/EPC-06/HW/278 Level & FDD Checking For GSB layer GSB 78+000 78+300 RHS 6/10/2020 6/11/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

SIPL/EPC-06/HW/281 Level & FDD Checking For GSB layer GSB 77+300 78+000 RHS 6/11/2020 6/12/2020

SIPL/EPC-06/HW/284 Dismantling of existing BT surface BT Scr 77+000 77+220 BHS 6/11/2020 6/12/2020

SIPL/EPC-06/HW/286 FDD Checking of Embt Top EMB 76+720 76+980 LHS 6/14/2020 6/15/2020

SIPL/EPC-06/HW/296 Level & FDD Checking of Subgrade Top layer SG Top 77+030 77+220 Rhs 6/17/2020 6/18/2020

SIPL/EPC-06/HW/299 Level & FDD Checking For GSB layer GSB 77+030 77+220 RHS 6/18/2020 6/19/2020

EPC-06/HW/301 Dismantling of existing BT surface BT Scr 76+560 77+000 BHS 6/19/2020 6/20/2020

SIPL/EPC-06/HW/304 FDD Checking of Sub grade 1st layer SG 1st 76+720 76+980 LHS 6/20/2020 6/21/2020

SIPL/EPC-06/HW/317 Level & FDD Checking of Subgrade Top layer SG Top 77+030 77+220 LHS 6/22/2020 6/23/2020

SIPL/EPC-06/HW/320 Dismantling of existing BT surface BT Scr 76+120 76+560 BHS 6/23/2020 6/24/2020

SIPL/EPC-06/HW/324 Level & FDD Checking of Subgrade Top layer SG Top 76+720 76+980 LHS 6/23/2020 6/24/2020

SIPL/EPC-06/HW/332 FDD Checking of Embt Top EMB 76+280 76+560 LHS 6/24/2020 6/25/2020

SIPL/EPC-06/HW/338 FDD Checking of Sub grade 1st layer SG 1st 76+280 76+560 LHS 6/25/2020 6/26/2020

SIPL/EPC-06/HW/341 Level & FDD Checking of Subgrade Top layer SG Top 76+280 76+560 LHS 6/25/2020 6/26/2020

SIPL/EPC-06/HW/353 FDD Checking of Embt Top EMB 79+700 79+960 LHS 6/30/2020 7/1/2020

SIPL/EPC-06/HW/359 FDD Checking of Embt Top EMB 76+280 76+560 RHS 6/30/2020 7/1/2020

SIPL/EPC-06/HW/365 FDD Checking of Sub grade 1st layer SG 1st 76+280 76+560 RHS 7/1/2020 7/2/2020

SIPL/EPC-06/HW/368 Level & FDD Checking of Subgrade Top layer SG Top 76+280 76+560 RHS 7/2/2020 7/3/2020

SIPL/EPC-06/HW/383 Level & FDD Checking of Subgrade Top layer SG Top 76+060 76+280 Rhs 7/7/2020 7/8/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

SIPL/EPC-06/HW/398 Level & FDD Checking of Subgrade Top layer SG Top 76+160 76+280 LHS 7/12/2020 7/13/2020

SIPL/EPC-06/HW/416 Dismantling of existing BT surface BT Scr 75+700 76+120 BHS 7/14/2020 7/15/2020

SIPL/EPC-06/HW/428 Dismantling of existing BT surface BT Scr 75+180 75+700 BHS 7/16/2020 7/17/2020 Not Done

SIPL/EPC-06/HW/431 Dismantling of existing BT surface BT Scr 75+180 75+700 BHS 7/19/2020 7/20/2020

SIPL/EPC-06/HW/455 Level & FDD Checking of Subgrade Top layer SG Top 75+180 75+700 LHS 7/22/2020 7/23/2020

SIPL/EPC-06/HW/458 Level & FDD Checking For GSB layer GSB 75+180 75+700 LHS 7/23/2020 7/24/2020

SIPL/EPC-06/HW/461 Dismantling of existing BT surface BT Scr 74+700 75+180 BHS 7/23/2020 7/24/2020

SIPL/EPC-06/HW/473 Level & FDD Checking of Subgrade Top layer SG Top 74+700 74+980 LHS 7/27/2020 7/28/2020

SIPL/EPC-06/HW/500 Level & FDD Checking of Subgrade Top layer SG Top 75+180 75+700 RHS 7/30/2020 7/31/2020

SIPL/EPC-06/HW/536 FDD Checking of Embt Top EMB 70+090 70+280 LHS 8/6/2020 8/7/2020

SIPL/EPC-06/HW/545 FDD Checking of Embt Top EMB 70+335 70+430 LHS 8/6/2020 8/7/2020

SIPL/EPC-06/HW/558 Dismantling of existing BT surface BT Scr 70+090 70+710 BHS 8/6/2020 8/7/2020

SIPL/EPC-06/HW/560 FDD Checking of Sub grade 1st layer SG 1st 70+090 70+280 RHS 8/9/2020 8/10/2020

SIPL/EPC-06/HW/566 FDD Checking of Sub grade 1st layer SG 1st 70+335 70+430 RHS 8/9/2020 8/10/2020

SIPL/EPC-06/HW/572 Level & FDD Checking of Subgrade Top layer SG Top 70+090 70+280 RHS 8/9/2020 8/10/2020

SIPL/EPC-06/HW/578 FDD Checking of Embt Top EMB 70+460 70+710 LHS 8/9/2020 8/10/2020

SIPL/EPC-06/HW/581 FDD Checking of Subgrade 1st layer SG 1st 70+460 70+710 LHS 8/9/2020 8/10/2020

SIPL/EPC-06/HW/584 Level & FDD Checking of Subgrade Top layer SG Top 70+460 70+710 LHS 8/9/2020 8/10/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

SIPL/EPC-06/HW/593 FDD Checking of Embt Top EMB 70+750 70+900 LHS 8/12/2020 8/13/2020

SIPL/EPC-06/HW/599 Dismantling of existing BT surface BT Scr 70+710 71+150 BHS 8/12/2020 8/13/2020

SIPL/EPC-06/HW/603 Level & FDD Checking of Subgrade Top layer SG Top 70+335 70+430 RHS 8/12/2020 8/13/2020

SIPL/EPC-06/HW/605 FDD Checking of Subgrade 1st layer SG 1st 70+750 70+900 LHS 8/13/2020 8/14/2020

SIPL/EPC-06/HW/611 Level & FDD Checking of Subgrade Top layer SG Top 70+750 70+900 LHS 8/16/2020 8/17/2020

SIPL/EPC-06/HW/653 Dismantling of existing BT surface BT Scr 71+150 71+600 BHS 8/24/2020 8/25/2020

SIPL/EPC-06/HW/670 Level & FDD Checking of Subgrade Top layer SG Top 71+350 71+600 LHS 8/26/2020 8/27/2020

SIPL/EPC-06/HW/677 Level & FDD Checking of Subgrade Top layer SG Top 75+700 75+830 RHS 8/27/2020 8/28/2020

SIPL/EPC-06/HW/680 Level & FDD Checking of Subgrade Top layer SG Top 75+850 75+900 RHS 8/27/2020 8/28/2020

SIPL/EPC-06/HW/695 Dismantling of existing BT surface BT Scr 71+600 72+000 BHS 8/29/2020 8/30/2020

SIPL/EPC-06/HW/697 Dismantling of existing BT surface BT Scr 74+300 74+700 BHS 8/29/2020 8/30/2020

SIPL/EPC-06/HW/704 Dismantling of existing BT surface BT Scr 72+500 73+000 BHS 8/30/2020 8/31/2020

SIPL/EPC-06/HW/725 Dismantling of existing BT surface BT Scr 72+150 72+500 BHS 9/3/2020 9/4/2020

SIPL/EPC-06/HW/730 Level & FDD Checking For GSB layer GSB 75+700 75+830 RHS 9/4/2020 9/5/2020

SIPL/EPC-06/HW/731 Level & FDD Checking For GSB layer GSB 75+850 75+900 RHS 9/4/2020 9/5/2020

SIPL/EPC-06/HW/733 Level & FDD Checking of Subgrade Top layer SG Top 72+220 72+360 RHS 9/4/2020 9/5/2020

SIPL/EPC-06/HW/739 FDD and level checking of DLC laying DLC 75+770 75+830 RHS 9/5/2020 9/6/2020

SIPL/EPC-06/HW/741 Level & FDD Checking of Subgrade Top layer SG Top 72+360 72+800 RHS 9/6/2020 9/7/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

SIPL/EPC-06/HW/742 FDD and level checking of DLC laying DLC 75+730 75+770 RHS 9/6/2020 9/7/2020

SIPL/EPC-06/HW/743 Dismantling of existing BT surface BT Scr 73+720 74+300 BHS 9/7/2020 9/8/2020

SIPL/EPC-06/HW/744 Dismantling of existing BT surface BT Scr 73+000 73+420 BHS 9/7/2020 9/8/2020

SIPL/EPC-06/HW/745 FDD Checking of Sub grade 1st layer SG 1st 73+120 73+300 RHS 9/8/2020 9/9/2020

SIPL/EPC-06/HW/746 Exc up to EMB Top Excavation 73+120 73+300 RHS 9/7/2020 9/8/2020

SIPL/EPC-06/HW/748 FDD and level checking of DLC laying DLC 75+700 75+730 RHS 9/8/2020 9/9/2020

SIPL/EPC-06/HW/758 Level & FDD Checking of Subgrade Top layer SG Top 72+870 73+045 RHS 9/10/2020 9/11/2020

EPC-06/HW/759 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+810 75+824 RHS 9/12/2020 9/13/2020

SIPL/EPC-06/HW/761 Level & FDD Checking of Subgrade Top layer SG Top 73+120 73+300 RHS 9/13/2020 9/14/2020

SIPL/EPC-06/HW/762 Level & FDD Checking For GSB layer GSB 79+000 79+140 RHS 9/13/2020 9/14/2020

SIPL/EPC-06/HW/763 Level & FDD Checking of Subgrade Top layer SG Top 74+300 74+700 LHS 9/13/2020 9/14/2020

EPC-06/HW/769 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+765 75+810 RHS 9/17/2020 9/18/2020

EPC-06/HW/777 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+724 75+765 RHS 9/20/2020 9/21/2020

EPC-06/HW/783 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+700 75+724 RHS 9/24/2020 9/25/2020

SIPL/EPC-06/HW/785 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 75+750 75+820 RHS 9/25/2020 9/26/2020

SIPL/EPC-06/HW/788 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 75+700 75+750 RHS 9/26/2020 9/27/2020

SIPL/EPC-06/HW/791 FDD and level checking of DLC laying DLC 75+850 75+900 RHS 9/27/2020 9/28/2020

SIPL/EPC-06/HW/794 Earthwork in excavation for SG Top Excavation 71+100 71+200 LHS 9/30/2020 10/1/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

SIPL/EPC-06/HW/798 Level & FDD Checking For GSB layer GSB 71+100 71+180 LHS 10/2/2020 10/3/2020

SIPL/EPC-06/HW/799 FDD and level checking of DLC laying DLC 71+100 71+180 LHS 10/2/2020 10/3/2020

SIPL/EPC-06/HW/800 Level & FDD Checking of Subgrade Top layer SG Top 71+200 71+350 LHS 10/2/2020 10/3/2020

EPC-06/HW/802 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+859 75+900 RHS 10/3/2020 10/4/2020

SIPL/EPC-06/HW/805 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 75+860 75+900 RHS 10/4/2020 10/5/2020

SIPL/EPC-06/HW/807 Level & FDD Checking For GSB layer GSB 71+180 71+300 LHS 10/5/2020 10/6/2020

SIPL/EPC-06/HW/811 Level & FDD Checking For GSB layer GSB 71+300 71+400 LHS 10/7/2020 10/8/2020

SIPL/EPC-06/HW/812 FDD and level checking of DLC laying DLC 71+180 71+215 LHS 10/7/2020 10/8/2020

SIPL/EPC-06/HW/815 FDD and level checking of DLC laying DLC 71+215 71+270 LHS 10/8/2020 10/9/2020

EPC-06/HW/816 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+100 71+134 LHS 10/8/2020 10/9/2020

EPC-06/HW/819 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+134 71+147 LHS 10/9/2020 10/10/2020

EPC-06/HW/822 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+147 71+211 LHS 10/10/2020 10/11/2020

SIPL/EPC-06/HW/823 Level & FDD Checking For GSB layer GSB 71+400 71+500 LHS 10/10/2020 10/11/2020

SIPL/EPC-06/HW/825 FDD and level checking of DLC laying DLC 71+270 71+290 LHS 10/11/2020 10/12/2020

SIPL/EPC-06/HW/826 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+100 71+150 LHS 10/11/2020 10/12/2020

EPC-06/HW/829 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+150 71+185 LHS 10/12/2020 10/13/2020

EPC-06/HW/830 FDD and level checking of DLC laying DLC 71+290 71+350 LHS 10/12/2020 10/13/2020

EPC-06/HW/833 FDD and level checking of DLC laying DLC 71+350 71+400 LHS 10/13/2020 10/14/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/836 FDD and level checking of DLC laying DLC 71+400 71+440 LHS 10/14/2020 10/15/2020

EPC-06/HW/837 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+211 71+230 LHS 10/14/2020 10/15/2020

EPC-06/HW/839 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+185 71+200 LHS 10/14/2020 10/15/2020

EPC-06/HW/840 FDD and level checking of DLC laying DLC 71+440 71+520 LHS 10/15/2020 10/16/2020

EPC-06/HW/841 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+230 71+264 LHS 10/15/2020 10/16/2020

EPC-06/HW/842 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+264 71+310 LHS 10/16/2020 10/17/2020

EPC-06/HW/843 Level & FDD Checking For GSB layer GSB 71+500 71+600 LHS 10/16/2020 10/17/2020

EPC-06/HW/847 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+310 71+350 LHS 10/17/2020 10/18/2020

EPC-06/HW/848 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+200 71+270 LHS 10/18/2020 10/19/2020

EPC-06/HW/852 Level & FDD Checking of Subgrade Top layer SG Top 71+740 71+900 RHS 10/19/2020 10/20/2020

EPC-06/HW/857 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+270 71+350 LHS 10/20/2020 10/21/2020

EPC-06/HW/859 FDD and level checking of DLC laying DLC 71+520 71+585 LHS 10/20/2020 10/21/2020

EPC-06/HW/863 FDD and level checking of DLC laying DLC 71+585 71+600 LHS 10/21/2020 10/22/2020

EPC-06/HW/869 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+350 71+385 LHS 10/22/2020 10/23/2020 Not Done

EPC-06/HW/873 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+350 71+385 LHS 10/23/2020 10/24/2020

EPC-06/HW/878 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+385 71+419 LHS 10/25/2020 10/26/2020

EPC-06/HW/884 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+419 71+476 LHS 10/26/2020 10/27/2020

EPC-06/HW/891 Level & FDD Checking of Subgrade Top layer SG Top 74+000 74+180 LHS 10/27/2020 10/28/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/895 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+350 71+450 LHS 10/28/2020 10/29/2020

EPC-06/HW/898 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+450 71+480 LHS 10/29/2020 10/30/2020

EPC-06/HW/900 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+476 71+540 LHS 10/29/2020 10/30/2020

EPC-06/HW/901 Level & FDD Checking For GSB layer GSB 74+030 74+180 LHS 10/29/2020 10/30/2020

EPC-06/HW/902 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+480 71+540 LHS 10/30/2020 10/31/2020

EPC-06/HW/903 FDD and level checking of DLC laying DLC 74+040 74+170 LHS 10/30/2020 10/31/2020

EPC-06/HW/905 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+540 71+600 LHS 10/31/2020 11/1/2020 Not Done

EPC-06/HW/908 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+540 71+600 LHS 11/4/2020 11/5/2020

EPC-06/HW/912 Level and FDD checking of subgrade Top layer SG Top 73+770 74+000 LHS 11/6/2020 11/7/2020

EPC-06/HW/913 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+540 71+600 LHS 11/6/2020 11/7/2020

EPC-06/HW/915 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+140 74+170 LHS 11/7/2020 11/8/2020

EPC-06/HW/920 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+064 74+140 LHS 11/8/2020 11/9/2020

EPC-06/HW/922 Level & FDD Checking For GSB layer GSB 73+900 74+030 LHS 11/8/2020 11/9/2020

EPC-06/HW/934 Level and FDD checking of DLC layer DLC 73+900 74+040 LHS 11/11/2020 11/12/2020

EPC-06/HW/938 Level & FDD Checking For GSB layer GSB 73+770 73+900 LHS 11/12/2020 11/13/2020

EPC-06/HW/942 Level and FDD checking of DLC layer DLC 73+790 73+900 LHS 11/15/2020 11/16/2020

EPC-06/HW/945 Level and FDD checking of subgrade Top layer SG Top 75+700 75+900 LHS 11/16/2020 11/17/2020

EPC-06/HW/949 Level and FDD checking of DLC layer DLC 73+770 73+790 LHS 11/16/2020 11/17/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/952 Level and FDD checking of subgrade Top layer SG Top 71+600 71+740 LHS 11/17/2020 11/18/2020

EPC-06/HW/956 Level & FDD Checking For GSB layer GSB 71+600 71+740 LHS 11/18/2020 11/19/2020

EPC-06/HW/961 Level & FDD Checking For GSB layer GSB 75+700 75+830 LHS 11/19/2020 11/20/2020

EPC-06/HW/965 Level and FDD checking of DLC layer DLC 75+700 75+830 LHS 11/20/2020 11/21/2020

EPC-06/HW/968 Level & FDD Checking For GSB layer GSB 79+700 79+940 LHS 11/21/2020 11/22/2020

EPC-06/HW/970 Level and FDD checking of subgrade Top layer SG Top 74+170 74+300 LHS 11/21/2020 11/22/2020

EPC-06/HW/973 Level & FDD Checking For GSB layer GSB 80+020 80+420 LHS 11/22/2020 11/23/2020

EPC-06/HW/978 Level & FDD Checking For GSB layer GSB 75+830 75+900 LHS 11/23/2020 11/24/2020

EPC-06/HW/989 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 74+087 74+170 LHS 11/26/2020 11/27/2020

EPC-06/HW/992 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 74+064 74+087 LHS 11/27/2020 11/28/2020

EPC-06/HW/993 Level & FDD Checking For GSB layer GSB 74+170 74+980 LHS 11/27/2020 11/28/2020

EPC-06/HW/997 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+000 74+064 LHS 11/28/2020 11/29/2020

EPC-06/HW/1002 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+948 74+000 LHS 11/29/2020 11/30/2020

EPC-06/HW/1004 Level & FDD Checking For GSB layer GSB 79+140 79+640 RHS 11/30/2020 12/1/2020

EPC-06/HW/1007 Level and FDD checking of DLC layer DLC 75+830 75+900 LHS 11/30/2020 12/1/2020

EPC-06/HW/1013 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+920 73+948 LHS 12/2/2020 12/3/2020

EPC-06/HW/1014 Level and FDD checking of subgrade Top layer SG Top 71+100 71+400 RHS 12/2/2020 12/3/2020

EPC-06/HW/1017 FDD Checking of WMM 1st layer WMM-I 80+020 80+420 LHS 12/3/2020 12/4/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1018 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+848 73+920 LHS 12/3/2020 12/4/2020

EPC-06/HW/1020 Level and FDD checking of subgrade Top layer SG Top 71+900 72+220 RHS 12/4/2020 12/5/2020

EPC-06/HW/1021 FDD Checking of WMM 1st layer WMM-I 79+700 79+940 LHS 12/4/2020 12/5/2020

EPC-06/HW/1022 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+770 73+848 LHS 12/4/2020 12/5/2020

EPC-06/HW/1025 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 74+020 74+064 LHS 12/5/2020 12/6/2020

EPC-06/HW/1026 Level and FDD checking of subgrade Top layer SG Top 71+400 71+600 RHS 12/5/2020 12/6/2020

EPC-06/HW/1029 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+930 74+020 LHS 12/6/2020 12/7/2020

EPC-06/HW/1032 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+830 73+930 LHS 12/7/2020 12/8/2020

EPC-06/HW/1033 Level & FDD Checking For GSB layer GSB 71+100 71+400 RHS 12/7/2020 12/8/2020

EPC-06/HW/1036 Level and FDD checking of DLC layer DLC 71+100 71+240 RHS 12/8/2020 12/9/2020

EPC-06/HW/1037 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+770 73+830 LHS 12/8/2020 12/9/2020

EPC-06/HW/1041 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+880 75+900 LHS 12/9/2020 12/10/2020

EPC-06/HW/1044 Level and FDD checking of DLC layer DLC 71+240 71+370 RHS 12/10/2020 12/11/2020

EPC-06/HW/1048 Level & FDD Checking For GSB layer GSB 71+400 71+460 RHS 12/11/2020 12/12/2020

EPC-06/HW/1049 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+820 75+880 LHS 12/11/2020 12/12/2020

EPC-06/HW/1053 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+750 75+820 LHS 12/12/2020 12/13/2020

EPC-06/HW/1062 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+700 75+750 LHS 12/13/2020 12/14/2020

EPC-06/HW/1064 Level and FDD checking of DLC layer DLC 71+370 71+440 RHS 12/13/2020 12/14/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1071 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 75+800 75+900 LHS 12/15/2020 12/16/2020

EPC-06/HW/1072 Level & FDD Checking For GSB layer GSB 71+460 71+600 RHS 12/15/2020 12/16/2020

EPC-06/HW/1079 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 75+700 75+800 LHS 12/17/2020 12/18/2020

EPC-06/HW/1084 Level and FDD checking of DLC layer DLC 71+440 71+510 RHS 12/18/2020 12/19/2020

EPC-06/HW/1087 Dismantling of existing BT surface BT Scr 73+420 73+720 BHS 12/19/2020 12/20/2020

EPC-06/HW/1088 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+100 71+185 RHS 12/19/2020 12/20/2020

EPC-06/HW/1089 Level and FDD checking of DLC layer DLC 71+510 71+580 RHS 12/19/2020 12/20/2020

EPC-06/HW/1090 Level & FDD Checking of Subgrade Top layer SG Top 76+720 77+030 RHS 12/19/2020 12/20/2020

EPC-06/HW/1092 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+185 71+230 RHS 12/20/2020 12/21/2020

EPC-06/HW/1093 Level & FDD Checking For GSB layer GSB 76+720 77+030 RHS 12/20/2020 12/21/2020

EPC-06/HW/1094 Level & FDD Checking of Subgrade Top layer SG Top 73+620 73+770 RHS 12/20/2020 12/21/2020

EPC-06/HW/1095 Level and FDD checking of DLC layer DLC 71+580 71+600 RHS 12/20/2020 12/21/2020

EPC-06/HW/1096 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+230 71+295 RHS 12/21/2020 12/22/2020

EPC-06/HW/1097 Dismantling of existing BT surface BT Scr 86+530 86+800 BHS 12/21/2020 12/22/2020

EPC-06/HW/1100 Level & FDD Checking For GSB layer GSB 76+060 76+560 RHS 12/22/2020 12/23/2020

EPC-06/HW/1101 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+295 71+396 RHS 12/22/2020 12/23/2020

EPC-06/HW/1103 Level & FDD Checking of Subgrade Top layer SG Top 86+530 86+650 LHS 12/22/2020 12/23/2020

EPC-06/HW/1104 Level & FDD Checking of Subgrade Top layer SG Top 73+400 73+560 RHS 12/22/2020 12/23/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1107 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+396 71+472 RHS 12/23/2020 12/24/2020

EPC-06/HW/1108 Level & FDD Checking of Subgrade Top layer SG Top 86+650 86+800 LHS 12/23/2020 12/24/2020

EPC-06/HW/1110 Level & FDD Checking For GSB layer GSB 73+620 73+770 RHS 12/23/2020 12/24/2020

EPC-06/HW/1111 Level & FDD Checking of Subgrade Top layer SG Top 73+300 73+350 RHS 12/24/2020 12/25/2020

EPC-06/HW/1112 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+472 71+531 RHS 12/24/2020 12/25/2020

EPC-06/HW/1113 Dismantling of existing BT surface BT Scr 88+960 89+270 BHS 12/24/2020 12/25/2020

EPC-06/HW/1114 Level & FDD Checking For GSB layer GSB 86+530 86+700 LHS 12/24/2020 12/25/2020

EPC-06/HW/1117 Level and FDD checking of DLC layer DLC 86+590 86+660 LHS 12/25/2020 12/26/2020

EPC-06/HW/1118 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+531 71+600 RHS 12/25/2020 12/26/2020

EPC-06/HW/1120 Level & FDD Checking For GSB layer GSB 73+400 73+560 RHS 12/25/2020 12/26/2020

EPC-06/HW/1123 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+100 71+180 RHS 12/26/2020 12/27/2020

EPC-06/HW/1125 Level & FDD Checking For GSB layer GSB 73+120 73+350 RHS 12/26/2020 12/27/2020

EPC-06/HW/1127 Level and FDD checking of DLC layer DLC 86+530 86+590 LHS 12/27/2020 12/28/2020

EPC-06/HW/1128 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+180 71+242 RHS 12/27/2020 12/28/2020

EPC-06/HW/1130 Level & FDD Checking For GSB layer GSB 86+700 86+800 LHS 12/27/2020 12/28/2020

EPC-06/HW/1131 Level & FDD Checking For GSB layer GSB 70+750 70+900 LHS 12/27/2020 12/28/2020

EPC-06/HW/1133 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+242 71+346 RHS 12/28/2020 12/29/2020

EPC-06/HW/1134 Level & FDD Checking of Subgrade Top layer SG Top 88+960 89+270 LHS 12/28/2020 12/29/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1135 Level & FDD Checking For GSB layer GSB 70+460 70+710 LHS 12/28/2020 12/29/2020

EPC-06/HW/1136 Level and FDD checking of DLC layer DLC 86+660 86+680 LHS 12/28/2020 12/29/2020

EPC-06/HW/1137 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+346 71+468 RHS 12/29/2020 12/30/2020

EPC-06/HW/1139 Level & FDD Checking For GSB layer GSB 70+340 70+430 RHS 12/29/2020 12/30/2020

EPC-06/HW/1141 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+468 71+600 RHS 12/30/2020 12/31/2020

EPC-06/HW/1142 Dismantling of existing BT surface BT Scr 72+000 72+150 BHS 12/30/2020 12/31/2020

EPC-06/HW/1143 Level & FDD Checking For GSB layer GSB 70+090 70+280 RHS 12/30/2020 12/31/2020

EPC-06/HW/1145 Level and FDD checking of DLC layer DLC 86+680 86+750 LHS 12/31/2020 1/1/2021

EPC-06/HW/1149 Level and FDD checking of DLC layer DLC 86+750 86+800 LHS 1/1/2021 1/2/2021

EPC-06/HW/1150 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+530 86+545 LHS 1/1/2021 1/2/2021

EPC-06/HW/1154 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+545 86+609 LHS 1/2/2021 1/3/2021

EPC-06/HW/1155 Level & FDD Checking For GSB layer GSB 88+960 89+160 LHS 1/2/2021 1/3/2021

EPC-06/HW/1157 Level & FDD Checking of Subgrade Top layer SG Top 74+170 74+980 RHS 1/2/2021 1/3/2021

EPC-06/HW/1159 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+609 86+672 LHS 1/3/2021 1/4/2021

EPC-06/HW/1161 Level & FDD Checking of Subgrade Top layer SG Top 71+600 72+400 LHS 1/3/2021 1/4/2021

EPC-06/HW/1163 Level & FDD Checking For GSB layer GSB 89+160 89+270 LHS 1/3/2021 1/4/2021

EPC-06/HW/1164 Level & FDD Checking of Subgrade Top layer SG Top 72+400 73+040 LHS 1/4/2021 1/5/2021

EPC-06/HW/1165 Level & FDD Checking of Subgrade Top layer SG Top 73+110 73+350 LHS 1/4/2021 1/5/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1166 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+672 86+720 LHS 1/4/2021 1/5/2021

EPC-06/HW/1168 Level and FDD checking of DLC layer DLC 88+960 89+035 LHS 1/4/2021 1/5/2021

EPC-06/HW/1169 Level & FDD Checking For GSB layer GSB 74+170 74+980 RHS 1/4/2021 1/5/2021

EPC-06/HW/1170 Level & FDD Checking of Subgrade Top layer SG Top 71+600 71+740 RHS 1/4/2021 1/5/2021

EPC-06/HW/1172 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+720 86+768 LHS 1/5/2021 1/6/2021

EPC-06/HW/1174 Level and FDD checking of DLC layer DLC 89+035 89+130 LHS 1/5/2021 1/6/2021

EPC-06/HW/1175 Level & FDD Checking For GSB layer GSB 71+600 72+300 LHS 1/5/2021 1/6/2021

EPC-06/HW/1178 Level and FDD checking of DLC layer DLC 89+130 89+200 LHS 1/6/2021 1/7/2021

EPC-06/HW/1179 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+768 86+800 LHS 1/6/2021 1/7/2021

EPC-06/HW/1183 Level & FDD Checking For GSB layer GSB 72+300 73+040 LHS 1/6/2021 1/7/2021

EPC-06/HW/1186 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+530 86+567 LHS 1/7/2021 1/8/2021

EPC-06/HW/1188 Level & FDD Checking For GSB layer GSB 73+110 73+350 LHS 1/7/2021 1/8/2021

EPC-06/HW/1189 Level and FDD checking of DLC layer DLC 89+200 89+270 LHS 1/7/2021 1/8/2021

EPC-06/HW/1191 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+567 86+625 LHS 1/8/2021 1/9/2021

EPC-06/HW/1197 Level & FDD Checking of Subgrade Top layer SG Top 72+800 72+870 RHS 1/9/2021 1/10/2021

EPC-06/HW/1200 Level & FDD Checking For GSB layer GSB 71+600 72+250 RHS 1/9/2021 1/10/2021

EPC-06/HW/1207 FDD Checking of WMM 1st layer WMM-I 77+300 78+500 RHS 1/12/2021 1/13/2021

EPC-06/HW/1209 Level & FDD Checking For GSB layer GSB 72+250 73+040 RHS 1/12/2021 1/13/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1212 Dismantling of existing BT surface BT Scr 89+270 91+000 BHS 1/13/2021 1/14/2021

EPC-06/HW/1213 Level & FDD Checking of WMM Top layer WMM-II 77+300 78+400 RHS 1/13/2021 1/14/2021

EPC-06/HW/1215 FDD Checking of WMM 1st layer WMM-I 76+060 76+560 RHS 1/18/2021 1/19/2021

EPC-06/HW/1216 Dismantling of existing BT surface BT Scr 90+700 92+000 BHS 1/13/2021 1/14/2021 Not done

EPC-06/HW/1217 FDD Checking of WMM 1st layer WMM-I 78+500 79+640 RHS 1/13/2021 1/14/2021

EPC-06/HW/1222 Dismantling of existing BT surface BT Scr 90+700 92+000 BHS 1/14/2021 1/15/2021

EPC-06/HW/1223 FDD Checking of WMM 1st layer WMM-I 76+720 77+220 RHS 1/14/2021 1/15/2021

EPC-06/HW/1224 Level & FDD Checking of Subgrade Top layer SG Top 89+270 90+000 LHS 1/14/2021 1/15/2021

EPC-06/HW/1228 Level & FDD Checking of Subgrade Top layer SG Top 90+000 90+700 LHS 1/15/2021 1/16/2021

EPC-06/HW/1229 Dismantling of existing BT surface BT Scr 92+000 93+100 BHS 1/16/2021 1/17/2021

EPC-06/HW/1233 Level & FDD Checking of Subgrade Top layer SG Top 90+700 91+230 LHS 1/16/2021 1/17/2021

EPC-06/HW/1236 Level & FDD Checking of WMM Top layer WMM-II 78+400 79+640 RHS 1/17/2021 1/18/2021

EPC-06/HW/1237 Level & FDD Checking of Subgrade Top layer SG Top 91+300 92+000 LHS 1/17/2021 1/18/2021

EPC-06/HW/1238 Level & FDD Checking of Subgrade Top layer SG Top 92+200 93+000 LHS 1/18/2021 1/19/2021

EPC-06/HW/1239 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+625 86+643 LHS 1/18/2021 1/19/2021

EPC-06/HW/1240 Dismantling of existing BT surface BT Scr 93+100 94+200 BHS 1/18/2021 1/19/2021

EPC-06/HW/1241 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+643 86+715 LHS 1/19/2021 1/20/2021

EPC-06/HW/1243 FDD Checking of WMM 1st layer WMM-I 73+620 73+770 RHS 1/19/2021 1/20/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1244 Level & FDD Checking of WMM Top layer WMM-II 80+020 80+420 LHS 1/19/2021 1/20/2021

EPC-06/HW/1245 Level & FDD Checking of Subgrade Top layer SG Top 76+980 77+030 LHS 1/19/2021 1/20/2021

EPC-06/HW/1246 Level & FDD Checking of Subgrade Top layer SG Top 93+000 93+700 LHS 1/19/2021 1/20/2021

EPC-06/HW/1247 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+715 86+800 LHS 1/20/2021 1/21/2021

EPC-06/HW/1248 FDD Checking of WMM 1st layer WMM-I 74+170 74+980 LHS 1/20/2021 1/21/2021 Not done

EPC-06/HW/1250 FDD Checking of WMM 1st layer WMM-I 75+180 75+700 LHS 1/20/2021 1/21/2021

EPC-06/HW/1251 Level & FDD Checking of Subgrade Top layer SG Top 73+770 74+170 RHS 1/20/2021 1/21/2021

EPC-06/HW/1252 Level & FDD Checking of WMM Top layer WMM-II 79+700 79+940 LHS 1/20/2021 1/21/2021

EPC-06/HW/1253 FDD Checking of WMM 1st layer WMM-I 73+400 73+560 RHS 1/20/2021 1/21/2021

EPC-06/HW/1254 FDD Checking of WMM 1st layer WMM-I 73+120 73+350 RHS 1/20/2021 1/21/2021

EPC-06/HW/1255 Level & FDD Checking of Subgrade Top layer SG Top 93+770 94+200 LHS 1/20/2021 1/21/2021

EPC-06/HW/1256 FDD Checking of WMM 1st layer WMM-I 74+170 74+980 LHS 1/21/2021 1/22/2021

EPC-06/HW/1259 Level & FDD Checking For GSB layer GSB 91+300 92+000 LHS 1/21/2021 1/22/2021

EPC-06/HW/1260 Level & FDD Checking of WMM Top layer WMM-II 76+720 77+220 RHS 1/21/2021 1/22/2021

EPC-06/HW/1261 FDD Checking of WMM 1st layer WMM-I 71+600 72+200 RHS 1/21/2021 1/22/2021

EPC-06/HW/1262 Level & FDD Checking For GSB layer GSB 73+770 74+170 RHS 1/21/2021 1/22/2021

EPC-06/HW/1263 FDD Checking of WMM 1st layer WMM-I 72+200 73+040 RHS 1/22/2021 1/23/2021

EPC-06/HW/1264 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 88+960 89+018 LHS 1/22/2021 1/23/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1267 Level & FDD Checking of WMM Top layer WMM-II 76+060 76+560 RHS 1/22/2021 1/23/2021

EPC-06/HW/1268 Applying primer coat Prime coat 80+020 80+420 LHS 1/22/2021 1/23/2021

EPC-06/HW/1269 Applying primer coat Prime coat 79+700 79+940 LHS 1/22/2021 1/23/2021

EPC-06/HW/1270 Applying primer coat Prime coat 77+300 78+400 RHS 1/22/2021 1/23/2021

EPC-06/HW/1271 FDD Checking of WMM 1st layer WMM-I 70+750 70+900 LHS 1/23/2021 1/24/2021

EPC-06/HW/1272 FDD Checking of WMM 1st layer WMM-I 70+460 70+710 LHS 1/23/2021 1/24/2021

EPC-06/HW/1273 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+018 89+040 LHS 1/23/2021 1/24/2021

EPC-06/HW/1274 Dismantling of existing BT surface BT Scr 80+460 82+150 BHS 1/23/2021 1/24/2021

EPC-06/HW/1275 Applying primer coat Prime coat 78+400 79+640 RHS 1/23/2021 1/24/2021

EPC-06/HW/1276 FDD Checking of WMM 1st layer WMM-I 70+340 70+430 RHS 1/23/2021 1/24/2021

EPC-06/HW/1277 FDD Checking of WMM 1st layer WMM-I 70+090 70+280 RHS 1/23/2021 1/24/2021

EPC-06/HW/1281 Level & FDD Checking of WMM Top layer WMM-II 75+180 75+700 LHS 1/24/2021 1/25/2021

EPC-06/HW/1282 Applying tack coat for DBM Tack coat (DBM) 80+020 80+420 LHS 1/24/2021 1/25/2021

EPC-06/HW/1283 Level checking and laying of DBM DBM 80+020 80+420 LHS 1/24/2021 1/25/2021

EPC-06/HW/1284 Applying tack coat for DBM Tack coat (DBM) 79+700 79+940 LHS 1/24/2021 1/25/2021

EPC-06/HW/1285 Level checking and laying of DBM DBM 79+700 79+940 LHS 1/24/2021 1/25/2021

EPC-06/HW/1286 Level & FDD Checking For GSB layer GSB 89+270 90+200 LHS 1/24/2021 1/25/2021

EPC-06/HW/1288 Level & FDD Checking of Subgrade Top layer SG Top 88+900 89+270 RHS 1/24/2021 1/25/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1290 Level & FDD Checking For GSB layer GSB 88+900 89+270 RHS 1/25/2021 1/26/2021

EPC-06/HW/1292 Level & FDD Checking of WMM Top layer WMM-II 74+170 74+980 LHS 1/26/2021 1/27/2021

EPC-06/HW/1293 Applying primer coat Prime coat 75+180 75+700 LHS 1/26/2021 1/27/2021

EPC-06/HW/1294 Applying primer coat Prime coat 76+720 77+220 RHS 1/26/2021 1/27/2021

EPC-06/HW/1295 Applying tack coat for DBM Tack coat (DBM) 78+400 79+640 RHS 1/26/2021 1/27/2021

EPC-06/HW/1296 Applying primer coat Prime coat 76+060 76+560 RHS 1/26/2021 1/27/2021

EPC-06/HW/1297 Level checking and laying of DBM DBM 78+400 79+640 RHS 1/26/2021 1/27/2021

EPC-06/HW/1298 Level & FDD Checking For GSB layer GSB 80+020 80+420 RHS 1/26/2021 1/27/2021

EPC-06/HW/1299 Level & FDD Checking For GSB layer GSB 79+700 79+940 RHS 1/26/2021 1/27/2021

EPC-06/HW/1300 Level & FDD Checking For GSB layer GSB 90+200 91+040 LHS 1/26/2021 1/27/2021

EPC-06/HW/1301 Level and FDD checking of DLC layer DLC 88+900 89+270 RHS 1/26/2021 1/27/2021

EPC-06/HW/1303 Level & FDD Checking of WMM Top layer WMM-II 80+020 80+420 RHS 1/27/2021 1/28/2021

EPC-06/HW/1304 Level & FDD Checking of WMM Top layer WMM-II 79+700 79+940 RHS 1/27/2021 1/28/2021

EPC-06/HW/1305 Level & FDD Checking of WMM Top layer WMM-II 73+620 73+770 RHS 1/27/2021 1/28/2021

EPC-06/HW/1306 Level & FDD Checking of WMM Top layer WMM-II 73+400 73+560 RHS 1/27/2021 1/28/2021

EPC-06/HW/1307 Applying tack coat for DBM Tack coat (DBM) 77+300 78+400 RHS 1/27/2021 1/28/2021

EPC-06/HW/1308 Level checking and laying of DBM DBM 77+300 78+400 RHS 1/27/2021 1/28/2021

EPC-06/HW/1309 Level & FDD Checking For GSB layer GSB 78+400 79+640 LHS 1/27/2021 1/28/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1310 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+040 89+072 LHS 1/27/2021 1/28/2021

EPC-06/HW/1311 Level & FDD Checking of Subgrade Top layer SG Top 80+500 80+950 LHS 1/28/2021 1/29/2021

EPC-06/HW/1312 Level & FDD Checking of Subgrade Top layer SG Top 81+050 81+440 RHS 1/28/2021 1/29/2021

EPC-06/HW/1313 Level & FDD Checking of Subgrade Top layer SG Top 81+500 82+150 RHS 1/28/2021 1/29/2021

EPC-06/HW/1314 Level & FDD Checking of WMM Top layer WMM-II 78+400 79+640 LHS 1/28/2021 1/29/2021

EPC-06/HW/1315 Applying tack coat for DBM Tack coat (DBM) 76+720 77+220 RHS 1/28/2021 1/29/2021

EPC-06/HW/1316 Level checking and laying of DBM DBM 76+720 77+220 RHS 1/28/2021 1/29/2021

EPC-06/HW/1318 Applying tack coat for DBM Tack coat (DBM) 76+060 76+560 RHS 1/28/2021 1/29/2021

EPC-06/HW/1319 Level & FDD Checking of WMM Top layer WMM-II 73+120 73+350 RHS 1/28/2021 1/29/2021

EPC-06/HW/1320 Level & FDD Checking of WMM Top layer WMM-II 71+600 72+200 RHS 1/28/2021 1/29/2021

EPC-06/HW/1321 Level checking and laying of DBM DBM 76+060 76+560 RHS 1/28/2021 1/29/2021

EPC-06/HW/1322 Level & FDD Checking For GSB layer GSB 77+300 78+400 LHS 1/28/2021 1/29/2021

EPC-06/HW/1323 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+072 89+119 LHS 1/28/2021 1/29/2021

EPC-06/HW/1324 Applying primer coat Prime coat 73+120 73+350 RHS 1/28/2021 1/29/2021

EPC-06/HW/1324 Applying primer coat Prime coat 71+600 72+200 RHS 1/28/2021 1/29/2021

EPC-06/HW/1325 Level & FDD Checking of WMM Top layer WMM-II 77+300 78+400 LHS 1/29/2021 1/30/2021

EPC-06/HW/1326 Applying tack coat for DBM Tack coat (DBM) 73+120 73+350 RHS 1/29/2021 1/30/2021

EPC-06/HW/1327 Applying tack coat for DBM Tack coat (DBM) 71+600 72+200 RHS 1/29/2021 1/30/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1328 Level checking and laying of DBM DBM 73+110 73+350 RHS 1/29/2021 1/30/2021

EPC-06/HW/1329 Level checking and laying of DBM DBM 71+600 72+200 RHS 1/29/2021 1/30/2021

EPC-06/HW/1330 Applying tack coat for DBM Tack coat (DBM) 75+180 75+700 LHS 1/29/2021 1/30/2021

EPC-06/HW/1331 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 88+960 89+060 LHS 1/29/2021 1/30/2021

EPC-06/HW/1332 Level and FDD checking of DLC layer DLC 74+060 74+170 RHS 1/29/2021 1/30/2021

EPC-06/HW/1333 Level checking and laying of DBM DBM 75+180 75+700 LHS 1/29/2021 1/30/2021

EPC-06/HW/1334 Applying primer coat Prime coat 74+170 74+980 LHS 1/29/2021 1/30/2021

EPC-06/HW/1335 Level & FDD Checking of WMM Top layer WMM-II 72+200 73+040 RHS 1/29/2021 1/30/2021

EPC-06/HW/1336 Level & FDD Checking For GSB layer GSB 76+720 77+220 LHS 1/29/2021 1/30/2021

EPC-06/HW/1337 Level & FDD Checking For GSB layer GSB 76+060 76+560 LHS 1/29/2021 1/30/2021

EPC-06/HW/1338 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+119 89+270 LHS 1/29/2021 1/30/2021

EPC-06/HW/1339 Applying primer coat Prime coat 72+200 73+040 RHS 1/29/2021 1/30/2021

EPC-06/HW/1340 Applying tack coat for DBM Tack coat (DBM) 74+170 74+980 RHS 1/30/2021 1/31/2021

EPC-06/HW/1341 Level checking and laying of DBM DBM 74+170 74+980 RHS 1/30/2021 1/31/2021

EPC-06/HW/1342 Level & FDD Checking For GSB layer GSB 80+500 80+950 LHS 1/29/2021 1/30/2021

EPC-06/HW/1342 Level & FDD Checking For GSB layer GSB 81+050 81+440 RHS 1/29/2021 1/30/2021

EPC-06/HW/1342 Level & FDD Checking For GSB layer GSB 81+500 82+150 RHS 1/29/2021 1/30/2021

EPC-06/HW/1344 Applying tack coat for DBM Tack coat (DBM) 72+200 73+040 RHS 1/30/2021 1/31/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1345 Level checking and laying of DBM DBM 72+200 73+040 RHS 1/30/2021 1/31/2021

EPC-06/HW/1346 Level & FDD Checking of WMM Top layer WMM-II 70+750 70+900 LHS 1/30/2021 1/31/2021

EPC-06/HW/1347 Level & FDD Checking of WMM Top layer WMM-II 70+460 70+710 LHS 1/30/2021 1/31/2021

EPC-06/HW/1348 Level & FDD Checking of WMM Top layer WMM-II 70+340 70+430 RHS 1/30/2021 1/31/2021

EPC-06/HW/1349 Level & FDD Checking of WMM Top layer WMM-II 70+090 70+280 RHS 1/30/2021 1/31/2021

EPC-06/HW/1350 Level & FDD Checking For GSB layer GSB 75+180 75+700 RHS 1/30/2021 1/31/2021

EPC-06/HW/1351 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 89+060 89+270 LHS 1/30/2021 1/31/2021

EPC-06/HW/1352 Level and FDD checking of DLC layer DLC 73+770 74+060 RHS 1/30/2021 1/31/2021

EPC-06/HW/1353 FDD Checking of WMM 1st layer WMM-I 80+500 80+950 LHS 1/30/2021 1/31/2021

EPC-06/HW/1354 FDD Checking of WMM 1st layer WMM-I 81+050 81+440 RHS 1/30/2021 1/31/2021

EPC-06/HW/1355 FDD Checking of WMM 1st layer WMM-I 81+500 82+150 RHS 1/30/2021 1/31/2021

EPC-06/HW/1356 Applying primer coat Prime coat 70+090 70+280 RHS 1/30/2021 1/31/2021

EPC-06/HW/1357 Level & FDD Checking of Subgrade Top layer SG Top 70+340 70+460 LHS 1/31/2021 2/1/2021

EPC-06/HW/1358 Level & FDD Checking of Subgrade Top layer SG Top 73+350 73+400 RHS 1/31/2021 2/1/2021

EPC-06/HW/1359 Level & FDD Checking For GSB layer GSB 70+340 70+460 LHS 1/31/2021 2/1/2021

EPC-06/HW/1360 Level & FDD Checking of WMM Top layer WMM-II 80+500 80+950 LHS 1/31/2021 2/1/2021

EPC-06/HW/1361 Level & FDD Checking of WMM Top layer WMM-II 81+050 81+440 RHS 1/31/2021 2/1/2021

EPC-06/HW/1362 Level & FDD Checking of WMM Top layer WMM-II 81+500 82+150 RHS 1/31/2021 2/1/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1363 Applying primer coat Prime coat 80+500 80+950 LHS 1/31/2021 2/1/2021

EPC-06/HW/1363 Applying primer coat Prime coat 81+050 81+440 RHS 1/31/2021 2/1/2021

EPC-06/HW/1363 Applying primer coat Prime coat 81+500 82+150 RHS 1/31/2021 2/1/2021

EPC-06/HW/1364 Applying tack coat for DBM Tack coat (DBM) 70+090 70+280 RHS 1/31/2021 2/1/2021

EPC-06/HW/1365 Level checking and laying of DBM DBM 70+090 70+280 RHS 1/31/2021 2/1/2021

EPC-06/HW/1366 Level & FDD Checking For GSB layer GSB 73+350 73+400 RHS 2/1/2021 2/2/2021

EPC-06/HW/1367 FDD Checking of WMM 1st layer WMM-I 70+340 70+460 LHS 2/1/2021 2/2/2021

EPC-06/HW/1368 Applying tack coat for DBM Tack coat (DBM) 80+500 80+950 LHS 2/1/2021 2/2/2021

EPC-06/HW/1368 Applying tack coat for DBM Tack coat (DBM) 81+050 81+440 RHS 2/1/2021 2/2/2021

EPC-06/HW/1368 Applying tack coat for DBM Tack coat (DBM) 81+500 82+150 RHS 2/1/2021 2/2/2021

EPC-06/HW/1369 Level checking and laying of DBM DBM 80+500 80+950 LHS 2/1/2021 2/2/2021

EPC-06/HW/1369 Level checking and laying of DBM DBM 81+050 81+440 RHS 2/1/2021 2/2/2021

EPC-06/HW/1369 Level checking and laying of DBM DBM 81+500 82+150 RHS 2/1/2021 2/2/2021

EPC-06/HW/1370 FDD Checking of WMM 1st layer WMM-I 73+350 73+400 RHS 2/2/2021 2/3/2021

EPC-06/HW/1371 Level & FDD Checking of WMM Top layer WMM-II 70+340 70+460 LHS 2/2/2021 2/3/2021

EPC-06/HW/1372 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 88+900 89+000 RHS 2/2/2021 2/3/2021

EPC-06/HW/1373 Level & FDD Checking of WMM Top layer WMM-II 73+350 73+400 RHS 2/3/2021 2/4/2021

EPC-06/HW/1374 Applying primer coat Prime coat 73+350 73+560 RHS 2/3/2021 2/4/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1374 Applying primer coat Prime coat 70+340 70+710 LHS 2/3/2021 2/4/2021

EPC-06/HW/1374 Applying primer coat Prime coat 70+750 70+900 LHS 2/3/2021 2/4/2021

EPC-06/HW/1375 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+000 89+040 RHS 2/3/2021 2/4/2021

EPC-06/HW/1376 Applying tack coat for DBM Tack coat (DBM) 73+350 73+560 RHS 2/4/2021 2/5/2021

EPC-06/HW/1376 Applying tack coat for DBM Tack coat (DBM) 70+340 70+710 LHS 2/4/2021 2/5/2021

EPC-06/HW/1376 Applying tack coat for DBM Tack coat (DBM) 70+750 70+900 LHS 2/4/2021 2/5/2021

EPC-06/HW/1377 Level checking and laying of DBM DBM 73+350 73+560 RHS 2/4/2021 2/5/2021

EPC-06/HW/1377 Level checking and laying of DBM DBM 70+340 70+710 LHS 2/4/2021 2/5/2021

EPC-06/HW/1377 Level checking and laying of DBM DBM 70+750 70+900 LHS 2/4/2021 2/5/2021

EPC-06/HW/1378 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+040 89+070 RHS 2/4/2021 2/5/2021

EPC-06/HW/1379 FDD Checking of WMM 1st layer WMM-I 76+720 77+220 LHS 2/5/2021 2/6/2021

EPC-06/HW/1380 FDD Checking of WMM 1st layer WMM-I 76+060 76+560 LHS 2/6/2021 2/7/2021

EPC-06/HW/1381 Level & FDD Checking of WMM Top layer WMM-II 76+720 77+220 LHS 2/6/2021 2/7/2021

EPC-06/HW/1382 Applying primer coat Prime coat 80+020 80+420 RHS 2/6/2021 2/7/2021

EPC-06/HW/1382 Applying primer coat Prime coat 79+700 79+940 RHS 2/6/2021 2/7/2021

EPC-06/HW/1382 Applying primer coat Prime coat 79+000 79+630 LHS 2/6/2021 2/7/2021

EPC-06/HW/1383 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+070 89+140 RHS 2/6/2021 2/7/2021

EPC-06/HW/1384 FDD Checking of WMM 1st layer WMM-I 75+180 75+700 RHS 2/7/2021 2/8/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1385 Level & FDD Checking of WMM Top layer WMM-II 76+060 76+560 LHS 2/7/2021 2/8/2021

EPC-06/HW/1386 Applying primer coat Prime coat 77+600 79+000 LHS 2/7/2021 2/8/2021

EPC-06/HW/1387 Applying tack coat for DBM Tack coat (DBM) 80+020 80+420 RHS 2/7/2021 2/8/2021

EPC-06/HW/1387 Applying tack coat for DBM Tack coat (DBM) 79+700 79+940 RHS 2/7/2021 2/8/2021

EPC-06/HW/1387 Applying tack coat for DBM Tack coat (DBM) 79+000 79+630 LHS 2/7/2021 2/8/2021

EPC-06/HW/1388 Level checking and laying of DBM DBM 80+020 80+420 RHS 2/7/2021 2/8/2021

EPC-06/HW/1388 Level checking and laying of DBM DBM 79+700 79+940 RHS 2/7/2021 2/8/2021

EPC-06/HW/1388 Level checking and laying of DBM DBM 79+000 79+630 LHS 2/7/2021 2/8/2021

EPC-06/HW/1389 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+140 89+160 RHS 2/7/2021 2/8/2021

EPC-06/HW/1390 Level & FDD Checking of Subgrade Top layer SG Top 73+350 73+560 LHS 2/8/2021 2/9/2021

EPC-06/HW/1391 FDD Checking of WMM 1st layer WMM-I 74+170 74+980 RHS 2/8/2021 2/9/2021

EPC-06/HW/1392 Level & FDD Checking of WMM Top layer WMM-II 75+180 75+700 RHS 2/8/2021 2/9/2021

EPC-06/HW/1393 Applying tack coat for DBM Tack coat (DBM) 77+600 79+000 LHS 2/8/2021 2/9/2021

EPC-06/HW/1394 Level checking and laying of DBM DBM 77+600 79+000 LHS 2/8/2021 2/9/2021

EPC-06/HW/1395 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+160 89+200 RHS 2/8/2021 2/9/2021

EPC-06/HW/1396 Level & FDD Checking For GSB layer GSB 73+350 73+560 LHS 2/9/2021 2/10/2021

EPC-06/HW/1397 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+200 89+270 RHS 2/9/2021 2/10/2021

EPC-06/HW/1398 Level & FDD Checking of WMM Top layer WMM-II 74+170 74+980 RHS 2/9/2021 2/10/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1399 Level and FDD checking of DLC layer DLC 75+830 75+850 RHS 2/9/2021 2/10/2021

EPC-06/HW/1400 FDD Checking of WMM 1st layer WMM-I 73+120 73+560 LHS 2/10/2021 2/11/2021

EPC-06/HW/1401 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+150 74+170 RHS 2/10/2021 2/11/2021

EPC-06/HW/1402 FDD Checking of WMM 1st layer WMM-I 72+200 73+040 LHS 2/11/2021 2/12/2021

EPC-06/HW/1403 Level & FDD Checking of WMM Top layer WMM-II 73+120 73+560 LHS 2/11/2021 2/12/2021

EPC-06/HW/1404 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+090 74+150 RHS 2/11/2021 2/12/2021

EPC-06/HW/1405 Level & FDD Checking of WMM Top layer WMM-II 72+200 73+040 LHS 2/12/2021 2/13/2021

EPC-06/HW/1406 Applying primer coat Prime coat 77+300 77+600 LHS 2/12/2021 2/13/2021

EPC-06/HW/1406 Applying primer coat Prime coat 76+720 77+220 LHS 2/12/2021 2/13/2021

EPC-06/HW/1406 Applying primer coat Prime coat 76+060 76+560 LHS 2/12/2021 2/13/2021

EPC-06/HW/1406 Applying primer coat Prime coat 75+180 75+700 RHS 2/12/2021 2/13/2021

EPC-06/HW/1407 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+040 74+090 RHS 2/12/2021 2/13/2021

EPC-06/HW/1408 Applying tack coat for DBM Tack coat (DBM) 77+300 77+600 LHS 2/13/2021 2/14/2021

EPC-06/HW/1408 Applying tack coat for DBM Tack coat (DBM) 76+720 77+220 LHS 2/13/2021 2/14/2021

EPC-06/HW/1408 Applying tack coat for DBM Tack coat (DBM) 76+060 76+560 LHS 2/13/2021 2/14/2021

EPC-06/HW/1408 Applying tack coat for DBM Tack coat (DBM) 75+180 75+700 RHS 2/13/2021 2/14/2021

EPC-06/HW/1409 Level checking and laying of DBM DBM 77+300 77+600 LHS 2/13/2021 2/14/2021

EPC-06/HW/1409 Level checking and laying of DBM DBM 76+720 77+220 LHS 2/13/2021 2/14/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1409 Level checking and laying of DBM DBM 76+060 76+560 LHS 2/13/2021 2/14/2021

EPC-06/HW/1409 Level checking and laying of DBM DBM 75+180 75+700 RHS 2/13/2021 2/14/2021

EPC-06/HW/1410 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+000 74+040 RHS 2/13/2021 2/14/2021

EPC-06/HW/1411 Level & FDD Checking of Subgrade Top layer SG Top 70+750 70+980 RHS 2/14/2021 2/15/2021

EPC-06/HW/1412 FDD Checking of WMM 1st layer WMM-I 71+600 72+200 LHS 2/14/2021 2/15/2021

EPC-06/HW/1413 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+960 74+000 RHS 2/14/2021 2/15/2021

EPC-06/HW/1414 Level & FDD Checking of Subgrade Top layer SG Top 70+430 70+710 RHS 2/15/2021 2/16/2021

EPC-06/HW/1415 Level & FDD Checking of Subgrade Top layer SG Top 70+090 70+280 LHS 2/15/2021 2/16/2021

EPC-06/HW/1416 Level & FDD Checking of WMM Top layer WMM-II 71+600 72+200 LHS 2/15/2021 2/16/2021

EPC-06/HW/1417 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+890 73+960 RHS 2/15/2021 2/16/2021

EPC-06/HW/1418 Level & FDD Checking of Subgrade Top layer SG Top 86+530 86+800 RHS 2/16/2021 2/17/2021

EPC-06/HW/1419 Level & FDD Checking For GSB layer GSB 70+750 70+980 RHS 2/16/2021 2/17/2021

EPC-06/HW/1420 Level & FDD Checking For GSB layer GSB 70+430 70+710 RHS 2/16/2021 2/17/2021

EPC-06/HW/1421 Level & FDD Checking For GSB layer GSB 70+090 70+280 LHS 2/16/2021 2/17/2021

EPC-06/HW/1422 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+840 73+890 RHS 2/16/2021 2/17/2021

EPC-06/HW/1423 FDD Checking of WMM 1st layer WMM-I 70+090 70+280 LHS 2/17/2021 2/18/2021

EPC-06/HW/1424 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 75+830 75+850 RHS 2/17/2021 2/18/2021

EPC-06/HW/1425 Level & FDD Checking For GSB layer GSB 86+530 86+800 RHS 2/18/2021 2/19/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1426 FDD Checking of WMM 1st layer WMM-I 70+750 70+980 RHS 2/18/2021 2/19/2021

EPC-06/HW/1427 FDD Checking of WMM 1st layer WMM-I 70+430 70+710 RHS 2/18/2021 2/19/2021

EPC-06/HW/1428 Level & FDD Checking of WMM Top layer WMM-II 70+090 70+280 LHS 2/18/2021 2/19/2021

EPC-06/HW/1429 Applying primer coat Prime coat 74+170 74+980 RHS 2/18/2021 2/19/2021

EPC-06/HW/1429 Applying primer coat Prime coat 73+620 73+770 RHS 2/18/2021 2/19/2021

EPC-06/HW/1429 Applying primer coat Prime coat 73+120 73+560 LHS 2/18/2021 2/19/2021

EPC-06/HW/1429 Applying primer coat Prime coat 72+600 73+040 LHS 2/18/2021 2/19/2021

EPC-06/HW/1430 Level & FDD Checking of WMM Top layer WMM-II 70+750 70+980 RHS 2/19/2021 2/20/2021

EPC-06/HW/1431 Level & FDD Checking of WMM Top layer WMM-II 70+430 70+710 RHS 2/19/2021 2/20/2021

EPC-06/HW/1432 Applying primer coat Prime coat 72+200 72+600 LHS 2/19/2021 2/20/2021

EPC-06/HW/1432 Applying primer coat Prime coat 71+600 72+200 LHS 2/19/2021 2/20/2021

EPC-06/HW/1432 Applying primer coat Prime coat 70+750 70+980 RHS 2/19/2021 2/20/2021

EPC-06/HW/1432 Applying primer coat Prime coat 70+340 70+710 RHS 2/19/2021 2/20/2021

EPC-06/HW/1432 Applying primer coat Prime coat 70+090 70+280 LHS 2/19/2021 2/20/2021

EPC-06/HW/1433 Applying tack coat for DBM Tack coat (DBM) 74+170 74+980 RHS 2/19/2021 2/20/2021

EPC-06/HW/1433 Applying tack coat for DBM Tack coat (DBM) 73+620 73+770 RHS 2/19/2021 2/20/2021

EPC-06/HW/1433 Applying tack coat for DBM Tack coat (DBM) 73+120 73+560 LHS 2/19/2021 2/20/2021

EPC-06/HW/1433 Applying tack coat for DBM Tack coat (DBM) 72+600 73+040 LHS 2/19/2021 2/20/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1434 Level checking and laying of DBM DBM 74+170 74+980 RHS 2/19/2021 2/20/2021

EPC-06/HW/1434 Level checking and laying of DBM DBM 73+620 73+770 RHS 2/19/2021 2/20/2021

EPC-06/HW/1434 Level checking and laying of DBM DBM 73+120 73+560 LHS 2/19/2021 2/20/2021

EPC-06/HW/1434 Level checking and laying of DBM DBM 72+600 73+040 LHS 2/19/2021 2/20/2021

EPC-06/HW/1435 Level and FDD checking of DLC layer DLC 86+530 86+800 RHS 2/19/2021 2/20/2021

EPC-06/HW/1436 Level & FDD Checking of Subgrade Top layer SG Top 92+000 92+200 LHS 2/19/2021 2/20/2021

EPC-06/HW/1438 Applying tack coat for DBM Tack coat (DBM) 72+200 72+600 LHS 2/20/2021 2/21/2021

EPC-06/HW/1438 Applying tack coat for DBM Tack coat (DBM) 71+600 72+200 LHS 2/20/2021 2/21/2021

EPC-06/HW/1438 Applying tack coat for DBM Tack coat (DBM) 70+750 70+980 RHS 2/20/2021 2/21/2021

EPC-06/HW/1438 Applying tack coat for DBM Tack coat (DBM) 70+340 70+710 RHS 2/20/2021 2/21/2021

EPC-06/HW/1438 Applying tack coat for DBM Tack coat (DBM) 70+090 70+280 LHS 2/20/2021 2/21/2021

EPC-06/HW/1439 Level checking and laying of DBM DBM 72+200 72+600 LHS 2/20/2021 2/21/2021

EPC-06/HW/1439 Level checking and laying of DBM DBM 71+600 72+200 LHS 2/20/2021 2/21/2021

EPC-06/HW/1439 Level checking and laying of DBM DBM 70+750 70+980 RHS 2/20/2021 2/21/2021

EPC-06/HW/1439 Level checking and laying of DBM DBM 70+340 70+710 RHS 2/20/2021 2/21/2021

EPC-06/HW/1439 Level checking and laying of DBM DBM 70+090 70+280 LHS 2/20/2021 2/21/2021

EPC-06/HW/1440 Level & FDD Checking For GSB layer GSB 92+000 92+500 LHS 2/20/2021 2/21/2021 Not done

EPC-06/HW/1443 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+770 73+840 RHS 2/21/2021 2/22/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1444 Level & FDD Checking For GSB layer GSB 92+000 92+500 LHS 2/21/2021 2/22/2021

EPC-06/HW/1446 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 74+100 74+170 RHS 2/22/2021 2/23/2021

EPC-06/HW/1447 Level & FDD Checking For GSB layer GSB 92+500 92+950 LHS 2/22/2021 2/23/2021

EPC-06/HW/1450 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 74+050 74+100 RHS 2/23/2021 2/24/2021

EPC-06/HW/1451 Dismantling of existing BT surface BT Scr 66+320 67+500 BHS 1/23/2021 1/24/2021

EPC-06/HW/1452 Level & FDD Checking For GSB layer GSB 92+950 93+700 LHS 1/23/2021 1/24/2021

EPC-06/HW/1454 Level & FDD Checking of Subgrade Top layer SG Top 80+500 80+950 RHS 2/24/2021 2/25/2021

EPC-06/HW/1455 Level & FDD Checking of Subgrade Top layer SG Top 81+050 81+440 LHS 2/24/2021 2/25/2021

EPC-06/HW/1456 Level & FDD Checking of Subgrade Top layer SG Top 81+500 82+150 LHS 2/24/2021 2/25/2021

EPC-06/HW/1457 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+960 74+050 RHS 2/24/2021 2/25/2021

EPC-06/HW/1458 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 88+900 89+000 RHS 2/24/2021 2/25/2021

EPC-06/HW/1459 Level & FDD Checking For GSB layer GSB 93+770 94+200 LHS 2/24/2021 2/25/2021

EPC-06/HW/1463 Level & FDD Checking of Subgrade Top layer SG Top 67+130 67+500 LHS 2/25/2021 2/26/2021

EPC-06/HW/1464 Level & FDD Checking For GSB layer GSB 80+500 80+950 RHS 2/25/2021 2/26/2021

EPC-06/HW/1465 Level & FDD Checking For GSB layer GSB 81+050 81+440 LHS 2/25/2021 2/26/2021

EPC-06/HW/1466 Level & FDD Checking For GSB layer GSB 81+500 82+150 LHS 2/25/2021 2/26/2021

EPC-06/HW/1467 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+910 73+960 RHS 2/25/2021 2/26/2021

EPC-06/HW/1468 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 89+000 89+110 RHS 2/25/2021 2/26/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1469 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+830 73+910 RHS 2/25/2021 2/26/2021 Not Done

EPC-06/HW/1473 Level & FDD Checking of Subgrade Top layer SG Top 66+320 67+070 LHS 2/26/2021 2/27/2021

EPC-06/HW/1474 Level & FDD Checking For GSB layer GSB 67+130 67+500 LHS 2/26/2021 2/27/2021

EPC-06/HW/1475 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+830 73+910 RHS 2/26/2021 2/27/2021

EPC-06/HW/1476 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 89+110 89+270 RHS 2/26/2021 2/27/2021

EPC-06/HW/1477 Dismantling of existing BT surface BT Scr 65+050 66+320 BHS 2/26/2021 2/27/2021

EPC-06/HW/1481 Level & FDD Checking For GSB layer GSB 66+320 67+070 LHS 2/27/2021 2/28/2021

EPC-06/HW/1482 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+770 73+830 RHS 2/27/2021 2/28/2021

EPC-06/HW/1483 Dismantling of existing BT surface BT Scr 64+000 65+050 BHS 2/27/2021 2/28/2021

EPC-06/HW/1494 FDD Checking of Subgrade Top layer on Minor Junction SG Top 88+965 LHS 2/28/2021 3/1/2021

EPC-06/HW/1495 Level & FDD Checking of Subgrade Top layer SG Top 65+970 66+250 LHS 2/28/2021 3/1/2021

EPC-06/HW/1496 FDD Checking of WMM 1st layer WMM-I 89+270 90+000 LHS 2/28/2021 3/1/2021

EPC-06/HW/1499 FDD Checking For GSB layer on Minor Junction GSB 88+965 LHS 3/1/2021 3/2/2021

EPC-06/HW/1500 Level & FDD Checking For GSB layer GSB 91+040 91+230 LHS 3/1/2021 3/2/2021

EPC-06/HW/1501 FDD Checking of WMM 1st layer WMM-I 90+000 90+550 LHS 3/1/2021 3/2/2021

EPC-06/HW/1502 Level & FDD Checking of WMM Top layer WMM-II 89+270 90+000 LHS 3/1/2021 3/2/2021

EPC-06/HW/1504 FDD Checking of WMM Top layer on Minor Junction WMM-II 88+965 LHS 3/2/2021 3/3/2021

EPC-06/HW/1505 Applying primer coat on Minor Junction Prime coat 88+965 LHS 3/2/2021 3/3/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1506 Level & FDD Checking of Subgrade Top layer SG Top 65+010 65+900 LHS 3/2/2021 3/3/2021

EPC-06/HW/1507 Level & FDD Checking of WMM Top layer WMM-II 90+000 90+550 LHS 3/2/2021 3/3/2021

EPC-06/HW/1508 Applying primer coat Prime coat 89+270 90+400 LHS 3/2/2021 3/3/2021

EPC-06/HW/1511 FDD Checking of Subgrade Top layer on Minor Junction SG Top 90+950 LHS 3/3/2021 3/4/2021

EPC-06/HW/1512 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 88+965 LHS 3/3/2021 3/4/2021

EPC-06/HW/1513 FDD Checking of WMM 1st layer WMM-I 90+550 91+230 LHS 3/3/2021 3/4/2021

EPC-06/HW/1514 Applying tack coat for DBM Tack coat (DBM) 89+270 90+400 LHS 3/3/2021 3/4/2021

EPC-06/HW/1515 Level checking and laying of DBM DBM 89+270 90+400 LHS 3/3/2021 3/4/2021

EPC-06/HW/1516 Laying of DBM on Minor Junction DBM 88+965 LHS 3/3/2021 3/4/2021

EPC-06/HW/1517 FDD Checking of WMM 1st layer WMM-I 91+300 92+000 LHS 3/3/2021 3/4/2021 Not done

EPC-06/HW/1520 FDD Checking For GSB layer on Minor Junction GSB 90+950 LHS 3/4/2021 3/5/2021

EPC-06/HW/1521 Level & FDD Checking of Subgrade Top layer SG Top 64+520 64+890 LHS 3/4/2021 3/5/2021

EPC-06/HW/1522 Level & FDD Checking For GSB layer GSB 65+970 66+250 LHS 3/4/2021 3/5/2021

EPC-06/HW/1523 FDD Checking of WMM 1st layer WMM-I 91+300 92+000 LHS 3/4/2021 3/5/2021

EPC-06/HW/1524 Level & FDD Checking of WMM Top layer WMM-II 90+550 91+230 LHS 3/4/2021 3/5/2021

EPC-06/HW/1526 FDD Checking of Subgrade Top layer on Minor Junction SG Top 91+562 LHS 3/5/2021 3/6/2021

EPC-06/HW/1527 FDD Checking of Subgrade Top layer on Minor Junction SG Top 80+990 RHS 3/5/2021 3/6/2021

EPC-06/HW/1528 FDD Checking of WMM Top layer on Minor Junction WMM-II 90+950 LHS 3/5/2021 3/6/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1529 Applying primer coat on Minor Junction Prime coat 90+950 LHS 3/5/2021 3/6/2021

EPC-06/HW/1530 FDD Checking of WMM 1st layer WMM-I 92+000 92+700 LHS 3/5/2021 3/6/2021

EPC-06/HW/1531 Level & FDD Checking of WMM Top layer WMM-II 91+300 92+000 LHS 3/5/2021 3/6/2021

EPC-06/HW/1532 Applying primer coat Prime coat 90+400 91+230 LHS 3/5/2021 3/6/2021

EPC-06/HW/1533 Dismantling of existing BT surface BT Scr 86+800 86+868 BHS 3/6/2021 3/7/2021

EPC-06/HW/1534 FDD Checking of Subgrade Top layer on Minor Junction SG Top 77+000 BHS 3/6/2021 3/7/2021

EPC-06/HW/1535 FDD Checking of Subgrade Top layer on Minor Junction SG Top 73+440 RHS 3/6/2021 3/7/2021

EPC-06/HW/1536 FDD Checking of Subgrade Top layer on Minor Junction SG Top 73+760 LHS 3/6/2021 3/7/2021

EPC-06/HW/1537 FDD Checking For GSB layer on Minor Junction GSB 91+562 LHS 3/6/2021 3/7/2021

EPC-06/HW/1538 FDD Checking For GSB layer on Minor Junction GSB 80+990 RHS 3/6/2021 3/7/2021

EPC-06/HW/1539 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 90+950 LHS 3/6/2021 3/7/2021

EPC-06/HW/1540 Level & FDD Checking of Subgrade Top layer SG Top 64+000 64+250 LHS 3/6/2021 3/7/2021

EPC-06/HW/1541 Level & FDD Checking of Subgrade Top layer SG Top 64+310 64+450 LHS 3/6/2021 3/7/2021

EPC-06/HW/1542 FDD Checking of WMM 1st layer WMM-I 92+700 93+400 LHS 3/6/2021 3/7/2021

EPC-06/HW/1543 Level & FDD Checking of WMM Top layer WMM-II 92+000 92+700 LHS 3/6/2021 3/7/2021

EPC-06/HW/1544 Applying tack coat for DBM Tack coat (DBM) 90+400 91+230 LHS 3/6/2021 3/7/2021

EPC-06/HW/1544 Laying of DBM on Minor Junction DBM 90+950 LHS 3/6/2021 3/7/2021

EPC-06/HW/1545 Level checking and laying of DBM DBM 90+400 91+230 LHS 3/6/2021 3/7/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1545 FDD Checking For GSB layer on Minor Junction GSB 77+000 BHS 3/7/2021 3/8/2021

EPC-06/HW/1546 FDD Checking For GSB layer on Minor Junction GSB 73+440 RHS 3/7/2021 3/8/2021

EPC-06/HW/1547 FDD Checking For GSB layer on Minor Junction GSB 73+760 LHS 3/7/2021 3/8/2021

EPC-06/HW/1548 FDD Checking of WMM Top layer on Minor Junction WMM-II 91+562 LHS 3/7/2021 3/8/2021

EPC-06/HW/1549 FDD Checking of WMM Top layer on Minor Junction WMM-II 80+990 RHS 3/7/2021 3/8/2021

EPC-06/HW/1550 Applying primer coat on Minor Junction Prime coat 91+562 LHS 3/7/2021 3/8/2021

EPC-06/HW/1551 Applying primer coat on Minor Junction Prime coat 80+990 RHS 3/7/2021 3/8/2021

EPC-06/HW/1552 Level & FDD Checking For GSB layer GSB 65+010 65+900 LHS 3/7/2021 3/8/2021

EPC-06/HW/1553 FDD Checking of WMM 1st layer WMM-I 93+400 93+700 LHS 3/7/2021 3/8/2021

EPC-06/HW/1554 FDD Checking of WMM 1st layer WMM-I 93+770 94+200 LHS 3/7/2021 3/8/2021

EPC-06/HW/1555 Level & FDD Checking of WMM Top layer WMM-II 92+700 93+400 LHS 3/7/2021 3/8/2021

EPC-06/HW/1556 Applying primer coat Prime coat 91+300 92+700 LHS 3/7/2021 3/8/2021

EPC-06/HW/1557 Level & FDD Checking of Subgrade Top layer SG Top 86+800 86+840 RHS 3/7/2021 3/8/2021

EPC-06/HW/1559 FDD Checking of WMM Top layer on Minor Junction WMM-II 77+000 BHS 3/8/2021 3/9/2021

EPC-06/HW/1560 FDD Checking of WMM Top layer on Minor Junction WMM-II 73+440 RHS 3/8/2021 3/9/2021

EPC-06/HW/1561 FDD Checking of WMM Top layer on Minor Junction WMM-II 73+760 LHS 3/8/2021 3/9/2021

EPC-06/HW/1562 Applying primer coat on Minor Junction Prime coat 77+000 BHS 3/8/2021 3/9/2021

EPC-06/HW/1563 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 91+562 LHS 3/8/2021 3/9/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1564 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 80+990 RHS 3/8/2021 3/9/2021

EPC-06/HW/1565 Level & FDD Checking For GSB layer GSB 64+520 64+890 LHS 3/8/2021 3/9/2021

EPC-06/HW/1566 Level & FDD Checking of WMM Top layer WMM-II 93+400 93+700 LHS 3/8/2021 3/9/2021

EPC-06/HW/1567 Level & FDD Checking of WMM Top layer WMM-II 93+770 94+200 LHS 3/8/2021 3/9/2021

EPC-06/HW/1568 Applying primer coat Prime coat 92+700 93+700 LHS 3/8/2021 3/9/2021

EPC-06/HW/1569 Applying primer coat Prime coat 93+770 94+200 LHS 3/8/2021 3/9/2021

EPC-06/HW/1570 Applying tack coat for DBM Tack coat (DBM) 91+300 92+700 LHS 3/8/2021 3/9/2021

EPC-06/HW/1571 Level checking and laying of DBM DBM 91+300 92+700 LHS 3/8/2021 3/9/2021

EPC-06/HW/1572 Level & FDD Checking For GSB layer GSB 86+800 86+840 RHS 3/8/2021 3/9/2021

EPC-06/HW/1573 Laying of DBM on Minor Junction DBM 91+562 LHS 3/8/2021 3/9/2021

EPC-06/HW/1574 Laying of DBM on Minor Junction DBM 80+990 RHS 3/8/2021 3/9/2021

EPC-06/HW/1575 Applying primer coat on Minor Junction Prime coat 73+440 RHS 3/8/2021 3/9/2021

EPC-06/HW/1576 Applying primer coat on Minor Junction Prime coat 73+760 LHS 3/8/2021 3/9/2021

EPC-06/HW/1577 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 77+000 BHS 3/9/2021 3/10/2021

EPC-06/HW/1578 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 73+440 RHS 3/9/2021 3/10/2021

EPC-06/HW/1579 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 73+760 LHS 3/9/2021 3/10/2021

EPC-06/HW/1580 Level & FDD Checking For GSB layer GSB 64+310 64+450 LHS 3/9/2021 3/10/2021

EPC-06/HW/1581 Applying tack coat for DBM Tack coat (DBM) 92+700 93+700 LHS 3/9/2021 3/10/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1582 Applying tack coat for DBM Tack coat (DBM) 93+770 94+200 LHS 3/9/2021 3/10/2021

EPC-06/HW/1583 Level checking and laying of DBM DBM 92+700 93+700 LHS 3/9/2021 3/10/2021

EPC-06/HW/1584 Level checking and laying of DBM DBM 93+770 94+200 LHS 3/9/2021 3/10/2021

EPC-06/HW/1585 Level and FDD checking of DLC layer DLC 86+800 86+840 RHS 3/9/2021 3/10/2021

EPC-06/HW/1586 Laying of DBM on Minor Junction DBM 77+000 BHS 3/9/2021 3/10/2021

EPC-06/HW/1587 Laying of DBM on Minor Junction DBM 73+440 RHS 3/9/2021 3/10/2021

EPC-06/HW/1588 Laying of DBM on Minor Junction DBM 73+760 LHS 3/9/2021 3/10/2021

EPC-06/HW/1589 FDD Checking of WMM 1st layer WMM-I 80+500 80+950 RHS 3/9/2021 3/10/2021 Not Done

EPC-06/HW/1593 Level & FDD Checking For GSB layer GSB 64+000 64+250 LHS 3/10/2021 3/11/2021

EPC-06/HW/1594 FDD Checking of WMM 1st layer WMM-I 80+500 80+950 RHS 3/10/2021 3/11/2021

EPC-06/HW/1601 FDD Checking of WMM 1st layer WMM-I 81+050 81+440 LHS 3/11/2021 3/12/2021

EPC-06/HW/1602 Level & FDD Checking of WMM Top layer WMM-II 80+500 80+950 RHS 3/11/2021 3/12/2021

EPC-06/HW/1610 Level & FDD Checking of WMM Top layer WMM-II 81+050 81+440 LHS 3/12/2021 3/13/2021

EPC-06/HW/1620 FDD Checking of WMM 1st layer WMM-I 81+500 82+150 LHS 3/13/2021 3/14/2021

EPC-06/HW/1627 FDD Checking of Subgrade Top layer on Minor Junction SG Top 80+750 LHS 3/14/2021 3/15/2021

EPC-06/HW/1628 FDD Checking of Subgrade Top layer on Minor Junction SG Top 79+550 RHS 3/14/2021 3/15/2021

EPC-06/HW/1629 FDD Checking of Subgrade Top layer on Minor Junction SG Top 78+750 RHS 3/14/2021 3/15/2021

EPC-06/HW/1630 Level & FDD Checking of WMM Top layer WMM-II 81+500 82+150 LHS 3/14/2021 3/15/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1634 FDD Checking For GSB layer on Minor Junction GSB 80+750 LHS 3/15/2021 3/16/2021

EPC-06/HW/1635 FDD Checking For GSB layer on Minor Junction GSB 79+550 RHS 3/15/2021 3/16/2021

EPC-06/HW/1636 FDD Checking For GSB layer on Minor Junction GSB 78+750 RHS 3/15/2021 3/16/2021

EPC-06/HW/1639 FDD Checking of WMM Top layer on Minor Junction WMM-II 80+750 LHS 3/16/2021 3/17/2021

EPC-06/HW/1640 FDD Checking of WMM Top layer on Minor Junction WMM-II 79+550 RHS 3/16/2021 3/17/2021

EPC-06/HW/1641 FDD Checking of WMM Top layer on Minor Junction WMM-II 78+750 RHS 3/16/2021 3/17/2021

EPC-06/HW/1642 Applying primer coat on Minor Junction Prime coat 80+750 LHS 3/16/2021 3/17/2021

EPC-06/HW/1643 Applying primer coat on Minor Junction Prime coat 79+550 RHS 3/16/2021 3/17/2021

EPC-06/HW/1644 Applying primer coat on Minor Junction Prime coat 78+750 RHS 3/16/2021 3/17/2021

EPC-06/HW/1645 Applying primer coat Prime coat 80+500 80+950 RHS 3/16/2021 3/17/2021

EPC-06/HW/1646 Applying primer coat Prime coat 81+050 81+440 LHS 3/16/2021 3/17/2021

EPC-06/HW/1647 Applying primer coat Prime coat 81+500 82+150 LHS 3/16/2021 3/17/2021

EPC-06/HW/1657 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 80+750 LHS 3/17/2021 3/18/2021

EPC-06/HW/1658 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 79+550 RHS 3/17/2021 3/18/2021

EPC-06/HW/1659 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 78+750 RHS 3/17/2021 3/18/2021

EPC-06/HW/1660 Applying tack coat for DBM Tack coat (DBM) 80+500 80+950 RHS 3/17/2021 3/18/2021

EPC-06/HW/1661 Applying tack coat for DBM Tack coat (DBM) 81+050 81+440 LHS 3/17/2021 3/18/2021

EPC-06/HW/1662 Applying tack coat for DBM Tack coat (DBM) 81+500 82+150 LHS 3/17/2021 3/18/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1663 Level checking and laying of DBM DBM 80+500 80+950 RHS 3/17/2021 3/18/2021

EPC-06/HW/1664 Level checking and laying of DBM DBM 81+050 81+440 LHS 3/17/2021 3/18/2021

EPC-06/HW/1665 Level checking and laying of DBM DBM 81+500 82+150 LHS 3/17/2021 3/18/2021

EPC-06/HW/1666 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+530 86+600 RHS 3/17/2021 3/18/2021

EPC-06/HW/1667 Laying of DBM on Minor Junction DBM 80+750 LHS 3/17/2021 3/18/2021

EPC-06/HW/1668 Laying of DBM on Minor Junction DBM 79+550 RHS 3/17/2021 3/18/2021

EPC-06/HW/1669 Laying of DBM on Minor Junction DBM 78+750 RHS 3/17/2021 3/18/2021

EPC-06/HW/1680 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+600 86+680 RHS 3/18/2021 3/19/2021

EPC-06/HW/1690 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+680 86+770 RHS 3/19/2021 3/20/2021

EPC-06/HW/1691 Level & FDD Checking of Subgrade Top layer SG Top 89+270 90+000 RHS 3/19/2021 3/20/2021

EPC-06/HW/1692 Level & FDD Checking of Subgrade Top layer SG Top 90+000 90+700 RHS 3/19/2021 3/20/2021 Not Done

EPC-06/HW/1700 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+770 86+840 RHS 3/20/2021 3/21/2021

EPC-06/HW/1701 Level & FDD Checking of Subgrade Top layer SG Top 90+000 90+700 RHS 3/20/2021 3/21/2021

EPC-06/HW/1710 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+530 86+610 RHS 3/21/2021 3/22/2021

EPC-06/HW/1720 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+610 86+720 RHS 3/22/2021 3/23/2021

EPC-06/HW/1721 Level & FDD Checking of Subgrade Top layer SG Top 90+700 91+230 RHS 3/22/2021 3/23/2021

EPC-06/HW/1730 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+720 86+840 RHS 3/23/2021 3/24/2021

EPC-06/HW/1731 Level & FDD Checking of Subgrade Top layer SG Top 91+300 92+200 RHS 3/23/2021 3/24/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1740 Level & FDD Checking For GSB layer GSB 89+270 90+000 RHS 3/24/2021 3/25/2021

EPC-06/HW/1748 Level & FDD Checking For GSB layer GSB 90+000 90+700 RHS 3/24/2021 3/25/2021

EPC-06/HW/1757 Level & FDD Checking For GSB layer GSB 90+700 91+230 RHS 3/25/2021 3/26/2021

EPC-06/HW/1765 Level & FDD Checking For GSB layer GSB 91+300 92+100 RHS 3/25/2021 3/26/2021

EPC-06/HW/1810 Dismantling of existing BT surface BT Scr 85+670 86+530 BHS 3/31/2021 4/1/2021

EPC-06/HW/1820 Level & FDD Checking of Subgrade Top layer SG Top 86+445 86+530 RHS 4/2/2021 4/3/2021

EPC-06/HW/1830 Level & FDD Checking of Subgrade Top layer SG Top 92+200 92+900 RHS 4/4/2021 4/5/2021

EPC-06/HW/1835 Level & FDD Checking of Subgrade Top layer SG Top 92+900 93+700 RHS 4/5/2021 4/6/2021

EPC-06/HW/1840 Level & FDD Checking of Subgrade Top layer SG Top 93+770 94+200 RHS 4/6/2021 4/7/2021

EPC-06/HW/1845 Level & FDD Checking of Subgrade Top layer SG Top 85+670 86+445 RHS 4/7/2021 4/8/2021

EPC-06/HW/1850 Level & FDD Checking For GSB layer GSB 85+670 86+445 RHS 4/9/2021 4/10/2021

EPC-06/HW/1851 Level & FDD Checking For GSB layer GSB 86+445 86+530 RHS 4/9/2021 4/10/2021

EPC-06/HW/1856 FDD Checking of WMM 1st layer WMM-I 85+670 86+445 RHS 4/10/2021 4/11/2021

EPC-06/HW/1861 Level & FDD Checking of WMM Top layer WMM-II 85+670 86+445 RHS 4/11/2021 4/12/2021

EPC-06/HW/1862 Applying primer coat Prime coat 85+670 86+445 RHS 4/11/2021 4/12/2021

EPC-06/HW/1863 Level and FDD checking of DLC layer DLC 86+445 86+530 RHS 4/11/2021 4/12/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1868 Level & FDD Checking For GSB layer GSB 92+100 92+700 RHS 4/12/2021 4/13/2021

EPC-06/HW/1869 FDD Checking of WMM 1st layer WMM-I 89+270 90+100 RHS 4/12/2021 4/13/2021

EPC-06/HW/1870 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+840 86+845 RHS 4/12/2021 4/13/2021

EPC-06/HW/1875 Dismantling of existing BT surface BT Scr 68+500 68+700 BHS 4/13/2021 4/14/2021

EPC-06/HW/1876 Level & FDD Checking of Subgrade Top layer SG Top 73+620 73+770 LHS 4/13/2021 4/14/2021

EPC-06/HW/1877 Level & FDD Checking of Subgrade Top layer SG Top 67+130 67+500 RHS 4/13/2021 4/14/2021

EPC-06/HW/1878 Level & FDD Checking For GSB layer GSB 92+700 93+200 RHS 4/13/2021 4/14/2021

EPC-06/HW/1879 FDD Checking of WMM 1st layer WMM-I 90+100 90+600 RHS 4/13/2021 4/14/2021

EPC-06/HW/1880 Level & FDD Checking of WMM Top layer WMM-II 89+270 90+100 RHS 4/13/2021 4/14/2021

EPC-06/HW/1881 Applying primer coat Prime coat 89+270 90+100 RHS 4/13/2021 4/14/2021

EPC-06/HW/1882 Applying tack coat for DBM Tack coat (DBM) 85+670 86+445 RHS 4/13/2021 4/14/2021

EPC-06/HW/1883 Level checking and laying of DBM DBM 85+670 86+445 RHS 4/13/2021 4/14/2021

EPC-06/HW/1884 Dismantling of existing BT surface BT Scr 68+700 68+780 BHS 4/13/2021 4/14/2021

EPC-06/HW/1888 Dismantling of existing BT surface BT Scr 58+300 58+740 BHS 4/14/2021 4/15/2021

EPC-06/HW/1889 Dismantling of existing BT surface BT Scr 58+840 59+010 BHS 4/14/2021 4/15/2021

EPC-06/HW/1890 Level & FDD Checking of Subgrade Top layer SG Top 66+320 67+070 RHS 4/14/2021 4/15/2021

EPC-06/HW/1891 Level & FDD Checking For GSB layer GSB 93+200 93+700 RHS 4/14/2021 4/15/2021

EPC-06/HW/1892 FDD Checking of WMM 1st layer WMM-I 90+600 91+230 RHS 4/14/2021 4/15/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1893 Level & FDD Checking of WMM Top layer WMM-II 90+100 90+600 RHS 4/14/2021 4/15/2021

EPC-06/HW/1894 Applying primer coat Prime coat 90+100 90+600 RHS 4/14/2021 4/15/2021

EPC-06/HW/1899 Dismantling of existing BT surface BT Scr 59+070 59+830 BHS 4/15/2021 4/16/2021

EPC-06/HW/1900 Dismantling of existing BT surface BT Scr 59+890 60+620 BHS 4/15/2021 4/16/2021

EPC-06/HW/1901 Level & FDD Checking of Subgrade Top layer SG Top 65+970 66+250 RHS 4/15/2021 4/16/2021

EPC-06/HW/1902 Level & FDD Checking of Subgrade Top layer SG Top 68+500 68+700 LHS 4/15/2021 4/16/2021

EPC-06/HW/1903 Level & FDD Checking For GSB layer GSB 93+770 94+200 RHS 4/15/2021 4/16/2021

EPC-06/HW/1904 FDD Checking of WMM 1st layer WMM-I 91+300 92+100 RHS 4/15/2021 4/16/2021

EPC-06/HW/1905 Level & FDD Checking of WMM Top layer WMM-II 90+600 91+230 RHS 4/15/2021 4/16/2021

EPC-06/HW/1906 Applying primer coat Prime coat 90+600 91+230 RHS 4/15/2021 4/16/2021

EPC-06/HW/1907 FDD Checking of Subgrade Top layer on Minor Junction SG Top 86+655 RHS 4/15/2021 4/16/2021

EPC-06/HW/1912 Dismantling of existing BT surface BT Scr 60+680 61+000 BHS 4/16/2021 4/17/2021

EPC-06/HW/1913 Level & FDD Checking of Subgrade Top layer SG Top 65+010 65+900 RHS 4/16/2021 4/17/2021

EPC-06/HW/1914 Level & FDD Checking For GSB layer GSB 73+620 73+770 LHS 4/16/2021 4/17/2021

EPC-06/HW/1915 Level & FDD Checking For GSB layer GSB 67+130 67+500 RHS 4/16/2021 4/17/2021

EPC-06/HW/1916 FDD Checking of WMM 1st layer WMM-I 92+100 92+600 RHS 4/16/2021 4/17/2021

EPC-06/HW/1917 Level & FDD Checking of WMM Top layer WMM-II 91+300 92+100 RHS 4/16/2021 4/17/2021

EPC-06/HW/1918 Applying primer coat Prime coat 91+300 92+100 RHS 4/16/2021 4/17/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1923 Level & FDD Checking of Subgrade Top layer SG Top 64+520 64+890 RHS 4/17/2021 4/18/2021

EPC-06/HW/1924 Level & FDD Checking of Subgrade Top layer SG Top 64+310 64+450 RHS 4/17/2021 4/18/2021

EPC-06/HW/1925 Level & FDD Checking of Subgrade Top layer SG Top 64+000 64+250 RHS 4/17/2021 4/18/2021

EPC-06/HW/1926 Level & FDD Checking For GSB layer GSB 66+320 67+070 RHS 4/17/2021 4/18/2021

EPC-06/HW/1927 Level & FDD Checking For GSB layer GSB 68+500 68+700 LHS 4/17/2021 4/18/2021

EPC-06/HW/1928 FDD Checking of WMM 1st layer WMM-I 92+600 93+140 RHS 4/17/2021 4/18/2021

EPC-06/HW/1929 Level & FDD Checking of WMM Top layer WMM-II 92+100 92+600 RHS 4/17/2021 4/18/2021

EPC-06/HW/1930 Applying primer coat Prime coat 92+100 92+600 RHS 4/17/2021 4/18/2021

EPC-06/HW/1931 FDD Checking For GSB layer on Minor Junction GSB 86+655 RHS 4/17/2021 4/18/2021

EPC-06/HW/1936 Level & FDD Checking For GSB layer GSB 65+970 66+250 RHS 4/18/2021 4/19/2021

EPC-06/HW/1937 FDD Checking of WMM 1st layer WMM-I 93+140 93+700 RHS 4/18/2021 4/19/2021

EPC-06/HW/1938 Level & FDD Checking of WMM Top layer WMM-II 92+600 93+140 RHS 4/18/2021 4/19/2021

EPC-06/HW/1939 Applying primer coat Prime coat 92+600 93+140 RHS 4/18/2021 4/19/2021

EPC-06/HW/1945 Level & FDD Checking For GSB layer GSB 65+010 65+900 RHS 4/19/2021 4/20/2021

EPC-06/HW/1946 FDD Checking of WMM 1st layer WMM-I 93+770 94+200 RHS 4/19/2021 4/20/2021

EPC-06/HW/1947 Level & FDD Checking of WMM Top layer WMM-II 93+140 93+700 RHS 4/19/2021 4/20/2021

EPC-06/HW/1948 Applying primer coat Prime coat 93+140 93+700 RHS 4/19/2021 4/20/2021

EPC-06/HW/1949 Applying tack coat for DBM Tack coat (DBM) 89+270 90+500 RHS 4/19/2021 4/20/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1950 Level checking and laying of DBM DBM 89+270 90+500 RHS 4/19/2021 4/20/2021

EPC-06/HW/1951 FDD Checking of WMM Top layer on Minor Junction WMM-II 86+655 RHS 4/19/2021 4/20/2021

EPC-06/HW/1952 Applying primer coat on Minor Junction Prime coat 86+655 RHS 4/19/2021 4/20/2021

EPC-06/HW/1957 Level & FDD Checking For GSB layer GSB 64+520 64+890 RHS 4/20/2021 4/21/2021

EPC-06/HW/1958 FDD Checking of WMM 1st layer WMM-I 73+620 73+770 LHS 4/20/2021 4/21/2021

EPC-06/HW/1959 FDD Checking of WMM 1st layer WMM-I 67+130 67+500 RHS 4/20/2021 4/21/2021

EPC-06/HW/1960 Level & FDD Checking of WMM Top layer WMM-II 93+770 94+200 RHS 4/20/2021 4/21/2021

EPC-06/HW/1961 Applying primer coat Prime coat 93+770 94+200 RHS 4/20/2021 4/21/2021

EPC-06/HW/1962 Applying tack coat for DBM Tack coat (DBM) 90+500 91+230 RHS 4/20/2021 4/21/2021

EPC-06/HW/1963 Level checking and laying of DBM DBM 90+500 91+230 RHS 4/20/2021 4/21/2021

EPC-06/HW/1964 FDD Checking of Subgrade Top layer on Minor Junction SG Top 67+465 LHS 4/20/2021 4/21/2021

EPC-06/HW/1965 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 86+655 RHS 4/20/2021 4/21/2021

EPC-06/HW/1966 Laying of DBM on Minor Junction DBM 86+655 RHS 4/20/2021 4/21/2021

EPC-06/HW/1971 Level & FDD Checking For GSB layer GSB 64+310 64+450 RHS 4/21/2021 4/22/2021

EPC-06/HW/1972 Level & FDD Checking For GSB layer GSB 64+000 64+250 RHS 4/21/2021 4/22/2021

EPC-06/HW/1973 FDD Checking of WMM 1st layer WMM-I 66+320 67+070 RHS 4/21/2021 4/22/2021

EPC-06/HW/1974 FDD Checking of WMM 1st layer WMM-I 65+970 66+250 RHS 4/21/2021 4/22/2021

EPC-06/HW/1975 Level & FDD Checking of WMM Top layer WMM-II 73+620 73+770 LHS 4/21/2021 4/22/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1976 Level & FDD Checking of WMM Top layer WMM-II 67+130 67+500 RHS 4/21/2021 4/22/2021

EPC-06/HW/1977 Applying primer coat Prime coat 73+620 73+770 LHS 4/21/2021 4/22/2021

EPC-06/HW/1978 Applying primer coat Prime coat 67+130 67+500 RHS 4/21/2021 4/22/2021

EPC-06/HW/1979 Level and FDD checking of DLC layer DLC 68+500 68+700 LHS 4/21/2021 4/22/2021

EPC-06/HW/1985 Level & FDD Checking of Subgrade Top layer SG Top 58+300 58+740 LHS 4/22/2021 4/23/2021

EPC-06/HW/1986 Level & FDD Checking of Subgrade Top layer SG Top 58+840 59+010 LHS 4/22/2021 4/23/2021

EPC-06/HW/1987 FDD Checking of WMM 1st layer WMM-I 65+010 65+900 RHS 4/22/2021 4/23/2021

EPC-06/HW/1988 Level & FDD Checking of WMM Top layer WMM-II 66+320 67+070 RHS 4/22/2021 4/23/2021

EPC-06/HW/1989 Level & FDD Checking of WMM Top layer WMM-II 65+970 66+250 RHS 4/22/2021 4/23/2021

EPC-06/HW/1990 Applying primer coat Prime coat 66+320 67+070 RHS 4/22/2021 4/23/2021

EPC-06/HW/1991 Applying primer coat Prime coat 65+970 66+250 RHS 4/22/2021 4/23/2021

EPC-06/HW/1992 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+445 86+530 RHS 4/22/2021 4/23/2021

EPC-06/HW/1997 Level & FDD Checking of Subgrade Top layer SG Top 59+070 59+830 LHS 4/23/2021 4/24/2021

EPC-06/HW/1998 FDD Checking of WMM 1st layer WMM-I 64+520 64+890 RHS 4/23/2021 4/24/2021

EPC-06/HW/1999 Level & FDD Checking of WMM Top layer WMM-II 65+010 65+900 RHS 4/23/2021 4/24/2021

EPC-06/HW/2000 Applying primer coat Prime coat 65+010 65+900 RHS 4/23/2021 4/24/2021

EPC-06/HW/2001 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+840 86+845 RHS 4/23/2021 4/24/2021

EPC-06/HW/2002 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+445 86+530 RHS 4/23/2021 4/24/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2007 Level & FDD Checking of Subgrade Top layer SG Top 59+890 60+620 LHS 4/24/2021 4/25/2021

EPC-06/HW/2008 FDD Checking of WMM 1st layer WMM-I 64+310 64+450 RHS 4/24/2021 4/25/2021

EPC-06/HW/2009 FDD Checking of WMM 1st layer WMM-I 64+000 64+250 RHS 4/24/2021 4/25/2021

EPC-06/HW/2010 Level & FDD Checking of WMM Top layer WMM-II 64+520 64+890 RHS 4/24/2021 4/25/2021

EPC-06/HW/2011 Applying primer coat Prime coat 64+520 64+890 RHS 4/24/2021 4/25/2021

EPC-06/HW/2012 FDD Checking For GSB layer on Minor Junction GSB 67+465 LHS 4/24/2021 4/25/2021

EPC-06/HW/2017 Level & FDD Checking of Subgrade Top layer SG Top 60+680 61+000 LHS 4/25/2021 4/26/2021

EPC-06/HW/2018 Level & FDD Checking of WMM Top layer WMM-II 64+310 64+450 RHS 4/25/2021 4/26/2021

EPC-06/HW/2019 Level & FDD Checking of WMM Top layer WMM-II 64+000 64+250 RHS 4/25/2021 4/26/2021

EPC-06/HW/2020 Applying primer coat Prime coat 64+310 64+450 RHS 4/25/2021 4/26/2021

EPC-06/HW/2021 Applying primer coat Prime coat 64+000 64+250 RHS 4/25/2021 4/26/2021

EPC-06/HW/2026 Applying tack coat for DBM Tack coat (DBM) 73+620 73+770 LHS 4/26/2021 4/27/2021

EPC-06/HW/2027 Applying tack coat for DBM Tack coat (DBM) 67+130 67+500 RHS 4/26/2021 4/27/2021

EPC-06/HW/2028 Applying tack coat for DBM Tack coat (DBM) 66+320 67+070 RHS 4/26/2021 4/27/2021

EPC-06/HW/2029 Applying tack coat for DBM Tack coat (DBM) 65+970 66+250 RHS 4/26/2021 4/27/2021

EPC-06/HW/2030 Level checking and laying of DBM DBM 73+620 73+770 LHS 4/26/2021 4/27/2021

EPC-06/HW/2030 Level checking and laying of DBM DBM 67+130 67+500 RHS 4/26/2021 4/27/2021

EPC-06/HW/2030 Level checking and laying of DBM DBM 66+320 67+070 RHS 4/26/2021 4/27/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2030 Level checking and laying of DBM DBM 65+970 66+250 RHS 4/26/2021 4/27/2021

EPC-06/HW/2031 FDD Checking of WMM Top layer on Minor Junction WMM-II 67+465 LHS 4/26/2021 4/27/2021

EPC-06/HW/2032 Applying primer coat on Minor Junction Prime coat 67+465 LHS 4/26/2021 4/27/2021

EPC-06/HW/2040 Applying tack coat for DBM Tack coat (DBM) 65+010 65+900 RHS 4/27/2021 4/28/2021

EPC-06/HW/2041 Applying tack coat for DBM Tack coat (DBM) 64+520 64+890 RHS 4/27/2021 4/28/2021

EPC-06/HW/2042 Applying tack coat for DBM Tack coat (DBM) 64+310 64+450 RHS 4/27/2021 4/28/2021

EPC-06/HW/2043 Applying tack coat for DBM Tack coat (DBM) 64+000 64+250 RHS 4/27/2021 4/28/2021

EPC-06/HW/2044 Level checking and laying of DBM DBM 65+010 65+900 RHS 4/27/2021 4/28/2021

EPC-06/HW/2044 Level checking and laying of DBM DBM 64+520 64+890 RHS 4/27/2021 4/28/2021

EPC-06/HW/2044 Level checking and laying of DBM DBM 64+310 64+450 RHS 4/27/2021 4/28/2021

EPC-06/HW/2044 Level checking and laying of DBM DBM 64+000 64+250 RHS 4/27/2021 4/28/2021

EPC-06/HW/2045 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 67+465 LHS 4/27/2021 4/28/2021

EPC-06/HW/2046 Laying of DBM on Minor Junction DBM 67+465 LHS 4/27/2021 4/28/2021

EPC-06/HW/1278 Dismantling of existing BT surface BT Scr 88+900 88+960 BHS 1/23/2021 1/24/2021

EPC-06/HW/1821 Level & FDD Checking of Subgrade Top layer SG Top 88+900 88+960 LHS 4/2/2021 4/3/2021

EPC-06/HW/1826 Level & FDD Checking For GSB layer GSB 88+900 88+960 LHS 4/3/2021 4/4/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1831 Level & FDD Checking of Subgrade Top layer SG Top 89+270 89+285 RHS 4/4/2021 4/5/2021

EPC-06/HW/1832 Level and FDD checking of DLC layer DLC 88+900 88+960 LHS 4/4/2021 4/5/2021

EPC-06/HW/1836 Level & FDD Checking For GSB layer GSB 89+270 89+285 RHS 4/5/2021 4/6/2021

EPC-06/HW/1841 Level and FDD checking of DLC layer DLC 89+270 89+285 RHS 4/6/2021 4/7/2021

EPC-06/HW/1864 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 88+900 88+960 LHS 4/11/2021 4/12/2021

EPC-06/HW/1871 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 88+900 88+960 LHS 4/12/2021 4/13/2021

EPC-06/HW/1884 Level & FDD Checking of Subgrade Top layer SG Top 86+840 86+845 RHS 4/13/2021 4/14/2021

EPC-06/HW/1885 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+270 89+285 RHS 4/13/2021 4/14/2021

EPC-06/HW/1895 Level & FDD Checking For GSB layer GSB 86+840 86+845 RHS 4/14/2021 4/15/2021

EPC-06/HW/1896 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 89+270 89+285 RHS 4/14/2021 4/15/2021

EPC-06/HW/1897 Dismantling of existing BT surface BT Scr 58+740 58+840 BHS 4/14/2021 4/15/2021

EPC-06/HW/1908 Level and FDD checking of DLC layer DLC 86+840 86+845 RHS 4/15/2021 4/16/2021

EPC-06/HW/1909 Dismantling of existing BT surface BT Scr 59+010 59+070 BHS 4/15/2021 4/16/2021

EPC-06/HW/1910 Dismantling of existing BT surface BT Scr 59+830 59+890 BHS 4/15/2021 4/16/2021

EPC-06/HW/1919 Dismantling of existing BT surface BT Scr 60+620 60+680 BHS 4/16/2021 4/17/2021

EPC-06/HW/2075 FDD Checking of WMM 1st layer WMM-I 67+130 67+500 LHS 4/30/2021 5/1/2021

EPC-06/HW/2076 FDD Checking of WMM 1st layer WMM-I 66+320 67+070 LHS 4/30/2021 5/1/2021

EPC-06/HW/2077 FDD Checking of Subgrade Top layer on Minor Junction SG Top 67+465 LHS 4/30/2021 5/1/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2078 Dismantling of existing BT surface BT Scr 68+300 68+500 BHS 4/30/2021 5/1/2021

EPC-06/HW/2079 Dismantling of existing BT surface BT Scr 68+000 68+300 BHS 4/30/2021 5/1/2021

EPC-06/HW/2083 FDD Checking of WMM 1st layer WMM-I 65+970 66+250 LHS 5/1/2021 5/2/2021

EPC-06/HW/2084 FDD Checking of WMM 1st layer WMM-I 65+010 65+900 LHS 5/1/2021 5/2/2021

EPC-06/HW/2085 Level & FDD Checking of WMM Top layer WMM-II 67+130 67+500 LHS 5/1/2021 5/2/2021

EPC-06/HW/2086 Level & FDD Checking of WMM Top layer WMM-II 66+320 67+070 LHS 5/1/2021 5/2/2021

EPC-06/HW/2087 Applying primer coat Prime coat 67+130 67+500 LHS 5/1/2021 5/2/2021

EPC-06/HW/2088 Applying primer coat Prime coat 66+320 67+070 LHS 5/1/2021 5/2/2021

EPC-06/HW/2089 FDD Checking For GSB layer on Minor Junction GSB 67+465 LHS 5/1/2021 5/2/2021

EPC-06/HW/2095 FDD Checking of WMM 1st layer WMM-I 64+520 64+890 LHS 5/2/2021 5/3/2021

EPC-06/HW/2096 FDD Checking of WMM 1st layer WMM-I 64+310 64+450 LHS 5/2/2021 5/3/2021

EPC-06/HW/2097 Level & FDD Checking of WMM Top layer WMM-II 65+970 66+250 LHS 5/2/2021 5/3/2021

EPC-06/HW/2098 Level & FDD Checking of WMM Top layer WMM-II 65+010 65+900 LHS 5/2/2021 5/3/2021

EPC-06/HW/2099 Applying primer coat Prime coat 65+970 66+250 LHS 5/2/2021 5/3/2021

EPC-06/HW/2100 Applying primer coat Prime coat 65+010 65+900 LHS 5/2/2021 5/3/2021

EPC-06/HW/2101 Level & FDD Checking of Subgrade Top layer SG Top 68+440 68+500 LHS 5/2/2021 5/3/2021

EPC-06/HW/2102 FDD Checking of WMM Top layer on Minor Junction WMM-II 67+465 LHS 5/2/2021 5/3/2021

EPC-06/HW/2103 Applying primer coat on Minor Junction Prime coat 67+465 LHS 5/2/2021 5/3/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2104 Level & FDD Checking of Subgrade Top layer SG Top 68+000 68+300 LHS 5/2/2021 5/3/2021

EPC-06/HW/2105 Dismantling of existing BT surface BT Scr 50+050 50+900 BHS 5/2/2021 5/3/2021

EPC-06/HW/2109 Level & FDD Checking For GSB layer GSB 60+680 61+000 LHS 5/3/2021 5/4/2021

EPC-06/HW/2110 FDD Checking of WMM 1st layer WMM-I 64+000 64+250 LHS 5/3/2021 5/4/2021

EPC-06/HW/2111 Level & FDD Checking of WMM Top layer WMM-II 64+520 64+890 LHS 5/3/2021 5/4/2021

EPC-06/HW/2112 Level & FDD Checking of WMM Top layer WMM-II 64+310 64+450 LHS 5/3/2021 5/4/2021

EPC-06/HW/2113 Applying primer coat Prime coat 64+520 64+890 LHS 5/3/2021 5/4/2021

EPC-06/HW/2114 Applying primer coat Prime coat 64+310 64+450 LHS 5/3/2021 5/4/2021

EPC-06/HW/2115 Applying tack coat for DBM Tack coat (DBM) 67+130 67+500 LHS 5/3/2021 5/4/2021

EPC-06/HW/2115 Applying tack coat for DBM Tack coat (DBM) 66+320 67+070 LHS 5/3/2021 5/4/2021

EPC-06/HW/2115 Applying tack coat for DBM Tack coat (DBM) 65+970 66+250 LHS 5/3/2021 5/4/2021

EPC-06/HW/2118 Level checking and laying of DBM DBM 67+130 67+500 LHS 5/3/2021 5/4/2021

EPC-06/HW/2118 Level checking and laying of DBM DBM 66+320 67+070 LHS 5/3/2021 5/4/2021

EPC-06/HW/2118 Level checking and laying of DBM DBM 65+970 66+250 LHS 5/3/2021 5/4/2021

EPC-06/HW/2121 Level & FDD Checking For GSB layer GSB 68+440 68+500 LHS 5/3/2021 5/4/2021

EPC-06/HW/2122 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 67+465 LHS 5/3/2021 5/4/2021

EPC-06/HW/2123 Laying of DBM on Minor Junction DBM 67+465 LHS 5/3/2021 5/4/2021

EPC-06/HW/2124 Level & FDD Checking For GSB layer GSB 68+000 68+300 LHS 5/3/2021 5/4/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2125 Dismantling of existing BT surface BT Scr 50+900 51+650 BHS 5/3/2021 5/4/2021

EPC-06/HW/2128 Level & FDD Checking For GSB layer GSB 59+890 60+620 LHS 5/4/2021 5/5/2021

EPC-06/HW/2129 FDD Checking of WMM 1st layer WMM-I 60+680 61+000 LHS 5/4/2021 5/5/2021

EPC-06/HW/2130 Level & FDD Checking of WMM Top layer WMM-II 64+000 64+250 LHS 5/4/2021 5/5/2021

EPC-06/HW/2131 Applying primer coat Prime coat 64+000 64+250 LHS 5/4/2021 5/5/2021

EPC-06/HW/2132 Level and FDD checking of DLC layer DLC 68+440 68+500 LHS 5/4/2021 5/5/2021

EPC-06/HW/2133 Dismantling of existing BT surface BT Scr 51+650 53+000 BHS 5/4/2021 5/5/2021

EPC-06/HW/2138 Level & FDD Checking For GSB layer GSB 59+070 59+830 LHS 5/5/2021 5/6/2021

EPC-06/HW/2139 FDD Checking of WMM 1st layer WMM-I 59+890 60+620 LHS 5/5/2021 5/6/2021

EPC-06/HW/2140 Level & FDD Checking of WMM Top layer WMM-II 60+680 61+000 LHS 5/5/2021 5/6/2021

EPC-06/HW/2141 Applying primer coat Prime coat 60+680 61+000 LHS 5/5/2021 5/6/2021

EPC-06/HW/2142 Level and FDD checking of DLC layer DLC 68+000 68+300 LHS 5/5/2021 5/6/2021

EPC-06/HW/2146 Level & FDD Checking For GSB layer GSB 58+840 59+010 LHS 5/6/2021 5/7/2021

EPC-06/HW/2147 Level & FDD Checking For GSB layer GSB 58+300 58+740 LHS 5/6/2021 5/7/2021

EPC-06/HW/2148 FDD Checking of WMM 1st layer WMM-I 59+070 59+830 LHS 5/6/2021 5/7/2021

EPC-06/HW/2149 Level & FDD Checking of WMM Top layer WMM-II 59+890 60+620 LHS 5/6/2021 5/7/2021

EPC-06/HW/2150 Applying primer coat Prime coat 59+890 60+620 LHS 5/6/2021 5/7/2021

EPC-06/HW/2151 Applying tack coat for DBM Tack coat (DBM) 65+010 65+900 LHS 5/6/2021 5/7/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2151 Applying tack coat for DBM Tack coat (DBM) 64+520 64+890 LHS 5/6/2021 5/7/2021

EPC-06/HW/2151 Applying tack coat for DBM Tack coat (DBM) 64+310 64+450 LHS 5/6/2021 5/7/2021

EPC-06/HW/2151 Applying tack coat for DBM Tack coat (DBM) 64+000 64+250 LHS 5/6/2021 5/7/2021

EPC-06/HW/2155 Level checking and laying of DBM DBM 65+010 65+900 LHS 5/6/2021 5/7/2021

EPC-06/HW/2155 Level checking and laying of DBM DBM 64+520 64+890 LHS 5/6/2021 5/7/2021

EPC-06/HW/2155 Level checking and laying of DBM DBM 64+310 64+450 LHS 5/6/2021 5/7/2021

EPC-06/HW/2155 Level checking and laying of DBM DBM 64+000 64+250 LHS 5/6/2021 5/7/2021

EPC-06/HW/2156 Level & FDD Checking of Subgrade Top layer SG Top 50+050 50+950 LHS 5/6/2021 5/7/2021

EPC-06/HW/2163 FDD Checking of WMM 1st layer WMM-I 58+840 59+010 LHS 5/7/2021 5/8/2021

EPC-06/HW/2164 FDD Checking of WMM 1st layer WMM-I 58+300 58+740 LHS 5/7/2021 5/8/2021

EPC-06/HW/2165 Level & FDD Checking of WMM Top layer WMM-II 59+070 59+830 LHS 5/7/2021 5/8/2021

EPC-06/HW/2166 Applying primer coat Prime coat 59+070 59+830 LHS 5/7/2021 5/8/2021

EPC-06/HW/2167 FDD Checking of Subgrade Top layer on Minor Junction SG Top 60+150 LHS 5/7/2021 5/8/2021

EPC-06/HW/2168 Level & FDD Checking of Subgrade Top layer SG Top 50+950 52+000 LHS 5/7/2021 5/8/2021

EPC-06/HW/2173 Level & FDD Checking of WMM Top layer WMM-II 58+840 59+010 LHS 5/8/2021 5/9/2021

EPC-06/HW/2174 Level & FDD Checking of WMM Top layer WMM-II 58+300 58+740 LHS 5/8/2021 5/9/2021

EPC-06/HW/2175 Applying primer coat Prime coat 58+840 59+010 LHS 5/8/2021 5/9/2021

EPC-06/HW/2176 Applying primer coat Prime coat 58+300 58+740 LHS 5/8/2021 5/9/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2177 Level & FDD Checking of Subgrade Top layer SG Top 89+270 89+285 LHS 5/8/2021 5/9/2021

EPC-06/HW/2178 FDD Checking For GSB layer on Minor Junction GSB 60+150 LHS 5/8/2021 5/9/2021

EPC-06/HW/2179 Level & FDD Checking of Subgrade Top layer SG Top 52+100 53+000 LHS 5/8/2021 5/9/2021

EPC-06/HW/2180 Level & FDD Checking For GSB layer GSB 50+050 50+950 LHS 5/8/2021 5/9/2021

EPC-06/HW/2183 Level & FDD Checking For GSB layer GSB 89+270 89+285 LHS 5/9/2021 5/10/2021

EPC-06/HW/2184 FDD Checking of WMM Top layer on Minor Junction WMM-II 60+150 LHS 5/9/2021 5/10/2021

EPC-06/HW/2185 Applying primer coat on Minor Junction Prime coat 60+150 LHS 5/9/2021 5/10/2021

EPC-06/HW/2186 Level & FDD Checking For GSB layer GSB 50+950 52+000 LHS 5/9/2021 5/10/2021

EPC-06/HW/2187 FDD Checking of WMM 1st layer WMM-I 50+050 50+950 LHS 5/9/2021 5/10/2021

EPC-06/HW/2190 Level & FDD Checking of Subgrade Top layer SG Top 85+670 86+445 LHS 5/10/2021 5/11/2021

EPC-06/HW/2191 Applying tack coat for DBM Tack coat (DBM) 60+680 61+000 LHS 5/10/2021 5/11/2021

EPC-06/HW/2191 Applying tack coat for DBM Tack coat (DBM) 59+890 60+620 LHS 5/10/2021 5/11/2021

EPC-06/HW/2193 Applying tack coat for DBM Tack coat (DBM) 59+070 59+830 LHS 5/10/2021 5/11/2021

EPC-06/HW/2193 Applying tack coat for DBM Tack coat (DBM) 58+840 59+010 LHS 5/10/2021 5/11/2021

EPC-06/HW/2193 Applying tack coat for DBM Tack coat (DBM) 58+300 58+740 LHS 5/10/2021 5/11/2021

EPC-06/HW/2196 Level checking and laying of DBM DBM 60+680 61+000 LHS 5/10/2021 5/11/2021

EPC-06/HW/2196 Level checking and laying of DBM DBM 59+890 60+620 LHS 5/10/2021 5/11/2021

EPC-06/HW/2198 Level checking and laying of DBM DBM 59+070 59+830 LHS 5/10/2021 5/11/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2198 Level checking and laying of DBM DBM 58+840 59+010 LHS 5/10/2021 5/11/2021

EPC-06/HW/2198 Level checking and laying of DBM DBM 58+300 58+740 LHS 5/10/2021 5/11/2021

EPC-06/HW/2201 Level and FDD checking of DLC layer DLC 89+270 89+285 LHS 5/10/2021 5/11/2021

EPC-06/HW/2202 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 60+150 LHS 5/10/2021 5/11/2021

EPC-06/HW/2203 Laying of DBM on Minor Junction DBM 60+150 LHS 5/10/2021 5/11/2021

EPC-06/HW/2204 Level & FDD Checking For GSB layer GSB 52+100 53+000 LHS 5/10/2021 5/11/2021

EPC-06/HW/2205 FDD Checking of WMM 1st layer WMM-I 50+950 52+000 LHS 5/10/2021 5/11/2021

EPC-06/HW/2206 Level & FDD Checking of WMM Top layer WMM-II 50+050 50+950 LHS 5/10/2021 5/11/2021

EPC-06/HW/2207 Applying primer coat Prime coat 50+050 50+950 LHS 5/10/2021 5/11/2021

EPC-06/HW/2208 Level & FDD Checking of Subgrade Top layer SG Top 60+680 61+000 RHS 5/11/2021 5/12/2021

EPC-06/HW/2209 FDD Checking of WMM 1st layer WMM-I 52+100 53+000 LHS 5/11/2021 5/12/2021

EPC-06/HW/2210 Level & FDD Checking of WMM Top layer WMM-II 50+950 52+000 LHS 5/11/2021 5/12/2021

EPC-06/HW/2211 Applying primer coat Prime coat 50+950 52+000 LHS 5/11/2021 5/12/2021

EPC-06/HW/2213 Level & FDD Checking of Subgrade Top layer SG Top 59+890 60+620 RHS 5/12/2021 5/13/2021

EPC-06/HW/2214 Level & FDD Checking For GSB layer GSB 85+670 86+445 LHS 5/12/2021 5/13/2021

EPC-06/HW/2215 Level & FDD Checking For GSB layer GSB 60+680 61+000 RHS 5/12/2021 5/13/2021

EPC-06/HW/2216 Level & FDD Checking of WMM Top layer WMM-II 52+100 53+000 LHS 5/12/2021 5/13/2021

EPC-06/HW/2217 Applying primer coat Prime coat 52+100 53+000 LHS 5/12/2021 5/13/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2220 Level & FDD Checking of Subgrade Top layer SG Top 59+070 59+830 RHS 5/13/2021 5/14/2021

EPC-06/HW/2221 Level & FDD Checking For GSB layer GSB 59+890 60+620 RHS 5/13/2021 5/14/2021

EPC-06/HW/2222 FDD Checking of WMM 1st layer WMM-I 85+670 86+445 LHS 5/13/2021 5/14/2021

EPC-06/HW/2223 FDD Checking of WMM 1st layer WMM-I 60+680 61+000 RHS 5/13/2021 5/14/2021

EPC-06/HW/2224 FDD Checking of Subgrade Top layer on Minor Junction SG Top 86+655 RHS 5/13/2021 5/14/2021

EPC-06/HW/2225 Dismantling of existing BT surface BT Scr 49+500 49+900 BHS 5/13/2021 5/14/2021

EPC-06/HW/2226 Applying tack coat for DBM Tack coat (DBM) 50+050 50+500 LHS 5/13/2021 5/14/2021

EPC-06/HW/2226 Applying tack coat for DBM Tack coat (DBM) 50+500 50+950 LHS 5/13/2021 5/14/2021

EPC-06/HW/2226 Applying tack coat for DBM Tack coat (DBM) 50+950 51+400 LHS 5/13/2021 5/14/2021

EPC-06/HW/2227 Level checking and laying of DBM DBM 50+050 50+500 LHS 5/13/2021 5/14/2021

EPC-06/HW/2227 Level checking and laying of DBM DBM 50+500 50+950 LHS 5/13/2021 5/14/2021

EPC-06/HW/2227 Level checking and laying of DBM DBM 50+950 51+400 LHS 5/13/2021 5/14/2021

EPC-06/HW/2230 Level & FDD Checking of Subgrade Top layer SG Top 58+840 59+010 RHS 5/14/2021 5/15/2021

EPC-06/HW/2231 Level & FDD Checking of Subgrade Top layer SG Top 58+300 58+740 RHS 5/14/2021 5/15/2021

EPC-06/HW/2232 Level & FDD Checking For GSB layer GSB 59+070 59+830 RHS 5/14/2021 5/15/2021

EPC-06/HW/2233 Level & FDD Checking of WMM Top layer WMM-II 85+670 86+445 LHS 5/14/2021 5/15/2021

EPC-06/HW/2234 Level & FDD Checking of WMM Top layer WMM-II 60+680 61+000 RHS 5/14/2021 5/15/2021

EPC-06/HW/2235 Applying primer coat Prime coat 85+670 86+445 LHS 5/14/2021 5/15/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2236 Applying primer coat Prime coat 60+680 61+000 RHS 5/14/2021 5/15/2021

EPC-06/HW/2237 Level & FDD Checking of Subgrade Top layer SG Top 49+500 49+900 LHS 5/14/2021 5/15/2021

EPC-06/HW/2238 FDD Checking For GSB layer on Minor Junction GSB 86+655 RHS 5/14/2021 5/15/2021

EPC-06/HW/2239 Applying tack coat for DBM Tack coat (DBM) 51+400 52+000 LHS 5/14/2021 5/15/2021

EPC-06/HW/2239 Applying tack coat for DBM Tack coat (DBM) 52+100 52+550 LHS 5/14/2021 5/15/2021

EPC-06/HW/2239 Applying tack coat for DBM Tack coat (DBM) 52+550 53+000 LHS 5/14/2021 5/15/2021

EPC-06/HW/2240 Level checking and laying of DBM DBM 51+400 52+000 LHS 5/14/2021 5/15/2021

EPC-06/HW/2240 Level checking and laying of DBM DBM 52+100 52+550 LHS 5/14/2021 5/15/2021

EPC-06/HW/2240 Level checking and laying of DBM DBM 52+550 53+000 LHS 5/14/2021 5/15/2021

EPC-06/HW/2241 Dismantling of existing BT surface BT Scr 44+400 45+600 BHS 5/14/2021 5/15/2021

EPC-06/HW/2243 Level & FDD Checking For GSB layer GSB 58+840 59+010 RHS 5/15/2021 5/16/2021

EPC-06/HW/2244 Level & FDD Checking For GSB layer GSB 58+300 58+740 RHS 5/15/2021 5/16/2021

EPC-06/HW/2245 Applying tack coat for DBM Tack coat (DBM) 91+300 92+100 RHS 5/15/2021 5/16/2021

EPC-06/HW/2245 Applying tack coat for DBM Tack coat (DBM) 92+100 92+600 RHS 5/15/2021 5/16/2021

EPC-06/HW/2247 Level checking and laying of DBM DBM 91+300 92+100 RHS 5/15/2021 5/16/2021

EPC-06/HW/2247 Level checking and laying of DBM DBM 92+100 92+600 RHS 5/15/2021 5/16/2021

EPC-06/HW/2249 Level & FDD Checking For GSB layer GSB 49+500 49+900 LHS 5/15/2021 5/16/2021

EPC-06/HW/2250 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+630 68+700 LHS 5/15/2021 5/16/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2251 FDD Checking of WMM Top layer on Minor Junction WMM-II 86+655 RHS 5/15/2021 5/16/2021

EPC-06/HW/2252 Applying primer coat on Minor Junction Prime coat 86+655 RHS 5/15/2021 5/16/2021

EPC-06/HW/2253 Dismantling of existing BT surface BT Scr 45+600 47+000 BHS 5/15/2021 5/16/2021

EPC-06/HW/2258 FDD Checking of WMM 1st layer WMM-I 59+890 60+620 RHS 5/16/2021 5/17/2021

EPC-06/HW/2259 Applying tack coat for DBM Tack coat (DBM) 92+600 93+140 RHS 5/16/2021 5/17/2021

EPC-06/HW/2259 Applying tack coat for DBM Tack coat (DBM) 93+140 93+700 RHS 5/16/2021 5/17/2021

EPC-06/HW/2259 Applying tack coat for DBM Tack coat (DBM) 93+770 94+200 RHS 5/16/2021 5/17/2021

EPC-06/HW/2262 Applying tack coat for DBM Tack coat (DBM) 85+670 86+445 LHS 5/16/2021 5/17/2021

EPC-06/HW/2263 Level checking and laying of DBM DBM 92+600 93+140 RHS 5/16/2021 5/17/2021

EPC-06/HW/2263 Level checking and laying of DBM DBM 93+140 93+700 RHS 5/16/2021 5/17/2021

EPC-06/HW/2263 Level checking and laying of DBM DBM 93+770 94+200 RHS 5/16/2021 5/17/2021

EPC-06/HW/2266 Level checking and laying of DBM DBM 85+670 86+445 LHS 5/16/2021 5/17/2021

EPC-06/HW/2267 Level and FDD checking of DLC layer DLC 49+500 49+900 LHS 5/16/2021 5/17/2021

EPC-06/HW/2268 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+510 68+630 LHS 5/16/2021 5/17/2021

EPC-06/HW/2269 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 86+655 RHS 5/16/2021 5/17/2021

EPC-06/HW/2270 Laying of DBM on Minor Junction DBM 86+655 RHS 5/16/2021 5/17/2021

EPC-06/HW/2271 Dismantling of existing BT surface BT Scr 47+000 48+970 BHS 5/16/2021 5/17/2021

EPC-06/HW/2277 FDD Checking of WMM 1st layer WMM-I 59+070 59+830 RHS 5/17/2021 5/18/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2278 Level & FDD Checking of WMM Top layer WMM-II 59+890 60+620 RHS 5/17/2021 5/18/2021

EPC-06/HW/2279 Applying primer coat Prime coat 59+890 60+620 RHS 5/17/2021 5/18/2021

EPC-06/HW/2280 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+270 89+285 LHS 5/17/2021 5/18/2021

EPC-06/HW/2281 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+440 68+510 LHS 5/17/2021 5/18/2021

EPC-06/HW/2282 Level & FDD Checking of Subgrade Top layer SG Top 85+670 86+445 RHS 5/17/2021 5/18/2021

EPC-06/HW/2288 FDD Checking of WMM 1st layer WMM-I 58+840 59+010 RHS 5/18/2021 5/19/2021

EPC-06/HW/2289 FDD Checking of WMM 1st layer WMM-I 58+300 58+740 RHS 5/18/2021 5/19/2021

EPC-06/HW/2290 Level & FDD Checking of WMM Top layer WMM-II 59+070 59+830 RHS 5/18/2021 5/19/2021

EPC-06/HW/2291 Applying primer coat Prime coat 59+070 59+830 RHS 5/18/2021 5/19/2021

EPC-06/HW/2293 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 89+270 89+285 LHS 5/18/2021 5/19/2021

EPC-06/HW/2294 Level & FDD Checking of Subgrade Top layer SG Top 44+400 44+900 LHS 5/18/2021 5/19/2021

EPC-06/HW/2300 Level & FDD Checking of WMM Top layer WMM-II 58+840 59+010 RHS 5/19/2021 5/20/2021

EPC-06/HW/2301 Level & FDD Checking of WMM Top layer WMM-II 58+300 58+740 RHS 5/19/2021 5/20/2021

EPC-06/HW/2302 Applying primer coat Prime coat 58+840 59+010 RHS 5/19/2021 5/20/2021

EPC-06/HW/2303 Applying primer coat Prime coat 58+300 58+740 RHS 5/19/2021 5/20/2021

EPC-06/HW/2304 Level & FDD Checking of Subgrade Top layer SG Top 86+800 86+845 LHS 5/19/2021 5/20/2021

EPC-06/HW/2305 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+620 68+700 LHS 5/19/2021 5/20/2021

EPC-06/HW/2306 Level & FDD Checking of Subgrade Top layer SG Top 44+900 45+600 LHS 5/19/2021 5/20/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2307 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+210 68+300 LHS 5/19/2021 5/20/2021

EPC-06/HW/2312 Applying tack coat for DBM Tack coat (DBM) 60+680 61+000 RHS 5/20/2021 5/21/2021

EPC-06/HW/2312 Applying tack coat for DBM Tack coat (DBM) 59+890 60+620 RHS 5/20/2021 5/21/2021

EPC-06/HW/2314 Applying tack coat for DBM Tack coat (DBM) 59+070 59+830 RHS 5/20/2021 5/21/2021

EPC-06/HW/2314 Applying tack coat for DBM Tack coat (DBM) 58+840 59+010 RHS 5/20/2021 5/21/2021

EPC-06/HW/2314 Applying tack coat for DBM Tack coat (DBM) 58+300 58+740 RHS 5/20/2021 5/21/2021

EPC-06/HW/2317 Level checking and laying of DBM DBM 60+680 61+000 RHS 5/20/2021 5/21/2021

EPC-06/HW/2317 Level checking and laying of DBM DBM 59+890 60+620 RHS 5/20/2021 5/21/2021

EPC-06/HW/2319 Level checking and laying of DBM DBM 59+070 59+830 RHS 5/20/2021 5/21/2021

EPC-06/HW/2319 Level checking and laying of DBM DBM 58+840 59+010 RHS 5/20/2021 5/21/2021

EPC-06/HW/2319 Level checking and laying of DBM DBM 58+300 58+740 RHS 5/20/2021 5/21/2021

EPC-06/HW/2322 Level & FDD Checking of Subgrade Top layer SG Top 86+445 86+530 LHS 5/20/2021 5/21/2021

EPC-06/HW/2323 Level & FDD Checking For GSB layer GSB 86+800 86+845 LHS 5/20/2021 5/21/2021

EPC-06/HW/2324 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+500 68+620 LHS 5/20/2021 5/21/2021

EPC-06/HW/2325 Level & FDD Checking of Subgrade Top layer SG Top 45+600 46+200 LHS 5/20/2021 5/21/2021

EPC-06/HW/2326 Level & FDD Checking For GSB layer GSB 85+670 86+445 RHS 5/20/2021 5/21/2021

EPC-06/HW/2327 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+100 68+210 LHS 5/20/2021 5/21/2021

EPC-06/HW/2331 Level & FDD Checking For GSB layer GSB 86+445 86+530 LHS 5/21/2021 5/22/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2332 Level and FDD checking of DLC layer DLC 86+800 86+845 LHS 5/21/2021 5/22/2021

EPC-06/HW/2333 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+440 68+500 LHS 5/21/2021 5/22/2021

EPC-06/HW/2334 Level & FDD Checking of Subgrade Top layer SG Top 46+200 46+940 LHS 5/21/2021 5/22/2021

EPC-06/HW/2335 Level & FDD Checking For GSB layer GSB 44+400 44+900 LHS 5/21/2021 5/22/2021

EPC-06/HW/2336 FDD Checking of WMM 1st layer WMM-I 85+670 86+445 RHS 5/21/2021 5/22/2021

EPC-06/HW/2337 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+000 68+100 LHS 5/21/2021 5/22/2021

EPC-06/HW/2340 Level and FDD checking of DLC layer DLC 86+445 86+530 LHS 5/22/2021 5/23/2021

EPC-06/HW/2342 Level & FDD Checking of Subgrade Top layer SG Top 50+050 50+950 RHS 5/22/2021 5/23/2021

EPC-06/HW/2343 Level & FDD Checking of Subgrade Top layer SG Top 47+000 47+970 LHS 5/22/2021 5/23/2021

EPC-06/HW/2344 Level & FDD Checking For GSB layer GSB 44+900 45+600 LHS 5/22/2021 5/23/2021

EPC-06/HW/2345 Level & FDD Checking of WMM Top layer WMM-II 85+670 86+445 RHS 5/22/2021 5/23/2021

EPC-06/HW/2346 Applying primer coat Prime coat 85+670 86+445 RHS 5/22/2021 5/23/2021

EPC-06/HW/2347 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+500 49+560 LHS 5/23/2021 5/24/2021

EPC-06/HW/2348 Level & FDD Checking of Subgrade Top layer SG Top 50+950 52+000 RHS 5/23/2021 5/24/2021

EPC-06/HW/2349 Level & FDD Checking of Subgrade Top layer SG Top 48+030 48+970 LHS 5/23/2021 5/24/2021

EPC-06/HW/2350 Level & FDD Checking For GSB layer GSB 45+600 46+200 LHS 5/23/2021 5/24/2021

EPC-06/HW/2351 FDD Checking of WMM 1st layer WMM-I 44+400 44+900 LHS 5/23/2021 5/24/2021

EPC-06/HW/2352 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+210 68+300 LHS 5/23/2021 5/24/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2354 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+560 49+680 LHS 5/24/2021 5/25/2021

EPC-06/HW/2355 Level & FDD Checking of Subgrade Top layer SG Top 52+100 53+000 RHS 5/24/2021 5/25/2021

EPC-06/HW/2356 Level & FDD Checking For GSB layer GSB 50+050 50+950 RHS 5/24/2021 5/25/2021

EPC-06/HW/2357 Level & FDD Checking For GSB layer GSB 46+200 46+940 LHS 5/24/2021 5/25/2021

EPC-06/HW/2358 FDD Checking of WMM 1st layer WMM-I 44+900 45+600 LHS 5/24/2021 5/25/2021

EPC-06/HW/2359 Level & FDD Checking of WMM Top layer WMM-II 44+400 44+900 LHS 5/24/2021 5/25/2021

EPC-06/HW/2360 Applying primer coat Prime coat 44+400 44+900 LHS 5/24/2021 5/25/2021

EPC-06/HW/2361 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+100 68+210 LHS 5/24/2021 5/25/2021

EPC-06/HW/2371 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+680 49+800 LHS 5/25/2021 5/26/2021

EPC-06/HW/2372 Level & FDD Checking For GSB layer GSB 50+950 52+000 RHS 5/25/2021 5/26/2021

EPC-06/HW/2373 Level & FDD Checking For GSB layer GSB 47+000 47+970 LHS 5/25/2021 5/26/2021

EPC-06/HW/2374 FDD Checking of WMM 1st layer WMM-I 50+050 50+950 RHS 5/25/2021 5/26/2021

EPC-06/HW/2375 FDD Checking of WMM 1st layer WMM-I 45+600 46+200 LHS 5/25/2021 5/26/2021

EPC-06/HW/2376 Level & FDD Checking of WMM Top layer WMM-II 44+900 45+600 LHS 5/25/2021 5/26/2021

EPC-06/HW/2377 Applying primer coat Prime coat 44+900 45+600 LHS 5/25/2021 5/26/2021

EPC-06/HW/2378 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+000 68+100 LHS 5/25/2021 5/26/2021

EPC-06/HW/2388 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+800 49+900 LHS 5/26/2021 5/27/2021

EPC-06/HW/2389 Level & FDD Checking For GSB layer GSB 52+100 53+000 RHS 5/26/2021 5/27/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2390 Level & FDD Checking For GSB layer GSB 48+030 48+970 LHS 5/26/2021 5/27/2021

EPC-06/HW/2391 FDD Checking of WMM 1st layer WMM-I 50+950 52+000 RHS 5/26/2021 5/27/2021

EPC-06/HW/2392 FDD Checking of WMM 1st layer WMM-I 46+200 46+940 LHS 5/26/2021 5/27/2021

EPC-06/HW/2393 Level & FDD Checking of WMM Top layer WMM-II 50+050 50+950 RHS 5/26/2021 5/27/2021

EPC-06/HW/2394 Level & FDD Checking of WMM Top layer WMM-II 45+600 46+200 LHS 5/26/2021 5/27/2021

EPC-06/HW/2395 Applying primer coat Prime coat 50+050 50+950 RHS 5/26/2021 5/27/2021

EPC-06/HW/2396 Applying primer coat Prime coat 45+600 46+200 LHS 5/26/2021 5/27/2021

EPC-06/HW/2406 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+500 49+560 LHS 5/27/2021 5/28/2021

EPC-06/HW/2407 FDD Checking of WMM 1st layer WMM-I 52+100 53+000 RHS 5/27/2021 5/28/2021

EPC-06/HW/2408 FDD Checking of WMM 1st layer WMM-I 47+000 47+970 LHS 5/27/2021 5/28/2021

EPC-06/HW/2409 Level & FDD Checking of WMM Top layer WMM-II 50+950 52+000 RHS 5/27/2021 5/28/2021

EPC-06/HW/2410 Level & FDD Checking of WMM Top layer WMM-II 46+200 46+940 LHS 5/27/2021 5/28/2021

EPC-06/HW/2411 Applying primer coat Prime coat 50+950 52+000 RHS 5/27/2021 5/28/2021

EPC-06/HW/2412 Applying primer coat Prime coat 46+200 46+940 LHS 5/27/2021 5/28/2021

EPC-06/HW/2422 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+800 86+845 LHS 5/28/2021 5/29/2021

EPC-06/HW/2423 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+560 49+680 LHS 5/28/2021 5/29/2021

EPC-06/HW/2424 FDD Checking of WMM 1st layer WMM-I 48+030 48+970 LHS 5/28/2021 5/29/2021

EPC-06/HW/2425 Level & FDD Checking of WMM Top layer WMM-II 52+100 53+000 RHS 5/28/2021 5/29/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2426 Level & FDD Checking of WMM Top layer WMM-II 47+000 47+970 LHS 5/28/2021 5/29/2021

EPC-06/HW/2427 Applying primer coat Prime coat 52+100 53+000 RHS 5/28/2021 5/29/2021

EPC-06/HW/2428 Applying primer coat Prime coat 47+000 47+970 LHS 5/28/2021 5/29/2021

EPC-06/HW/2429 Applying tack coat for DBM Tack coat (DBM) 85+670 86+445 RHS 5/28/2021 5/29/2021

EPC-06/HW/2430 Level checking and laying of DBM DBM 85+670 86+445 RHS 5/28/2021 5/29/2021

EPC-06/HW/2440 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+445 86+530 LHS 5/29/2021 5/30/2021

EPC-06/HW/2441 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+800 86+845 LHS 5/29/2021 5/30/2021

EPC-06/HW/2442 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+680 49+800 LHS 5/29/2021 5/30/2021

EPC-06/HW/2443 Level & FDD Checking of WMM Top layer WMM-II 48+030 48+970 LHS 5/29/2021 5/30/2021

EPC-06/HW/2444 Applying primer coat Prime coat 48+030 48+970 LHS 5/29/2021 5/30/2021

EPC-06/HW/2445 Applying tack coat for DBM Tack coat (DBM) 50+050 50+500 RHS 5/29/2021 5/30/2021

EPC-06/HW/2445 Applying tack coat for DBM Tack coat (DBM) 50+500 50+950 RHS 5/29/2021 5/30/2021

EPC-06/HW/2445 Applying tack coat for DBM Tack coat (DBM) 50+950 51+400 RHS 5/29/2021 5/30/2021

EPC-06/HW/2448 Level checking and laying of DBM DBM 50+050 50+500 RHS 5/29/2021 5/30/2021

EPC-06/HW/2448 Level checking and laying of DBM DBM 50+500 50+950 RHS 5/29/2021 5/30/2021

EPC-06/HW/2448 Level checking and laying of DBM DBM 50+950 51+400 RHS 5/29/2021 5/30/2021

EPC-06/HW/2449 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 50+133 RHS 5/29/2021 5/30/2021

EPC-06/HW/2450 Laying of DBM on Minor Junction DBM 50+133 RHS 5/29/2021 5/30/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2460 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+445 86+530 LHS 5/30/2021 5/31/2021

EPC-06/HW/2461 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+800 49+900 LHS 5/30/2021 5/31/2021

EPC-06/HW/2462 Applying tack coat for DBM Tack coat (DBM) 51+400 52+000 RHS 5/30/2021 5/31/2021

EPC-06/HW/2462 Applying tack coat for DBM Tack coat (DBM) 52+100 52+550 RHS 5/30/2021 5/31/2021

EPC-06/HW/2462 Applying tack coat for DBM Tack coat (DBM) 52+550 53+000 RHS 5/30/2021 5/31/2021

EPC-06/HW/2465 Level checking and laying of DBM DBM 51+400 52+000 RHS 5/30/2021 5/31/2021

EPC-06/HW/2465 Level checking and laying of DBM DBM 52+100 52+550 RHS 5/30/2021 5/31/2021

EPC-06/HW/2465 Level checking and laying of DBM DBM 52+550 53+000 RHS 5/30/2021 5/31/2021

EPC-06/HW/2480 Level & FDD Checking of Subgrade Top layer SG Top 79+960 80+000 BHS 5/31/2021 6/1/2021

EPC-06/HW/2481 Level & FDD Checking of Subgrade Top layer SG Top 80+440 80+500 BHS 5/31/2021 6/1/2021

EPC-06/HW/2482 Level & FDD Checking of Subgrade Top layer SG Top 80+950 81+050 BHS 5/31/2021 6/1/2021

EPC-06/HW/2483 Level & FDD Checking of Subgrade Top layer SG Top 81+440 81+500 BHS 5/31/2021 6/1/2021

EPC-06/HW/2489 Level & FDD Checking of Subgrade Top layer SG Top 73+560 73+620 BHS 6/1/2021 6/2/2021

EPC-06/HW/2490 Level & FDD Checking of Subgrade Top layer SG Top 74+980 75+180 BHS 6/1/2021 6/2/2021

EPC-06/HW/2491 Level & FDD Checking of Subgrade Top layer SG Top 75+900 76+060 BHS 6/1/2021 6/2/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2492 Level & FDD Checking of Subgrade Top layer SG Top 76+560 76+720 BHS 6/1/2021 6/2/2021

EPC-06/HW/2493 Level & FDD Checking of Subgrade Top layer SG Top 77+220 77+300 BHS 6/1/2021 6/2/2021

EPC-06/HW/2494 Level & FDD Checking of Subgrade Top layer SG Top 79+640 79+700 BHS 6/1/2021 6/2/2021

EPC-06/HW/2495 Level & FDD Checking For GSB layer GSB 79+940 80+020 BHS 6/1/2021 6/2/2021

EPC-06/HW/2496 Level & FDD Checking For GSB layer GSB 80+420 80+500 BHS 6/1/2021 6/2/2021

EPC-06/HW/2497 Level & FDD Checking For GSB layer GSB 80+950 81+050 BHS 6/1/2021 6/2/2021

EPC-06/HW/2498 Level & FDD Checking For GSB layer GSB 81+440 81+500 BHS 6/1/2021 6/2/2021

EPC-06/HW/2504 Level & FDD Checking of Subgrade Top layer SG Top 70+900 71+100 LHS 6/2/2021 6/3/2021

EPC-06/HW/2505 Level & FDD Checking of Subgrade Top layer SG Top 70+980 71+100 RHS 6/2/2021 6/3/2021

EPC-06/HW/2506 Level & FDD Checking of Subgrade Top layer SG Top 73+040 73+120 LHS 6/2/2021 6/3/2021

EPC-06/HW/2507 Level & FDD Checking of Subgrade Top layer SG Top 73+045 73+120 RHS 6/2/2021 6/3/2021

EPC-06/HW/2508 Level & FDD Checking For GSB layer GSB 73+560 73+620 BHS 6/2/2021 6/3/2021

EPC-06/HW/2509 Level & FDD Checking For GSB layer GSB 74+980 75+180 BHS 6/2/2021 6/3/2021

EPC-06/HW/2510 Level & FDD Checking For GSB layer GSB 75+900 76+060 BHS 6/2/2021 6/3/2021

EPC-06/HW/2511 Level & FDD Checking For GSB layer GSB 76+560 76+720 BHS 6/2/2021 6/3/2021

EPC-06/HW/2512 Level & FDD Checking For GSB layer GSB 77+220 77+300 BHS 6/2/2021 6/3/2021

EPC-06/HW/2513 Level & FDD Checking For GSB layer GSB 79+640 79+700 BHS 6/2/2021 6/3/2021

EPC-06/HW/2514 FDD Checking of WMM 1st layer WMM-I 79+940 80+020 BHS 6/2/2021 6/3/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2515 FDD Checking of WMM 1st layer WMM-I 80+420 80+500 BHS 6/2/2021 6/3/2021

EPC-06/HW/2516 FDD Checking of WMM 1st layer WMM-I 80+950 81+050 BHS 6/2/2021 6/3/2021

EPC-06/HW/2517 FDD Checking of WMM 1st layer WMM-I 81+440 81+500 BHS 6/2/2021 6/3/2021

EPC-06/HW/2524 Level & FDD Checking of Subgrade Top layer SG Top 70+280 70+340 LHS 6/3/2021 6/4/2021

EPC-06/HW/2525 Level & FDD Checking of Subgrade Top layer SG Top 70+280 70+335 RHS 6/3/2021 6/4/2021

EPC-06/HW/2526 Level & FDD Checking of Subgrade Top layer SG Top 70+710 70+750 BHS 6/3/2021 6/4/2021

EPC-06/HW/2527 Level & FDD Checking For GSB layer GSB 70+900 71+100 LHS 6/3/2021 6/4/2021

EPC-06/HW/2528 Level & FDD Checking For GSB layer GSB 70+980 71+100 RHS 6/3/2021 6/4/2021

EPC-06/HW/2529 Level & FDD Checking For GSB layer GSB 73+040 73+120 BHS 6/3/2021 6/4/2021

EPC-06/HW/2530 FDD Checking of WMM 1st layer WMM-I 73+560 73+620 BHS 6/3/2021 6/4/2021

EPC-06/HW/2531 FDD Checking of WMM 1st layer WMM-I 74+980 75+180 BHS 6/3/2021 6/4/2021

EPC-06/HW/2532 FDD Checking of WMM 1st layer WMM-I 75+900 76+060 BHS 6/3/2021 6/4/2021

EPC-06/HW/2533 FDD Checking of WMM 1st layer WMM-I 76+560 76+720 BHS 6/3/2021 6/4/2021

EPC-06/HW/2534 FDD Checking of WMM 1st layer WMM-I 77+220 77+300 BHS 6/3/2021 6/4/2021

EPC-06/HW/2535 FDD Checking of WMM 1st layer WMM-I 79+640 79+700 BHS 6/3/2021 6/4/2021

EPC-06/HW/2536 Level & FDD Checking of WMM Top layer WMM-II 79+940 80+020 BHS 6/3/2021 6/4/2021

EPC-06/HW/2537 Level & FDD Checking of WMM Top layer WMM-II 80+420 80+500 BHS 6/3/2021 6/4/2021

EPC-06/HW/2538 Level & FDD Checking of WMM Top layer WMM-II 80+950 81+050 BHS 6/3/2021 6/4/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2539 Level & FDD Checking of WMM Top layer WMM-II 81+440 81+500 BHS 6/3/2021 6/4/2021

EPC-06/HW/2540 Applying primer coat Prime coat 79+940 80+020 BHS 6/3/2021 6/4/2021

EPC-06/HW/2540 Applying primer coat Prime coat 80+420 80+500 BHS 6/3/2021 6/4/2021

EPC-06/HW/2540 Applying primer coat Prime coat 80+950 81+050 BHS 6/3/2021 6/4/2021

EPC-06/HW/2540 Applying primer coat Prime coat 81+440 81+500 BHS 6/3/2021 6/4/2021

EPC-06/HW/2549 Level & FDD Checking For GSB layer GSB 70+280 70+340 BHS 6/4/2021 6/5/2021

EPC-06/HW/2550 Level & FDD Checking For GSB layer GSB 70+710 70+750 BHS 6/4/2021 6/5/2021

EPC-06/HW/2551 FDD Checking of WMM 1st layer WMM-I 70+900 71+100 LHS 6/4/2021 6/5/2021

EPC-06/HW/2552 FDD Checking of WMM 1st layer WMM-I 70+980 71+100 RHS 6/4/2021 6/5/2021

EPC-06/HW/2553 FDD Checking of WMM 1st layer WMM-I 73+040 73+120 BHS 6/4/2021 6/5/2021

EPC-06/HW/2554 Level & FDD Checking of WMM Top layer WMM-II 73+560 73+620 BHS 6/4/2021 6/5/2021

EPC-06/HW/2555 Level & FDD Checking of WMM Top layer WMM-II 74+980 75+180 BHS 6/4/2021 6/5/2021

EPC-06/HW/2556 Level & FDD Checking of WMM Top layer WMM-II 75+900 76+060 BHS 6/4/2021 6/5/2021

EPC-06/HW/2557 Level & FDD Checking of WMM Top layer WMM-II 76+560 76+720 BHS 6/4/2021 6/5/2021

EPC-06/HW/2558 Level & FDD Checking of WMM Top layer WMM-II 77+220 77+300 BHS 6/4/2021 6/5/2021

EPC-06/HW/2559 Level & FDD Checking of WMM Top layer WMM-II 79+640 79+700 BHS 6/4/2021 6/5/2021

EPC-06/HW/2560 Applying primer coat Prime coat 73+560 73+620 BHS 6/4/2021 6/5/2021

EPC-06/HW/2560 Applying primer coat Prime coat 74+980 75+180 BHS 6/4/2021 6/5/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2560 Applying primer coat Prime coat 75+900 76+060 BHS 6/4/2021 6/5/2021

EPC-06/HW/2563 Applying primer coat Prime coat 76+560 76+720 BHS 6/4/2021 6/5/2021

EPC-06/HW/2563 Applying primer coat Prime coat 77+220 77+300 BHS 6/4/2021 6/5/2021

EPC-06/HW/2563 Applying primer coat Prime coat 79+640 79+700 BHS 6/4/2021 6/5/2021

EPC-06/HW/2571 FDD Checking of WMM 1st layer WMM-I 70+280 70+340 BHS 6/5/2021 6/6/2021

EPC-06/HW/2572 FDD Checking of WMM 1st layer WMM-I 70+710 70+750 BHS 6/5/2021 6/6/2021

EPC-06/HW/2573 Level & FDD Checking of WMM Top layer WMM-II 70+900 71+100 LHS 6/5/2021 6/6/2021

EPC-06/HW/2574 Level & FDD Checking of WMM Top layer WMM-II 70+980 71+100 RHS 6/5/2021 6/6/2021

EPC-06/HW/2575 Level & FDD Checking of WMM Top layer WMM-II 73+040 73+120 BHS 6/5/2021 6/6/2021

EPC-06/HW/2576 Applying primer coat Prime coat 70+900 71+100 LHS 6/5/2021 6/6/2021

EPC-06/HW/2576 Applying primer coat Prime coat 70+980 71+100 RHS 6/5/2021 6/6/2021

EPC-06/HW/2576 Applying primer coat Prime coat 73+040 73+120 BHS 6/5/2021 6/6/2021

EPC-06/HW/2579 Applying tack coat for DBM Tack coat (DBM) 76+560 76+720 BHS 6/5/2021 6/6/2021

EPC-06/HW/2579 Applying tack coat for DBM Tack coat (DBM) 77+220 77+300 BHS 6/5/2021 6/6/2021

EPC-06/HW/2579 Applying tack coat for DBM Tack coat (DBM) 79+630 79+700 LHS 6/5/2021 6/6/2021

EPC-06/HW/2579 Applying tack coat for DBM Tack coat (DBM) 79+640 79+700 RHS 6/5/2021 6/6/2021

EPC-06/HW/2583 Applying tack coat for DBM Tack coat (DBM) 79+940 80+020 BHS 6/5/2021 6/6/2021

EPC-06/HW/2583 Applying tack coat for DBM Tack coat (DBM) 80+420 80+500 BHS 6/5/2021 6/6/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2583 Applying tack coat for DBM Tack coat (DBM) 80+950 81+050 BHS 6/5/2021 6/6/2021

EPC-06/HW/2583 Applying tack coat for DBM Tack coat (DBM) 81+440 81+500 BHS 6/5/2021 6/6/2021

EPC-06/HW/2587 Level checking and laying of DBM DBM 76+560 76+720 BHS 6/5/2021 6/6/2021

EPC-06/HW/2587 Level checking and laying of DBM DBM 77+220 77+300 BHS 6/5/2021 6/6/2021

EPC-06/HW/2587 Level checking and laying of DBM DBM 79+630 79+700 LHS 6/5/2021 6/6/2021

EPC-06/HW/2587 Level checking and laying of DBM DBM 79+640 79+700 RHS 6/5/2021 6/6/2021

EPC-06/HW/2591 Level checking and laying of DBM DBM 79+940 80+020 BHS 6/5/2021 6/6/2021

EPC-06/HW/2591 Level checking and laying of DBM DBM 80+420 80+500 BHS 6/5/2021 6/6/2021

EPC-06/HW/2591 Level checking and laying of DBM DBM 80+950 81+050 BHS 6/5/2021 6/6/2021

EPC-06/HW/2591 Level checking and laying of DBM DBM 81+440 81+500 BHS 6/5/2021 6/6/2021

EPC-06/HW/2600 Level & FDD Checking of WMM Top layer WMM-II 70+280 70+340 BHS 6/6/2021 6/7/2021

EPC-06/HW/2601 Level & FDD Checking of WMM Top layer WMM-II 70+710 70+750 BHS 6/6/2021 6/7/2021

EPC-06/HW/2602 Applying primer coat Prime coat 70+280 70+340 BHS 6/6/2021 6/7/2021

EPC-06/HW/2602 Applying primer coat Prime coat 70+710 70+750 BHS 6/6/2021 6/7/2021

EPC-06/HW/2609 Applying tack coat for DBM Tack coat (DBM) 70+280 70+340 BHS 6/7/2021 6/8/2021

EPC-06/HW/2609 Applying tack coat for DBM Tack coat (DBM) 70+710 70+750 BHS 6/7/2021 6/8/2021

EPC-06/HW/2609 Applying tack coat for DBM Tack coat (DBM) 70+900 71+100 LHS 6/7/2021 6/8/2021

EPC-06/HW/2609 Applying tack coat for DBM Tack coat (DBM) 70+980 71+100 RHS 6/7/2021 6/8/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2613 Applying tack coat for DBM Tack coat (DBM) 73+040 73+120 BHS 6/7/2021 6/8/2021

EPC-06/HW/2613 Applying tack coat for DBM Tack coat (DBM) 73+560 73+620 BHS 6/7/2021 6/8/2021

EPC-06/HW/2613 Applying tack coat for DBM Tack coat (DBM) 74+980 75+180 BHS 6/7/2021 6/8/2021

EPC-06/HW/2613 Applying tack coat for DBM Tack coat (DBM) 75+900 76+060 BHS 6/7/2021 6/8/2021

EPC-06/HW/2617 Level checking and laying of DBM DBM 70+280 70+340 BHS 6/7/2021 6/8/2021

EPC-06/HW/2617 Level checking and laying of DBM DBM 70+710 70+750 BHS 6/7/2021 6/8/2021

EPC-06/HW/2617 Level checking and laying of DBM DBM 70+900 71+100 LHS 6/7/2021 6/8/2021

EPC-06/HW/2617 Level checking and laying of DBM DBM 70+980 71+100 RHS 6/7/2021 6/8/2021

EPC-06/HW/2620 Level checking and laying of DBM DBM 73+040 73+120 BHS 6/7/2021 6/8/2021

EPC-06/HW/2620 Level checking and laying of DBM DBM 73+560 73+620 BHS 6/7/2021 6/8/2021

EPC-06/HW/2620 Level checking and laying of DBM DBM 74+980 75+180 BHS 6/7/2021 6/8/2021

EPC-06/HW/2620 Level checking and laying of DBM DBM 75+900 76+060 BHS 6/7/2021 6/8/2021

EPC-06/HW/2634 Level & FDD Checking of Subgrade Top layer SG Top 64+450 64+520 BHS 6/11/2021 6/12/2021

EPC-06/HW/2635 Level & FDD Checking of Subgrade Top layer SG Top 64+890 65+010 BHS 6/11/2021 6/12/2021

EPC-06/HW/2636 Level & FDD Checking of Subgrade Top layer SG Top 65+900 65+970 BHS 6/11/2021 6/12/2021

EPC-06/HW/2637 Level & FDD Checking of Subgrade Top layer SG Top 66+250 66+320 BHS 6/11/2021 6/12/2021

EPC-06/HW/2638 Level & FDD Checking of Subgrade Top layer SG Top 67+070 67+130 BHS 6/11/2021 6/12/2021

EPC-06/HW/2644 Level & FDD Checking For GSB layer GSB 64+450 64+520 BHS 6/12/2021 6/13/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2645 Level & FDD Checking For GSB layer GSB 64+890 65+010 BHS 6/12/2021 6/13/2021

EPC-06/HW/2646 Level & FDD Checking For GSB layer GSB 65+900 65+970 BHS 6/12/2021 6/13/2021

EPC-06/HW/2647 Level & FDD Checking For GSB layer GSB 66+250 66+320 BHS 6/12/2021 6/13/2021

EPC-06/HW/2648 Level & FDD Checking For GSB layer GSB 67+070 67+130 BHS 6/12/2021 6/13/2021

EPC-06/HW/2654 FDD Checking of WMM 1st layer WMM-I 64+450 64+520 BHS 6/13/2021 6/14/2021

EPC-06/HW/2655 FDD Checking of WMM 1st layer WMM-I 64+890 65+010 BHS 6/13/2021 6/14/2021

EPC-06/HW/2656 FDD Checking of WMM 1st layer WMM-I 65+900 65+970 BHS 6/13/2021 6/14/2021

EPC-06/HW/2657 FDD Checking of WMM 1st layer WMM-I 66+250 66+320 BHS 6/13/2021 6/14/2021

EPC-06/HW/2658 FDD Checking of WMM 1st layer WMM-I 67+070 67+130 BHS 6/13/2021 6/14/2021

EPC-06/HW/2664 Level & FDD Checking of WMM Top layer WMM-II 64+450 64+520 BHS 6/14/2021 6/15/2021

EPC-06/HW/2665 Level & FDD Checking of WMM Top layer WMM-II 64+890 65+010 BHS 6/14/2021 6/15/2021

EPC-06/HW/2666 Level & FDD Checking of WMM Top layer WMM-II 65+900 65+970 BHS 6/14/2021 6/15/2021

EPC-06/HW/2667 Level & FDD Checking of WMM Top layer WMM-II 66+250 66+320 BHS 6/14/2021 6/15/2021

EPC-06/HW/2668 Level & FDD Checking of WMM Top layer WMM-II 67+070 67+130 BHS 6/14/2021 6/15/2021

EPC-06/HW/2669 Applying primer coat Prime coat 64+450 64+520 BHS 6/14/2021 6/15/2021

EPC-06/HW/2669 Applying primer coat Prime coat 64+890 65+010 BHS 6/14/2021 6/15/2021

EPC-06/HW/2669 Applying primer coat Prime coat 65+900 65+970 BHS 6/14/2021 6/15/2021

EPC-06/HW/2672 Applying primer coat Prime coat 66+250 66+320 BHS 6/14/2021 6/15/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2672 Applying primer coat Prime coat 67+070 67+130 BHS 6/14/2021 6/15/2021

EPC-06/HW/2679 Level & FDD Checking of Subgrade Top layer SG Top 59+010 59+070 BHS 6/15/2021 6/16/2021

EPC-06/HW/2680 Level & FDD Checking of Subgrade Top layer SG Top 59+830 59+890 BHS 6/15/2021 6/16/2021

EPC-06/HW/2681 Level & FDD Checking of Subgrade Top layer SG Top 60+620 60+680 BHS 6/15/2021 6/16/2021

EPC-06/HW/2682 Level & FDD Checking of Subgrade Top layer SG Top 64+250 64+310 BHS 6/15/2021 6/16/2021

EPC-06/HW/2688 Applying tack coat for DBM Tack coat (DBM) 64+450 64+520 BHS 6/16/2021 6/17/2021

EPC-06/HW/2688 Applying tack coat for DBM Tack coat (DBM) 64+890 65+010 BHS 6/16/2021 6/17/2021

EPC-06/HW/2688 Applying tack coat for DBM Tack coat (DBM) 65+900 65+970 BHS 6/16/2021 6/17/2021

EPC-06/HW/2691 Applying tack coat for DBM Tack coat (DBM) 66+250 66+320 BHS 6/16/2021 6/17/2021

EPC-06/HW/2691 Applying tack coat for DBM Tack coat (DBM) 67+070 67+130 BHS 6/16/2021 6/17/2021

EPC-06/HW/2693 Level checking and laying of DBM DBM 64+450 64+520 BHS 6/16/2021 6/17/2021

EPC-06/HW/2693 Level checking and laying of DBM DBM 64+890 65+010 BHS 6/16/2021 6/17/2021

EPC-06/HW/2693 Level checking and laying of DBM DBM 65+900 65+970 BHS 6/16/2021 6/17/2021

EPC-06/HW/2696 Level checking and laying of DBM DBM 66+250 66+320 BHS 6/16/2021 6/17/2021

EPC-06/HW/2696 Level checking and laying of DBM DBM 67+070 67+130 BHS 6/16/2021 6/17/2021

EPC-06/HW/2703 Level & FDD Checking For GSB layer GSB 59+010 59+070 BHS 6/17/2021 6/18/2021

EPC-06/HW/2704 Level & FDD Checking For GSB layer GSB 59+830 59+890 BHS 6/17/2021 6/18/2021

EPC-06/HW/2705 Level & FDD Checking For GSB layer GSB 60+620 60+680 BHS 6/17/2021 6/18/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2706 Level & FDD Checking For GSB layer GSB 64+250 64+310 BHS 6/17/2021 6/18/2021

EPC-06/HW/2716 FDD Checking of WMM 1st layer WMM-I 59+010 59+070 BHS 6/19/2021 6/20/2021

EPC-06/HW/2717 FDD Checking of WMM 1st layer WMM-I 59+830 59+890 BHS 6/19/2021 6/20/2021

EPC-06/HW/2718 FDD Checking of WMM 1st layer WMM-I 60+620 60+680 BHS 6/19/2021 6/20/2021

EPC-06/HW/2719 FDD Checking of WMM 1st layer WMM-I 64+250 64+310 BHS 6/19/2021 6/20/2021

EPC-06/HW/2720 Dismantling of existing BT surface BT Scr 88+520 88+900 BHS 6/19/2021 6/20/2021

EPC-06/HW/2725 Level & FDD Checking of WMM Top layer WMM-II 59+010 59+070 BHS 6/20/2021 6/21/2021

EPC-06/HW/2726 Level & FDD Checking of WMM Top layer WMM-II 59+830 59+890 BHS 6/20/2021 6/21/2021

EPC-06/HW/2727 Level & FDD Checking of WMM Top layer WMM-II 60+620 60+680 BHS 6/20/2021 6/21/2021

EPC-06/HW/2728 Level & FDD Checking of WMM Top layer WMM-II 64+250 64+310 BHS 6/20/2021 6/21/2021

EPC-06/HW/2729 Applying primer coat Prime coat 59+010 59+070 BHS 6/20/2021 6/21/2021

EPC-06/HW/2729 Applying primer coat Prime coat 59+830 59+890 BHS 6/20/2021 6/21/2021

EPC-06/HW/2729 Applying primer coat Prime coat 60+620 60+680 BHS 6/20/2021 6/21/2021

EPC-06/HW/2729 Applying primer coat Prime coat 64+250 64+310 BHS 6/20/2021 6/21/2021

EPC-06/HW/2738 Level & FDD Checking of Subgrade Top layer SG Top 68+000 68+080 LHS 6/21/2021 6/22/2021

EPC-06/HW/2739 Level & FDD Checking of Subgrade Top layer SG Top 68+780 69+230 LHS 6/21/2021 6/22/2021

EPC-06/HW/2740 Level & FDD Checking of Subgrade Top layer SG Top 68+000 68+080 RHS 6/21/2021 6/22/2021

EPC-06/HW/2746 Level & FDD Checking For GSB layer GSB 68+000 68+080 LHS 6/22/2021 6/23/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2747 Level & FDD Checking For GSB layer GSB 68+780 69+230 LHS 6/22/2021 6/23/2021

EPC-06/HW/2748 Level & FDD Checking For GSB layer GSB 68+000 68+080 RHS 6/22/2021 6/23/2021

EPC-06/HW/2749 Applying tack coat for DBM Tack coat (DBM) 59+010 59+070 BHS 6/22/2021 6/23/2021

EPC-06/HW/2749 Applying tack coat for DBM Tack coat (DBM) 59+830 59+890 BHS 6/22/2021 6/23/2021

EPC-06/HW/2749 Applying tack coat for DBM Tack coat (DBM) 60+620 60+680 BHS 6/22/2021 6/23/2021

EPC-06/HW/2749 Applying tack coat for DBM Tack coat (DBM) 64+250 64+310 BHS 6/22/2021 6/23/2021

EPC-06/HW/2753 Level checking and laying of DBM DBM 59+010 59+070 BHS 6/22/2021 6/23/2021

EPC-06/HW/2753 Level checking and laying of DBM DBM 59+830 59+890 BHS 6/22/2021 6/23/2021

EPC-06/HW/2755 Level checking and laying of DBM DBM 60+620 60+680 BHS 6/22/2021 6/23/2021

EPC-06/HW/2755 Level checking and laying of DBM DBM 64+250 64+310 BHS 6/22/2021 6/23/2021

EPC-06/HW/2757 FDD Checking of Subgrade Top layer on Minor Junction SG Top 47+755 LHS 6/22/2021 6/23/2021

EPC-06/HW/2758 FDD Checking of Subgrade Top layer on Minor Junction SG Top 47+847 LHS 6/22/2021 6/23/2021

EPC-06/HW/2765 FDD Checking of WMM 1st layer WMM-I 68+000 68+080 LHS 6/23/2021 6/24/2021

EPC-06/HW/2766 FDD Checking of WMM 1st layer WMM-I 68+780 69+230 LHS 6/23/2021 6/24/2021

EPC-06/HW/2767 FDD Checking of WMM 1st layer WMM-I 68+000 68+080 RHS 6/23/2021 6/24/2021

EPC-06/HW/2768 FDD Checking For GSB layer on Minor Junction GSB 47+755 LHS 6/23/2021 6/24/2021

EPC-06/HW/2769 FDD Checking For GSB layer on Minor Junction GSB 47+847 LHS 6/23/2021 6/24/2021

EPC-06/HW/2776 Level & FDD Checking of Subgrade Top layer SG Top 88+650 88+850 BHS 6/24/2021 6/25/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2777 Level & FDD Checking of WMM Top layer WMM-II 68+000 68+080 LHS 6/24/2021 6/25/2021

EPC-06/HW/2778 Level & FDD Checking of WMM Top layer WMM-II 68+780 69+230 LHS 6/24/2021 6/25/2021

EPC-06/HW/2779 Level & FDD Checking of WMM Top layer WMM-II 68+000 68+080 RHS 6/24/2021 6/25/2021

EPC-06/HW/2780 Applying primer coat Prime coat 68+000 68+080 LHS 6/24/2021 6/25/2021

EPC-06/HW/2780 Applying primer coat Prime coat 68+780 69+230 LHS 6/24/2021 6/25/2021

EPC-06/HW/2780 Applying primer coat Prime coat 68+000 68+080 RHS 6/24/2021 6/25/2021

EPC-06/HW/2783 Level & FDD Checking of Subgrade Top layer SG Top 68+440 68+780 RHS 6/24/2021 6/25/2021

EPC-06/HW/2793 FDD Checking of WMM Top layer on Minor Junction WMM-II 47+755 LHS 6/26/2021 6/27/2021

EPC-06/HW/2794 Applying primer coat on Minor Junction Prime coat 47+755 LHS 6/26/2021 6/27/2021

EPC-06/HW/2795 FDD Checking of WMM Top layer on Minor Junction WMM-II 47+847 LHS 6/26/2021 6/27/2021

EPC-06/HW/2794 Applying primer coat on Minor Junction Prime coat 47+847 LHS 6/26/2021 6/27/2021

EPC-06/HW/2802 Level & FDD Checking For GSB layer GSB 88+650 88+850 BHS 6/27/2021 6/28/2021

EPC-06/HW/2803 Applying tack coat for DBM Tack coat (DBM) 68+000 68+080 LHS 6/27/2021 6/28/2021

EPC-06/HW/2803 Applying tack coat for DBM Tack coat (DBM) 68+780 69+230 LHS 6/27/2021 6/28/2021

EPC-06/HW/2803 Applying tack coat for DBM Tack coat (DBM) 68+000 68+080 RHS 6/27/2021 6/28/2021

EPC-06/HW/2806 Level checking and laying of DBM DBM 68+000 68+080 LHS 6/27/2021 6/28/2021

EPC-06/HW/2806 Level checking and laying of DBM DBM 68+780 69+230 LHS 6/27/2021 6/28/2021

EPC-06/HW/2806 Level checking and laying of DBM DBM 68+000 68+080 RHS 6/27/2021 6/28/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2809 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 47+755 LHS 6/27/2021 6/28/2021

EPC-06/HW/2810 Laying of DBM on Minor Junction DBM 47+755 LHS 6/27/2021 6/28/2021

EPC-06/HW/2809 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 47+847 LHS 6/27/2021 6/28/2021

EPC-06/HW/2812 Laying of DBM on Minor Junction DBM 47+847 LHS 6/27/2021 6/28/2021

EPC-06/HW/2822 Level & FDD Checking For GSB layer GSB 68+440 68+780 RHS 6/29/2021 6/30/2021

EPC-06/HW/2828 FDD Checking of WMM 1st layer WMM-I 88+650 88+850 BHS 6/30/2021 7/1/2021

EPC-06/HW/2834 Level & FDD Checking of WMM Top layer WMM-II 88+650 88+850 BHS 7/1/2021 7/2/2021

EPC-06/HW/2835 Applying primer coat Prime coat 88+650 88+850 BHS 7/1/2021 7/2/2021

EPC-06/HW/2836 Level and FDD checking of DLC layer DLC 68+440 68+780 RHS 7/1/2021 7/2/2021

EPC-06/HW/2837 Dismantling of existing BT surface BT Scr 68+780 69+230 BHS 7/1/2021 7/2/2021

EPC-06/HW/2846 Applying tack coat for DBM Tack coat (DBM) 88+650 88+850 BHS 7/3/2021 7/4/2021

EPC-06/HW/2847 Level checking and laying of DBM DBM 88+650 88+850 BHS 7/3/2021 7/4/2021

EPC-06/HW/2848 Laying of DBM on Minor Junction DBM 58+360 RHS 7/3/2021 7/4/2021

EPC-06/HW/2854 Level & FDD Checking of Subgrade Top layer SG Top 68+780 69+230 RHS 7/5/2021 7/6/2021

EPC-06/HW/2865 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+440 68+570 RHS 7/13/2021 7/14/2021

EPC-06/HW/2872 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+570 68+680 RHS 7/15/2021 7/16/2021

EPC-06/HW/2877 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+680 68+780 RHS 7/16/2021 7/17/2021

EPC-06/HW/2884 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+440 68+600 RHS 7/18/2021 7/19/2021

EPC-06/HW/2894 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+600 68+690 RHS 7/22/2021 7/23/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2900 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+690 68+780 RHS 7/24/2021 7/25/2021

EPC-06/HW/2911 Level & FDD Checking of Subgrade Top layer SG Top 49+500 49+900 RHS 7/29/2021 7/30/2021

EPC-06/HW/2923 Level & FDD Checking For GSB layer GSB 49+500 49+900 RHS 8/2/2021 8/3/2021

EPC-06/HW/2930 Level and FDD checking of DLC layer DLC 49+500 49+900 RHS 8/4/2021 8/5/2021

EPC-06/HW/2942 Level & FDD Checking of Subgrade Top layer SG Top 68+080 68+300 RHS 8/9/2021 8/10/2021

EPC-06/HW/2952 Level & FDD Checking For GSB layer GSB 68+080 68+300 RHS 8/12/2021 8/13/2021

EPC-06/HW/2959 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+500 49+620 RHS 8/15/2021 8/16/2021

EPC-06/HW/2964 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+620 49+730 RHS 8/16/2021 8/17/2021

EPC-06/HW/2969 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+730 49+800 RHS 8/17/2021 8/18/2021

EPC-06/HW/2977 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+800 49+900 RHS 8/19/2021 8/20/2021

EPC-06/HW/2987 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+500 49+600 RHS 8/22/2021 8/23/2021

EPC-06/HW/2992 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+600 49+690 RHS 8/24/2021 8/25/2021

EPC-06/HW/2997 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+690 49+830 RHS 8/25/2021 8/26/2021

EPC-06/HW/3003 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+830 49+900 RHS 8/26/2021 8/27/2021

EPC-06/HW/3053 Dismantling of existing BT surface BT Scr 44+300 44+400 BHS 8/31/2021 9/1/2021

EPC-06/HW/3054 Dismantling of existing BT surface BT Scr 48+970 49+500 BHS 8/31/2021 9/1/2021

EPC-06/HW/3055 Dismantling of existing BT surface BT Scr 49+900 50+050 BHS 8/31/2021 9/1/2021

EPC-06/HW/3058 Level & FDD Checking of Subgrade Top layer SG Top 44+300 44+400 LHS 9/1/2021 9/2/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3059 Level & FDD Checking of Subgrade Top layer SG Top 46+940 47+000 LHS 9/1/2021 9/2/2021

EPC-06/HW/3060 Level & FDD Checking of Subgrade Top layer SG Top 47+970 48+030 LHS 9/1/2021 9/2/2021

EPC-06/HW/3065 Level & FDD Checking For GSB layer GSB 44+300 44+400 LHS 9/3/2021 9/4/2021

EPC-06/HW/3066 Level & FDD Checking For GSB layer GSB 46+940 47+000 LHS 9/3/2021 9/4/2021

EPC-06/HW/3067 Level & FDD Checking For GSB layer GSB 47+970 48+030 LHS 9/3/2021 9/4/2021

EPC-06/HW/3077 FDD Checking of WMM 1st layer WMM-I 44+300 44+400 LHS 9/8/2021 9/9/2021

EPC-06/HW/3078 FDD Checking of WMM 1st layer WMM-I 46+940 47+000 LHS 9/8/2021 9/9/2021

EPC-06/HW/3079 FDD Checking of WMM 1st layer WMM-I 47+970 48+030 LHS 9/8/2021 9/9/2021

EPC-06/HW/3080 FDD Checking of Subgrade Top layer on Minor Junction SG Top 45+065 LHS 9/8/2021 9/9/2021

EPC-06/HW/3083 Level & FDD Checking of WMM Top layer WMM-II 44+300 44+400 LHS 9/9/2021 9/10/2021

EPC-06/HW/3084 Level & FDD Checking of WMM Top layer WMM-II 46+940 47+000 LHS 9/9/2021 9/10/2021

EPC-06/HW/3085 Level & FDD Checking of WMM Top layer WMM-II 47+970 48+030 LHS 9/9/2021 9/10/2021

EPC-06/HW/3086 Applying primer coat Prime coat 44+300 44+400 LHS 9/9/2021 9/10/2021

EPC-06/HW/3086 Applying primer coat Prime coat 46+940 47+000 LHS 9/9/2021 9/10/2021

EPC-06/HW/3086 Applying primer coat Prime coat 47+970 48+030 LHS 9/9/2021 9/10/2021

EPC-06/HW/3089 FDD Checking For GSB layer on Minor Junction GSB 45+065 LHS 9/9/2021 9/10/2021

EPC-06/HW/3092 FDD Checking of Subgrade Top layer on Minor Junction SG Top 47+275 LHS 9/10/2021 9/11/2021

EPC-06/HW/3095 FDD Checking For GSB layer on Minor Junction GSB 47+275 LHS 9/11/2021 9/12/2021

EPC-06/HW/3098 FDD Checking of WMM Top layer on Minor Junction WMM-II 45+065 LHS 9/12/2021 9/13/2021

EPC-06/HW/3099 Applying primer coat on Minor Junction Prime coat 45+065 LHS 9/12/2021 9/13/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3102 Level & FDD Checking of Subgrade Top layer SG Top 91+230 91+300 LHS 9/13/2021 9/14/2021

EPC-06/HW/3103 Level & FDD Checking of Subgrade Top layer SG Top 93+700 93+770 LHS 9/13/2021 9/14/2021

EPC-06/HW/3104 Level & FDD Checking of Subgrade Top layer SG Top 91+230 91+300 RHS 9/13/2021 9/14/2021

EPC-06/HW/3105 Level & FDD Checking of Subgrade Top layer SG Top 93+700 93+770 RHS 9/13/2021 9/14/2021

EPC-06/HW/3106 Applying tack coat for DBM Tack coat (DBM) 44+300 46+250 LHS 9/13/2021 9/14/2021

EPC-06/HW/3107 Level checking and laying of DBM DBM 44+300 46+250 LHS 9/13/2021 9/14/2021

EPC-06/HW/3108 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 45+065 LHS 9/13/2021 9/14/2021

EPC-06/HW/3109 Laying of DBM on Minor Junction DBM 45+065 LHS 9/13/2021 9/14/2021

EPC-06/HW/3112 FDD Checking of WMM Top layer on Minor Junction WMM-II 47+275 LHS 9/14/2021 9/15/2021

EPC-06/HW/3113 Applying primer coat on Minor Junction Prime coat 47+275 LHS 9/14/2021 9/15/2021

EPC-06/HW/3116 Level & FDD Checking For GSB layer GSB 91+230 91+300 LHS 9/15/2021 9/16/2021

EPC-06/HW/3117 Level & FDD Checking For GSB layer GSB 93+700 93+770 LHS 9/15/2021 9/16/2021

EPC-06/HW/3118 Level & FDD Checking For GSB layer GSB 91+230 91+300 RHS 9/15/2021 9/16/2021

EPC-06/HW/3119 Level & FDD Checking For GSB layer GSB 93+700 93+770 RHS 9/15/2021 9/16/2021

EPC-06/HW/3120 Applying tack coat for DBM Tack coat (DBM) 46+320 47+900 LHS 9/15/2021 9/16/2021

EPC-06/HW/3121 Level checking and laying of DBM DBM 46+320 47+900 LHS 9/15/2021 9/16/2021

EPC-06/HW/3122 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 47+275 LHS 9/15/2021 9/16/2021

EPC-06/HW/3123 Laying of DBM on Minor Junction DBM 47+275 LHS 9/15/2021 9/16/2021

EPC-06/HW/3133 Level & FDD Checking of Subgrade Top layer SG Top 49+050 49+500 LHS 9/21/2021 9/22/2021

EPC-06/HW/3138 Level & FDD Checking of Subgrade Top layer SG Top 52+000 52+100 LHS 9/23/2021 9/24/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3139 Level & FDD Checking of Subgrade Top layer SG Top 58+740 58+840 LHS 9/23/2021 9/24/2021

EPC-06/HW/3140 Level & FDD Checking of Subgrade Top layer SG Top 52+000 52+100 RHS 9/23/2021 9/24/2021

EPC-06/HW/3141 Level & FDD Checking of Subgrade Top layer SG Top 58+740 58+840 RHS 9/23/2021 9/24/2021

EPC-06/HW/3142 Level & FDD Checking For GSB layer GSB 49+050 49+500 LHS 9/23/2021 9/24/2021

EPC-06/HW/3143 FDD Checking of WMM 1st layer WMM-I 91+230 91+300 LHS 9/23/2021 9/24/2021

EPC-06/HW/3144 FDD Checking of WMM 1st layer WMM-I 93+700 93+770 LHS 9/23/2021 9/24/2021

EPC-06/HW/3145 FDD Checking of WMM 1st layer WMM-I 91+230 91+300 RHS 9/23/2021 9/24/2021

EPC-06/HW/3146 FDD Checking of WMM 1st layer WMM-I 93+700 93+770 RHS 9/23/2021 9/24/2021

EPC-06/HW/3149 Level & FDD Checking of WMM Top layer WMM-II 91+230 91+300 LHS 9/24/2021 9/25/2021

EPC-06/HW/3150 Level & FDD Checking of WMM Top layer WMM-II 93+700 93+770 LHS 9/24/2021 9/25/2021

EPC-06/HW/3151 Level & FDD Checking of WMM Top layer WMM-II 91+230 91+300 RHS 9/24/2021 9/25/2021

EPC-06/HW/3152 Level & FDD Checking of WMM Top layer WMM-II 93+700 93+770 RHS 9/24/2021 9/25/2021

EPC-06/HW/3153 Applying primer coat Prime coat 91+230 91+300 LHS 9/24/2021 9/25/2021

EPC-06/HW/3153 Applying primer coat Prime coat 93+700 93+770 LHS 9/24/2021 9/25/2021

EPC-06/HW/3153 Applying primer coat Prime coat 91+230 91+300 RHS 9/24/2021 9/25/2021

EPC-06/HW/3153 Applying primer coat Prime coat 93+700 93+770 RHS 9/24/2021 9/25/2021

EPC-06/HW/3160 Level & FDD Checking For GSB layer GSB 52+000 52+100 LHS 9/26/2021 9/27/2021

EPC-06/HW/3161 Level & FDD Checking For GSB layer GSB 58+740 58+840 LHS 9/26/2021 9/27/2021

EPC-06/HW/3162 Level & FDD Checking For GSB layer GSB 52+000 52+100 RHS 9/26/2021 9/27/2021

EPC-06/HW/3163 Level & FDD Checking For GSB layer GSB 58+740 58+840 RHS 9/26/2021 9/27/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3167 FDD Checking of WMM 1st layer WMM-I 49+050 49+500 LHS 9/28/2021 9/29/2021

EPC-06/HW/3170 Level & FDD Checking of WMM Top layer WMM-II 49+050 49+500 LHS 9/29/2021 9/30/2021

EPC-06/HW/3171 Applying primer coat Prime coat 49+050 49+500 LHS 9/29/2021 9/30/2021

EPC-06/HW/3174 Applying tack coat for DBM Tack coat (DBM) 91+230 91+300 LHS 9/30/2021 10/1/2021

EPC-06/HW/3174 Applying tack coat for DBM Tack coat (DBM) 93+700 93+770 LHS 9/30/2021 10/1/2021

EPC-06/HW/3174 Applying tack coat for DBM Tack coat (DBM) 91+230 91+300 RHS 9/30/2021 10/1/2021

EPC-06/HW/3174 Applying tack coat for DBM Tack coat (DBM) 93+700 93+770 RHS 9/30/2021 10/1/2021

EPC-06/HW/3178 Level checking and laying of DBM DBM 91+230 91+300 LHS 9/30/2021 10/1/2021

EPC-06/HW/3178 Level checking and laying of DBM DBM 93+700 93+770 LHS 9/30/2021 10/1/2021

EPC-06/HW/3178 Level checking and laying of DBM DBM 91+230 91+300 RHS 9/30/2021 10/1/2021

EPC-06/HW/3178 Level checking and laying of DBM DBM 93+700 93+770 RHS 9/30/2021 10/1/2021

EPC-06/HW/3184 FDD Checking of WMM 1st layer WMM-I 52+000 52+100 LHS 10/1/2021 10/2/2021

EPC-06/HW/3185 FDD Checking of WMM 1st layer WMM-I 58+740 58+840 LHS 10/1/2021 10/2/2021

EPC-06/HW/3186 FDD Checking of WMM 1st layer WMM-I 52+000 52+100 RHS 10/1/2021 10/2/2021

EPC-06/HW/3187 FDD Checking of WMM 1st layer WMM-I 58+740 58+840 RHS 10/1/2021 10/2/2021

EPC-06/HW/3190 Level & FDD Checking of WMM Top layer WMM-II 52+000 52+100 LHS 10/2/2021 10/3/2021

EPC-06/HW/3191 Level & FDD Checking of WMM Top layer WMM-II 58+740 58+840 LHS 10/2/2021 10/3/2021

EPC-06/HW/3192 Level & FDD Checking of WMM Top layer WMM-II 52+000 52+100 RHS 10/2/2021 10/3/2021

EPC-06/HW/3193 Level & FDD Checking of WMM Top layer WMM-II 58+740 58+840 RHS 10/2/2021 10/3/2021

EPC-06/HW/3194 Applying primer coat Prime coat 52+000 52+100 LHS 10/2/2021 10/3/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3194 Applying primer coat Prime coat 58+740 58+840 LHS 10/2/2021 10/3/2021

EPC-06/HW/3194 Applying primer coat Prime coat 52+000 52+100 RHS 10/2/2021 10/3/2021

EPC-06/HW/3194 Applying primer coat Prime coat 58+740 58+840 RHS 10/2/2021 10/3/2021

EPC-06/HW/3200 Applying tack coat for DBM Tack coat (DBM) 52+000 52+100 LHS 10/3/2021 10/4/2021

EPC-06/HW/3200 Applying tack coat for DBM Tack coat (DBM) 58+740 58+840 LHS 10/3/2021 10/4/2021

EPC-06/HW/3200 Applying tack coat for DBM Tack coat (DBM) 52+000 52+100 RHS 10/3/2021 10/4/2021

EPC-06/HW/3200 Applying tack coat for DBM Tack coat (DBM) 58+740 58+840 RHS 10/3/2021 10/4/2021

EPC-06/HW/3209 Level checking and laying of DBM DBM 52+000 52+100 LHS 10/4/2021 10/5/2021

EPC-06/HW/3209 Level checking and laying of DBM DBM 58+740 58+840 LHS 10/4/2021 10/5/2021

EPC-06/HW/3209 Level checking and laying of DBM DBM 52+000 52+100 RHS 10/4/2021 10/5/2021

EPC-06/HW/3209 Level checking and laying of DBM DBM 58+740 58+840 RHS 10/4/2021 10/5/2021

EPC-06/HW/3210 Applying tack coat for DBM Tack coat (DBM) 47+900 48+970 LHS 10/4/2021 10/5/2021

EPC-06/HW/3210 Applying tack coat for DBM Tack coat (DBM) 49+050 49+500 LHS 10/4/2021 10/5/2021

EPC-06/HW/3212 Level checking and laying of DBM DBM 47+900 48+970 LHS 10/4/2021 10/5/2021

EPC-06/HW/3212 Level checking and laying of DBM DBM 49+050 49+500 LHS 10/4/2021 10/5/2021

EPC-06/HW/3223 Level & FDD Checking For GSB layer GSB 68+780 69+230 RHS 10/9/2021 10/10/2021

EPC-06/HW/3227 Level & FDD Checking of Subgrade Top layer SG Top 44+300 45+200 RHS 10/11/2021 10/12/2021

EPC-06/HW/3230 Level & FDD Checking of Subgrade Top layer SG Top 45+200 46+250 RHS 10/12/2021 10/13/2021

EPC-06/HW/3233 Level & FDD Checking of Subgrade Top layer SG Top 46+320 47+200 RHS 10/13/2021 10/14/2021

EPC-06/HW/3236 Level & FDD Checking of Subgrade Top layer SG Top 47+200 48+100 RHS 10/14/2021 10/15/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3237 Level & FDD Checking For GSB layer GSB 44+300 44+900 RHS 10/14/2021 10/15/2021

EPC-06/HW/3240 Level & FDD Checking of Subgrade Top layer SG Top 48+100 48+970 RHS 10/15/2021 10/16/2021

EPC-06/HW/3241 Level & FDD Checking For GSB layer GSB 44+900 45+600 RHS 10/15/2021 10/16/2021

EPC-06/HW/3242 FDD Checking of WMM 1st layer WMM-I 68+780 69+230 RHS 10/15/2021 10/16/2021

EPC-06/HW/3245 Level & FDD Checking of Subgrade Top layer SG Top 49+050 49+500 RHS 10/16/2021 10/17/2021

EPC-06/HW/3246 Level & FDD Checking For GSB layer GSB 45+600 46+250 RHS 10/16/2021 10/17/2021

EPC-06/HW/3247 Level & FDD Checking of WMM Top layer WMM-II 68+780 69+230 RHS 10/16/2021 10/17/2021

EPC-06/HW/3248 Applying primer coat Prime coat 68+780 69+230 RHS 10/16/2021 10/17/2021

EPC-06/HW/3251 Level & FDD Checking For GSB layer GSB 46+320 47+150 RHS 10/17/2021 10/18/2021

EPC-06/HW/3254 Level & FDD Checking For GSB layer GSB 47+150 47+800 RHS 10/18/2021 10/19/2021

EPC-06/HW/3257 Level & FDD Checking For GSB layer GSB 47+800 48+350 RHS 10/19/2021 10/20/2021

EPC-06/HW/3260 Level & FDD Checking For GSB layer GSB 48+350 48+970 RHS 10/20/2021 10/21/2021

EPC-06/HW/3261 FDD Checking of WMM 1st layer WMM-I 44+300 45+000 RHS 10/20/2021 10/21/2021

EPC-06/HW/3264 Level & FDD Checking For GSB layer GSB 49+050 49+500 RHS 10/21/2021 10/22/2021

EPC-06/HW/3265 FDD Checking of WMM 1st layer WMM-I 45+000 45+700 RHS 10/21/2021 10/22/2021

EPC-06/HW/3266 Level & FDD Checking of WMM Top layer WMM-II 44+300 45+000 RHS 10/21/2021 10/22/2021

EPC-06/HW/3267 Applying primer coat Prime coat 44+300 45+000 RHS 10/21/2021 10/22/2021

EPC-06/HW/3270 FDD Checking of WMM 1st layer WMM-I 45+700 46+250 RHS 10/22/2021 10/23/2021

EPC-06/HW/3271 Level & FDD Checking of WMM Top layer WMM-II 45+000 45+700 RHS 10/22/2021 10/23/2021

EPC-06/HW/3272 Applying primer coat Prime coat 45+000 45+700 RHS 10/22/2021 10/23/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3273 Applying tack coat for DBM Tack coat (DBM) 68+780 69+230 RHS 10/22/2021 10/23/2021

EPC-06/HW/3274 Level checking and laying of DBM DBM 68+780 69+230 RHS 10/22/2021 10/23/2021

EPC-06/HW/3277 FDD Checking of WMM 1st layer WMM-I 46+320 47+100 RHS 10/23/2021 10/24/2021

EPC-06/HW/3278 Level & FDD Checking of WMM Top layer WMM-II 45+700 46+250 RHS 10/23/2021 10/24/2021

EPC-06/HW/3279 Applying primer coat Prime coat 45+700 46+250 RHS 10/23/2021 10/24/2021

EPC-06/HW/3282 FDD Checking of WMM 1st layer WMM-I 47+100 48+000 RHS 10/24/2021 10/25/2021

EPC-06/HW/3283 Level & FDD Checking of WMM Top layer WMM-II 46+320 47+100 RHS 10/24/2021 10/25/2021

EPC-06/HW/3284 Applying primer coat Prime coat 46+320 47+100 RHS 10/24/2021 10/25/2021

EPC-06/HW/3287 Level & FDD Checking of WMM Top layer WMM-II 47+100 48+000 RHS 10/25/2021 10/26/2021

EPC-06/HW/3288 Applying primer coat Prime coat 47+100 48+000 RHS 10/25/2021 10/26/2021

EPC-06/HW/3291 FDD Checking of WMM 1st layer WMM-I 48+000 48+550 RHS 10/26/2021 10/27/2021

EPC-06/HW/3292 Applying tack coat for DBM Tack coat (DBM) 44+300 46+250 RHS 10/26/2021 10/27/2021

EPC-06/HW/3293 Level checking and laying of DBM DBM 44+300 46+250 RHS 10/26/2021 10/27/2021

EPC-06/HW/3296 FDD Checking of WMM 1st layer WMM-I 48+550 48+970 RHS 10/27/2021 10/28/2021

EPC-06/HW/3297 Level & FDD Checking of WMM Top layer WMM-II 48+000 48+550 RHS 10/27/2021 10/28/2021

EPC-06/HW/3298 Applying primer coat Prime coat 48+000 48+550 RHS 10/27/2021 10/28/2021

EPC-06/HW/3301 Level & FDD Checking of Subgrade Top layer SG Top (OL) 54+600 55+150 RHS 10/28/2021 10/29/2021

EPC-06/HW/3302 FDD Checking of WMM 1st layer WMM-I 49+050 49+500 RHS 10/28/2021 10/29/2021

EPC-06/HW/3303 Level & FDD Checking of WMM Top layer WMM-II 48+550 48+970 RHS 10/28/2021 10/29/2021

EPC-06/HW/3304 Applying primer coat Prime coat 48+550 48+970 RHS 10/28/2021 10/29/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3307 Level & FDD Checking of Subgrade Top layer SG Top (OL) 55+150 55+620 RHS 10/29/2021 10/30/2021

EPC-06/HW/3308 Level & FDD Checking of WMM Top layer WMM-II 49+050 49+500 RHS 10/29/2021 10/30/2021

EPC-06/HW/3309 Applying primer coat Prime coat 49+050 49+500 RHS 10/29/2021 10/30/2021

EPC-06/HW/3310 Applying tack coat for DBM Tack coat (DBM) 46+320 48+000 RHS 10/29/2021 10/30/2021

EPC-06/HW/3311 Level checking and laying of DBM DBM 46+320 48+000 RHS 10/29/2021 10/30/2021

EPC-06/HW/3314 Level & FDD Checking of Subgrade Top layer SG Top (OL) 53+000 53+850 RHS 10/30/2021 10/31/2021

EPC-06/HW/3315 Level & FDD Checking For GSB layer GSB (OL) 54+600 55+150 RHS 10/30/2021 10/31/2021

EPC-06/HW/3318 Level & FDD Checking of Subgrade Top layer SG Top (OL) 53+850 54+600 RHS 10/31/2021 11/1/2021

EPC-06/HW/3319 Level & FDD Checking For GSB layer GSB (OL) 55+150 55+620 RHS 10/31/2021 11/1/2021

EPC-06/HW/3320 Applying tack coat for DBM Tack coat (DBM) 48+000 48+970 RHS 10/31/2021 11/1/2021

EPC-06/HW/3320 Applying tack coat for DBM Tack coat (DBM) 49+050 49+500 RHS 10/31/2021 11/1/2021

EPC-06/HW/3322 Level checking and laying of DBM DBM 48+000 48+970 RHS 10/31/2021 11/1/2021

EPC-06/HW/3322 Level checking and laying of DBM DBM 49+050 49+500 RHS 10/31/2021 11/1/2021

EPC-06/HW/3326 Level & FDD Checking For GSB layer GSB (OL) 53+000 53+850 RHS 11/1/2021 11/2/2021

EPC-06/HW/3329 Level & FDD Checking For GSB layer GSB (OL) 53+850 54+600 RHS 11/2/2021 11/3/2021

EPC-06/HW/3334 FDD Checking of WMM 1st layer WMM-I (OL) 54+600 55+150 RHS 11/5/2021 11/6/2021

EPC-06/HW/3337 FDD Checking of WMM 1st layer WMM-I (OL) 55+150 55+620 RHS 11/6/2021 11/7/2021

EPC-06/HW/3338 Level & FDD Checking of WMM Top layer WMM-II (OL) 54+600 55+150 RHS 11/6/2021 11/7/2021

EPC-06/HW/3339 Applying primer coat Prime coat 54+600 55+150 RHS 11/6/2021 11/7/2021

EPC-06/HW/3342 FDD Checking of WMM 1st layer WMM-I (OL) 53+000 53+850 RHS 11/7/2021 11/8/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3343 Level & FDD Checking of WMM Top layer WMM-II (OL) 55+150 55+620 RHS 11/7/2021 11/8/2021

EPC-06/HW/3344 Applying primer coat Prime coat 55+150 55+620 RHS 11/7/2021 11/8/2021

EPC-06/HW/3347 FDD Checking of WMM 1st layer WMM-I (OL) 53+850 54+600 RHS 11/8/2021 11/9/2021

EPC-06/HW/3348 Level & FDD Checking of WMM Top layer WMM-II (OL) 53+000 53+850 RHS 11/8/2021 11/9/2021

EPC-06/HW/3349 Applying primer coat Prime coat 53+000 53+850 RHS 11/8/2021 11/9/2021

EPC-06/HW/3352 Level & FDD Checking of WMM Top layer WMM-II (OL) 53+850 54+600 RHS 11/9/2021 11/10/2021

EPC-06/HW/3353 Applying primer coat Prime coat 53+850 54+600 RHS 11/9/2021 11/10/2021

EPC-06/HW/3358 Level & FDD Checking of Subgrade Top layer SG Top (OL) 54+600 55+100 LHS 11/11/2021 11/12/2021

EPC-06/HW/3361 Level & FDD Checking of Subgrade Top layer SG Top (OL) 55+100 55+620 LHS 11/12/2021 11/13/2021

EPC-06/HW/3362 FDD Checking of WMM 1st layer WMM-I (OL) 61+000 61+110 LHS 11/12/2021 11/13/2021

EPC-06/HW/3363 FDD Checking of WMM 1st layer WMM-I (OL) 62+130 62+900 LHS 11/12/2021 11/13/2021

EPC-06/HW/3366 Level & FDD Checking of Subgrade Top layer SG Top (OL) 53+000 53+800 LHS 11/13/2021 11/14/2021

EPC-06/HW/3367 Level & FDD Checking For GSB layer GSB (OL) 54+600 55+100 LHS 11/13/2021 11/14/2021

EPC-06/HW/3368 FDD Checking of WMM 1st layer WMM-I (OL) 62+900 63+550 LHS 11/13/2021 11/14/2021

EPC-06/HW/3369 FDD Checking of WMM 1st layer WMM-I (OL) 63+950 64+000 LHS 11/13/2021 11/14/2021

EPC-06/HW/3370 Level & FDD Checking of WMM Top layer WMM-II (OL) 61+000 61+110 LHS 11/13/2021 11/14/2021

EPC-06/HW/3371 Level & FDD Checking of WMM Top layer WMM-II (OL) 62+130 62+900 LHS 11/13/2021 11/14/2021

EPC-06/HW/3372 Applying primer coat Prime coat 61+000 61+110 LHS 11/13/2021 11/14/2021

EPC-06/HW/3372 Applying primer coat Prime coat 62+130 62+900 LHS 11/13/2021 11/14/2021

EPC-06/HW/3376 Level & FDD Checking of Subgrade Top layer SG Top (OL) 53+800 54+600 LHS 11/14/2021 11/15/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3377 Level & FDD Checking For GSB layer GSB (OL) 55+100 55+620 LHS 11/14/2021 11/15/2021

EPC-06/HW/3378 Level & FDD Checking of WMM Top layer WMM-II (OL) 62+900 63+550 LHS 11/14/2021 11/15/2021

EPC-06/HW/3379 Level & FDD Checking of WMM Top layer WMM-II (OL) 63+950 64+000 LHS 11/14/2021 11/15/2021

EPC-06/HW/3380 Applying primer coat Prime coat 62+900 63+550 LHS 11/14/2021 11/15/2021

EPC-06/HW/3380 Applying primer coat Prime coat 63+950 64+000 LHS 11/14/2021 11/15/2021

EPC-06/HW/3384 Level & FDD Checking For GSB layer GSB (OL) 53+000 53+800 LHS 11/15/2021 11/16/2021

EPC-06/HW/3387 Level & FDD Checking For GSB layer GSB (OL) 53+800 54+600 LHS 11/16/2021 11/17/2021

EPC-06/HW/3388 Level and FDD checking of DLC layer DLC 68+080 68+300 RHS 11/16/2021 11/17/2021

EPC-06/HW/3393 Dismantling of existing BT surface BT Scr 61+110 61+550 BHS 11/19/2021 11/20/2021

EPC-06/HW/3394 Dismantling of existing BT surface BT Scr 63+550 63+950 BHS 11/19/2021 11/20/2021

EPC-06/HW/3395 FDD Checking of WMM 1st layer WMM-I (OL) 54+600 55+100 LHS 11/19/2021 11/20/2021

EPC-06/HW/3398 FDD Checking of WMM 1st layer WMM-I (OL) 55+100 55+620 LHS 11/20/2021 11/21/2021

EPC-06/HW/3399 Level & FDD Checking of WMM Top layer WMM-II (OL) 54+600 55+100 LHS 11/20/2021 11/21/2021

EPC-06/HW/3400 Applying primer coat Prime coat 54+600 55+100 LHS 11/20/2021 11/21/2021

EPC-06/HW/3401 FDD Checking of Subgrade Top layer on Minor Junction SG Top 53+845 LHS 11/20/2021 11/21/2021

EPC-06/HW/3404 FDD Checking of WMM 1st layer WMM-I (OL) 53+000 53+800 LHS 11/21/2021 11/22/2021

EPC-06/HW/3405 Level & FDD Checking of WMM Top layer WMM-II (OL) 55+100 55+620 LHS 11/21/2021 11/22/2021

EPC-06/HW/3406 Applying primer coat Prime coat 55+100 55+620 LHS 11/21/2021 11/22/2021

EPC-06/HW/3407 FDD Checking For GSB layer on Minor Junction GSB 53+845 LHS 11/21/2021 11/22/2021

EPC-06/HW/3410 Applying tack coat for BM Tack coat (BM) 54+600 55+620 LHS 11/22/2021 11/23/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3411 Level checking and laying of BM BM 54+600 55+620 LHS 11/22/2021 11/23/2021

EPC-06/HW/3412 FDD Checking of WMM 1st layer WMM-I (OL) 53+800 54+600 LHS 11/22/2021 11/23/2021

EPC-06/HW/3413 Level & FDD Checking of WMM Top layer WMM-II (OL) 53+000 53+800 LHS 11/22/2021 11/23/2021

EPC-06/HW/3414 Applying primer coat Prime coat 53+000 53+800 LHS 11/22/2021 11/23/2021

EPC-06/HW/3417 Level & FDD Checking of Subgrade Top layer SG Top 61+110 61+550 LHS 11/23/2021 11/24/2021

EPC-06/HW/3418 Level & FDD Checking of Subgrade Top layer SG Top (OL) 02+700 03+550 LHS 11/23/2021 11/24/2021

EPC-06/HW/3419 Applying tack coat for BM Tack coat (BM) 53+000 54+600 LHS 11/23/2021 11/24/2021

EPC-06/HW/3420 Level checking and laying of BM BM 53+000 54+600 LHS 11/23/2021 11/24/2021

EPC-06/HW/3421 Level & FDD Checking of WMM Top layer WMM-II (OL) 53+800 54+600 LHS 11/23/2021 11/24/2021

EPC-06/HW/3422 Applying primer coat Prime coat 53+800 54+600 LHS 11/23/2021 11/24/2021

EPC-06/HW/3425 Level & FDD Checking of Subgrade Top layer SG Top 63+550 63+950 LHS 11/24/2021 11/25/2021

EPC-06/HW/3426 Level & FDD Checking of Subgrade Top layer SG Top (OL) 03+550 04+300 LHS 11/24/2021 11/25/2021

EPC-06/HW/3427 Applying tack coat for DBM Tack coat (DBM) (OL) 54+600 55+620 LHS 11/24/2021 11/25/2021

EPC-06/HW/3428 Level checking and laying of DBM DBM (OL) 54+600 55+620 LHS 11/24/2021 11/25/2021

EPC-06/HW/3429 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+080 68+300 RHS 11/24/2021 11/25/2021

EPC-06/HW/3430 FDD Checking of WMM Top layer on Minor Junction WMM-II 53+845 LHS 11/24/2021 11/25/2021

EPC-06/HW/3431 Applying primer coat on Minor Junction Prime coat 53+845 LHS 11/24/2021 11/25/2021

EPC-06/HW/3434 Level & FDD Checking of Subgrade Top layer SG Top (OL) 61+000 61+110 RHS 11/25/2021 11/26/2021

EPC-06/HW/3435 Level & FDD Checking of Subgrade Top layer SG Top (OL) 62+130 62+900 RHS 11/25/2021 11/26/2021

EPC-06/HW/3436 Level & FDD Checking of Subgrade Top layer SG Top (OL) 04+300 05+000 LHS 11/25/2021 11/26/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3437 Level & FDD Checking For GSB layer GSB 61+110 61+550 LHS 11/25/2021 11/26/2021

EPC-06/HW/3438 Level & FDD Checking For GSB layer GSB (OL) 02+700 03+550 LHS 11/25/2021 11/26/2021

EPC-06/HW/3439 Applying tack coat for DBM Tack coat (DBM) (OL) 53+000 54+600 LHS 11/25/2021 11/26/2021

EPC-06/HW/3440 Level checking and laying of DBM DBM (OL) 53+000 54+600 LHS 11/25/2021 11/26/2021

EPC-06/HW/3441 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 53+845 LHS 11/25/2021 11/26/2021

EPC-06/HW/3442 Laying of DBM on Minor Junction DBM 53+845 LHS 11/25/2021 11/26/2021

EPC-06/HW/3445 Level & FDD Checking of Subgrade Top layer SG Top (OL) 62+900 63+550 RHS 11/26/2021 11/27/2021

EPC-06/HW/3446 Level & FDD Checking of Subgrade Top layer SG Top (OL) 63+950 64+000 RHS 11/26/2021 11/27/2021

EPC-06/HW/3447 Level & FDD Checking of Subgrade Top layer SG Top (OL) 05+000 05+750 LHS 11/26/2021 11/27/2021

EPC-06/HW/3448 Level & FDD Checking For GSB layer GSB 63+550 63+950 LHS 11/26/2021 11/27/2021

EPC-06/HW/3449 Level & FDD Checking For GSB layer GSB (OL) 03+550 04+200 LHS 11/26/2021 11/27/2021

EPC-06/HW/3450 Applying tack coat for BM Tack coat (BM) 54+600 55+620 RHS 11/26/2021 11/27/2021

EPC-06/HW/3451 Level checking and laying of BM BM 54+600 55+620 RHS 11/26/2021 11/27/2021

EPC-06/HW/3452 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+080 68+300 RHS 11/26/2021 11/27/2021

EPC-06/HW/3455 Level & FDD Checking of Subgrade Top layer SG Top (OL) 05+750 06+500 LHS 11/27/2021 11/28/2021

EPC-06/HW/3456 Level & FDD Checking For GSB layer GSB (OL) 61+000 61+110 RHS 11/27/2021 11/28/2021

EPC-06/HW/3457 Level & FDD Checking For GSB layer GSB (OL) 62+130 62+850 RHS 11/27/2021 11/28/2021

EPC-06/HW/3458 Level & FDD Checking For GSB layer GSB (OL) 04+200 04+850 LHS 11/27/2021 11/28/2021

EPC-06/HW/3459 Applying tack coat for BM Tack coat (BM) 53+000 54+600 RHS 11/27/2021 11/28/2021

EPC-06/HW/3460 Level checking and laying of BM BM 53+000 54+600 RHS 11/27/2021 11/28/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3463 Level & FDD Checking For GSB layer GSB (OL) 62+850 63+550 RHS 11/28/2021 11/29/2021

EPC-06/HW/3464 Level & FDD Checking For GSB layer GSB (OL) 63+950 64+000 RHS 11/28/2021 11/29/2021

EPC-06/HW/3465 Level & FDD Checking For GSB layer GSB (OL) 04+850 05+700 LHS 11/28/2021 11/29/2021

EPC-06/HW/3466 Applying tack coat for DBM Tack coat (DBM) (OL) 54+600 55+620 RHS 11/28/2021 11/29/2021

EPC-06/HW/3467 Level checking and laying of DBM DBM (OL) 54+600 55+620 RHS 11/28/2021 11/29/2021

EPC-06/HW/3470 Level & FDD Checking For GSB layer GSB (OL) 05+700 06+500 LHS 11/29/2021 11/30/2021

EPC-06/HW/3471 Applying tack coat for DBM Tack coat (DBM) (OL) 53+000 54+600 RHS 11/29/2021 11/30/2021

EPC-06/HW/3472 Level checking and laying of DBM DBM (OL) 53+000 54+600 RHS 11/29/2021 11/30/2021

EPC-06/HW/3476 FDD Checking of WMM 1st layer WMM-I (OL) 02+700 03+500 LHS 12/1/2021 12/2/2021

EPC-06/HW/3477 FDD Checking of Subgrade Top layer on Minor Junction SG Top 62+545 RHS 12/1/2021 12/2/2021

EPC-06/HW/3478 Level & FDD Checking of Subgrade Top layer SG Top 48+970 49+050 BHS 12/1/2021 12/2/2021

EPC-06/HW/3479 Level & FDD Checking of Subgrade Top layer SG Top 49+900 50+050 BHS 12/1/2021 12/2/2021

EPC-06/HW/3480 FDD Checking of WMM 1st layer WMM-I 61+110 61+550 LHS 12/2/2021 12/3/2021

EPC-06/HW/3481 FDD Checking of WMM 1st layer WMM-I (OL) 61+000 61+110 RHS 12/2/2021 12/3/2021

EPC-06/HW/3482 FDD Checking of WMM 1st layer WMM-I (OL) 62+130 62+800 RHS 12/2/2021 12/3/2021

EPC-06/HW/3483 FDD Checking of WMM 1st layer WMM-I (OL) 03+500 04+200 LHS 12/2/2021 12/3/2021

EPC-06/HW/3484 Level & FDD Checking of WMM Top layer WMM-II (OL) 02+700 03+500 LHS 12/2/2021 12/3/2021

EPC-06/HW/3485 Applying primer coat Prime coat 02+700 03+500 LHS 12/2/2021 12/3/2021

EPC-06/HW/3486 FDD Checking For GSB layer on Minor Junction GSB 62+545 RHS 12/2/2021 12/3/2021

EPC-06/HW/3487 Level & FDD Checking For GSB layer GSB 48+970 49+050 BHS 12/2/2021 12/3/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3488 Level & FDD Checking For GSB layer GSB 49+900 50+050 BHS 12/2/2021 12/3/2021

EPC-06/HW/3489 Level & FDD Checking of Subgrade Top layer SG Top 61+110 61+550 RHS 12/3/2021 12/4/2021

EPC-06/HW/3490 FDD Checking of WMM 1st layer WMM-I 63+550 63+950 LHS 12/3/2021 12/4/2021

EPC-06/HW/3491 FDD Checking of WMM 1st layer WMM-I (OL) 62+800 63+550 RHS 12/3/2021 12/4/2021

EPC-06/HW/3492 FDD Checking of WMM 1st layer WMM-I (OL) 63+950 64+000 RHS 12/3/2021 12/4/2021

EPC-06/HW/3493 FDD Checking of WMM 1st layer WMM-I (OL) 04+200 04+800 LHS 12/3/2021 12/4/2021

EPC-06/HW/3494 Level & FDD Checking of WMM Top layer WMM-II 61+110 61+550 LHS 12/3/2021 12/4/2021

EPC-06/HW/3495 Level & FDD Checking of WMM Top layer WMM-II (OL) 61+000 61+110 RHS 12/3/2021 12/4/2021

EPC-06/HW/3496 Level & FDD Checking of WMM Top layer WMM-II (OL) 62+130 62+800 RHS 12/3/2021 12/4/2021

EPC-06/HW/3497 Level & FDD Checking of WMM Top layer WMM-II (OL) 03+500 04+200 LHS 12/3/2021 12/4/2021

EPC-06/HW/3498 Applying primer coat Prime coat 61+110 61+550 LHS 12/3/2021 12/4/2021

EPC-06/HW/3498 Applying primer coat Prime coat 61+000 61+110 RHS 12/3/2021 12/4/2021

EPC-06/HW/3498 Applying primer coat Prime coat 62+130 62+800 RHS 12/3/2021 12/4/2021

EPC-06/HW/3498 Applying primer coat Prime coat 03+500 04+200 LHS 12/3/2021 12/4/2021

EPC-06/HW/3499 FDD Checking of WMM 1st layer WMM-I 48+970 49+050 BHS 12/3/2021 12/4/2021

EPC-06/HW/3500 FDD Checking of WMM 1st layer WMM-I 49+900 50+050 BHS 12/3/2021 12/4/2021

EPC-06/HW/3504 Level & FDD Checking of Subgrade Top layer SG Top 63+550 63+950 RHS 12/4/2021 12/5/2021

EPC-06/HW/3505 Applying tack coat for BM Tack coat (BM) 61+000 61+110 RHS 12/4/2021 12/5/2021

EPC-06/HW/3505 Applying tack coat for BM Tack coat (BM) 62+130 63+550 RHS 12/4/2021 12/5/2021

EPC-06/HW/3505 Applying tack coat for BM Tack coat (BM) 63+950 64+000 RHS 12/4/2021 12/5/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3508 Level checking and laying of BM BM 61+000 61+110 RHS 12/4/2021 12/5/2021

EPC-06/HW/3508 Level checking and laying of BM BM 62+130 63+550 RHS 12/4/2021 12/5/2021

EPC-06/HW/3508 Level checking and laying of BM BM 63+950 64+000 RHS 12/4/2021 12/5/2021

EPC-06/HW/3511 FDD Checking of WMM 1st layer WMM-I (OL) 04+800 05+600 LHS 12/4/2021 12/5/2021

EPC-06/HW/3512 Level & FDD Checking of WMM Top layer WMM-II 63+550 63+950 LHS 12/4/2021 12/5/2021

EPC-06/HW/3513 Level & FDD Checking of WMM Top layer WMM-II (OL) 62+800 63+550 RHS 12/4/2021 12/5/2021

EPC-06/HW/3514 Level & FDD Checking of WMM Top layer WMM-II (OL) 63+950 64+000 RHS 12/4/2021 12/5/2021

EPC-06/HW/3515 Level & FDD Checking of WMM Top layer WMM-II (OL) 04+200 04+800 LHS 12/4/2021 12/5/2021

EPC-06/HW/3516 Applying primer coat Prime coat 63+550 63+950 LHS 12/4/2021 12/5/2021

EPC-06/HW/3516 Applying primer coat Prime coat 62+800 63+550 RHS 12/4/2021 12/5/2021

EPC-06/HW/3516 Applying primer coat Prime coat 63+950 64+000 RHS 12/4/2021 12/5/2021

EPC-06/HW/3516 Applying primer coat Prime coat 04+200 04+800 LHS 12/4/2021 12/5/2021

EPC-06/HW/3517 Level & FDD Checking of WMM Top layer WMM-II 48+970 49+050 BHS 12/4/2021 12/5/2021

EPC-06/HW/3518 Level & FDD Checking of WMM Top layer WMM-II 49+900 50+050 BHS 12/4/2021 12/5/2021

EPC-06/HW/3522 Level & FDD Checking For GSB layer GSB 61+110 61+550 RHS 12/5/2021 12/6/2021

EPC-06/HW/3523 FDD Checking of WMM 1st layer WMM-I (OL) 05+600 06+500 LHS 12/5/2021 12/6/2021

EPC-06/HW/3524 Level & FDD Checking of WMM Top layer WMM-II (OL) 04+800 05+600 LHS 12/5/2021 12/6/2021

EPC-06/HW/3525 Applying primer coat Prime coat 04+800 05+600 LHS 12/5/2021 12/6/2021

EPC-06/HW/3526 FDD Checking of WMM Top layer on Minor Junction WMM-II 62+545 RHS 12/5/2021 12/6/2021

EPC-06/HW/3527 Applying primer coat on Minor Junction Prime coat 62+545 RHS 12/5/2021 12/6/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3528 Applying primer coat Prime coat 48+970 49+050 BHS 12/5/2021 12/6/2021

EPC-06/HW/3529 Applying primer coat Prime coat 49+900 50+050 BHS 12/5/2021 12/6/2021

EPC-06/HW/3530 Level & FDD Checking For GSB layer GSB 63+550 63+950 RHS 12/6/2021 12/7/2021

EPC-06/HW/3531 Level & FDD Checking of WMM Top layer WMM-II (OL) 05+600 06+500 LHS 12/6/2021 12/7/2021

EPC-06/HW/3532 Applying primer coat Prime coat 05+600 06+500 LHS 12/6/2021 12/7/2021

EPC-06/HW/3533 Applying tack coat for DBM Tack coat (DBM) 61+110 61+550 RHS 12/6/2021 12/7/2021

EPC-06/HW/3533 Applying tack coat for DBM Tack coat (DBM) 63+550 63+950 RHS 12/6/2021 12/7/2021

EPC-06/HW/3535 Applying tack coat for DBM Tack coat (DBM) (OL) 61+000 61+110 RHS 12/6/2021 12/7/2021

EPC-06/HW/3535 Applying tack coat for DBM Tack coat (DBM) (OL) 62+130 63+550 RHS 12/6/2021 12/7/2021

EPC-06/HW/3535 Applying tack coat for DBM Tack coat (DBM) (OL) 63+950 64+000 RHS 12/6/2021 12/7/2021

EPC-06/HW/3538 Level checking and laying of DBM DBM 61+110 61+550 RHS 12/6/2021 12/7/2021

EPC-06/HW/3538 Level checking and laying of DBM DBM 63+550 63+950 RHS 12/6/2021 12/7/2021

EPC-06/HW/3540 Level checking and laying of DBM DBM (OL) 61+000 61+110 RHS 12/6/2021 12/7/2021

EPC-06/HW/3540 Level checking and laying of DBM DBM (OL) 62+130 63+550 RHS 12/6/2021 12/7/2021

EPC-06/HW/3540 Level checking and laying of DBM DBM (OL) 63+950 64+000 RHS 12/6/2021 12/7/2021

EPC-06/HW/3543 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 62+545 RHS 12/6/2021 12/7/2021

EPC-06/HW/3544 Laying of DBM on Minor Junction DBM 62+545 RHS 12/6/2021 12/7/2021

EPC-06/HW/3545 Applying tack coat for DBM Tack coat (DBM) 48+970 49+050 BHS 12/6/2021 12/7/2021

EPC-06/HW/3545 Applying tack coat for DBM Tack coat (DBM) 49+900 50+050 BHS 12/6/2021 12/7/2021

EPC-06/HW/3546 Level checking and laying of DBM DBM 48+970 49+050 BHS 12/6/2021 12/7/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3546 Level checking and laying of DBM DBM 49+900 50+050 BHS 12/6/2021 12/7/2021

EPC-06/HW/3547 Level & FDD Checking of Subgrade Top layer SG Top (OL) 61+000 61+110 LHS 12/7/2021 12/8/2021

EPC-06/HW/3548 Level & FDD Checking of Subgrade Top layer SG Top (OL) 62+130 62+800 LHS 12/7/2021 12/8/2021

EPC-06/HW/3549 Level & FDD Checking of Subgrade Top layer SG Top (OL) 02+700 03+450 RHS 12/7/2021 12/8/2021

EPC-06/HW/3552 Level & FDD Checking of Subgrade Top layer SG Top (OL) 62+800 63+550 LHS 12/8/2021 12/9/2021

EPC-06/HW/3553 Level & FDD Checking of Subgrade Top layer SG Top (OL) 63+950 64+000 LHS 12/8/2021 12/9/2021

EPC-06/HW/3554 Level & FDD Checking of Subgrade Top layer SG Top (OL) 03+450 04+200 RHS 12/8/2021 12/9/2021

EPC-06/HW/3557 Level & FDD Checking of Subgrade Top layer SG Top (OL) 04+200 04+800 RHS 12/9/2021 12/10/2021

EPC-06/HW/3558 Level & FDD Checking For GSB layer GSB (OL) 61+000 61+110 LHS 12/9/2021 12/10/2021

EPC-06/HW/3559 Level & FDD Checking For GSB layer GSB (OL) 62+130 62+800 LHS 12/9/2021 12/10/2021

EPC-06/HW/3560 Level & FDD Checking For GSB layer GSB (OL) 02+700 03+450 RHS 12/9/2021 12/10/2021

EPC-06/HW/3563 Level & FDD Checking of Subgrade Top layer SG Top (OL) 04+800 05+700 RHS 12/10/2021 12/11/2021

EPC-06/HW/3564 Level & FDD Checking For GSB layer GSB (OL) 62+800 63+550 LHS 12/10/2021 12/11/2021

EPC-06/HW/3565 Level & FDD Checking For GSB layer GSB (OL) 63+950 64+000 LHS 12/10/2021 12/11/2021

EPC-06/HW/3566 Level & FDD Checking For GSB layer GSB (OL) 03+450 04+200 RHS 12/10/2021 12/11/2021

EPC-06/HW/3569 Level & FDD Checking of Subgrade Top layer SG Top (OL) 05+700 06+500 RHS 12/11/2021 12/12/2021

EPC-06/HW/3570 Level & FDD Checking For GSB layer GSB (OL) 04+200 04+800 RHS 12/11/2021 12/12/2021

EPC-06/HW/3573 Level & FDD Checking of Subgrade Top layer SG Top (OL) 00+000 00+950 RHS 12/12/2021 12/13/2021

EPC-06/HW/3574 Level & FDD Checking For GSB layer GSB (OL) 04+800 05+600 RHS 12/12/2021 12/13/2021

EPC-06/HW/3575 FDD Checking of WMM 1st layer WMM-I 61+110 61+550 RHS 12/12/2021 12/13/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3578 Level & FDD Checking of Subgrade Top layer SG Top (OL) 00+950 01+950 RHS 12/13/2021 12/14/2021

EPC-06/HW/3579 Level & FDD Checking For GSB layer GSB (OL) 05+600 06+500 RHS 12/13/2021 12/14/2021

EPC-06/HW/3580 FDD Checking of WMM 1st layer WMM-I 63+550 63+950 RHS 12/13/2021 12/14/2021

EPC-06/HW/3581 Level & FDD Checking of WMM Top layer WMM-II 61+110 61+550 RHS 12/13/2021 12/14/2021

EPC-06/HW/3582 Applying primer coat Prime coat 61+110 61+550 RHS 12/13/2021 12/14/2021

EPC-06/HW/3585 Level & FDD Checking For GSB layer GSB (OL) 00+000 01+000 RHS 12/14/2021 12/15/2021

EPC-06/HW/3586 Applying tack coat for BM Tack coat (BM) 61+000 61+110 LHS 12/14/2021 12/15/2021

EPC-06/HW/3586 Applying tack coat for BM Tack coat (BM) 02+700 06+500 LHS 12/14/2021 12/15/2021

EPC-06/HW/3587 Level checking and laying of BM BM 61+000 61+110 LHS 12/14/2021 12/15/2021

EPC-06/HW/3587 Level checking and laying of BM BM 02+700 06+500 LHS 12/14/2021 12/15/2021

EPC-06/HW/3588 Level & FDD Checking of WMM Top layer WMM-II 63+550 63+950 RHS 12/14/2021 12/15/2021

EPC-06/HW/3589 Applying primer coat Prime coat 63+550 63+950 RHS 12/14/2021 12/15/2021

EPC-06/HW/3592 Level & FDD Checking For GSB layer GSB (OL) 01+000 01+950 RHS 12/15/2021 12/16/2021

EPC-06/HW/3593 Applying tack coat for BM Tack coat (BM) 62+130 63+550 LHS 12/15/2021 12/16/2021

EPC-06/HW/3593 Applying tack coat for BM Tack coat (BM) 63+950 64+000 LHS 12/15/2021 12/16/2021

EPC-06/HW/3595 Level checking and laying of BM BM 62+130 63+550 LHS 12/15/2021 12/16/2021

EPC-06/HW/3595 Level checking and laying of BM BM 63+950 64+000 LHS 12/15/2021 12/16/2021

EPC-06/HW/3597 FDD Checking of WMM 1st layer WMM-I (OL) 02+700 03+400 RHS 12/15/2021 12/16/2021

EPC-06/HW/3599 FDD Checking of WMM 1st layer WMM-I (OL) 00+000 00+900 RHS 12/16/2021 12/17/2021

EPC-06/HW/3600 FDD Checking of WMM 1st layer WMM-I (OL) 03+400 04+150 RHS 12/16/2021 12/17/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3601 Level & FDD Checking of WMM Top layer WMM-II (OL) 02+700 03+400 RHS 12/16/2021 12/17/2021

EPC-06/HW/3602 Applying primer coat Prime coat 02+700 03+400 RHS 12/16/2021 12/17/2021

EPC-06/HW/3603 Applying tack coat for DBM Tack coat (DBM) 61+110 61+550 LHS 12/16/2021 12/17/2021

EPC-06/HW/3604 Applying tack coat for DBM Tack coat (DBM) (OL) 61+000 61+110 LHS 12/16/2021 12/17/2021

EPC-06/HW/3605 Applying tack coat for DBM Tack coat (DBM) (OL) 02+700 04+500 LHS 12/16/2021 12/17/2021

EPC-06/HW/3606 Level checking and laying of DBM DBM (OL) 02+700 04+500 LHS 12/16/2021 12/17/2021

EPC-06/HW/3609 FDD Checking of WMM 1st layer WMM-I (OL) 04+150 04+800 RHS 12/17/2021 12/18/2021

EPC-06/HW/3610 Level & FDD Checking of WMM Top layer WMM-II (OL) 03+400 04+150 RHS 12/17/2021 12/18/2021

EPC-06/HW/3611 Applying primer coat Prime coat 03+400 04+150 RHS 12/17/2021 12/18/2021

EPC-06/HW/3612 Applying tack coat for DBM Tack coat (DBM) 63+550 63+950 LHS 12/17/2021 12/18/2021

EPC-06/HW/3613 Applying tack coat for DBM Tack coat (DBM) (OL) 62+130 63+550 LHS 12/17/2021 12/18/2021

EPC-06/HW/3613 Applying tack coat for DBM Tack coat (DBM) (OL) 63+950 64+000 LHS 12/17/2021 12/18/2021

EPC-06/HW/3615 Level checking and laying of DBM DBM 61+110 61+550 LHS 12/17/2021 12/18/2021

EPC-06/HW/3615 Level checking and laying of DBM DBM 63+550 63+950 LHS 12/17/2021 12/18/2021

EPC-06/HW/3616 Level checking and laying of DBM DBM (OL) 61+000 61+110 LHS 12/17/2021 12/18/2021

EPC-06/HW/3616 Level checking and laying of DBM DBM (OL) 62+130 63+550 LHS 12/17/2021 12/18/2021

EPC-06/HW/3616 Level checking and laying of DBM DBM (OL) 63+950 64+000 LHS 12/17/2021 12/18/2021

EPC-06/HW/3617 FDD Checking of WMM 1st layer WMM-I (OL) 00+900 01+950 RHS 12/17/2021 12/18/2021

EPC-06/HW/3619 Level & FDD Checking of WMM Top layer WMM-II (OL) 00+000 00+900 RHS 12/18/2021 12/19/2021

EPC-06/HW/3620 Applying tack coat for BM Tack coat (BM) 02+700 04+600 RHS 12/18/2021 12/19/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3621 Level checking and laying of BM BM 02+700 04+600 RHS 12/18/2021 12/19/2021

EPC-06/HW/3622 FDD Checking of WMM 1st layer WMM-I (OL) 04+800 05+650 RHS 12/18/2021 12/19/2021

EPC-06/HW/3623 Level & FDD Checking of WMM Top layer WMM-II (OL) 04+150 04+800 RHS 12/18/2021 12/19/2021

EPC-06/HW/3624 Applying primer coat Prime coat 04+150 04+800 RHS 12/18/2021 12/19/2021

EPC-06/HW/3625 Applying tack coat for DBM Tack coat (DBM) (OL) 04+500 06+500 LHS 12/18/2021 12/19/2021

EPC-06/HW/3626 Level checking and laying of DBM DBM (OL) 04+500 06+500 LHS 12/18/2021 12/19/2021

EPC-06/HW/3627 Applying tack coat for BM Tack coat (BM) 04+600 06+500 RHS 12/19/2021 12/20/2021

EPC-06/HW/3628 Level checking and laying of BM BM 04+600 06+500 RHS 12/19/2021 12/20/2021

EPC-06/HW/3629 FDD Checking of WMM 1st layer WMM-I (OL) 05+650 06+500 RHS 12/19/2021 12/20/2021

EPC-06/HW/3630 Level & FDD Checking of WMM Top layer WMM-II (OL) 04+800 05+650 RHS 12/19/2021 12/20/2021

EPC-06/HW/3631 Applying primer coat Prime coat 04+800 05+650 RHS 12/19/2021 12/20/2021

EPC-06/HW/3632 Level & FDD Checking of WMM Top layer WMM-II (OL) 00+900 01+950 RHS 12/19/2021 12/20/2021

EPC-06/HW/3634 Level & FDD Checking of WMM Top layer WMM-II (OL) 05+650 06+500 RHS 12/20/2021 12/21/2021

EPC-06/HW/3635 Applying primer coat Prime coat 05+650 06+500 RHS 12/20/2021 12/21/2021

EPC-06/HW/3636 Applying tack coat for DBM Tack coat (DBM) (OL) 02+700 04+600 RHS 12/20/2021 12/21/2021

EPC-06/HW/3637 Level checking and laying of DBM DBM (OL) 02+700 04+600 RHS 12/20/2021 12/21/2021

EPC-06/HW/3640 Applying tack coat for DBM Tack coat (DBM) (OL) 04+600 06+500 RHS 12/21/2021 12/22/2021

EPC-06/HW/3641 Level checking and laying of DBM DBM (OL) 04+600 06+500 RHS 12/21/2021 12/22/2021

EPC-06/HW/3670 FDD Checking of Subgrade Top layer on Minor Junction SG Top 01+587 LHS 12/28/2021 12/29/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3671 FDD Checking of Subgrade Top layer on Minor Junction SG Top 68+740 LHS 12/28/2021 12/29/2021

EPC-06/HW/3675 FDD Checking For GSB layer on Minor Junction GSB 01+587 LHS 12/29/2021 12/30/2021

EPC-06/HW/3676 FDD Checking For GSB layer on Minor Junction GSB 68+740 LHS 12/29/2021 12/30/2021

EPC-06/HW/3680 Applying primer coat Prime coat (OL) 00+000 01+950 RHS 12/30/2021 12/31/2021

EPC-06/HW/3681 FDD Checking of WMM Top layer on Minor Junction WMM-II 01+587 LHS 12/30/2021 12/31/2021

EPC-06/HW/3682 Applying primer coat on Minor Junction Prime coat 01+587 LHS 12/30/2021 12/31/2021

EPC-06/HW/3683 FDD Checking of WMM Top layer on Minor Junction WMM-II 68+740 LHS 12/30/2021 12/31/2021

EPC-06/HW/3684 Applying primer coat on Minor Junction Prime coat 68+740 LHS 12/30/2021 12/31/2021

EPC-06/HW/3688 Applying tack coat for DBM Tack coat (DBM) (OL) 00+000 01+950 RHS 12/31/2021 1/1/2022

EPC-06/HW/3689 Level checking and laying of DBM DBM (OL) 00+000 01+950 RHS 12/31/2021 1/1/2022

EPC-06/HW/3690 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 01+587 LHS 12/31/2021 1/1/2022

EPC-06/HW/3691 Laying of DBM on Minor Junction DBM 01+587 LHS 12/31/2021 1/1/2022

EPC-06/HW/3692 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 68+740 LHS 12/31/2021 1/1/2022

EPC-06/HW/3693 Laying of DBM on Minor Junction DBM 68+740 LHS 12/31/2021 1/1/2022

EPC-06/HW/3703 Level & FDD Checking of Subgrade Top layer SG Top (OL) 00+000 01+950 LHS 1/3/2022 1/4/2022

EPC-06/HW/3704 Level & FDD Checking of Subgrade Top layer SG Top (OL) 06+500 06+560 BHS 1/3/2022 1/4/2022

EPC-06/HW/3714 Level & FDD Checking For GSB layer GSB (OL) 00+000 01+950 LHS 1/7/2022 1/8/2022

EPC-06/HW/3715 Level & FDD Checking For GSB layer GSB (OL) 06+500 06+560 BHS 1/7/2022 1/8/2022

EPC-06/HW/3723 FDD Checking of WMM 1st layer WMM-I (OL) 00+000 01+950 LHS 1/9/2022 1/10/2022

EPC-06/HW/3724 FDD Checking of WMM 1st layer WMM-I (OL) 06+500 06+560 BHS 1/9/2022 1/10/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3728 FDD Checking of Subgrade Top layer on Major Junction SG Top 03+185 LHS 1/10/2022 1/11/2022

EPC-06/HW/3729 FDD Checking of Subgrade Top layer on Major Junction SG Top 05+710 RHS 1/10/2022 1/11/2022

EPC-06/HW/3730 FDD Checking of Subgrade Top layer on Major Junction SG Top 82+130 LHS 1/10/2022 1/11/2022

EPC-06/HW/3734 Level & FDD Checking of WMM Top layer WMM-II (OL) 00+000 01+950 LHS 1/11/2022 1/12/2022

EPC-06/HW/3735 Level & FDD Checking of WMM Top layer WMM-II (OL) 06+500 06+560 BHS 1/11/2022 1/12/2022

EPC-06/HW/3736 FDD Checking For GSB layer on Major Junction GSB 03+185 LHS 1/11/2022 1/12/2022

EPC-06/HW/3737 FDD Checking For GSB layer on Major Junction GSB 05+710 RHS 1/11/2022 1/12/2022

EPC-06/HW/3738 FDD Checking For GSB layer on Major Junction GSB 82+130 LHS 1/11/2022 1/12/2022

EPC-06/HW/3742 Applying primer coat Prime coat (OL) 00+000 01+950 LHS 1/12/2022 1/13/2022

EPC-06/HW/3743 Applying primer coat Prime coat (OL) 06+500 06+560 BHS 1/12/2022 1/13/2022

EPC-06/HW/3744 FDD Checking of WMM Top layer on Major Junction WMM-II 03+185 LHS 1/12/2022 1/13/2022

EPC-06/HW/3745 Applying primer coat on Major Junction Prime coat 03+185 LHS 1/12/2022 1/13/2022

EPC-06/HW/3746 FDD Checking of WMM Top layer on Major Junction WMM-II 05+710 RHS 1/12/2022 1/13/2022

EPC-06/HW/3747 Applying primer coat on Major Junction Prime coat 05+710 RHS 1/12/2022 1/13/2022

EPC-06/HW/3748 FDD Checking of WMM Top layer on Major Junction WMM-II 82+130 LHS 1/12/2022 1/13/2022

EPC-06/HW/3749 Applying primer coat on Major Junction Prime coat 82+130 LHS 1/12/2022 1/13/2022

EPC-06/HW/3753 Applying tack coat for DBM Tack coat (DBM) (OL) 00+000 01+950 LHS 1/13/2022 1/14/2022

EPC-06/HW/3754 Applying tack coat for DBM Tack coat (DBM) (OL) 06+500 06+560 BHS 1/13/2022 1/14/2022

EPC-06/HW/3755 Level checking and laying of DBM DBM (OL) 00+000 01+950 LHS 1/13/2022 1/14/2022

EPC-06/HW/3756 Level checking and laying of DBM DBM (OL) 06+500 06+560 BHS 1/13/2022 1/14/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3757 Applying tack coat for DBM on Major Junction Tack coat (DBM) 03+185 LHS 1/13/2022 1/14/2022

EPC-06/HW/3758 Laying of DBM on Major Junction DBM 03+185 LHS 1/13/2022 1/14/2022

EPC-06/HW/3759 Applying tack coat for DBM on Major Junction Tack coat (DBM) 05+710 RHS 1/13/2022 1/14/2022

EPC-06/HW/3760 Laying of DBM on Major Junction DBM 05+710 RHS 1/13/2022 1/14/2022

EPC-06/HW/3761 Applying tack coat for DBM on Major Junction Tack coat (DBM) 82+130 LHS 1/13/2022 1/14/2022

EPC-06/HW/3762 Laying of DBM on Major Junction DBM 82+130 LHS 1/13/2022 1/14/2022

EPC-06/HW/3812 Dismantling of existing BT surface BT Scr 94+500 96+600 BHS 2/8/2022 2/9/2022

EPC-06/HW/3816 Dismantling of existing BT surface BT Scr 94+200 94+300 BHS 2/9/2022 2/10/2022

EPC-06/HW/3817 Dismantling of existing BT surface BT Scr 96+600 96+800 BHS 2/9/2022 2/10/2022

EPC-06/HW/3818 Level & FDD Checking of Subgrade Top layer SG Top 94+500 96+150 LHS 2/9/2022 2/10/2022

EPC-06/HW/3822 Dismantling of existing BT surface BT Scr 96+800 98+700 BHS 2/10/2022 2/11/2022

EPC-06/HW/3823 Level & FDD Checking of Subgrade Top layer SG Top 96+150 97+680 LHS 2/10/2022 2/11/2022

EPC-06/HW/3827 Dismantling of existing BT surface BT Scr 98+700 100+500 BHS 2/11/2022 2/12/2022

EPC-06/HW/3828 Level & FDD Checking of Subgrade Top layer SG Top 97+750 98+500 LHS 2/11/2022 2/12/2022

EPC-06/HW/3829 Level & FDD Checking For GSB layer GSB 94+500 95+200 LHS 2/11/2022 2/12/2022

EPC-06/HW/3833 Dismantling of existing BT surface BT Scr 100+500 102+100 BHS 2/12/2022 2/13/2022

EPC-06/HW/3834 Level & FDD Checking of Subgrade Top layer SG Top 98+500 99+300 LHS 2/12/2022 2/13/2022

EPC-06/HW/3835 Level & FDD Checking For GSB layer GSB 95+200 96+100 LHS 2/12/2022 2/13/2022

EPC-06/HW/3839 Level & FDD Checking of Subgrade Top layer SG Top 86+860 86+868 BHS 2/13/2022 2/14/2022

EPC-06/HW/3839 Level & FDD Checking of Subgrade Top layer SG Top 88+520 88+650 BHS 2/13/2022 2/14/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3841 Level & FDD Checking of Subgrade Top layer SG Top 88+850 88+900 BHS 2/13/2022 2/14/2022

EPC-06/HW/3841 Level & FDD Checking of Subgrade Top layer SG Top 94+200 94+300 BHS 2/13/2022 2/14/2022

EPC-06/HW/3843 Level & FDD Checking of Subgrade Top layer SG Top 99+360 100+600 LHS 2/13/2022 2/14/2022

EPC-06/HW/3844 Level & FDD Checking For GSB layer GSB 96+100 96+850 LHS 2/13/2022 2/14/2022

EPC-06/HW/3848 Level & FDD Checking For GSB layer GSB 96+850 97+680 LHS 2/14/2022 2/15/2022

EPC-06/HW/3852 Level & FDD Checking For GSB layer GSB 86+860 86+868 BHS 2/15/2022 2/16/2022

EPC-06/HW/3852 Level & FDD Checking For GSB layer GSB 88+520 88+650 BHS 2/15/2022 2/16/2022

EPC-06/HW/3854 Level & FDD Checking For GSB layer GSB 88+850 88+900 BHS 2/15/2022 2/16/2022

EPC-06/HW/3854 Level & FDD Checking For GSB layer GSB 94+200 94+300 BHS 2/15/2022 2/16/2022

EPC-06/HW/3856 Level & FDD Checking For GSB layer GSB 97+750 98+500 LHS 2/15/2022 2/16/2022

EPC-06/HW/3857 FDD Checking of WMM 1st layer WMM-I 94+500 95+200 LHS 2/15/2022 2/16/2022

EPC-06/HW/3861 Level & FDD Checking For GSB layer GSB 98+500 99+300 LHS 2/16/2022 2/17/2022

EPC-06/HW/3862 FDD Checking of WMM 1st layer WMM-I 95+200 96+100 LHS 2/16/2022 2/17/2022

EPC-06/HW/3863 Level & FDD Checking of WMM Top layer WMM-II 94+500 95+200 LHS 2/16/2022 2/17/2022

EPC-06/HW/3867 Level & FDD Checking For GSB layer GSB 99+360 99+950 LHS 2/17/2022 2/18/2022

EPC-06/HW/3868 FDD Checking of WMM 1st layer WMM-I 96+100 96+850 LHS 2/17/2022 2/18/2022

EPC-06/HW/3869 Level & FDD Checking of WMM Top layer WMM-II 95+200 96+100 LHS 2/17/2022 2/18/2022

EPC-06/HW/3873 FDD Checking of WMM 1st layer WMM-I 86+860 86+868 BHS 2/18/2022 2/19/2022

EPC-06/HW/3873 FDD Checking of WMM 1st layer WMM-I 88+520 88+650 BHS 2/18/2022 2/19/2022

EPC-06/HW/3875 FDD Checking of WMM 1st layer WMM-I 88+850 88+900 BHS 2/18/2022 2/19/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3875 FDD Checking of WMM 1st layer WMM-I 94+200 94+300 BHS 2/18/2022 2/19/2022

EPC-06/HW/3877 Level & FDD Checking For GSB layer GSB 99+950 100+600 LHS 2/18/2022 2/19/2022

EPC-06/HW/3878 FDD Checking of WMM 1st layer WMM-I 96+850 97+680 LHS 2/18/2022 2/19/2022

EPC-06/HW/3879 Level & FDD Checking of WMM Top layer WMM-II 96+100 96+850 LHS 2/18/2022 2/19/2022

EPC-06/HW/3883 Level & FDD Checking of WMM Top layer WMM-II 86+860 86+868 BHS 2/19/2022 2/20/2022

EPC-06/HW/3883 Level & FDD Checking of WMM Top layer WMM-II 88+520 88+650 BHS 2/19/2022 2/20/2022

EPC-06/HW/3885 Level & FDD Checking of WMM Top layer WMM-II 88+850 88+900 BHS 2/19/2022 2/20/2022

EPC-06/HW/3885 Level & FDD Checking of WMM Top layer WMM-II 94+200 94+300 BHS 2/19/2022 2/20/2022

EPC-06/HW/3887 FDD Checking of WMM 1st layer WMM-I 97+750 98+500 LHS 2/19/2022 2/20/2022

EPC-06/HW/3888 Level & FDD Checking of WMM Top layer WMM-II 96+850 97+680 LHS 2/19/2022 2/20/2022

EPC-06/HW/3892 FDD Checking of Subgrade Top layer on Major Junction SG Top 85+670 LHS 2/20/2022 2/21/2022

EPC-06/HW/3893 FDD Checking of Subgrade Top layer on Major Junction SG Top 94+270 BHS 2/20/2022 2/21/2022

EPC-06/HW/3894 FDD Checking of Subgrade Top layer on Minor Junction SG Top 97+095 LHS 2/20/2022 2/21/2022

EPC-06/HW/3895 FDD Checking of WMM 1st layer WMM-I 98+500 99+300 LHS 2/20/2022 2/21/2022

EPC-06/HW/3896 Level & FDD Checking of WMM Top layer WMM-II 97+750 98+500 LHS 2/20/2022 2/21/2022

EPC-06/HW/3900 FDD Checking For GSB layer on Major Junction GSB 85+670 LHS 2/21/2022 2/22/2022

EPC-06/HW/3901 FDD Checking For GSB layer on Major Junction GSB 94+270 BHS 2/21/2022 2/22/2022

EPC-06/HW/3902 FDD Checking For GSB layer on Minor Junction GSB 97+095 LHS 2/21/2022 2/22/2022

EPC-06/HW/3903 FDD Checking of WMM 1st layer WMM-I 99+360 99+950 LHS 2/21/2022 2/22/2022

EPC-06/HW/3904 Level & FDD Checking of WMM Top layer WMM-II 98+500 99+300 LHS 2/21/2022 2/22/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3905 Applying primer coat Prime coat 94+500 96+040 LHS 2/21/2022 2/22/2022

EPC-06/HW/3909 Applying primer coat Prime coat 86+860 86+868 BHS 2/22/2022 2/23/2022

EPC-06/HW/3909 Applying primer coat Prime coat 88+520 88+650 BHS 2/22/2022 2/23/2022

EPC-06/HW/3909 Applying primer coat Prime coat 88+850 88+900 BHS 2/22/2022 2/23/2022

EPC-06/HW/3909 Applying primer coat Prime coat 94+200 94+300 BHS 2/22/2022 2/23/2022

EPC-06/HW/3913 FDD Checking of WMM Top layer on Major Junction WMM-II 85+670 LHS 2/22/2022 2/23/2022

EPC-06/HW/3914 Applying primer coat on Major Junction Prime coat 85+670 LHS 2/22/2022 2/23/2022

EPC-06/HW/3915 FDD Checking of WMM Top layer on Major Junction WMM-II 94+270 BHS 2/22/2022 2/23/2022

EPC-06/HW/3916 Applying primer coat on Major Junction Prime coat 94+270 BHS 2/22/2022 2/23/2022

EPC-06/HW/3917 FDD Checking of WMM Top layer on Minor Junction WMM-II 97+095 LHS 2/22/2022 2/23/2022

EPC-06/HW/3918 Applying primer coat on Minor Junction Prime coat 97+095 LHS 2/22/2022 2/23/2022

EPC-06/HW/3919 FDD Checking of WMM 1st layer WMM-I 99+950 100+550 LHS 2/22/2022 2/23/2022

EPC-06/HW/3920 Level & FDD Checking of WMM Top layer WMM-II 99+360 99+950 LHS 2/22/2022 2/23/2022

EPC-06/HW/3921 Applying primer coat Prime coat 96+040 97+680 LHS 2/22/2022 2/23/2022

EPC-06/HW/3922 Applying tack coat for DBM Tack coat (DBM) 94+500 96+040 LHS 2/22/2022 2/23/2022

EPC-06/HW/3923 Level checking and laying of DBM DBM 94+500 96+040 LHS 2/22/2022 2/23/2022

EPC-06/HW/3927 Applying tack coat for DBM Tack coat (DBM) 86+860 86+868 BHS 2/23/2022 2/24/2022

EPC-06/HW/3927 Applying tack coat for DBM Tack coat (DBM) 88+520 88+650 BHS 2/23/2022 2/24/2022

EPC-06/HW/3927 Applying tack coat for DBM Tack coat (DBM) 88+850 88+900 BHS 2/23/2022 2/24/2022

EPC-06/HW/3927 Applying tack coat for DBM Tack coat (DBM) 94+200 94+300 BHS 2/23/2022 2/24/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3931 Level checking and laying of DBM DBM 86+860 86+868 BHS 2/23/2022 2/24/2022

EPC-06/HW/3931 Level checking and laying of DBM DBM 88+520 88+650 BHS 2/23/2022 2/24/2022

EPC-06/HW/3931 Level checking and laying of DBM DBM 88+850 88+900 BHS 2/23/2022 2/24/2022

EPC-06/HW/3931 Level checking and laying of DBM DBM 94+200 94+300 BHS 2/23/2022 2/24/2022

EPC-06/HW/3935 Applying tack coat for DBM on Major Junction Tack coat (DBM) 85+670 LHS 2/23/2022 2/24/2022

EPC-06/HW/3936 Laying of DBM on Major Junction DBM 85+670 LHS 2/23/2022 2/24/2022

EPC-06/HW/3937 Applying tack coat for DBM on Major Junction Tack coat (DBM) 94+270 BHS 2/23/2022 2/24/2022

EPC-06/HW/3938 Laying of DBM on Major Junction DBM 94+270 BHS 2/23/2022 2/24/2022

EPC-06/HW/3939 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 97+095 LHS 2/23/2022 2/24/2022

EPC-06/HW/3940 Laying of DBM on Minor Junction DBM 97+095 LHS 2/23/2022 2/24/2022

EPC-06/HW/3941 Level & FDD Checking of Subgrade Top layer SG Top 94+500 96+000 RHS 2/23/2022 2/24/2022

EPC-06/HW/3942 Level & FDD Checking of WMM Top layer WMM-II 99+950 100+550 LHS 2/23/2022 2/24/2022

EPC-06/HW/3943 Applying primer coat Prime coat 97+750 99+300 LHS 2/23/2022 2/24/2022

EPC-06/HW/3943 Applying primer coat Prime coat 99+360 100+500 LHS 2/23/2022 2/24/2022

EPC-06/HW/3945 Applying tack coat for DBM Tack coat (DBM) 96+040 97+680 LHS 2/23/2022 2/24/2022

EPC-06/HW/3946 Level checking and laying of DBM DBM 96+040 97+680 LHS 2/23/2022 2/24/2022

EPC-06/HW/3950 Level & FDD Checking of Subgrade Top layer SG Top 96+000 97+680 RHS 2/24/2022 2/25/2022

EPC-06/HW/3951 Applying tack coat for DBM Tack coat (DBM) 97+750 99+300 LHS 2/24/2022 2/25/2022

EPC-06/HW/3951 Applying tack coat for DBM Tack coat (DBM) 99+360 100+500 LHS 2/24/2022 2/25/2022

EPC-06/HW/3953 Level checking and laying of DBM DBM 97+750 99+300 LHS 2/24/2022 2/25/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3953 Level checking and laying of DBM DBM 99+360 100+500 LHS 2/24/2022 2/25/2022

EPC-06/HW/3958 Level & FDD Checking For GSB layer GSB 94+500 95+300 RHS 2/25/2022 2/26/2022

EPC-06/HW/3962 Level & FDD Checking of Subgrade Top layer SG Top 97+750 99+300 RHS 2/26/2022 2/27/2022

EPC-06/HW/3963 Level & FDD Checking For GSB layer GSB 95+300 96+150 RHS 2/26/2022 2/27/2022

EPC-06/HW/3967 Level & FDD Checking of Subgrade Top layer SG Top 99+360 100+500 RHS 2/27/2022 2/28/2022

EPC-06/HW/3968 Level & FDD Checking For GSB layer GSB 96+150 96+900 RHS 2/27/2022 2/28/2022

EPC-06/HW/3972 Applying tack coat for BC Tack coat (BC) 75+900 78+700 RHS 2/28/2022 3/1/2022

EPC-06/HW/3973 Level checking and laying of BC BC 75+900 78+700 RHS 2/28/2022 3/1/2022

EPC-06/HW/3974 Level & FDD Checking For GSB layer GSB 96+900 97+680 RHS 2/28/2022 3/1/2022

EPC-06/HW/3978 Level & FDD Checking For GSB layer GSB 97+750 98+500 RHS 3/1/2022 3/2/2022

EPC-06/HW/3982 Applying tack coat for BC Tack coat (BC) 75+900 79+000 LHS 3/2/2022 3/3/2022

EPC-06/HW/3983 Level checking and laying of BC BC 75+900 79+000 LHS 3/2/2022 3/3/2022

EPC-06/HW/3984 Level & FDD Checking For GSB layer GSB 98+500 99+300 RHS 3/2/2022 3/3/2022

EPC-06/HW/3988 Applying tack coat for BC Tack coat (BC) 79+000 82+150 LHS 3/3/2022 3/4/2022

EPC-06/HW/3989 Level checking and laying of BC BC 79+000 82+150 LHS 3/3/2022 3/4/2022

EPC-06/HW/3990 Level & FDD Checking For GSB layer GSB 99+360 99+900 RHS 3/3/2022 3/4/2022

EPC-06/HW/3994 Applying tack coat for BC Tack coat (BC) 78+700 82+150 RHS 3/4/2022 3/5/2022

EPC-06/HW/3995 Level checking and laying of BC BC 78+700 82+150 RHS 3/4/2022 3/5/2022

EPC-06/HW/3996 Level & FDD Checking of Subgrade Top layer SG Top 100+600 101+800 LHS 3/4/2022 3/5/2022

EPC-06/HW/3997 Level & FDD Checking For GSB layer GSB 99+900 100+400 RHS 3/4/2022 3/5/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4001 FDD Checking of WMM 1st layer WMM-I 94+500 95+300 RHS 3/5/2022 3/6/2022

EPC-06/HW/4005 Applying tack coat for BC Tack coat (BC) 74+170 75+700 RHS 3/6/2022 3/7/2022

EPC-06/HW/4006 Applying tack coat for BC Tack coat (BC) 72+200 73+770 RHS 3/6/2022 3/7/2022

EPC-06/HW/4007 Level checking and laying of BC BC 74+170 75+700 RHS 3/6/2022 3/7/2022

EPC-06/HW/4007 Level checking and laying of BC BC 72+200 73+770 RHS 3/6/2022 3/7/2022

EPC-06/HW/4009 FDD Checking of WMM 1st layer WMM-I 95+300 96+150 RHS 3/6/2022 3/7/2022

EPC-06/HW/4010 Level & FDD Checking of WMM Top layer WMM-II 94+500 95+300 RHS 3/6/2022 3/7/2022

EPC-06/HW/4014 Applying tack coat for BC Tack coat (BC) 71+600 72+200 RHS 3/7/2022 3/8/2022

EPC-06/HW/4015 Applying tack coat for BC Tack coat (BC) 70+070 71+100 RHS 3/7/2022 3/8/2022

EPC-06/HW/4016 Applying tack coat for BC Tack coat (BC) 74+170 75+700 LHS 3/7/2022 3/8/2022

EPC-06/HW/4017 Level checking and laying of BC BC 71+600 72+200 RHS 3/7/2022 3/8/2022

EPC-06/HW/4017 Level checking and laying of BC BC 70+070 71+100 RHS 3/7/2022 3/8/2022

EPC-06/HW/4017 Level checking and laying of BC BC 74+170 75+700 LHS 3/7/2022 3/8/2022

EPC-06/HW/4020 FDD Checking of WMM 1st layer WMM-I 96+150 96+900 RHS 3/7/2022 3/8/2022

EPC-06/HW/4021 Level & FDD Checking of WMM Top layer WMM-II 95+300 96+150 RHS 3/7/2022 3/8/2022

EPC-06/HW/4025 Applying tack coat for BC Tack coat (BC) 71+600 73+770 LHS 3/8/2022 3/9/2022

EPC-06/HW/4026 Applying tack coat for BC Tack coat (BC) 70+070 71+100 LHS 3/8/2022 3/9/2022

EPC-06/HW/4027 Level checking and laying of BC BC 71+600 73+770 LHS 3/8/2022 3/9/2022

EPC-06/HW/4027 Level checking and laying of BC BC 70+070 71+100 LHS 3/8/2022 3/9/2022

EPC-06/HW/4029 FDD Checking of WMM 1st layer WMM-I 96+900 97+680 RHS 3/8/2022 3/9/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4030 Level & FDD Checking of WMM Top layer WMM-II 96+150 96+900 RHS 3/8/2022 3/9/2022

EPC-06/HW/4034 Applying tack coat for BC Tack coat (BC) 64+600 67+500 LHS 3/9/2022 3/10/2022

EPC-06/HW/4035 Level checking and laying of BC BC 64+600 67+500 LHS 3/9/2022 3/10/2022

EPC-06/HW/4036 FDD Checking of WMM 1st layer WMM-I 97+750 98+500 RHS 3/9/2022 3/10/2022

EPC-06/HW/4037 Level & FDD Checking of WMM Top layer WMM-II 96+900 97+680 RHS 3/9/2022 3/10/2022

EPC-06/HW/4041 Applying tack coat for BC Tack coat (BC) (OL) 63+950 64+000 LHS 3/10/2022 3/11/2022

EPC-06/HW/4042 Applying tack coat for BC Tack coat (BC) (OL) 61+550 63+550 LHS 3/10/2022 3/11/2022

EPC-06/HW/4043 Level checking and laying of BC BC (OL) 63+950 64+000 LHS 3/10/2022 3/11/2022

EPC-06/HW/4043 Level checking and laying of BC BC (OL) 61+550 63+550 LHS 3/10/2022 3/11/2022

EPC-06/HW/4045 Applying tack coat for BC Tack coat (BC) 64+000 64+600 LHS 3/10/2022 3/11/2022

EPC-06/HW/4046 Applying tack coat for BC Tack coat (BC) 63+550 63+950 LHS 3/10/2022 3/11/2022

EPC-06/HW/4047 Level checking and laying of BC BC 64+000 64+600 LHS 3/10/2022 3/11/2022

EPC-06/HW/4047 Level checking and laying of BC BC 63+550 63+950 LHS 3/10/2022 3/11/2022

EPC-06/HW/4049 FDD Checking of WMM 1st layer WMM-I 98+500 99+300 RHS 3/10/2022 3/11/2022

EPC-06/HW/4050 Level & FDD Checking of WMM Top layer WMM-II 97+750 98+500 RHS 3/10/2022 3/11/2022

EPC-06/HW/4051 Dismantling of existing BT surface BT Scr 102+100 104+000 BHS 3/10/2022 3/11/2022

EPC-06/HW/4054 Applying tack coat for BC Tack coat (BC) (OL) 61+000 61+110 LHS 3/11/2022 3/12/2022

EPC-06/HW/4055 Level checking and laying of BC BC (OL) 61+000 61+110 LHS 3/11/2022 3/12/2022

EPC-06/HW/4056 Applying tack coat for BC Tack coat (BC) 61+110 61+550 LHS 3/11/2022 3/12/2022

EPC-06/HW/4057 Applying tack coat for BC Tack coat (BC) 58+130 61+000 LHS 3/11/2022 3/12/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4058 Level checking and laying of BC BC 61+110 61+550 LHS 3/11/2022 3/12/2022

EPC-06/HW/4058 Level checking and laying of BC BC 58+130 61+000 LHS 3/11/2022 3/12/2022

EPC-06/HW/4060 FDD Checking of WMM 1st layer WMM-I 99+360 99+900 RHS 3/11/2022 3/12/2022

EPC-06/HW/4061 Level & FDD Checking of WMM Top layer WMM-II 98+500 99+300 RHS 3/11/2022 3/12/2022

EPC-06/HW/4062 Applying primer coat Prime coat 94+500 96+500 RHS 3/11/2022 3/12/2022

EPC-06/HW/4063 Dismantling of existing BT surface BT Scr 104+000 106+000 BHS 3/11/2022 3/12/2022

EPC-06/HW/4064 FDD Checking of Subgrade Top layer on Minor Junction SG Top 98+340 LHS 3/11/2022 3/12/2022

EPC-06/HW/4065 FDD Checking of Subgrade Top layer on Minor Junction SG Top 100+260 LHS 3/11/2022 3/12/2022

EPC-06/HW/4067 FDD Checking of WMM 1st layer WMM-I 99+900 100+450 RHS 3/12/2022 3/13/2022

EPC-06/HW/4068 Level & FDD Checking of WMM Top layer WMM-II 99+360 99+900 RHS 3/12/2022 3/13/2022

EPC-06/HW/4069 Applying primer coat Prime coat 96+500 97+680 RHS 3/12/2022 3/13/2022

EPC-06/HW/4069 Applying primer coat Prime coat 97+750 98+500 RHS 3/12/2022 3/13/2022

EPC-06/HW/4071 Applying tack coat for DBM Tack coat (DBM) 94+500 96+500 RHS 3/12/2022 3/13/2022

EPC-06/HW/4072 Level checking and laying of DBM DBM 94+500 96+500 RHS 3/12/2022 3/13/2022

EPC-06/HW/4073 FDD Checking For GSB layer on Minor Junction GSB 98+340 LHS 3/12/2022 3/13/2022

EPC-06/HW/4074 FDD Checking For GSB layer on Minor Junction GSB 100+260 LHS 3/12/2022 3/13/2022

EPC-06/HW/4077 Level & FDD Checking of WMM Top layer WMM-II 99+900 100+450 RHS 3/13/2022 3/14/2022

EPC-06/HW/4078 Applying primer coat Prime coat 98+500 99+300 RHS 3/13/2022 3/14/2022

EPC-06/HW/4078 Applying primer coat Prime coat 99+360 100+400 RHS 3/13/2022 3/14/2022

EPC-06/HW/4080 Applying tack coat for DBM Tack coat (DBM) 96+500 97+680 RHS 3/13/2022 3/14/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4080 Applying tack coat for DBM Tack coat (DBM) 97+750 98+500 RHS 3/13/2022 3/14/2022

EPC-06/HW/4082 Level checking and laying of DBM DBM 96+500 97+680 RHS 3/13/2022 3/14/2022

EPC-06/HW/4082 Level checking and laying of DBM DBM 97+750 98+500 RHS 3/13/2022 3/14/2022

EPC-06/HW/4083 Level & FDD Checking of Subgrade Top layer SG Top 101+800 102+900 LHS 3/13/2022 3/14/2022

EPC-06/HW/4084 Level & FDD Checking For GSB layer GSB 100+600 101+500 LHS 3/13/2022 3/14/2022

EPC-06/HW/4085 FDD Checking of WMM Top layer on Minor Junction WMM-II 98+340 LHS 3/13/2022 3/14/2022

EPC-06/HW/4086 FDD Checking of WMM Top layer on Minor Junction WMM-II 100+260 LHS 3/13/2022 3/14/2022

EPC-06/HW/4087 Applying primer coat on Minor Junction Prime coat 98+340 LHS 3/13/2022 3/14/2022

EPC-06/HW/4087 Applying primer coat on Minor Junction Prime coat 100+260 LHS 3/13/2022 3/14/2022

EPC-06/HW/4088 Applying tack coat for DBM Tack coat (DBM) 98+500 99+300 RHS 3/14/2022 3/15/2022

EPC-06/HW/4088 Applying tack coat for DBM Tack coat (DBM) 99+360 100+400 RHS 3/14/2022 3/15/2022

EPC-06/HW/4090 Level checking and laying of DBM DBM 98+500 99+300 RHS 3/14/2022 3/15/2022

EPC-06/HW/4090 Level checking and laying of DBM DBM 99+360 100+400 RHS 3/14/2022 3/15/2022

EPC-06/HW/4091 Level & FDD Checking of Subgrade Top layer SG Top 102+900 104+100 LHS 3/14/2022 3/15/2022

EPC-06/HW/4092 Level & FDD Checking For GSB layer GSB 101+500 102+350 LHS 3/14/2022 3/15/2022

EPC-06/HW/4093 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 98+340 LHS 3/14/2022 3/15/2022

EPC-06/HW/4093 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 100+260 LHS 3/14/2022 3/15/2022

EPC-06/HW/4094 Laying of DBM on Minor Junction DBM 98+340 LHS 3/14/2022 3/15/2022

EPC-06/HW/4094 Laying of DBM on Minor Junction DBM 100+260 LHS 3/14/2022 3/15/2022

EPC-06/HW/4095 Level & FDD Checking For GSB layer GSB 102+350 103+300 LHS 3/14/2022 3/15/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4096 Applying tack coat for BC Tack coat (BC) 58+130 61+000 RHS 3/15/2022 3/16/2022

EPC-06/HW/4097 Level checking and laying of BC BC 58+130 61+000 RHS 3/15/2022 3/16/2022

EPC-06/HW/4098 Level & FDD Checking of Subgrade Top layer SG Top 100+500 101+800 RHS 3/15/2022 3/16/2022

EPC-06/HW/4099 Level & FDD Checking of Subgrade Top layer SG Top 104+100 105+100 LHS 3/16/2022 3/17/2022

EPC-06/HW/4100 Level & FDD Checking For GSB layer GSB 103+300 104+100 LHS 3/16/2022 3/17/2022

EPC-06/HW/4101 Level & FDD Checking of WMM Top layer WMM-II 100+550 101+450 LHS 3/16/2022 3/17/2022

EPC-06/HW/4102 Level & FDD Checking of Subgrade Top layer SG Top 101+800 102+800 RHS 3/17/2022 3/18/2022

EPC-06/HW/4103 Level & FDD Checking For GSB layer GSB 104+100 105+000 LHS 3/17/2022 3/18/2022

EPC-06/HW/4104 Level & FDD Checking of WMM Top layer WMM-II 101+450 102+350 LHS 3/17/2022 3/18/2022

EPC-06/HW/4105 Level & FDD Checking of Subgrade Top layer SG Top 102+800 104+100 RHS 3/18/2022 3/19/2022

EPC-06/HW/4106 Level & FDD Checking For GSB layer GSB 100+400 101+350 RHS 3/18/2022 3/19/2022

EPC-06/HW/4107 Level & FDD Checking of WMM Top layer WMM-II 102+350 103+250 LHS 3/18/2022 3/19/2022

EPC-06/HW/4108 Level & FDD Checking of Subgrade Top layer SG Top 104+100 105+200 RHS 3/19/2022 3/20/2022

EPC-06/HW/4109 Level & FDD Checking For GSB layer GSB 101+350 102+250 RHS 3/19/2022 3/20/2022

EPC-06/HW/4110 Level & FDD Checking of WMM Top layer WMM-II 103+250 104+200 LHS 3/19/2022 3/20/2022

EPC-06/HW/4111 Level & FDD Checking For GSB layer GSB 102+250 103+200 RHS 3/20/2022 3/21/2022

EPC-06/HW/4112 Level & FDD Checking of WMM Top layer WMM-II 104+200 105+000 LHS 3/20/2022 3/21/2022

EPC-06/HW/4113 Applying tack coat for BC Tack coat (BC) (OL) 61+000 61+110 RHS 3/21/2022 3/22/2022

EPC-06/HW/4114 Applying tack coat for BC Tack coat (BC) (OL) 61+550 63+550 RHS 3/21/2022 3/22/2022

EPC-06/HW/4115 Level checking and laying of BC BC (OL) 61+000 61+110 RHS 3/21/2022 3/22/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4115 Level checking and laying of BC BC (OL) 61+550 63+550 RHS 3/21/2022 3/22/2022

EPC-06/HW/4117 Applying tack coat for BC Tack coat (BC) 61+110 61+550 RHS 3/21/2022 3/22/2022

EPC-06/HW/4118 Applying tack coat for BC Tack coat (BC) 63+550 63+950 RHS 3/21/2022 3/22/2022

EPC-06/HW/4119 Level checking and laying of BC BC 61+110 61+550 RHS 3/21/2022 3/22/2022

EPC-06/HW/4119 Level checking and laying of BC BC 63+550 63+950 RHS 3/21/2022 3/22/2022

EPC-06/HW/4120 Level & FDD Checking For GSB layer GSB 103+200 104+100 RHS 3/21/2022 3/22/2022

EPC-06/HW/4121 FDD Checking of WMM 1st layer WMM-I 101+400 102+300 RHS 3/21/2022 3/22/2022

EPC-06/HW/4122 Level & FDD Checking of WMM Top layer WMM-II 100+450 101+400 RHS 3/21/2022 3/22/2022

EPC-06/HW/4125 Applying tack coat for BC Tack coat (BC) (OL) 63+950 64+000 RHS 3/22/2022 3/23/2022

EPC-06/HW/4126 Level checking and laying of BC BC (OL) 63+950 64+000 RHS 3/22/2022 3/23/2022

EPC-06/HW/4127 Applying tack coat for BC Tack coat (BC) 64+000 67+500 RHS 3/22/2022 3/23/2022

EPC-06/HW/4128 Level checking and laying of BC BC 64+000 67+500 RHS 3/22/2022 3/23/2022

EPC-06/HW/4129 Level & FDD Checking For GSB layer GSB 104+100 105+000 RHS 3/22/2022 3/23/2022

EPC-06/HW/4130 FDD Checking of WMM 1st layer WMM-I 102+300 103+200 RHS 3/22/2022 3/23/2022

EPC-06/HW/4131 Level & FDD Checking of WMM Top layer WMM-II 101+400 102+300 RHS 3/22/2022 3/23/2022

EPC-06/HW/4133 Applying tack coat for BC Tack coat (BC) (OL) 53+000 55+620 RHS 3/23/2022 3/24/2022

EPC-06/HW/4134 Level checking and laying of BC BC (OL) 53+000 55+620 RHS 3/23/2022 3/24/2022

EPC-06/HW/4135 FDD Checking of WMM 1st layer WMM-I 103+200 104+050 RHS 3/23/2022 3/24/2022

EPC-06/HW/4136 Level & FDD Checking of WMM Top layer WMM-II 102+300 103+200 RHS 3/23/2022 3/24/2022

EPC-06/HW/4142 FDD Checking of WMM 1st layer WMM-I 104+050 105+000 RHS 3/24/2022 3/25/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4143 Level & FDD Checking of WMM Top layer WMM-II 103+200 104+050 RHS 3/24/2022 3/25/2022

EPC-06/HW/4155 Level & FDD Checking of WMM Top layer WMM-II 104+050 105+000 RHS 3/25/2022 3/26/2022

EPC-06/HW/4215 Applying tack coat for BC Tack coat (BC) 85+670 86+445 LHS 4/15/2022 4/16/2022

EPC-06/HW/4216 Applying tack coat for BC Tack coat (BC) 88+520 88+900 LHS 4/15/2022 4/16/2022

EPC-06/HW/4217 Applying tack coat for BC Tack coat (BC) 89+285 90+300 LHS 4/15/2022 4/16/2022

EPC-06/HW/4218 Level checking and laying of BC BC 85+670 86+445 LHS 4/15/2022 4/16/2022

EPC-06/HW/4219 Level checking and laying of BC BC 88+520 88+900 LHS 4/15/2022 4/16/2022

EPC-06/HW/4220 Level checking and laying of BC BC 89+285 90+300 LHS 4/15/2022 4/16/2022

EPC-06/HW/4232 Applying tack coat for BC Tack coat (BC) 90+300 92+200 LHS 4/17/2022 4/18/2022

EPC-06/HW/4233 Level checking and laying of BC BC 90+300 92+200 LHS 4/17/2022 4/18/2022

EPC-06/HW/4243 Applying tack coat for BC Tack coat (BC) 92+200 94+300 LHS 4/18/2022 4/19/2022

EPC-06/HW/4244 Level checking and laying of BC BC 92+200 94+300 LHS 4/18/2022 4/19/2022

EPC-06/HW/4259 Applying tack coat for BC Tack coat (BC) 85+670 86+445 RHS 4/21/2022 4/22/2022

EPC-06/HW/4260 Applying tack coat for BC Tack coat (BC) 86+860 86+868 BHS 4/21/2022 4/22/2022

EPC-06/HW/4261 Applying tack coat for BC Tack coat (BC) 88+520 88+900 RHS 4/21/2022 4/22/2022

EPC-06/HW/4262 Applying tack coat for BC Tack coat (BC) 89+285 90+200 RHS 4/21/2022 4/22/2022

EPC-06/HW/4263 Level checking and laying of BC BC 85+670 86+445 RHS 4/21/2022 4/22/2022

EPC-06/HW/4264 Level checking and laying of BC BC 86+860 86+868 BHS 4/21/2022 4/22/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4265 Level checking and laying of BC BC 88+520 88+900 RHS 4/21/2022 4/22/2022

EPC-06/HW/4266 Level checking and laying of BC BC 89+285 90+200 RHS 4/21/2022 4/22/2022

EPC-06/HW/4276 Applying tack coat for BC Tack coat (BC) 90+200 92+300 RHS 4/22/2022 4/23/2022

EPC-06/HW/4277 Level checking and laying of BC BC 90+200 92+300 RHS 4/22/2022 4/23/2022

EPC-06/HW/4292 Applying tack coat for BC Tack coat (BC) 92+300 94+300 RHS 4/24/2022 4/25/2022

EPC-06/HW/4293 Level checking and laying of BC BC 92+300 94+300 RHS 4/24/2022 4/25/2022

EPC-06/HW/4323 Applying tack coat for BC Tack coat (BC) 44+300 46+250 LHS 4/30/2022 5/1/2022

EPC-06/HW/4324 Level checking and laying of BC BC 44+300 46+250 LHS 4/30/2022 5/1/2022

EPC-06/HW/4334 Applying tack coat for BC Tack coat (BC) 46+320 49+500 LHS 5/1/2022 5/2/2022

EPC-06/HW/4335 Level checking and laying of BC BC 46+320 49+500 LHS 5/1/2022 5/2/2022

EPC-06/HW/4345 Applying tack coat for BC Tack coat (BC) 49+900 53+000 LHS 5/2/2022 5/3/2022

EPC-06/HW/4346 Level checking and laying of BC BC 49+900 53+000 LHS 5/2/2022 5/3/2022

EPC-06/HW/4361 Level & FDD Checking of Subgrade Top layer SG Top 105+100 105+900 LHS 5/5/2022 5/6/2022

EPC-06/HW/4362 Applying tack coat for BC Tack coat (BC) (OL) 53+000 55+620 LHS 5/5/2022 5/6/2022

EPC-06/HW/4363 Level checking and laying of BC BC (OL) 53+000 55+620 LHS 5/5/2022 5/6/2022

EPC-06/HW/4070 Laying of BC on Minor Junction BC 56+230 LHS 5/5/2022 5/6/2022

EPC-06/HW/4373 Dismantling of existing BT surface BT Scr 106+000 108+300 BHS 5/6/2022 5/7/2022

EPC-06/HW/4374 Applying tack coat for BC Tack coat (BC) 44+300 46+250 RHS 5/6/2022 5/7/2022

EPC-06/HW/4375 Level checking and laying of BC BC 44+300 46+250 RHS 5/6/2022 5/7/2022

EPC-06/HW/4385 Level & FDD Checking For GSB layer GSB 105+000 105+700 LHS 5/7/2022 5/8/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4395 Level & FDD Checking of Subgrade Top layer SG Top 105+900 106+700 LHS 5/8/2022 5/9/2022

EPC-06/HW/4405 FDD Checking of WMM 1st layer WMM-I 105+000 105+800 LHS 5/9/2022 5/10/2022

EPC-06/HW/4415 Dismantling of existing BT surface BT Scr 94+300 94+500 BHS 5/10/2022 5/11/2022

EPC-06/HW/4416 Level & FDD Checking For GSB layer GSB 105+700 106+700 LHS 5/10/2022 5/11/2022

EPC-06/HW/4417 Level & FDD Checking of WMM Top layer WMM-II 105+000 105+800 LHS 5/10/2022 5/11/2022

EPC-06/HW/4427 Level & FDD Checking of Subgrade Top layer SG Top 106+700 107+500 LHS 5/11/2022 5/12/2022

EPC-06/HW/4437 FDD Checking of WMM 1st layer WMM-I 105+800 106+700 LHS 5/12/2022 5/13/2022

EPC-06/HW/4447 Level & FDD Checking For GSB layer GSB 106+700 107+600 LHS 5/13/2022 5/14/2022

EPC-06/HW/4448 Level & FDD Checking of WMM Top layer WMM-II 105+800 106+700 LHS 5/13/2022 5/14/2022

EPC-06/HW/4449 Applying tack coat for BC Tack coat (BC) 46+320 49+500 RHS 5/13/2022 5/14/2022

EPC-06/HW/4450 Level checking and laying of BC BC 46+320 49+500 RHS 5/13/2022 5/14/2022

EPC-06/HW/4460 Level & FDD Checking of Subgrade Top layer SG Top 107+500 108+300 LHS 5/14/2022 5/15/2022

EPC-06/HW/4461 Applying tack coat for BC Tack coat (BC) 49+900 53+000 RHS 5/14/2022 5/15/2022

EPC-06/HW/4462 Level checking and laying of BC BC 49+900 53+000 RHS 5/14/2022 5/15/2022

EPC-06/HW/4472 FDD Checking of WMM 1st layer WMM-I 106+700 107+500 LHS 5/15/2022 5/16/2022

EPC-06/HW/4482 Level & FDD Checking For GSB layer GSB 107+600 108+300 LHS 5/16/2022 5/17/2022

EPC-06/HW/4483 Level & FDD Checking of WMM Top layer WMM-II 106+700 107+500 LHS 5/16/2022 5/17/2022

EPC-06/HW/4493 Applying tack coat for BC Tack coat (BC) 68+000 68+080 LHS 5/17/2022 5/18/2022

EPC-06/HW/4494 Applying tack coat for BC Tack coat (BC) 68+780 69+230 LHS 5/17/2022 5/18/2022

EPC-06/HW/4495 Applying tack coat for BC Tack coat (BC) 68+000 68+080 RHS 5/17/2022 5/18/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4496 Applying tack coat for BC Tack coat (BC) 68+780 69+230 RHS 5/17/2022 5/18/2022

EPC-06/HW/4497 Level checking and laying of BC BC 68+000 68+080 LHS 5/17/2022 5/18/2022

EPC-06/HW/4498 Level checking and laying of BC BC 68+780 69+230 LHS 5/17/2022 5/18/2022

EPC-06/HW/4499 Level checking and laying of BC BC 68+000 68+080 RHS 5/17/2022 5/18/2022

EPC-06/HW/4500 Level checking and laying of BC BC 68+780 69+230 RHS 5/17/2022 5/18/2022

EPC-06/HW/4505 Laying of DBM on Minor Junction DBM 69+550 LHS 5/17/2022 5/18/2022

EPC-06/HW/4510 Level & FDD Checking of Subgrade Top layer SG Top 99+300 99+360 BHS 5/18/2022 5/19/2022

EPC-06/HW/4511 Level & FDD Checking of Subgrade Top layer SG Top 94+300 94+500 LHS 5/18/2022 5/19/2022

EPC-06/HW/4512 Level & FDD Checking of Subgrade Top layer SG Top 94+300 94+500 RHS 5/18/2022 5/19/2022

EPC-06/HW/4513 FDD Checking of WMM 1st layer WMM-I 107+500 108+300 LHS 5/18/2022 5/19/2022

EPC-06/HW/4523 Level & FDD Checking of WMM Top layer WMM-II 107+500 108+300 LHS 5/19/2022 5/20/2022

EPC-06/HW/4533 Level & FDD Checking For GSB layer GSB 99+300 99+360 BHS 5/20/2022 5/21/2022

EPC-06/HW/4534 Level & FDD Checking For GSB layer GSB 94+300 94+500 LHS 5/20/2022 5/21/2022

EPC-06/HW/4535 Level & FDD Checking For GSB layer GSB 94+300 94+500 RHS 5/20/2022 5/21/2022

EPC-06/HW/4550 FDD Checking of WMM 1st layer WMM-I 99+300 99+360 BHS 5/22/2022 5/23/2022

EPC-06/HW/4551 FDD Checking of WMM 1st layer WMM-I 94+300 94+500 LHS 5/22/2022 5/23/2022

EPC-06/HW/4552 FDD Checking of WMM 1st layer WMM-I 94+300 94+500 RHS 5/22/2022 5/23/2022

EPC-06/HW/4562 Level & FDD Checking of WMM Top layer WMM-II 99+300 99+360 BHS 5/23/2022 5/24/2022

EPC-06/HW/4563 Level & FDD Checking of WMM Top layer WMM-II 94+300 94+500 LHS 5/23/2022 5/24/2022

EPC-06/HW/4564 Level & FDD Checking of WMM Top layer WMM-II 94+300 94+500 RHS 5/23/2022 5/24/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4579 Level & FDD Checking of Subgrade Top layer SG Top 105+200 106+000 RHS 5/25/2022 5/26/2022

EPC-06/HW/4580 Applying primer coat Prime coat 99+300 99+360 LHS 5/25/2022 5/26/2022

EPC-06/HW/4581 Applying primer coat Prime coat 100+500 102+400 LHS 5/25/2022 5/26/2022

EPC-06/HW/4596 Applying tack coat for DBM Tack coat (DBM) 99+300 99+360 LHS 5/26/2022 5/27/2022

EPC-06/HW/4597 Applying tack coat for DBM Tack coat (DBM) 100+500 102+400 LHS 5/26/2022 5/27/2022

EPC-06/HW/4598 Level checking and laying of DBM DBM 99+300 99+360 LHS 5/26/2022 5/27/2022

EPC-06/HW/4599 Level checking and laying of DBM DBM 100+500 102+400 LHS 5/26/2022 5/27/2022

EPC-06/HW/4605 Laying of DBM on Minor Junction DBM 98+340 LHS 5/26/2022 5/27/2022

EPC-06/HW/4605 Laying of DBM on Minor Junction DBM 100+480 BHS 5/26/2022 5/27/2022

EPC-06/HW/4614 Level & FDD Checking of Subgrade Top layer SG Top 106+000 106+800 RHS 5/27/2022 5/28/2022

EPC-06/HW/4615 Level & FDD Checking For GSB layer GSB 105+000 105+800 RHS 5/27/2022 5/28/2022

EPC-06/HW/4616 Applying primer coat Prime coat 102+400 104+500 LHS 5/27/2022 5/28/2022

EPC-06/HW/4631 Applying primer coat Prime coat 104+500 106+200 LHS 5/28/2022 5/29/2022

EPC-06/HW/4632 Applying tack coat for DBM Tack coat (DBM) 102+400 104+500 LHS 5/28/2022 5/29/2022

EPC-06/HW/4633 Level checking and laying of DBM DBM 102+400 104+500 LHS 5/28/2022 5/29/2022

EPC-06/HW/4640 Laying of DBM on Minor Junction DBM 102+060 RHS 5/28/2022 5/29/2022

EPC-06/HW/4648 Level & FDD Checking of Subgrade Top layer SG Top 106+800 107+500 RHS 5/29/2022 5/30/2022

EPC-06/HW/4649 Level & FDD Checking For GSB layer GSB 105+800 106+400 RHS 5/29/2022 5/30/2022

EPC-06/HW/4650 FDD Checking of WMM 1st layer WMM-I 105+000 105+700 RHS 5/29/2022 5/30/2022

EPC-06/HW/4651 Applying primer coat Prime coat 106+200 108+300 LHS 5/29/2022 5/30/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4652 Applying tack coat for DBM Tack coat (DBM) 104+500 106+200 LHS 5/29/2022 5/30/2022

EPC-06/HW/4653 Level checking and laying of DBM DBM 104+500 106+200 LHS 5/29/2022 5/30/2022

EPC-06/HW/4668 Level & FDD Checking of WMM Top layer WMM-II 105+000 105+700 RHS 5/30/2022 5/31/2022

EPC-06/HW/4669 Applying tack coat for DBM Tack coat (DBM) 106+200 108+300 LHS 5/30/2022 5/31/2022

EPC-06/HW/4670 Level checking and laying of DBM DBM 106+200 108+300 LHS 5/30/2022 5/31/2022

EPC-06/HW/4680 Level & FDD Checking of Subgrade Top layer SG Top 107+500 108+300 RHS 5/31/2022 6/1/2022

EPC-06/HW/4681 Level & FDD Checking For GSB layer GSB 106+400 107+400 RHS 5/31/2022 6/1/2022

EPC-06/HW/4682 FDD Checking of WMM 1st layer WMM-I 105+700 106+400 RHS 5/31/2022 6/1/2022

EPC-06/HW/4692 Level & FDD Checking of WMM Top layer WMM-II 105+700 106+400 RHS 6/1/2022 6/2/2022

EPC-06/HW/4693 Applying primer coat Prime coat 99+300 99+360 RHS 6/1/2022 6/2/2022

EPC-06/HW/4694 Applying primer coat Prime coat 100+400 102+500 RHS 6/1/2022 6/2/2022

EPC-06/HW/4704 Level & FDD Checking For GSB layer GSB 107+400 108+300 RHS 6/2/2022 6/3/2022

EPC-06/HW/4705 FDD Checking of WMM 1st layer WMM-I 106+400 107+300 RHS 6/2/2022 6/3/2022

EPC-06/HW/4706 Applying primer coat Prime coat 102+500 104+200 RHS 6/2/2022 6/3/2022

EPC-06/HW/4707 Applying primer coat Prime coat 94+300 94+500 LHS 6/2/2022 6/3/2022

EPC-06/HW/4708 Applying tack coat for DBM Tack coat (DBM) 99+300 99+360 RHS 6/2/2022 6/3/2022

EPC-06/HW/4709 Applying tack coat for DBM Tack coat (DBM) 100+400 102+500 RHS 6/2/2022 6/3/2022

EPC-06/HW/4710 Level checking and laying of DBM DBM 99+300 99+360 RHS 6/2/2022 6/3/2022

EPC-06/HW/4711 Level checking and laying of DBM DBM 100+400 102+500 RHS 6/2/2022 6/3/2022

EPC-06/HW/4721 Level & FDD Checking of WMM Top layer WMM-II 106+400 107+300 RHS 6/3/2022 6/4/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4722 Applying primer coat Prime coat 104+200 106+100 RHS 6/3/2022 6/4/2022

EPC-06/HW/4723 Applying primer coat Prime coat 94+300 94+500 RHS 6/3/2022 6/4/2022

EPC-06/HW/4724 Applying tack coat for DBM Tack coat (DBM) 102+500 104+200 RHS 6/3/2022 6/4/2022

EPC-06/HW/4725 Applying tack coat for DBM Tack coat (DBM) 94+300 94+500 LHS 6/3/2022 6/4/2022

EPC-06/HW/4726 Level checking and laying of DBM DBM 102+500 104+200 RHS 6/3/2022 6/4/2022

EPC-06/HW/4727 Level checking and laying of DBM DBM 94+300 94+500 LHS 6/3/2022 6/4/2022

EPC-06/HW/4730 Laying of DBM on Minor Junction DBM 102+565 RHS 6/3/2022 6/4/2022

EPC-06/HW/4730 Laying of DBM on Minor Junction DBM 103+760 RHS 6/3/2022 6/4/2022

EPC-06/HW/4737 FDD Checking of WMM 1st layer WMM-I 107+300 108+300 RHS 6/4/2022 6/5/2022

EPC-06/HW/4738 Applying tack coat for DBM Tack coat (DBM) 104+200 106+100 RHS 6/4/2022 6/5/2022

EPC-06/HW/4739 Applying tack coat for DBM Tack coat (DBM) 94+300 94+500 RHS 6/4/2022 6/5/2022

EPC-06/HW/4740 Level checking and laying of DBM DBM 104+200 106+100 RHS 6/4/2022 6/5/2022

EPC-06/HW/4741 Level checking and laying of DBM DBM 94+300 94+500 RHS 6/4/2022 6/5/2022

EPC-06/HW/4745 Laying of DBM on Minor Junction DBM 104+715 LHS 6/4/2022 6/5/2022

EPC-06/HW/4751 Level & FDD Checking of WMM Top layer WMM-II 107+300 108+300 RHS 6/5/2022 6/6/2022

EPC-06/HW/4761 Applying primer coat Prime coat 106+100 108+300 RHS 6/6/2022 6/7/2022

EPC-06/HW/4771 Applying tack coat for DBM Tack coat (DBM) 106+100 108+300 RHS 6/7/2022 6/8/2022

EPC-06/HW/4772 Level checking and laying of DBM DBM 106+100 108+300 RHS 6/7/2022 6/8/2022

EPC-06/HW/4773 Applying tack coat for BC Tack coat (BC) (OL) 00+000 01+950 LHS 6/7/2022 6/8/2022

EPC-06/HW/4774 Level checking and laying of BC BC (OL) 00+000 01+950 LHS 6/7/2022 6/8/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4776 Laying of DBM on Minor Junction DBM 108+205 LHS 6/7/2022 6/8/2022

EPC-06/HW/4784 Applying tack coat for BC Tack coat (BC) (OL) 02+700 04+600 LHS 6/8/2022 6/9/2022

EPC-06/HW/4785 Level checking and laying of BC BC (OL) 02+700 04+600 LHS 6/8/2022 6/9/2022

EPC-06/HW/4795 Applying tack coat for BC Tack coat (BC) (OL) 04+600 06+560 LHS 6/9/2022 6/10/2022

EPC-06/HW/4796 Level checking and laying of BC BC (OL) 04+600 06+560 LHS 6/9/2022 6/10/2022

EPC-06/HW/4806 Applying tack coat for BC Tack coat (BC) (OL) 00+000 01+950 RHS 6/10/2022 6/11/2022

EPC-06/HW/4807 Level checking and laying of BC BC (OL) 00+000 01+950 RHS 6/10/2022 6/11/2022

EPC-06/HW/4827 Applying tack coat for BC Tack coat (BC) (OL) 02+700 04+500 RHS 6/13/2022 6/14/2022

EPC-06/HW/4828 Level checking and laying of BC BC (OL) 02+700 04+500 RHS 6/13/2022 6/14/2022

EPC-06/HW/4848 Applying tack coat for BC Tack coat (BC) (OL) 04+500 06+560 RHS 6/14/2022 6/15/2022

EPC-06/HW/4849 Level checking and laying of BC BC (OL) 04+500 06+560 RHS 6/14/2022 6/15/2022

EPC-06/HW/4895 Level & FDD Checking of Subgrade Top layer SG Top 55+620 56+250 RHS 6/15/2022 6/16/2022

EPC-06/HW/4896 Level & FDD Checking of Subgrade Top layer SG Top 61+550 62+130 RHS 6/15/2022 6/16/2022

EPC-06/HW/4897 Level & FDD Checking of Subgrade Top layer SG Top 46+250 46+320 RHS 6/15/2022 6/16/2022

EPC-06/HW/4903 Level & FDD Checking of Subgrade Top layer SG Top 69+230 70+070 LHS 6/16/2022 6/17/2022

EPC-06/HW/4904 Level & FDD Checking of Subgrade Top layer SG Top 01+950 02+700 LHS 6/16/2022 6/17/2022

EPC-06/HW/4905 Level & FDD Checking of Subgrade Top layer SG Top 68+300 68+440 RHS 6/16/2022 6/17/2022

EPC-06/HW/4906 Level & FDD Checking of Subgrade Top layer SG Top 86+860 86+868 RHS 6/16/2022 6/17/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4907 Level & FDD Checking of Subgrade Top layer SG Top 97+680 97+750 RHS 6/16/2022 6/17/2022

EPC-06/HW/4908 Level & FDD Checking For GSB layer GSB 55+620 56+250 RHS 6/16/2022 6/17/2022

EPC-06/HW/4909 Level & FDD Checking For GSB layer GSB 61+550 62+130 RHS 6/16/2022 6/17/2022

EPC-06/HW/4910 Level & FDD Checking For GSB layer GSB 46+250 46+320 RHS 6/16/2022 6/17/2022

EPC-06/HW/4918 Level & FDD Checking of Subgrade Top layer SG Top 55+620 56+250 LHS 6/17/2022 6/18/2022

EPC-06/HW/4919 Level & FDD Checking of Subgrade Top layer SG Top 61+550 62+130 LHS 6/17/2022 6/18/2022

EPC-06/HW/4920 Level & FDD Checking of Subgrade Top layer SG Top 46+250 46+320 LHS 6/17/2022 6/18/2022

EPC-06/HW/4921 Level & FDD Checking For GSB layer GSB 69+230 70+070 LHS 6/17/2022 6/18/2022

EPC-06/HW/4922 Level & FDD Checking For GSB layer GSB 01+950 02+700 LHS 6/17/2022 6/18/2022

EPC-06/HW/4923 Level & FDD Checking For GSB layer GSB 68+300 68+440 RHS 6/17/2022 6/18/2022

EPC-06/HW/4924 Level & FDD Checking For GSB layer GSB 86+860 86+868 RHS 6/17/2022 6/18/2022

EPC-06/HW/4925 Level & FDD Checking For GSB layer GSB 97+680 97+750 RHS 6/17/2022 6/18/2022

EPC-06/HW/4931 FDD Checking of WMM 1st layer WMM-I 55+620 56+250 RHS 6/18/2022 6/19/2022

EPC-06/HW/4932 FDD Checking of WMM 1st layer WMM-I 61+550 62+130 RHS 6/18/2022 6/19/2022

EPC-06/HW/4933 FDD Checking of WMM 1st layer WMM-I 46+250 46+320 RHS 6/18/2022 6/19/2022

EPC-06/HW/4934 Level & FDD Checking of Subgrade Top layer SG Top 69+230 70+070 RHS 6/18/2022 6/19/2022

EPC-06/HW/4935 Level & FDD Checking of Subgrade Top layer SG Top 01+950 02+700 RHS 6/18/2022 6/19/2022

EPC-06/HW/4936 Level & FDD Checking of Subgrade Top layer SG Top 68+300 68+440 LHS 6/18/2022 6/19/2022

EPC-06/HW/4937 Level & FDD Checking of Subgrade Top layer SG Top 86+860 86+868 LHS 6/18/2022 6/19/2022

EPC-06/HW/4938 Level & FDD Checking of Subgrade Top layer SG Top 97+680 97+750 LHS 6/18/2022 6/19/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4939 Level & FDD Checking For GSB layer GSB 55+620 56+250 LHS 6/18/2022 6/19/2022

EPC-06/HW/4940 Level & FDD Checking For GSB layer GSB 61+550 62+130 LHS 6/18/2022 6/19/2022

EPC-06/HW/4941 Level & FDD Checking For GSB layer GSB 46+250 46+320 LHS 6/18/2022 6/19/2022

EPC-06/HW/4946 FDD Checking of WMM 1st layer WMM-I 69+230 70+070 LHS 6/19/2022 6/20/2022

EPC-06/HW/4947 FDD Checking of WMM 1st layer WMM-I 01+950 02+700 LHS 6/19/2022 6/20/2022

EPC-06/HW/4948 FDD Checking of WMM 1st layer WMM-I 97+680 97+750 RHS 6/19/2022 6/20/2022

EPC-06/HW/4949 Level & FDD Checking of WMM Top layer WMM-II 55+620 56+250 RHS 6/19/2022 6/20/2022

EPC-06/HW/4950 Level & FDD Checking of WMM Top layer WMM-II 61+550 62+130 RHS 6/19/2022 6/20/2022

EPC-06/HW/4951 Level & FDD Checking of WMM Top layer WMM-II 46+250 46+320 RHS 6/19/2022 6/20/2022

EPC-06/HW/4952 Level & FDD Checking For GSB layer GSB 69+230 70+070 RHS 6/19/2022 6/20/2022

EPC-06/HW/4953 Level & FDD Checking For GSB layer GSB 01+950 02+700 RHS 6/19/2022 6/20/2022

EPC-06/HW/4954 Level & FDD Checking For GSB layer GSB 68+300 68+440 LHS 6/19/2022 6/20/2022

EPC-06/HW/4955 Level & FDD Checking For GSB layer GSB 86+860 86+868 LHS 6/19/2022 6/20/2022

EPC-06/HW/4956 Level & FDD Checking For GSB layer GSB 97+680 97+750 LHS 6/19/2022 6/20/2022

EPC-06/HW/4957 FDD and level checking of DLC laying DLC 68+300 68+440 RHS 6/19/2022 6/20/2022

EPC-06/HW/4958 FDD and level checking of DLC laying DLC 86+860 86+868 RHS 6/19/2022 6/20/2022

EPC-06/HW/4967 FDD Checking of WMM 1st layer WMM-I 55+620 56+250 LHS 6/20/2022 6/21/2022

EPC-06/HW/4968 FDD Checking of WMM 1st layer WMM-I 61+550 62+130 LHS 6/20/2022 6/21/2022

EPC-06/HW/4969 FDD Checking of WMM 1st layer WMM-I 46+250 46+320 LHS 6/20/2022 6/21/2022

EPC-06/HW/4970 Level & FDD Checking of WMM Top layer WMM-II 69+230 70+070 LHS 6/20/2022 6/21/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4971 Level & FDD Checking of WMM Top layer WMM-II 01+950 02+700 LHS 6/20/2022 6/21/2022

EPC-06/HW/4972 Level & FDD Checking of WMM Top layer WMM-II 97+680 97+750 RHS 6/20/2022 6/21/2022

EPC-06/HW/4973 Applying tack coat for DBM Tack coat (DBM) 55+620 56+250 RHS 6/20/2022 6/21/2022

EPC-06/HW/4974 Applying tack coat for DBM Tack coat (DBM) 61+550 62+130 RHS 6/20/2022 6/21/2022

EPC-06/HW/4975 Applying tack coat for DBM Tack coat (DBM) 97+680 97+750 RHS 6/20/2022 6/21/2022

EPC-06/HW/4976 Applying tack coat for DBM Tack coat (DBM) 46+250 46+320 RHS 6/20/2022 6/21/2022

EPC-06/HW/4977 Applying tack coat for DBM Tack coat (DBM) 97+680 97+750 RHS 6/20/2022 6/21/2022

EPC-06/HW/4978 Level checking and laying of DBM DBM 55+620 56+250 RHS 6/20/2022 6/21/2022

EPC-06/HW/4979 Level checking and laying of DBM DBM 61+550 62+130 RHS 6/20/2022 6/21/2022

EPC-06/HW/4980 Level checking and laying of DBM DBM 97+680 97+750 RHS 6/20/2022 6/21/2022

EPC-06/HW/4981 Level checking and laying of DBM DBM 46+250 46+320 RHS 6/20/2022 6/21/2022

EPC-06/HW/4982 Level checking and laying of DBM DBM 97+680 97+750 RHS 6/20/2022 6/21/2022

EPC-06/HW/4983 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+300 68+440 RHS 6/20/2022 6/21/2022

EPC-06/HW/4984 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+860 86+868 RHS 6/20/2022 6/21/2022

EPC-06/HW/4992 FDD Checking of WMM 1st layer WMM-I 69+230 70+070 RHS 6/21/2022 6/22/2022

EPC-06/HW/4993 FDD Checking of WMM 1st layer WMM-I 01+950 02+700 RHS 6/21/2022 6/22/2022

EPC-06/HW/4994 FDD Checking of WMM 1st layer WMM-I 97+680 97+750 LHS 6/21/2022 6/22/2022

EPC-06/HW/4995 Level & FDD Checking of WMM Top layer WMM-II 55+620 56+250 LHS 6/21/2022 6/22/2022

EPC-06/HW/4996 Level & FDD Checking of WMM Top layer WMM-II 61+550 62+130 LHS 6/21/2022 6/22/2022

EPC-06/HW/4997 Level & FDD Checking of WMM Top layer WMM-II 46+250 46+320 LHS 6/21/2022 6/22/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4998 Applying tack coat for DBM Tack coat (DBM) 69+230 70+070 LHS 6/21/2022 6/22/2022

EPC-06/HW/4999 Applying tack coat for DBM Tack coat (DBM) 01+950 02+700 LHS 6/21/2022 6/22/2022

EPC-06/HW/5000 Applying tack coat for DBM Tack coat (DBM) 97+680 97+750 LHS 6/21/2022 6/22/2022

EPC-06/HW/5001 Applying tack coat for DBM Tack coat (DBM) 97+680 97+750 LHS 6/21/2022 6/22/2022

EPC-06/HW/5002 Level checking and laying of DBM DBM 69+230 70+070 LHS 6/21/2022 6/22/2022

EPC-06/HW/5003 Level checking and laying of DBM DBM 01+950 02+700 LHS 6/21/2022 6/22/2022

EPC-06/HW/5004 Level checking and laying of DBM DBM 97+680 97+750 LHS 6/21/2022 6/22/2022

EPC-06/HW/5005 Level checking and laying of DBM DBM 97+680 97+750 LHS 6/21/2022 6/22/2022

EPC-06/HW/5006 Applying tack coat for BC Tack coat (BC) 55+620 56+250 RHS 6/21/2022 6/22/2022

EPC-06/HW/5007 Applying tack coat for BC Tack coat (BC) 61+550 62+130 RHS 6/21/2022 6/22/2022

EPC-06/HW/5008 Applying tack coat for BC Tack coat (BC) 46+250 46+320 RHS 6/21/2022 6/22/2022

EPC-06/HW/5009 Level checking and laying of BC BC 55+620 56+250 RHS 6/21/2022 6/22/2022

EPC-06/HW/5010 Level checking and laying of BC BC 61+550 62+130 RHS 6/21/2022 6/22/2022

EPC-06/HW/5011 Level checking and laying of BC BC 46+250 46+320 RHS 6/21/2022 6/22/2022

EPC-06/HW/5012 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+860 86+868 RHS 6/21/2022 6/22/2022

EPC-06/HW/5013 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+300 68+440 RHS 6/21/2022 6/22/2022

EPC-06/HW/5014 FDD and level checking of DLC laying DLC 68+300 68+440 LHS 6/21/2022 6/22/2022

EPC-06/HW/5015 FDD and level checking of DLC laying DLC 86+860 86+868 LHS 6/21/2022 6/22/2022

EPC-06/HW/5022 Level & FDD Checking of WMM Top layer WMM-II 69+230 70+070 RHS 6/22/2022 6/23/2022

EPC-06/HW/5023 Level & FDD Checking of WMM Top layer WMM-II 01+950 02+700 RHS 6/22/2022 6/23/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5024 Level & FDD Checking of WMM Top layer WMM-II 97+680 97+750 LHS 6/22/2022 6/23/2022

EPC-06/HW/5025 Applying tack coat for DBM Tack coat (DBM) 55+620 56+250 LHS 6/22/2022 6/23/2022

EPC-06/HW/5026 Applying tack coat for DBM Tack coat (DBM) 61+550 62+130 LHS 6/22/2022 6/23/2022

EPC-06/HW/5027 Applying tack coat for DBM Tack coat (DBM) 46+250 46+320 LHS 6/22/2022 6/23/2022

EPC-06/HW/5028 Level checking and laying of DBM DBM 55+620 56+250 LHS 6/22/2022 6/23/2022

EPC-06/HW/5029 Level checking and laying of DBM DBM 61+550 62+130 LHS 6/22/2022 6/23/2022

EPC-06/HW/5030 Level checking and laying of DBM DBM 46+250 46+320 LHS 6/22/2022 6/23/2022

EPC-06/HW/5031 Applying tack coat for BC Tack coat (BC) 69+230 70+070 LHS 6/22/2022 6/23/2022

EPC-06/HW/5032 Level checking and laying of BC BC 69+230 70+070 LHS 6/22/2022 6/23/2022

EPC-06/HW/5033 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+300 68+440 LHS 6/22/2022 6/23/2022

EPC-06/HW/5034 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+860 86+868 LHS 6/22/2022 6/23/2022

EPC-06/HW/5039 Applying tack coat for BC Tack coat (BC) 01+950 02+700 LHS 6/23/2022 6/24/2022

EPC-06/HW/5040 Level checking and laying of BC BC 01+950 02+700 LHS 6/23/2022 6/24/2022

EPC-06/HW/5041 Applying tack coat for DBM Tack coat (DBM) 69+230 70+070 RHS 6/23/2022 6/24/2022

EPC-06/HW/5042 Applying tack coat for DBM Tack coat (DBM) 01+950 02+700 RHS 6/23/2022 6/24/2022

EPC-06/HW/5043 Level checking and laying of DBM DBM 69+230 70+070 RHS 6/23/2022 6/24/2022

EPC-06/HW/5044 Level checking and laying of DBM DBM 01+950 02+700 RHS 6/23/2022 6/24/2022

EPC-06/HW/5045 Applying tack coat for BC Tack coat (BC) 55+620 56+250 LHS 6/23/2022 6/24/2022

EPC-06/HW/5046 Applying tack coat for BC Tack coat (BC) 61+550 62+130 LHS 6/23/2022 6/24/2022

EPC-06/HW/5047 Applying tack coat for BC Tack coat (BC) 46+250 46+320 LHS 6/23/2022 6/24/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5048 Level checking and laying of BC BC 55+620 56+250 LHS 6/23/2022 6/24/2022

EPC-06/HW/5049 Level checking and laying of BC BC 61+550 62+130 LHS 6/23/2022 6/24/2022

EPC-06/HW/5050 Level checking and laying of BC BC 46+250 46+320 LHS 6/23/2022 6/24/2022

EPC-06/HW/5051 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+860 86+868 LHS 6/23/2022 6/24/2022

EPC-06/HW/5052 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+300 68+440 LHS 6/23/2022 6/24/2022

EPC-06/HW/5060 Applying tack coat for BC Tack coat (BC) 69+230 70+070 RHS 6/24/2022 6/25/2022

EPC-06/HW/5061 Applying tack coat for BC Tack coat (BC) 01+950 02+700 RHS 6/24/2022 6/25/2022

EPC-06/HW/5062 Level checking and laying of BC BC 69+230 70+070 RHS 6/24/2022 6/25/2022

EPC-06/HW/5063 Level checking and laying of BC BC 01+950 02+700 RHS 6/24/2022 6/25/2022

EPC-06/HW/5064 Applying tack coat for BC Tack coat (BC) 97+700 100+000 LHS 6/24/2022 6/25/2022

EPC-06/HW/5065 Level checking and laying of BC BC 97+700 100+000 LHS 6/24/2022 6/25/2022

EPC-06/HW/5069 Applying tack coat for BC Tack coat (BC) 94+300 96+100 LHS 6/25/2022 6/26/2022

EPC-06/HW/5070 Applying tack coat for BC Tack coat (BC) 96+100 97+700 LHS 6/25/2022 6/26/2022

EPC-06/HW/5071 Level checking and laying of BC BC 94+300 96+100 LHS 6/25/2022 6/26/2022

EPC-06/HW/5072 Level checking and laying of BC BC 96+100 97+700 LHS 6/25/2022 6/26/2022

EPC-06/HW/5073 Applying tack coat for BC Tack coat (BC) 100+000 102+100 LHS 6/25/2022 6/26/2022

EPC-06/HW/5074 Applying tack coat for BC Tack coat (BC) 102+100 104+300 LHS 6/25/2022 6/26/2022

EPC-06/HW/5075 Level checking and laying of BC BC 100+000 102+100 LHS 6/25/2022 6/26/2022

EPC-06/HW/5076 Level checking and laying of BC BC 102+100 104+300 LHS 6/25/2022 6/26/2022

EPC-06/HW/5077 Road side plantation Plantation 44+300 46+251 BHS 6/25/2022 6/26/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5085 Applying tack coat for BC Tack coat (BC) 104+300 106+300 LHS 6/26/2022 6/27/2022

EPC-06/HW/5086 Applying tack coat for BC Tack coat (BC) 106+300 108+300 LHS 6/26/2022 6/27/2022

EPC-06/HW/5087 Level checking and laying of BC BC 104+300 106+300 LHS 6/26/2022 6/27/2022

EPC-06/HW/5088 Level checking and laying of BC BC 106+300 108+300 LHS 6/26/2022 6/27/2022

EPC-06/HW/5089 Road side plantation Plantation 46+320 48+500 BHS 6/26/2022 6/27/2022

EPC-06/HW/5095 Applying tack coat for BC Tack coat (BC) 94+300 96+200 RHS 6/27/2022 6/28/2022

EPC-06/HW/5096 Applying tack coat for BC Tack coat (BC) 96+200 97+800 RHS 6/27/2022 6/28/2022

EPC-06/HW/5097 Applying tack coat for BC Tack coat (BC) 97+800 100+000 RHS 6/27/2022 6/28/2022

EPC-06/HW/5098 Level checking and laying of BC BC 94+300 96+200 RHS 6/27/2022 6/28/2022

EPC-06/HW/5099 Level checking and laying of BC BC 96+200 97+800 RHS 6/27/2022 6/28/2022

EPC-06/HW/5100 Level checking and laying of BC BC 97+800 100+000 RHS 6/27/2022 6/28/2022

EPC-06/HW/5101 Road side plantation Plantation 48+500 49+500 BHS 6/27/2022 6/28/2022

EPC-06/HW/5109 Applying tack coat for BC Tack coat (BC) 100+000 102+000 RHS 6/28/2022 6/29/2022

EPC-06/HW/5110 Applying tack coat for BC Tack coat (BC) 102+000 104+000 RHS 6/28/2022 6/29/2022

EPC-06/HW/5111 Level checking and laying of BC BC 100+000 102+000 RHS 6/28/2022 6/29/2022

EPC-06/HW/5112 Level checking and laying of BC BC 102+000 104+000 RHS 6/28/2022 6/29/2022

EPC-06/HW/5113 Road side plantation Plantation 49+900 51+500 BHS 6/28/2022 6/29/2022

EPC-06/HW/5120 Applying tack coat for BC Tack coat (BC) 104+000 106+400 RHS 6/29/2022 6/30/2022

EPC-06/HW/5121 Applying tack coat for BC Tack coat (BC) 106+400 108+300 RHS 6/29/2022 6/30/2022

EPC-06/HW/5122 Level checking and laying of BC BC 104+000 106+400 RHS 6/29/2022 6/30/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5123 Level checking and laying of BC BC 106+400 108+300 RHS 6/29/2022 6/30/2022

EPC-06/HW/5124 Road side plantation Plantation 51+500 53+820 BHS 6/29/2022 6/30/2022

EPC-06/HW/5133 Road signs, markings, km stones, safety device R,M,K,S 44+300 46+251 BHS 6/30/2022 7/1/2022

EPC-06/HW/5134 Road side plantation Plantation 53+820 55+623 BHS 6/30/2022 7/1/2022

EPC-06/HW/5139 Road signs, markings, km stones, safety device R,M,K,S 46+320 48+500 RHS 7/1/2022 7/2/2022

EPC-06/HW/5140 Road side plantation Plantation 58+130 60+100 BHS 7/1/2022 7/2/2022

EPC-06/HW/5145 Road signs, markings, km stones, safety device R,M,K,S 46+320 48+500 LHS 7/2/2022 7/3/2022

EPC-06/HW/5146 Road side plantation Plantation 60+100 61+550 BHS 7/2/2022 7/3/2022

EPC-06/HW/5150 Road signs, markings, km stones, safety device R,M,K,S 48+500 50+050 BHS 7/3/2022 7/4/2022

EPC-06/HW/5151 Road side plantation Plantation 62+130 64+870 BHS 7/3/2022 7/4/2022

EPC-06/HW/5160 Road signs, markings, km stones, safety device R,M,K,S 50+050 51+500 RHS 7/4/2022 7/5/2022

EPC-06/HW/5161 Road side plantation Plantation 64+870 66+190 BHS 7/4/2022 7/5/2022

EPC-06/HW/5167 Road signs, markings, km stones, safety device R,M,K,S 50+050 51+500 LHS 7/5/2022 7/6/2022

EPC-06/HW/5168 Road side plantation Plantation 66+190 67+500 BHS 7/5/2022 7/6/2022

EPC-06/HW/5173 Road signs, markings, km stones, safety device R,M,K,S 51+500 53+820 RHS 7/6/2022 7/7/2022

EPC-06/HW/5174 Road side plantation Plantation 68+772 69+230 BHS 7/6/2022 7/7/2022

EPC-06/HW/5179 Road signs, markings, km stones, safety device R,M,K,S 51+500 53+820 LHS 7/7/2022 7/8/2022

EPC-06/HW/5180 Road side plantation Plantation 70+067 71+100 BHS 7/7/2022 7/8/2022

EPC-06/HW/5186 Road signs, markings, km stones, safety device R,M,K,S 53+820 55+623 BHS 7/8/2022 7/9/2022

EPC-06/HW/5187 Road side plantation Plantation 71+600 73+770 BHS 7/8/2022 7/9/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5193 Road signs, markings, km stones, safety device R,M,K,S 58+130 60+100 LHS 7/9/2022 7/10/2022

EPC-06/HW/5194 Road side plantation Plantation 74+170 75+700 BHS 7/9/2022 7/10/2022

EPC-06/HW/5202 Road signs, markings, km stones, safety device R,M,K,S 58+130 60+100 RHS 7/10/2022 7/11/2022

EPC-06/HW/5203 Road side plantation Plantation 75+900 78+100 BHS 7/10/2022 7/11/2022

EPC-06/HW/5208 Road signs, markings, km stones, safety device R,M,K,S 60+100 61+550 LHS 7/11/2022 7/12/2022

EPC-06/HW/5209 Road side plantation Plantation 78+100 80+250 BHS 7/11/2022 7/12/2022

EPC-06/HW/5216 Road signs, markings, km stones, safety device R,M,K,S 60+100 61+550 RHS 7/12/2022 7/13/2022

EPC-06/HW/5217 Road side plantation Plantation 80+250 82+150 BHS 7/12/2022 7/13/2022

EPC-06/HW/5224 Road signs, markings, km stones, safety device R,M,K,S 62+130 64+870 BHS 7/13/2022 7/14/2022

EPC-06/HW/5225 Road side plantation Plantation 00+000 01+950 BHS 7/13/2022 7/14/2022

EPC-06/HW/5229 Road signs, markings, km stones, safety device R,M,K,S 64+870 66+190 RHS 7/14/2022 7/15/2022

EPC-06/HW/5230 Road side plantation Plantation 02+700 04+500 BHS 7/14/2022 7/15/2022

EPC-06/HW/5236 Road signs, markings, km stones, safety device R,M,K,S 64+870 66+190 LHS 7/15/2022 7/16/2022

EPC-06/HW/5237 Road side plantation Plantation 04+500 06+560 BHS 7/15/2022 7/16/2022

EPC-06/HW/5243 Road side plantation Plantation 85+670 86+868 BHS 7/16/2022 7/17/2022

EPC-06/HW/5251 Road signs, markings, km stones, safety device R,M,K,S 66+190 67+500 BHS 7/17/2022 7/18/2022

EPC-06/HW/5252 Road side plantation Plantation 86+868 88+520 BHS 7/17/2022 7/18/2022

EPC-06/HW/5257 Road signs, markings, km stones, safety device R,M,K,S 68+000 68+080 BHS 7/18/2022 7/19/2022

EPC-06/HW/5258 Road side plantation Plantation 88+520 88+900 BHS 7/18/2022 7/19/2022

EPC-06/HW/5263 Road signs, markings, km stones, safety device R,M,K,S 68+772 69+230 BHS 7/19/2022 7/20/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5264 Road side plantation Plantation 89+285 92+000 BHS 7/19/2022 7/20/2022

EPC-06/HW/5269 Road signs, markings, km stones, safety device R,M,K,S 70+067 72+090 BHS 7/20/2022 7/21/2022

EPC-06/HW/5270 Road side plantation Plantation 89+005 92+000 BHS 7/20/2022 7/21/2022

EPC-06/HW/5274 Road signs, markings, km stones, safety device R,M,K,S 72+090 74+000 BHS 7/21/2022 7/22/2022

EPC-06/HW/5275 Road side plantation Plantation 92+000 94+300 BHS 7/21/2022 7/22/2022

EPC-06/HW/5280 Road side plantation Plantation 94+300 97+750 BHS 7/22/2022 7/23/2022

EPC-06/HW/5286 Road signs, markings, km stones, safety device R,M,K,S 74+000 75+910 RHS 7/23/2022 7/24/2022

EPC-06/HW/5287 Road side plantation Plantation 97+750 100+500 BHS 7/23/2022 7/24/2022

EPC-06/HW/5294 Road signs, markings, km stones, safety device R,M,K,S 74+000 75+910 LHS 7/24/2022 7/25/2022

EPC-06/HW/5295 Road side plantation Plantation 100+500 102+800 BHS 7/24/2022 7/25/2022

EPC-06/HW/5301 Road signs, markings, km stones, safety device R,M,K,S 75+910 78+100 BHS 7/25/2022 7/26/2022

EPC-06/HW/5302 Road side plantation Plantation 102+800 105+150 BHS 7/25/2022 7/26/2022

EPC-06/HW/5308 Road signs, markings, km stones, safety device R,M,K,S 78+100 80+250 BHS 7/26/2022 7/27/2022

EPC-06/HW/5309 Road side plantation Plantation 105+150 107+200 BHS 7/26/2022 7/27/2022

EPC-06/HW/5313 Road signs, markings, km stones, safety device R,M,K,S 80+250 82+150 BHS 7/27/2022 7/28/2022

EPC-06/HW/5314 Road side plantation Plantation 107+200 108+300 BHS 7/27/2022 7/28/2022

EPC-06/HW/5320 Road signs, markings, km stones, safety device R,M,K,S 00+000 01+950 BHS 7/28/2022 7/29/2022

EPC-06/HW/5324 Road signs, markings, km stones, safety device R,M,K,S 02+700 04+500 BHS 7/29/2022 7/30/2022

EPC-06/HW/5329 Road signs, markings, km stones, safety device R,M,K,S 04+500 06+560 BHS 7/31/2022 8/1/2022

EPC-06/HW/5334 Road signs, markings, km stones, safety device R,M,K,S 85+670 86+868 LHS 8/1/2022 8/2/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5339 Road signs, markings, km stones, safety device R,M,K,S 85+670 86+868 RHS 8/2/2022 8/3/2022

EPC-06/HW/5343 Road signs, markings, km stones, safety device R,M,K,S 86+868 89+005 BHS 8/3/2022 8/4/2022

EPC-06/HW/5348 Road signs, markings, km stones, safety device R,M,K,S 89+005 92+000 RHS 8/4/2022 8/5/2022

EPC-06/HW/5353 Road signs, markings, km stones, safety device R,M,K,S 89+005 92+000 LHS 8/5/2022 8/6/2022

EPC-06/HW/5360 Road signs, markings, km stones, safety device R,M,K,S 92+000 94+300 BHS 8/6/2022 8/7/2022

EPC-06/HW/5482 Road signs, markings, km stones, safety device R,M,K,S 94+300 96+700 BHS 9/20/2022 9/21/2022

EPC-06/HW/5515 Road signs, markings, km stones, safety device R,M,K,S 96+700 98+700 BHS 9/24/2022 9/25/2022

EPC-06/HW/5522 Road signs, markings, km stones, safety device R,M,K,S 98+700 101+200 BHS 9/25/2022 9/26/2022

EPC-06/HW/5535 Road signs, markings, km stones, safety device R,M,K,S 101+200 103+500 BHS 9/27/2022 9/28/2022

EPC-06/HW/5549 Road signs, markings, km stones, safety device R,M,K,S 103+500 105+600 BHS 9/29/2022 9/30/2022

EPC-06/HW/5558 Road signs, markings, km stones, safety device R,M,K,S 105+600 108+300 BHS 9/1/2022 9/2/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/8 Checking of Layout and excavation for head wall. HPC 74+546 BHS 7/15/2020 7/16/2020

EPC-06/STR/9 Dismantling of existing HPC. HPC 74+546 BHS 7/15/2020 7/16/2020

EPC-06/STR/11 Pouring of Concrete M-15 grade for head wall P.C.C. HPC 74+546 BHS 7/16/2020 7/17/2020

EPC-06/STR/12 Shuttering checking and pouring of concrete (M-20 Grade) for head wall 1st lift. HPC 74+546 BHS 7/18/2020 7/19/2020

EPC-06/STR/37 Excavation of Pipe Barel Portion. HPC 74+546 LHS 7/26/2020 7/27/2020

EPC-06/STR/40 Granual beding & pipe laying 1200mm dia HPC. HPC 74+546 LHS 7/27/2020 7/28/2020

EPC-06/STR/53 Shuttering Checking and Pouring of concrete M-20 for head wall 2nd lift. HPC 74+546 RHS 8/1/2020 8/2/2020

EPC-06/STR/61 Shuttering Checking and Pouring of concrete M-20 for head wall 2nd lift. HPC 74+546 LHS 8/5/2020 8/6/2020

EPC-06/STR/64 Checking of Layout and excavation for head wall. HPC 72+851 BHS 8/16/2020 8/17/2020

EPC-06/STR/65 Dismantling of existing HPC. HPC 72+851 BHS 8/16/2020 8/17/2020

EPC-06/STR/66 Pouring of Concrete M-15 grade for head wall P.C.C. HPC 72+851 BHS 8/16/2020 8/17/2020

EPC-06/STR/75 Shuttering Checking and Pouring of concrete M-20 for head wall 3rd lift. HPC 74+546 LHS 8/16/2020 8/17/2020

EPC-06/STR/80 Shuttering Checking and Pouring of concrete M-20 for head wall 3rd lift. HPC 74+546 RHS 8/21/2020 8/22/2020

EPC-06/STR/94 Shuttering Checking and Pouring of concrete M-20 for head wall 1st lift. HPC 72+851 BHS 8/24/2020 8/25/2020

EPC-06/STR/97 Excavation of Pipe Barel Portion. HPC 72+851 BHS 8/25/2020 8/26/2020

EPC-06/STR/98 Granual beding & pipe laying 1200mm dia HPC. HPC 72+851 BHS 8/25/2020 8/26/2020

EPC-06/STR/99 Shuttering Checking and Pouring of concrete M-20 for head wall 2nd lift. HPC 72+851 LHS 8/25/2020 8/26/2020

EPC-06/STR/115 Checking of Layout and excavation for head wall. HPC 73+423 BHS 8/31/2020 9/1/2020

EPC-06/STR/116 Dismantling of existing HPC. HPC 73+423 BHS 8/31/2020 9/1/2020

EPC-06/STR/121 Pouring of Concrete M-15 grade for head wall P.C.C. HPC 73+423 BHS 9/1/2020 9/2/2020

EPC-06/STR/125 Shuttering checking and pouring of concrete M-20 for Head wall 1st lift (HPC) HPC 73+423 LHS 9/2/2020 9/3/2020

EPC-06/STR/128 Excavation of Pipe Barel Portion. HPC 73+423 BHS 9/3/2020 9/4/2020

EPC-06/STR/129 Granual beding & pipe laying 1200mm dia HPC. HPC 73+423 BHS 9/3/2020 9/4/2020

EPC-06/STR/130 Shuttering checking and pouring of concrete M-20 for Head wall 1st lift (HPC) HPC 73+423 RHS 9/3/2020 9/4/2020

EPC-06/STR/135 Shuttering checking and pouring of concrete M-20 for Head wall 2nd lift (HPC) HPC 73+423 LHS 9/4/2020 9/5/2020

EPC-06/STR/140 Dismantling of existing Structure Box Culvert 79+671 BHS 9/4/2020 9/5/2020
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/152 Shuttering checking and pouring of concrete M-20 for Head wall 2nd lift (HPC) HPC 73+423 RHS 9/9/2020 9/10/2020

EPC-06/STR/155 Shuttering checking and pouring of concrete M-20 for Head wall final lift (HPC) HPC 73+423 RHS 9/10/2020 9/11/2020 Not Done

EPC-06/STR/164 Shuttering checking and pouring of concrete M-20 for Head wall final lift (HPC) HPC 73+423 RHS 9/12/2020 9/13/2020

EPC-06/STR/169 Dismantling of Existing Structure Box Culvert 80+477 BHS 9/17/2020 9/18/2020

EPC-06/STR/200 Shuttering and reinforcement checking for Top Slab (Box Culvert) Box Culvert 80+477 BHS 9/26/2020 9/27/2020

EPC-06/STR/201 Pouring of concrete RCC M-25 for Top Slab (Box Culvert) Box Culvert 80+477 BHS 9/26/2020 9/27/2020

EPC-06/STR/208 Layout marking and OGL checking for excavation. (Box Culvert) Box Culvert 77+243 9/27/2020 9/28/2020

EPC-06/STR/209 Dismantling of existing structure (Box Culvert) Box Culvert 77+243 9/27/2020 9/28/2020

EPC-06/STR/210 Earthwork in excavation for Box Culvert Box Culvert 77+243 9/27/2020 9/28/2020

EPC-06/STR/223 EGL checking and Boulder Soling below PCC (Box Culvert) Box Culvert 77+243 9/30/2020 10/1/2020

EPC-06/STR/225 Pouring of concrete PCC M-15 below raft with Cut off wall (Box Culvert) Box Culvert 77+243 9/30/2020 10/1/2020

EPC-06/STR/226 Shuttering checking and pouring of concrete M-20 for Head wall final lift (HPC) HPC 72+851 LHS 9/30/2020 10/1/2020

EPC-06/STR/230 Shuttering and Reinforcement checking of raft (Box Culvert) Box Culvert 77+243 10/2/2020 10/3/2020

EPC-06/STR/231 Pouring of concrete RCC M-25 for raft (Box Culvert) Box Culvert 77+243 10/2/2020 10/3/2020

EPC-06/STR/234 Shuttering and reinforcement checking for bottom hunch (Box Culvert) Box Culvert 77+243 10/3/2020 10/4/2020

EPC-06/STR/235 Pouring of concrete RCC M-25 for bottom hunch (Box Culvert) Box Culvert 77+243 10/3/2020 10/4/2020

EPC-06/STR/253 Shuttering and reinforcement checking for Wall 1st lift -A1, A2 (Box Culvert) Box Culvert 77+243 10/6/2020 10/7/2020

EPC-06/STR/254 Pouring of concrete RCC M-25 for Wall 1st lift -A1, A2 (Box Culvert) Box Culvert 77+243 10/6/2020 10/7/2020

EPC-06/STR/257 Shuttering checking and pouring of concrete M-20 for Head wall 2nd lift (HPC) HPC 72+851 RHS 10/7/2020 10/8/2020

EPC-06/STR/268 Shuttering checking and pouring of concrete M-20 for Head wall final lift (HPC) HPC 72+851 RHS 10/8/2020 10/9/2020 Not Done

EPC-06/STR/270 Layout marking and OGL checking for excavation of Head Wall (HPC) HPC 75+841 BHS 10/8/2020 10/9/2020

EPC-06/STR/277 Earthwork in excavation for Head Wall (HPC) HPC 75+841 BHS 10/9/2020 10/10/2020

EPC-06/STR/278 EGL checking and Pouring of concrete PCC M-15 below Head Wall (HPC) HPC 75+841 RHS 10/9/2020 10/10/2020

EPC-06/STR/279 Dismantling of existing HPC. HPC 75+841 BHS 10/9/2020 10/10/2020

EPC-06/STR/280 Dismantling of Head wall final lift (NCR-001) HPC 73+423 LHS 10/9/2020 10/10/2020

EPC-06/STR/285 Earthwork in excavation for Head Wall (HPC) HPC 73+716 BHS 10/10/2020 10/11/2020
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/287 Dismantling of existing HPC. HPC 72+148 BHS 10/10/2020 10/11/2020

EPC-06/STR/288 Earthwork in excavation for Head Wall (HPC) HPC 72+148 BHS 10/10/2020 10/11/2020

EPC-06/STR/290 EGL checking and Pouring of concrete PCC M-15 below Head Wall (HPC) HPC 73+716 BHS 10/10/2020 10/11/2020

EPC-06/STR/292 EGL checking and Pouring of concrete PCC M-15 below Head Wall (HPC) HPC 72+148 LHS 10/10/2020 10/11/2020

EPC-06/STR/293 Shuttering checking and pouring of concrete M-20 for Head wall final lift (HPC) HPC 72+851 RHS 10/10/2020 10/11/2020

EPC-06/STR/294 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 75+841 RHS 10/10/2020 10/11/2020 Not Done

EPC-06/STR/295 Dismantling of existing HPC. HPC 73+716 BHS 10/10/2020 10/11/2020

Shuttering checking and pouring of concrete M-20 for Head wall final lift (HPC)-
EPC-06/STR/296 HPC 73+423 LHS 10/10/2020 10/11/2020
Closing NCR-001

EPC-06/STR/301 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 75+841 RHS 10/11/2020 10/12/2020

EPC-06/STR/302 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 72+148 LHS 10/11/2020 10/12/2020

EPC-06/STR/312 Earthwork in excavation for pipe laying HPC 72+148 LHS 10/12/2020 10/13/2020

EPC-06/STR/313 Laying of NP-4 Pipe 1200 mm dia HPC 72+148 LHS 10/12/2020 10/13/2020

EPC-06/STR/314 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift (HPC) HPC 72+148 LHS 10/12/2020 10/13/2020

Shuttering and reinforcement checking for Wall 2nd lift & bracket -A1, A2 (Box
EPC-06/STR/317 Box Culvert 77+243 10/13/2020 10/14/2020
Culvert)

EPC-06/STR/318 Pouring of concrete RCC M-25 for Wall 2nd lift & bracket -A1, A2 (Box Culvert) Box Culvert 77+243 10/13/2020 10/14/2020

EPC-06/STR/327 Shuttering and reinforcement checking for Wall Top Slab (Box Culvert) Box Culvert 77+243 BHS 10/14/2020 10/15/2020

EPC-06/STR/328 Pouring of concrete RCC M-25 for Top Slab and Hunch (Box Culvert) Box Culvert 77+243 BHS 10/14/2020 10/15/2020

EPC-06/STR/330 Dismantling of existing structure MNB 76+647 BHS 10/14/2020 10/15/2020

EPC-06/STR/338 EGL checking and Pouring of concrete PCC M-15 below Head Wall (HPC) HPC 72+148 RHS 10/15/2020 10/16/2020

EPC-06/STR/339 Dismantling of existing structure HPC 72+110 BHS 10/15/2020 10/16/2020

EPC-06/STR/350 Earthwork in excavation for pipe laying HPC 75+841 RHS 10/17/2020 10/18/2020

EPC-06/STR/351 Laying of NP-4 Pipe 1000 mm dia HPC 75+841 RHS 10/17/2020 10/18/2020

EPC-06/STR/353 Earthwork in excavation for Head Wall (HPC) HPC 92+563 BHS 10/17/2020 10/18/2020

EPC-06/STR/354 Dismantling of existing HPC. HPC 92+563 BHS 10/17/2020 10/18/2020

EPC-06/STR/355 EGL checking and Pouring of concrete PCC M-15 below Head Wall (HPC) HPC 92+563 BHS 10/17/2020 10/18/2020

EPC-06/STR/357 Earthwork in excavation for Head Wall (HPC) HPC 90+575 BHS 10/18/2020 10/19/2020
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/359 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 92+563 RHS 10/18/2020 10/19/2020

EPC-06/STR/360 EGL checking and Pouring of concrete PCC M-15 below Head Wall (HPC) HPC 90+575 LHS 10/18/2020 10/19/2020

EPC-06/STR/361 Dismantling of existing HPC. HPC 90+575 BHS 10/18/2020 10/19/2020

EPC-06/STR/363 Layout checking and earthwork in excavation for Head Wall (HPC) HPC 90+795 BHS 10/19/2020 10/20/2020

EPC-06/STR/370 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 92+563 LHS 10/19/2020 10/20/2020

EPC-06/STR/374 EGL checking and Pouring of concrete PCC M-15 below Head Wall (HPC) HPC 75+841 LHS 10/19/2020 10/20/2020

EPC-06/STR/376 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 72+148 RHS 10/19/2020 10/20/2020

EPC-06/STR/377 EGL checking and Pouring of concrete PCC M-15 below Head Wall (HPC) HPC 90+575 RHS 10/19/2020 10/20/2020

EPC-06/STR/381 Shuttering checking and pouring of concrete PCC M-20 for Head wall final lift (HPC) HPC 72+148 LHS 10/20/2020 10/21/2020

EPC-06/STR/382 EGL checking and Pouring of concrete PCC M-15 below Head Wall (HPC) HPC 90+795 BHS 10/20/2020 10/21/2020

EPC-06/STR/383 Layout checking and earthwork in excavation for Head Wall (HPC) HPC 92+279 BHS 10/20/2020 10/21/2020 Not Done

EPC-06/STR/388 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 90+575 LHS 10/20/2020 10/21/2020

EPC-06/STR/392 Dismantling of existing HPC. HPC 90+795 BHS 10/21/2020 10/22/2020

EPC-06/STR/397 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 90+575 RHS 10/21/2020 10/22/2020

EPC-06/STR/398 Layout checking and earthwork in excavation for Head Wall (HPC) HPC 92+279 BHS 10/21/2020 10/22/2020

EPC-06/STR/401 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 90+795 LHS 10/21/2020 10/22/2020

EPC-06/STR/402 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 75+841 LHS 10/21/2020 10/22/2020

EPC-06/STR/404 Pouring of concrete RCC M-25 for Wall Top slab (Box Culvert) Box Culvert 79+671 BHS 10/22/2020 10/23/2020

EPC-06/STR/405 Dismantling of existing HPC. HPC 92+279 BHS 10/22/2020 10/23/2020

EPC-06/STR/407 Layout checking and earthwork in excavation for Head Wall (HPC) HPC 90+237 BHS 10/22/2020 10/23/2020

EPC-06/STR/412 EGL checking and Pouring of concrete PCC M-15 below Head Wall (HPC) HPC 92+279 BHS 10/23/2020 10/24/2020

EPC-06/STR/413 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 90+795 RHS 10/23/2020 10/24/2020

EPC-06/STR/414 Dismantling of existing HPC. HPC 90+237 BHS 10/23/2020 10/24/2020

EPC-06/STR/415 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift (HPC) HPC 75+841 RHS 10/23/2020 10/24/2020

EPC-06/STR/420 Earthwork in excavation for pipe laying HPC 90+795 BHS 10/24/2020 10/25/2020

EPC-06/STR/421 Laying of NP-4 Pipe 1200 mm dia HPC 90+795 BHS 10/24/2020 10/25/2020
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/421 Earthwork in excavation for pipe laying HPC 90+575 BHS 10/25/2020 10/26/2020

EPC-06/STR/422 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 92+279 BHS 10/25/2020 10/26/2020

EPC-06/STR/423 Earthwork in excavation for pipe laying HPC 92+563 BHS 10/25/2020 10/26/2020

EPC-06/STR/424 Shuttering checking and pouring of concrete PCC M-20 for Head wall final lift (HPC) HPC 75+841 RHS 10/25/2020 10/26/2020

EPC-06/STR/427 Laying of NP-4 Pipe 1200 mm dia HPC 90+575 BHS 10/25/2020 10/26/2020

EPC-06/STR/428 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 73+716 RHS 10/25/2020 10/26/2020

EPC-06/STR/431 EGL checking and Pouring of concrete PCC M-15 below Head Wall (HPC) HPC 90+237 BHS 10/25/2020 10/26/2020

EPC-06/STR/432 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift (HPC) HPC 90+795 BHS 10/25/2020 10/26/2020

EPC-06/STR/435 Laying of NP-4 Pipe 1200 mm dia HPC 92+563 BHS 10/26/2020 10/27/2020

EPC-06/STR/436 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 90+237 BHS 10/26/2020 10/27/2020

EPC-06/STR/439 Earthwork in excavation for pipe laying HPC 75+841 LHS 10/26/2020 10/27/2020

EPC-06/STR/440 Laying of NP-4 Pipe 1200 mm dia HPC 75+841 LHS 10/26/2020 10/27/2020

EPC-06/STR/441 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift (HPC) HPC 75+841 LHS 10/26/2020 10/27/2020

EPC-06/STR/443 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift (HPC) HPC 92+563 BHS 10/27/2020 10/28/2020

EPC-06/STR/445 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift (HPC) HPC 90+575 BHS 10/27/2020 10/28/2020

EPC-06/STR/447 Earthwork in excavation for pipe laying HPC 90+237 BHS 10/27/2020 10/28/2020

EPC-06/STR/448 Laying of NP-4 Pipe 1200 mm dia HPC 90+237 BHS 10/27/2020 10/28/2020

EPC-06/STR/449 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift (HPC) HPC 90+237 BHS 10/27/2020 10/28/2020

EPC-06/STR/450 Shuttering checking and pouring of concrete PCC M-20 for Head wall final lift (HPC) HPC 92+563 RHS 10/28/2020 10/29/2020 Not Done

EPC-06/STR/456 Earthwork in excavation for pipe laying HPC 72+148 RHS 10/28/2020 10/29/2020

EPC-06/STR/457 Laying of NP-4 Pipe 1200 mm dia HPC 72+148 RHS 10/28/2020 10/29/2020

EPC-06/STR/460 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift (HPC) HPC 73+716 LHS 10/28/2020 10/29/2020

EPC-06/STR/461 Shuttering checking and pouring of concrete PCC M-20 for Head wall 3rd lift (HPC) HPC 90+237 BHS 10/29/2020 10/30/2020

EPC-06/STR/465 Shuttering checking and pouring of concrete PCC M-20 for Head wall final lift (HPC) HPC 92+563 BHS 10/29/2020 10/30/2020

EPC-06/STR/466 Shuttering checking and pouring of concrete PCC M-20 for Head wall final lift (HPC) HPC 90+575 BHS 10/29/2020 10/30/2020

EPC-06/STR/467 Earthwork in excavation for pipe laying HPC 73+716 BHS 10/29/2020 10/30/2020
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/469 Laying of NP-4 Pipe 1200 mm dia HPC 73+716 BHS 10/29/2020 10/30/2020

EPC-06/STR/473 Earthwork in excavation for pipe laying HPC 92+279 BHS 10/29/2020 10/30/2020

EPC-06/STR/474 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift (HPC) HPC 73+716 BHS 10/29/2020 10/30/2020

EPC-06/STR/475 Laying of NP-4 Pipe 1200 mm dia HPC 92+279 BHS 10/29/2020 10/30/2020

EPC-06/STR/476 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift (HPC) HPC 92+279 BHS 10/29/2020 10/30/2020

EPC-06/STR/477 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift (HPC) HPC 72+148 RHS 10/29/2020 10/30/2020

EPC-06/STR/481 Shuttering checking and pouring of concrete PCC M-20 for Head wall 3rd lift (HPC) HPC 75+841 LHS 10/30/2020 10/31/2020

EPC-06/STR/482 Shuttering checking and pouring of concrete PCC M-20 for Head wall 3rd lift (HPC) HPC 72+148 RHS 10/30/2020 10/31/2020

EPC-06/STR/484 Shuttering checking and pouring of concrete PCC M-20 for Head wall final lift (HPC) HPC 92+279 BHS 10/30/2020 10/31/2020

EPC-06/STR/485 Shuttering checking and pouring of concrete PCC M-20 for Head wall final lift (HPC) HPC 90+795 BHS 10/30/2020 10/31/2020

EPC-06/STR/489 Shuttering checking and pouring of concrete PCC M-20 for Head wall 3rd lift (HPC) HPC 73+716 BHS 10/30/2020 10/31/2020

EPC-06/STR/492 Shuttering checking and pouring of concrete PCC M-20 for Head wall final lift HPC 72+110 RHS 10/31/2020 11/1/2020

EPC-06/STR/496 Dismantling of existing structure HPC 94+981 BHS 11/1/2020 11/2/2020

EPC-06/STR/529 Dismantling of existing structure HPC 95+720 BHS 11/4/2020 11/5/2020

RCC Cover
EPC-06/STR/540 Pouring of concrete RCC M-20 for Slab (RCC cover drain) 71+240 71+255 LHS 11/4/2020 11/5/2020
Drain
RCC Cover
EPC-06/STR/551 Pouring of concrete RCC M-20 for Slab (RCC cover drain) 71+220 71+240 LHS 11/5/2020 11/6/2020
Drain
RCC Cover
EPC-06/STR/557 Pouring of concrete RCC M-20 for Slab (RCC cover drain) 71+295 71+340 LHS 11/6/2020 11/7/2020
Drain
RCC Cover
EPC-06/STR/564 Pouring of concrete RCC M-20 for Slab (RCC cover drain) 71+340 71+384 LHS 11/8/2020 11/9/2020
Drain

EPC-06/STR/632 Dismantling of existing structure Box Culvert 79+979 BHS 11/21/2020 11/22/2020

RCC Cover
EPC-06/STR/704 Pouring of concrete RCC M-20 for Slab 71+255 71+295 LHS 11/28/2020 11/29/2020
Drain
RCC Cover
EPC-06/STR/716 Pouring of concrete RCC M-20 for Slab 71+384 71+448 LHS 11/29/2020 11/30/2020
Drain

EPC-06/STR/726 Shuttering checking and pouring of concrete PCC M-20 for Head wall 3rd lift HPC 94+981 RHS 11/30/2020 12/1/2020

EPC-06/STR/745 Shuttering checking and pouring of concrete PCC M-20 for Head wall 3rd lift HPC 95+720 RHS 12/2/2020 12/3/2020

RCC Cover
EPC-06/STR/754 Pouring of concrete RCC M-20 for Slab 71+498 71+530 LHS 12/3/2020 12/4/2020
Drain
RCC Cover
EPC-06/STR/759 Pouring of concrete RCC M-20 for Slab 71+448 71+498 LHS 12/4/2020 12/5/2020
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/760 Pouring of concrete RCC M-20 for Slab 71+530 71+550 LHS 12/4/2020 12/5/2020 Not Done
Drain

EPC-06/STR/761 Dismantling of existing structure HPC 66+509 BHS 12/4/2020 12/5/2020

RCC Cover
EPC-06/STR/765 Pouring of concrete RCC M-20 for Slab 71+530 71+550 LHS 12/5/2020 12/6/2020
Drain
RCC Cover
EPC-06/STR/771 Pouring of concrete RCC M-20 for Slab 71+550 71+580 LHS 12/6/2020 12/7/2020
Drain

EPC-06/STR/773 Dismantling of existing structure HPC 81+040 BHS 12/7/2020 12/8/2020

RCC Cover
EPC-06/STR/784 Pouring of concrete RCC M-20 for Slab 71+580 71+617 LHS 12/7/2020 12/8/2020
Drain
RCC Cover
EPC-06/STR/792 Pouring of concrete RCC M-20 for Slab 71+617 71+642 LHS 12/8/2020 12/9/2020
Drain
RCC Cover
EPC-06/STR/796 Pouring of concrete RCC M-20 for Slab 71+642 71+658 LHS 12/9/2020 12/10/2020
Drain
RCC Cover
EPC-06/STR/806 Pouring of concrete RCC M-20 for Slab 71+658 71+672 LHS 12/10/2020 12/11/2020
Drain
RCC Cover
EPC-06/STR/815 Pouring of concrete RCC M-20 for Slab 71+672 71+700 LHS 12/11/2020 12/12/2020
Drain

EPC-06/STR/853 Pouring of concrete RCC M-25 for top slab Box Culvert 79+979 BHS 12/16/2020 12/17/2020

EPC-06/STR/854 Dismantling of existing structure Box Culvert 73+592 BHS 12/16/2020 12/17/2020 Not Done

EPC-06/STR/867 Dismantling of existing structure Box Culvert 73+592 BHS 12/18/2020 12/19/2020

EPC-06/STR/875 Shuttering checking and pouring of concrete PCC M-20 for Head wall 3rd lift HPC 81+040 RHS 12/18/2020 12/19/2020

EPC-06/STR/894 Shuttering checking and pouring of concrete PCC M-20 for Head wall 3rd lift HPC 66+509 BHS 12/19/2020 12/20/2020

EPC-06/STR/902 Dismantling of existing structure HPC 86+378 12/21/2020 12/22/2020

RCC Cover
EPC-06/STR/906 Pouring of concrete RCC M-20 for Slab 74+020 74+120 LHS 12/21/2020 12/22/2020
Drain

EPC-06/STR/915 Dismantling of existing structure Box Culvert 73+080 BHS 12/22/2020 12/23/2020

EPC-06/STR/934 Dismantling of existing structure Box Culvert 71+022 BHS 12/23/2020 12/24/2020

RCC Cover
EPC-06/STR/941 Pouring of concrete RCC M-20 for Slab 74+120 74+170 LHS 12/24/2020 12/25/2020
Drain
RCC Cover
EPC-06/STR/952 Pouring of concrete RCC M-20 for Slab 73+770 73+820 LHS 12/25/2020 12/26/2020
Drain

EPC-06/STR/977 Dismantling of existing structure Box Culvert 70+312 BHS 12/26/2020 12/27/2020

RCC Cover
EPC-06/STR/983 Pouring of concrete RCC M-20 for Slab 73+820 73+880 LHS 12/27/2020 12/28/2020
Drain

EPC-06/STR/989 Dismantling of existing structure Box Culvert 70+729 BHS 12/27/2020 12/28/2020

RCC Cover
EPC-06/STR/995 Pouring of concrete RCC M-20 for Slab 73+880 73+950 LHS 12/28/2020 12/29/2020
Drain

EPC-06/STR/996 Pouring of concrete RCC M-30 for inner wall final lift of cell 2 with bracket - A1 side MNB 76+647 BHS 12/28/2020 12/29/2020 Not Done
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/1055 Pouring of concrete RCC M-20 for Slab 73+950 74+020 LHS 1/3/2021 1/4/2021
Drain

EPC-06/STR/1064 Pouring of concrete RCC M-30 for inner wall final lift of cell 2 with bracket - A1 side MNB 76+647 BHS 1/4/2021 1/5/2021

EPC-06/STR/1090 Pouring of concrete RCC M-30 for top slab of cell 1 & 2 MNB 76+647 BHS 1/7/2021 1/8/2021

EPC-06/STR/1109 Dismantling of existing structure Box Culvert 75+956 BHS 1/9/2021 1/10/2021

RCC Cover
EPC-06/STR/1115 Pouring of concrete RCC M-20 for Slab 75+700 75+750 LHS 1/10/2021 1/11/2021
Drain
RCC Cover
EPC-06/STR/1135 Pouring of concrete RCC M-20 for Slab 75+750 75+774 LHS 1/12/2021 1/13/2021
Drain
RCC Cover
EPC-06/STR/1139 Pouring of concrete RCC M-20 for Slab 75+774 75+798 LHS 1/14/2021 1/15/2021
Drain
RCC Cover
EPC-06/STR/1153 Pouring of concrete RCC M-20 for Slab 75+798 75+818 LHS 1/15/2021 1/16/2021
Drain
RCC Cover
EPC-06/STR/1172 Pouring of concrete RCC M-20 for Slab 75+830 75+875 LHS 1/16/2021 1/17/2021
Drain
RCC Cover
EPC-06/STR/1229 Pouring of concrete RCC M-20 for Slab 75+818 75+830 LHS 1/21/2021 1/22/2021
Drain

EPC-06/STR/1241 Pouring of concrete RCC M-25 for Top slab Box Culvert 71+022 BHS 1/24/2021 1/25/2021

RCC Cover
EPC-06/STR/1243 Pouring of concrete RCC M-20 for Slab 75+875 75+900 LHS 1/24/2021 1/25/2021
Drain

EPC-06/STR/1248 Shuttering checking and pouring of concrete PCC M-20 for Head wall final lift HPC 86+378 RHS 1/26/2021 1/27/2021

RCC Cover
EPC-06/STR/1249 Pouring of concrete RCC M-20 for Slab 71+240 71+350 RHS 1/26/2021 1/27/2021
Drain
RCC Cover
EPC-06/STR/1257 Pouring of concrete RCC M-20 for Slab 71+350 71+440 RHS 1/27/2021 1/28/2021
Drain

EPC-06/STR/1259 Pouring of concrete RCC M-25 for Top slab Box Culvert 75+956 BHS 1/28/2021 1/29/2021

RCC Cover
EPC-06/STR/1261 Pouring of concrete RCC M-20 for Slab 75+850 75+900 RHS 1/28/2021 1/29/2021
Drain

EPC-06/STR/1265 Pouring of concrete RCC M-25 for Top slab Box Culvert 70+312 BHS 1/29/2021 1/30/2021

EPC-06/STR/1267 Pouring of concrete RCC M-25 for Top slab Box Culvert 73+080 BHS 1/29/2021 1/30/2021

RCC Cover
EPC-06/STR/1269 Pouring of concrete RCC M-20 for Slab 75+800 75+850 RHS 1/29/2021 1/30/2021
Drain

EPC-06/STR/1272 Pouring of concrete RCC M-25 for Top slab Box Culvert 70+729 BHS 1/30/2021 1/31/2021

EPC-06/STR/1274 Pouring of concrete RCC M-25 for Top slab Box Culvert 73+592 BHS 1/30/2021 1/31/2021

RCC Cover
EPC-06/STR/1276 Pouring of concrete RCC M-20 for Slab 71+440 71+600 RHS 1/30/2021 1/31/2021
Drain

RCC Cover
EPC-06/STR/1329 Layout checking and earthwork in excavation 73+770 74+170 RHS 2/7/2021 2/8/2021
Drain
RCC Cover
EPC-06/STR/1337 EGL checking and Pouring of concrete PCC M-15 below Raft 73+770 73+950 RHS 2/9/2021 2/10/2021
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/1347 EGL checking and Pouring of concrete PCC M-15 below Raft 73+950 74+110 RHS 2/10/2021 2/11/2021
Drain
RCC Cover
EPC-06/STR/1348 Pouring of concrete RCC M-20 for raft 73+770 73+860 RHS 2/10/2021 2/11/2021
Drain
RCC Cover
EPC-06/STR/1355 EGL checking and Pouring of concrete PCC M-15 below Raft 74+110 74+170 RHS 2/11/2021 2/12/2021
Drain
RCC Cover
EPC-06/STR/1356 Pouring of concrete RCC M-20 for raft 73+860 73+960 RHS 2/11/2021 2/12/2021
Drain
RCC Cover
EPC-06/STR/1358 Pouring of concrete RCC M-20 for both walls 73+770 73+810 RHS 2/12/2021 2/13/2021
Drain
RCC Cover
EPC-06/STR/1359 Pouring of concrete RCC M-20 for raft 73+960 74+040 RHS 2/12/2021 2/13/2021
Drain

EPC-06/STR/1360 Layout marking and OGL checking for excavation Box Culvert 75+079 BHS 2/13/2021 2/14/2021

EPC-06/STR/1361 Dismantling of existing structure Box Culvert 75+079 BHS 2/13/2021 2/14/2021

EPC-06/STR/1362 Earthwork in excavation for Box Culvert Box Culvert 75+079 BHS 2/13/2021 2/14/2021

RCC Cover
EPC-06/STR/1363 Pouring of concrete RCC M-20 for raft 74+040 74+110 RHS 2/13/2021 2/14/2021
Drain
RCC Cover
EPC-06/STR/1364 Pouring of concrete RCC M-20 for both walls 73+810 73+860 RHS 2/13/2021 2/14/2021
Drain
RCC Cover
EPC-06/STR/1367 Pouring of concrete RCC M-20 for raft 74+110 74+170 RHS 2/14/2021 2/15/2021
Drain
RCC Cover
EPC-06/STR/1368 Pouring of concrete RCC M-20 for both walls 73+860 73+920 RHS 2/14/2021 2/15/2021
Drain

EPC-06/STR/1370 EGL checking and Boulder Soling below PCC Box Culvert 75+079 BHS 2/15/2021 2/16/2021

EPC-06/STR/1371 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 75+079 BHS 2/15/2021 2/16/2021

RCC Cover
EPC-06/STR/1378 Pouring of concrete RCC M-20 for both walls 73+920 73+960 RHS 2/15/2021 2/16/2021
Drain

EPC-06/STR/1381 Shuttering and reinforcement checking for raft Box Culvert 75+079 BHS 2/16/2021 2/17/2021

EPC-06/STR/1382 Pouring of concrete RCC M-25 for raft Box Culvert 75+079 BHS 2/16/2021 2/17/2021

RCC Cover
EPC-06/STR/1387 Pouring of concrete RCC M-20 for both walls 73+960 74+020 RHS 2/16/2021 2/17/2021
Drain
RCC Cover
EPC-06/STR/1389 Pouring of concrete RCC M-20 for both walls 74+020 74+070 RHS 2/17/2021 2/18/2021
Drain

EPC-06/STR/1391 Shuttering and reinforcement checking for bottom hunch and wall 1st lift Box Culvert 75+079 BHS 2/18/2021 2/19/2021

EPC-06/STR/1392 Pouring of concrete RCC M-30 for bottom hunch and wall 1st lift Box Culvert 75+079 BHS 2/18/2021 2/19/2021

RCC Cover
EPC-06/STR/1393 Pouring of concrete RCC M-20 for both walls 74+070 74+120 RHS 2/18/2021 2/19/2021
Drain
RCC Cover
EPC-06/STR/1394 Pouring of concrete RCC M-20 for both walls 74+120 74+170 RHS 2/18/2021 2/19/2021 Not Done
Drain
RCC Cover
EPC-06/STR/1401 Pouring of concrete RCC M-20 for both walls 74+120 74+170 RHS 2/19/2021 2/20/2021
Drain

EPC-06/STR/1407 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 75+079 BHS 2/20/2021 2/21/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/1408 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 75+079 BHS 2/20/2021 2/21/2021

RCC Cover
EPC-06/STR/1409 Pouring of concrete RCC M-20 for Slab 73+770 73+830 RHS 2/20/2021 2/21/2021
Drain

EPC-06/STR/1410 Layout marking and OGL checking for excavation Box Culvert 67+102 BHS 2/21/2021 2/22/2021

RCC Cover
EPC-06/STR/1412 Pouring of concrete RCC M-20 for Slab 73+830 73+880 RHS 2/21/2021 2/22/2021
Drain

EPC-06/STR/1416 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 75+079 BHS 2/22/2021 2/23/2021

EPC-06/STR/1417 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 75+079 BHS 2/22/2021 2/23/2021

EPC-06/STR/1418 Dismantling of existing structure Box Culvert 67+102 BHS 2/22/2021 2/23/2021

EPC-06/STR/1419 Earthwork in excavation for Box Culvert Box Culvert 67+102 BHS 2/22/2021 2/23/2021

RCC Cover
EPC-06/STR/1420 Pouring of concrete RCC M-20 for Slab 73+880 73+920 RHS 2/22/2021 2/23/2021
Drain

EPC-06/STR/1423 EGL checking and Boulder Soling below PCC Box Culvert 67+102 BHS 2/23/2021 2/24/2021

EPC-06/STR/1424 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 67+102 BHS 2/23/2021 2/24/2021

RCC Cover
EPC-06/STR/1425 Pouring of concrete RCC M-20 for Slab 73+920 73+970 RHS 2/23/2021 2/24/2021
Drain

EPC-06/STR/1429 Shuttering and reinforcement checking for top slab Box Culvert 75+079 BHS 2/24/2021 2/25/2021

EPC-06/STR/1430 Pouring of concrete RCC M-25 for top slab Box Culvert 75+079 BHS 2/24/2021 2/25/2021

RCC Cover
EPC-06/STR/1431 Pouring of concrete RCC M-20 for Slab 73+970 74+020 RHS 2/24/2021 2/25/2021
Drain

EPC-06/STR/1432 Shuttering and reinforcement checking for raft Box Culvert 67+102 BHS 2/24/2021 2/25/2021

EPC-06/STR/1433 Pouring of concrete RCC M-25 for raft Box Culvert 67+102 BHS 2/24/2021 2/25/2021

EPC-06/STR/1436 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 67+102 BHS 2/25/2021 2/26/2021

EPC-06/STR/1437 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 67+102 BHS 2/25/2021 2/26/2021

RCC Cover
EPC-06/STR/1438 Pouring of concrete RCC M-20 for Slab 74+020 74+070 RHS 2/25/2021 2/26/2021
Drain
RCC Cover
EPC-06/STR/1445 Pouring of concrete RCC M-20 for Slab 74+070 74+120 RHS 2/26/2021 2/27/2021
Drain
RCC Cover
EPC-06/STR/1449 Pouring of concrete RCC M-20 for Slab 74+120 74+170 RHS 2/27/2021 2/28/2021
Drain

EPC-06/STR/1450 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 67+102 BHS 2/27/2021 2/28/2021

EPC-06/STR/1451 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 67+102 BHS 2/27/2021 2/28/2021

EPC-06/STR/1452 Layout marking and OGL checking for excavation Box Culvert 66+283 BHS 2/27/2021 2/28/2021 Not Done

EPC-06/STR/1475 Layout marking and OGL checking for excavation Box Culvert 66+283 BHS 2/28/2021 3/1/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/1476 Dismantling of existing structure Box Culvert 66+283 BHS 2/28/2021 3/1/2021

EPC-06/STR/1477 Earthwork in excavation for Box Culvert Box Culvert 66+283 BHS 2/28/2021 3/1/2021

EPC-06/STR/1490 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 67+102 BHS 3/1/2021 3/2/2021

EPC-06/STR/1491 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 67+102 BHS 3/1/2021 3/2/2021

EPC-06/STR/1492 EGL checking and Boulder Soling below PCC Box Culvert 66+283 BHS 3/1/2021 3/2/2021

EPC-06/STR/1493 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 66+283 BHS 3/1/2021 3/2/2021

EPC-06/STR/1500 Shuttering and reinforcement checking for raft Box Culvert 66+283 BHS 3/2/2021 3/3/2021

EPC-06/STR/1501 Pouring of concrete RCC M-25 for raft Box Culvert 66+283 BHS 3/2/2021 3/3/2021

EPC-06/STR/1506 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 66+283 BHS 3/3/2021 3/4/2021

EPC-06/STR/1507 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 66+283 BHS 3/3/2021 3/4/2021

EPC-06/STR/1515 Shuttering and reinforcement checking for top slab Box Culvert 67+102 BHS 3/4/2021 3/5/2021

EPC-06/STR/1516 Pouring of concrete RCC M-25 for top slab Box Culvert 67+102 BHS 3/4/2021 3/5/2021

EPC-06/STR/1525 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 66+283 BHS 3/5/2021 3/6/2021

EPC-06/STR/1526 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 66+283 BHS 3/5/2021 3/6/2021

EPC-06/STR/1527 Layout marking and OGL checking for excavation Box Culvert 65+933 BHS 3/5/2021 3/6/2021

EPC-06/STR/1528 Dismantling of existing structure Box Culvert 65+933 BHS 3/5/2021 3/6/2021

EPC-06/STR/1529 Earthwork in excavation for Box Culvert Box Culvert 65+933 BHS 3/5/2021 3/6/2021

EPC-06/STR/1530 EGL checking and Boulder Soling below PCC Box Culvert 65+933 BHS 3/5/2021 3/6/2021 Not Done

EPC-06/STR/1536 EGL checking and Boulder Soling below PCC Box Culvert 65+933 BHS 3/6/2021 3/7/2021

EPC-06/STR/1537 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 65+933 BHS 3/6/2021 3/7/2021

EPC-06/STR/1545 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 66+283 BHS 3/7/2021 3/8/2021

EPC-06/STR/1546 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 66+283 BHS 3/7/2021 3/8/2021

EPC-06/STR/1547 Shuttering and reinforcement checking for raft Box Culvert 65+933 BHS 3/7/2021 3/8/2021

EPC-06/STR/1548 Pouring of concrete RCC M-25 for raft Box Culvert 65+933 BHS 3/7/2021 3/8/2021

EPC-06/STR/1556 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 65+933 BHS 3/8/2021 3/9/2021

EPC-06/STR/1557 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 65+933 BHS 3/8/2021 3/9/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/1558 Layout marking and OGL checking for excavation Box Culvert 64+491 BHS 3/8/2021 3/9/2021

EPC-06/STR/1559 Dismantling of existing structure Box Culvert 64+491 BHS 3/8/2021 3/9/2021

EPC-06/STR/1560 Earthwork in excavation for Box Culvert Box Culvert 64+491 BHS 3/8/2021 3/9/2021

RCC Cover
EPC-06/STR/1561 Layout checking and earthwork in excavation 88+880 89+270 LHS 3/8/2021 3/9/2021
Drain

EPC-06/STR/1570 Shuttering and reinforcement checking for top slab Box Culvert 66+283 BHS 3/9/2021 3/10/2021

EPC-06/STR/1571 Pouring of concrete RCC M-25 for top slab Box Culvert 66+283 BHS 3/9/2021 3/10/2021

EPC-06/STR/1572 EGL checking and Boulder Soling below PCC Box Culvert 64+491 BHS 3/9/2021 3/10/2021

EPC-06/STR/1573 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 64+491 BHS 3/9/2021 3/10/2021

EPC-06/STR/1574 Layout checking and earthwork in excavation for Head Wall HPC 47+455 BHS 3/9/2021 3/10/2021

EPC-06/STR/1575 Dismantling of existing HPC. HPC 47+455 BHS 3/9/2021 3/10/2021

EPC-06/STR/1585 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 65+933 BHS 3/10/2021 3/11/2021

EPC-06/STR/1586 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 65+933 BHS 3/10/2021 3/11/2021

EPC-06/STR/1587 Shuttering and reinforcement checking for raft Box Culvert 64+491 BHS 3/10/2021 3/11/2021

EPC-06/STR/1588 Pouring of concrete RCC M-25 for raft Box Culvert 64+491 BHS 3/10/2021 3/11/2021

EPC-06/STR/1589 EGL checking and Pouring of concrete PCC M-15 below Head Wall HPC 47+455 BHS 3/10/2021 3/11/2021

RCC Cover
EPC-06/STR/1590 EGL checking and Pouring of concrete PCC M-15 below Raft 88+880 89+050 LHS 3/10/2021 3/11/2021
Drain

EPC-06/STR/1596 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 64+491 BHS 3/11/2021 3/12/2021

EPC-06/STR/1597 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 64+491 BHS 3/11/2021 3/12/2021

EPC-06/STR/1598 Layout marking and OGL checking for excavation Box Culvert 81+469 BHS 3/11/2021 3/12/2021

EPC-06/STR/1599 Dismantling of existing structure Box Culvert 81+469 BHS 3/11/2021 3/12/2021

EPC-06/STR/1600 Earthwork in excavation for Box Culvert Box Culvert 81+469 BHS 3/11/2021 3/12/2021

EPC-06/STR/1601 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift HPC 47+455 BHS 3/11/2021 3/12/2021

RCC Cover
EPC-06/STR/1602 EGL checking and Pouring of concrete PCC M-15 below Raft 89+100 89+270 LHS 3/11/2021 3/12/2021
Drain

EPC-06/STR/1610 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 65+933 BHS 3/12/2021 3/13/2021

EPC-06/STR/1611 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 65+933 BHS 3/12/2021 3/13/2021

EPC-06/STR/1612 EGL checking and Boulder Soling below PCC Box Culvert 81+469 BHS 3/12/2021 3/13/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/1613 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 81+469 BHS 3/12/2021 3/13/2021

EPC-06/STR/1620 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 64+491 BHS 3/13/2021 3/14/2021

EPC-06/STR/1621 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 64+491 BHS 3/13/2021 3/14/2021

EPC-06/STR/1622 Shuttering and reinforcement checking for raft Box Culvert 81+469 BHS 3/13/2021 3/14/2021

EPC-06/STR/1623 Pouring of concrete RCC M-25 for raft Box Culvert 81+469 BHS 3/13/2021 3/14/2021

EPC-06/STR/1624 Earthwork in excavation for pipe laying HPC 47+455 BHS 3/13/2021 3/14/2021

EPC-06/STR/1625 Laying of NP-4 Pipe 1200 mm dia HPC 47+455 BHS 3/13/2021 3/14/2021

RCC Cover
EPC-06/STR/1626 Pouring of concrete RCC M-20 for raft 88+880 89+050 LHS 3/13/2021 3/14/2021
Drain

EPC-06/STR/1632 Shuttering and reinforcement checking for top slab Box Culvert 65+933 BHS 3/14/2021 3/15/2021

EPC-06/STR/1633 Pouring of concrete RCC M-25 for top slab Box Culvert 65+933 BHS 3/14/2021 3/15/2021

EPC-06/STR/1634 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 81+469 BHS 3/14/2021 3/15/2021

EPC-06/STR/1635 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 81+469 BHS 3/14/2021 3/15/2021

EPC-06/STR/1636 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift HPC 47+455 BHS 3/14/2021 3/15/2021

RCC Cover
EPC-06/STR/1637 Pouring of concrete RCC M-20 for raft 89+100 89+270 LHS 3/14/2021 3/15/2021
Drain

EPC-06/STR/1638 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 64+491 BHS 3/14/2021 3/15/2021 Not Done

EPC-06/STR/1645 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 64+491 BHS 3/15/2021 3/16/2021

EPC-06/STR/1646 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 64+491 BHS 3/15/2021 3/16/2021

RCC Cover
EPC-06/STR/1647 Shuttering and reinforcement checking for both walls 88+880 88+940 LHS 3/15/2021 3/16/2021
Drain
RCC Cover
EPC-06/STR/1648 Pouring of concrete RCC M-20 for both walls 88+880 88+940 LHS 3/15/2021 3/16/2021
Drain

EPC-06/STR/1655 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 81+469 BHS 3/16/2021 3/17/2021

EPC-06/STR/1656 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 81+469 BHS 3/16/2021 3/17/2021

EPC-06/STR/1657 Layout checking and earthwork in excavation for Head Wall HPC 46+667 BHS 3/16/2021 3/17/2021

EPC-06/STR/1658 Dismantling of existing HPC. HPC 46+667 BHS 3/16/2021 3/17/2021

EPC-06/STR/1659 Shuttering checking and pouring of concrete PCC M-20 for Head wall 3rd lift HPC 47+455 BHS 3/16/2021 3/17/2021

RCC Cover
EPC-06/STR/1660 Shuttering and reinforcement checking for both walls 88+940 89+020 LHS 3/16/2021 3/17/2021
Drain
RCC Cover
EPC-06/STR/1661 Pouring of concrete RCC M-20 for both walls 88+940 89+020 LHS 3/16/2021 3/17/2021
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/1670 Shuttering and reinforcement checking for top slab Box Culvert 64+491 BHS 3/17/2021 3/18/2021

EPC-06/STR/1671 Pouring of concrete RCC M-25 for top slab Box Culvert 64+491 BHS 3/17/2021 3/18/2021

EPC-06/STR/1672 EGL checking and Pouring of concrete PCC M-15 below Head Wall HPC 46+667 BHS 3/17/2021 3/18/2021

RCC Cover
EPC-06/STR/1673 Shuttering and reinforcement checking for both walls 89+020 89+100 LHS 3/17/2021 3/18/2021
Drain
RCC Cover
EPC-06/STR/1674 Pouring of concrete RCC M-20 for both walls 89+020 89+100 LHS 3/17/2021 3/18/2021
Drain

EPC-06/STR/1682 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 81+469 BHS 3/18/2021 3/19/2021

EPC-06/STR/1683 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 81+469 BHS 3/18/2021 3/19/2021

EPC-06/STR/1684 Layout marking and OGL checking for excavation Box Culvert 64+284 BHS 3/18/2021 3/19/2021

EPC-06/STR/1685 Dismantling of existing structure Box Culvert 64+284 BHS 3/18/2021 3/19/2021

EPC-06/STR/1686 Earthwork in excavation for Box Culvert Box Culvert 64+284 BHS 3/18/2021 3/19/2021

EPC-06/STR/1687 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift HPC 46+667 BHS 3/18/2021 3/19/2021

RCC Cover
EPC-06/STR/1688 Shuttering and reinforcement checking for both walls 89+100 89+150 LHS 3/18/2021 3/19/2021
Drain
RCC Cover
EPC-06/STR/1689 Pouring of concrete RCC M-20 for both walls 89+100 89+150 LHS 3/18/2021 3/19/2021
Drain

EPC-06/STR/1695 EGL checking and Boulder Soling below PCC Box Culvert 64+284 BHS 3/19/2021 3/20/2021

EPC-06/STR/1696 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 64+284 BHS 3/19/2021 3/20/2021

RCC Cover
EPC-06/STR/1697 Shuttering and reinforcement checking for both walls 89+150 89+210 LHS 3/19/2021 3/20/2021
Drain
RCC Cover
EPC-06/STR/1698 Pouring of concrete RCC M-20 for both walls 89+150 89+210 LHS 3/19/2021 3/20/2021
Drain

EPC-06/STR/1699 Pouring of concrete RCC M-25 for top slab Box Culvert 81+469 BHS 3/19/2021 3/20/2021 Not Done

EPC-06/STR/1705 Shuttering and reinforcement checking for top slab Box Culvert 81+469 BHS 3/20/2021 3/21/2021

EPC-06/STR/1706 Pouring of concrete RCC M-25 for top slab Box Culvert 81+469 BHS 3/20/2021 3/21/2021

EPC-06/STR/1707 Shuttering and reinforcement checking for raft Box Culvert 64+284 BHS 3/20/2021 3/21/2021

EPC-06/STR/1708 Pouring of concrete RCC M-25 for raft Box Culvert 64+284 BHS 3/20/2021 3/21/2021

EPC-06/STR/1709 Earthwork in excavation for pipe laying HPC 46+667 BHS 3/20/2021 3/21/2021

EPC-06/STR/1710 Laying of NP-4 Pipe 1200 mm dia HPC 46+667 BHS 3/20/2021 3/21/2021

RCC Cover
EPC-06/STR/1711 Shuttering and reinforcement checking for both walls 89+210 89+270 LHS 3/20/2021 3/21/2021
Drain
RCC Cover
EPC-06/STR/1712 Pouring of concrete RCC M-20 for both walls 89+210 89+270 LHS 3/20/2021 3/21/2021
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/1718 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 64+284 BHS 3/21/2021 3/22/2021

EPC-06/STR/1719 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 64+284 BHS 3/21/2021 3/22/2021

EPC-06/STR/1720 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift HPC 46+667 BHS 3/21/2021 3/22/2021

RCC Cover
EPC-06/STR/1721 Shuttering and reinforcement checking for Slab 88+880 88+950 LHS 3/21/2021 3/22/2021
Drain
RCC Cover
EPC-06/STR/1722 Pouring of concrete RCC M-20 for Slab 88+880 88+950 LHS 3/21/2021 3/22/2021
Drain
RCC Cover
EPC-06/STR/1728 Shuttering and reinforcement checking for Slab 88+950 89+020 LHS 3/22/2021 3/23/2021
Drain
RCC Cover
EPC-06/STR/1729 Pouring of concrete RCC M-20 for Slab 88+950 89+020 LHS 3/22/2021 3/23/2021
Drain

EPC-06/STR/1734 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 64+284 BHS 3/23/2021 3/24/2021

EPC-06/STR/1735 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 64+284 BHS 3/23/2021 3/24/2021

EPC-06/STR/1736 Shuttering checking and pouring of concrete PCC M-20 for Head wall 3rd lift HPC 46+667 BHS 3/23/2021 3/24/2021

RCC Cover
EPC-06/STR/1742 Shuttering and reinforcement checking for Slab 89+020 89+080 LHS 3/24/2021 3/25/2021
Drain
RCC Cover
EPC-06/STR/1743 Pouring of concrete RCC M-20 for Slab 89+020 89+080 LHS 3/24/2021 3/25/2021
Drain

EPC-06/STR/1746 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 64+284 BHS 3/24/2021 3/25/2021

EPC-06/STR/1747 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 64+284 BHS 3/24/2021 3/25/2021

RCC Cover
EPC-06/STR/1748 Shuttering and reinforcement checking for Slab 89+080 89+150 LHS 3/24/2021 3/25/2021
Drain
RCC Cover
EPC-06/STR/1749 Pouring of concrete RCC M-20 for Slab 89+080 89+150 LHS 3/24/2021 3/25/2021
Drain
RCC Cover
EPC-06/STR/1750 Pouring of concrete RCC M-20 for Slab 89+150 89+200 LHS 3/24/2021 3/25/2021 Not Done
Drain
RCC Cover
EPC-06/STR/1755 Shuttering and reinforcement checking for Slab 89+150 89+200 LHS 3/25/2021 3/26/2021
Drain
RCC Cover
EPC-06/STR/1756 Pouring of concrete RCC M-20 for Slab 89+150 89+200 LHS 3/25/2021 3/26/2021
Drain

EPC-06/STR/1761 Shuttering and reinforcement checking for top slab Box Culvert 64+284 BHS 3/25/2021 3/26/2021

EPC-06/STR/1762 Pouring of concrete RCC M-25 for top slab Box Culvert 64+284 BHS 3/25/2021 3/26/2021

RCC Cover
EPC-06/STR/1763 Shuttering and reinforcement checking for Slab 89+200 89+270 LHS 3/25/2021 3/26/2021
Drain
RCC Cover
EPC-06/STR/1764 Pouring of concrete RCC M-20 for Slab 89+200 89+270 LHS 3/25/2021 3/26/2021
Drain

EPC-06/STR/1835 Layout marking and OGL checking for excavation Box Culvert 63+099 BHS 4/3/2021 4/4/2021 Not Done

EPC-06/STR/1841 Layout marking and OGL checking for excavation Box Culvert 63+099 BHS 4/4/2021 4/5/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/1842 Dismantling of existing structure Box Culvert 63+099 BHS 4/4/2021 4/5/2021

EPC-06/STR/1848 Earthwork in excavation for Box Culvert Box Culvert 63+099 BHS 4/5/2021 4/6/2021

EPC-06/STR/1849 Layout marking and OGL checking for excavation Box Culvert 63+535 BHS 4/5/2021 4/6/2021

EPC-06/STR/1850 Dismantling of existing structure Box Culvert 63+535 BHS 4/5/2021 4/6/2021

EPC-06/STR/1856 EGL checking and Boulder Soling below PCC Box Culvert 63+099 BHS 4/6/2021 4/7/2021

EPC-06/STR/1857 Earthwork in excavation for Box Culvert Box Culvert 63+535 BHS 4/6/2021 4/7/2021

EPC-06/STR/1863 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 63+099 BHS 4/7/2021 4/8/2021

EPC-06/STR/1864 EGL checking and Boulder Soling below PCC Box Culvert 63+535 BHS 4/7/2021 4/8/2021

EPC-06/STR/1870 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 63+535 BHS 4/8/2021 4/9/2021

EPC-06/STR/1871 Layout marking and OGL checking for excavation MNB 64+941 BHS 4/8/2021 4/9/2021

EPC-06/STR/1872 Dismantling of existing structure MNB 64+941 BHS 4/8/2021 4/9/2021

EPC-06/STR/1878 Shuttering and reinforcement checking for raft Box Culvert 63+099 BHS 4/9/2021 4/10/2021

EPC-06/STR/1879 Pouring of concrete RCC M-25 for raft Box Culvert 63+099 BHS 4/9/2021 4/10/2021

EPC-06/STR/1885 Layout marking and OGL checking for excavation Box Culvert 62+758 BHS 4/10/2021 4/11/2021

EPC-06/STR/1886 Dismantling of existing structure Box Culvert 62+758 BHS 4/10/2021 4/11/2021

EPC-06/STR/1887 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 63+099 BHS 4/10/2021 4/11/2021

EPC-06/STR/1888 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 63+099 BHS 4/10/2021 4/11/2021

EPC-06/STR/1889 Shuttering and reinforcement checking for raft Box Culvert 63+535 BHS 4/10/2021 4/11/2021

EPC-06/STR/1890 Pouring of concrete RCC M-25 for raft Box Culvert 63+535 BHS 4/10/2021 4/11/2021

EPC-06/STR/1891 Earthwork in excavation for MNB MNB 64+941 BHS 4/10/2021 4/11/2021

EPC-06/STR/1897 Earthwork in excavation for Box Culvert Box Culvert 62+758 BHS 4/11/2021 4/12/2021

EPC-06/STR/1898 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 63+535 BHS 4/11/2021 4/12/2021

EPC-06/STR/1899 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 63+535 BHS 4/11/2021 4/12/2021

EPC-06/STR/1900 EGL checking and Boulder Soling below PCC MNB 64+941 BHS 4/11/2021 4/12/2021

EPC-06/STR/1906 EGL checking and Boulder Soling below PCC Box Culvert 62+758 BHS 4/12/2021 4/13/2021

EPC-06/STR/1907 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 63+099 BHS 4/12/2021 4/13/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/1908 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 63+099 BHS 4/12/2021 4/13/2021

EPC-06/STR/1909 Pouring of concrete PCC M-15 below raft with Cut off wall MNB 64+941 BHS 4/12/2021 4/13/2021

EPC-06/STR/1915 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 62+758 BHS 4/13/2021 4/14/2021

EPC-06/STR/1916 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 63+099 BHS 4/13/2021 4/14/2021

EPC-06/STR/1917 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 63+099 BHS 4/13/2021 4/14/2021

EPC-06/STR/1918 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 63+535 BHS 4/13/2021 4/14/2021

EPC-06/STR/1919 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 63+535 BHS 4/13/2021 4/14/2021

EPC-06/STR/1925 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 63+535 BHS 4/14/2021 4/15/2021

EPC-06/STR/1926 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 63+535 BHS 4/14/2021 4/15/2021

EPC-06/STR/1932 Shuttering and reinforcement checking for raft Box Culvert 62+758 BHS 4/15/2021 4/16/2021

EPC-06/STR/1933 Pouring of concrete RCC M-25 for raft Box Culvert 62+758 BHS 4/15/2021 4/16/2021

EPC-06/STR/1939 Layout marking and OGL checking for excavation Box Culvert 62+528 BHS 4/16/2021 4/17/2021

EPC-06/STR/1940 Dismantling of existing structure Box Culvert 62+528 BHS 4/16/2021 4/17/2021

EPC-06/STR/1941 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 62+758 BHS 4/16/2021 4/17/2021

EPC-06/STR/1942 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 62+758 BHS 4/16/2021 4/17/2021

EPC-06/STR/1943 Shuttering and reinforcement checking for top slab Box Culvert 63+099 BHS 4/16/2021 4/17/2021

EPC-06/STR/1944 Pouring of concrete RCC M-25 for top slab Box Culvert 63+099 BHS 4/16/2021 4/17/2021

EPC-06/STR/1945 Shuttering and reinforcement checking for Raft of cell 1 & 2 MNB 64+941 BHS 4/16/2021 4/17/2021

EPC-06/STR/1946 Pouring of concrete RCC M-30 for Raft of cell 1 & 2 MNB 64+941 BHS 4/16/2021 4/17/2021

EPC-06/STR/1952 Earthwork in excavation for Box Culvert Box Culvert 62+528 BHS 4/17/2021 4/18/2021

EPC-06/STR/1953 Shuttering and reinforcement checking for top slab Box Culvert 63+535 BHS 4/17/2021 4/18/2021

EPC-06/STR/1954 Pouring of concrete RCC M-25 for top slab Box Culvert 63+535 BHS 4/17/2021 4/18/2021

EPC-06/STR/1955 Layout marking and OGL checking for excavation Box Culvert 60+649 BHS 4/17/2021 4/18/2021

EPC-06/STR/1956 Dismantling of existing structure Box Culvert 60+649 BHS 4/17/2021 4/18/2021

EPC-06/STR/1960 EGL checking and Boulder Soling below PCC Box Culvert 62+528 BHS 4/18/2021 4/19/2021

EPC-06/STR/1961 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 62+758 BHS 4/18/2021 4/19/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/1962 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 62+758 BHS 4/18/2021 4/19/2021

EPC-06/STR/1963 Shuttering and reinforcement checking for bottom hunch of cell 1 & 2 MNB 64+941 BHS 4/18/2021 4/19/2021

EPC-06/STR/1964 Pouring of concrete RCC M-30 for bottom hunch of cell 1 & 2 MNB 64+941 BHS 4/18/2021 4/19/2021

EPC-06/STR/1965 Earthwork in excavation for Box Culvert Box Culvert 60+649 BHS 4/18/2021 4/19/2021

EPC-06/STR/1970 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 62+528 BHS 4/19/2021 4/20/2021

EPC-06/STR/1971 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 62+758 BHS 4/19/2021 4/20/2021

EPC-06/STR/1972 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 62+758 BHS 4/19/2021 4/20/2021

EPC-06/STR/1973 EGL checking and Boulder Soling below PCC Box Culvert 60+649 BHS 4/19/2021 4/20/2021

EPC-06/STR/1978 Shuttering and reinforcement checking for outer wall 1st lift of cell 1-A1 Side MNB 64+941 BHS 4/20/2021 4/21/2021

EPC-06/STR/1979 Pouring of concrete RCC M-30 for outer wall 1st lift of cell 1-A1 side MNB 64+941 BHS 4/20/2021 4/21/2021

EPC-06/STR/1980 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 60+649 BHS 4/20/2021 4/21/2021

EPC-06/STR/1985 Shuttering and reinforcement checking for raft Box Culvert 62+528 BHS 4/21/2021 4/22/2021

EPC-06/STR/1986 Pouring of concrete RCC M-25 for raft Box Culvert 62+528 BHS 4/21/2021 4/22/2021

Shuttering and reinforcement checking for outer wall 2nd lift with bracket of cell 1 -
EPC-06/STR/1987 MNB 64+941 BHS 4/21/2021 4/22/2021
A1 Side

EPC-06/STR/1988 Pouring of concrete RCC M-30 for outer wall 2nd lift with bracket of cell 1-A1 side MNB 64+941 BHS 4/21/2021 4/22/2021

EPC-06/STR/1994 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 62+528 BHS 4/22/2021 4/23/2021

EPC-06/STR/1995 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 62+528 BHS 4/22/2021 4/23/2021

EPC-06/STR/1996 Shuttering and reinforcement checking for top slab Box Culvert 62+758 BHS 4/22/2021 4/23/2021

EPC-06/STR/1997 Pouring of concrete RCC M-25 for top slab Box Culvert 62+758 BHS 4/22/2021 4/23/2021

EPC-06/STR/1998 Shuttering and reinforcement checking for intermediate wall 1st lift MNB 64+941 BHS 4/22/2021 4/23/2021

EPC-06/STR/1999 Pouring of concrete RCC M-30 for outer intermediate wall 1st lift MNB 64+941 BHS 4/22/2021 4/23/2021

EPC-06/STR/2000 Shuttering and reinforcement checking for raft Box Culvert 60+649 BHS 4/22/2021 4/23/2021

EPC-06/STR/2001 Pouring of concrete RCC M-25 for raft Box Culvert 60+649 BHS 4/22/2021 4/23/2021

EPC-06/STR/2006 Shuttering and reinforcement checking for intermediate wall 2nd lift MNB 64+941 BHS 4/23/2021 4/24/2021

EPC-06/STR/2007 Pouring of concrete RCC M-30 for outer intermediate wall 2nd lift MNB 64+941 BHS 4/23/2021 4/24/2021

EPC-06/STR/2008 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 60+649 BHS 4/23/2021 4/24/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/2009 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 60+649 BHS 4/23/2021 4/24/2021

EPC-06/STR/2013 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 62+528 BHS 4/24/2021 4/25/2021

EPC-06/STR/2014 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 62+528 BHS 4/24/2021 4/25/2021

EPC-06/STR/2015 Shuttering and reinforcement checking for outer wall 1st lift of cell 2-A2 Side MNB 64+941 BHS 4/24/2021 4/25/2021

EPC-06/STR/2016 Pouring of concrete RCC M-30 for outer wall 1st lift of cell 2-A2 Side MNB 64+941 BHS 4/24/2021 4/25/2021

EPC-06/STR/2022 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 62+528 BHS 4/25/2021 4/26/2021

EPC-06/STR/2023 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 62+528 BHS 4/25/2021 4/26/2021

Shuttering and reinforcement checking for outer wall 2nd lift with bracket of cell 2-A2
EPC-06/STR/2024 MNB 64+941 BHS 4/25/2021 4/26/2021
Side

EPC-06/STR/2025 Pouring of concrete RCC M-30 for outer wall 2nd lift with bracket of cell 2-A2 Side MNB 64+941 BHS 4/25/2021 4/26/2021

EPC-06/STR/2026 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 60+649 BHS 4/25/2021 4/26/2021

EPC-06/STR/2027 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 60+649 BHS 4/25/2021 4/26/2021

EPC-06/STR/2033 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 60+649 BHS 4/26/2021 4/27/2021

EPC-06/STR/2034 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 60+649 BHS 4/26/2021 4/27/2021

EPC-06/STR/2043 Shuttering and reinforcement checking for top slab Box Culvert 62+528 BHS 4/28/2021 4/29/2021

EPC-06/STR/2044 Pouring of concrete RCC M-25 for top slab Box Culvert 62+528 BHS 4/28/2021 4/29/2021

EPC-06/STR/2050 Shuttering and reinforcement checking for Top slab (Cell1 & Cell 2) MNB 64+941 BHS 4/29/2021 4/30/2021 Not Done

EPC-06/STR/2051 Pouring of concrete RCC M-30 for for Top slab (Cell1 & Cell 2) MNB 64+941 BHS 4/29/2021 4/30/2021 Not Done

EPC-06/STR/2052 Shuttering and reinforcement checking for top slab Box Culvert 60+649 BHS 4/29/2021 4/30/2021

EPC-06/STR/2053 Pouring of concrete RCC M-25 for top slab Box Culvert 60+649 BHS 4/29/2021 4/30/2021

2150

2424

EPC-06/STR/2002 Layout marking and OGL checking for excavation Box Culvert 59+042 BHS 4/22/2021 4/23/2021

EPC-06/STR/2003 Dismantling of existing structure Box Culvert 59+042 BHS 4/22/2021 4/23/2021

EPC-06/STR/2010 Earthwork in excavation for Box Culvert Box Culvert 59+042 BHS 4/23/2021 4/24/2021

EPC-06/STR/2017 EGL checking and Boulder Soling below PCC Box Culvert 59+042 BHS 4/24/2021 4/25/2021

EPC-06/STR/2028 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 59+042 BHS 4/25/2021 4/26/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/2035 EGL checking and Pouring of concrete PCC M-15 below Raft 86+445 86+645 LHS 4/26/2021 4/27/2021
Drain

EPC-06/STR/2038 Shuttering and reinforcement checking for raft Box Culvert 59+042 BHS 4/27/2021 4/28/2021

EPC-06/STR/2039 Pouring of concrete RCC M-25 for raft Box Culvert 59+042 BHS 4/27/2021 4/28/2021

EPC-06/STR/2045 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 59+042 BHS 4/28/2021 4/29/2021

EPC-06/STR/2046 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 59+042 BHS 4/28/2021 4/29/2021

RCC Cover
EPC-06/STR/2047 Pouring of concrete RCC M-20 for raft 86+540 86+645 LHS 4/28/2021 4/29/2021
Drain

EPC-06/STR/2054 Layout marking and OGL checking for excavation Box Culvert 59+683 BHS 4/29/2021 4/30/2021

EPC-06/STR/2055 Dismantling of existing structure Box Culvert 59+683 BHS 4/29/2021 4/30/2021

EPC-06/STR/2080 Shuttering and reinforcement checking for Top slab (Cell1 & Cell 2) MNB 64+941 BHS 4/30/2021 5/1/2021

EPC-06/STR/2081 Pouring of concrete RCC M-30 for for Top slab (Cell1 & Cell 2) MNB 64+941 BHS 4/30/2021 5/1/2021

EPC-06/STR/2082 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 59+042 BHS 4/30/2021 5/1/2021

EPC-06/STR/2083 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 59+042 BHS 4/30/2021 5/1/2021

EPC-06/STR/2084 Earthwork in excavation for Box Culvert Box Culvert 59+683 BHS 4/30/2021 5/1/2021

RCC Cover
EPC-06/STR/2085 Pouring of concrete RCC M-20 for raft 86+445 86+540 LHS 4/30/2021 5/1/2021
Drain
RCC Cover
EPC-06/STR/2086 Shuttering and reinforcement checking for both walls 86+540 86+645 LHS 4/30/2021 5/1/2021
Drain
RCC Cover
EPC-06/STR/2087 Pouring of concrete RCC M-20 for both walls 86+540 86+645 LHS 4/30/2021 5/1/2021
Drain

EPC-06/STR/2094 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 59+042 BHS 5/1/2021 5/2/2021

EPC-06/STR/2095 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 59+042 BHS 5/1/2021 5/2/2021

EPC-06/STR/2096 EGL checking and Boulder Soling below PCC Box Culvert 59+683 BHS 5/1/2021 5/2/2021

EPC-06/STR/2106 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 59+683 BHS 5/2/2021 5/3/2021

RCC Cover
EPC-06/STR/2107 Shuttering and reinforcement checking for both walls 86+445 86+540 LHS 5/2/2021 5/3/2021
Drain
RCC Cover
EPC-06/STR/2108 Pouring of concrete RCC M-20 for both walls 86+445 86+540 LHS 5/2/2021 5/3/2021
Drain
RCC Cover
EPC-06/STR/2116 Shuttering and reinforcement checking for Slab 86+540 86+645 LHS 5/3/2021 5/4/2021
Drain
RCC Cover
EPC-06/STR/2117 Pouring of concrete RCC M-20 for Slab 86+540 86+645 LHS 5/3/2021 5/4/2021
Drain

EPC-06/STR/2126 Shuttering and reinforcement checking for top slab Box Culvert 59+042 BHS 5/4/2021 5/5/2021

EPC-06/STR/2127 Pouring of concrete RCC M-25 for top slab Box Culvert 59+042 BHS 5/4/2021 5/5/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/2128 Shuttering and reinforcement checking for raft Box Culvert 59+683 BHS 5/4/2021 5/5/2021

EPC-06/STR/2129 Pouring of concrete RCC M-25 for raft Box Culvert 59+683 BHS 5/4/2021 5/5/2021

EPC-06/STR/2130 Layout marking and OGL checking for excavation Box Culvert 59+864 BHS 5/4/2021 5/5/2021

EPC-06/STR/2131 Dismantling of existing structure Box Culvert 59+864 BHS 5/4/2021 5/5/2021

EPC-06/STR/2141 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 59+683 BHS 5/5/2021 5/6/2021

EPC-06/STR/2142 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 59+683 BHS 5/5/2021 5/6/2021

EPC-06/STR/2143 Earthwork in excavation for Box Culvert Box Culvert 59+864 BHS 5/5/2021 5/6/2021

RCC Cover
EPC-06/STR/2144 Shuttering and reinforcement checking for Slab 86+445 86+540 LHS 5/5/2021 5/6/2021
Drain
RCC Cover
EPC-06/STR/2145 Pouring of concrete RCC M-20 for Slab 86+445 86+540 LHS 5/5/2021 5/6/2021
Drain
RCC Cover
EPC-06/STR/2146 EGL checking and Pouring of concrete PCC M-15 below Raft 86+445 86+645 RHS 5/5/2021 5/6/2021
Drain

EPC-06/STR/2153 EGL checking and Boulder Soling below PCC Box Culvert 59+864 BHS 5/6/2021 5/7/2021

EPC-06/STR/2163 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 59+683 BHS 5/7/2021 5/8/2021

EPC-06/STR/2164 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 59+683 BHS 5/7/2021 5/8/2021

EPC-06/STR/2165 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 59+864 BHS 5/7/2021 5/8/2021

RCC Cover
EPC-06/STR/2166 Pouring of concrete RCC M-20 for raft 86+560 86+645 RHS 5/7/2021 5/8/2021
Drain

EPC-06/STR/2175 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 59+683 BHS 5/8/2021 5/9/2021

EPC-06/STR/2176 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 59+683 BHS 5/8/2021 5/9/2021

RCC Cover
EPC-06/STR/2177 Pouring of concrete RCC M-20 for raft 86+445 86+560 RHS 5/8/2021 5/9/2021
Drain

EPC-06/STR/2186 Shuttering and reinforcement checking for raft Box Culvert 59+864 BHS 5/9/2021 5/10/2021

EPC-06/STR/2187 Pouring of concrete RCC M-25 for raft Box Culvert 59+864 BHS 5/9/2021 5/10/2021

EPC-06/STR/2188 Layout marking and OGL checking for excavation Box Culvert 68+147 BHS 5/9/2021 5/10/2021

EPC-06/STR/2189 Dismantling of existing structure Box Culvert 68+147 BHS 5/9/2021 5/10/2021

RCC Cover
EPC-06/STR/2190 Shuttering and reinforcement checking for both walls 86+560 86+645 RHS 5/9/2021 5/10/2021
Drain
RCC Cover
EPC-06/STR/2191 Pouring of concrete RCC M-20 for both walls 86+560 86+645 RHS 5/9/2021 5/10/2021
Drain

EPC-06/STR/2199 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 59+864 BHS 5/10/2021 5/11/2021

EPC-06/STR/2200 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 59+864 BHS 5/10/2021 5/11/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/2201 Earthwork in excavation for Box Culvert Box Culvert 68+147 BHS 5/10/2021 5/11/2021

RCC Cover
EPC-06/STR/2202 Shuttering and reinforcement checking for both walls 86+445 86+560 RHS 5/10/2021 5/11/2021
Drain
RCC Cover
EPC-06/STR/2203 Pouring of concrete RCC M-20 for both walls 86+445 86+560 RHS 5/10/2021 5/11/2021
Drain

EPC-06/STR/2211 Shuttering and reinforcement checking for top slab Box Culvert 59+683 BHS 5/11/2021 5/12/2021

EPC-06/STR/2212 Pouring of concrete RCC M-25 for top slab Box Culvert 59+683 BHS 5/11/2021 5/12/2021

EPC-06/STR/2213 EGL checking and Boulder Soling below PCC Box Culvert 68+147 BHS 5/11/2021 5/12/2021

EPC-06/STR/2223 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 59+864 BHS 5/12/2021 5/13/2021

EPC-06/STR/2224 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 59+864 BHS 5/12/2021 5/13/2021

EPC-06/STR/2225 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 68+147 BHS 5/12/2021 5/13/2021

EPC-06/STR/2226 Layout checking and earthwork in excavation for Head Wall HPC 103+788 BHS 5/12/2021 5/13/2021

EPC-06/STR/2227 Dismantling of existing HPC. HPC 103+788 BHS 5/12/2021 5/13/2021

RCC Cover
EPC-06/STR/2228 Shuttering and reinforcement checking for Slab 86+560 86+645 RHS 5/12/2021 5/13/2021
Drain
RCC Cover
EPC-06/STR/2229 Pouring of concrete RCC M-20 for Slab 86+560 86+645 RHS 5/12/2021 5/13/2021
Drain

EPC-06/STR/2235 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 59+864 BHS 5/13/2021 5/14/2021

EPC-06/STR/2236 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 59+864 BHS 5/13/2021 5/14/2021

EPC-06/STR/2237 EGL checking and Pouring of concrete PCC M-15 below Head Wall HPC 103+788 BHS 5/13/2021 5/14/2021

RCC Cover
EPC-06/STR/2238 Shuttering and reinforcement checking for Slab 86+445 86+560 RHS 5/13/2021 5/14/2021
Drain
RCC Cover
EPC-06/STR/2239 Pouring of concrete RCC M-20 for Slab 86+445 86+560 RHS 5/13/2021 5/14/2021
Drain
RCC Cover
EPC-06/STR/2240 EGL checking and Pouring of concrete PCC M-15 below Raft 68+550 68+700 LHS 5/13/2021 5/14/2021
Drain

EPC-06/STR/2246 Shuttering and reinforcement checking for raft Box Culvert 68+147 BHS 5/14/2021 5/15/2021

EPC-06/STR/2247 Pouring of concrete RCC M-25 for raft Box Culvert 68+147 BHS 5/14/2021 5/15/2021

EPC-06/STR/2248 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift HPC 103+788 BHS 5/14/2021 5/15/2021

EPC-06/STR/2257 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 68+147 BHS 5/15/2021 5/16/2021

EPC-06/STR/2258 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 68+147 BHS 5/15/2021 5/16/2021

EPC-06/STR/2259 Layout marking and OGL checking for excavation Box Culvert 06+385 BHS 5/15/2021 5/16/2021

EPC-06/STR/2260 Dismantling of existing structure Box Culvert 06+385 BHS 5/15/2021 5/16/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/2261 Pouring of concrete RCC M-20 for raft 68+550 68+700 LHS 5/15/2021 5/16/2021
Drain

EPC-06/STR/2270 Shuttering and reinforcement checking for top slab Box Culvert 59+864 BHS 5/16/2021 5/17/2021

EPC-06/STR/2271 Pouring of concrete RCC M-25 for top slab Box Culvert 59+864 BHS 5/16/2021 5/17/2021

EPC-06/STR/2272 Earthwork in excavation for Box Culvert Box Culvert 06+385 BHS 5/16/2021 5/17/2021

EPC-06/STR/2273 Earthwork in excavation for pipe laying HPC 103+788 BHS 5/16/2021 5/17/2021

EPC-06/STR/2274 Laying of NP-4 Pipe 1200 mm dia HPC 103+788 BHS 5/16/2021 5/17/2021

RCC Cover
EPC-06/STR/2275 EGL checking and Pouring of concrete PCC M-15 below Raft 68+000 68+300 LHS 5/16/2021 5/17/2021
Drain
RCC Cover
EPC-06/STR/2276 Pouring of concrete RCC M-20 for raft 68+440 68+550 LHS 5/16/2021 5/17/2021
Drain

EPC-06/STR/2282 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 68+147 BHS 5/17/2021 5/18/2021

EPC-06/STR/2283 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 68+147 BHS 5/17/2021 5/18/2021

EPC-06/STR/2284 EGL checking and Boulder Soling below PCC Box Culvert 06+385 BHS 5/17/2021 5/18/2021

EPC-06/STR/2285 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift HPC 103+788 BHS 5/17/2021 5/18/2021

RCC Cover
EPC-06/STR/2286 Shuttering and reinforcement checking for both walls 68+550 68+700 LHS 5/17/2021 5/18/2021
Drain
RCC Cover
EPC-06/STR/2287 Pouring of concrete RCC M-20 for both walls 68+550 68+700 LHS 5/17/2021 5/18/2021
Drain

EPC-06/STR/2294 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 68+147 BHS 5/18/2021 5/19/2021

EPC-06/STR/2295 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 68+147 BHS 5/18/2021 5/19/2021

EPC-06/STR/2296 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 06+385 BHS 5/18/2021 5/19/2021

RCC Cover
EPC-06/STR/2297 Pouring of concrete RCC M-20 for raft 68+190 68+300 LHS 5/18/2021 5/19/2021
Drain
RCC Cover
EPC-06/STR/2298 Shuttering and reinforcement checking for both walls 68+440 68+550 LHS 5/18/2021 5/19/2021
Drain
RCC Cover
EPC-06/STR/2299 Pouring of concrete RCC M-20 for both walls 68+440 68+550 LHS 5/18/2021 5/19/2021
Drain

EPC-06/STR/2306 Shuttering checking and pouring of concrete PCC M-20 for Head wall 3rd lift HPC 103+788 BHS 5/19/2021 5/20/2021

RCC Cover
EPC-06/STR/2307 Pouring of concrete RCC M-20 for raft 68+100 68+190 LHS 5/19/2021 5/20/2021
Drain

EPC-06/STR/2316 Shuttering and reinforcement checking for raft Box Culvert 06+385 BHS 5/20/2021 5/21/2021

EPC-06/STR/2317 Pouring of concrete RCC M-25 for raft Box Culvert 06+385 BHS 5/20/2021 5/21/2021

RCC Cover
EPC-06/STR/2318 Shuttering and reinforcement checking for Slab 68+550 68+700 LHS 5/20/2021 5/21/2021
Drain
RCC Cover
EPC-06/STR/2319 Pouring of concrete RCC M-20 for Slab 68+550 68+700 LHS 5/20/2021 5/21/2021
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/2320 Pouring of concrete RCC M-20 for raft 68+000 68+100 LHS 5/20/2021 5/21/2021
Drain
RCC Cover
EPC-06/STR/2321 Shuttering and reinforcement checking for both walls 68+190 68+300 LHS 5/20/2021 5/21/2021
Drain
RCC Cover
EPC-06/STR/2322 Pouring of concrete RCC M-20 for both walls 68+190 68+300 LHS 5/20/2021 5/21/2021
Drain

EPC-06/STR/2327 Shuttering and reinforcement checking for top slab Box Culvert 68+147 BHS 5/21/2021 5/22/2021

EPC-06/STR/2328 Pouring of concrete RCC M-25 for top slab Box Culvert 68+147 BHS 5/21/2021 5/22/2021

EPC-06/STR/2329 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 06+385 BHS 5/21/2021 5/22/2021

EPC-06/STR/2330 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 06+385 BHS 5/21/2021 5/22/2021

RCC Cover
EPC-06/STR/2331 Shuttering and reinforcement checking for Slab 68+440 68+550 LHS 5/21/2021 5/22/2021
Drain
RCC Cover
EPC-06/STR/2332 Pouring of concrete RCC M-20 for Slab 68+440 68+550 LHS 5/21/2021 5/22/2021
Drain
RCC Cover
EPC-06/STR/2333 Shuttering and reinforcement checking for both walls 68+100 68+190 LHS 5/21/2021 5/22/2021
Drain
RCC Cover
EPC-06/STR/2334 Pouring of concrete RCC M-20 for both walls 68+100 68+190 LHS 5/21/2021 5/22/2021
Drain

EPC-06/STR/2340 Layout checking and earthwork in excavation for Head Wall HPC 105+006 BHS 5/22/2021 5/23/2021

EPC-06/STR/2341 Dismantling of existing HPC. HPC 105+006 BHS 5/22/2021 5/23/2021

RCC Cover
EPC-06/STR/2342 Shuttering and reinforcement checking for both walls 68+000 68+100 LHS 5/22/2021 5/23/2021
Drain
RCC Cover
EPC-06/STR/2343 Pouring of concrete RCC M-20 for both walls 68+000 68+100 LHS 5/22/2021 5/23/2021
Drain

EPC-06/STR/2350 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 06+385 BHS 5/23/2021 5/24/2021

EPC-06/STR/2351 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 06+385 BHS 5/23/2021 5/24/2021

EPC-06/STR/2352 EGL checking and Pouring of concrete PCC M-15 below Head Wall HPC 105+006 BHS 5/23/2021 5/24/2021

EPC-06/STR/2353 Layout checking and earthwork in excavation for Head Wall HPC 107+258 BHS 5/23/2021 5/24/2021

EPC-06/STR/2354 Dismantling of existing HPC. HPC 107+258 BHS 5/23/2021 5/24/2021

RCC Cover
EPC-06/STR/2355 Shuttering and reinforcement checking for Slab 68+190 68+300 LHS 5/23/2021 5/24/2021
Drain
RCC Cover
EPC-06/STR/2356 Pouring of concrete RCC M-20 for Slab 68+190 68+300 LHS 5/23/2021 5/24/2021
Drain

EPC-06/STR/2361 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 06+385 BHS 5/24/2021 5/25/2021

EPC-06/STR/2362 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 06+385 BHS 5/24/2021 5/25/2021

EPC-06/STR/2363 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift HPC 105+006 BHS 5/24/2021 5/25/2021

EPC-06/STR/2364 EGL checking and Pouring of concrete PCC M-15 below Head Wall HPC 107+258 BHS 5/24/2021 5/25/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/2365 Shuttering and reinforcement checking for Slab 68+100 68+190 LHS 5/24/2021 5/25/2021
Drain
RCC Cover
EPC-06/STR/2366 Pouring of concrete RCC M-20 for Slab 68+100 68+190 LHS 5/24/2021 5/25/2021
Drain

EPC-06/STR/2372 Shuttering checking and pouring of concrete PCC M-20 for Head wall 1st lift HPC 107+258 BHS 5/25/2021 5/26/2021

RCC Cover
EPC-06/STR/2373 Shuttering and reinforcement checking for Slab 68+000 68+100 LHS 5/25/2021 5/26/2021
Drain
RCC Cover
EPC-06/STR/2374 Pouring of concrete RCC M-20 for Slab 68+000 68+100 LHS 5/25/2021 5/26/2021
Drain

EPC-06/STR/2382 Earthwork in excavation for pipe laying HPC 105+006 BHS 5/26/2021 5/27/2021

EPC-06/STR/2383 Laying of NP-4 Pipe 1200 mm dia HPC 105+006 BHS 5/26/2021 5/27/2021

EPC-06/STR/2392 Shuttering and reinforcement checking for top slab Box Culvert 06+385 BHS 5/27/2021 5/28/2021

EPC-06/STR/2393 Pouring of concrete RCC M-25 for top slab Box Culvert 06+385 BHS 5/27/2021 5/28/2021

EPC-06/STR/2394 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift HPC 105+006 BHS 5/27/2021 5/28/2021

EPC-06/STR/2395 Earthwork in excavation for pipe laying HPC 107+258 BHS 5/27/2021 5/28/2021

EPC-06/STR/2396 Laying of NP-4 Pipe 1200 mm dia HPC 107+258 BHS 5/27/2021 5/28/2021

EPC-06/STR/2402 Shuttering checking and pouring of concrete PCC M-20 for Head wall 2nd lift HPC 107+258 BHS 5/28/2021 5/29/2021

EPC-06/STR/2403 Shuttering checking and pouring of concrete PCC M-20 for Head wall 3rd lift HPC 105+006 BHS 5/29/2021 5/30/2021

EPC-06/STR/2404 Shuttering checking and pouring of concrete PCC M-20 for Head wall 3rd lift HPC 107+258 BHS 5/30/2021 5/31/2021

RCC Cover
EPC-06/STR/2425 EGL checking and Pouring of concrete PCC M-15 below Raft 71+200 71+240 RHS 6/1/2021 6/2/2021
Drain
RCC Cover
EPC-06/STR/2432 EGL checking and Pouring of concrete PCC M-15 below Raft 71+600 71+700 RHS 6/2/2021 6/3/2021
Drain
RCC Cover
EPC-06/STR/2433 Pouring of concrete RCC M-20 for raft 71+200 71+240 RHS 6/2/2021 6/3/2021
Drain
RCC Cover
EPC-06/STR/2440 Pouring of concrete RCC M-20 for raft 71+600 71+700 RHS 6/3/2021 6/4/2021
Drain
RCC Cover
EPC-06/STR/2452 Shuttering and reinforcement checking for both walls 71+200 71+240 RHS 6/5/2021 6/6/2021
Drain
RCC Cover
EPC-06/STR/2453 Pouring of concrete RCC M-20 for both walls 71+200 71+240 RHS 6/5/2021 6/6/2021
Drain
RCC Cover
EPC-06/STR/2461 Shuttering and reinforcement checking for both walls 71+600 71+700 RHS 6/6/2021 6/7/2021
Drain
RCC Cover
EPC-06/STR/2462 Pouring of concrete RCC M-20 for both walls 71+600 71+700 RHS 6/6/2021 6/7/2021
Drain
RCC Cover
EPC-06/STR/2474 Shuttering and reinforcement checking for Slab 71+200 71+240 RHS 6/8/2021 6/9/2021
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/2475 Pouring of concrete RCC M-20 for Slab 71+200 71+240 RHS 6/8/2021 6/9/2021
Drain
RCC Cover
EPC-06/STR/2482 Shuttering and reinforcement checking for Slab 71+600 71+700 RHS 6/9/2021 6/10/2021
Drain
RCC Cover
EPC-06/STR/2483 Pouring of concrete RCC M-20 for Slab 71+600 71+700 RHS 6/9/2021 6/10/2021
Drain

EPC-06/STR/2563 Layout marking and OGL checking for excavation Box Culvert 88+879 BHS 7/17/2021 7/18/2021

EPC-06/STR/2564 Dismantling of existing structure Box Culvert 88+879 BHS 7/17/2021 7/18/2021

EPC-06/STR/2572 Earthwork in excavation for Box Culvert Box Culvert 88+879 BHS 7/18/2021 7/19/2021

EPC-06/STR/2580 EGL checking and Boulder Soling below PCC Box Culvert 88+879 BHS 7/19/2021 7/20/2021

EPC-06/STR/2588 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 88+879 BHS 7/20/2021 7/21/2021

EPC-06/STR/2601 Shuttering and reinforcement checking for raft Box Culvert 88+879 BHS 7/22/2021 7/23/2021

EPC-06/STR/2602 Pouring of concrete RCC M-25 for raft Box Culvert 88+879 BHS 7/22/2021 7/23/2021

EPC-06/STR/2611 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 88+879 BHS 7/23/2021 7/24/2021

EPC-06/STR/2612 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 88+879 BHS 7/23/2021 7/24/2021

EPC-06/STR/2613 Layout marking and OGL checking for excavation Box Culvert 52+048 BHS 7/23/2021 7/24/2021

EPC-06/STR/2614 Dismantling of existing structure Box Culvert 52+048 BHS 7/23/2021 7/24/2021

EPC-06/STR/2622 Earthwork in excavation for Box Culvert Box Culvert 52+048 BHS 7/24/2021 7/25/2021

RCC Cover
EPC-06/STR/2623 EGL checking and Pouring of concrete PCC M-15 below Raft 86+645 86+820 LHS 7/24/2021 7/25/2021
Drain

EPC-06/STR/2631 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 88+879 BHS 7/25/2021 7/26/2021

EPC-06/STR/2632 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 88+879 BHS 7/25/2021 7/26/2021

EPC-06/STR/2633 EGL checking and Boulder Soling below PCC Box Culvert 52+048 BHS 7/25/2021 7/26/2021

EPC-06/STR/2641 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 88+879 BHS 7/26/2021 7/27/2021

EPC-06/STR/2642 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 88+879 BHS 7/26/2021 7/27/2021

EPC-06/STR/2643 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 52+048 BHS 7/26/2021 7/27/2021

RCC Cover
EPC-06/STR/2644 Pouring of concrete RCC M-20 for raft 86+645 86+820 LHS 7/26/2021 7/27/2021
Drain

EPC-06/STR/2659 Shuttering and reinforcement checking for raft Box Culvert 52+048 BHS 7/28/2021 7/29/2021

EPC-06/STR/2660 Pouring of concrete RCC M-25 for raft Box Culvert 52+048 BHS 7/28/2021 7/29/2021

EPC-06/STR/2672 Shuttering and reinforcement checking for top slab Box Culvert 88+879 BHS 7/29/2021 7/30/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/2673 Pouring of concrete RCC M-25 for top slab Box Culvert 88+879 BHS 7/29/2021 7/30/2021

EPC-06/STR/2674 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 52+048 BHS 7/29/2021 7/30/2021

EPC-06/STR/2675 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 52+048 BHS 7/29/2021 7/30/2021

RCC Cover
EPC-06/STR/2676 Shuttering and reinforcement checking for both walls 86+645 86+740 LHS 7/29/2021 7/30/2021
Drain
RCC Cover
EPC-06/STR/2677 Pouring of concrete RCC M-20 for both walls 86+645 86+740 LHS 7/29/2021 7/30/2021
Drain
RCC Cover
EPC-06/STR/2685 Shuttering and reinforcement checking for both walls 86+740 86+820 LHS 7/30/2021 7/31/2021
Drain
RCC Cover
EPC-06/STR/2686 Pouring of concrete RCC M-20 for both walls 86+740 86+820 LHS 7/30/2021 7/31/2021
Drain

EPC-06/STR/2694 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 52+048 BHS 7/31/2021 8/1/2021

EPC-06/STR/2695 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 52+048 BHS 7/31/2021 8/1/2021

EPC-06/STR/2703 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 52+048 BHS 8/1/2021 8/2/2021

EPC-06/STR/2704 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 52+048 BHS 8/1/2021 8/2/2021

EPC-06/STR/2705 Layout marking and OGL checking for excavation MNB 91+264 BHS 8/1/2021 8/2/2021

EPC-06/STR/2706 Dismantling of existing structure MNB 91+264 BHS 8/1/2021 8/2/2021

EPC-06/STR/2714 Earthwork in excavation for MNB MNB 91+264 BHS 8/2/2021 8/3/2021

RCC Cover
EPC-06/STR/2715 Shuttering and reinforcement checking for Slab 86+645 86+740 LHS 8/2/2021 8/3/2021
Drain
RCC Cover
EPC-06/STR/2716 Pouring of concrete RCC M-20 for Slab 86+645 86+740 LHS 8/2/2021 8/3/2021
Drain

EPC-06/STR/2724 EGL checking and Boulder Soling below PCC MNB 91+264 BHS 8/3/2021 8/4/2021

RCC Cover
EPC-06/STR/2725 Shuttering and reinforcement checking for Slab 86+740 86+820 LHS 8/3/2021 8/4/2021
Drain
RCC Cover
EPC-06/STR/2726 Pouring of concrete RCC M-20 for Slab 86+740 86+820 LHS 8/3/2021 8/4/2021
Drain

EPC-06/STR/2734 Shuttering and reinforcement checking for top slab Box Culvert 52+048 BHS 8/4/2021 8/5/2021

EPC-06/STR/2735 Pouring of concrete RCC M-25 for top slab Box Culvert 52+048 BHS 8/4/2021 8/5/2021

EPC-06/STR/2736 Pouring of concrete PCC M-15 below raft with Cut off wall MNB 91+264 BHS 8/4/2021 8/5/2021

EPC-06/STR/2746 Layout marking and OGL checking for excavation Box Culvert 46+970 BHS 8/5/2021 8/6/2021

EPC-06/STR/2747 Dismantling of existing structure Box Culvert 46+970 BHS 8/5/2021 8/6/2021

EPC-06/STR/2756 Earthwork in excavation for Box Culvert Box Culvert 46+970 BHS 8/6/2021 8/7/2021

EPC-06/STR/2757 Shuttering and reinforcement checking for raft MNB 91+264 BHS 8/6/2021 8/7/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/2758 Pouring of concrete RCC M-30 for raft MNB 91+264 BHS 8/6/2021 8/7/2021

EPC-06/STR/2767 EGL checking and Boulder Soling below PCC Box Culvert 46+970 BHS 8/7/2021 8/8/2021

RCC Cover
EPC-06/STR/2768 EGL checking and Pouring of concrete PCC M-15 below Raft 88+880 89+060 RHS 8/7/2021 8/8/2021
Drain

EPC-06/STR/2777 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 46+970 BHS 8/8/2021 8/9/2021

RCC Cover
EPC-06/STR/2778 EGL checking and Pouring of concrete PCC M-15 below Raft 89+060 89+280 RHS 8/8/2021 8/9/2021
Drain

EPC-06/STR/2795 Shuttering and reinforcement checking for raft Box Culvert 46+970 BHS 8/10/2021 8/11/2021

EPC-06/STR/2796 Pouring of concrete RCC M-25 for raft Box Culvert 46+970 BHS 8/10/2021 8/11/2021

EPC-06/STR/2797 Layout marking and OGL checking for excavation Box Culvert 93+737 BHS 8/10/2021 8/11/2021

EPC-06/STR/2798 Dismantling of existing structure Box Culvert 93+737 BHS 8/10/2021 8/11/2021

RCC Cover
EPC-06/STR/2801 Pouring of concrete RCC M-20 for raft 88+880 89+060 RHS 8/10/2021 8/11/2021
Drain

EPC-06/STR/2813 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 46+970 BHS 8/11/2021 8/12/2021

EPC-06/STR/2814 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 46+970 BHS 8/11/2021 8/12/2021

EPC-06/STR/2815 Earthwork in excavation for Box Culvert Box Culvert 93+737 BHS 8/11/2021 8/12/2021

RCC Cover
EPC-06/STR/2817 Pouring of concrete RCC M-20 for raft 89+060 89+280 RHS 8/11/2021 8/12/2021
Drain

EPC-06/STR/2827 EGL checking and Boulder Soling below PCC Box Culvert 93+737 BHS 8/12/2021 8/13/2021

EPC-06/STR/2838 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 46+970 BHS 8/13/2021 8/14/2021

EPC-06/STR/2839 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 46+970 BHS 8/13/2021 8/14/2021

EPC-06/STR/2840 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 93+737 BHS 8/13/2021 8/14/2021

RCC Cover
EPC-06/STR/2842 Shuttering and reinforcement checking for both walls 88+880 88+970 RHS 8/13/2021 8/14/2021
Drain
RCC Cover
EPC-06/STR/2843 Pouring of concrete RCC M-20 for both walls 88+880 88+970 RHS 8/13/2021 8/14/2021
Drain

EPC-06/STR/2854 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 46+970 BHS 8/14/2021 8/15/2021

EPC-06/STR/2855 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 46+970 BHS 8/14/2021 8/15/2021

RCC Cover
EPC-06/STR/2856 Shuttering and reinforcement checking for both walls 88+970 89+050 RHS 8/14/2021 8/15/2021
Drain
RCC Cover
EPC-06/STR/2857 Pouring of concrete RCC M-20 for both walls 88+970 89+050 RHS 8/14/2021 8/15/2021
Drain

EPC-06/STR/2865 Shuttering and reinforcement checking for raft Box Culvert 93+737 BHS 8/15/2021 8/16/2021

EPC-06/STR/2866 Pouring of concrete RCC M-25 for raft Box Culvert 93+737 BHS 8/15/2021 8/16/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/2867 Layout marking and OGL checking for excavation Box Culvert 94+749 BHS 8/15/2021 8/16/2021

EPC-06/STR/2868 Dismantling of existing structure Box Culvert 94+749 BHS 8/15/2021 8/16/2021

RCC Cover
EPC-06/STR/2871 Shuttering and reinforcement checking for both walls 89+050 89+170 RHS 8/15/2021 8/16/2021
Drain
RCC Cover
EPC-06/STR/2872 Pouring of concrete RCC M-20 for both walls 89+050 89+170 RHS 8/15/2021 8/16/2021
Drain

EPC-06/STR/2881 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 93+737 BHS 8/16/2021 8/17/2021

EPC-06/STR/2882 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 93+737 BHS 8/16/2021 8/17/2021

EPC-06/STR/2883 Earthwork in excavation for Box Culvert Box Culvert 94+749 BHS 8/16/2021 8/17/2021

RCC Cover
EPC-06/STR/2884 Shuttering and reinforcement checking for both walls 89+170 89+280 RHS 8/16/2021 8/17/2021
Drain
RCC Cover
EPC-06/STR/2885 Pouring of concrete RCC M-20 for both walls 89+170 89+280 RHS 8/16/2021 8/17/2021
Drain

EPC-06/STR/2896 Shuttering and reinforcement checking for top slab Box Culvert 46+970 BHS 8/17/2021 8/18/2021

EPC-06/STR/2897 Pouring of concrete RCC M-25 for top slab Box Culvert 46+970 BHS 8/17/2021 8/18/2021

EPC-06/STR/2898 EGL checking and Boulder Soling below PCC Box Culvert 94+749 BHS 8/17/2021 8/18/2021

RCC Cover
EPC-06/STR/2899 Shuttering and reinforcement checking for Slab 88+880 88+970 RHS 8/17/2021 8/18/2021
Drain
RCC Cover
EPC-06/STR/2900 Pouring of concrete RCC M-20 for Slab 88+880 88+970 RHS 8/17/2021 8/18/2021
Drain

EPC-06/STR/2909 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 93+737 BHS 8/18/2021 8/19/2021

EPC-06/STR/2910 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 93+737 BHS 8/18/2021 8/19/2021

EPC-06/STR/2911 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 94+749 BHS 8/18/2021 8/19/2021

RCC Cover
EPC-06/STR/2912 EGL checking and Pouring of concrete PCC M-15 below Raft 49+500 49+600 RHS 8/18/2021 8/19/2021
Drain
RCC Cover
EPC-06/STR/2913 Shuttering and reinforcement checking for Slab 88+970 89+050 RHS 8/18/2021 8/19/2021
Drain
RCC Cover
EPC-06/STR/2914 Pouring of concrete RCC M-20 for Slab 88+970 89+050 RHS 8/18/2021 8/19/2021
Drain

EPC-06/STR/2923 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 93+737 BHS 8/19/2021 8/20/2021

EPC-06/STR/2924 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 93+737 BHS 8/19/2021 8/20/2021

RCC Cover
EPC-06/STR/2925 Shuttering and reinforcement checking for Slab 89+050 89+170 RHS 8/19/2021 8/20/2021
Drain
RCC Cover
EPC-06/STR/2926 Pouring of concrete RCC M-20 for Slab 89+050 89+170 RHS 8/19/2021 8/20/2021
Drain

EPC-06/STR/2935 Shuttering and reinforcement checking for raft Box Culvert 94+749 BHS 8/20/2021 8/21/2021

EPC-06/STR/2936 Pouring of concrete RCC M-25 for raft Box Culvert 94+749 BHS 8/20/2021 8/21/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/2937 Pouring of concrete RCC M-20 for raft 49+500 49+600 RHS 8/20/2021 8/21/2021
Drain
RCC Cover
EPC-06/STR/2938 Shuttering and reinforcement checking for Slab 89+170 89+280 RHS 8/20/2021 8/21/2021
Drain
RCC Cover
EPC-06/STR/2939 Pouring of concrete RCC M-20 for Slab 89+170 89+280 RHS 8/20/2021 8/21/2021
Drain

EPC-06/STR/2948 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 94+749 BHS 8/21/2021 8/22/2021

EPC-06/STR/2949 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 94+749 BHS 8/21/2021 8/22/2021

EPC-06/STR/2959 Shuttering and reinforcement checking for top slab Box Culvert 93+737 BHS 8/22/2021 8/23/2021

EPC-06/STR/2960 Pouring of concrete RCC M-25 for top slab Box Culvert 93+737 BHS 8/22/2021 8/23/2021

RCC Cover
EPC-06/STR/2961 Shuttering and reinforcement checking for both walls 49+500 49+600 RHS 8/22/2021 8/23/2021
Drain
RCC Cover
EPC-06/STR/2962 Pouring of concrete RCC M-20 for both walls 49+500 49+600 RHS 8/22/2021 8/23/2021
Drain

EPC-06/STR/2972 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 94+749 BHS 8/23/2021 8/24/2021

EPC-06/STR/2973 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 94+749 BHS 8/23/2021 8/24/2021

EPC-06/STR/2983 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 94+749 BHS 8/24/2021 8/25/2021

EPC-06/STR/2984 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 94+749 BHS 8/24/2021 8/25/2021

EPC-06/STR/2985 Layout marking and OGL checking for excavation MNB 48+006 BHS 8/24/2021 8/25/2021

EPC-06/STR/2986 Dismantling of existing structure MNB 48+006 BHS 8/24/2021 8/25/2021

EPC-06/STR/2996 Earthwork in excavation for MNB MNB 48+006 BHS 8/25/2021 8/26/2021

EPC-06/STR/3006 EGL checking and Boulder Soling below PCC MNB 48+006 BHS 8/26/2021 8/27/2021

RCC Cover
EPC-06/STR/3007 Shuttering and reinforcement checking for Slab 49+500 49+600 RHS 8/26/2021 8/27/2021
Drain
RCC Cover
EPC-06/STR/3008 Pouring of concrete RCC M-20 for Slab 49+500 49+600 RHS 8/26/2021 8/27/2021
Drain

EPC-06/STR/3018 Shuttering and reinforcement checking for top slab Box Culvert 94+749 BHS 8/27/2021 8/28/2021

EPC-06/STR/3019 Pouring of concrete RCC M-25 for top slab Box Culvert 94+749 BHS 8/27/2021 8/28/2021

EPC-06/STR/3020 Pouring of concrete PCC M-15 below raft with Cut off wall MNB 48+006 BHS 8/27/2021 8/28/2021

EPC-06/STR/3038 Shuttering and reinforcement checking for raft MNB 48+006 BHS 8/29/2021 8/30/2021

EPC-06/STR/3039 Pouring of concrete RCC M-30 for raft MNB 48+006 BHS 8/29/2021 8/30/2021

EPC-06/STR/3060 Shuttering and reinforcement checking for top slab MNB 91+264 BHS 9/5/2021 9/6/2021

EPC-06/STR/3061 Pouring of concrete RCC M-30 for top slab MNB 91+264 BHS 9/5/2021 9/6/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/3122 Pouring of concrete PCC M-15 below Approach Slab MNB 76+647 LHS 9/23/2021 9/24/2021

EPC-06/STR/3137 Shuttering and reinforcement checking for Approach Slab MNB 76+647 LHS 9/24/2021 9/25/2021

EPC-06/STR/3138 Pouring of concrete RCC M-30 for Approach Slab MNB 76+647 LHS 9/24/2021 9/25/2021

Shuttering and reinforcement checking for wall 1st lift with bottom hunch A1 & A2
EPC-06/STR/3178 MNB 48+006 BHS 10/2/2021 10/3/2021
side

EPC-06/STR/3179 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch A1 & A2 side MNB 48+006 BHS 10/2/2021 10/3/2021

Shuttering and reinforcement checking for wall 1st lift with bottom hunch -
EPC-06/STR/3194 MNB 48+006 BHS 10/3/2021 10/4/2021
Intermediate wall

EPC-06/STR/3195 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch - Intermediate wall MNB 48+006 BHS 10/3/2021 10/4/2021

EPC-06/STR/3196 Layout marking and OGL checking for excavation Box Culvert 50+011 BHS 10/3/2021 10/4/2021

EPC-06/STR/3197 Dismantling of existing structure Box Culvert 50+011 BHS 10/3/2021 10/4/2021

EPC-06/STR/3212 Earthwork in excavation for Box Culvert Box Culvert 50+011 BHS 10/4/2021 10/5/2021

EPC-06/STR/3227 Layout marking and OGL checking for excavation Box Culvert 88+627 BHS 10/5/2021 10/6/2021

EPC-06/STR/3228 Dismantling of existing structure Box Culvert 88+627 BHS 10/5/2021 10/6/2021

EPC-06/STR/3229 Shuttering and reinforcement checking for wall 2nd lift- Intermediate wall MNB 48+006 BHS 10/5/2021 10/6/2021

EPC-06/STR/3230 Pouring of concrete RCC M-30 for wall 2nd lift- Intermediate wall MNB 48+006 BHS 10/5/2021 10/6/2021

EPC-06/STR/3231 EGL checking and Boulder Soling below PCC Box Culvert 50+011 BHS 10/5/2021 10/6/2021

EPC-06/STR/3246 Earthwork in excavation for Box Culvert Box Culvert 88+627 BHS 10/6/2021 10/7/2021

EPC-06/STR/3247 Shuttering and reinforcement checking for wall 2nd lift- A1 & A2 side MNB 48+006 BHS 10/6/2021 10/7/2021

EPC-06/STR/3248 Pouring of concrete RCC M-30 for wall 2nd lift- A1 & A2 side MNB 48+006 BHS 10/6/2021 10/7/2021

EPC-06/STR/3263 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 50+011 BHS 10/7/2021 10/8/2021

EPC-06/STR/3264 EGL checking and Boulder Soling below PCC Box Culvert 88+627 BHS 10/7/2021 10/8/2021

EPC-06/STR/3279 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 88+627 BHS 10/8/2021 10/9/2021

EPC-06/STR/3294 Shuttering and reinforcement checking for raft Box Culvert 50+011 BHS 10/9/2021 10/10/2021

EPC-06/STR/3295 Pouring of concrete RCC M-25 for raft Box Culvert 50+011 BHS 10/9/2021 10/10/2021

EPC-06/STR/3315 Shuttering and reinforcement checking for raft Box Culvert 88+627 BHS 10/11/2021 10/12/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/3316 Pouring of concrete RCC M-25 for raft Box Culvert 88+627 BHS 10/11/2021 10/12/2021

EPC-06/STR/3331 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 50+011 BHS 10/12/2021 10/13/2021

EPC-06/STR/3332 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 50+011 BHS 10/12/2021 10/13/2021

RCC Cover
EPC-06/STR/3347 Earthwork in excavation for RCC drain 86+645 86+820 RHS 10/13/2021 10/14/2021
Drain
RCC Cover
EPC-06/STR/3362 EGL checking and Pouring of concrete PCC M-15 below Raft 86+645 86+740 RHS 10/14/2021 10/15/2021
Drain
RCC Cover
EPC-06/STR/3377 EGL checking and Pouring of concrete PCC M-15 below Raft 86+740 86+820 RHS 10/15/2021 10/16/2021
Drain
RCC Cover
EPC-06/STR/3392 Pouring of concrete RCC M-20 for raft 86+645 86+740 RHS 10/16/2021 10/17/2021
Drain
RCC Cover
EPC-06/STR/3407 Pouring of concrete RCC M-20 for raft 86+740 86+820 RHS 10/17/2021 10/18/2021
Drain

EPC-06/STR/3437 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 50+011 BHS 10/19/2021 10/20/2021

EPC-06/STR/3438 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 50+011 BHS 10/19/2021 10/20/2021

EPC-06/STR/3439 Shuttering and reinforcement checking for top slab Box Culvert 50+011 BHS 10/19/2021 10/20/2021

EPC-06/STR/3440 Pouring of concrete RCC M-25 for top slab Box Culvert 50+011 BHS 10/19/2021 10/20/2021

EPC-06/STR/3441 Layout marking and OGL checking for excavation Box Culvert 55+343 BHS 10/19/2021 10/20/2021

EPC-06/STR/3442 Dismantling of existing structure Box Culvert 55+343 BHS 10/19/2021 10/20/2021

EPC-06/STR/3443 Pouring of concrete PCC M-15 below Approach Slab MNB 64+941 LHS 10/19/2021 10/20/2021

RCC Cover
EPC-06/STR/3444 Shuttering and reinforcement checking for both walls 86+645 86+690 RHS 10/19/2021 10/20/2021
Drain
RCC Cover
EPC-06/STR/3445 Pouring of concrete RCC M-20 for both walls 86+645 86+690 RHS 10/19/2021 10/20/2021
Drain

EPC-06/STR/3460 Earthwork in excavation for Box Culvert Box Culvert 55+343 BHS 10/20/2021 10/21/2021

EPC-06/STR/3461 Layout marking and OGL checking for excavation Box Culvert 95+361 BHS 10/20/2021 10/21/2021

EPC-06/STR/3462 Dismantling of existing structure Box Culvert 95+361 BHS 10/20/2021 10/21/2021

EPC-06/STR/3463 Shuttering and reinforcement checking for Approach Slab MNB 64+941 LHS 10/20/2021 10/21/2021

EPC-06/STR/3464 Pouring of concrete RCC M-30 for Approach Slab MNB 64+941 LHS 10/20/2021 10/21/2021

EPC-06/STR/3479 EGL checking and Boulder Soling below PCC Box Culvert 55+343 BHS 10/21/2021 10/22/2021

EPC-06/STR/3480 Earthwork in excavation for Box Culvert Box Culvert 95+361 BHS 10/21/2021 10/22/2021

EPC-06/STR/3481 Shuttering and reinforcement checking for wall final lift- Intermediate wall MNB 48+006 BHS 10/21/2021 10/22/2021

EPC-06/STR/3482 Pouring of concrete RCC M-30 for wall final lift- Intermediate wall MNB 48+006 BHS 10/21/2021 10/22/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/3483 Shuttering and reinforcement checking for both walls 86+690 86+730 RHS 10/21/2021 10/22/2021
Drain
RCC Cover
EPC-06/STR/3484 Pouring of concrete RCC M-20 for both walls 86+690 86+730 RHS 10/21/2021 10/22/2021
Drain

EPC-06/STR/3499 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 55+343 BHS 10/22/2021 10/23/2021

EPC-06/STR/3500 EGL checking and Boulder Soling below PCC Box Culvert 95+361 BHS 10/22/2021 10/23/2021

RCC Cover
EPC-06/STR/3501 Shuttering and reinforcement checking for Slab 86+645 86+690 RHS 10/22/2021 10/23/2021
Drain
RCC Cover
EPC-06/STR/3502 Pouring of concrete RCC M-20 for Slab 86+645 86+690 RHS 10/22/2021 10/23/2021
Drain

EPC-06/STR/3517 Layout marking and OGL checking for excavation Box Culvert 53+404 BHS 10/23/2021 10/24/2021

EPC-06/STR/3518 Dismantling of existing structure Box Culvert 53+404 BHS 10/23/2021 10/24/2021

EPC-06/STR/3519 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 95+361 BHS 10/23/2021 10/24/2021

RCC Cover
EPC-06/STR/3520 Shuttering and reinforcement checking for both walls 86+730 86+770 RHS 10/23/2021 10/24/2021
Drain
RCC Cover
EPC-06/STR/3521 Pouring of concrete RCC M-20 for both walls 86+730 86+770 RHS 10/23/2021 10/24/2021
Drain

EPC-06/STR/3536 Earthwork in excavation for Box Culvert Box Culvert 53+404 BHS 10/24/2021 10/25/2021

EPC-06/STR/3537 Shuttering and reinforcement checking for raft Box Culvert 55+343 BHS 10/24/2021 10/25/2021

EPC-06/STR/3538 Pouring of concrete RCC M-25 for raft Box Culvert 55+343 BHS 10/24/2021 10/25/2021

EPC-06/STR/3539 Pouring of concrete PCC M-15 below Approach Slab MNB 76+647 RHS 10/24/2021 10/25/2021

RCC Cover
EPC-06/STR/3540 Shuttering and reinforcement checking for Slab 86+690 86+730 RHS 10/24/2021 10/25/2021
Drain
RCC Cover
EPC-06/STR/3541 Pouring of concrete RCC M-20 for Slab 86+690 86+730 RHS 10/24/2021 10/25/2021
Drain

EPC-06/STR/3556 EGL checking and Boulder Soling below PCC Box Culvert 53+404 BHS 10/25/2021 10/26/2021

EPC-06/STR/3557 Shuttering and reinforcement checking for Approach Slab MNB 76+647 RHS 10/25/2021 10/26/2021

EPC-06/STR/3558 Pouring of concrete RCC M-30 for Approach Slab MNB 76+647 RHS 10/25/2021 10/26/2021

RCC Cover
EPC-06/STR/3559 Shuttering and reinforcement checking for both walls 86+770 86+820 RHS 10/25/2021 10/26/2021
Drain
RCC Cover
EPC-06/STR/3560 Pouring of concrete RCC M-20 for both walls 86+770 86+820 RHS 10/25/2021 10/26/2021
Drain

EPC-06/STR/3575 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 53+404 BHS 10/26/2021 10/27/2021

Shuttering and reinforcement checking for wall 1st lift with bottom hunch A1 & A2
EPC-06/STR/3576 Box Culvert 88+627 BHS 10/26/2021 10/27/2021
side

EPC-06/STR/3577 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch A1 & A2 side Box Culvert 88+627 BHS 10/26/2021 10/27/2021

RCC Cover
EPC-06/STR/3578 Shuttering and reinforcement checking for Slab 86+730 86+770 RHS 10/26/2021 10/27/2021
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/3579 Pouring of concrete RCC M-20 for Slab 86+730 86+770 RHS 10/26/2021 10/27/2021
Drain

EPC-06/STR/3594 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 55+343 BHS 10/27/2021 10/28/2021

EPC-06/STR/3595 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 55+343 BHS 10/27/2021 10/28/2021

RCC Cover
EPC-06/STR/3596 Shuttering and reinforcement checking for Slab 86+770 86+820 RHS 10/27/2021 10/28/2021
Drain
RCC Cover
EPC-06/STR/3597 Pouring of concrete RCC M-20 for Slab 86+770 86+820 RHS 10/27/2021 10/28/2021
Drain
Shuttering and reinforcement checking for wall 1st lift with bottom hunch -
EPC-06/STR/3622 Box Culvert 88+627 BHS 10/29/2021 10/30/2021
Intermediate wall

EPC-06/STR/3623 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch - Intermediate wall Box Culvert 88+627 BHS 10/29/2021 10/30/2021

EPC-06/STR/3638 Shuttering and reinforcement checking for wall final lift with bracket- A1 & A2 side MNB 48+006 BHS 10/30/2021 10/31/2021

EPC-06/STR/3639 Pouring of concrete RCC M-30 for wall final lift with bracket- A1 & A2 side MNB 48+006 BHS 10/30/2021 10/31/2021

EPC-06/STR/3640 Shuttering and reinforcement checking for top slab MNB 48+006 BHS 10/30/2021 10/31/2021

EPC-06/STR/3641 Pouring of concrete RCC M-30 for top slab MNB 48+006 BHS 10/30/2021 10/31/2021

EPC-06/STR/3656 Shuttering and reinforcement checking for wall 2nd lift- Intermediate wall Box Culvert 88+627 BHS 10/31/2021 11/1/2021

EPC-06/STR/3657 Pouring of concrete RCC M-25 for wall 2nd lift- Intermediate wall Box Culvert 88+627 BHS 10/31/2021 11/1/2021

EPC-06/STR/3682 Shuttering and reinforcement checking for raft Box Culvert 53+404 BHS 11/2/2021 11/3/2021

EPC-06/STR/3683 Pouring of concrete RCC M-25 for raft Box Culvert 53+404 BHS 11/2/2021 11/3/2021

EPC-06/STR/3684 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 55+343 BHS 11/2/2021 11/3/2021

EPC-06/STR/3685 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 55+343 BHS 11/2/2021 11/3/2021

RCC Cover
EPC-06/STR/3710 Earthwork in excavation for RCC drain 49+600 49+750 RHS 11/5/2021 11/6/2021
Drain
RCC Cover
EPC-06/STR/3711 EGL checking and Pouring of concrete PCC M-15 below Raft 49+600 49+750 RHS 11/5/2021 11/6/2021
Drain

EPC-06/STR/3726 Shuttering and reinforcement checking for raft Box Culvert 95+361 BHS 11/6/2021 11/7/2021

EPC-06/STR/3727 Pouring of concrete RCC M-25 for raft Box Culvert 95+361 BHS 11/6/2021 11/7/2021

RCC Cover
EPC-06/STR/3728 Earthwork in excavation for RCC drain 49+750 49+900 RHS 11/6/2021 11/7/2021
Drain
RCC Cover
EPC-06/STR/3729 EGL checking and Pouring of concrete PCC M-15 below Raft 49+750 49+900 RHS 11/6/2021 11/7/2021
Drain
RCC Cover
EPC-06/STR/3744 Pouring of concrete RCC M-20 for raft 49+600 49+750 RHS 11/7/2021 11/8/2021
Drain

EPC-06/STR/3759 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 53+404 BHS 11/8/2021 11/9/2021

EPC-06/STR/3760 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 53+404 BHS 11/8/2021 11/9/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/3761 Shuttering and reinforcement checking for wall final lift with bracket- A1 & A2 side Box Culvert 88+627 BHS 11/8/2021 11/9/2021

EPC-06/STR/3762 Pouring of concrete RCC M-25 for wall final lift with bracket- A1 & A2 side Box Culvert 88+627 BHS 11/8/2021 11/9/2021

RCC Cover
EPC-06/STR/3763 Pouring of concrete RCC M-20 for raft 49+750 49+900 RHS 11/8/2021 11/9/2021
Drain

EPC-06/STR/3778 Layout marking and OGL checking for excavation Box Culvert 54+601 BHS 11/9/2021 11/10/2021

EPC-06/STR/3779 Dismantling of existing structure Box Culvert 54+601 BHS 11/9/2021 11/10/2021

EPC-06/STR/3794 Earthwork in excavation for Box Culvert Box Culvert 54+601 BHS 11/10/2021 11/11/2021

EPC-06/STR/3795 Shuttering and reinforcement checking for top slab Box Culvert 88+627 BHS 11/10/2021 11/11/2021

EPC-06/STR/3796 Pouring of concrete RCC M-25 for top slab Box Culvert 88+627 BHS 11/10/2021 11/11/2021

RCC Cover
EPC-06/STR/3797 Shuttering and reinforcement checking for both walls 49+600 49+650 RHS 11/10/2021 11/11/2021
Drain
RCC Cover
EPC-06/STR/3798 Pouring of concrete RCC M-20 for both walls 49+600 49+650 RHS 11/10/2021 11/11/2021
Drain

EPC-06/STR/3813 EGL checking and Boulder Soling below PCC Box Culvert 54+601 BHS 11/11/2021 11/12/2021

EPC-06/STR/3828 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 54+601 BHS 11/12/2021 11/13/2021

EPC-06/STR/3829 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 95+361 BHS 11/12/2021 11/13/2021

EPC-06/STR/3830 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 95+361 BHS 11/12/2021 11/13/2021

RCC Cover
EPC-06/STR/3831 Shuttering and reinforcement checking for both walls 49+650 49+700 RHS 11/12/2021 11/13/2021
Drain
RCC Cover
EPC-06/STR/3832 Pouring of concrete RCC M-20 for both walls 49+650 49+700 RHS 11/12/2021 11/13/2021
Drain
RCC Cover
EPC-06/STR/3847 Shuttering and reinforcement checking for Slab 49+600 49+650 RHS 11/13/2021 11/14/2021
Drain
RCC Cover
EPC-06/STR/3848 Pouring of concrete RCC M-20 for Slab 49+600 49+650 RHS 11/13/2021 11/14/2021
Drain
RCC Cover
EPC-06/STR/3863 Shuttering and reinforcement checking for both walls 49+700 49+750 RHS 11/14/2021 11/15/2021
Drain
RCC Cover
EPC-06/STR/3864 Pouring of concrete RCC M-20 for both walls 49+700 49+750 RHS 11/14/2021 11/15/2021
Drain

EPC-06/STR/3879 Layout marking and OGL checking for excavation MNB 58+787 BHS 11/15/2021 11/16/2021

EPC-06/STR/3880 Dismantling of existing structure MNB 58+787 BHS 11/15/2021 11/16/2021

RCC Cover
EPC-06/STR/3881 Shuttering and reinforcement checking for Slab 49+650 49+700 RHS 11/15/2021 11/16/2021
Drain
RCC Cover
EPC-06/STR/3882 Pouring of concrete RCC M-20 for Slab 49+650 49+700 RHS 11/15/2021 11/16/2021
Drain

EPC-06/STR/3897 Earthwork in excavation for Box Culvert MNB 58+787 BHS 11/16/2021 11/17/2021

RCC Cover
EPC-06/STR/3898 Shuttering and reinforcement checking for both walls 49+750 49+800 RHS 11/16/2021 11/17/2021
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/3899 Pouring of concrete RCC M-20 for both walls 49+750 49+800 RHS 11/16/2021 11/17/2021
Drain

EPC-06/STR/3914 EGL checking and Boulder Soling below PCC MNB 58+787 BHS 11/17/2021 11/18/2021

EPC-06/STR/3915 Layout marking and OGL checking for excavation MNB 49+026 BHS 11/17/2021 11/18/2021

EPC-06/STR/3916 Dismantling of existing structure MNB 49+026 BHS 11/17/2021 11/18/2021

RCC Cover
EPC-06/STR/3917 Shuttering and reinforcement checking for Slab 49+700 49+750 RHS 11/17/2021 11/18/2021
Drain
RCC Cover
EPC-06/STR/3918 Pouring of concrete RCC M-20 for Slab 49+700 49+750 RHS 11/17/2021 11/18/2021
Drain

EPC-06/STR/3933 Pouring of concrete PCC M-15 below raft with Cut off wall MNB 58+787 BHS 11/18/2021 11/19/2021

EPC-06/STR/3934 Earthwork in excavation for Box Culvert MNB 49+026 BHS 11/18/2021 11/19/2021

RCC Open
EPC-06/STR/3935 Earthwork in excavation for RCC drain 78+760 78+910 RHS 11/18/2021 11/19/2021
Drain
RCC Cover
EPC-06/STR/3936 Shuttering and reinforcement checking for both walls 49+800 49+850 RHS 11/18/2021 11/19/2021
Drain
RCC Cover
EPC-06/STR/3937 Pouring of concrete RCC M-20 for both walls 49+800 49+850 RHS 11/18/2021 11/19/2021
Drain

EPC-06/STR/3952 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 53+404 BHS 11/19/2021 11/20/2021

EPC-06/STR/3953 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 53+404 BHS 11/19/2021 11/20/2021

EPC-06/STR/3954 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 95+361 BHS 11/19/2021 11/20/2021

EPC-06/STR/3955 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 95+361 BHS 11/19/2021 11/20/2021

EPC-06/STR/3956 EGL checking and Boulder Soling below PCC MNB 49+026 BHS 11/19/2021 11/20/2021

EPC-06/STR/3957 Pouring of concrete PCC M-15 below Approach Slab MNB 64+941 RHS 11/19/2021 11/20/2021

RCC Cover
EPC-06/STR/3958 Shuttering and reinforcement checking for Slab 49+750 49+800 RHS 11/19/2021 11/20/2021
Drain
RCC Cover
EPC-06/STR/3959 Pouring of concrete RCC M-20 for Slab 49+750 49+800 RHS 11/19/2021 11/20/2021
Drain

EPC-06/STR/3974 Shuttering and reinforcement checking for top slab Box Culvert 53+404 BHS 11/20/2021 11/21/2021

EPC-06/STR/3975 Pouring of concrete RCC M-25 for top slab Box Culvert 53+404 BHS 11/20/2021 11/21/2021

EPC-06/STR/3976 Pouring of concrete PCC M-15 below raft with Cut off wall MNB 49+026 BHS 11/20/2021 11/21/2021

EPC-06/STR/3977 Shuttering and reinforcement checking for Approach Slab MNB 64+941 RHS 11/20/2021 11/21/2021

EPC-06/STR/3978 Pouring of concrete RCC M-30 for Approach Slab MNB 64+941 RHS 11/20/2021 11/21/2021

RCC Open
EPC-06/STR/3979 EGL checking and Pouring of concrete PCC M-15 below Raft 78+760 78+910 RHS 11/20/2021 11/21/2021
Drain
RCC Cover
EPC-06/STR/3980 Shuttering and reinforcement checking for both walls 49+850 49+900 RHS 11/20/2021 11/21/2021
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/3981 Pouring of concrete RCC M-20 for both walls 49+850 49+900 RHS 11/20/2021 11/21/2021
Drain

EPC-06/STR/3996 Layout marking and OGL checking for excavation Box Culvert 100+952 BHS 11/21/2021 11/22/2021

EPC-06/STR/3997 Dismantling of existing structure Box Culvert 100+952 BHS 11/21/2021 11/22/2021

RCC Cover
EPC-06/STR/3998 Shuttering and reinforcement checking for Slab 49+800 49+850 RHS 11/21/2021 11/22/2021
Drain
RCC Cover
EPC-06/STR/3999 Pouring of concrete RCC M-20 for Slab 49+800 49+850 RHS 11/21/2021 11/22/2021
Drain

EPC-06/STR/4014 Shuttering and reinforcement checking for top slab Box Culvert 95+361 BHS 11/22/2021 11/23/2021

EPC-06/STR/4015 Pouring of concrete RCC M-25 for top slab Box Culvert 95+361 BHS 11/22/2021 11/23/2021

EPC-06/STR/4016 Earthwork in excavation for Box Culvert Box Culvert 100+952 BHS 11/22/2021 11/23/2021

RCC Open
EPC-06/STR/4017 Pouring of concrete RCC M-20 for raft 78+760 78+910 RHS 11/22/2021 11/23/2021
Drain
RCC Cover
EPC-06/STR/4018 Shuttering and reinforcement checking for Slab 49+850 49+900 RHS 11/22/2021 11/23/2021
Drain
RCC Cover
EPC-06/STR/4019 Pouring of concrete RCC M-20 for Slab 49+850 49+900 RHS 11/22/2021 11/23/2021
Drain

EPC-06/STR/4034 Shuttering and reinforcement checking for raft Box Culvert 54+601 BHS 11/23/2021 11/24/2021

EPC-06/STR/4035 Pouring of concrete RCC M-25 for raft Box Culvert 54+601 BHS 11/23/2021 11/24/2021

EPC-06/STR/4036 EGL checking and Boulder Soling below PCC Box Culvert 100+952 BHS 11/23/2021 11/24/2021

EPC-06/STR/4051 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 55+343 BHS 11/24/2021 11/25/2021

EPC-06/STR/4052 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 55+343 BHS 11/24/2021 11/25/2021

EPC-06/STR/4053 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 100+952 BHS 11/24/2021 11/25/2021

RCC Open
EPC-06/STR/4054 Shuttering and reinforcement checking for both walls 78+760 78+810 RHS 11/24/2021 11/25/2021
Drain
RCC Open
EPC-06/STR/4055 Pouring of concrete RCC M-20 for both walls 78+760 78+810 RHS 11/24/2021 11/25/2021
Drain

EPC-06/STR/4080 Shuttering and reinforcement checking for top slab Box Culvert 55+343 BHS 11/26/2021 11/27/2021

EPC-06/STR/4081 Pouring of concrete RCC M-25 for top slab Box Culvert 55+343 BHS 11/26/2021 11/27/2021

RCC Open
EPC-06/STR/4082 Shuttering and reinforcement checking for both walls 78+810 78+860 RHS 11/26/2021 11/27/2021
Drain
RCC Open
EPC-06/STR/4083 Pouring of concrete RCC M-20 for both walls 78+810 78+860 RHS 11/26/2021 11/27/2021
Drain

EPC-06/STR/4108 Layout marking and OGL checking for excavation MNB 100+780 BHS 11/28/2021 11/29/2021

EPC-06/STR/4109 Dismantling of existing structure MNB 100+780 BHS 11/28/2021 11/29/2021

RCC Open
EPC-06/STR/4110 Shuttering and reinforcement checking for both walls 78+860 78+910 RHS 11/28/2021 11/29/2021
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Open
EPC-06/STR/4111 Pouring of concrete RCC M-20 for both walls 78+860 78+910 RHS 11/28/2021 11/29/2021
Drain
RCC Open
EPC-06/STR/4112 Earthwork in excavation for RCC drain 78+760 78+910 LHS 11/28/2021 11/29/2021
Drain

EPC-06/STR/4127 Shuttering and reinforcement checking for raft Box Culvert 100+952 BHS 11/29/2021 11/30/2021

EPC-06/STR/4128 Pouring of concrete RCC M-25 for raft Box Culvert 100+952 BHS 11/29/2021 11/30/2021

EPC-06/STR/4129 Earthwork in excavation for Box Culvert MNB 100+780 BHS 11/29/2021 11/30/2021

EPC-06/STR/4144 EGL checking and Boulder Soling below PCC MNB 100+780 BHS 11/30/2021 12/1/2021

RCC Open
EPC-06/STR/4145 EGL checking and Pouring of concrete PCC M-15 below Raft 78+760 78+910 LHS 11/30/2021 12/1/2021
Drain

EPC-06/STR/4160 Pouring of concrete PCC M-15 below raft with Cut off wall MNB 100+780 BHS 12/1/2021 12/2/2021

RCC Open
EPC-06/STR/4175 Pouring of concrete RCC M-20 for raft 78+760 78+910 LHS 12/2/2021 12/3/2021
Drain

EPC-06/STR/4190 Shuttering and reinforcement checking for raft MNB 58+787 BHS 12/3/2021 12/4/2021

EPC-06/STR/4191 Pouring of concrete RCC M-30 for raft MNB 58+787 BHS 12/3/2021 12/4/2021

EPC-06/STR/4192 Layout marking and OGL checking for excavation MNB 99+329 BHS 12/3/2021 12/4/2021

EPC-06/STR/4193 Dismantling of existing structure MNB 99+329 BHS 12/3/2021 12/4/2021

RCC Open
EPC-06/STR/4208 Shuttering and reinforcement checking for both walls 78+760 78+810 LHS 12/4/2021 12/5/2021
Drain
RCC Open
EPC-06/STR/4209 Pouring of concrete RCC M-20 for both walls 78+760 78+810 LHS 12/4/2021 12/5/2021
Drain

EPC-06/STR/4210 Earthwork in excavation for Box Culvert MNB 99+329 BHS 12/4/2021 12/5/2021

EPC-06/STR/4225 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 100+952 BHS 12/5/2021 12/6/2021

EPC-06/STR/4226 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 100+952 BHS 12/5/2021 12/6/2021

EPC-06/STR/4227 EGL checking and Boulder Soling below PCC MNB 99+329 BHS 12/5/2021 12/6/2021

EPC-06/STR/4242 Shuttering and reinforcement checking for raft MNB 100+780 BHS 12/6/2021 12/7/2021

EPC-06/STR/4243 Pouring of concrete RCC M-30 for raft MNB 100+780 BHS 12/6/2021 12/7/2021

RCC Open
EPC-06/STR/4244 Shuttering and reinforcement checking for both walls 78+810 78+860 LHS 12/6/2021 12/7/2021
Drain
RCC Open
EPC-06/STR/4245 Pouring of concrete RCC M-20 for both walls 78+810 78+860 LHS 12/6/2021 12/7/2021
Drain

EPC-06/STR/4246 Pouring of concrete PCC M-15 below raft with Cut off wall MNB 99+329 BHS 12/6/2021 12/7/2021

EPC-06/STR/4261 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 54+601 BHS 12/7/2021 12/8/2021

EPC-06/STR/4262 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 54+601 BHS 12/7/2021 12/8/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/4263 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 100+952 BHS 12/7/2021 12/8/2021

EPC-06/STR/4264 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 100+952 BHS 12/7/2021 12/8/2021

Shuttering and reinforcement checking for wall 1st lift with bottom hunch A1 & A2
EPC-06/STR/4265 MNB 58+787 BHS 12/7/2021 12/8/2021
side

EPC-06/STR/4266 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch A1 & A2 side MNB 58+787 BHS 12/7/2021 12/8/2021

EPC-06/STR/4267 Shuttering and reinforcement checking for raft MNB 49+026 BHS 12/7/2021 12/8/2021

EPC-06/STR/4268 Pouring of concrete RCC M-30 for raft MNB 49+026 BHS 12/7/2021 12/8/2021

EPC-06/STR/4283 Shuttering and reinforcement checking for top slab Box Culvert 100+952 BHS 12/8/2021 12/9/2021

EPC-06/STR/4284 Pouring of concrete RCC M-25 for top slab Box Culvert 100+952 BHS 12/8/2021 12/9/2021

EPC-06/STR/4285 Shuttering and reinforcement checking for raft MNB 99+329 BHS 12/8/2021 12/9/2021

EPC-06/STR/4286 Pouring of concrete RCC M-30 for raft MNB 99+329 BHS 12/8/2021 12/9/2021

EPC-06/STR/4301 Shuttering and reinforcement checking for wall 2nd lift- A1 & A2 side MNB 58+787 BHS 12/9/2021 12/10/2021

EPC-06/STR/4302 Pouring of concrete RCC M-30 for wall 2nd lift - A1 & A2 side MNB 58+787 BHS 12/9/2021 12/10/2021

Shuttering and reinforcement checking for wall 1st lift with bottom hunch A1 & A2
EPC-06/STR/4303 MNB 49+026 BHS 12/9/2021 12/10/2021
side

EPC-06/STR/4304 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch A1 & A2 side MNB 49+026 BHS 12/9/2021 12/10/2021

Shuttering and reinforcement checking for wall 1st lift with bottom hunch A1 & A2
EPC-06/STR/4305 MNB 100+780 BHS 12/9/2021 12/10/2021
side

EPC-06/STR/4306 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch A1 & A2 side MNB 100+780 BHS 12/9/2021 12/10/2021

RCC Open
EPC-06/STR/4307 Shuttering and reinforcement checking for both walls 78+860 78+910 LHS 12/9/2021 12/10/2021
Drain
RCC Open
EPC-06/STR/4308 Pouring of concrete RCC M-20 for both walls 78+860 78+910 LHS 12/9/2021 12/10/2021
Drain
RCC Open
EPC-06/STR/4309 Earthwork in excavation for RCC drain 81+730 81+820 LHS 12/9/2021 12/10/2021
Drain
RCC Open
EPC-06/STR/4310 EGL checking and Pouring of concrete PCC M-15 below Raft 81+730 81+820 LHS 12/9/2021 12/10/2021
Drain

EPC-06/STR/4311 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 54+601 BHS 12/9/2021 12/10/2021

EPC-06/STR/4312 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 54+601 BHS 12/9/2021 12/10/2021

RCC Open
EPC-06/STR/4327 Pouring of concrete RCC M-20 for raft 81+730 81+820 LHS 12/10/2021 12/11/2021
Drain
Shuttering and reinforcement checking for Outer wall 1st lift with bottom hunch (Cell-
EPC-06/STR/4328 MNB 99+329 BHS 12/10/2021 12/11/2021
1 & 2)

EPC-06/STR/4329 Pouring of concrete RCC M-30 for Outer wall 1st lift with bottom hunch (Cell-1 & 2) MNB 99+329 BHS 12/10/2021 12/11/2021

EPC-06/STR/4330 Shuttering and reinforcement checking for top slab Box Culvert 54+601 BHS 12/10/2021 12/11/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/4331 Pouring of concrete RCC M-25 for top slab Box Culvert 54+601 BHS 12/10/2021 12/11/2021

Shuttering and reinforcement checking for Intermediate wall 1st lift with bottom
EPC-06/STR/4346 MNB 99+329 BHS 12/11/2021 12/12/2021
hunch -(Cell-1 & 2)
Pouring of concrete RCC M-30 for Intermediate wall 1st lift with bottom hunch -(Cell-
EPC-06/STR/4347 MNB 99+329 BHS 12/11/2021 12/12/2021
1 & 2)

EPC-06/STR/4362 Layout marking and OGL checking for excavation Box Culvert 101+494 BHS 12/12/2021 12/13/2021

EPC-06/STR/4363 Dismantling of existing structure Box Culvert 101+494 BHS 12/12/2021 12/13/2021

Shuttering and reinforcement checking for wall 1st lift with bottom hunch -
EPC-06/STR/4364 MNB 49+026 BHS 12/12/2021 12/13/2021
Intermediate wall

EPC-06/STR/4365 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch - Intermediate wall MNB 49+026 BHS 12/12/2021 12/13/2021

EPC-06/STR/4366 Shuttering and reinforcement checking for wall 2nd lift- A1 & A2 side MNB 49+026 BHS 12/12/2021 12/13/2021

EPC-06/STR/4367 Pouring of concrete RCC M-30 for wall 2nd lift - A1 & A2 side MNB 49+026 BHS 12/12/2021 12/13/2021

EPC-06/STR/4368 Shuttering and reinforcement checking for wall 2nd lift- A1 & A2 side MNB 100+780 BHS 12/12/2021 12/13/2021

EPC-06/STR/4369 Pouring of concrete RCC M-30 for wall 2nd lift - A1 & A2 side MNB 100+780 BHS 12/12/2021 12/13/2021

RCC Open
EPC-06/STR/4370 Shuttering and reinforcement checking for both walls 81+730 81+780 LHS 12/12/2021 12/13/2021
Drain
RCC Open
EPC-06/STR/4371 Pouring of concrete RCC M-20 for both walls 81+730 81+780 LHS 12/12/2021 12/13/2021
Drain
Shuttering and reinforcement checking for Outer wall 1st lift with bottom hunch (Cell-
EPC-06/STR/4372 MNB 99+329 BHS 12/12/2021 12/13/2021
3 & 4)

EPC-06/STR/4373 Pouring of concrete RCC M-30 for Outer wall 1st lift with bottom hunch (Cell-3 & 4) MNB 99+329 BHS 12/12/2021 12/13/2021

EPC-06/STR/4388 Earthwork in excavation for Box Culvert Box Culvert 101+494 BHS 12/13/2021 12/14/2021

Shuttering and reinforcement checking for wall 1st lift with bottom hunch -
EPC-06/STR/4389 MNB 58+787 BHS 12/13/2021 12/14/2021
Intermediate wall

EPC-06/STR/4390 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch - Intermediate wall MNB 58+787 BHS 12/13/2021 12/14/2021

Shuttering and reinforcement checking for Intermediate wall 1st lift with bottom
EPC-06/STR/4391 MNB 99+329 BHS 12/13/2021 12/14/2021
hunch -(Cell-3 & 4)
Pouring of concrete RCC M-30 for Intermediate wall 1st lift with bottom hunch -(Cell-
EPC-06/STR/4392 MNB 99+329 BHS 12/13/2021 12/14/2021
3 & 4)

EPC-06/STR/4407 EGL checking and Boulder Soling below PCC Box Culvert 101+494 BHS 12/14/2021 12/15/2021

EPC-06/STR/4408 Shuttering and reinforcement checking for wall 2nd lift- Intermediate wall MNB 58+787 BHS 12/14/2021 12/15/2021

EPC-06/STR/4409 Pouring of concrete RCC M-30 for wall 2nd lift- Intermediate wall MNB 58+787 BHS 12/14/2021 12/15/2021

Shuttering and reinforcement checking for wall 1st lift with bottom hunch -
EPC-06/STR/4410 MNB 100+780 BHS 12/14/2021 12/15/2021
Intermediate wall

EPC-06/STR/4411 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch - Intermediate wall MNB 100+780 BHS 12/14/2021 12/15/2021

RCC Open
EPC-06/STR/4412 Shuttering and reinforcement checking for both walls 81+780 81+820 LHS 12/14/2021 12/15/2021
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Open
EPC-06/STR/4413 Pouring of concrete RCC M-20 for both walls 81+780 81+820 LHS 12/14/2021 12/15/2021
Drain
RCC Cover
EPC-06/STR/4414 Earthwork in excavation for RCC drain 94+280 94+400 RHS 12/14/2021 12/15/2021
Drain
RCC Cover
EPC-06/STR/4415 EGL checking and Pouring of concrete PCC M-15 below Raft 94+280 94+400 RHS 12/14/2021 12/15/2021
Drain

EPC-06/STR/4416 Shuttering and reinforcement checking for Outer wall 2nd lift (Cell-1 & 2) MNB 99+329 BHS 12/14/2021 12/15/2021

EPC-06/STR/4417 Pouring of concrete RCC M-30 for Outer wall 2nd lift (Cell-1 & 2) MNB 99+329 BHS 12/14/2021 12/15/2021

EPC-06/STR/4433 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 101+494 BHS 12/15/2021 12/16/2021

EPC-06/STR/4434 Shuttering and reinforcement checking for wall 2nd lift- Intermediate wall MNB 49+026 BHS 12/15/2021 12/16/2021

EPC-06/STR/4435 Pouring of concrete RCC M-30 for wall 2nd lift- Intermediate wall MNB 49+026 BHS 12/15/2021 12/16/2021

EPC-06/STR/4436 Shuttering and reinforcement checking for Intermediate wall 2nd lift -(Cell-1 & 2) MNB 99+329 BHS 12/15/2021 12/16/2021

EPC-06/STR/4437 Pouring of concrete RCC M-30 for Intermediate wall 2nd lift -(Cell-1 & 2) MNB 99+329 BHS 12/15/2021 12/16/2021

EPC-06/STR/4452 Shuttering and reinforcement checking for wall 3rd lift- Intermediate wall MNB 49+026 BHS 12/16/2021 12/17/2021

EPC-06/STR/4453 Pouring of concrete RCC M-30 for wall 3rd lift- Intermediate wall MNB 49+026 BHS 12/16/2021 12/17/2021

EPC-06/STR/4454 Shuttering and reinforcement checking for wall 2nd lift- Intermediate wall MNB 100+780 BHS 12/16/2021 12/17/2021

EPC-06/STR/4455 Pouring of concrete RCC M-30 for wall 2nd lift- Intermediate wall MNB 100+780 BHS 12/16/2021 12/17/2021

RCC Cover
EPC-06/STR/4456 Pouring of concrete RCC M-20 for raft 94+280 94+400 RHS 12/16/2021 12/17/2021
Drain

EPC-06/STR/4457 Shuttering and reinforcement checking for Outer wall 2nd lift (Cell-3 & 4) MNB 99+329 BHS 12/16/2021 12/17/2021

EPC-06/STR/4458 Pouring of concrete RCC M-30 for Outer wall 2nd lift (Cell-3 & 4) MNB 99+329 BHS 12/16/2021 12/17/2021

EPC-06/STR/4473 Shuttering and reinforcement checking for wall 3rd lift- Intermediate wall MNB 58+787 BHS 12/17/2021 12/18/2021

EPC-06/STR/4474 Pouring of concrete RCC M-30 for wall 3rd lift- Intermediate wall MNB 58+787 BHS 12/17/2021 12/18/2021

EPC-06/STR/4475 Shuttering and reinforcement checking for wall 3rd lift- A1 & A2 side MNB 49+026 BHS 12/17/2021 12/18/2021

EPC-06/STR/4476 Pouring of concrete RCC M-30 for wall 3rd lift - A1 & A2 side MNB 49+026 BHS 12/17/2021 12/18/2021

EPC-06/STR/4477 Shuttering and reinforcement checking for Intermediate wall 2nd lift -(Cell-3 & 4) MNB 99+329 BHS 12/17/2021 12/18/2021

EPC-06/STR/4478 Pouring of concrete RCC M-30 for Intermediate wall 2nd lift -(Cell-3 & 4) MNB 99+329 BHS 12/17/2021 12/18/2021

EPC-06/STR/4493 Shuttering and reinforcement checking for wall 3rd lift- A1 & A2 side MNB 58+787 BHS 12/18/2021 12/19/2021

EPC-06/STR/4494 Pouring of concrete RCC M-30 for wall 3rd lift - A1 & A2 side MNB 58+787 BHS 12/18/2021 12/19/2021

EPC-06/STR/4495 Shuttering and reinforcement checking for wall final lift- Intermediate wall MNB 49+026 BHS 12/18/2021 12/19/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/4496 Pouring of concrete RCC M-30 for wall final lift- Intermediate wall MNB 49+026 BHS 12/18/2021 12/19/2021

EPC-06/STR/4497 Shuttering and reinforcement checking for wall final lift- Intermediate wall MNB 100+780 BHS 12/18/2021 12/19/2021

EPC-06/STR/4498 Pouring of concrete RCC M-30 for wall final lift- Intermediate wall MNB 100+780 BHS 12/18/2021 12/19/2021

RCC Cover
EPC-06/STR/4499 Shuttering and reinforcement checking for both walls 94+280 94+320 RHS 12/18/2021 12/19/2021
Drain
RCC Cover
EPC-06/STR/4500 Pouring of concrete RCC M-20 for both walls 94+280 94+320 RHS 12/18/2021 12/19/2021
Drain
Shuttering and reinforcement checking for Outer wall final lift (Cell-1 & 2) with hunch
EPC-06/STR/4501 MNB 99+329 BHS 12/18/2021 12/19/2021
A1 side
Pouring of concrete RCC M-30 for Outer wall final lift (Cell-1 & 2) with hunch A1
EPC-06/STR/4502 MNB 99+329 BHS 12/18/2021 12/19/2021
side

EPC-06/STR/4517 Shuttering and reinforcement checking for raft Box Culvert 101+494 BHS 12/19/2021 12/20/2021

EPC-06/STR/4518 Pouring of concrete RCC M-25 for raft Box Culvert 101+494 BHS 12/19/2021 12/20/2021

EPC-06/STR/4519 Shuttering and reinforcement checking for wall final lift with bracket- A1 & A2 side MNB 49+026 BHS 12/19/2021 12/20/2021

EPC-06/STR/4520 Pouring of concrete RCC M-30 for wall final lift with bracket- A1 & A2 side MNB 49+026 BHS 12/19/2021 12/20/2021

EPC-06/STR/4521 Shuttering and reinforcement checking for Intermediate wall final lift -(Cell-1 & 2) MNB 99+329 BHS 12/19/2021 12/20/2021

EPC-06/STR/4522 Pouring of concrete RCC M-30 for Intermediate wall final lift -(Cell-1 & 2) MNB 99+329 BHS 12/19/2021 12/20/2021

Shuttering and reinforcement checking for Outer wall final lift (Cell-3 & 4) with hunch
EPC-06/STR/4523 MNB 99+329 BHS 12/19/2021 12/20/2021
A2 side
Pouring of concrete RCC M-30 for Outer wall final lift (Cell-3 & 4) with hunch A2
EPC-06/STR/4524 MNB 99+329 BHS 12/19/2021 12/20/2021
side

EPC-06/STR/4525 Shuttering and reinforcement checking for wall final lift- Intermediate wall MNB 58+787 BHS 12/19/2021 12/20/2021

EPC-06/STR/4526 Pouring of concrete RCC M-30 for wall final lift- Intermediate wall MNB 58+787 BHS 12/19/2021 12/20/2021

EPC-06/STR/4541 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 101+494 BHS 12/20/2021 12/21/2021

EPC-06/STR/4542 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 101+494 BHS 12/20/2021 12/21/2021

EPC-06/STR/4543 Shuttering and reinforcement checking for top slab MNB 49+026 BHS 12/20/2021 12/21/2021

EPC-06/STR/4544 Pouring of concrete RCC M-30 for top slab MNB 49+026 BHS 12/20/2021 12/21/2021

EPC-06/STR/4545 Shuttering and reinforcement checking for wall final lift with bracket- A1 & A2 side MNB 100+780 BHS 12/20/2021 12/21/2021

EPC-06/STR/4546 Pouring of concrete RCC M-30 for wall final lift with bracket- A1 & A2 side MNB 100+780 BHS 12/20/2021 12/21/2021

RCC Cover
EPC-06/STR/4547 Shuttering and reinforcement checking for both walls 94+320 94+360 RHS 12/20/2021 12/21/2021
Drain
RCC Cover
EPC-06/STR/4548 Pouring of concrete RCC M-20 for both walls 94+320 94+360 RHS 12/20/2021 12/21/2021
Drain
RCC Open
EPC-06/STR/4549 Earthwork in excavation for RCC drain 51+420 51+590 LHS 12/20/2021 12/21/2021
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/4550 Shuttering and reinforcement checking for wall final lift with bracket- A1 & A2 side MNB 58+787 BHS 12/20/2021 12/21/2021

EPC-06/STR/4551 Pouring of concrete RCC M-30 for wall final lift with bracket- A1 & A2 side MNB 58+787 BHS 12/20/2021 12/21/2021

EPC-06/STR/4566 Shuttering and reinforcement checking for top slab MNB 100+780 BHS 12/21/2021 12/22/2021

EPC-06/STR/4567 Pouring of concrete RCC M-30 for top slab MNB 100+780 BHS 12/21/2021 12/22/2021

RCC Cover
EPC-06/STR/4568 Shuttering and reinforcement checking for Slab 94+280 94+340 RHS 12/21/2021 12/22/2021
Drain
RCC Cover
EPC-06/STR/4569 Pouring of concrete RCC M-20 for Slab 94+280 94+340 RHS 12/21/2021 12/22/2021
Drain
RCC Open
EPC-06/STR/4570 EGL checking and Pouring of concrete PCC M-15 below Raft 51+420 51+590 LHS 12/21/2021 12/22/2021
Drain

EPC-06/STR/4571 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 101+494 BHS 12/21/2021 12/22/2021

EPC-06/STR/4572 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 101+494 BHS 12/21/2021 12/22/2021

EPC-06/STR/4573 Shuttering and reinforcement checking for top slab Box Culvert 101+494 BHS 12/21/2021 12/22/2021

EPC-06/STR/4574 Pouring of concrete RCC M-25 for top slab Box Culvert 101+494 BHS 12/21/2021 12/22/2021

EPC-06/STR/4575 Shuttering and reinforcement checking for Intermediate wall final lift -(Cell-3 & 4) MNB 99+329 BHS 12/21/2021 12/22/2021

EPC-06/STR/4576 Pouring of concrete RCC M-30 for Intermediate wall final lift -(Cell-3 & 4) MNB 99+329 BHS 12/21/2021 12/22/2021

EPC-06/STR/4577 Shuttering and reinforcement checking for top slab MNB 58+787 BHS 12/21/2021 12/22/2021

EPC-06/STR/4578 Pouring of concrete RCC M-30 for top slab MNB 58+787 BHS 12/21/2021 12/22/2021

RCC Cover
EPC-06/STR/4593 Shuttering and reinforcement checking for both walls 94+360 94+400 RHS 12/22/2021 12/23/2021
Drain
RCC Cover
EPC-06/STR/4594 Pouring of concrete RCC M-20 for both walls 94+360 94+400 RHS 12/22/2021 12/23/2021
Drain
RCC Open
EPC-06/STR/4595 Pouring of concrete RCC M-20 for raft 51+420 51+590 LHS 12/22/2021 12/23/2021
Drain
RCC Cover
EPC-06/STR/4610 Shuttering and reinforcement checking for Slab 94+340 94+400 RHS 12/23/2021 12/24/2021
Drain
RCC Cover
EPC-06/STR/4611 Pouring of concrete RCC M-20 for Slab 94+340 94+400 RHS 12/23/2021 12/24/2021
Drain
RCC Open
EPC-06/STR/4626 Shuttering and reinforcement checking for both walls 51+420 51+460 LHS 12/24/2021 12/25/2021
Drain
RCC Open
EPC-06/STR/4627 Pouring of concrete RCC M-20 for both walls 51+420 51+460 LHS 12/24/2021 12/25/2021
Drain
RCC Open
EPC-06/STR/4642 Shuttering and reinforcement checking for both walls 51+460 51+500 LHS 12/25/2021 12/26/2021
Drain
RCC Open
EPC-06/STR/4643 Pouring of concrete RCC M-20 for both walls 51+460 51+500 LHS 12/25/2021 12/26/2021
Drain
RCC Open
EPC-06/STR/4668 Shuttering and reinforcement checking for both walls 51+500 51+540 LHS 12/27/2021 12/28/2021
Drain
RCC Open
EPC-06/STR/4669 Pouring of concrete RCC M-20 for both walls 51+500 51+540 LHS 12/27/2021 12/28/2021
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Open
EPC-06/STR/4684 Shuttering and reinforcement checking for both walls 51+540 51+590 LHS 12/28/2021 12/29/2021
Drain
RCC Open
EPC-06/STR/4685 Pouring of concrete RCC M-20 for both walls 51+540 51+590 LHS 12/28/2021 12/29/2021
Drain

EPC-06/STR/4700 Shuttering and reinforcement checking for Slab (Bus Shelter) Bus Shelter 80+960 LHS 12/28/2021 12/29/2021

EPC-06/STR/4701 Pouring of concrete RCC M-25 for Slab (Bus Shelter) Bus Shelter 80+960 LHS 12/28/2021 12/29/2021

EPC-06/STR/4194 Pouring of concrete PCC M-15 below Approach Slab MNB 48+006 LHS 12/3/2021 12/4/2021

EPC-06/STR/4211 Shuttering and reinforcement checking for Approach Slab MNB 48+006 LHS 12/4/2021 12/5/2021

EPC-06/STR/4211 Pouring of concrete RCC M-30 for Approach Slab MNB 48+006 LHS 12/4/2021 12/5/2021

EPC-06/STR/4287 Pouring of concrete PCC M-15 below Approach Slab MNB 49+026 LHS 12/8/2021 12/9/2021

EPC-06/STR/4313 Shuttering and reinforcement checking for Approach Slab MNB 49+026 LHS 12/9/2021 12/10/2021

EPC-06/STR/4314 Pouring of concrete RCC M-30 for Approach Slab MNB 49+026 LHS 12/9/2021 12/10/2021

EPC-06/STR/4418 Pouring of concrete PCC M-15 below Approach Slab MNB 58+787 RHS 12/14/2021 12/15/2021

EPC-06/STR/4438 Shuttering and reinforcement checking for Approach Slab MNB 58+787 RHS 12/15/2021 12/16/2021

EPC-06/STR/4439 Pouring of concrete RCC M-30 for Approach Slab MNB 58+787 RHS 12/15/2021 12/16/2021

EPC-06/STR/4760 Pouring of concrete PCC M-15 below Approach Slab MNB 48+006 RHS 1/3/2022 1/4/2022

EPC-06/STR/4761 Pouring of concrete PCC M-15 below Approach Slab MNB 91+264 LHS 1/3/2022 1/4/2022

EPC-06/STR/4771 Shuttering and reinforcement checking for Approach Slab MNB 48+006 RHS 1/4/2022 1/5/2022

EPC-06/STR/4772 Pouring of concrete RCC M-30 for Approach Slab MNB 48+006 RHS 1/4/2022 1/5/2022

EPC-06/STR/4773 Shuttering and reinforcement checking for Approach Slab MNB 91+264 LHS 1/4/2022 1/5/2022

EPC-06/STR/4774 Pouring of concrete RCC M-30 for Approach Slab MNB 91+264 LHS 1/4/2022 1/5/2022

EPC-06/STR/4814 Pouring of concrete PCC M-15 below Approach Slab MNB 49+026 RHS 1/8/2022 1/9/2022

EPC-06/STR/4824 Shuttering and reinforcement checking for Approach Slab MNB 49+026 RHS 1/9/2022 1/10/2022

EPC-06/STR/4825 Pouring of concrete RCC M-30 for Approach Slab MNB 49+026 RHS 1/9/2022 1/10/2022

EPC-06/STR/4865 Pouring of concrete PCC M-15 below Approach Slab MNB 100+780 RHS 1/13/2022 1/14/2022

EPC-06/STR/4875 Pouring of concrete PCC M-15 below Approach Slab MNB 58+787 LHS 1/14/2022 1/15/2022
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/4876 Shuttering and reinforcement checking for Approach Slab MNB 100+780 RHS 1/14/2022 1/15/2022

EPC-06/STR/4877 Pouring of concrete RCC M-30 for Approach Slab MNB 100+780 RHS 1/14/2022 1/15/2022

EPC-06/STR/4887 Shuttering and reinforcement checking for Approach Slab MNB 58+787 LHS 1/15/2022 1/16/2022

EPC-06/STR/4888 Pouring of concrete RCC M-30 for Approach Slab MNB 58+787 LHS 1/15/2022 1/16/2022

EPC-06/STR/4948 Layout marking and OGL checking for excavation Box Culvert 103+301 BHS 1/26/2022 1/27/2022

EPC-06/STR/4949 Dismantling of existing structure Box Culvert 103+301 BHS 1/26/2022 1/27/2022

EPC-06/STR/4959 Earthwork in excavation for Box Culvert Box Culvert 103+301 BHS 1/27/2022 1/28/2022

EPC-06/STR/4960 EGL checking and Boulder Soling below PCC Box Culvert 103+301 BHS 1/27/2022 1/28/2022

EPC-06/STR/4970 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 103+301 BHS 1/28/2022 1/29/2022

EPC-06/STR/4990 Shuttering and reinforcement checking for raft Box Culvert 103+301 BHS 1/30/2022 1/31/2022

EPC-06/STR/4991 Pouring of concrete RCC M-25 for raft Box Culvert 103+301 BHS 1/30/2022 1/31/2022

EPC-06/STR/5011 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 103+301 BHS 2/1/2022 2/2/2022

EPC-06/STR/5012 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 103+301 BHS 2/1/2022 2/2/2022

EPC-06/STR/5013 Shuttering and reinforcement checking for roof slab Bus Shelter 80+980 LHS 2/1/2022 2/2/2022

EPC-06/STR/5014 Pouring of concrete RCC M-25 for roof slab Bus Shelter 80+980 LHS 2/1/2022 2/2/2022

EPC-06/STR/5034 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 103+301 BHS 2/3/2022 2/4/2022

EPC-06/STR/5035 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 103+301 BHS 2/3/2022 2/4/2022

EPC-06/STR/5036 Pouring of concrete PCC M-15 below Approach Slab MNB 91+264 RHS 2/3/2022 2/4/2022

EPC-06/STR/5046 Shuttering and reinforcement checking for Approach Slab MNB 91+264 RHS 2/4/2022 2/5/2022

EPC-06/STR/5047 Pouring of concrete RCC M-30 for Approach Slab MNB 91+264 RHS 2/4/2022 2/5/2022

EPC-06/STR/5057 Shuttering and reinforcement checking for top slab Box Culvert 103+301 BHS 2/5/2022 2/6/2022

EPC-06/STR/5058 Pouring of concrete RCC M-25 for top slab Box Culvert 103+301 BHS 2/5/2022 2/6/2022

EPC-06/STR/5068 Layout marking and OGL checking for excavation Box Culvert 102+076 BHS 2/6/2022 2/7/2022

EPC-06/STR/5069 Dismantling of existing structure Box Culvert 102+076 BHS 2/6/2022 2/7/2022

EPC-06/STR/5079 Earthwork in excavation for Box Culvert Box Culvert 102+076 BHS 2/7/2022 2/8/2022

EPC-06/STR/5080 EGL checking and Boulder Soling below PCC Box Culvert 102+076 BHS 2/7/2022 2/8/2022
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/5090 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 102+076 BHS 2/8/2022 2/9/2022

EPC-06/STR/5110 Shuttering and reinforcement checking for raft Box Culvert 102+076 BHS 2/10/2022 2/11/2022

EPC-06/STR/5111 Pouring of concrete RCC M-25 for raft Box Culvert 102+076 BHS 2/10/2022 2/11/2022

EPC-06/STR/5121 Shuttering and reinforcement checking for top slab (Cell 3 & 4) with bracket A2 side MNB 99+329 2/11/2022 2/12/2022

EPC-06/STR/5122 Pouring of concrete RCC M-30 for top slab (Cell 3 & 4) with bracket A2 side MNB 99+329 2/11/2022 2/12/2022

EPC-06/STR/5132 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 102+076 BHS 2/12/2022 2/13/2022

EPC-06/STR/5133 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 102+076 BHS 2/12/2022 2/13/2022

EPC-06/STR/5134 Layout marking and OGL checking for excavation MNB 97+722 BHS 2/12/2022 2/13/2022

EPC-06/STR/5135 Dismantling of existing structure MNB 97+722 BHS 2/12/2022 2/13/2022

EPC-06/STR/5145 Pouring of concrete PCC M-15 below Approach Slab MNB 100+780 LHS 2/13/2022 2/14/2022

EPC-06/STR/5155 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 102+076 BHS 2/14/2022 2/15/2022

EPC-06/STR/5156 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 102+076 BHS 2/14/2022 2/15/2022

EPC-06/STR/5157 Shuttering and reinforcement checking for Approach Slab MNB 100+780 LHS 2/14/2022 2/15/2022

EPC-06/STR/5158 Pouring of concrete RCC M-30 for Approach Slab MNB 100+780 LHS 2/14/2022 2/15/2022

EPC-06/STR/5168 Earthwork in excavation for Box Culvert MNB 97+722 BHS 2/15/2022 2/16/2022

EPC-06/STR/5178 Shuttering and reinforcement checking for top slab Box Culvert 102+076 BHS 2/16/2022 2/17/2022

EPC-06/STR/5179 Pouring of concrete RCC M-25 for top slab Box Culvert 102+076 BHS 2/16/2022 2/17/2022

EPC-06/STR/5199 EGL checking and Boulder Soling below PCC MNB 97+722 BHS 2/18/2022 2/19/2022

EPC-06/STR/5219 Pouring of concrete PCC M-15 below raft MNB 97+722 BHS 2/20/2022 2/21/2022

EPC-06/STR/5259 Shuttering and reinforcement checking for raft MNB 97+722 BHS 2/23/2022 2/24/2022

EPC-06/STR/5260 Pouring of concrete RCC M-30 for raft MNB 97+722 BHS 2/23/2022 2/24/2022

Shuttering and reinforcement checking for wall 1st lift with bottom hunch A1 & A2
EPC-06/STR/5320 MNB 97+722 BHS 2/28/2022 3/1/2022
side

EPC-06/STR/5321 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch A1 & A2 side MNB 97+722 BHS 2/28/2022 3/1/2022

EPC-06/STR/5381 Shuttering and reinforcement checking for top slab (Cell 1 & 2) with bracket A1 side MNB 99+329 3/2/2022 3/3/2022

EPC-06/STR/5382 Pouring of concrete RCC M-30 for top slab (Cell 1 & 2) with bracket A1 side MNB 99+329 3/2/2022 3/3/2022

Shuttering and reinforcement checking for wall 1st lift with bottom hunch -
EPC-06/STR/5392 MNB 97+722 BHS 3/3/2022 3/4/2022
Intermediate wall- 1 & 2
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch - Intermediate wall-
EPC-06/STR/5393 MNB 97+722 BHS 3/3/2022 3/4/2022
1&2

EPC-06/STR/5423 Shuttering and reinforcement checking for roof slab Bus Shelter 94+133 RHS 3/6/2022 3/7/2022

EPC-06/STR/5424 Pouring of concrete RCC M-25 for roof slab Bus Shelter 94+133 RHS 3/6/2022 3/7/2022

EPC-06/STR/5425 Shuttering and reinforcement checking for wall 2nd lift- A1 & A2 side MNB 97+722 BHS 3/6/2022 3/7/2022

EPC-06/STR/5426 Pouring of concrete RCC M-30 for wall 2nd lift - A1 & A2 side MNB 97+722 BHS 3/6/2022 3/7/2022

EPC-06/STR/5486 Shuttering and reinforcement checking for roof slab Bus Shelter 94+183 LHS 3/9/2022 3/10/2022

EPC-06/STR/5487 Pouring of concrete RCC M-25 for roof slab Bus Shelter 94+183 LHS 3/9/2022 3/10/2022

EPC-06/STR/5488 Shuttering and reinforcement checking for wall 2nd lift- Intermediate wall- 1 & 2 MNB 97+722 BHS 3/9/2022 3/10/2022

EPC-06/STR/5489 Pouring of concrete RCC M-30 for wall 2nd lift- Intermediate wall- 1 & 2 MNB 97+722 BHS 3/9/2022 3/10/2022

EPC-06/STR/5499 Layout marking and OGL checking for excavation Box Culvert 107+755 BHS 3/10/2022 3/11/2022

EPC-06/STR/5500 Dismantling of existing structure Box Culvert 107+755 BHS 3/10/2022 3/11/2022

EPC-06/STR/5510 Earthwork in excavation for Box Culvert Box Culvert 107+755 BHS 3/11/2022 3/12/2022

EPC-06/STR/5511 EGL checking and Boulder Soling below PCC Box Culvert 107+755 BHS 3/11/2022 3/12/2022

EPC-06/STR/5521 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 107+755 BHS 3/12/2022 3/13/2022

EPC-06/STR/5522 Shuttering and reinforcement checking for wall 3rd lift- Intermediate wall- 1 & 2 MNB 97+722 BHS 3/12/2022 3/13/2022

EPC-06/STR/5523 Pouring of concrete RCC M-30 for wall 3rd lift- Intermediate wall- 1 & 2 MNB 97+722 BHS 3/12/2022 3/13/2022

EPC-06/STR/5548 Shuttering and reinforcement checking for raft Box Culvert 107+755 BHS 3/14/2022 3/15/2022

EPC-06/STR/5549 Pouring of concrete RCC M-25 for raft Box Culvert 107+755 BHS 3/14/2022 3/15/2022

EPC-06/STR/5550 Shuttering and reinforcement checking for roof slab Bus Shelter 90+990 LHS 3/14/2022 3/15/2022

EPC-06/STR/5551 Pouring of concrete RCC M-25 for roof slab Bus Shelter 90+990 LHS 3/14/2022 3/15/2022

EPC-06/STR/5561 Shuttering and reinforcement checking for wall 3rd lift- A1 & A2 side MNB 97+722 BHS 3/15/2022 3/16/2022

EPC-06/STR/5562 Pouring of concrete RCC M-30 for wall 3rd lift - A1 & A2 side MNB 97+722 BHS 3/15/2022 3/16/2022

EPC-06/STR/5572 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 107+755 BHS 3/16/2022 3/17/2022

EPC-06/STR/5573 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 107+755 BHS 3/16/2022 3/17/2022

EPC-06/STR/5574 Shuttering and reinforcement checking for roof slab Bus Shelter 90+920 RHS 3/16/2022 3/17/2022

EPC-06/STR/5575 Pouring of concrete RCC M-25 for roof slab Bus Shelter 90+920 RHS 3/16/2022 3/17/2022
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/5585 Shuttering and reinforcement checking for wall final lift- Intermediate wall- 1 & 2 MNB 97+722 BHS 3/17/2022 3/18/2022

EPC-06/STR/5586 Pouring of concrete RCC M-30 for wall final lift- Intermediate wall-1 & 2 MNB 97+722 BHS 3/17/2022 3/18/2022

EPC-06/STR/5596 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 107+755 BHS 3/18/2022 3/19/2022

EPC-06/STR/5597 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 107+755 BHS 3/18/2022 3/19/2022

EPC-06/STR/5598 Layout marking and OGL checking for excavation MNB 68+779 BHS 3/18/2022 3/19/2022

EPC-06/STR/5599 Dismantling of existing structure MNB 68+779 BHS 3/18/2022 3/19/2022

EPC-06/STR/5600 Earthwork in excavation for Box Culvert MNB 68+779 BHS 3/18/2022 3/19/2022

EPC-06/STR/5601 EGL checking and Boulder Soling below PCC MNB 68+779 BHS 3/18/2022 3/19/2022

EPC-06/STR/5602 Pouring of concrete PCC M-15 below raft with Cut off wall MNB 68+779 BHS 3/18/2022 3/19/2022

EPC-06/STR/5610 Shuttering and reinforcement checking for raft MNB 68+779 BHS 3/19/2022 3/20/2022

EPC-06/STR/5611 Pouring of concrete RCC M-30 for raft MNB 68+779 BHS 3/19/2022 3/20/2022

EPC-06/STR/5622 Shuttering and reinforcement checking for top slab Box Culvert 107+755 BHS 3/20/2022 3/21/2022

EPC-06/STR/5623 Pouring of concrete RCC M-25 for top slab Box Culvert 107+755 BHS 3/20/2022 3/21/2022

EPC-06/STR/5624 Shuttering and reinforcement checking for roof slab Bus Shelter 89+000 LHS 3/20/2022 3/21/2022

EPC-06/STR/5625 Pouring of concrete RCC M-25 for roof slab Bus Shelter 89+000 LHS 3/20/2022 3/21/2022

Shuttering and reinforcement checking for wall 1st lift with bottom hunch A1 & A2
EPC-06/STR/5626 MNB 68+779 BHS 3/20/2022 3/21/2022
side

EPC-06/STR/5627 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch A1 & A2 side MNB 68+779 BHS 3/20/2022 3/21/2022

EPC-06/STR/5635 Shuttering and reinforcement checking for wall final lift with bracket- A1 & A2 side MNB 97+722 BHS 3/21/2022 3/22/2022

EPC-06/STR/5636 Pouring of concrete RCC M-30 for wall final lift with bracket- A1 & A2 side MNB 97+722 BHS 3/21/2022 3/22/2022

Shuttering and reinforcement checking for wall 1st lift with bottom hunch -
EPC-06/STR/5637 MNB 68+779 BHS 3/21/2022 3/22/2022
Intermediate wall

EPC-06/STR/5638 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch - Intermediate wall MNB 68+779 BHS 3/21/2022 3/22/2022

EPC-06/STR/5639 Shuttering and reinforcement checking for wall final lift- Intermediate wall MNB 68+779 BHS 3/22/2022 3/23/2022

EPC-06/STR/5640 Pouring of concrete RCC M-30 for wall final lift- Intermediate wall MNB 68+779 BHS 3/22/2022 3/23/2022

EPC-06/STR/5661 Shuttering and reinforcement checking for roof slab Bus Shelter 88+960 RHS 3/23/2022 3/24/2022

EPC-06/STR/5662 Pouring of concrete RCC M-25 for roof slab Bus Shelter 88+960 RHS 3/23/2022 3/24/2022

EPC-06/STR/5663 Shuttering and reinforcement checking for wall final lift with bracket- A1 & A2 side MNB 68+779 BHS 3/23/2022 3/24/2022
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/5664 Pouring of concrete RCC M-30 for wall final lift with bracket- A1 & A2 side MNB 68+779 BHS 3/23/2022 3/24/2022

EPC-06/STR/5715

EPC-06/STR/5765 Approch Slab MNB 99+329 4/5/2022 4/6/2022

EPC-06/STR/5865 Drain Slab 94+280 94+340 LHS 4/14/2022 4/15/2022


6.00

EPC-06/STR/5875 Drain Slab 94+340 94+400 LHS 4/15/2022 4/16/2022


6.00

EPC-06/STR/5975 MNB Slab MNB 68+779 4/25/2022 4/26/2022

EPC-06/STR/6065 Drain Wall 44+340 44+430 LHS 5/4/2022 5/5/2022


14.40

EPC-06/STR/6075 Drain Wall 44+430 44+520 LHS 5/5/2022 5/6/2022


14.40

EPC-06/STR/6095 Drain Wall 44+520 44+610 LHS 6/7/2022 6/8/2022


14.40

EPC-06/STR/6115 Drain Wall 44+610 44+680 LHS 5/9/2022 5/10/2022


11.20

EPC-06/STR/6165 Drain Wall 44+480 44+570 RHS 5/14/2022 5/15/2022


14.40

EPC-06/STR/6175 Drain Wall 44+570 44+660 RHS 5/15/2022 5/16/2022


14.40

EPC-06/STR/6195 Drain Wall 44+660 44+680 RHS 5/17/2022 5/18/2022


3.20

EPC-06/STR/6265 Drain Wall 49+500 49+590 LHS 5/24/2022 5/25/2022


14.40

EPC-06/STR/6275 MNB Slab MNB 97+722 5/25/2022 5/26/2022

EPC-06/STR/6285 Drain Wall 49+590 49+680 LHS 5/26/2022 5/27/2022


14.40

EPC-06/STR/6335 Drain Wall 49+680 49+770 LHS 5/31/2022 6/1/2022


14.40

EPC-06/STR/6345 Drain Wall 49+770 49+860 LHS 6/1/2022 6/2/2022


14.40

EPC-06/STR/6355 Approch Slab MNB 68+779 6/2/2022 6/3/2022

EPC-06/STR/6365 Drain Wall 49+860 49+900 LHS 6/3/2022 6/4/2022


6.40

EPC-06/STR/6266 Layout marking and OGL checking for excavation Box Culvert 55+706 BHS 5/23/2022 5/24/2022
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/6267 Dismantling of existing structure Box Culvert 55+706 BHS 5/24/2022 5/25/2022

EPC-06/STR/6412 Earthwork in excavation for Box Culvert Box Culvert 55+706 BHS 6/6/2022 6/7/2022

EPC-06/STR/6417 EGL checking and Boulder Soling below PCC Box Culvert 55+706 BHS 6/7/2022 6/8/2022

EPC-06/STR/6422 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 55+706 BHS 6/8/2022 6/9/2022

EPC-06/STR/6427 Shuttering and reinforcement checking for raft Box Culvert 55+706 BHS 6/9/2022 6/10/2022

EPC-06/STR/6428 Pouring of concrete RCC M-25 for raft Box Culvert 55+706 BHS 6/9/2022 6/10/2022

EPC-06/STR/6433 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 55+706 BHS 6/11/2022 6/12/2022

EPC-06/STR/6434 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 55+706 BHS 6/11/2022 6/12/2022

EPC-06/STR/6436 Approch Slab MNB 97+722 BHS 6/15/2022 6/16/2022

EPC-06/STR/6439 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 55+706 BHS 6/15/2022 6/16/2022

EPC-06/STR/6440 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 55+706 BHS 6/15/2022 6/16/2022

EPC-06/STR/6445 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 55+706 BHS 6/17/2022 6/18/2022

EPC-06/STR/6446 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 55+706 BHS 6/17/2022 6/18/2022

EPC-06/STR/6451 Shuttering and reinforcement checking for top slab Box Culvert 55+706 BHS 6/19/2022 6/20/2022

EPC-06/STR/6452 Pouring of concrete RCC M-25 for top slab Box Culvert 55+706 BHS 6/19/2022 6/20/2022

EPC-06/STR/6453 Dismantling of existing structure Box Culvert 70+047 BHS 7/18/2022 7/19/2022

EPC-06/STR/6478 Layout marking and OGL checking for excavation Box Culvert 70+047 BHS 7/19/2022 7/20/2022

EPC-06/STR/6558 Earthwork in excavation for Box Culvert Box Culvert 70+047 BHS 8/6/2022 8/7/2022 8/6/2021

EPC-06/STR/6563 EGL checking and Boulder Soling below PCC Box Culvert 70+047 BHS 8/7/2022 8/8/2022 8/6/2021

EPC-06/STR/6568 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 70+047 BHS 8/8/2022 8/9/2022 8/7/2021

EPC-06/STR/6573 Shuttering and reinforcement checking for raft Box Culvert 70+047 BHS 8/10/2022 8/11/2022 8/8/2021

EPC-06/STR/6574 Pouring of concrete RCC M-25 for raft Box Culvert 70+047 BHS 8/10/2022 8/11/2022 8/9/2021

EPC-06/STR/6579 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 70+047 BHS 8/11/2022 8/12/2022 8/11/2021

EPC-06/STR/6580 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 70+047 BHS 8/11/2022 8/12/2022 8/11/2021

EPC-06/STR/6585 Shuttering and reinforcement checking for wall 2nd lift Box Culvert 70+047 BHS 8/12/2022 8/13/2022 8/12/2021

EPC-06/STR/6586 Pouring of concrete RCC M-25 for wall 2nd lift Box Culvert 70+047 BHS 8/12/2022 8/13/2022 8/12/2021
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

EPC-06/STR/6591 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 70+047 BHS 8/13/2022 8/14/2022 8/14/2021

EPC-06/STR/6592 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 70+047 BHS 8/13/2022 8/14/2022 8/14/2021

EPC-06/STR/6597 Shuttering and reinforcement checking for top slab Box Culvert 70+047 BHS 8/14/2022 8/15/2022 8/15/2021

EPC-06/STR/6598 Pouring of concrete RCC M-25 for top slab Box Culvert 70+047 BHS 8/14/2022 8/15/2022 8/15/2021

MNb 97+722 8/18/2021

RCC Cover
EPC-06/STR/6699 Layout checking and earthwork in excavation 71+200 71+220 LHS 8/28/2022 8/29/2022
Drain
RCC Cover
EPC-06/STR/6700 Layout checking and earthwork in excavation 86+820 86+845 LHS 8/30/2022 8/31/2022
Drain
RCC Cover
EPC-06/STR/6701 Layout checking and earthwork in excavation 86+820 86+845 RHS 8/30/2022 8/31/2022
Drain
RCC Cover
EPC-06/STR/6702 Layout checking and earthwork in excavation 89+270 89+285 LHS 8/30/2022 8/31/2022
Drain
RCC Cover
EPC-06/STR/6703 Layout checking and earthwork in excavation 89+280 89+285 RHS 8/30/2022 8/31/2022
Drain
RCC Cover
EPC-06/STR/6716 EGL checking and Pouring of concrete PCC M-15 below Raft 71+200 71+220 LHS 8/31/2022 9/1/2022
Drain
RCC Cover
EPC-06/STR/6725 Pouring of concrete RCC M-20 for raft 71+200 71+220 LHS 9/1/2022 9/2/2022
Drain
RCC Cover
EPC-06/STR/6726 Layout checking and earthwork in excavation 68+300 68+380 LHS 9/1/2022 9/2/2022
Drain
RCC Cover
EPC-06/STR/6733 EGL checking and Pouring of concrete PCC M-15 below Raft 86+820 86+845 LHS 9/2/2022 9/3/2022
Drain
RCC Cover
EPC-06/STR/6734 EGL checking and Pouring of concrete PCC M-15 below Raft 86+820 86+845 RHS 9/2/2022 9/3/2022
Drain
RCC Cover
EPC-06/STR/6735 EGL checking and Pouring of concrete PCC M-15 below Raft 89+270 89+285 LHS 9/2/2022 9/3/2022
Drain
RCC Cover
EPC-06/STR/6736 EGL checking and Pouring of concrete PCC M-15 below Raft 89+280 89+285 RHS 9/2/2022 9/3/2022
Drain
RCC Cover
EPC-06/STR/6743 Shuttering and reinforcement checking for both walls 71+200 71+220 LHS 9/3/2022 9/4/2022
Drain
RCC Cover
EPC-06/STR/6744 Pouring of concrete RCC M-20 for both walls 71+200 71+220 LHS 9/3/2022 9/4/2022
Drain
RCC Cover
EPC-06/STR/6745 Pouring of concrete RCC M-20 for raft 86+820 86+845 LHS 9/3/2022 9/4/2022
Drain
RCC Cover
EPC-06/STR/6746 Pouring of concrete RCC M-20 for raft 86+820 86+845 RHS 9/3/2022 9/4/2022
Drain
RCC Cover
EPC-06/STR/6747 Pouring of concrete RCC M-20 for raft 89+270 89+285 LHS 9/3/2022 9/4/2022
Drain
RCC Cover
EPC-06/STR/6748 Pouring of concrete RCC M-20 for raft 89+280 89+285 RHS 9/3/2022 9/4/2022
Drain
RCC Cover
EPC-06/STR/6749 Layout checking and earthwork in excavation 68+380 68+440 LHS 9/3/2022 9/4/2022
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/6757 Shuttering and reinforcement checking for Slab 71+200 71+220 LHS 9/4/2022 9/5/2022
Drain
RCC Cover
EPC-06/STR/6758 Pouring of concrete RCC M-20 for Slab 71+200 71+220 LHS 9/4/2022 9/5/2022
Drain
RCC Cover
EPC-06/STR/6759 EGL checking and Pouring of concrete PCC M-15 below Raft 68+300 68+380 LHS 9/4/2022 9/5/2022
Drain
RCC Cover
EPC-06/STR/6766 Shuttering and reinforcement checking for both walls 86+820 86+845 LHS 9/5/2022 9/6/2022
Drain
RCC Cover
EPC-06/STR/6767 Pouring of concrete RCC M-20 for both walls 86+820 86+845 LHS 9/5/2022 9/6/2022
Drain
RCC Cover
EPC-06/STR/6768 Shuttering and reinforcement checking for both walls 86+820 86+845 RHS 9/5/2022 9/6/2022
Drain
RCC Cover
EPC-06/STR/6769 Pouring of concrete RCC M-20 for both walls 86+820 86+845 RHS 9/5/2022 9/6/2022
Drain
RCC Cover
EPC-06/STR/6770 Shuttering and reinforcement checking for both walls 89+270 89+285 LHS 9/5/2022 9/6/2022
Drain
RCC Cover
EPC-06/STR/6771 Pouring of concrete RCC M-20 for both walls 89+270 89+285 LHS 9/5/2022 9/6/2022
Drain
RCC Cover
EPC-06/STR/6772 Shuttering and reinforcement checking for both walls 89+280 89+285 RHS 9/5/2022 9/6/2022
Drain
RCC Cover
EPC-06/STR/6773 Pouring of concrete RCC M-20 for both walls 89+280 89+285 RHS 9/5/2022 9/6/2022
Drain
RCC Cover
EPC-06/STR/6774 Pouring of concrete RCC M-20 for raft 68+300 68+380 LHS 9/5/2022 9/6/2022
Drain
RCC Cover
EPC-06/STR/6775 Layout checking and earthwork in excavation 68+000 68+080 RHS 9/5/2022 9/6/2022
Drain
RCC Cover
EPC-06/STR/6782 Shuttering and reinforcement checking for Slab 86+820 86+845 LHS 9/6/2022 9/7/2022
Drain
RCC Cover
EPC-06/STR/6783 Pouring of concrete RCC M-20 for Slab 86+820 86+845 LHS 9/6/2022 9/7/2022
Drain
RCC Cover
EPC-06/STR/6784 Shuttering and reinforcement checking for Slab 86+820 86+845 RHS 9/6/2022 9/7/2022
Drain
RCC Cover
EPC-06/STR/6785 Pouring of concrete RCC M-20 for Slab 86+820 86+845 RHS 9/6/2022 9/7/2022
Drain
RCC Cover
EPC-06/STR/6786 Shuttering and reinforcement checking for Slab 89+270 89+285 LHS 9/6/2022 9/7/2022
Drain
RCC Cover
EPC-06/STR/6787 Pouring of concrete RCC M-20 for Slab 89+270 89+285 LHS 9/6/2022 9/7/2022
Drain
RCC Cover
EPC-06/STR/6788 Shuttering and reinforcement checking for Slab 89+280 89+285 RHS 9/6/2022 9/7/2022
Drain
RCC Cover
EPC-06/STR/6789 Pouring of concrete RCC M-20 for Slab 89+280 89+285 RHS 9/6/2022 9/7/2022
Drain
RCC Cover
EPC-06/STR/6790 EGL checking and Pouring of concrete PCC M-15 below Raft 68+380 68+440 LHS 9/6/2022 9/7/2022
Drain
RCC Cover
EPC-06/STR/6791 Layout checking and earthwork in excavation 68+080 68+170 RHS 9/6/2022 9/7/2022
Drain
RCC Cover
EPC-06/STR/6799 Shuttering and reinforcement checking for both walls 68+300 68+380 LHS 9/7/2022 9/8/2022
Drain
RCC Cover
EPC-06/STR/6800 Pouring of concrete RCC M-20 for both walls 68+300 68+380 LHS 9/7/2022 9/8/2022
Drain
RCC Cover
EPC-06/STR/6801 Pouring of concrete RCC M-20 for raft 68+380 68+440 LHS 9/7/2022 9/8/2022
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/6808 Shuttering and reinforcement checking for Slab 68+300 68+380 LHS 9/8/2022 9/9/2022
Drain
RCC Cover
EPC-06/STR/6809 Pouring of concrete RCC M-20 for Slab 68+300 68+380 LHS 9/8/2022 9/9/2022
Drain
RCC Cover
EPC-06/STR/6810 EGL checking and Pouring of concrete PCC M-15 below Raft 68+000 68+080 RHS 9/8/2022 9/9/2022
Drain
RCC Cover
EPC-06/STR/6811 Layout checking and earthwork in excavation 68+170 68+255 RHS 9/8/2022 9/9/2022
Drain
RCC Cover
EPC-06/STR/6817 Shuttering and reinforcement checking for both walls 68+380 68+440 LHS 9/9/2022 9/10/2022
Drain
RCC Cover
EPC-06/STR/6818 Pouring of concrete RCC M-20 for both walls 68+380 68+440 LHS 9/9/2022 9/10/2022
Drain
RCC Cover
EPC-06/STR/6819 Pouring of concrete RCC M-20 for raft 68+000 68+080 RHS 9/9/2022 9/10/2022
Drain
RCC Cover
EPC-06/STR/6820 EGL checking and Pouring of concrete PCC M-15 below Raft 68+080 68+170 RHS 9/9/2022 9/10/2022
Drain
RCC Cover
EPC-06/STR/6827 Shuttering and reinforcement checking for Slab 68+380 68+440 LHS 9/10/2022 9/11/2022
Drain
RCC Cover
EPC-06/STR/6828 Pouring of concrete RCC M-20 for Slab 68+380 68+440 LHS 9/10/2022 9/11/2022
Drain
RCC Cover
EPC-06/STR/6829 Pouring of concrete RCC M-20 for raft 68+080 68+170 RHS 9/10/2022 9/11/2022
Drain
RCC Cover
EPC-06/STR/6830 Layout checking and earthwork in excavation 68+255 68+333 RHS 9/10/2022 9/11/2022
Drain
RCC Cover
EPC-06/STR/6837 Shuttering and reinforcement checking for both walls 68+000 68+080 RHS 9/11/2022 9/12/2022
Drain
RCC Cover
EPC-06/STR/6838 Pouring of concrete RCC M-20 for both walls 68+000 68+080 RHS 9/11/2022 9/12/2022
Drain
RCC Cover
EPC-06/STR/6839 EGL checking and Pouring of concrete PCC M-15 below Raft 68+170 68+255 RHS 9/11/2022 9/12/2022
Drain
RCC Cover
EPC-06/STR/6845 Shuttering and reinforcement checking for Slab 68+000 68+080 RHS 9/12/2022 9/13/2022
Drain
RCC Cover
EPC-06/STR/6846 Pouring of concrete RCC M-20 for Slab 68+000 68+080 RHS 9/12/2022 9/13/2022
Drain
RCC Cover
EPC-06/STR/6847 Shuttering and reinforcement checking for both walls 68+080 68+170 RHS 9/12/2022 9/13/2022
Drain
RCC Cover
EPC-06/STR/6848 Pouring of concrete RCC M-20 for both walls 68+080 68+170 RHS 9/12/2022 9/13/2022
Drain
RCC Cover
EPC-06/STR/6849 Pouring of concrete RCC M-20 for raft 68+170 68+255 RHS 9/12/2022 9/13/2022
Drain
RCC Cover
EPC-06/STR/6850 Layout checking and earthwork in excavation 68+333 68+422 RHS 9/12/2022 9/13/2022
Drain
RCC Cover
EPC-06/STR/6857 Shuttering and reinforcement checking for Slab 68+080 68+170 RHS 9/13/2022 9/14/2022
Drain
RCC Cover
EPC-06/STR/6858 Pouring of concrete RCC M-20 for Slab 68+080 68+170 RHS 9/13/2022 9/14/2022
Drain
RCC Cover
EPC-06/STR/6859 EGL checking and Pouring of concrete PCC M-15 below Raft 68+255 68+333 RHS 9/13/2022 9/14/2022
Drain
RCC Cover
EPC-06/STR/6860 Layout checking and earthwork in excavation 68+422 68+512 RHS 9/13/2022 9/14/2022
Drain
RCC Cover
EPC-06/STR/6867 Shuttering and reinforcement checking for both walls 68+170 68+255 RHS 9/14/2022 9/15/2022
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/6868 Pouring of concrete RCC M-20 for both walls 68+170 68+255 RHS 9/14/2022 9/15/2022
Drain
RCC Cover
EPC-06/STR/6869 Pouring of concrete RCC M-20 for raft 68+255 68+333 RHS 9/14/2022 9/15/2022
Drain
RCC Cover
EPC-06/STR/6875 Shuttering and reinforcement checking for Slab 68+170 68+255 RHS 9/15/2022 9/16/2022
Drain
RCC Cover
EPC-06/STR/6876 Pouring of concrete RCC M-20 for Slab 68+170 68+255 RHS 9/15/2022 9/16/2022
Drain
RCC Cover
EPC-06/STR/6877 EGL checking and Pouring of concrete PCC M-15 below Raft 68+333 68+422 RHS 9/15/2022 9/16/2022
Drain
RCC Cover
EPC-06/STR/6878 Layout checking and earthwork in excavation 68+512 68+600 RHS 9/15/2022 9/16/2022
Drain
RCC Cover
EPC-06/STR/6885 Shuttering and reinforcement checking for both walls 68+255 68+333 RHS 9/16/2022 9/17/2022
Drain
RCC Cover
EPC-06/STR/6886 Pouring of concrete RCC M-20 for both walls 68+255 68+333 RHS 9/16/2022 9/17/2022
Drain
RCC Cover
EPC-06/STR/6887 Pouring of concrete RCC M-20 for raft 68+333 68+422 RHS 9/16/2022 9/17/2022
Drain
RCC Cover
EPC-06/STR/6888 EGL checking and Pouring of concrete PCC M-15 below Raft 68+422 68+512 RHS 9/16/2022 9/17/2022
Drain
RCC Cover
EPC-06/STR/6889 Layout checking and earthwork in excavation 68+600 68+700 RHS 9/16/2022 9/17/2022
Drain
RCC Cover
EPC-06/STR/6895 Shuttering and reinforcement checking for Slab 68+255 68+333 RHS 9/17/2022 9/18/2022
Drain
RCC Cover
EPC-06/STR/6896 Pouring of concrete RCC M-20 for Slab 68+255 68+333 RHS 9/17/2022 9/18/2022
Drain
RCC Cover
EPC-06/STR/6897 Pouring of concrete RCC M-20 for raft 68+422 68+512 RHS 9/17/2022 9/18/2022
Drain
RCC Cover
EPC-06/STR/6905 Shuttering and reinforcement checking for both walls 68+333 68+422 RHS 9/18/2022 9/19/2022
Drain
RCC Cover
EPC-06/STR/6906 Pouring of concrete RCC M-20 for both walls 68+333 68+422 RHS 9/18/2022 9/19/2022
Drain
RCC Cover
EPC-06/STR/6907 EGL checking and Pouring of concrete PCC M-15 below Raft 68+512 68+600 RHS 9/18/2022 9/19/2022
Drain
RCC Cover
EPC-06/STR/6908 Layout checking and earthwork in excavation 80+965 81+035 LHS 9/18/2022 9/19/2022
Drain
RCC Cover
EPC-06/STR/6916 Shuttering and reinforcement checking for Slab 68+333 68+422 RHS 9/19/2022 9/20/2022
Drain
RCC Cover
EPC-06/STR/6917 Pouring of concrete RCC M-20 for Slab 68+333 68+422 RHS 9/19/2022 9/20/2022
Drain
RCC Cover
EPC-06/STR/6918 Shuttering and reinforcement checking for both walls 68+422 68+512 RHS 9/19/2022 9/20/2022
Drain
RCC Cover
EPC-06/STR/6919 Pouring of concrete RCC M-20 for both walls 68+422 68+512 RHS 9/19/2022 9/20/2022
Drain
RCC Cover
EPC-06/STR/6920 Pouring of concrete RCC M-20 for raft 68+512 68+600 RHS 9/19/2022 9/20/2022
Drain
RCC Cover
EPC-06/STR/6921 EGL checking and Pouring of concrete PCC M-15 below Raft 68+600 68+700 RHS 9/19/2022 9/20/2022
Drain
RCC Cover
EPC-06/STR/6922 Layout checking and earthwork in excavation 80+945 80+985 RHS 9/19/2022 9/20/2022
Drain
RCC Cover
EPC-06/STR/6929 Shuttering and reinforcement checking for Slab 68+422 68+512 RHS 9/20/2022 9/21/2022
Drain
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Sr. Chainage Date of Date of
RFI No. Description Type Side Time Remarks
No. From To Submission Inspection

RCC Cover
EPC-06/STR/6930 Pouring of concrete RCC M-20 for Slab 68+422 68+512 RHS 9/20/2022 9/21/2022
Drain
RCC Cover
EPC-06/STR/6931 Pouring of concrete RCC M-20 for raft 68+600 68+700 RHS 9/20/2022 9/21/2022
Drain
RCC Cover
EPC-06/STR/6937 Shuttering and reinforcement checking for both walls 68+512 68+600 RHS 9/21/2022 9/22/2022
Drain
RCC Cover
EPC-06/STR/6938 Pouring of concrete RCC M-20 for both walls 68+512 68+600 RHS 9/21/2022 9/22/2022
Drain
RCC Cover
EPC-06/STR/6939 EGL checking and Pouring of concrete PCC M-15 below Raft 80+965 81+035 LHS 9/21/2022 9/22/2022
Drain
RCC Cover
EPC-06/STR/6945 Shuttering and reinforcement checking for Slab 68+512 68+600 RHS 9/22/2022 9/23/2022
Drain
RCC Cover
EPC-06/STR/6946 Pouring of concrete RCC M-20 for Slab 68+512 68+600 RHS 9/22/2022 9/23/2022
Drain
RCC Cover
EPC-06/STR/6947 Shuttering and reinforcement checking for both walls 68+600 68+700 RHS 9/22/2022 9/23/2022
Drain
RCC Cover
EPC-06/STR/6948 Pouring of concrete RCC M-20 for both walls 68+600 68+700 RHS 9/22/2022 9/23/2022
Drain
RCC Cover
EPC-06/STR/6949 Pouring of concrete RCC M-20 for raft 80+965 81+035 LHS 9/22/2022 9/23/2022
Drain
RCC Cover
EPC-06/STR/6950 EGL checking and Pouring of concrete PCC M-15 below Raft 80+945 80+985 RHS 9/22/2022 9/23/2022
Drain
RCC Cover
EPC-06/STR/6956 Shuttering and reinforcement checking for Slab 68+600 68+700 RHS 9/23/2022 9/24/2022
Drain
RCC Cover
EPC-06/STR/6957 Pouring of concrete RCC M-20 for Slab 68+600 68+700 RHS 9/23/2022 9/24/2022
Drain
RCC Cover
EPC-06/STR/6958 Pouring of concrete RCC M-20 for raft 80+945 80+985 RHS 9/23/2022 9/24/2022
Drain
RCC Cover
EPC-06/STR/6965 Shuttering and reinforcement checking for both walls 80+965 81+035 LHS 9/24/2022 9/25/2022
Drain
RCC Cover
EPC-06/STR/6966 Pouring of concrete RCC M-20 for both walls 80+965 81+035 LHS 9/24/2022 9/25/2022
Drain
RCC Cover
EPC-06/STR/6972 Shuttering and reinforcement checking for Slab 80+965 81+035 LHS 9/25/2022 9/26/2022
Drain
RCC Cover
EPC-06/STR/6973 Pouring of concrete RCC M-20 for Slab 80+965 81+035 LHS 9/25/2022 9/26/2022
Drain
RCC Cover
EPC-06/STR/6974 Shuttering and reinforcement checking for both walls 80+945 80+985 RHS 9/25/2022 9/26/2022
Drain
RCC Cover
EPC-06/STR/6975 Pouring of concrete RCC M-20 for both walls 80+945 80+985 RHS 9/25/2022 9/26/2022
Drain
RFI No. Date Description Side From To
EPC-06/HW/1356 1/31/2021 Applying primer coat RHS 70+090 70+280
EPC-06/HW/1363 2/1/2021 Applying primer coat LHS 80+500 80+950
EPC-06/HW/1363 2/1/2021 Applying primer coat RHS 81+050 81+440
EPC-06/HW/1363 2/1/2021 Applying primer coat RHS 81+500 82+150
EPC-06/HW/1374 2/4/2021 Applying primer coat RHS 73+350 73+560
EPC-06/HW/1374 2/4/2021 Applying primer coat LHS 70+340 70+710
EPC-06/HW/1374 2/4/2021 Applying primer coat LHS 70+750 70+900
EPC-06/HW/1382 2/7/2021 Applying primer coat RHS 80+020 80+420
EPC-06/HW/1382 2/7/2021 Applying primer coat RHS 79+700 79+940
EPC-06/HW/1382 2/7/2021 Applying primer coat LHS 79+000 79+630
EPC-06/HW/1386 2/8/2021 Applying primer coat LHS 77+600 79+000
EPC-06/HW/1406 2/13/2021 Applying primer coat LHS 77+300 77+600
EPC-06/HW/1406 2/13/2021 Applying primer coat LHS 76+720 77+220
EPC-06/HW/1406 2/13/2021 Applying primer coat LHS 76+060 76+560
EPC-06/HW/1406 2/13/2021 Applying primer coat RHS 75+180 75+700
EPC-06/HW/1429 2/19/2021 Applying primer coat RHS 74+170 74+980
EPC-06/HW/1429 2/19/2021 Applying primer coat RHS 73+620 73+770
EPC-06/HW/1429 2/19/2021 Applying primer coat LHS 73+120 73+560
EPC-06/HW/1429 2/19/2021 Applying primer coat LHS 72+600 73+040
EPC-06/HW/1432 2/20/2021 Applying primer coat LHS 72+200 72+600
EPC-06/HW/1432 2/20/2021 Applying primer coat LHS 71+600 72+200
EPC-06/HW/1432 2/20/2021 Applying primer coat RHS 70+750 70+980
EPC-06/HW/1432 2/20/2021 Applying primer coat RHS 70+340 70+710
EPC-06/HW/1432 2/20/2021 Applying primer coat LHS 70+090 70+280

EPC-06/HW/1364 2/1/2021 Applying tack coat for DBM RHS 70+090 70+280
EPC-06/HW/1368 2/2/2021 Applying tack coat for DBM LHS 80+500 80+950
EPC-06/HW/1368 2/2/2021 Applying tack coat for DBM RHS 81+050 81+440
EPC-06/HW/1368 2/2/2021 Applying tack coat for DBM RHS 81+500 82+150
EPC-06/HW/1376 2/5/2021 Applying tack coat for DBM RHS 73+350 73+560
EPC-06/HW/1376 2/5/2021 Applying tack coat for DBM LHS 70+340 70+710
EPC-06/HW/1376 2/5/2021 Applying tack coat for DBM LHS 70+750 70+900
EPC-06/HW/1387 2/8/2021 Applying tack coat for DBM RHS 80+020 80+420
EPC-06/HW/1387 2/8/2021 Applying tack coat for DBM RHS 79+700 79+940
EPC-06/HW/1387 2/8/2021 Applying tack coat for DBM LHS 79+000 79+630
EPC-06/HW/1393 2/9/2021 Applying tack coat for DBM LHS 77+600 79+000
EPC-06/HW/1408 2/14/2021 Applying tack coat for DBM LHS 77+300 77+600
EPC-06/HW/1408 2/14/2021 Applying tack coat for DBM LHS 76+720 77+220
EPC-06/HW/1408 2/14/2021 Applying tack coat for DBM LHS 76+060 76+560
EPC-06/HW/1408 2/14/2021 Applying tack coat for DBM RHS 75+180 75+700
EPC-06/HW/1433 2/20/2021 Applying tack coat for DBM RHS 74+170 74+980
EPC-06/HW/1433 2/20/2021 Applying tack coat for DBM RHS 73+620 73+770
EPC-06/HW/1433 2/20/2021 Applying tack coat for DBM LHS 73+120 73+560
EPC-06/HW/1433 2/20/2021 Applying tack coat for DBM LHS 72+600 73+040
EPC-06/HW/1438 2/21/2021 Applying tack coat for DBM LHS 72+200 72+600
EPC-06/HW/1438 2/21/2021 Applying tack coat for DBM LHS 71+600 72+200
EPC-06/HW/1438 2/21/2021 Applying tack coat for DBM RHS 70+750 70+980
EPC-06/HW/1438 2/21/2021 Applying tack coat for DBM RHS 70+340 70+710
EPC-06/HW/1438 2/21/2021 Applying tack coat for DBM LHS 70+090 70+280
RFI No. Date Description Side From To

EPC-06/HW/1353 1/31/2021 FDD Checking of WMM 1st layer LHS 80+500 80+950
EPC-06/HW/1354 1/31/2021 FDD Checking of WMM 1st layer RHS 81+050 81+440
EPC-06/HW/1355 1/31/2021 FDD Checking of WMM 1st layer RHS 81+500 82+150
EPC-06/HW/1367 2/2/2021 FDD Checking of WMM 1st layer LHS 70+340 70+460
EPC-06/HW/1370 2/3/2021 FDD Checking of WMM 1st layer RHS 73+350 73+400
EPC-06/HW/1379 2/6/2021 FDD Checking of WMM 1st layer LHS 76+720 77+220
EPC-06/HW/1380 2/7/2021 FDD Checking of WMM 1st layer LHS 76+060 76+560
EPC-06/HW/1384 2/8/2021 FDD Checking of WMM 1st layer RHS 75+180 75+700
EPC-06/HW/1391 2/9/2021 FDD Checking of WMM 1st layer RHS 74+170 74+980
EPC-06/HW/1400 2/11/2021 FDD Checking of WMM 1st layer LHS 73+120 73+560
EPC-06/HW/1402 2/12/2021 FDD Checking of WMM 1st layer LHS 72+200 73+040
EPC-06/HW/1412 2/15/2021 FDD Checking of WMM 1st layer LHS 71+600 72+200
EPC-06/HW/1423 2/18/2021 FDD Checking of WMM 1st layer LHS 70+090 70+280
EPC-06/HW/1426 2/19/2021 FDD Checking of WMM 1st layer RHS 70+750 70+980
EPC-06/HW/1427 2/19/2021 FDD Checking of WMM 1st layer RHS 70+430 70+710

EPC-06/HW/1290 1/26/2021 Level & FDD Checking For GSB layer RHS 88+900 89+270
EPC-06/HW/1342 1/30/2021 Level & FDD Checking For GSB layer LHS 80+500 80+950
EPC-06/HW/1342 1/30/2021 Level & FDD Checking For GSB layer RHS 81+050 81+440
EPC-06/HW/1342 1/30/2021 Level & FDD Checking For GSB layer RHS 81+500 82+150
EPC-06/HW/1359 2/1/2021 Level & FDD Checking For GSB layer LHS 70+340 70+460
EPC-06/HW/1366 2/2/2021 Level & FDD Checking For GSB layer RHS 73+350 73+400
EPC-06/HW/1396 2/10/2021 Level & FDD Checking For GSB layer LHS 73+350 73+560
EPC-06/HW/1419 2/17/2021 Level & FDD Checking For GSB layer RHS 70+750 70+980
EPC-06/HW/1420 2/17/2021 Level & FDD Checking For GSB layer RHS 70+430 70+710
EPC-06/HW/1421 2/17/2021 Level & FDD Checking For GSB layer LHS 70+090 70+280
EPC-06/HW/1425 2/19/2021 Level & FDD Checking For GSB layer RHS 86+530 86+800
EPC-06/HW/1464 2/26/2021 Level & FDD Checking For GSB layer RHS 80+500 80+950
EPC-06/HW/1465 2/26/2021 Level & FDD Checking For GSB layer LHS 81+050 81+440
EPC-06/HW/1466 2/26/2021 Level & FDD Checking For GSB layer LHS 81+500 82+150
EPC-06/HW/1474 2/27/2021 Level & FDD Checking For GSB layer LHS 67+130 67+500
EPC-06/HW/1481 2/28/2021 Level & FDD Checking For GSB layer LHS 66+320 67+070

EPC-06/HW/1288 1/25/2021 Level & FDD Checking of Subgrade Top layer RHS 88+900 89+270
EPC-06/HW/1311 1/29/2021 Level & FDD Checking of Subgrade Top layer LHS 80+500 80+950
EPC-06/HW/1312 1/29/2021 Level & FDD Checking of Subgrade Top layer RHS 81+050 81+440
EPC-06/HW/1313 1/29/2021 Level & FDD Checking of Subgrade Top layer RHS 81+500 82+150
EPC-06/HW/1357 2/1/2021 Level & FDD Checking of Subgrade Top layer LHS 70+340 70+460
EPC-06/HW/1358 2/1/2021 Level & FDD Checking of Subgrade Top layer RHS 73+350 73+400
EPC-06/HW/1390 2/9/2021 Level & FDD Checking of Subgrade Top layer LHS 73+350 73+560
EPC-06/HW/1411 2/15/2021 Level & FDD Checking of Subgrade Top layer RHS 70+750 70+980
EPC-06/HW/1414 2/16/2021 Level & FDD Checking of Subgrade Top layer RHS 70+430 70+710
EPC-06/HW/1415 2/16/2021 Level & FDD Checking of Subgrade Top layer LHS 70+090 70+280
EPC-06/HW/1418 2/17/2021 Level & FDD Checking of Subgrade Top layer RHS 86+530 86+800
EPC-06/HW/1454 2/25/2021 Level & FDD Checking of Subgrade Top layer RHS 80+500 80+950
EPC-06/HW/1455 2/25/2021 Level & FDD Checking of Subgrade Top layer LHS 81+050 81+440
EPC-06/HW/1456 2/25/2021 Level & FDD Checking of Subgrade Top layer LHS 81+500 82+150
EPC-06/HW/1463 2/26/2021 Level & FDD Checking of Subgrade Top layer LHS 67+130 67+500
EPC-06/HW/1473 2/27/2021 Level & FDD Checking of Subgrade Top layer LHS 66+320 67+070
RFI No. Date Description Side From To

EPC-06/HW/1360 2/1/2021 Level & FDD Checking of WMM Top layer LHS 80+500 80+950
EPC-06/HW/1361 2/1/2021 Level & FDD Checking of WMM Top layer RHS 81+050 81+440
EPC-06/HW/1362 2/1/2021 Level & FDD Checking of WMM Top layer RHS 81+500 82+150
EPC-06/HW/1371 2/3/2021 Level & FDD Checking of WMM Top layer LHS 70+340 70+460
EPC-06/HW/1373 2/4/2021 Level & FDD Checking of WMM Top layer RHS 73+350 73+400
EPC-06/HW/1381 2/7/2021 Level & FDD Checking of WMM Top layer LHS 76+720 77+220
EPC-06/HW/1385 2/8/2021 Level & FDD Checking of WMM Top layer LHS 76+060 76+560
EPC-06/HW/1392 2/9/2021 Level & FDD Checking of WMM Top layer RHS 75+180 75+700
EPC-06/HW/1398 2/10/2021 Level & FDD Checking of WMM Top layer RHS 74+170 74+980
EPC-06/HW/1403 2/12/2021 Level & FDD Checking of WMM Top layer LHS 73+120 73+560
EPC-06/HW/1405 2/13/2021 Level & FDD Checking of WMM Top layer LHS 72+200 73+040
EPC-06/HW/1416 2/16/2021 Level & FDD Checking of WMM Top layer LHS 71+600 72+200
EPC-06/HW/1428 2/19/2021 Level & FDD Checking of WMM Top layer LHS 70+090 70+280
EPC-06/HW/1430 2/20/2021 Level & FDD Checking of WMM Top layer RHS 70+750 70+980
EPC-06/HW/1431 2/20/2021 Level & FDD Checking of WMM Top layer RHS 70+430 70+710

EPC-06/HW/1301 1/27/2021 Level and FDD checking of DLC layer RHS 88+900 89+270
EPC-06/HW/1399 2/10/2021 Level and FDD checking of DLC layer RHS 75+830 75+850
EPC-06/HW/1435 2/20/2021 Level and FDD checking of DLC layer RHS 86+530 86+800

EPC-06/HW/1365 2/1/2021 Level checking and laying of DBM RHS 70+090 70+280
EPC-06/HW/1369 2/2/2021 Level checking and laying of DBM LHS 80+500 80+950
EPC-06/HW/1369 2/2/2021 Level checking and laying of DBM RHS 81+050 81+440
EPC-06/HW/1369 2/2/2021 Level checking and laying of DBM RHS 81+500 82+150
EPC-06/HW/1377 2/5/2021 Level checking and laying of DBM RHS 73+350 73+560
EPC-06/HW/1377 2/5/2021 Level checking and laying of DBM LHS 70+340 70+710
EPC-06/HW/1377 2/5/2021 Level checking and laying of DBM LHS 70+750 70+900
EPC-06/HW/1388 2/8/2021 Level checking and laying of DBM RHS 80+020 80+420
EPC-06/HW/1388 2/8/2021 Level checking and laying of DBM RHS 79+700 79+940
EPC-06/HW/1388 2/8/2021 Level checking and laying of DBM LHS 79+000 79+630
EPC-06/HW/1394 2/9/2021 Level checking and laying of DBM LHS 77+600 79+000
EPC-06/HW/1409 2/14/2021 Level checking and laying of DBM LHS 77+300 77+600
EPC-06/HW/1409 2/14/2021 Level checking and laying of DBM LHS 76+720 77+220
EPC-06/HW/1409 2/14/2021 Level checking and laying of DBM LHS 76+060 76+560
EPC-06/HW/1409 2/14/2021 Level checking and laying of DBM RHS 75+180 75+700
EPC-06/HW/1434 2/20/2021 Level checking and laying of DBM RHS 74+170 74+980
EPC-06/HW/1434 2/20/2021 Level checking and laying of DBM RHS 73+620 73+770
EPC-06/HW/1434 2/20/2021 Level checking and laying of DBM LHS 73+120 73+560
EPC-06/HW/1434 2/20/2021 Level checking and laying of DBM LHS 72+600 73+040
EPC-06/HW/1439 2/21/2021 Level checking and laying of DBM LHS 72+200 72+600
EPC-06/HW/1439 2/21/2021 Level checking and laying of DBM LHS 71+600 72+200
EPC-06/HW/1439 2/21/2021 Level checking and laying of DBM RHS 70+750 70+980
EPC-06/HW/1439 2/21/2021 Level checking and laying of DBM RHS 70+340 70+710
EPC-06/HW/1439 2/21/2021 Level checking and laying of DBM LHS 70+090 70+280
RFI No. Date Description Side From To

EPC-06/HW/1372 2/3/2021 Level checking and laying of PQC (Carriageway Portion) RHS 88+900 89+000
EPC-06/HW/1375 2/4/2021 Level checking and laying of PQC (Carriageway Portion) RHS 89+000 89+040
EPC-06/HW/1378 2/5/2021 Level checking and laying of PQC (Carriageway Portion) RHS 89+040 89+070
EPC-06/HW/1383 2/7/2021 Level checking and laying of PQC (Carriageway Portion) RHS 89+070 89+140
EPC-06/HW/1389 2/8/2021 Level checking and laying of PQC (Carriageway Portion) RHS 89+140 89+160
EPC-06/HW/1395 2/9/2021 Level checking and laying of PQC (Carriageway Portion) RHS 89+160 89+200
EPC-06/HW/1397 2/10/2021 Level checking and laying of PQC (Carriageway Portion) RHS 89+200 89+270
EPC-06/HW/1401 2/11/2021 Level checking and laying of PQC (Carriageway Portion) RHS 74+150 74+170
EPC-06/HW/1404 2/12/2021 Level checking and laying of PQC (Carriageway Portion) RHS 74+090 74+150
EPC-06/HW/1407 2/13/2021 Level checking and laying of PQC (Carriageway Portion) RHS 74+040 74+090
EPC-06/HW/1410 2/14/2021 Level checking and laying of PQC (Carriageway Portion) RHS 74+000 74+040
EPC-06/HW/1413 2/15/2021 Level checking and laying of PQC (Carriageway Portion) RHS 73+960 74+000
EPC-06/HW/1417 2/16/2021 Level checking and laying of PQC (Carriageway Portion) RHS 73+890 73+960
EPC-06/HW/1422 2/17/2021 Level checking and laying of PQC (Carriageway Portion) RHS 73+840 73+890
EPC-06/HW/1443 2/22/2021 Level checking and laying of PQC (Carriageway Portion) RHS 73+770 73+840

EPC-06/HW/1424 2/18/2021 Level checking and laying of PQC (Paved shoulder Portion) RHS 75+830 75+850
EPC-06/HW/1446 2/23/2021 Level checking and laying of PQC (Paved shoulder Portion) RHS 74+100 74+170
EPC-06/HW/1450 2/24/2021 Level checking and laying of PQC (Paved shoulder Portion) RHS 74+050 74+100
EPC-06/HW/1457 2/25/2021 Level checking and laying of PQC (Paved shoulder Portion) RHS 73+960 74+050
EPC-06/HW/1458 2/25/2021 Level checking and laying of PQC (Paved shoulder Portion) RHS 88+900 89+000
EPC-06/HW/1467 2/26/2021 Level checking and laying of PQC (Paved shoulder Portion) RHS 73+910 73+960
EPC-06/HW/1468 2/26/2021 Level checking and laying of PQC (Paved shoulder Portion) RHS 89+000 89+110
EPC-06/HW/1475 2/27/2021 Level checking and laying of PQC (Paved shoulder Portion) RHS 73+830 73+910
EPC-06/HW/1476 2/27/2021 Level checking and laying of PQC (Paved shoulder Portion) RHS 89+110 89+270
EPC-06/HW/1482 2/28/2021 Level checking and laying of PQC (Paved shoulder Portion) RHS 73+770 73+830
RFI No. Date Description Type From To Side
EPC-06/HW/4218 4/16/2022 Level checking and laying of BC BC 85+670 86+445 LHS
EPC-06/HW/4219 4/16/2022 Level checking and laying of BC BC 88+520 88+900 LHS
EPC-06/HW/4220 4/16/2022 Level checking and laying of BC BC 89+285 90+300 LHS
EPC-06/HW/4233 4/18/2022 Level checking and laying of BC BC 90+300 92+200 LHS
EPC-06/HW/4244 4/19/2022 Level checking and laying of BC BC 92+200 94+300 LHS
EPC-06/HW/4263 4/22/2022 Level checking and laying of BC BC 85+670 86+445 RHS
EPC-06/HW/4264 4/22/2022 Level checking and laying of BC BC 86+860 86+868 BHS
EPC-06/HW/4265 4/22/2022 Level checking and laying of BC BC 88+520 88+900 RHS
EPC-06/HW/4266 4/22/2022 Level checking and laying of BC BC 89+285 90+200 RHS
EPC-06/HW/4277 4/23/2022 Level checking and laying of BC BC 90+200 92+300 RHS
EPC-06/HW/4293 4/25/2022 Level checking and laying of BC BC 92+300 94+300 RHS
EPC-06/HW/4324 5/1/2022 Level checking and laying of BC BC 44+300 46+250 LHS
EPC-06/HW/4335 5/2/2022 Level checking and laying of BC BC 46+320 49+500 LHS
EPC-06/HW/4346 5/3/2022 Level checking and laying of BC BC 49+900 53+000 LHS
EPC-06/HW/4070 5/6/2022 Laying of BC on Minor Junction BC 56+230 LHS
EPC-06/HW/4375 5/7/2022 Level checking and laying of BC BC 44+300 46+250 RHS
EPC-06/HW/4450 5/14/2022 Level checking and laying of BC BC 46+320 49+500 RHS
EPC-06/HW/4462 5/15/2022 Level checking and laying of BC BC 49+900 53+000 RHS
EPC-06/HW/4497 5/18/2022 Level checking and laying of BC BC 68+000 68+080 LHS
EPC-06/HW/4498 5/18/2022 Level checking and laying of BC BC 68+780 69+230 LHS
EPC-06/HW/4499 5/18/2022 Level checking and laying of BC BC 68+000 68+080 RHS
EPC-06/HW/4500 5/18/2022 Level checking and laying of BC BC 68+780 69+230 RHS
EPC-06/HW/4363 5/6/2022 Level checking and laying of BC BC (OL) 53+000 55+620 LHS
EPC-06/HW/4774 6/8/2022 Level checking and laying of BC BC (OL) 00+000 01+950 LHS
EPC-06/HW/4785 6/9/2022 Level checking and laying of BC BC (OL) 02+700 04+600 LHS
EPC-06/HW/4796 6/10/2022 Level checking and laying of BC BC (OL) 04+600 06+560 LHS
EPC-06/HW/4807 6/11/2022 Level checking and laying of BC BC (OL) 00+000 01+950 RHS
EPC-06/HW/4828 6/14/2022 Level checking and laying of BC BC (OL) 02+700 04+500 RHS
EPC-06/HW/4849 6/15/2022 Level checking and laying of BC BC (OL) 04+500 06+560 RHS
EPC-06/HW/4373 5/7/2022 Dismantling of existing BT surface BT Scr 106+000 108+300 BHS
EPC-06/HW/4415 5/11/2022 Dismantling of existing BT surface BT Scr 94+300 94+500 BHS
EPC-06/HW/4505 5/18/2022 Laying of DBM on Minor Junction DBM 69+550 LHS
EPC-06/HW/4598 5/27/2022 Level checking and laying of DBM DBM 99+300 99+360 LHS
EPC-06/HW/4599 5/27/2022 Level checking and laying of DBM DBM 100+500 102+400 LHS
EPC-06/HW/4605 5/27/2022 Laying of DBM on Minor Junction DBM 98+340 LHS
EPC-06/HW/4605 5/27/2022 Laying of DBM on Minor Junction DBM 100+480 BHS
EPC-06/HW/4633 5/29/2022 Level checking and laying of DBM DBM 102+400 104+500 LHS
RFI No. Date Description Type From To Side
EPC-06/HW/4640 5/29/2022 Laying of DBM on Minor Junction DBM 102+060 RHS
EPC-06/HW/4653 5/30/2022 Level checking and laying of DBM DBM 104+500 106+200 LHS
EPC-06/HW/4670 5/31/2022 Level checking and laying of DBM DBM 106+200 108+300 LHS
EPC-06/HW/4710 6/3/2022 Level checking and laying of DBM DBM 99+300 99+360 RHS
EPC-06/HW/4711 6/3/2022 Level checking and laying of DBM DBM 100+400 102+500 RHS
EPC-06/HW/4726 6/4/2022 Level checking and laying of DBM DBM 102+500 104+200 RHS
EPC-06/HW/4727 6/4/2022 Level checking and laying of DBM DBM 94+300 94+500 LHS
EPC-06/HW/4730 6/4/2022 Laying of DBM on Minor Junction DBM 102+565 RHS
EPC-06/HW/4730 6/4/2022 Laying of DBM on Minor Junction DBM 103+760 RHS
EPC-06/HW/4740 6/5/2022 Level checking and laying of DBM DBM 104+200 106+100 RHS
EPC-06/HW/4741 6/5/2022 Level checking and laying of DBM DBM 94+300 94+500 RHS
EPC-06/HW/4745 6/5/2022 Laying of DBM on Minor Junction DBM 104+715 LHS
EPC-06/HW/4772 6/8/2022 Level checking and laying of DBM DBM 106+100 108+300 RHS
EPC-06/HW/4776 6/8/2022 Laying of DBM on Minor Junction DBM 108+205 LHS
EPC-06/HW/4385 5/8/2022 Level & FDD Checking For GSB layer GSB 105+000 105+700 LHS
EPC-06/HW/4416 5/11/2022 Level & FDD Checking For GSB layer GSB 105+700 106+700 LHS
EPC-06/HW/4447 5/14/2022 Level & FDD Checking For GSB layer GSB 106+700 107+600 LHS
EPC-06/HW/4482 5/17/2022 Level & FDD Checking For GSB layer GSB 107+600 108+300 LHS
EPC-06/HW/4533 5/21/2022 Level & FDD Checking For GSB layer GSB 99+300 99+360 BHS
EPC-06/HW/4534 5/21/2022 Level & FDD Checking For GSB layer GSB 94+300 94+500 LHS
EPC-06/HW/4535 5/21/2022 Level & FDD Checking For GSB layer GSB 94+300 94+500 RHS
EPC-06/HW/4615 5/28/2022 Level & FDD Checking For GSB layer GSB 105+000 105+800 RHS
EPC-06/HW/4649 5/30/2022 Level & FDD Checking For GSB layer GSB 105+800 106+400 RHS
EPC-06/HW/4681 6/1/2022 Level & FDD Checking For GSB layer GSB 106+400 107+400 RHS
EPC-06/HW/4704 6/3/2022 Level & FDD Checking For GSB layer GSB 107+400 108+300 RHS
EPC-06/HW/4580 5/26/2022 Applying primer coat Prime coat 99+300 99+360 LHS
EPC-06/HW/4581 5/26/2022 Applying primer coat Prime coat 100+500 102+400 LHS
EPC-06/HW/4616 5/28/2022 Applying primer coat Prime coat 102+400 104+500 LHS
EPC-06/HW/4631 5/29/2022 Applying primer coat Prime coat 104+500 106+200 LHS
EPC-06/HW/4651 5/30/2022 Applying primer coat Prime coat 106+200 108+300 LHS
EPC-06/HW/4693 6/2/2022 Applying primer coat Prime coat 99+300 99+360 RHS
EPC-06/HW/4694 6/2/2022 Applying primer coat Prime coat 100+400 102+500 RHS
EPC-06/HW/4706 6/3/2022 Applying primer coat Prime coat 102+500 104+200 RHS
EPC-06/HW/4707 6/3/2022 Applying primer coat Prime coat 94+300 94+500 LHS
EPC-06/HW/4722 6/4/2022 Applying primer coat Prime coat 104+200 106+100 RHS
EPC-06/HW/4723 6/4/2022 Applying primer coat Prime coat 94+300 94+500 RHS
EPC-06/HW/4761 6/7/2022 Applying primer coat Prime coat 106+100 108+300 RHS
RFI No. Date Description Type From To Side
EPC-06/HW/4361 5/6/2022 Level & FDD Checking of Subgrade Top layer SG Top 105+100 105+900 LHS
EPC-06/HW/4395 5/9/2022 Level & FDD Checking of Subgrade Top layer SG Top 105+900 106+700 LHS
EPC-06/HW/4427 5/12/2022 Level & FDD Checking of Subgrade Top layer SG Top 106+700 107+500 LHS
EPC-06/HW/4460 5/15/2022 Level & FDD Checking of Subgrade Top layer SG Top 107+500 108+300 LHS
EPC-06/HW/4510 5/19/2022 Level & FDD Checking of Subgrade Top layer SG Top 99+300 99+360 BHS
EPC-06/HW/4511 5/19/2022 Level & FDD Checking of Subgrade Top layer SG Top 94+300 94+500 LHS
EPC-06/HW/4512 5/19/2022 Level & FDD Checking of Subgrade Top layer SG Top 94+300 94+500 RHS
EPC-06/HW/4579 5/26/2022 Level & FDD Checking of Subgrade Top layer SG Top 105+200 106+000 RHS
EPC-06/HW/4614 5/28/2022 Level & FDD Checking of Subgrade Top layer SG Top 106+000 106+800 RHS
EPC-06/HW/4648 5/30/2022 Level & FDD Checking of Subgrade Top layer SG Top 106+800 107+500 RHS
EPC-06/HW/4680 6/1/2022 Level & FDD Checking of Subgrade Top layer SG Top 107+500 108+300 RHS
EPC-06/HW/4215 4/16/2022 Applying tack coat for BC Tack coat (BC) 85+670 86+445 LHS
EPC-06/HW/4216 4/16/2022 Applying tack coat for BC Tack coat (BC) 88+520 88+900 LHS
EPC-06/HW/4217 4/16/2022 Applying tack coat for BC Tack coat (BC) 89+285 90+300 LHS
EPC-06/HW/4232 4/18/2022 Applying tack coat for BC Tack coat (BC) 90+300 92+200 LHS
EPC-06/HW/4243 4/19/2022 Applying tack coat for BC Tack coat (BC) 92+200 94+300 LHS
EPC-06/HW/4259 4/22/2022 Applying tack coat for BC Tack coat (BC) 85+670 86+445 RHS
EPC-06/HW/4260 4/22/2022 Applying tack coat for BC Tack coat (BC) 86+860 86+868 BHS
EPC-06/HW/4261 4/22/2022 Applying tack coat for BC Tack coat (BC) 88+520 88+900 RHS
EPC-06/HW/4262 4/22/2022 Applying tack coat for BC Tack coat (BC) 89+285 90+200 RHS
EPC-06/HW/4276 4/23/2022 Applying tack coat for BC Tack coat (BC) 90+200 92+300 RHS
EPC-06/HW/4292 4/25/2022 Applying tack coat for BC Tack coat (BC) 92+300 94+300 RHS
EPC-06/HW/4323 5/1/2022 Applying tack coat for BC Tack coat (BC) 44+300 46+250 LHS
EPC-06/HW/4334 5/2/2022 Applying tack coat for BC Tack coat (BC) 46+320 49+500 LHS
EPC-06/HW/4345 5/3/2022 Applying tack coat for BC Tack coat (BC) 49+900 53+000 LHS
EPC-06/HW/4374 5/7/2022 Applying tack coat for BC Tack coat (BC) 44+300 46+250 RHS
EPC-06/HW/4449 5/14/2022 Applying tack coat for BC Tack coat (BC) 46+320 49+500 RHS
EPC-06/HW/4461 5/15/2022 Applying tack coat for BC Tack coat (BC) 49+900 53+000 RHS
EPC-06/HW/4493 5/18/2022 Applying tack coat for BC Tack coat (BC) 68+000 68+080 LHS
EPC-06/HW/4494 5/18/2022 Applying tack coat for BC Tack coat (BC) 68+780 69+230 LHS
EPC-06/HW/4495 5/18/2022 Applying tack coat for BC Tack coat (BC) 68+000 68+080 RHS
EPC-06/HW/4496 5/18/2022 Applying tack coat for BC Tack coat (BC) 68+780 69+230 RHS
EPC-06/HW/4362 5/6/2022 Applying tack coat for BC Tack coat (BC) (OL) 53+000 55+620 LHS
EPC-06/HW/4773 6/8/2022 Applying tack coat for BC Tack coat (BC) (OL) 00+000 01+950 LHS
EPC-06/HW/4784 6/9/2022 Applying tack coat for BC Tack coat (BC) (OL) 02+700 04+600 LHS
EPC-06/HW/4795 6/10/2022 Applying tack coat for BC Tack coat (BC) (OL) 04+600 06+560 LHS
EPC-06/HW/4806 6/11/2022 Applying tack coat for BC Tack coat (BC) (OL) 00+000 01+950 RHS
RFI No. Date Description Type From To Side
EPC-06/HW/4827 6/14/2022 Applying tack coat for BC Tack coat (BC) (OL) 02+700 04+500 RHS
EPC-06/HW/4848 6/15/2022 Applying tack coat for BC Tack coat (BC) (OL) 04+500 06+560 RHS
EPC-06/HW/4596 5/27/2022 Applying tack coat for DBM Tack coat (DBM) 99+300 99+360 LHS
EPC-06/HW/4597 5/27/2022 Applying tack coat for DBM Tack coat (DBM) 100+500 102+400 LHS
EPC-06/HW/4632 5/29/2022 Applying tack coat for DBM Tack coat (DBM) 102+400 104+500 LHS
EPC-06/HW/4652 5/30/2022 Applying tack coat for DBM Tack coat (DBM) 104+500 106+200 LHS
EPC-06/HW/4669 5/31/2022 Applying tack coat for DBM Tack coat (DBM) 106+200 108+300 LHS
EPC-06/HW/4708 6/3/2022 Applying tack coat for DBM Tack coat (DBM) 99+300 99+360 RHS
EPC-06/HW/4709 6/3/2022 Applying tack coat for DBM Tack coat (DBM) 100+400 102+500 RHS
EPC-06/HW/4724 6/4/2022 Applying tack coat for DBM Tack coat (DBM) 102+500 104+200 RHS
EPC-06/HW/4725 6/4/2022 Applying tack coat for DBM Tack coat (DBM) 94+300 94+500 LHS
EPC-06/HW/4738 6/5/2022 Applying tack coat for DBM Tack coat (DBM) 104+200 106+100 RHS
EPC-06/HW/4739 6/5/2022 Applying tack coat for DBM Tack coat (DBM) 94+300 94+500 RHS
EPC-06/HW/4771 6/8/2022 Applying tack coat for DBM Tack coat (DBM) 106+100 108+300 RHS
EPC-06/HW/4405 5/10/2022 FDD Checking of WMM 1st layer WMM-I 105+000 105+800 LHS
EPC-06/HW/4437 5/13/2022 FDD Checking of WMM 1st layer WMM-I 105+800 106+700 LHS
EPC-06/HW/4472 5/16/2022 FDD Checking of WMM 1st layer WMM-I 106+700 107+500 LHS
EPC-06/HW/4513 5/19/2022 FDD Checking of WMM 1st layer WMM-I 107+500 108+300 LHS
EPC-06/HW/4550 5/23/2022 FDD Checking of WMM 1st layer WMM-I 99+300 99+360 BHS
EPC-06/HW/4551 5/23/2022 FDD Checking of WMM 1st layer WMM-I 94+300 94+500 LHS
EPC-06/HW/4552 5/23/2022 FDD Checking of WMM 1st layer WMM-I 94+300 94+500 RHS
EPC-06/HW/4650 5/30/2022 FDD Checking of WMM 1st layer WMM-I 105+000 105+700 RHS
EPC-06/HW/4682 6/1/2022 FDD Checking of WMM 1st layer WMM-I 105+700 106+400 RHS
EPC-06/HW/4705 6/3/2022 FDD Checking of WMM 1st layer WMM-I 106+400 107+300 RHS
EPC-06/HW/4737 6/5/2022 FDD Checking of WMM 1st layer WMM-I 107+300 108+300 RHS
EPC-06/HW/4417 5/11/2022 Level & FDD Checking of WMM Top layer WMM-II 105+000 105+800 LHS
EPC-06/HW/4448 5/14/2022 Level & FDD Checking of WMM Top layer WMM-II 105+800 106+700 LHS
EPC-06/HW/4483 5/17/2022 Level & FDD Checking of WMM Top layer WMM-II 106+700 107+500 LHS
EPC-06/HW/4523 5/20/2022 Level & FDD Checking of WMM Top layer WMM-II 107+500 108+300 LHS
EPC-06/HW/4562 5/24/2022 Level & FDD Checking of WMM Top layer WMM-II 99+300 99+360 BHS
EPC-06/HW/4563 5/24/2022 Level & FDD Checking of WMM Top layer WMM-II 94+300 94+500 LHS
EPC-06/HW/4564 5/24/2022 Level & FDD Checking of WMM Top layer WMM-II 94+300 94+500 RHS
EPC-06/HW/4668 5/31/2022 Level & FDD Checking of WMM Top layer WMM-II 105+000 105+700 RHS
EPC-06/HW/4692 6/2/2022 Level & FDD Checking of WMM Top layer WMM-II 105+700 106+400 RHS
EPC-06/HW/4721 6/4/2022 Level & FDD Checking of WMM Top layer WMM-II 106+400 107+300 RHS
EPC-06/HW/4751 6/6/2022 Level & FDD Checking of WMM Top layer WMM-II 107+300 108+300 RHS
RFI No. Date Description Type From To Side Qnty
EPC-06/STR/4949 1/27/2022 Dismantling of existing structure Box Culvert 103+301 BHS
EPC-06/STR/5069 2/7/2022 Dismantling of existing structure Box Culvert 102+076 BHS
EPC-06/STR/5135 2/13/2022 Dismantling of existing structure MNB 97+722 BHS
EPC-06/STR/5500 3/11/2022 Dismantling of existing structure Box Culvert 107+755 BHS
EPC-06/STR/4959 1/28/2022 Earthwork in excavation for Box Culvert Box Culvert 103+301 BHS
EPC-06/STR/5079 2/8/2022 Earthwork in excavation for Box Culvert Box Culvert 102+076 BHS
EPC-06/STR/5168 2/16/2022 Earthwork in excavation for Box Culvert MNB 97+722 BHS
EPC-06/STR/5510 3/12/2022 Earthwork in excavation for Box Culvert Box Culvert 107+755 BHS
EPC-06/STR/4960 1/28/2022 EGL checking and Boulder Soling below PCC Box Culvert 103+301 BHS
EPC-06/STR/5080 2/8/2022 EGL checking and Boulder Soling below PCC Box Culvert 102+076 BHS
EPC-06/STR/5199 2/19/2022 EGL checking and Boulder Soling below PCC MNB 97+722 BHS
EPC-06/STR/5511 3/12/2022 EGL checking and Boulder Soling below PCC Box Culvert 107+755 BHS
EPC-06/STR/4948 1/27/2022 Layout marking and OGL checking for excavation Box Culvert 103+301 BHS
EPC-06/STR/5068 2/7/2022 Layout marking and OGL checking for excavation Box Culvert 102+076 BHS
EPC-06/STR/5134 2/13/2022 Layout marking and OGL checking for excavation MNB 97+722 BHS
EPC-06/STR/5499 3/11/2022 Layout marking and OGL checking for excavation Box Culvert 107+755 BHS
EPC-06/STR/4194 12/4/2021 Pouring of concrete PCC M-15 below Approach Slab MNB 48+006 LHS
EPC-06/STR/4287 12/9/2021 Pouring of concrete PCC M-15 below Approach Slab MNB 49+026 LHS
EPC-06/STR/4418 12/15/2021 Pouring of concrete PCC M-15 below Approach Slab MNB 58+787 RHS
EPC-06/STR/4760 1/4/2022 Pouring of concrete PCC M-15 below Approach Slab MNB 48+006 RHS
EPC-06/STR/4761 1/4/2022 Pouring of concrete PCC M-15 below Approach Slab MNB 91+264 LHS
EPC-06/STR/4814 1/9/2022 Pouring of concrete PCC M-15 below Approach Slab MNB 49+026 RHS
EPC-06/STR/4865 1/14/2022 Pouring of concrete PCC M-15 below Approach Slab MNB 100+780 RHS
EPC-06/STR/4875 1/15/2022 Pouring of concrete PCC M-15 below Approach Slab MNB 58+787 LHS
EPC-06/STR/5036 2/4/2022 Pouring of concrete PCC M-15 below Approach Slab MNB 91+264 RHS
EPC-06/STR/5145 2/14/2022 Pouring of concrete PCC M-15 below Approach Slab MNB 100+780 LHS
EPC-06/STR/5219 2/21/2022 Pouring of concrete PCC M-15 below raft MNB 97+722 BHS
EPC-06/STR/4970 1/29/2022 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 103+301 BHS
EPC-06/STR/5090 2/9/2022 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 102+076 BHS
EPC-06/STR/5521 3/13/2022 Pouring of concrete PCC M-15 below raft with Cut off wall Box Culvert 107+755 BHS
EPC-06/STR/4991 1/31/2022 Pouring of concrete RCC M-25 for raft Box Culvert 103+301 BHS 9.72
EPC-06/STR/5111 2/11/2022 Pouring of concrete RCC M-25 for raft Box Culvert 102+076 BHS
EPC-06/STR/5549 3/15/2022 Pouring of concrete RCC M-25 for raft Box Culvert 107+755 BHS
EPC-06/STR/5014 2/2/2022 Pouring of concrete RCC M-25 for roof slab Bus Shelter 80+980 LHS
EPC-06/STR/5424 3/7/2022 Pouring of concrete RCC M-25 for roof slab Bus Shelter 94+133 RHS
EPC-06/STR/5487 3/10/2022 Pouring of concrete RCC M-25 for roof slab Bus Shelter 94+183 LHS
EPC-06/STR/5551 3/15/2022 Pouring of concrete RCC M-25 for roof slab Bus Shelter 90+990 LHS
EPC-06/STR/5575 3/17/2022 Pouring of concrete RCC M-25 for roof slab Bus Shelter 90+920 RHS
EPC-06/STR/5625 3/21/2022 Pouring of concrete RCC M-25 for roof slab Bus Shelter 89+000 LHS
EPC-06/STR/5662 3/24/2022 Pouring of concrete RCC M-25 for roof slab Bus Shelter 88+960 RHS
EPC-06/STR/5058 2/6/2022 Pouring of concrete RCC M-25 for top slab Box Culvert 103+301 BHS
EPC-06/STR/5179 2/17/2022 Pouring of concrete RCC M-25 for top slab Box Culvert 102+076 BHS
EPC-06/STR/5623 3/21/2022 Pouring of concrete RCC M-25 for top slab Box Culvert 107+755 BHS
RFI No. Date Description Type From To Side Qnty
EPC-06/STR/5012 2/2/2022 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 103+301 BHS
EPC-06/STR/5133 2/13/2022 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 102+076 BHS
EPC-06/STR/5573 3/17/2022 Pouring of concrete RCC M-25 for wall 1st lift with bottom hunch Box Culvert 107+755 BHS
EPC-06/STR/5035 2/4/2022 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 103+301 BHS
EPC-06/STR/5156 2/15/2022 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 102+076 BHS
EPC-06/STR/5597 3/19/2022 Pouring of concrete RCC M-25 for wall final lift with bracket Box Culvert 107+755 BHS
EPC-06/STR/4211 12/5/2021 Pouring of concrete RCC M-30 for Approach Slab MNB 48+006 LHS
EPC-06/STR/4314 12/10/2021 Pouring of concrete RCC M-30 for Approach Slab MNB 49+026 LHS
EPC-06/STR/4439 12/16/2021 Pouring of concrete RCC M-30 for Approach Slab MNB 58+787 RHS
EPC-06/STR/4772 1/5/2022 Pouring of concrete RCC M-30 for Approach Slab MNB 48+006 RHS
EPC-06/STR/4774 1/5/2022 Pouring of concrete RCC M-30 for Approach Slab MNB 91+264 LHS
EPC-06/STR/4825 1/10/2022 Pouring of concrete RCC M-30 for Approach Slab MNB 49+026 RHS
EPC-06/STR/4877 1/15/2022 Pouring of concrete RCC M-30 for Approach Slab MNB 100+780 RHS
EPC-06/STR/4888 1/16/2022 Pouring of concrete RCC M-30 for Approach Slab MNB 58+787 LHS
EPC-06/STR/5047 2/5/2022 Pouring of concrete RCC M-30 for Approach Slab MNB 91+264 RHS
EPC-06/STR/5158 2/15/2022 Pouring of concrete RCC M-30 for Approach Slab MNB 100+780 LHS
EPC-06/STR/5260 2/24/2022 Pouring of concrete RCC M-30 for raft MNB 97+722 BHS
EPC-06/STR/5382 3/3/2022 Pouring of concrete RCC M-30 for top slab (Cell 1 & 2) with bracket A1 side MNB 99+329
EPC-06/STR/5122 2/12/2022 Pouring of concrete RCC M-30 for top slab (Cell 3 & 4) with bracket A2 side MNB 99+329
Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch - Intermediate
EPC-06/STR/5393 3/4/2022 MNB 97+722 BHS
wall- 1 & 2

EPC-06/STR/5321 3/1/2022 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch A1 & A2 side MNB 97+722 BHS
EPC-06/STR/5426 3/7/2022 Pouring of concrete RCC M-30 for wall 2nd lift - A1 & A2 side MNB 97+722 BHS
EPC-06/STR/5489 3/10/2022 Pouring of concrete RCC M-30 for wall 2nd lift- Intermediate wall- 1 & 2 MNB 97+722 BHS
EPC-06/STR/5562 3/16/2022 Pouring of concrete RCC M-30 for wall 3rd lift - A1 & A2 side MNB 97+722 BHS
EPC-06/STR/5523 3/13/2022 Pouring of concrete RCC M-30 for wall 3rd lift- Intermediate wall- 1 & 2 MNB 97+722 BHS
EPC-06/STR/5586 3/18/2022 Pouring of concrete RCC M-30 for wall final lift- Intermediate wall-1 & 2 MNB 97+722 BHS
EPC-06/STR/5636 3/22/2022 Pouring of concrete RCC M-30 for wall final lift with bracket- A1 & A2 side MNB 97+722 BHS
EPC-06/STR/4211 12/5/2021 Shuttering and reinforcement checking for Approach Slab MNB 48+006 LHS
EPC-06/STR/4313 12/10/2021 Shuttering and reinforcement checking for Approach Slab MNB 49+026 LHS
EPC-06/STR/4438 12/16/2021 Shuttering and reinforcement checking for Approach Slab MNB 58+787 RHS
EPC-06/STR/4771 1/5/2022 Shuttering and reinforcement checking for Approach Slab MNB 48+006 RHS
EPC-06/STR/4773 1/5/2022 Shuttering and reinforcement checking for Approach Slab MNB 91+264 LHS
EPC-06/STR/4824 1/10/2022 Shuttering and reinforcement checking for Approach Slab MNB 49+026 RHS
EPC-06/STR/4876 1/15/2022 Shuttering and reinforcement checking for Approach Slab MNB 100+780 RHS
EPC-06/STR/4887 1/16/2022 Shuttering and reinforcement checking for Approach Slab MNB 58+787 LHS
EPC-06/STR/5046 2/5/2022 Shuttering and reinforcement checking for Approach Slab MNB 91+264 RHS
EPC-06/STR/5157 2/15/2022 Shuttering and reinforcement checking for Approach Slab MNB 100+780 LHS
EPC-06/STR/4990 1/31/2022 Shuttering and reinforcement checking for raft Box Culvert 103+301 BHS
EPC-06/STR/5110 2/11/2022 Shuttering and reinforcement checking for raft Box Culvert 102+076 BHS
EPC-06/STR/5259 2/24/2022 Shuttering and reinforcement checking for raft MNB 97+722 BHS
EPC-06/STR/5548 3/15/2022 Shuttering and reinforcement checking for raft Box Culvert 107+755 BHS
RFI No. Date Description Type From To Side Qnty
EPC-06/STR/5013 2/2/2022 Shuttering and reinforcement checking for roof slab Bus Shelter 80+980 LHS
EPC-06/STR/5423 3/7/2022 Shuttering and reinforcement checking for roof slab Bus Shelter 94+133 RHS
EPC-06/STR/5486 3/10/2022 Shuttering and reinforcement checking for roof slab Bus Shelter 94+183 LHS
EPC-06/STR/5550 3/15/2022 Shuttering and reinforcement checking for roof slab Bus Shelter 90+990 LHS
EPC-06/STR/5574 3/17/2022 Shuttering and reinforcement checking for roof slab Bus Shelter 90+920 RHS
EPC-06/STR/5624 3/21/2022 Shuttering and reinforcement checking for roof slab Bus Shelter 89+000 LHS
EPC-06/STR/5661 3/24/2022 Shuttering and reinforcement checking for roof slab Bus Shelter 88+960 RHS
EPC-06/STR/5057 2/6/2022 Shuttering and reinforcement checking for top slab Box Culvert 103+301 BHS
EPC-06/STR/5178 2/17/2022 Shuttering and reinforcement checking for top slab Box Culvert 102+076 BHS
EPC-06/STR/5622 3/21/2022 Shuttering and reinforcement checking for top slab Box Culvert 107+755 BHS

EPC-06/STR/5381 3/3/2022 Shuttering and reinforcement checking for top slab (Cell 1 & 2) with bracket A1 side MNB 99+329

EPC-06/STR/5121 2/12/2022 Shuttering and reinforcement checking for top slab (Cell 3 & 4) with bracket A2 side MNB 99+329
EPC-06/STR/5011 2/2/2022 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 103+301 BHS
EPC-06/STR/5132 2/13/2022 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 102+076 BHS
EPC-06/STR/5572 3/17/2022 Shuttering and reinforcement checking for wall 1st lift with bottom hunch Box Culvert 107+755 BHS
Shuttering and reinforcement checking for wall 1st lift with bottom hunch A1 & A2
EPC-06/STR/5320 3/1/2022 MNB 97+722 BHS
side
Shuttering and reinforcement checking for wall 1st lift with bottom hunch -
EPC-06/STR/5392 3/4/2022 MNB 97+722 BHS
Intermediate wall- 1 & 2
EPC-06/STR/5425 3/7/2022 Shuttering and reinforcement checking for wall 2nd lift- A1 & A2 side MNB 97+722 BHS

EPC-06/STR/5488 3/10/2022 Shuttering and reinforcement checking for wall 2nd lift- Intermediate wall- 1 & 2 MNB 97+722 BHS

EPC-06/STR/5561 3/16/2022 Shuttering and reinforcement checking for wall 3rd lift- A1 & A2 side MNB 97+722 BHS

EPC-06/STR/5522 3/13/2022 Shuttering and reinforcement checking for wall 3rd lift- Intermediate wall- 1 & 2 MNB 97+722 BHS

EPC-06/STR/5585 3/18/2022 Shuttering and reinforcement checking for wall final lift- Intermediate wall- 1 & 2 MNB 97+722 BHS

EPC-06/STR/5034 2/4/2022 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 103+301 BHS
EPC-06/STR/5155 2/15/2022 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 102+076 BHS
EPC-06/STR/5596 3/19/2022 Shuttering and reinforcement checking for wall final lift with bracket Box Culvert 107+755 BHS

EPC-06/STR/5635 3/22/2022 Shuttering and reinforcement checking for wall final lift with bracket- A1 & A2 side MNB 97+722 BHS
RFI No. Date Description Type From To Side
EPC-06/HW/4051 3/11/2022 Dismantling of existing BT surface BT Scr 102+100 104+000 BHS
EPC-06/HW/4063 3/12/2022 Dismantling of existing BT surface BT Scr 104+000 106+000 BHS
EPC-06/HW/4094 3/15/2022 Laying of DBM on Minor Junction DBM 98+340 LHS
EPC-06/HW/4094 3/15/2022 Laying of DBM on Minor Junction DBM 100+260 LHS
EPC-06/HW/4073 3/13/2022 FDD Checking For GSB layer on Minor Junction GSB 98+340 LHS
EPC-06/HW/4074 3/13/2022 FDD Checking For GSB layer on Minor Junction GSB 100+260 LHS
EPC-06/HW/4084 3/14/2022 Level & FDD Checking For GSB layer GSB 100+600 101+500 LHS
EPC-06/HW/4092 3/15/2022 Level & FDD Checking For GSB layer GSB 101+500 102+350 LHS
EPC-06/HW/4095 3/15/2022 Level & FDD Checking For GSB layer GSB 102+350 103+300 LHS
EPC-06/HW/4100 3/17/2022 Level & FDD Checking For GSB layer GSB 103+300 104+100 LHS
EPC-06/HW/4103 3/18/2022 Level & FDD Checking For GSB layer GSB 104+100 105+000 LHS
EPC-06/HW/4106 3/19/2022 Level & FDD Checking For GSB layer GSB 100+400 101+350 RHS
EPC-06/HW/4109 3/20/2022 Level & FDD Checking For GSB layer GSB 101+350 102+250 RHS
EPC-06/HW/4111 3/21/2022 Level & FDD Checking For GSB layer GSB 102+250 103+200 RHS
EPC-06/HW/4120 3/22/2022 Level & FDD Checking For GSB layer GSB 103+200 104+100 RHS
EPC-06/HW/4129 3/23/2022 Level & FDD Checking For GSB layer GSB 104+100 105+000 RHS
EPC-06/HW/4087 3/14/2022 Applying primer coat on Minor Junction Prime coat 98+340 LHS
EPC-06/HW/4087 3/14/2022 Applying primer coat on Minor Junction Prime coat 100+260 LHS
EPC-06/HW/4064 3/12/2022 FDD Checking of Subgrade Top layer on Minor Junction SG Top 98+340 LHS
EPC-06/HW/4065 3/12/2022 FDD Checking of Subgrade Top layer on Minor Junction SG Top 100+260 LHS
EPC-06/HW/4083 3/14/2022 Level & FDD Checking of Subgrade Top layer SG Top 101+800 102+900 LHS
EPC-06/HW/4091 3/15/2022 Level & FDD Checking of Subgrade Top layer SG Top 102+900 104+100 LHS
EPC-06/HW/4099 3/17/2022 Level & FDD Checking of Subgrade Top layer SG Top 104+100 105+100 LHS
EPC-06/HW/4102 3/18/2022 Level & FDD Checking of Subgrade Top layer SG Top 101+800 102+800 RHS
EPC-06/HW/4105 3/19/2022 Level & FDD Checking of Subgrade Top layer SG Top 102+800 104+100 RHS
EPC-06/HW/4108 3/20/2022 Level & FDD Checking of Subgrade Top layer SG Top 104+100 105+200 RHS
EPC-06/HW/4093 3/15/2022 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 98+340 LHS
EPC-06/HW/4093 3/15/2022 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 100+260 LHS
EPC-06/HW/4121 3/22/2022 FDD Checking of WMM 1st layer WMM-I 101+400 102+300 RHS
EPC-06/HW/4130 3/23/2022 FDD Checking of WMM 1st layer WMM-I 102+300 103+200 RHS
EPC-06/HW/4135 3/24/2022 FDD Checking of WMM 1st layer WMM-I 103+200 104+050 RHS
EPC-06/HW/4142 3/25/2022 FDD Checking of WMM 1st layer WMM-I 104+050 105+000 RHS
EPC-06/HW/4085 3/14/2022 FDD Checking of WMM Top layer on Minor Junction WMM-II 98+340 LHS
EPC-06/HW/4086 3/14/2022 FDD Checking of WMM Top layer on Minor Junction WMM-II 100+260 LHS
EPC-06/HW/4101 3/17/2022 Level & FDD Checking of WMM Top layer WMM-II 100+550 101+450 LHS
EPC-06/HW/4104 3/18/2022 Level & FDD Checking of WMM Top layer WMM-II 101+450 102+350 LHS
RFI No. Date Description Type From To Side
EPC-06/HW/4107 3/19/2022 Level & FDD Checking of WMM Top layer WMM-II 102+350 103+250 LHS
EPC-06/HW/4110 3/20/2022 Level & FDD Checking of WMM Top layer WMM-II 103+250 104+200 LHS
EPC-06/HW/4112 3/21/2022 Level & FDD Checking of WMM Top layer WMM-II 104+200 105+000 LHS
EPC-06/HW/4122 3/22/2022 Level & FDD Checking of WMM Top layer WMM-II 100+450 101+400 RHS
EPC-06/HW/4131 3/23/2022 Level & FDD Checking of WMM Top layer WMM-II 101+400 102+300 RHS
EPC-06/HW/4136 3/24/2022 Level & FDD Checking of WMM Top layer WMM-II 102+300 103+200 RHS
EPC-06/HW/4143 3/25/2022 Level & FDD Checking of WMM Top layer WMM-II 103+200 104+050 RHS
EPC-06/HW/4155 3/26/2022 Level & FDD Checking of WMM Top layer WMM-II 104+050 105+000 RHS
RFI No. Date Description Type From To Side Qnty
EPC-06/STR/5599 3/19/2022 Dismantling of existing structure MNB 68+779 BHS
EPC-06/STR/5600 3/19/2022 Earthwork in excavation for Box Culvert MNB 68+779 BHS
EPC-06/STR/5601 3/19/2022 EGL checking and Boulder Soling below PCC MNB 68+779 BHS
EPC-06/STR/5598 3/19/2022 Layout marking and OGL checking for excavation MNB 68+779 BHS

EPC-06/STR/5602 3/19/2022 Pouring of concrete PCC M-15 below raft with Cut off wall MNB 68+779 BHS
EPC-06/STR/5611 3/20/2022 Pouring of concrete RCC M-30 for raft MNB 68+779 BHS

EPC-06/STR/5638 3/22/2022 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch - Intermediate wall MNB 68+779 BHS

EPC-06/STR/5627 3/21/2022 Pouring of concrete RCC M-30 for wall 1st lift with bottom hunch A1 & A2 side MNB 68+779 BHS

EPC-06/STR/5640 3/23/2022 Pouring of concrete RCC M-30 for wall final lift- Intermediate wall MNB 68+779 BHS
EPC-06/STR/5664 3/24/2022 Pouring of concrete RCC M-30 for wall final lift with bracket- A1 & A2 side MNB 68+779 BHS

EPC-06/STR/5610 3/20/2022 Shuttering and reinforcement checking for raft MNB 68+779 BHS
Shuttering and reinforcement checking for wall 1st lift with bottom hunch A1 & A2
EPC-06/STR/5626 3/21/2022 MNB 68+779 BHS
side
Shuttering and reinforcement checking for wall 1st lift with bottom hunch -
EPC-06/STR/5637 3/22/2022 MNB 68+779 BHS
Intermediate wall
EPC-06/STR/5639 3/23/2022 Shuttering and reinforcement checking for wall final lift- Intermediate wall MNB 68+779 BHS

EPC-06/STR/5663 3/24/2022 Shuttering and reinforcement checking for wall final lift with bracket- A1 & A2 side MNB 68+779 BHS
RFI Summary Till Date Tiwsa To Dhamangaon EPC-06
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

SIPL/EPC-06/HW/41 Dismantling of existing BT surface BT Scr 77+220 78+000 BHS 3/13/2020 3/14/2020

SIPL/EPC-06/HW/43 Dismantling of existing BT surface BT Scr 78+740 79+060 BHS 3/14/2020 3/15/2020

SIPL/EPC-06/HW/45 Dismantling of existing BT surface BT Scr 78+000 78+740 BHS 3/15/2020 3/16/2020

SIPL/EPC-06/HW/49 Dismantling of existing BT surface BT Scr 79+060 79+650 BHS 3/17/2020 3/18/2020

SIPL/EPC-06/HW/61 Earthwork in excavation for SG Top Excavation 78+740 79+060 LHS 4/10/2020 4/11/2020

SIPL/EPC-06/HW/67 Level & FDD Checking of Subgrade Top layer SG Top 79+060 79+140 LHS 4/11/2020 4/12/2020

SIPL/EPC-06/HW/70 Level & FDD Checking of Subgrade Top layer SG Top 78+000 78+740 Rhs 4/12/2020 4/13/2020 Not Done

SIPL/EPC-06/HW/71 Level & FDD Checking of Subgrade Top layer SG Top 78+350 78+740 LHS 4/12/2020 4/13/2020

SIPL/EPC-06/HW/78 Level & FDD Checking of Subgrade Top layer SG Top 79+060 79+140 RHS 4/15/2020 4/16/2020

SIPL/EPC-06/HW/79 Level & FDD Checking of Subgrade Top layer SG Top 78+000 78+350 LHS 4/15/2020 4/16/2020

SIPL/EPC-06/HW/86 Level & FDD Checking of Subgrade Top layer SG Top 78+000 78+740 Rhs 4/17/2020 4/18/2020

SIPL/EPC-06/HW/87 Earthwork in excavation for SG Top Excavation 78+740 79+060 Rhs 4/17/2020 4/18/2020

SIPL/EPC-06/HW/92 Level & FDD Checking of Subgrade Top layer SG Top 77+630 78+000 LHS 4/18/2020 4/19/2020

SIPL/EPC-06/HW/96 Level & FDD Checking of Subgrade Top layer SG Top 79+140 79+640 LHS 4/19/2020 4/20/2020

SIPL/EPC-06/HW/98 Level & FDD Checking of Subgrade Top layer SG Top 78+350 78+740 RHS 4/19/2020 4/20/2020

SIPL/EPC-06/HW/100 Level & FDD Checking of Subgrade Top layer SG Top 77+300 77+630 LHS 4/20/2020 4/21/2020

SIPL/EPC-06/HW/102 Level & FDD Checking of Subgrade Top layer SG Top 78+000 78+350 RHS 4/21/2020 4/22/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

SIPL/EPC-06/HW/106 Level & FDD Checking of Subgrade Top layer SG Top 79+140 79+640 RHS 4/22/2020 4/23/2020

SIPL/EPC-06/HW/112 Level & FDD Checking of Subgrade Top layer SG Top 77+630 78+000 RHS 4/27/2020 4/28/2020

SIPL/EPC-06/HW/113 Dismantling of existing BT surface BT Scr 79+650 79+960 BHS 4/27/2020 4/28/2020

SIPL/EPC-06/HW/120 Level & FDD Checking of Subgrade Top layer SG Top 77+300 77+630 RHS 4/30/2020 5/1/2020

SIPL/EPC-06/HW/131 FDD Checking of Sub grade 1st layer SG 1st 79+700 79+960 LHS 5/3/2020 5/4/2020

SIPL/EPC-06/HW/134 Level & FDD Checking of Subgrade Top layer SG Top 79+700 79+960 LHS 5/4/2020 5/5/2020

SIPL/EPC-06/HW/170 FDD Checking of Embt Top EMB 79+700 79+960 RHS 5/17/2020 5/18/2020

SIPL/EPC-06/HW/176 FDD Checking of Sub grade 1st layer SG 1st 79+700 79+960 RHS 5/18/2020 5/19/2020

SIPL/EPC-06/HW/179 Level & FDD Checking of Subgrade Top layer SG Top 79+700 79+960 RHS 5/19/2020 5/20/2020

SIPL/EPC-06/HW/182 Dismantling of existing BT surface BT Scr 79+960 80+220 BHS 5/19/2020 5/20/2020

SIPL/EPC-06/HW/209 Level & FDD Checking of Subgrade Top layer SG Top 80+000 80+220 RHS 5/26/2020 5/27/2020

SIPL/EPC-06/HW/210 Level & FDD Checking For GSB layer GSB 78+300 78+740 RHS 5/26/2020 5/27/2020

SIPL/EPC-06/HW/239 Level & FDD Checking of Subgrade Top layer SG Top 80+000 80+220 LHS 6/2/2020 6/3/2020

SIPL/EPC-06/HW/242 Dismantling of existing BT surface BT Scr 80+220 80+460 BHS 6/3/2020 6/4/2020

SIPL/EPC-06/HW/257 Level & FDD Checking of Subgrade Top layer SG Top 80+220 80+440 LHS 6/7/2020 6/8/2020

SIPL/EPC-06/HW/272 Level & FDD Checking of Subgrade Top layer SG Top 80+220 80+460 Rhs 6/10/2020 6/11/2020

SIPL/EPC-06/HW/275 Level & FDD Checking For GSB layer GSB 78+740 79+000 RHS 6/10/2020 6/11/2020

SIPL/EPC-06/HW/278 Level & FDD Checking For GSB layer GSB 78+000 78+300 RHS 6/10/2020 6/11/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

SIPL/EPC-06/HW/281 Level & FDD Checking For GSB layer GSB 77+300 78+000 RHS 6/11/2020 6/12/2020

SIPL/EPC-06/HW/284 Dismantling of existing BT surface BT Scr 77+000 77+220 BHS 6/11/2020 6/12/2020

SIPL/EPC-06/HW/286 FDD Checking of Embt Top EMB 76+720 76+980 LHS 6/14/2020 6/15/2020

SIPL/EPC-06/HW/296 Level & FDD Checking of Subgrade Top layer SG Top 77+030 77+220 Rhs 6/17/2020 6/18/2020

SIPL/EPC-06/HW/299 Level & FDD Checking For GSB layer GSB 77+030 77+220 RHS 6/18/2020 6/19/2020

EPC-06/HW/301 Dismantling of existing BT surface BT Scr 76+560 77+000 BHS 6/19/2020 6/20/2020

SIPL/EPC-06/HW/304 FDD Checking of Sub grade 1st layer SG 1st 76+720 76+980 LHS 6/20/2020 6/21/2020

SIPL/EPC-06/HW/317 Level & FDD Checking of Subgrade Top layer SG Top 77+030 77+220 LHS 6/22/2020 6/23/2020

SIPL/EPC-06/HW/320 Dismantling of existing BT surface BT Scr 76+120 76+560 BHS 6/23/2020 6/24/2020

SIPL/EPC-06/HW/324 Level & FDD Checking of Subgrade Top layer SG Top 76+720 76+980 LHS 6/23/2020 6/24/2020

SIPL/EPC-06/HW/332 FDD Checking of Embt Top EMB 76+280 76+560 LHS 6/24/2020 6/25/2020

SIPL/EPC-06/HW/338 FDD Checking of Sub grade 1st layer SG 1st 76+280 76+560 LHS 6/25/2020 6/26/2020

SIPL/EPC-06/HW/341 Level & FDD Checking of Subgrade Top layer SG Top 76+280 76+560 LHS 6/25/2020 6/26/2020

SIPL/EPC-06/HW/353 FDD Checking of Embt Top EMB 79+700 79+960 LHS 6/30/2020 7/1/2020

SIPL/EPC-06/HW/359 FDD Checking of Embt Top EMB 76+280 76+560 RHS 6/30/2020 7/1/2020

SIPL/EPC-06/HW/365 FDD Checking of Sub grade 1st layer SG 1st 76+280 76+560 RHS 7/1/2020 7/2/2020

SIPL/EPC-06/HW/368 Level & FDD Checking of Subgrade Top layer SG Top 76+280 76+560 RHS 7/2/2020 7/3/2020

SIPL/EPC-06/HW/383 Level & FDD Checking of Subgrade Top layer SG Top 76+060 76+280 Rhs 7/7/2020 7/8/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

SIPL/EPC-06/HW/398 Level & FDD Checking of Subgrade Top layer SG Top 76+160 76+280 LHS 7/12/2020 7/13/2020

SIPL/EPC-06/HW/416 Dismantling of existing BT surface BT Scr 75+700 76+120 BHS 7/14/2020 7/15/2020

SIPL/EPC-06/HW/428 Dismantling of existing BT surface BT Scr 75+180 75+700 BHS 7/16/2020 7/17/2020 Not Done

SIPL/EPC-06/HW/431 Dismantling of existing BT surface BT Scr 75+180 75+700 BHS 7/19/2020 7/20/2020

SIPL/EPC-06/HW/455 Level & FDD Checking of Subgrade Top layer SG Top 75+180 75+700 LHS 7/22/2020 7/23/2020

SIPL/EPC-06/HW/458 Level & FDD Checking For GSB layer GSB 75+180 75+700 LHS 7/23/2020 7/24/2020

SIPL/EPC-06/HW/461 Dismantling of existing BT surface BT Scr 74+700 75+180 BHS 7/23/2020 7/24/2020

SIPL/EPC-06/HW/473 Level & FDD Checking of Subgrade Top layer SG Top 74+700 74+980 LHS 7/27/2020 7/28/2020

SIPL/EPC-06/HW/500 Level & FDD Checking of Subgrade Top layer SG Top 75+180 75+700 RHS 7/30/2020 7/31/2020

SIPL/EPC-06/HW/536 FDD Checking of Embt Top EMB 70+090 70+280 LHS 8/6/2020 8/7/2020

SIPL/EPC-06/HW/545 FDD Checking of Embt Top EMB 70+335 70+430 LHS 8/6/2020 8/7/2020

SIPL/EPC-06/HW/558 Dismantling of existing BT surface BT Scr 70+090 70+710 BHS 8/6/2020 8/7/2020

SIPL/EPC-06/HW/560 FDD Checking of Sub grade 1st layer SG 1st 70+090 70+280 RHS 8/9/2020 8/10/2020

SIPL/EPC-06/HW/566 FDD Checking of Sub grade 1st layer SG 1st 70+335 70+430 RHS 8/9/2020 8/10/2020

SIPL/EPC-06/HW/572 Level & FDD Checking of Subgrade Top layer SG Top 70+090 70+280 RHS 8/9/2020 8/10/2020

SIPL/EPC-06/HW/578 FDD Checking of Embt Top EMB 70+460 70+710 LHS 8/9/2020 8/10/2020

SIPL/EPC-06/HW/581 FDD Checking of Subgrade 1st layer SG 1st 70+460 70+710 LHS 8/9/2020 8/10/2020

SIPL/EPC-06/HW/584 Level & FDD Checking of Subgrade Top layer SG Top 70+460 70+710 LHS 8/9/2020 8/10/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

SIPL/EPC-06/HW/593 FDD Checking of Embt Top EMB 70+750 70+900 LHS 8/12/2020 8/13/2020

SIPL/EPC-06/HW/599 Dismantling of existing BT surface BT Scr 70+710 71+150 BHS 8/12/2020 8/13/2020

SIPL/EPC-06/HW/603 Level & FDD Checking of Subgrade Top layer SG Top 70+335 70+430 RHS 8/12/2020 8/13/2020

SIPL/EPC-06/HW/605 FDD Checking of Subgrade 1st layer SG 1st 70+750 70+900 LHS 8/13/2020 8/14/2020

SIPL/EPC-06/HW/611 Level & FDD Checking of Subgrade Top layer SG Top 70+750 70+900 LHS 8/16/2020 8/17/2020

SIPL/EPC-06/HW/653 Dismantling of existing BT surface BT Scr 71+150 71+600 BHS 8/24/2020 8/25/2020

SIPL/EPC-06/HW/670 Level & FDD Checking of Subgrade Top layer SG Top 71+350 71+600 LHS 8/26/2020 8/27/2020

SIPL/EPC-06/HW/677 Level & FDD Checking of Subgrade Top layer SG Top 75+700 75+830 RHS 8/27/2020 8/28/2020

SIPL/EPC-06/HW/680 Level & FDD Checking of Subgrade Top layer SG Top 75+850 75+900 RHS 8/27/2020 8/28/2020

SIPL/EPC-06/HW/695 Dismantling of existing BT surface BT Scr 71+600 72+000 BHS 8/29/2020 8/30/2020

SIPL/EPC-06/HW/697 Dismantling of existing BT surface BT Scr 74+300 74+700 BHS 8/29/2020 8/30/2020

SIPL/EPC-06/HW/704 Dismantling of existing BT surface BT Scr 72+500 73+000 BHS 8/30/2020 8/31/2020

SIPL/EPC-06/HW/725 Dismantling of existing BT surface BT Scr 72+150 72+500 BHS 9/3/2020 9/4/2020

SIPL/EPC-06/HW/730 Level & FDD Checking For GSB layer GSB 75+700 75+830 RHS 9/4/2020 9/5/2020

SIPL/EPC-06/HW/731 Level & FDD Checking For GSB layer GSB 75+850 75+900 RHS 9/4/2020 9/5/2020

SIPL/EPC-06/HW/733 Level & FDD Checking of Subgrade Top layer SG Top 72+220 72+360 RHS 9/4/2020 9/5/2020

SIPL/EPC-06/HW/739 FDD and level checking of DLC laying DLC 75+770 75+830 RHS 9/5/2020 9/6/2020

SIPL/EPC-06/HW/741 Level & FDD Checking of Subgrade Top layer SG Top 72+360 72+800 RHS 9/6/2020 9/7/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

SIPL/EPC-06/HW/742 FDD and level checking of DLC laying DLC 75+730 75+770 RHS 9/6/2020 9/7/2020

SIPL/EPC-06/HW/743 Dismantling of existing BT surface BT Scr 73+720 74+300 BHS 9/7/2020 9/8/2020

SIPL/EPC-06/HW/744 Dismantling of existing BT surface BT Scr 73+000 73+420 BHS 9/7/2020 9/8/2020

SIPL/EPC-06/HW/745 FDD Checking of Sub grade 1st layer SG 1st 73+120 73+300 RHS 9/8/2020 9/9/2020

SIPL/EPC-06/HW/746 Exc up to EMB Top Excavation 73+120 73+300 RHS 9/7/2020 9/8/2020

SIPL/EPC-06/HW/748 FDD and level checking of DLC laying DLC 75+700 75+730 RHS 9/8/2020 9/9/2020

SIPL/EPC-06/HW/758 Level & FDD Checking of Subgrade Top layer SG Top 72+870 73+045 RHS 9/10/2020 9/11/2020

EPC-06/HW/759 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+810 75+824 RHS 9/12/2020 9/13/2020

SIPL/EPC-06/HW/761 Level & FDD Checking of Subgrade Top layer SG Top 73+120 73+300 RHS 9/13/2020 9/14/2020

SIPL/EPC-06/HW/762 Level & FDD Checking For GSB layer GSB 79+000 79+140 RHS 9/13/2020 9/14/2020

SIPL/EPC-06/HW/763 Level & FDD Checking of Subgrade Top layer SG Top 74+300 74+700 LHS 9/13/2020 9/14/2020

EPC-06/HW/769 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+765 75+810 RHS 9/17/2020 9/18/2020

EPC-06/HW/777 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+724 75+765 RHS 9/20/2020 9/21/2020

EPC-06/HW/783 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+700 75+724 RHS 9/24/2020 9/25/2020

SIPL/EPC-06/HW/785 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 75+750 75+820 RHS 9/25/2020 9/26/2020

SIPL/EPC-06/HW/788 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 75+700 75+750 RHS 9/26/2020 9/27/2020

SIPL/EPC-06/HW/791 FDD and level checking of DLC laying DLC 75+850 75+900 RHS 9/27/2020 9/28/2020

SIPL/EPC-06/HW/794 Earthwork in excavation for SG Top Excavation 71+100 71+200 LHS 9/30/2020 10/1/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

SIPL/EPC-06/HW/798 Level & FDD Checking For GSB layer GSB 71+100 71+180 LHS 10/2/2020 10/3/2020

SIPL/EPC-06/HW/799 FDD and level checking of DLC laying DLC 71+100 71+180 LHS 10/2/2020 10/3/2020

SIPL/EPC-06/HW/800 Level & FDD Checking of Subgrade Top layer SG Top 71+200 71+350 LHS 10/2/2020 10/3/2020

EPC-06/HW/802 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+859 75+900 RHS 10/3/2020 10/4/2020

SIPL/EPC-06/HW/805 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 75+860 75+900 RHS 10/4/2020 10/5/2020

SIPL/EPC-06/HW/807 Level & FDD Checking For GSB layer GSB 71+180 71+300 LHS 10/5/2020 10/6/2020

SIPL/EPC-06/HW/811 Level & FDD Checking For GSB layer GSB 71+300 71+400 LHS 10/7/2020 10/8/2020

SIPL/EPC-06/HW/812 FDD and level checking of DLC laying DLC 71+180 71+215 LHS 10/7/2020 10/8/2020

SIPL/EPC-06/HW/815 FDD and level checking of DLC laying DLC 71+215 71+270 LHS 10/8/2020 10/9/2020

EPC-06/HW/816 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+100 71+134 LHS 10/8/2020 10/9/2020

EPC-06/HW/819 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+134 71+147 LHS 10/9/2020 10/10/2020

EPC-06/HW/822 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+147 71+211 LHS 10/10/2020 10/11/2020

SIPL/EPC-06/HW/823 Level & FDD Checking For GSB layer GSB 71+400 71+500 LHS 10/10/2020 10/11/2020

SIPL/EPC-06/HW/825 FDD and level checking of DLC laying DLC 71+270 71+290 LHS 10/11/2020 10/12/2020

SIPL/EPC-06/HW/826 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+100 71+150 LHS 10/11/2020 10/12/2020

EPC-06/HW/829 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+150 71+185 LHS 10/12/2020 10/13/2020

EPC-06/HW/830 FDD and level checking of DLC laying DLC 71+290 71+350 LHS 10/12/2020 10/13/2020

EPC-06/HW/833 FDD and level checking of DLC laying DLC 71+350 71+400 LHS 10/13/2020 10/14/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/836 FDD and level checking of DLC laying DLC 71+400 71+440 LHS 10/14/2020 10/15/2020

EPC-06/HW/837 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+211 71+230 LHS 10/14/2020 10/15/2020

EPC-06/HW/839 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+185 71+200 LHS 10/14/2020 10/15/2020

EPC-06/HW/840 FDD and level checking of DLC laying DLC 71+440 71+520 LHS 10/15/2020 10/16/2020

EPC-06/HW/841 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+230 71+264 LHS 10/15/2020 10/16/2020

EPC-06/HW/842 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+264 71+310 LHS 10/16/2020 10/17/2020

EPC-06/HW/843 Level & FDD Checking For GSB layer GSB 71+500 71+600 LHS 10/16/2020 10/17/2020

EPC-06/HW/847 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+310 71+350 LHS 10/17/2020 10/18/2020

EPC-06/HW/848 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+200 71+270 LHS 10/18/2020 10/19/2020

EPC-06/HW/852 Level & FDD Checking of Subgrade Top layer SG Top 71+740 71+900 RHS 10/19/2020 10/20/2020

EPC-06/HW/857 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+270 71+350 LHS 10/20/2020 10/21/2020

EPC-06/HW/859 FDD and level checking of DLC laying DLC 71+520 71+585 LHS 10/20/2020 10/21/2020

EPC-06/HW/863 FDD and level checking of DLC laying DLC 71+585 71+600 LHS 10/21/2020 10/22/2020

EPC-06/HW/869 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+350 71+385 LHS 10/22/2020 10/23/2020 Not Done

EPC-06/HW/873 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+350 71+385 LHS 10/23/2020 10/24/2020

EPC-06/HW/878 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+385 71+419 LHS 10/25/2020 10/26/2020

EPC-06/HW/884 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+419 71+476 LHS 10/26/2020 10/27/2020

EPC-06/HW/891 Level & FDD Checking of Subgrade Top layer SG Top 74+000 74+180 LHS 10/27/2020 10/28/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/895 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+350 71+450 LHS 10/28/2020 10/29/2020

EPC-06/HW/898 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+450 71+480 LHS 10/29/2020 10/30/2020

EPC-06/HW/900 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+476 71+540 LHS 10/29/2020 10/30/2020

EPC-06/HW/901 Level & FDD Checking For GSB layer GSB 74+030 74+180 LHS 10/29/2020 10/30/2020

EPC-06/HW/902 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+480 71+540 LHS 10/30/2020 10/31/2020

EPC-06/HW/903 FDD and level checking of DLC laying DLC 74+040 74+170 LHS 10/30/2020 10/31/2020

EPC-06/HW/905 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+540 71+600 LHS 10/31/2020 11/1/2020 Not Done

EPC-06/HW/908 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+540 71+600 LHS 11/4/2020 11/5/2020

EPC-06/HW/912 Level and FDD checking of subgrade Top layer SG Top 73+770 74+000 LHS 11/6/2020 11/7/2020

EPC-06/HW/913 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+540 71+600 LHS 11/6/2020 11/7/2020

EPC-06/HW/915 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+140 74+170 LHS 11/7/2020 11/8/2020

EPC-06/HW/920 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+064 74+140 LHS 11/8/2020 11/9/2020

EPC-06/HW/922 Level & FDD Checking For GSB layer GSB 73+900 74+030 LHS 11/8/2020 11/9/2020

EPC-06/HW/934 Level and FDD checking of DLC layer DLC 73+900 74+040 LHS 11/11/2020 11/12/2020

EPC-06/HW/938 Level & FDD Checking For GSB layer GSB 73+770 73+900 LHS 11/12/2020 11/13/2020

EPC-06/HW/942 Level and FDD checking of DLC layer DLC 73+790 73+900 LHS 11/15/2020 11/16/2020

EPC-06/HW/945 Level and FDD checking of subgrade Top layer SG Top 75+700 75+900 LHS 11/16/2020 11/17/2020

EPC-06/HW/949 Level and FDD checking of DLC layer DLC 73+770 73+790 LHS 11/16/2020 11/17/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/952 Level and FDD checking of subgrade Top layer SG Top 71+600 71+740 LHS 11/17/2020 11/18/2020

EPC-06/HW/956 Level & FDD Checking For GSB layer GSB 71+600 71+740 LHS 11/18/2020 11/19/2020

EPC-06/HW/961 Level & FDD Checking For GSB layer GSB 75+700 75+830 LHS 11/19/2020 11/20/2020

EPC-06/HW/965 Level and FDD checking of DLC layer DLC 75+700 75+830 LHS 11/20/2020 11/21/2020

EPC-06/HW/968 Level & FDD Checking For GSB layer GSB 79+700 79+940 LHS 11/21/2020 11/22/2020

EPC-06/HW/970 Level and FDD checking of subgrade Top layer SG Top 74+170 74+300 LHS 11/21/2020 11/22/2020

EPC-06/HW/973 Level & FDD Checking For GSB layer GSB 80+020 80+420 LHS 11/22/2020 11/23/2020

EPC-06/HW/978 Level & FDD Checking For GSB layer GSB 75+830 75+900 LHS 11/23/2020 11/24/2020

EPC-06/HW/989 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 74+087 74+170 LHS 11/26/2020 11/27/2020

EPC-06/HW/992 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 74+064 74+087 LHS 11/27/2020 11/28/2020

EPC-06/HW/993 Level & FDD Checking For GSB layer GSB 74+170 74+980 LHS 11/27/2020 11/28/2020

EPC-06/HW/997 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+000 74+064 LHS 11/28/2020 11/29/2020

EPC-06/HW/1002 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+948 74+000 LHS 11/29/2020 11/30/2020

EPC-06/HW/1004 Level & FDD Checking For GSB layer GSB 79+140 79+640 RHS 11/30/2020 12/1/2020

EPC-06/HW/1007 Level and FDD checking of DLC layer DLC 75+830 75+900 LHS 11/30/2020 12/1/2020

EPC-06/HW/1013 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+920 73+948 LHS 12/2/2020 12/3/2020

EPC-06/HW/1014 Level and FDD checking of subgrade Top layer SG Top 71+100 71+400 RHS 12/2/2020 12/3/2020

EPC-06/HW/1017 FDD Checking of WMM 1st layer WMM-I 80+020 80+420 LHS 12/3/2020 12/4/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1018 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+848 73+920 LHS 12/3/2020 12/4/2020

EPC-06/HW/1020 Level and FDD checking of subgrade Top layer SG Top 71+900 72+220 RHS 12/4/2020 12/5/2020

EPC-06/HW/1021 FDD Checking of WMM 1st layer WMM-I 79+700 79+940 LHS 12/4/2020 12/5/2020

EPC-06/HW/1022 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+770 73+848 LHS 12/4/2020 12/5/2020

EPC-06/HW/1025 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 74+020 74+064 LHS 12/5/2020 12/6/2020

EPC-06/HW/1026 Level and FDD checking of subgrade Top layer SG Top 71+400 71+600 RHS 12/5/2020 12/6/2020

EPC-06/HW/1029 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+930 74+020 LHS 12/6/2020 12/7/2020

EPC-06/HW/1032 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+830 73+930 LHS 12/7/2020 12/8/2020

EPC-06/HW/1033 Level & FDD Checking For GSB layer GSB 71+100 71+400 RHS 12/7/2020 12/8/2020

EPC-06/HW/1036 Level and FDD checking of DLC layer DLC 71+100 71+240 RHS 12/8/2020 12/9/2020

EPC-06/HW/1037 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+770 73+830 LHS 12/8/2020 12/9/2020

EPC-06/HW/1041 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+880 75+900 LHS 12/9/2020 12/10/2020

EPC-06/HW/1044 Level and FDD checking of DLC layer DLC 71+240 71+370 RHS 12/10/2020 12/11/2020

EPC-06/HW/1048 Level & FDD Checking For GSB layer GSB 71+400 71+460 RHS 12/11/2020 12/12/2020

EPC-06/HW/1049 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+820 75+880 LHS 12/11/2020 12/12/2020

EPC-06/HW/1053 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+750 75+820 LHS 12/12/2020 12/13/2020

EPC-06/HW/1062 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 75+700 75+750 LHS 12/13/2020 12/14/2020

EPC-06/HW/1064 Level and FDD checking of DLC layer DLC 71+370 71+440 RHS 12/13/2020 12/14/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1071 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 75+800 75+900 LHS 12/15/2020 12/16/2020

EPC-06/HW/1072 Level & FDD Checking For GSB layer GSB 71+460 71+600 RHS 12/15/2020 12/16/2020

EPC-06/HW/1079 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 75+700 75+800 LHS 12/17/2020 12/18/2020

EPC-06/HW/1084 Level and FDD checking of DLC layer DLC 71+440 71+510 RHS 12/18/2020 12/19/2020

EPC-06/HW/1087 Dismantling of existing BT surface BT Scr 73+420 73+720 BHS 12/19/2020 12/20/2020

EPC-06/HW/1088 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+100 71+185 RHS 12/19/2020 12/20/2020

EPC-06/HW/1089 Level and FDD checking of DLC layer DLC 71+510 71+580 RHS 12/19/2020 12/20/2020

EPC-06/HW/1090 Level & FDD Checking of Subgrade Top layer SG Top 76+720 77+030 RHS 12/19/2020 12/20/2020

EPC-06/HW/1092 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+185 71+230 RHS 12/20/2020 12/21/2020

EPC-06/HW/1093 Level & FDD Checking For GSB layer GSB 76+720 77+030 RHS 12/20/2020 12/21/2020

EPC-06/HW/1094 Level & FDD Checking of Subgrade Top layer SG Top 73+620 73+770 RHS 12/20/2020 12/21/2020

EPC-06/HW/1095 Level and FDD checking of DLC layer DLC 71+580 71+600 RHS 12/20/2020 12/21/2020

EPC-06/HW/1096 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+230 71+295 RHS 12/21/2020 12/22/2020

EPC-06/HW/1097 Dismantling of existing BT surface BT Scr 86+530 86+800 BHS 12/21/2020 12/22/2020

EPC-06/HW/1100 Level & FDD Checking For GSB layer GSB 76+060 76+560 RHS 12/22/2020 12/23/2020

EPC-06/HW/1101 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+295 71+396 RHS 12/22/2020 12/23/2020

EPC-06/HW/1103 Level & FDD Checking of Subgrade Top layer SG Top 86+530 86+650 LHS 12/22/2020 12/23/2020

EPC-06/HW/1104 Level & FDD Checking of Subgrade Top layer SG Top 73+400 73+560 RHS 12/22/2020 12/23/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1107 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+396 71+472 RHS 12/23/2020 12/24/2020

EPC-06/HW/1108 Level & FDD Checking of Subgrade Top layer SG Top 86+650 86+800 LHS 12/23/2020 12/24/2020

EPC-06/HW/1110 Level & FDD Checking For GSB layer GSB 73+620 73+770 RHS 12/23/2020 12/24/2020

EPC-06/HW/1111 Level & FDD Checking of Subgrade Top layer SG Top 73+300 73+350 RHS 12/24/2020 12/25/2020

EPC-06/HW/1112 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+472 71+531 RHS 12/24/2020 12/25/2020

EPC-06/HW/1113 Dismantling of existing BT surface BT Scr 88+960 89+270 BHS 12/24/2020 12/25/2020

EPC-06/HW/1114 Level & FDD Checking For GSB layer GSB 86+530 86+700 LHS 12/24/2020 12/25/2020

EPC-06/HW/1117 Level and FDD checking of DLC layer DLC 86+590 86+660 LHS 12/25/2020 12/26/2020

EPC-06/HW/1118 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 71+531 71+600 RHS 12/25/2020 12/26/2020

EPC-06/HW/1120 Level & FDD Checking For GSB layer GSB 73+400 73+560 RHS 12/25/2020 12/26/2020

EPC-06/HW/1123 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+100 71+180 RHS 12/26/2020 12/27/2020

EPC-06/HW/1125 Level & FDD Checking For GSB layer GSB 73+120 73+350 RHS 12/26/2020 12/27/2020

EPC-06/HW/1127 Level and FDD checking of DLC layer DLC 86+530 86+590 LHS 12/27/2020 12/28/2020

EPC-06/HW/1128 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+180 71+242 RHS 12/27/2020 12/28/2020

EPC-06/HW/1130 Level & FDD Checking For GSB layer GSB 86+700 86+800 LHS 12/27/2020 12/28/2020

EPC-06/HW/1131 Level & FDD Checking For GSB layer GSB 70+750 70+900 LHS 12/27/2020 12/28/2020

EPC-06/HW/1133 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+242 71+346 RHS 12/28/2020 12/29/2020

EPC-06/HW/1134 Level & FDD Checking of Subgrade Top layer SG Top 88+960 89+270 LHS 12/28/2020 12/29/2020
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1135 Level & FDD Checking For GSB layer GSB 70+460 70+710 LHS 12/28/2020 12/29/2020

EPC-06/HW/1136 Level and FDD checking of DLC layer DLC 86+660 86+680 LHS 12/28/2020 12/29/2020

EPC-06/HW/1137 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+346 71+468 RHS 12/29/2020 12/30/2020

EPC-06/HW/1139 Level & FDD Checking For GSB layer GSB 70+340 70+430 RHS 12/29/2020 12/30/2020

EPC-06/HW/1141 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 71+468 71+600 RHS 12/30/2020 12/31/2020

EPC-06/HW/1142 Dismantling of existing BT surface BT Scr 72+000 72+150 BHS 12/30/2020 12/31/2020

EPC-06/HW/1143 Level & FDD Checking For GSB layer GSB 70+090 70+280 RHS 12/30/2020 12/31/2020

EPC-06/HW/1145 Level and FDD checking of DLC layer DLC 86+680 86+750 LHS 12/31/2020 1/1/2021

EPC-06/HW/1149 Level and FDD checking of DLC layer DLC 86+750 86+800 LHS 1/1/2021 1/2/2021

EPC-06/HW/1150 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+530 86+545 LHS 1/1/2021 1/2/2021

EPC-06/HW/1154 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+545 86+609 LHS 1/2/2021 1/3/2021

EPC-06/HW/1155 Level & FDD Checking For GSB layer GSB 88+960 89+160 LHS 1/2/2021 1/3/2021

EPC-06/HW/1157 Level & FDD Checking of Subgrade Top layer SG Top 74+170 74+980 RHS 1/2/2021 1/3/2021

EPC-06/HW/1159 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+609 86+672 LHS 1/3/2021 1/4/2021

EPC-06/HW/1161 Level & FDD Checking of Subgrade Top layer SG Top 71+600 72+400 LHS 1/3/2021 1/4/2021

EPC-06/HW/1163 Level & FDD Checking For GSB layer GSB 89+160 89+270 LHS 1/3/2021 1/4/2021

EPC-06/HW/1164 Level & FDD Checking of Subgrade Top layer SG Top 72+400 73+040 LHS 1/4/2021 1/5/2021

EPC-06/HW/1165 Level & FDD Checking of Subgrade Top layer SG Top 73+110 73+350 LHS 1/4/2021 1/5/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1166 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+672 86+720 LHS 1/4/2021 1/5/2021

EPC-06/HW/1168 Level and FDD checking of DLC layer DLC 88+960 89+035 LHS 1/4/2021 1/5/2021

EPC-06/HW/1169 Level & FDD Checking For GSB layer GSB 74+170 74+980 RHS 1/4/2021 1/5/2021

EPC-06/HW/1170 Level & FDD Checking of Subgrade Top layer SG Top 71+600 71+740 RHS 1/4/2021 1/5/2021

EPC-06/HW/1172 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+720 86+768 LHS 1/5/2021 1/6/2021

EPC-06/HW/1174 Level and FDD checking of DLC layer DLC 89+035 89+130 LHS 1/5/2021 1/6/2021

EPC-06/HW/1175 Level & FDD Checking For GSB layer GSB 71+600 72+300 LHS 1/5/2021 1/6/2021

EPC-06/HW/1178 Level and FDD checking of DLC layer DLC 89+130 89+200 LHS 1/6/2021 1/7/2021

EPC-06/HW/1179 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+768 86+800 LHS 1/6/2021 1/7/2021

EPC-06/HW/1183 Level & FDD Checking For GSB layer GSB 72+300 73+040 LHS 1/6/2021 1/7/2021

EPC-06/HW/1186 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+530 86+567 LHS 1/7/2021 1/8/2021

EPC-06/HW/1188 Level & FDD Checking For GSB layer GSB 73+110 73+350 LHS 1/7/2021 1/8/2021

EPC-06/HW/1189 Level and FDD checking of DLC layer DLC 89+200 89+270 LHS 1/7/2021 1/8/2021

EPC-06/HW/1191 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+567 86+625 LHS 1/8/2021 1/9/2021

EPC-06/HW/1197 Level & FDD Checking of Subgrade Top layer SG Top 72+800 72+870 RHS 1/9/2021 1/10/2021

EPC-06/HW/1200 Level & FDD Checking For GSB layer GSB 71+600 72+250 RHS 1/9/2021 1/10/2021

EPC-06/HW/1207 FDD Checking of WMM 1st layer WMM-I 77+300 78+500 RHS 1/12/2021 1/13/2021

EPC-06/HW/1209 Level & FDD Checking For GSB layer GSB 72+250 73+040 RHS 1/12/2021 1/13/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1212 Dismantling of existing BT surface BT Scr 89+270 91+000 BHS 1/13/2021 1/14/2021

EPC-06/HW/1213 Level & FDD Checking of WMM Top layer WMM-II 77+300 78+400 RHS 1/13/2021 1/14/2021

EPC-06/HW/1215 FDD Checking of WMM 1st layer WMM-I 76+060 76+560 RHS 1/18/2021 1/19/2021

EPC-06/HW/1216 Dismantling of existing BT surface BT Scr 90+700 92+000 BHS 1/13/2021 1/14/2021 Not done

EPC-06/HW/1217 FDD Checking of WMM 1st layer WMM-I 78+500 79+640 RHS 1/13/2021 1/14/2021

EPC-06/HW/1222 Dismantling of existing BT surface BT Scr 90+700 92+000 BHS 1/14/2021 1/15/2021

EPC-06/HW/1223 FDD Checking of WMM 1st layer WMM-I 76+720 77+220 RHS 1/14/2021 1/15/2021

EPC-06/HW/1224 Level & FDD Checking of Subgrade Top layer SG Top 89+270 90+000 LHS 1/14/2021 1/15/2021

EPC-06/HW/1228 Level & FDD Checking of Subgrade Top layer SG Top 90+000 90+700 LHS 1/15/2021 1/16/2021

EPC-06/HW/1229 Dismantling of existing BT surface BT Scr 92+000 93+100 BHS 1/16/2021 1/17/2021

EPC-06/HW/1233 Level & FDD Checking of Subgrade Top layer SG Top 90+700 91+230 LHS 1/16/2021 1/17/2021

EPC-06/HW/1236 Level & FDD Checking of WMM Top layer WMM-II 78+400 79+640 RHS 1/17/2021 1/18/2021

EPC-06/HW/1237 Level & FDD Checking of Subgrade Top layer SG Top 91+300 92+000 LHS 1/17/2021 1/18/2021

EPC-06/HW/1238 Level & FDD Checking of Subgrade Top layer SG Top 92+200 93+000 LHS 1/18/2021 1/19/2021

EPC-06/HW/1239 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+625 86+643 LHS 1/18/2021 1/19/2021

EPC-06/HW/1240 Dismantling of existing BT surface BT Scr 93+100 94+200 BHS 1/18/2021 1/19/2021

EPC-06/HW/1241 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+643 86+715 LHS 1/19/2021 1/20/2021

EPC-06/HW/1243 FDD Checking of WMM 1st layer WMM-I 73+620 73+770 RHS 1/19/2021 1/20/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1244 Level & FDD Checking of WMM Top layer WMM-II 80+020 80+420 LHS 1/19/2021 1/20/2021

EPC-06/HW/1245 Level & FDD Checking of Subgrade Top layer SG Top 76+980 77+030 LHS 1/19/2021 1/20/2021

EPC-06/HW/1246 Level & FDD Checking of Subgrade Top layer SG Top 93+000 93+700 LHS 1/19/2021 1/20/2021

EPC-06/HW/1247 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+715 86+800 LHS 1/20/2021 1/21/2021

EPC-06/HW/1248 FDD Checking of WMM 1st layer WMM-I 74+170 74+980 LHS 1/20/2021 1/21/2021 Not done

EPC-06/HW/1250 FDD Checking of WMM 1st layer WMM-I 75+180 75+700 LHS 1/20/2021 1/21/2021

EPC-06/HW/1251 Level & FDD Checking of Subgrade Top layer SG Top 73+770 74+170 RHS 1/20/2021 1/21/2021

EPC-06/HW/1252 Level & FDD Checking of WMM Top layer WMM-II 79+700 79+940 LHS 1/20/2021 1/21/2021

EPC-06/HW/1253 FDD Checking of WMM 1st layer WMM-I 73+400 73+560 RHS 1/20/2021 1/21/2021

EPC-06/HW/1254 FDD Checking of WMM 1st layer WMM-I 73+120 73+350 RHS 1/20/2021 1/21/2021

EPC-06/HW/1255 Level & FDD Checking of Subgrade Top layer SG Top 93+770 94+200 LHS 1/20/2021 1/21/2021

EPC-06/HW/1256 FDD Checking of WMM 1st layer WMM-I 74+170 74+980 LHS 1/21/2021 1/22/2021

EPC-06/HW/1259 Level & FDD Checking For GSB layer GSB 91+300 92+000 LHS 1/21/2021 1/22/2021

EPC-06/HW/1260 Level & FDD Checking of WMM Top layer WMM-II 76+720 77+220 RHS 1/21/2021 1/22/2021

EPC-06/HW/1261 FDD Checking of WMM 1st layer WMM-I 71+600 72+200 RHS 1/21/2021 1/22/2021

EPC-06/HW/1262 Level & FDD Checking For GSB layer GSB 73+770 74+170 RHS 1/21/2021 1/22/2021

EPC-06/HW/1263 FDD Checking of WMM 1st layer WMM-I 72+200 73+040 RHS 1/22/2021 1/23/2021

EPC-06/HW/1264 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 88+960 89+018 LHS 1/22/2021 1/23/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1267 Level & FDD Checking of WMM Top layer WMM-II 76+060 76+560 RHS 1/22/2021 1/23/2021

EPC-06/HW/1268 Applying primer coat Prime coat 80+020 80+420 LHS 1/22/2021 1/23/2021

EPC-06/HW/1269 Applying primer coat Prime coat 79+700 79+940 LHS 1/22/2021 1/23/2021

EPC-06/HW/1270 Applying primer coat Prime coat 77+300 78+400 RHS 1/22/2021 1/23/2021

EPC-06/HW/1271 FDD Checking of WMM 1st layer WMM-I 70+750 70+900 LHS 1/23/2021 1/24/2021

EPC-06/HW/1272 FDD Checking of WMM 1st layer WMM-I 70+460 70+710 LHS 1/23/2021 1/24/2021

EPC-06/HW/1273 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+018 89+040 LHS 1/23/2021 1/24/2021

EPC-06/HW/1274 Dismantling of existing BT surface BT Scr 80+460 82+150 BHS 1/23/2021 1/24/2021

EPC-06/HW/1275 Applying primer coat Prime coat 78+400 79+640 RHS 1/23/2021 1/24/2021

EPC-06/HW/1276 FDD Checking of WMM 1st layer WMM-I 70+340 70+430 RHS 1/23/2021 1/24/2021

EPC-06/HW/1277 FDD Checking of WMM 1st layer WMM-I 70+090 70+280 RHS 1/23/2021 1/24/2021

EPC-06/HW/1281 Level & FDD Checking of WMM Top layer WMM-II 75+180 75+700 LHS 1/24/2021 1/25/2021

EPC-06/HW/1282 Applying tack coat for DBM Tack coat (DBM) 80+020 80+420 LHS 1/24/2021 1/25/2021

EPC-06/HW/1283 Level checking and laying of DBM DBM 80+020 80+420 LHS 1/24/2021 1/25/2021

EPC-06/HW/1284 Applying tack coat for DBM Tack coat (DBM) 79+700 79+940 LHS 1/24/2021 1/25/2021

EPC-06/HW/1285 Level checking and laying of DBM DBM 79+700 79+940 LHS 1/24/2021 1/25/2021

EPC-06/HW/1286 Level & FDD Checking For GSB layer GSB 89+270 90+200 LHS 1/24/2021 1/25/2021

EPC-06/HW/1288 Level & FDD Checking of Subgrade Top layer SG Top 88+900 89+270 RHS 1/24/2021 1/25/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1290 Level & FDD Checking For GSB layer GSB 88+900 89+270 RHS 1/25/2021 1/26/2021

EPC-06/HW/1292 Level & FDD Checking of WMM Top layer WMM-II 74+170 74+980 LHS 1/26/2021 1/27/2021

EPC-06/HW/1293 Applying primer coat Prime coat 75+180 75+700 LHS 1/26/2021 1/27/2021

EPC-06/HW/1294 Applying primer coat Prime coat 76+720 77+220 RHS 1/26/2021 1/27/2021

EPC-06/HW/1295 Applying tack coat for DBM Tack coat (DBM) 78+400 79+640 RHS 1/26/2021 1/27/2021

EPC-06/HW/1296 Applying primer coat Prime coat 76+060 76+560 RHS 1/26/2021 1/27/2021

EPC-06/HW/1297 Level checking and laying of DBM DBM 78+400 79+640 RHS 1/26/2021 1/27/2021

EPC-06/HW/1298 Level & FDD Checking For GSB layer GSB 80+020 80+420 RHS 1/26/2021 1/27/2021

EPC-06/HW/1299 Level & FDD Checking For GSB layer GSB 79+700 79+940 RHS 1/26/2021 1/27/2021

EPC-06/HW/1300 Level & FDD Checking For GSB layer GSB 90+200 91+040 LHS 1/26/2021 1/27/2021

EPC-06/HW/1301 Level and FDD checking of DLC layer DLC 88+900 89+270 RHS 1/26/2021 1/27/2021

EPC-06/HW/1303 Level & FDD Checking of WMM Top layer WMM-II 80+020 80+420 RHS 1/27/2021 1/28/2021

EPC-06/HW/1304 Level & FDD Checking of WMM Top layer WMM-II 79+700 79+940 RHS 1/27/2021 1/28/2021

EPC-06/HW/1305 Level & FDD Checking of WMM Top layer WMM-II 73+620 73+770 RHS 1/27/2021 1/28/2021

EPC-06/HW/1306 Level & FDD Checking of WMM Top layer WMM-II 73+400 73+560 RHS 1/27/2021 1/28/2021

EPC-06/HW/1307 Applying tack coat for DBM Tack coat (DBM) 77+300 78+400 RHS 1/27/2021 1/28/2021

EPC-06/HW/1308 Level checking and laying of DBM DBM 77+300 78+400 RHS 1/27/2021 1/28/2021

EPC-06/HW/1309 Level & FDD Checking For GSB layer GSB 78+400 79+640 LHS 1/27/2021 1/28/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1310 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+040 89+072 LHS 1/27/2021 1/28/2021

EPC-06/HW/1311 Level & FDD Checking of Subgrade Top layer SG Top 80+500 80+950 LHS 1/28/2021 1/29/2021

EPC-06/HW/1312 Level & FDD Checking of Subgrade Top layer SG Top 81+050 81+440 RHS 1/28/2021 1/29/2021

EPC-06/HW/1313 Level & FDD Checking of Subgrade Top layer SG Top 81+500 82+150 RHS 1/28/2021 1/29/2021

EPC-06/HW/1314 Level & FDD Checking of WMM Top layer WMM-II 78+400 79+640 LHS 1/28/2021 1/29/2021

EPC-06/HW/1315 Applying tack coat for DBM Tack coat (DBM) 76+720 77+220 RHS 1/28/2021 1/29/2021

EPC-06/HW/1316 Level checking and laying of DBM DBM 76+720 77+220 RHS 1/28/2021 1/29/2021

EPC-06/HW/1318 Applying tack coat for DBM Tack coat (DBM) 76+060 76+560 RHS 1/28/2021 1/29/2021

EPC-06/HW/1319 Level & FDD Checking of WMM Top layer WMM-II 73+120 73+350 RHS 1/28/2021 1/29/2021

EPC-06/HW/1320 Level & FDD Checking of WMM Top layer WMM-II 71+600 72+200 RHS 1/28/2021 1/29/2021

EPC-06/HW/1321 Level checking and laying of DBM DBM 76+060 76+560 RHS 1/28/2021 1/29/2021

EPC-06/HW/1322 Level & FDD Checking For GSB layer GSB 77+300 78+400 LHS 1/28/2021 1/29/2021

EPC-06/HW/1323 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+072 89+119 LHS 1/28/2021 1/29/2021

EPC-06/HW/1324 Applying primer coat Prime coat 73+120 73+350 RHS 1/28/2021 1/29/2021

EPC-06/HW/1324 Applying primer coat Prime coat 71+600 72+200 RHS 1/28/2021 1/29/2021

EPC-06/HW/1325 Level & FDD Checking of WMM Top layer WMM-II 77+300 78+400 LHS 1/29/2021 1/30/2021

EPC-06/HW/1326 Applying tack coat for DBM Tack coat (DBM) 73+120 73+350 RHS 1/29/2021 1/30/2021

EPC-06/HW/1327 Applying tack coat for DBM Tack coat (DBM) 71+600 72+200 RHS 1/29/2021 1/30/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1328 Level checking and laying of DBM DBM 73+110 73+350 RHS 1/29/2021 1/30/2021

EPC-06/HW/1329 Level checking and laying of DBM DBM 71+600 72+200 RHS 1/29/2021 1/30/2021

EPC-06/HW/1330 Applying tack coat for DBM Tack coat (DBM) 75+180 75+700 LHS 1/29/2021 1/30/2021

EPC-06/HW/1331 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 88+960 89+060 LHS 1/29/2021 1/30/2021

EPC-06/HW/1332 Level and FDD checking of DLC layer DLC 74+060 74+170 RHS 1/29/2021 1/30/2021

EPC-06/HW/1333 Level checking and laying of DBM DBM 75+180 75+700 LHS 1/29/2021 1/30/2021

EPC-06/HW/1334 Applying primer coat Prime coat 74+170 74+980 LHS 1/29/2021 1/30/2021

EPC-06/HW/1335 Level & FDD Checking of WMM Top layer WMM-II 72+200 73+040 RHS 1/29/2021 1/30/2021

EPC-06/HW/1336 Level & FDD Checking For GSB layer GSB 76+720 77+220 LHS 1/29/2021 1/30/2021

EPC-06/HW/1337 Level & FDD Checking For GSB layer GSB 76+060 76+560 LHS 1/29/2021 1/30/2021

EPC-06/HW/1338 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+119 89+270 LHS 1/29/2021 1/30/2021

EPC-06/HW/1339 Applying primer coat Prime coat 72+200 73+040 RHS 1/29/2021 1/30/2021

EPC-06/HW/1340 Applying tack coat for DBM Tack coat (DBM) 74+170 74+980 RHS 1/30/2021 1/31/2021

EPC-06/HW/1341 Level checking and laying of DBM DBM 74+170 74+980 RHS 1/30/2021 1/31/2021

EPC-06/HW/1342 Level & FDD Checking For GSB layer GSB 80+500 80+950 LHS 1/29/2021 1/30/2021

EPC-06/HW/1342 Level & FDD Checking For GSB layer GSB 81+050 81+440 RHS 1/29/2021 1/30/2021

EPC-06/HW/1342 Level & FDD Checking For GSB layer GSB 81+500 82+150 RHS 1/29/2021 1/30/2021

EPC-06/HW/1344 Applying tack coat for DBM Tack coat (DBM) 72+200 73+040 RHS 1/30/2021 1/31/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1345 Level checking and laying of DBM DBM 72+200 73+040 RHS 1/30/2021 1/31/2021

EPC-06/HW/1346 Level & FDD Checking of WMM Top layer WMM-II 70+750 70+900 LHS 1/30/2021 1/31/2021

EPC-06/HW/1347 Level & FDD Checking of WMM Top layer WMM-II 70+460 70+710 LHS 1/30/2021 1/31/2021

EPC-06/HW/1348 Level & FDD Checking of WMM Top layer WMM-II 70+340 70+430 RHS 1/30/2021 1/31/2021

EPC-06/HW/1349 Level & FDD Checking of WMM Top layer WMM-II 70+090 70+280 RHS 1/30/2021 1/31/2021

EPC-06/HW/1350 Level & FDD Checking For GSB layer GSB 75+180 75+700 RHS 1/30/2021 1/31/2021

EPC-06/HW/1351 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 89+060 89+270 LHS 1/30/2021 1/31/2021

EPC-06/HW/1352 Level and FDD checking of DLC layer DLC 73+770 74+060 RHS 1/30/2021 1/31/2021

EPC-06/HW/1353 FDD Checking of WMM 1st layer WMM-I 80+500 80+950 LHS 1/30/2021 1/31/2021

EPC-06/HW/1354 FDD Checking of WMM 1st layer WMM-I 81+050 81+440 RHS 1/30/2021 1/31/2021

EPC-06/HW/1355 FDD Checking of WMM 1st layer WMM-I 81+500 82+150 RHS 1/30/2021 1/31/2021

EPC-06/HW/1356 Applying primer coat Prime coat 70+090 70+280 RHS 1/30/2021 1/31/2021

EPC-06/HW/1357 Level & FDD Checking of Subgrade Top layer SG Top 70+340 70+460 LHS 1/31/2021 2/1/2021

EPC-06/HW/1358 Level & FDD Checking of Subgrade Top layer SG Top 73+350 73+400 RHS 1/31/2021 2/1/2021

EPC-06/HW/1359 Level & FDD Checking For GSB layer GSB 70+340 70+460 LHS 1/31/2021 2/1/2021

EPC-06/HW/1360 Level & FDD Checking of WMM Top layer WMM-II 80+500 80+950 LHS 1/31/2021 2/1/2021

EPC-06/HW/1361 Level & FDD Checking of WMM Top layer WMM-II 81+050 81+440 RHS 1/31/2021 2/1/2021

EPC-06/HW/1362 Level & FDD Checking of WMM Top layer WMM-II 81+500 82+150 RHS 1/31/2021 2/1/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1363 Applying primer coat Prime coat 80+500 80+950 LHS 1/31/2021 2/1/2021

EPC-06/HW/1363 Applying primer coat Prime coat 81+050 81+440 RHS 1/31/2021 2/1/2021

EPC-06/HW/1363 Applying primer coat Prime coat 81+500 82+150 RHS 1/31/2021 2/1/2021

EPC-06/HW/1364 Applying tack coat for DBM Tack coat (DBM) 70+090 70+280 RHS 1/31/2021 2/1/2021

EPC-06/HW/1365 Level checking and laying of DBM DBM 70+090 70+280 RHS 1/31/2021 2/1/2021

EPC-06/HW/1366 Level & FDD Checking For GSB layer GSB 73+350 73+400 RHS 2/1/2021 2/2/2021

EPC-06/HW/1367 FDD Checking of WMM 1st layer WMM-I 70+340 70+460 LHS 2/1/2021 2/2/2021

EPC-06/HW/1368 Applying tack coat for DBM Tack coat (DBM) 80+500 80+950 LHS 2/1/2021 2/2/2021

EPC-06/HW/1368 Applying tack coat for DBM Tack coat (DBM) 81+050 81+440 RHS 2/1/2021 2/2/2021

EPC-06/HW/1368 Applying tack coat for DBM Tack coat (DBM) 81+500 82+150 RHS 2/1/2021 2/2/2021

EPC-06/HW/1369 Level checking and laying of DBM DBM 80+500 80+950 LHS 2/1/2021 2/2/2021

EPC-06/HW/1369 Level checking and laying of DBM DBM 81+050 81+440 RHS 2/1/2021 2/2/2021

EPC-06/HW/1369 Level checking and laying of DBM DBM 81+500 82+150 RHS 2/1/2021 2/2/2021

EPC-06/HW/1370 FDD Checking of WMM 1st layer WMM-I 73+350 73+400 RHS 2/2/2021 2/3/2021

EPC-06/HW/1371 Level & FDD Checking of WMM Top layer WMM-II 70+340 70+460 LHS 2/2/2021 2/3/2021

EPC-06/HW/1372 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 88+900 89+000 RHS 2/2/2021 2/3/2021

EPC-06/HW/1373 Level & FDD Checking of WMM Top layer WMM-II 73+350 73+400 RHS 2/3/2021 2/4/2021

EPC-06/HW/1374 Applying primer coat Prime coat 73+350 73+560 RHS 2/3/2021 2/4/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1374 Applying primer coat Prime coat 70+340 70+710 LHS 2/3/2021 2/4/2021

EPC-06/HW/1374 Applying primer coat Prime coat 70+750 70+900 LHS 2/3/2021 2/4/2021

EPC-06/HW/1375 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+000 89+040 RHS 2/3/2021 2/4/2021

EPC-06/HW/1376 Applying tack coat for DBM Tack coat (DBM) 73+350 73+560 RHS 2/4/2021 2/5/2021

EPC-06/HW/1376 Applying tack coat for DBM Tack coat (DBM) 70+340 70+710 LHS 2/4/2021 2/5/2021

EPC-06/HW/1376 Applying tack coat for DBM Tack coat (DBM) 70+750 70+900 LHS 2/4/2021 2/5/2021

EPC-06/HW/1377 Level checking and laying of DBM DBM 73+350 73+560 RHS 2/4/2021 2/5/2021

EPC-06/HW/1377 Level checking and laying of DBM DBM 70+340 70+710 LHS 2/4/2021 2/5/2021

EPC-06/HW/1377 Level checking and laying of DBM DBM 70+750 70+900 LHS 2/4/2021 2/5/2021

EPC-06/HW/1378 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+040 89+070 RHS 2/4/2021 2/5/2021

EPC-06/HW/1379 FDD Checking of WMM 1st layer WMM-I 76+720 77+220 LHS 2/5/2021 2/6/2021

EPC-06/HW/1380 FDD Checking of WMM 1st layer WMM-I 76+060 76+560 LHS 2/6/2021 2/7/2021

EPC-06/HW/1381 Level & FDD Checking of WMM Top layer WMM-II 76+720 77+220 LHS 2/6/2021 2/7/2021

EPC-06/HW/1382 Applying primer coat Prime coat 80+020 80+420 RHS 2/6/2021 2/7/2021

EPC-06/HW/1382 Applying primer coat Prime coat 79+700 79+940 RHS 2/6/2021 2/7/2021

EPC-06/HW/1382 Applying primer coat Prime coat 79+000 79+630 LHS 2/6/2021 2/7/2021

EPC-06/HW/1383 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+070 89+140 RHS 2/6/2021 2/7/2021

EPC-06/HW/1384 FDD Checking of WMM 1st layer WMM-I 75+180 75+700 RHS 2/7/2021 2/8/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1385 Level & FDD Checking of WMM Top layer WMM-II 76+060 76+560 LHS 2/7/2021 2/8/2021

EPC-06/HW/1386 Applying primer coat Prime coat 77+600 79+000 LHS 2/7/2021 2/8/2021

EPC-06/HW/1387 Applying tack coat for DBM Tack coat (DBM) 80+020 80+420 RHS 2/7/2021 2/8/2021

EPC-06/HW/1387 Applying tack coat for DBM Tack coat (DBM) 79+700 79+940 RHS 2/7/2021 2/8/2021

EPC-06/HW/1387 Applying tack coat for DBM Tack coat (DBM) 79+000 79+630 LHS 2/7/2021 2/8/2021

EPC-06/HW/1388 Level checking and laying of DBM DBM 80+020 80+420 RHS 2/7/2021 2/8/2021

EPC-06/HW/1388 Level checking and laying of DBM DBM 79+700 79+940 RHS 2/7/2021 2/8/2021

EPC-06/HW/1388 Level checking and laying of DBM DBM 79+000 79+630 LHS 2/7/2021 2/8/2021

EPC-06/HW/1389 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+140 89+160 RHS 2/7/2021 2/8/2021

EPC-06/HW/1390 Level & FDD Checking of Subgrade Top layer SG Top 73+350 73+560 LHS 2/8/2021 2/9/2021

EPC-06/HW/1391 FDD Checking of WMM 1st layer WMM-I 74+170 74+980 RHS 2/8/2021 2/9/2021

EPC-06/HW/1392 Level & FDD Checking of WMM Top layer WMM-II 75+180 75+700 RHS 2/8/2021 2/9/2021

EPC-06/HW/1393 Applying tack coat for DBM Tack coat (DBM) 77+600 79+000 LHS 2/8/2021 2/9/2021

EPC-06/HW/1394 Level checking and laying of DBM DBM 77+600 79+000 LHS 2/8/2021 2/9/2021

EPC-06/HW/1395 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+160 89+200 RHS 2/8/2021 2/9/2021

EPC-06/HW/1396 Level & FDD Checking For GSB layer GSB 73+350 73+560 LHS 2/9/2021 2/10/2021

EPC-06/HW/1397 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+200 89+270 RHS 2/9/2021 2/10/2021

EPC-06/HW/1398 Level & FDD Checking of WMM Top layer WMM-II 74+170 74+980 RHS 2/9/2021 2/10/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1399 Level and FDD checking of DLC layer DLC 75+830 75+850 RHS 2/9/2021 2/10/2021

EPC-06/HW/1400 FDD Checking of WMM 1st layer WMM-I 73+120 73+560 LHS 2/10/2021 2/11/2021

EPC-06/HW/1401 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+150 74+170 RHS 2/10/2021 2/11/2021

EPC-06/HW/1402 FDD Checking of WMM 1st layer WMM-I 72+200 73+040 LHS 2/11/2021 2/12/2021

EPC-06/HW/1403 Level & FDD Checking of WMM Top layer WMM-II 73+120 73+560 LHS 2/11/2021 2/12/2021

EPC-06/HW/1404 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+090 74+150 RHS 2/11/2021 2/12/2021

EPC-06/HW/1405 Level & FDD Checking of WMM Top layer WMM-II 72+200 73+040 LHS 2/12/2021 2/13/2021

EPC-06/HW/1406 Applying primer coat Prime coat 77+300 77+600 LHS 2/12/2021 2/13/2021

EPC-06/HW/1406 Applying primer coat Prime coat 76+720 77+220 LHS 2/12/2021 2/13/2021

EPC-06/HW/1406 Applying primer coat Prime coat 76+060 76+560 LHS 2/12/2021 2/13/2021

EPC-06/HW/1406 Applying primer coat Prime coat 75+180 75+700 RHS 2/12/2021 2/13/2021

EPC-06/HW/1407 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+040 74+090 RHS 2/12/2021 2/13/2021

EPC-06/HW/1408 Applying tack coat for DBM Tack coat (DBM) 77+300 77+600 LHS 2/13/2021 2/14/2021

EPC-06/HW/1408 Applying tack coat for DBM Tack coat (DBM) 76+720 77+220 LHS 2/13/2021 2/14/2021

EPC-06/HW/1408 Applying tack coat for DBM Tack coat (DBM) 76+060 76+560 LHS 2/13/2021 2/14/2021

EPC-06/HW/1408 Applying tack coat for DBM Tack coat (DBM) 75+180 75+700 RHS 2/13/2021 2/14/2021

EPC-06/HW/1409 Level checking and laying of DBM DBM 77+300 77+600 LHS 2/13/2021 2/14/2021

EPC-06/HW/1409 Level checking and laying of DBM DBM 76+720 77+220 LHS 2/13/2021 2/14/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1409 Level checking and laying of DBM DBM 76+060 76+560 LHS 2/13/2021 2/14/2021

EPC-06/HW/1409 Level checking and laying of DBM DBM 75+180 75+700 RHS 2/13/2021 2/14/2021

EPC-06/HW/1410 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 74+000 74+040 RHS 2/13/2021 2/14/2021

EPC-06/HW/1411 Level & FDD Checking of Subgrade Top layer SG Top 70+750 70+980 RHS 2/14/2021 2/15/2021

EPC-06/HW/1412 FDD Checking of WMM 1st layer WMM-I 71+600 72+200 LHS 2/14/2021 2/15/2021

EPC-06/HW/1413 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+960 74+000 RHS 2/14/2021 2/15/2021

EPC-06/HW/1414 Level & FDD Checking of Subgrade Top layer SG Top 70+430 70+710 RHS 2/15/2021 2/16/2021

EPC-06/HW/1415 Level & FDD Checking of Subgrade Top layer SG Top 70+090 70+280 LHS 2/15/2021 2/16/2021

EPC-06/HW/1416 Level & FDD Checking of WMM Top layer WMM-II 71+600 72+200 LHS 2/15/2021 2/16/2021

EPC-06/HW/1417 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+890 73+960 RHS 2/15/2021 2/16/2021

EPC-06/HW/1418 Level & FDD Checking of Subgrade Top layer SG Top 86+530 86+800 RHS 2/16/2021 2/17/2021

EPC-06/HW/1419 Level & FDD Checking For GSB layer GSB 70+750 70+980 RHS 2/16/2021 2/17/2021

EPC-06/HW/1420 Level & FDD Checking For GSB layer GSB 70+430 70+710 RHS 2/16/2021 2/17/2021

EPC-06/HW/1421 Level & FDD Checking For GSB layer GSB 70+090 70+280 LHS 2/16/2021 2/17/2021

EPC-06/HW/1422 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+840 73+890 RHS 2/16/2021 2/17/2021

EPC-06/HW/1423 FDD Checking of WMM 1st layer WMM-I 70+090 70+280 LHS 2/17/2021 2/18/2021

EPC-06/HW/1424 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 75+830 75+850 RHS 2/17/2021 2/18/2021

EPC-06/HW/1425 Level & FDD Checking For GSB layer GSB 86+530 86+800 RHS 2/18/2021 2/19/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1426 FDD Checking of WMM 1st layer WMM-I 70+750 70+980 RHS 2/18/2021 2/19/2021

EPC-06/HW/1427 FDD Checking of WMM 1st layer WMM-I 70+430 70+710 RHS 2/18/2021 2/19/2021

EPC-06/HW/1428 Level & FDD Checking of WMM Top layer WMM-II 70+090 70+280 LHS 2/18/2021 2/19/2021

EPC-06/HW/1429 Applying primer coat Prime coat 74+170 74+980 RHS 2/18/2021 2/19/2021

EPC-06/HW/1429 Applying primer coat Prime coat 73+620 73+770 RHS 2/18/2021 2/19/2021

EPC-06/HW/1429 Applying primer coat Prime coat 73+120 73+560 LHS 2/18/2021 2/19/2021

EPC-06/HW/1429 Applying primer coat Prime coat 72+600 73+040 LHS 2/18/2021 2/19/2021

EPC-06/HW/1430 Level & FDD Checking of WMM Top layer WMM-II 70+750 70+980 RHS 2/19/2021 2/20/2021

EPC-06/HW/1431 Level & FDD Checking of WMM Top layer WMM-II 70+430 70+710 RHS 2/19/2021 2/20/2021

EPC-06/HW/1432 Applying primer coat Prime coat 72+200 72+600 LHS 2/19/2021 2/20/2021

EPC-06/HW/1432 Applying primer coat Prime coat 71+600 72+200 LHS 2/19/2021 2/20/2021

EPC-06/HW/1432 Applying primer coat Prime coat 70+750 70+980 RHS 2/19/2021 2/20/2021

EPC-06/HW/1432 Applying primer coat Prime coat 70+340 70+710 RHS 2/19/2021 2/20/2021

EPC-06/HW/1432 Applying primer coat Prime coat 70+090 70+280 LHS 2/19/2021 2/20/2021

EPC-06/HW/1433 Applying tack coat for DBM Tack coat (DBM) 74+170 74+980 RHS 2/19/2021 2/20/2021

EPC-06/HW/1433 Applying tack coat for DBM Tack coat (DBM) 73+620 73+770 RHS 2/19/2021 2/20/2021

EPC-06/HW/1433 Applying tack coat for DBM Tack coat (DBM) 73+120 73+560 LHS 2/19/2021 2/20/2021

EPC-06/HW/1433 Applying tack coat for DBM Tack coat (DBM) 72+600 73+040 LHS 2/19/2021 2/20/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1434 Level checking and laying of DBM DBM 74+170 74+980 RHS 2/19/2021 2/20/2021

EPC-06/HW/1434 Level checking and laying of DBM DBM 73+620 73+770 RHS 2/19/2021 2/20/2021

EPC-06/HW/1434 Level checking and laying of DBM DBM 73+120 73+560 LHS 2/19/2021 2/20/2021

EPC-06/HW/1434 Level checking and laying of DBM DBM 72+600 73+040 LHS 2/19/2021 2/20/2021

EPC-06/HW/1435 Level and FDD checking of DLC layer DLC 86+530 86+800 RHS 2/19/2021 2/20/2021

EPC-06/HW/1436 Level & FDD Checking of Subgrade Top layer SG Top 92+000 92+200 LHS 2/19/2021 2/20/2021

EPC-06/HW/1438 Applying tack coat for DBM Tack coat (DBM) 72+200 72+600 LHS 2/20/2021 2/21/2021

EPC-06/HW/1438 Applying tack coat for DBM Tack coat (DBM) 71+600 72+200 LHS 2/20/2021 2/21/2021

EPC-06/HW/1438 Applying tack coat for DBM Tack coat (DBM) 70+750 70+980 RHS 2/20/2021 2/21/2021

EPC-06/HW/1438 Applying tack coat for DBM Tack coat (DBM) 70+340 70+710 RHS 2/20/2021 2/21/2021

EPC-06/HW/1438 Applying tack coat for DBM Tack coat (DBM) 70+090 70+280 LHS 2/20/2021 2/21/2021

EPC-06/HW/1439 Level checking and laying of DBM DBM 72+200 72+600 LHS 2/20/2021 2/21/2021

EPC-06/HW/1439 Level checking and laying of DBM DBM 71+600 72+200 LHS 2/20/2021 2/21/2021

EPC-06/HW/1439 Level checking and laying of DBM DBM 70+750 70+980 RHS 2/20/2021 2/21/2021

EPC-06/HW/1439 Level checking and laying of DBM DBM 70+340 70+710 RHS 2/20/2021 2/21/2021

EPC-06/HW/1439 Level checking and laying of DBM DBM 70+090 70+280 LHS 2/20/2021 2/21/2021

EPC-06/HW/1440 Level & FDD Checking For GSB layer GSB 92+000 92+500 LHS 2/20/2021 2/21/2021 Not done

EPC-06/HW/1443 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 73+770 73+840 RHS 2/21/2021 2/22/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1444 Level & FDD Checking For GSB layer GSB 92+000 92+500 LHS 2/21/2021 2/22/2021

EPC-06/HW/1446 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 74+100 74+170 RHS 2/22/2021 2/23/2021

EPC-06/HW/1447 Level & FDD Checking For GSB layer GSB 92+500 92+950 LHS 2/22/2021 2/23/2021

EPC-06/HW/1450 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 74+050 74+100 RHS 2/23/2021 2/24/2021

EPC-06/HW/1451 Dismantling of existing BT surface BT Scr 66+320 67+500 BHS 1/23/2021 1/24/2021

EPC-06/HW/1452 Level & FDD Checking For GSB layer GSB 92+950 93+700 LHS 1/23/2021 1/24/2021

EPC-06/HW/1454 Level & FDD Checking of Subgrade Top layer SG Top 80+500 80+950 RHS 2/24/2021 2/25/2021

EPC-06/HW/1455 Level & FDD Checking of Subgrade Top layer SG Top 81+050 81+440 LHS 2/24/2021 2/25/2021

EPC-06/HW/1456 Level & FDD Checking of Subgrade Top layer SG Top 81+500 82+150 LHS 2/24/2021 2/25/2021

EPC-06/HW/1457 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+960 74+050 RHS 2/24/2021 2/25/2021

EPC-06/HW/1458 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 88+900 89+000 RHS 2/24/2021 2/25/2021

EPC-06/HW/1459 Level & FDD Checking For GSB layer GSB 93+770 94+200 LHS 2/24/2021 2/25/2021

EPC-06/HW/1463 Level & FDD Checking of Subgrade Top layer SG Top 67+130 67+500 LHS 2/25/2021 2/26/2021

EPC-06/HW/1464 Level & FDD Checking For GSB layer GSB 80+500 80+950 RHS 2/25/2021 2/26/2021

EPC-06/HW/1465 Level & FDD Checking For GSB layer GSB 81+050 81+440 LHS 2/25/2021 2/26/2021

EPC-06/HW/1466 Level & FDD Checking For GSB layer GSB 81+500 82+150 LHS 2/25/2021 2/26/2021

EPC-06/HW/1467 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+910 73+960 RHS 2/25/2021 2/26/2021

EPC-06/HW/1468 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 89+000 89+110 RHS 2/25/2021 2/26/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1469 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+830 73+910 RHS 2/25/2021 2/26/2021 Not Done

EPC-06/HW/1473 Level & FDD Checking of Subgrade Top layer SG Top 66+320 67+070 LHS 2/26/2021 2/27/2021

EPC-06/HW/1474 Level & FDD Checking For GSB layer GSB 67+130 67+500 LHS 2/26/2021 2/27/2021

EPC-06/HW/1475 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+830 73+910 RHS 2/26/2021 2/27/2021

EPC-06/HW/1476 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 89+110 89+270 RHS 2/26/2021 2/27/2021

EPC-06/HW/1477 Dismantling of existing BT surface BT Scr 65+050 66+320 BHS 2/26/2021 2/27/2021

EPC-06/HW/1481 Level & FDD Checking For GSB layer GSB 66+320 67+070 LHS 2/27/2021 2/28/2021

EPC-06/HW/1482 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 73+770 73+830 RHS 2/27/2021 2/28/2021

EPC-06/HW/1483 Dismantling of existing BT surface BT Scr 64+000 65+050 BHS 2/27/2021 2/28/2021

EPC-06/HW/1494 FDD Checking of Subgrade Top layer on Minor Junction SG Top 88+965 LHS 2/28/2021 3/1/2021

EPC-06/HW/1495 Level & FDD Checking of Subgrade Top layer SG Top 65+970 66+250 LHS 2/28/2021 3/1/2021

EPC-06/HW/1496 FDD Checking of WMM 1st layer WMM-I 89+270 90+000 LHS 2/28/2021 3/1/2021

EPC-06/HW/1499 FDD Checking For GSB layer on Minor Junction GSB 88+965 LHS 3/1/2021 3/2/2021

EPC-06/HW/1500 Level & FDD Checking For GSB layer GSB 91+040 91+230 LHS 3/1/2021 3/2/2021

EPC-06/HW/1501 FDD Checking of WMM 1st layer WMM-I 90+000 90+550 LHS 3/1/2021 3/2/2021

EPC-06/HW/1502 Level & FDD Checking of WMM Top layer WMM-II 89+270 90+000 LHS 3/1/2021 3/2/2021

EPC-06/HW/1504 FDD Checking of WMM Top layer on Minor Junction WMM-II 88+965 LHS 3/2/2021 3/3/2021

EPC-06/HW/1505 Applying primer coat on Minor Junction Prime coat 88+965 LHS 3/2/2021 3/3/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1506 Level & FDD Checking of Subgrade Top layer SG Top 65+010 65+900 LHS 3/2/2021 3/3/2021

EPC-06/HW/1507 Level & FDD Checking of WMM Top layer WMM-II 90+000 90+550 LHS 3/2/2021 3/3/2021

EPC-06/HW/1508 Applying primer coat Prime coat 89+270 90+400 LHS 3/2/2021 3/3/2021

EPC-06/HW/1511 FDD Checking of Subgrade Top layer on Minor Junction SG Top 90+950 LHS 3/3/2021 3/4/2021

EPC-06/HW/1512 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 88+965 LHS 3/3/2021 3/4/2021

EPC-06/HW/1513 FDD Checking of WMM 1st layer WMM-I 90+550 91+230 LHS 3/3/2021 3/4/2021

EPC-06/HW/1514 Applying tack coat for DBM Tack coat (DBM) 89+270 90+400 LHS 3/3/2021 3/4/2021

EPC-06/HW/1515 Level checking and laying of DBM DBM 89+270 90+400 LHS 3/3/2021 3/4/2021

EPC-06/HW/1516 Laying of DBM on Minor Junction DBM 88+965 LHS 3/3/2021 3/4/2021

EPC-06/HW/1517 FDD Checking of WMM 1st layer WMM-I 91+300 92+000 LHS 3/3/2021 3/4/2021 Not done

EPC-06/HW/1520 FDD Checking For GSB layer on Minor Junction GSB 90+950 LHS 3/4/2021 3/5/2021

EPC-06/HW/1521 Level & FDD Checking of Subgrade Top layer SG Top 64+520 64+890 LHS 3/4/2021 3/5/2021

EPC-06/HW/1522 Level & FDD Checking For GSB layer GSB 65+970 66+250 LHS 3/4/2021 3/5/2021

EPC-06/HW/1523 FDD Checking of WMM 1st layer WMM-I 91+300 92+000 LHS 3/4/2021 3/5/2021

EPC-06/HW/1524 Level & FDD Checking of WMM Top layer WMM-II 90+550 91+230 LHS 3/4/2021 3/5/2021

EPC-06/HW/1526 FDD Checking of Subgrade Top layer on Minor Junction SG Top 91+562 LHS 3/5/2021 3/6/2021

EPC-06/HW/1527 FDD Checking of Subgrade Top layer on Minor Junction SG Top 80+990 RHS 3/5/2021 3/6/2021

EPC-06/HW/1528 FDD Checking of WMM Top layer on Minor Junction WMM-II 90+950 LHS 3/5/2021 3/6/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1529 Applying primer coat on Minor Junction Prime coat 90+950 LHS 3/5/2021 3/6/2021

EPC-06/HW/1530 FDD Checking of WMM 1st layer WMM-I 92+000 92+700 LHS 3/5/2021 3/6/2021

EPC-06/HW/1531 Level & FDD Checking of WMM Top layer WMM-II 91+300 92+000 LHS 3/5/2021 3/6/2021

EPC-06/HW/1532 Applying primer coat Prime coat 90+400 91+230 LHS 3/5/2021 3/6/2021

EPC-06/HW/1533 Dismantling of existing BT surface BT Scr 86+800 86+868 BHS 3/6/2021 3/7/2021

EPC-06/HW/1534 FDD Checking of Subgrade Top layer on Minor Junction SG Top 77+000 BHS 3/6/2021 3/7/2021

EPC-06/HW/1535 FDD Checking of Subgrade Top layer on Minor Junction SG Top 73+440 RHS 3/6/2021 3/7/2021

EPC-06/HW/1536 FDD Checking of Subgrade Top layer on Minor Junction SG Top 73+760 LHS 3/6/2021 3/7/2021

EPC-06/HW/1537 FDD Checking For GSB layer on Minor Junction GSB 91+562 LHS 3/6/2021 3/7/2021

EPC-06/HW/1538 FDD Checking For GSB layer on Minor Junction GSB 80+990 RHS 3/6/2021 3/7/2021

EPC-06/HW/1539 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 90+950 LHS 3/6/2021 3/7/2021

EPC-06/HW/1540 Level & FDD Checking of Subgrade Top layer SG Top 64+000 64+250 LHS 3/6/2021 3/7/2021

EPC-06/HW/1541 Level & FDD Checking of Subgrade Top layer SG Top 64+310 64+450 LHS 3/6/2021 3/7/2021

EPC-06/HW/1542 FDD Checking of WMM 1st layer WMM-I 92+700 93+400 LHS 3/6/2021 3/7/2021

EPC-06/HW/1543 Level & FDD Checking of WMM Top layer WMM-II 92+000 92+700 LHS 3/6/2021 3/7/2021

EPC-06/HW/1544 Applying tack coat for DBM Tack coat (DBM) 90+400 91+230 LHS 3/6/2021 3/7/2021

EPC-06/HW/1544 Laying of DBM on Minor Junction DBM 90+950 LHS 3/6/2021 3/7/2021

EPC-06/HW/1545 Level checking and laying of DBM DBM 90+400 91+230 LHS 3/6/2021 3/7/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1545 FDD Checking For GSB layer on Minor Junction GSB 77+000 BHS 3/7/2021 3/8/2021

EPC-06/HW/1546 FDD Checking For GSB layer on Minor Junction GSB 73+440 RHS 3/7/2021 3/8/2021

EPC-06/HW/1547 FDD Checking For GSB layer on Minor Junction GSB 73+760 LHS 3/7/2021 3/8/2021

EPC-06/HW/1548 FDD Checking of WMM Top layer on Minor Junction WMM-II 91+562 LHS 3/7/2021 3/8/2021

EPC-06/HW/1549 FDD Checking of WMM Top layer on Minor Junction WMM-II 80+990 RHS 3/7/2021 3/8/2021

EPC-06/HW/1550 Applying primer coat on Minor Junction Prime coat 91+562 LHS 3/7/2021 3/8/2021

EPC-06/HW/1551 Applying primer coat on Minor Junction Prime coat 80+990 RHS 3/7/2021 3/8/2021

EPC-06/HW/1552 Level & FDD Checking For GSB layer GSB 65+010 65+900 LHS 3/7/2021 3/8/2021

EPC-06/HW/1553 FDD Checking of WMM 1st layer WMM-I 93+400 93+700 LHS 3/7/2021 3/8/2021

EPC-06/HW/1554 FDD Checking of WMM 1st layer WMM-I 93+770 94+200 LHS 3/7/2021 3/8/2021

EPC-06/HW/1555 Level & FDD Checking of WMM Top layer WMM-II 92+700 93+400 LHS 3/7/2021 3/8/2021

EPC-06/HW/1556 Applying primer coat Prime coat 91+300 92+700 LHS 3/7/2021 3/8/2021

EPC-06/HW/1557 Level & FDD Checking of Subgrade Top layer SG Top 86+800 86+840 RHS 3/7/2021 3/8/2021

EPC-06/HW/1559 FDD Checking of WMM Top layer on Minor Junction WMM-II 77+000 BHS 3/8/2021 3/9/2021

EPC-06/HW/1560 FDD Checking of WMM Top layer on Minor Junction WMM-II 73+440 RHS 3/8/2021 3/9/2021

EPC-06/HW/1561 FDD Checking of WMM Top layer on Minor Junction WMM-II 73+760 LHS 3/8/2021 3/9/2021

EPC-06/HW/1562 Applying primer coat on Minor Junction Prime coat 77+000 BHS 3/8/2021 3/9/2021

EPC-06/HW/1563 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 91+562 LHS 3/8/2021 3/9/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1564 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 80+990 RHS 3/8/2021 3/9/2021

EPC-06/HW/1565 Level & FDD Checking For GSB layer GSB 64+520 64+890 LHS 3/8/2021 3/9/2021

EPC-06/HW/1566 Level & FDD Checking of WMM Top layer WMM-II 93+400 93+700 LHS 3/8/2021 3/9/2021

EPC-06/HW/1567 Level & FDD Checking of WMM Top layer WMM-II 93+770 94+200 LHS 3/8/2021 3/9/2021

EPC-06/HW/1568 Applying primer coat Prime coat 92+700 93+700 LHS 3/8/2021 3/9/2021

EPC-06/HW/1569 Applying primer coat Prime coat 93+770 94+200 LHS 3/8/2021 3/9/2021

EPC-06/HW/1570 Applying tack coat for DBM Tack coat (DBM) 91+300 92+700 LHS 3/8/2021 3/9/2021

EPC-06/HW/1571 Level checking and laying of DBM DBM 91+300 92+700 LHS 3/8/2021 3/9/2021

EPC-06/HW/1572 Level & FDD Checking For GSB layer GSB 86+800 86+840 RHS 3/8/2021 3/9/2021

EPC-06/HW/1573 Laying of DBM on Minor Junction DBM 91+562 LHS 3/8/2021 3/9/2021

EPC-06/HW/1574 Laying of DBM on Minor Junction DBM 80+990 RHS 3/8/2021 3/9/2021

EPC-06/HW/1575 Applying primer coat on Minor Junction Prime coat 73+440 RHS 3/8/2021 3/9/2021

EPC-06/HW/1576 Applying primer coat on Minor Junction Prime coat 73+760 LHS 3/8/2021 3/9/2021

EPC-06/HW/1577 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 77+000 BHS 3/9/2021 3/10/2021

EPC-06/HW/1578 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 73+440 RHS 3/9/2021 3/10/2021

EPC-06/HW/1579 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 73+760 LHS 3/9/2021 3/10/2021

EPC-06/HW/1580 Level & FDD Checking For GSB layer GSB 64+310 64+450 LHS 3/9/2021 3/10/2021

EPC-06/HW/1581 Applying tack coat for DBM Tack coat (DBM) 92+700 93+700 LHS 3/9/2021 3/10/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1582 Applying tack coat for DBM Tack coat (DBM) 93+770 94+200 LHS 3/9/2021 3/10/2021

EPC-06/HW/1583 Level checking and laying of DBM DBM 92+700 93+700 LHS 3/9/2021 3/10/2021

EPC-06/HW/1584 Level checking and laying of DBM DBM 93+770 94+200 LHS 3/9/2021 3/10/2021

EPC-06/HW/1585 Level and FDD checking of DLC layer DLC 86+800 86+840 RHS 3/9/2021 3/10/2021

EPC-06/HW/1586 Laying of DBM on Minor Junction DBM 77+000 BHS 3/9/2021 3/10/2021

EPC-06/HW/1587 Laying of DBM on Minor Junction DBM 73+440 RHS 3/9/2021 3/10/2021

EPC-06/HW/1588 Laying of DBM on Minor Junction DBM 73+760 LHS 3/9/2021 3/10/2021

EPC-06/HW/1589 FDD Checking of WMM 1st layer WMM-I 80+500 80+950 RHS 3/9/2021 3/10/2021 Not Done

EPC-06/HW/1593 Level & FDD Checking For GSB layer GSB 64+000 64+250 LHS 3/10/2021 3/11/2021

EPC-06/HW/1594 FDD Checking of WMM 1st layer WMM-I 80+500 80+950 RHS 3/10/2021 3/11/2021

EPC-06/HW/1601 FDD Checking of WMM 1st layer WMM-I 81+050 81+440 LHS 3/11/2021 3/12/2021

EPC-06/HW/1602 Level & FDD Checking of WMM Top layer WMM-II 80+500 80+950 RHS 3/11/2021 3/12/2021

EPC-06/HW/1610 Level & FDD Checking of WMM Top layer WMM-II 81+050 81+440 LHS 3/12/2021 3/13/2021

EPC-06/HW/1620 FDD Checking of WMM 1st layer WMM-I 81+500 82+150 LHS 3/13/2021 3/14/2021

EPC-06/HW/1627 FDD Checking of Subgrade Top layer on Minor Junction SG Top 80+750 LHS 3/14/2021 3/15/2021

EPC-06/HW/1628 FDD Checking of Subgrade Top layer on Minor Junction SG Top 79+550 RHS 3/14/2021 3/15/2021

EPC-06/HW/1629 FDD Checking of Subgrade Top layer on Minor Junction SG Top 78+750 RHS 3/14/2021 3/15/2021

EPC-06/HW/1630 Level & FDD Checking of WMM Top layer WMM-II 81+500 82+150 LHS 3/14/2021 3/15/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1634 FDD Checking For GSB layer on Minor Junction GSB 80+750 LHS 3/15/2021 3/16/2021

EPC-06/HW/1635 FDD Checking For GSB layer on Minor Junction GSB 79+550 RHS 3/15/2021 3/16/2021

EPC-06/HW/1636 FDD Checking For GSB layer on Minor Junction GSB 78+750 RHS 3/15/2021 3/16/2021

EPC-06/HW/1639 FDD Checking of WMM Top layer on Minor Junction WMM-II 80+750 LHS 3/16/2021 3/17/2021

EPC-06/HW/1640 FDD Checking of WMM Top layer on Minor Junction WMM-II 79+550 RHS 3/16/2021 3/17/2021

EPC-06/HW/1641 FDD Checking of WMM Top layer on Minor Junction WMM-II 78+750 RHS 3/16/2021 3/17/2021

EPC-06/HW/1642 Applying primer coat on Minor Junction Prime coat 80+750 LHS 3/16/2021 3/17/2021

EPC-06/HW/1643 Applying primer coat on Minor Junction Prime coat 79+550 RHS 3/16/2021 3/17/2021

EPC-06/HW/1644 Applying primer coat on Minor Junction Prime coat 78+750 RHS 3/16/2021 3/17/2021

EPC-06/HW/1645 Applying primer coat Prime coat 80+500 80+950 RHS 3/16/2021 3/17/2021

EPC-06/HW/1646 Applying primer coat Prime coat 81+050 81+440 LHS 3/16/2021 3/17/2021

EPC-06/HW/1647 Applying primer coat Prime coat 81+500 82+150 LHS 3/16/2021 3/17/2021

EPC-06/HW/1657 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 80+750 LHS 3/17/2021 3/18/2021

EPC-06/HW/1658 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 79+550 RHS 3/17/2021 3/18/2021

EPC-06/HW/1659 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 78+750 RHS 3/17/2021 3/18/2021

EPC-06/HW/1660 Applying tack coat for DBM Tack coat (DBM) 80+500 80+950 RHS 3/17/2021 3/18/2021

EPC-06/HW/1661 Applying tack coat for DBM Tack coat (DBM) 81+050 81+440 LHS 3/17/2021 3/18/2021

EPC-06/HW/1662 Applying tack coat for DBM Tack coat (DBM) 81+500 82+150 LHS 3/17/2021 3/18/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1663 Level checking and laying of DBM DBM 80+500 80+950 RHS 3/17/2021 3/18/2021

EPC-06/HW/1664 Level checking and laying of DBM DBM 81+050 81+440 LHS 3/17/2021 3/18/2021

EPC-06/HW/1665 Level checking and laying of DBM DBM 81+500 82+150 LHS 3/17/2021 3/18/2021

EPC-06/HW/1666 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+530 86+600 RHS 3/17/2021 3/18/2021

EPC-06/HW/1667 Laying of DBM on Minor Junction DBM 80+750 LHS 3/17/2021 3/18/2021

EPC-06/HW/1668 Laying of DBM on Minor Junction DBM 79+550 RHS 3/17/2021 3/18/2021

EPC-06/HW/1669 Laying of DBM on Minor Junction DBM 78+750 RHS 3/17/2021 3/18/2021

EPC-06/HW/1680 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+600 86+680 RHS 3/18/2021 3/19/2021

EPC-06/HW/1690 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+680 86+770 RHS 3/19/2021 3/20/2021

EPC-06/HW/1691 Level & FDD Checking of Subgrade Top layer SG Top 89+270 90+000 RHS 3/19/2021 3/20/2021

EPC-06/HW/1692 Level & FDD Checking of Subgrade Top layer SG Top 90+000 90+700 RHS 3/19/2021 3/20/2021 Not Done

EPC-06/HW/1700 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+770 86+840 RHS 3/20/2021 3/21/2021

EPC-06/HW/1701 Level & FDD Checking of Subgrade Top layer SG Top 90+000 90+700 RHS 3/20/2021 3/21/2021

EPC-06/HW/1710 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+530 86+610 RHS 3/21/2021 3/22/2021

EPC-06/HW/1720 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+610 86+720 RHS 3/22/2021 3/23/2021

EPC-06/HW/1721 Level & FDD Checking of Subgrade Top layer SG Top 90+700 91+230 RHS 3/22/2021 3/23/2021

EPC-06/HW/1730 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+720 86+840 RHS 3/23/2021 3/24/2021

EPC-06/HW/1731 Level & FDD Checking of Subgrade Top layer SG Top 91+300 92+200 RHS 3/23/2021 3/24/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1740 Level & FDD Checking For GSB layer GSB 89+270 90+000 RHS 3/24/2021 3/25/2021

EPC-06/HW/1748 Level & FDD Checking For GSB layer GSB 90+000 90+700 RHS 3/24/2021 3/25/2021

EPC-06/HW/1757 Level & FDD Checking For GSB layer GSB 90+700 91+230 RHS 3/25/2021 3/26/2021

EPC-06/HW/1765 Level & FDD Checking For GSB layer GSB 91+300 92+100 RHS 3/25/2021 3/26/2021

EPC-06/HW/1810 Dismantling of existing BT surface BT Scr 85+670 86+530 BHS 3/31/2021 4/1/2021

EPC-06/HW/1820 Level & FDD Checking of Subgrade Top layer SG Top 86+445 86+530 RHS 4/2/2021 4/3/2021

EPC-06/HW/1830 Level & FDD Checking of Subgrade Top layer SG Top 92+200 92+900 RHS 4/4/2021 4/5/2021

EPC-06/HW/1835 Level & FDD Checking of Subgrade Top layer SG Top 92+900 93+700 RHS 4/5/2021 4/6/2021

EPC-06/HW/1840 Level & FDD Checking of Subgrade Top layer SG Top 93+770 94+200 RHS 4/6/2021 4/7/2021

EPC-06/HW/1845 Level & FDD Checking of Subgrade Top layer SG Top 85+670 86+445 RHS 4/7/2021 4/8/2021

EPC-06/HW/1850 Level & FDD Checking For GSB layer GSB 85+670 86+445 RHS 4/9/2021 4/10/2021

EPC-06/HW/1851 Level & FDD Checking For GSB layer GSB 86+445 86+530 RHS 4/9/2021 4/10/2021

EPC-06/HW/1856 FDD Checking of WMM 1st layer WMM-I 85+670 86+445 RHS 4/10/2021 4/11/2021

EPC-06/HW/1861 Level & FDD Checking of WMM Top layer WMM-II 85+670 86+445 RHS 4/11/2021 4/12/2021

EPC-06/HW/1862 Applying primer coat Prime coat 85+670 86+445 RHS 4/11/2021 4/12/2021

EPC-06/HW/1863 Level and FDD checking of DLC layer DLC 86+445 86+530 RHS 4/11/2021 4/12/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1868 Level & FDD Checking For GSB layer GSB 92+100 92+700 RHS 4/12/2021 4/13/2021

EPC-06/HW/1869 FDD Checking of WMM 1st layer WMM-I 89+270 90+100 RHS 4/12/2021 4/13/2021

EPC-06/HW/1870 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+840 86+845 RHS 4/12/2021 4/13/2021

EPC-06/HW/1875 Dismantling of existing BT surface BT Scr 68+500 68+700 BHS 4/13/2021 4/14/2021

EPC-06/HW/1876 Level & FDD Checking of Subgrade Top layer SG Top 73+620 73+770 LHS 4/13/2021 4/14/2021

EPC-06/HW/1877 Level & FDD Checking of Subgrade Top layer SG Top 67+130 67+500 RHS 4/13/2021 4/14/2021

EPC-06/HW/1878 Level & FDD Checking For GSB layer GSB 92+700 93+200 RHS 4/13/2021 4/14/2021

EPC-06/HW/1879 FDD Checking of WMM 1st layer WMM-I 90+100 90+600 RHS 4/13/2021 4/14/2021

EPC-06/HW/1880 Level & FDD Checking of WMM Top layer WMM-II 89+270 90+100 RHS 4/13/2021 4/14/2021

EPC-06/HW/1881 Applying primer coat Prime coat 89+270 90+100 RHS 4/13/2021 4/14/2021

EPC-06/HW/1882 Applying tack coat for DBM Tack coat (DBM) 85+670 86+445 RHS 4/13/2021 4/14/2021

EPC-06/HW/1883 Level checking and laying of DBM DBM 85+670 86+445 RHS 4/13/2021 4/14/2021

EPC-06/HW/1884 Dismantling of existing BT surface BT Scr 68+700 68+780 BHS 4/13/2021 4/14/2021

EPC-06/HW/1888 Dismantling of existing BT surface BT Scr 58+300 58+740 BHS 4/14/2021 4/15/2021

EPC-06/HW/1889 Dismantling of existing BT surface BT Scr 58+840 59+010 BHS 4/14/2021 4/15/2021

EPC-06/HW/1890 Level & FDD Checking of Subgrade Top layer SG Top 66+320 67+070 RHS 4/14/2021 4/15/2021

EPC-06/HW/1891 Level & FDD Checking For GSB layer GSB 93+200 93+700 RHS 4/14/2021 4/15/2021

EPC-06/HW/1892 FDD Checking of WMM 1st layer WMM-I 90+600 91+230 RHS 4/14/2021 4/15/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1893 Level & FDD Checking of WMM Top layer WMM-II 90+100 90+600 RHS 4/14/2021 4/15/2021

EPC-06/HW/1894 Applying primer coat Prime coat 90+100 90+600 RHS 4/14/2021 4/15/2021

EPC-06/HW/1899 Dismantling of existing BT surface BT Scr 59+070 59+830 BHS 4/15/2021 4/16/2021

EPC-06/HW/1900 Dismantling of existing BT surface BT Scr 59+890 60+620 BHS 4/15/2021 4/16/2021

EPC-06/HW/1901 Level & FDD Checking of Subgrade Top layer SG Top 65+970 66+250 RHS 4/15/2021 4/16/2021

EPC-06/HW/1902 Level & FDD Checking of Subgrade Top layer SG Top 68+500 68+700 LHS 4/15/2021 4/16/2021

EPC-06/HW/1903 Level & FDD Checking For GSB layer GSB 93+770 94+200 RHS 4/15/2021 4/16/2021

EPC-06/HW/1904 FDD Checking of WMM 1st layer WMM-I 91+300 92+100 RHS 4/15/2021 4/16/2021

EPC-06/HW/1905 Level & FDD Checking of WMM Top layer WMM-II 90+600 91+230 RHS 4/15/2021 4/16/2021

EPC-06/HW/1906 Applying primer coat Prime coat 90+600 91+230 RHS 4/15/2021 4/16/2021

EPC-06/HW/1907 FDD Checking of Subgrade Top layer on Minor Junction SG Top 86+655 RHS 4/15/2021 4/16/2021

EPC-06/HW/1912 Dismantling of existing BT surface BT Scr 60+680 61+000 BHS 4/16/2021 4/17/2021

EPC-06/HW/1913 Level & FDD Checking of Subgrade Top layer SG Top 65+010 65+900 RHS 4/16/2021 4/17/2021

EPC-06/HW/1914 Level & FDD Checking For GSB layer GSB 73+620 73+770 LHS 4/16/2021 4/17/2021

EPC-06/HW/1915 Level & FDD Checking For GSB layer GSB 67+130 67+500 RHS 4/16/2021 4/17/2021

EPC-06/HW/1916 FDD Checking of WMM 1st layer WMM-I 92+100 92+600 RHS 4/16/2021 4/17/2021

EPC-06/HW/1917 Level & FDD Checking of WMM Top layer WMM-II 91+300 92+100 RHS 4/16/2021 4/17/2021

EPC-06/HW/1918 Applying primer coat Prime coat 91+300 92+100 RHS 4/16/2021 4/17/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1923 Level & FDD Checking of Subgrade Top layer SG Top 64+520 64+890 RHS 4/17/2021 4/18/2021

EPC-06/HW/1924 Level & FDD Checking of Subgrade Top layer SG Top 64+310 64+450 RHS 4/17/2021 4/18/2021

EPC-06/HW/1925 Level & FDD Checking of Subgrade Top layer SG Top 64+000 64+250 RHS 4/17/2021 4/18/2021

EPC-06/HW/1926 Level & FDD Checking For GSB layer GSB 66+320 67+070 RHS 4/17/2021 4/18/2021

EPC-06/HW/1927 Level & FDD Checking For GSB layer GSB 68+500 68+700 LHS 4/17/2021 4/18/2021

EPC-06/HW/1928 FDD Checking of WMM 1st layer WMM-I 92+600 93+140 RHS 4/17/2021 4/18/2021

EPC-06/HW/1929 Level & FDD Checking of WMM Top layer WMM-II 92+100 92+600 RHS 4/17/2021 4/18/2021

EPC-06/HW/1930 Applying primer coat Prime coat 92+100 92+600 RHS 4/17/2021 4/18/2021

EPC-06/HW/1931 FDD Checking For GSB layer on Minor Junction GSB 86+655 RHS 4/17/2021 4/18/2021

EPC-06/HW/1936 Level & FDD Checking For GSB layer GSB 65+970 66+250 RHS 4/18/2021 4/19/2021

EPC-06/HW/1937 FDD Checking of WMM 1st layer WMM-I 93+140 93+700 RHS 4/18/2021 4/19/2021

EPC-06/HW/1938 Level & FDD Checking of WMM Top layer WMM-II 92+600 93+140 RHS 4/18/2021 4/19/2021

EPC-06/HW/1939 Applying primer coat Prime coat 92+600 93+140 RHS 4/18/2021 4/19/2021

EPC-06/HW/1945 Level & FDD Checking For GSB layer GSB 65+010 65+900 RHS 4/19/2021 4/20/2021

EPC-06/HW/1946 FDD Checking of WMM 1st layer WMM-I 93+770 94+200 RHS 4/19/2021 4/20/2021

EPC-06/HW/1947 Level & FDD Checking of WMM Top layer WMM-II 93+140 93+700 RHS 4/19/2021 4/20/2021

EPC-06/HW/1948 Applying primer coat Prime coat 93+140 93+700 RHS 4/19/2021 4/20/2021

EPC-06/HW/1949 Applying tack coat for DBM Tack coat (DBM) 89+270 90+500 RHS 4/19/2021 4/20/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1950 Level checking and laying of DBM DBM 89+270 90+500 RHS 4/19/2021 4/20/2021

EPC-06/HW/1951 FDD Checking of WMM Top layer on Minor Junction WMM-II 86+655 RHS 4/19/2021 4/20/2021

EPC-06/HW/1952 Applying primer coat on Minor Junction Prime coat 86+655 RHS 4/19/2021 4/20/2021

EPC-06/HW/1957 Level & FDD Checking For GSB layer GSB 64+520 64+890 RHS 4/20/2021 4/21/2021

EPC-06/HW/1958 FDD Checking of WMM 1st layer WMM-I 73+620 73+770 LHS 4/20/2021 4/21/2021

EPC-06/HW/1959 FDD Checking of WMM 1st layer WMM-I 67+130 67+500 RHS 4/20/2021 4/21/2021

EPC-06/HW/1960 Level & FDD Checking of WMM Top layer WMM-II 93+770 94+200 RHS 4/20/2021 4/21/2021

EPC-06/HW/1961 Applying primer coat Prime coat 93+770 94+200 RHS 4/20/2021 4/21/2021

EPC-06/HW/1962 Applying tack coat for DBM Tack coat (DBM) 90+500 91+230 RHS 4/20/2021 4/21/2021

EPC-06/HW/1963 Level checking and laying of DBM DBM 90+500 91+230 RHS 4/20/2021 4/21/2021

EPC-06/HW/1964 FDD Checking of Subgrade Top layer on Minor Junction SG Top 67+465 LHS 4/20/2021 4/21/2021

EPC-06/HW/1965 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 86+655 RHS 4/20/2021 4/21/2021

EPC-06/HW/1966 Laying of DBM on Minor Junction DBM 86+655 RHS 4/20/2021 4/21/2021

EPC-06/HW/1971 Level & FDD Checking For GSB layer GSB 64+310 64+450 RHS 4/21/2021 4/22/2021

EPC-06/HW/1972 Level & FDD Checking For GSB layer GSB 64+000 64+250 RHS 4/21/2021 4/22/2021

EPC-06/HW/1973 FDD Checking of WMM 1st layer WMM-I 66+320 67+070 RHS 4/21/2021 4/22/2021

EPC-06/HW/1974 FDD Checking of WMM 1st layer WMM-I 65+970 66+250 RHS 4/21/2021 4/22/2021

EPC-06/HW/1975 Level & FDD Checking of WMM Top layer WMM-II 73+620 73+770 LHS 4/21/2021 4/22/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1976 Level & FDD Checking of WMM Top layer WMM-II 67+130 67+500 RHS 4/21/2021 4/22/2021

EPC-06/HW/1977 Applying primer coat Prime coat 73+620 73+770 LHS 4/21/2021 4/22/2021

EPC-06/HW/1978 Applying primer coat Prime coat 67+130 67+500 RHS 4/21/2021 4/22/2021

EPC-06/HW/1979 Level and FDD checking of DLC layer DLC 68+500 68+700 LHS 4/21/2021 4/22/2021

EPC-06/HW/1985 Level & FDD Checking of Subgrade Top layer SG Top 58+300 58+740 LHS 4/22/2021 4/23/2021

EPC-06/HW/1986 Level & FDD Checking of Subgrade Top layer SG Top 58+840 59+010 LHS 4/22/2021 4/23/2021

EPC-06/HW/1987 FDD Checking of WMM 1st layer WMM-I 65+010 65+900 RHS 4/22/2021 4/23/2021

EPC-06/HW/1988 Level & FDD Checking of WMM Top layer WMM-II 66+320 67+070 RHS 4/22/2021 4/23/2021

EPC-06/HW/1989 Level & FDD Checking of WMM Top layer WMM-II 65+970 66+250 RHS 4/22/2021 4/23/2021

EPC-06/HW/1990 Applying primer coat Prime coat 66+320 67+070 RHS 4/22/2021 4/23/2021

EPC-06/HW/1991 Applying primer coat Prime coat 65+970 66+250 RHS 4/22/2021 4/23/2021

EPC-06/HW/1992 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+445 86+530 RHS 4/22/2021 4/23/2021

EPC-06/HW/1997 Level & FDD Checking of Subgrade Top layer SG Top 59+070 59+830 LHS 4/23/2021 4/24/2021

EPC-06/HW/1998 FDD Checking of WMM 1st layer WMM-I 64+520 64+890 RHS 4/23/2021 4/24/2021

EPC-06/HW/1999 Level & FDD Checking of WMM Top layer WMM-II 65+010 65+900 RHS 4/23/2021 4/24/2021

EPC-06/HW/2000 Applying primer coat Prime coat 65+010 65+900 RHS 4/23/2021 4/24/2021

EPC-06/HW/2001 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+840 86+845 RHS 4/23/2021 4/24/2021

EPC-06/HW/2002 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+445 86+530 RHS 4/23/2021 4/24/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2007 Level & FDD Checking of Subgrade Top layer SG Top 59+890 60+620 LHS 4/24/2021 4/25/2021

EPC-06/HW/2008 FDD Checking of WMM 1st layer WMM-I 64+310 64+450 RHS 4/24/2021 4/25/2021

EPC-06/HW/2009 FDD Checking of WMM 1st layer WMM-I 64+000 64+250 RHS 4/24/2021 4/25/2021

EPC-06/HW/2010 Level & FDD Checking of WMM Top layer WMM-II 64+520 64+890 RHS 4/24/2021 4/25/2021

EPC-06/HW/2011 Applying primer coat Prime coat 64+520 64+890 RHS 4/24/2021 4/25/2021

EPC-06/HW/2012 FDD Checking For GSB layer on Minor Junction GSB 67+465 LHS 4/24/2021 4/25/2021

EPC-06/HW/2017 Level & FDD Checking of Subgrade Top layer SG Top 60+680 61+000 LHS 4/25/2021 4/26/2021

EPC-06/HW/2018 Level & FDD Checking of WMM Top layer WMM-II 64+310 64+450 RHS 4/25/2021 4/26/2021

EPC-06/HW/2019 Level & FDD Checking of WMM Top layer WMM-II 64+000 64+250 RHS 4/25/2021 4/26/2021

EPC-06/HW/2020 Applying primer coat Prime coat 64+310 64+450 RHS 4/25/2021 4/26/2021

EPC-06/HW/2021 Applying primer coat Prime coat 64+000 64+250 RHS 4/25/2021 4/26/2021

EPC-06/HW/2026 Applying tack coat for DBM Tack coat (DBM) 73+620 73+770 LHS 4/26/2021 4/27/2021

EPC-06/HW/2027 Applying tack coat for DBM Tack coat (DBM) 67+130 67+500 RHS 4/26/2021 4/27/2021

EPC-06/HW/2028 Applying tack coat for DBM Tack coat (DBM) 66+320 67+070 RHS 4/26/2021 4/27/2021

EPC-06/HW/2029 Applying tack coat for DBM Tack coat (DBM) 65+970 66+250 RHS 4/26/2021 4/27/2021

EPC-06/HW/2030 Level checking and laying of DBM DBM 73+620 73+770 LHS 4/26/2021 4/27/2021

EPC-06/HW/2030 Level checking and laying of DBM DBM 67+130 67+500 RHS 4/26/2021 4/27/2021

EPC-06/HW/2030 Level checking and laying of DBM DBM 66+320 67+070 RHS 4/26/2021 4/27/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2030 Level checking and laying of DBM DBM 65+970 66+250 RHS 4/26/2021 4/27/2021

EPC-06/HW/2031 FDD Checking of WMM Top layer on Minor Junction WMM-II 67+465 LHS 4/26/2021 4/27/2021

EPC-06/HW/2032 Applying primer coat on Minor Junction Prime coat 67+465 LHS 4/26/2021 4/27/2021

EPC-06/HW/2040 Applying tack coat for DBM Tack coat (DBM) 65+010 65+900 RHS 4/27/2021 4/28/2021

EPC-06/HW/2041 Applying tack coat for DBM Tack coat (DBM) 64+520 64+890 RHS 4/27/2021 4/28/2021

EPC-06/HW/2042 Applying tack coat for DBM Tack coat (DBM) 64+310 64+450 RHS 4/27/2021 4/28/2021

EPC-06/HW/2043 Applying tack coat for DBM Tack coat (DBM) 64+000 64+250 RHS 4/27/2021 4/28/2021

EPC-06/HW/2044 Level checking and laying of DBM DBM 65+010 65+900 RHS 4/27/2021 4/28/2021

EPC-06/HW/2044 Level checking and laying of DBM DBM 64+520 64+890 RHS 4/27/2021 4/28/2021

EPC-06/HW/2044 Level checking and laying of DBM DBM 64+310 64+450 RHS 4/27/2021 4/28/2021

EPC-06/HW/2044 Level checking and laying of DBM DBM 64+000 64+250 RHS 4/27/2021 4/28/2021

EPC-06/HW/2045 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 67+465 LHS 4/27/2021 4/28/2021

EPC-06/HW/2046 Laying of DBM on Minor Junction DBM 67+465 LHS 4/27/2021 4/28/2021

EPC-06/HW/1278 Dismantling of existing BT surface BT Scr 88+900 88+960 BHS 1/23/2021 1/24/2021

EPC-06/HW/1821 Level & FDD Checking of Subgrade Top layer SG Top 88+900 88+960 LHS 4/2/2021 4/3/2021

EPC-06/HW/1826 Level & FDD Checking For GSB layer GSB 88+900 88+960 LHS 4/3/2021 4/4/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/1831 Level & FDD Checking of Subgrade Top layer SG Top 89+270 89+285 RHS 4/4/2021 4/5/2021

EPC-06/HW/1832 Level and FDD checking of DLC layer DLC 88+900 88+960 LHS 4/4/2021 4/5/2021

EPC-06/HW/1836 Level & FDD Checking For GSB layer GSB 89+270 89+285 RHS 4/5/2021 4/6/2021

EPC-06/HW/1841 Level and FDD checking of DLC layer DLC 89+270 89+285 RHS 4/6/2021 4/7/2021

EPC-06/HW/1864 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 88+900 88+960 LHS 4/11/2021 4/12/2021

EPC-06/HW/1871 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 88+900 88+960 LHS 4/12/2021 4/13/2021

EPC-06/HW/1884 Level & FDD Checking of Subgrade Top layer SG Top 86+840 86+845 RHS 4/13/2021 4/14/2021

EPC-06/HW/1885 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+270 89+285 RHS 4/13/2021 4/14/2021

EPC-06/HW/1895 Level & FDD Checking For GSB layer GSB 86+840 86+845 RHS 4/14/2021 4/15/2021

EPC-06/HW/1896 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 89+270 89+285 RHS 4/14/2021 4/15/2021

EPC-06/HW/1897 Dismantling of existing BT surface BT Scr 58+740 58+840 BHS 4/14/2021 4/15/2021

EPC-06/HW/1908 Level and FDD checking of DLC layer DLC 86+840 86+845 RHS 4/15/2021 4/16/2021

EPC-06/HW/1909 Dismantling of existing BT surface BT Scr 59+010 59+070 BHS 4/15/2021 4/16/2021

EPC-06/HW/1910 Dismantling of existing BT surface BT Scr 59+830 59+890 BHS 4/15/2021 4/16/2021

EPC-06/HW/1919 Dismantling of existing BT surface BT Scr 60+620 60+680 BHS 4/16/2021 4/17/2021

EPC-06/HW/2075 FDD Checking of WMM 1st layer WMM-I 67+130 67+500 LHS 4/30/2021 5/1/2021

EPC-06/HW/2076 FDD Checking of WMM 1st layer WMM-I 66+320 67+070 LHS 4/30/2021 5/1/2021

EPC-06/HW/2077 FDD Checking of Subgrade Top layer on Minor Junction SG Top 67+465 LHS 4/30/2021 5/1/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2078 Dismantling of existing BT surface BT Scr 68+300 68+500 BHS 4/30/2021 5/1/2021

EPC-06/HW/2079 Dismantling of existing BT surface BT Scr 68+000 68+300 BHS 4/30/2021 5/1/2021

EPC-06/HW/2083 FDD Checking of WMM 1st layer WMM-I 65+970 66+250 LHS 5/1/2021 5/2/2021

EPC-06/HW/2084 FDD Checking of WMM 1st layer WMM-I 65+010 65+900 LHS 5/1/2021 5/2/2021

EPC-06/HW/2085 Level & FDD Checking of WMM Top layer WMM-II 67+130 67+500 LHS 5/1/2021 5/2/2021

EPC-06/HW/2086 Level & FDD Checking of WMM Top layer WMM-II 66+320 67+070 LHS 5/1/2021 5/2/2021

EPC-06/HW/2087 Applying primer coat Prime coat 67+130 67+500 LHS 5/1/2021 5/2/2021

EPC-06/HW/2088 Applying primer coat Prime coat 66+320 67+070 LHS 5/1/2021 5/2/2021

EPC-06/HW/2089 FDD Checking For GSB layer on Minor Junction GSB 67+465 LHS 5/1/2021 5/2/2021

EPC-06/HW/2095 FDD Checking of WMM 1st layer WMM-I 64+520 64+890 LHS 5/2/2021 5/3/2021

EPC-06/HW/2096 FDD Checking of WMM 1st layer WMM-I 64+310 64+450 LHS 5/2/2021 5/3/2021

EPC-06/HW/2097 Level & FDD Checking of WMM Top layer WMM-II 65+970 66+250 LHS 5/2/2021 5/3/2021

EPC-06/HW/2098 Level & FDD Checking of WMM Top layer WMM-II 65+010 65+900 LHS 5/2/2021 5/3/2021

EPC-06/HW/2099 Applying primer coat Prime coat 65+970 66+250 LHS 5/2/2021 5/3/2021

EPC-06/HW/2100 Applying primer coat Prime coat 65+010 65+900 LHS 5/2/2021 5/3/2021

EPC-06/HW/2101 Level & FDD Checking of Subgrade Top layer SG Top 68+440 68+500 LHS 5/2/2021 5/3/2021

EPC-06/HW/2102 FDD Checking of WMM Top layer on Minor Junction WMM-II 67+465 LHS 5/2/2021 5/3/2021

EPC-06/HW/2103 Applying primer coat on Minor Junction Prime coat 67+465 LHS 5/2/2021 5/3/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2104 Level & FDD Checking of Subgrade Top layer SG Top 68+000 68+300 LHS 5/2/2021 5/3/2021

EPC-06/HW/2105 Dismantling of existing BT surface BT Scr 50+050 50+900 BHS 5/2/2021 5/3/2021

EPC-06/HW/2109 Level & FDD Checking For GSB layer GSB 60+680 61+000 LHS 5/3/2021 5/4/2021

EPC-06/HW/2110 FDD Checking of WMM 1st layer WMM-I 64+000 64+250 LHS 5/3/2021 5/4/2021

EPC-06/HW/2111 Level & FDD Checking of WMM Top layer WMM-II 64+520 64+890 LHS 5/3/2021 5/4/2021

EPC-06/HW/2112 Level & FDD Checking of WMM Top layer WMM-II 64+310 64+450 LHS 5/3/2021 5/4/2021

EPC-06/HW/2113 Applying primer coat Prime coat 64+520 64+890 LHS 5/3/2021 5/4/2021

EPC-06/HW/2114 Applying primer coat Prime coat 64+310 64+450 LHS 5/3/2021 5/4/2021

EPC-06/HW/2115 Applying tack coat for DBM Tack coat (DBM) 67+130 67+500 LHS 5/3/2021 5/4/2021

EPC-06/HW/2115 Applying tack coat for DBM Tack coat (DBM) 66+320 67+070 LHS 5/3/2021 5/4/2021

EPC-06/HW/2115 Applying tack coat for DBM Tack coat (DBM) 65+970 66+250 LHS 5/3/2021 5/4/2021

EPC-06/HW/2118 Level checking and laying of DBM DBM 67+130 67+500 LHS 5/3/2021 5/4/2021

EPC-06/HW/2118 Level checking and laying of DBM DBM 66+320 67+070 LHS 5/3/2021 5/4/2021

EPC-06/HW/2118 Level checking and laying of DBM DBM 65+970 66+250 LHS 5/3/2021 5/4/2021

EPC-06/HW/2121 Level & FDD Checking For GSB layer GSB 68+440 68+500 LHS 5/3/2021 5/4/2021

EPC-06/HW/2122 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 67+465 LHS 5/3/2021 5/4/2021

EPC-06/HW/2123 Laying of DBM on Minor Junction DBM 67+465 LHS 5/3/2021 5/4/2021

EPC-06/HW/2124 Level & FDD Checking For GSB layer GSB 68+000 68+300 LHS 5/3/2021 5/4/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2125 Dismantling of existing BT surface BT Scr 50+900 51+650 BHS 5/3/2021 5/4/2021

EPC-06/HW/2128 Level & FDD Checking For GSB layer GSB 59+890 60+620 LHS 5/4/2021 5/5/2021

EPC-06/HW/2129 FDD Checking of WMM 1st layer WMM-I 60+680 61+000 LHS 5/4/2021 5/5/2021

EPC-06/HW/2130 Level & FDD Checking of WMM Top layer WMM-II 64+000 64+250 LHS 5/4/2021 5/5/2021

EPC-06/HW/2131 Applying primer coat Prime coat 64+000 64+250 LHS 5/4/2021 5/5/2021

EPC-06/HW/2132 Level and FDD checking of DLC layer DLC 68+440 68+500 LHS 5/4/2021 5/5/2021

EPC-06/HW/2133 Dismantling of existing BT surface BT Scr 51+650 53+000 BHS 5/4/2021 5/5/2021

EPC-06/HW/2138 Level & FDD Checking For GSB layer GSB 59+070 59+830 LHS 5/5/2021 5/6/2021

EPC-06/HW/2139 FDD Checking of WMM 1st layer WMM-I 59+890 60+620 LHS 5/5/2021 5/6/2021

EPC-06/HW/2140 Level & FDD Checking of WMM Top layer WMM-II 60+680 61+000 LHS 5/5/2021 5/6/2021

EPC-06/HW/2141 Applying primer coat Prime coat 60+680 61+000 LHS 5/5/2021 5/6/2021

EPC-06/HW/2142 Level and FDD checking of DLC layer DLC 68+000 68+300 LHS 5/5/2021 5/6/2021

EPC-06/HW/2146 Level & FDD Checking For GSB layer GSB 58+840 59+010 LHS 5/6/2021 5/7/2021

EPC-06/HW/2147 Level & FDD Checking For GSB layer GSB 58+300 58+740 LHS 5/6/2021 5/7/2021

EPC-06/HW/2148 FDD Checking of WMM 1st layer WMM-I 59+070 59+830 LHS 5/6/2021 5/7/2021

EPC-06/HW/2149 Level & FDD Checking of WMM Top layer WMM-II 59+890 60+620 LHS 5/6/2021 5/7/2021

EPC-06/HW/2150 Applying primer coat Prime coat 59+890 60+620 LHS 5/6/2021 5/7/2021

EPC-06/HW/2151 Applying tack coat for DBM Tack coat (DBM) 65+010 65+900 LHS 5/6/2021 5/7/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2151 Applying tack coat for DBM Tack coat (DBM) 64+520 64+890 LHS 5/6/2021 5/7/2021

EPC-06/HW/2151 Applying tack coat for DBM Tack coat (DBM) 64+310 64+450 LHS 5/6/2021 5/7/2021

EPC-06/HW/2151 Applying tack coat for DBM Tack coat (DBM) 64+000 64+250 LHS 5/6/2021 5/7/2021

EPC-06/HW/2155 Level checking and laying of DBM DBM 65+010 65+900 LHS 5/6/2021 5/7/2021

EPC-06/HW/2155 Level checking and laying of DBM DBM 64+520 64+890 LHS 5/6/2021 5/7/2021

EPC-06/HW/2155 Level checking and laying of DBM DBM 64+310 64+450 LHS 5/6/2021 5/7/2021

EPC-06/HW/2155 Level checking and laying of DBM DBM 64+000 64+250 LHS 5/6/2021 5/7/2021

EPC-06/HW/2156 Level & FDD Checking of Subgrade Top layer SG Top 50+050 50+950 LHS 5/6/2021 5/7/2021

EPC-06/HW/2163 FDD Checking of WMM 1st layer WMM-I 58+840 59+010 LHS 5/7/2021 5/8/2021

EPC-06/HW/2164 FDD Checking of WMM 1st layer WMM-I 58+300 58+740 LHS 5/7/2021 5/8/2021

EPC-06/HW/2165 Level & FDD Checking of WMM Top layer WMM-II 59+070 59+830 LHS 5/7/2021 5/8/2021

EPC-06/HW/2166 Applying primer coat Prime coat 59+070 59+830 LHS 5/7/2021 5/8/2021

EPC-06/HW/2167 FDD Checking of Subgrade Top layer on Minor Junction SG Top 60+150 LHS 5/7/2021 5/8/2021

EPC-06/HW/2168 Level & FDD Checking of Subgrade Top layer SG Top 50+950 52+000 LHS 5/7/2021 5/8/2021

EPC-06/HW/2173 Level & FDD Checking of WMM Top layer WMM-II 58+840 59+010 LHS 5/8/2021 5/9/2021

EPC-06/HW/2174 Level & FDD Checking of WMM Top layer WMM-II 58+300 58+740 LHS 5/8/2021 5/9/2021

EPC-06/HW/2175 Applying primer coat Prime coat 58+840 59+010 LHS 5/8/2021 5/9/2021

EPC-06/HW/2176 Applying primer coat Prime coat 58+300 58+740 LHS 5/8/2021 5/9/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2177 Level & FDD Checking of Subgrade Top layer SG Top 89+270 89+285 LHS 5/8/2021 5/9/2021

EPC-06/HW/2178 FDD Checking For GSB layer on Minor Junction GSB 60+150 LHS 5/8/2021 5/9/2021

EPC-06/HW/2179 Level & FDD Checking of Subgrade Top layer SG Top 52+100 53+000 LHS 5/8/2021 5/9/2021

EPC-06/HW/2180 Level & FDD Checking For GSB layer GSB 50+050 50+950 LHS 5/8/2021 5/9/2021

EPC-06/HW/2183 Level & FDD Checking For GSB layer GSB 89+270 89+285 LHS 5/9/2021 5/10/2021

EPC-06/HW/2184 FDD Checking of WMM Top layer on Minor Junction WMM-II 60+150 LHS 5/9/2021 5/10/2021

EPC-06/HW/2185 Applying primer coat on Minor Junction Prime coat 60+150 LHS 5/9/2021 5/10/2021

EPC-06/HW/2186 Level & FDD Checking For GSB layer GSB 50+950 52+000 LHS 5/9/2021 5/10/2021

EPC-06/HW/2187 FDD Checking of WMM 1st layer WMM-I 50+050 50+950 LHS 5/9/2021 5/10/2021

EPC-06/HW/2190 Level & FDD Checking of Subgrade Top layer SG Top 85+670 86+445 LHS 5/10/2021 5/11/2021

EPC-06/HW/2191 Applying tack coat for DBM Tack coat (DBM) 60+680 61+000 LHS 5/10/2021 5/11/2021

EPC-06/HW/2191 Applying tack coat for DBM Tack coat (DBM) 59+890 60+620 LHS 5/10/2021 5/11/2021

EPC-06/HW/2193 Applying tack coat for DBM Tack coat (DBM) 59+070 59+830 LHS 5/10/2021 5/11/2021

EPC-06/HW/2193 Applying tack coat for DBM Tack coat (DBM) 58+840 59+010 LHS 5/10/2021 5/11/2021

EPC-06/HW/2193 Applying tack coat for DBM Tack coat (DBM) 58+300 58+740 LHS 5/10/2021 5/11/2021

EPC-06/HW/2196 Level checking and laying of DBM DBM 60+680 61+000 LHS 5/10/2021 5/11/2021

EPC-06/HW/2196 Level checking and laying of DBM DBM 59+890 60+620 LHS 5/10/2021 5/11/2021

EPC-06/HW/2198 Level checking and laying of DBM DBM 59+070 59+830 LHS 5/10/2021 5/11/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2198 Level checking and laying of DBM DBM 58+840 59+010 LHS 5/10/2021 5/11/2021

EPC-06/HW/2198 Level checking and laying of DBM DBM 58+300 58+740 LHS 5/10/2021 5/11/2021

EPC-06/HW/2201 Level and FDD checking of DLC layer DLC 89+270 89+285 LHS 5/10/2021 5/11/2021

EPC-06/HW/2202 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 60+150 LHS 5/10/2021 5/11/2021

EPC-06/HW/2203 Laying of DBM on Minor Junction DBM 60+150 LHS 5/10/2021 5/11/2021

EPC-06/HW/2204 Level & FDD Checking For GSB layer GSB 52+100 53+000 LHS 5/10/2021 5/11/2021

EPC-06/HW/2205 FDD Checking of WMM 1st layer WMM-I 50+950 52+000 LHS 5/10/2021 5/11/2021

EPC-06/HW/2206 Level & FDD Checking of WMM Top layer WMM-II 50+050 50+950 LHS 5/10/2021 5/11/2021

EPC-06/HW/2207 Applying primer coat Prime coat 50+050 50+950 LHS 5/10/2021 5/11/2021

EPC-06/HW/2208 Level & FDD Checking of Subgrade Top layer SG Top 60+680 61+000 RHS 5/11/2021 5/12/2021

EPC-06/HW/2209 FDD Checking of WMM 1st layer WMM-I 52+100 53+000 LHS 5/11/2021 5/12/2021

EPC-06/HW/2210 Level & FDD Checking of WMM Top layer WMM-II 50+950 52+000 LHS 5/11/2021 5/12/2021

EPC-06/HW/2211 Applying primer coat Prime coat 50+950 52+000 LHS 5/11/2021 5/12/2021

EPC-06/HW/2213 Level & FDD Checking of Subgrade Top layer SG Top 59+890 60+620 RHS 5/12/2021 5/13/2021

EPC-06/HW/2214 Level & FDD Checking For GSB layer GSB 85+670 86+445 LHS 5/12/2021 5/13/2021

EPC-06/HW/2215 Level & FDD Checking For GSB layer GSB 60+680 61+000 RHS 5/12/2021 5/13/2021

EPC-06/HW/2216 Level & FDD Checking of WMM Top layer WMM-II 52+100 53+000 LHS 5/12/2021 5/13/2021

EPC-06/HW/2217 Applying primer coat Prime coat 52+100 53+000 LHS 5/12/2021 5/13/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2220 Level & FDD Checking of Subgrade Top layer SG Top 59+070 59+830 RHS 5/13/2021 5/14/2021

EPC-06/HW/2221 Level & FDD Checking For GSB layer GSB 59+890 60+620 RHS 5/13/2021 5/14/2021

EPC-06/HW/2222 FDD Checking of WMM 1st layer WMM-I 85+670 86+445 LHS 5/13/2021 5/14/2021

EPC-06/HW/2223 FDD Checking of WMM 1st layer WMM-I 60+680 61+000 RHS 5/13/2021 5/14/2021

EPC-06/HW/2224 FDD Checking of Subgrade Top layer on Minor Junction SG Top 86+655 RHS 5/13/2021 5/14/2021

EPC-06/HW/2225 Dismantling of existing BT surface BT Scr 49+500 49+900 BHS 5/13/2021 5/14/2021

EPC-06/HW/2226 Applying tack coat for DBM Tack coat (DBM) 50+050 50+500 LHS 5/13/2021 5/14/2021

EPC-06/HW/2226 Applying tack coat for DBM Tack coat (DBM) 50+500 50+950 LHS 5/13/2021 5/14/2021

EPC-06/HW/2226 Applying tack coat for DBM Tack coat (DBM) 50+950 51+400 LHS 5/13/2021 5/14/2021

EPC-06/HW/2227 Level checking and laying of DBM DBM 50+050 50+500 LHS 5/13/2021 5/14/2021

EPC-06/HW/2227 Level checking and laying of DBM DBM 50+500 50+950 LHS 5/13/2021 5/14/2021

EPC-06/HW/2227 Level checking and laying of DBM DBM 50+950 51+400 LHS 5/13/2021 5/14/2021

EPC-06/HW/2230 Level & FDD Checking of Subgrade Top layer SG Top 58+840 59+010 RHS 5/14/2021 5/15/2021

EPC-06/HW/2231 Level & FDD Checking of Subgrade Top layer SG Top 58+300 58+740 RHS 5/14/2021 5/15/2021

EPC-06/HW/2232 Level & FDD Checking For GSB layer GSB 59+070 59+830 RHS 5/14/2021 5/15/2021

EPC-06/HW/2233 Level & FDD Checking of WMM Top layer WMM-II 85+670 86+445 LHS 5/14/2021 5/15/2021

EPC-06/HW/2234 Level & FDD Checking of WMM Top layer WMM-II 60+680 61+000 RHS 5/14/2021 5/15/2021

EPC-06/HW/2235 Applying primer coat Prime coat 85+670 86+445 LHS 5/14/2021 5/15/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2236 Applying primer coat Prime coat 60+680 61+000 RHS 5/14/2021 5/15/2021

EPC-06/HW/2237 Level & FDD Checking of Subgrade Top layer SG Top 49+500 49+900 LHS 5/14/2021 5/15/2021

EPC-06/HW/2238 FDD Checking For GSB layer on Minor Junction GSB 86+655 RHS 5/14/2021 5/15/2021

EPC-06/HW/2239 Applying tack coat for DBM Tack coat (DBM) 51+400 52+000 LHS 5/14/2021 5/15/2021

EPC-06/HW/2239 Applying tack coat for DBM Tack coat (DBM) 52+100 52+550 LHS 5/14/2021 5/15/2021

EPC-06/HW/2239 Applying tack coat for DBM Tack coat (DBM) 52+550 53+000 LHS 5/14/2021 5/15/2021

EPC-06/HW/2240 Level checking and laying of DBM DBM 51+400 52+000 LHS 5/14/2021 5/15/2021

EPC-06/HW/2240 Level checking and laying of DBM DBM 52+100 52+550 LHS 5/14/2021 5/15/2021

EPC-06/HW/2240 Level checking and laying of DBM DBM 52+550 53+000 LHS 5/14/2021 5/15/2021

EPC-06/HW/2241 Dismantling of existing BT surface BT Scr 44+400 45+600 BHS 5/14/2021 5/15/2021

EPC-06/HW/2243 Level & FDD Checking For GSB layer GSB 58+840 59+010 RHS 5/15/2021 5/16/2021

EPC-06/HW/2244 Level & FDD Checking For GSB layer GSB 58+300 58+740 RHS 5/15/2021 5/16/2021

EPC-06/HW/2245 Applying tack coat for DBM Tack coat (DBM) 91+300 92+100 RHS 5/15/2021 5/16/2021

EPC-06/HW/2245 Applying tack coat for DBM Tack coat (DBM) 92+100 92+600 RHS 5/15/2021 5/16/2021

EPC-06/HW/2247 Level checking and laying of DBM DBM 91+300 92+100 RHS 5/15/2021 5/16/2021

EPC-06/HW/2247 Level checking and laying of DBM DBM 92+100 92+600 RHS 5/15/2021 5/16/2021

EPC-06/HW/2249 Level & FDD Checking For GSB layer GSB 49+500 49+900 LHS 5/15/2021 5/16/2021

EPC-06/HW/2250 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+630 68+700 LHS 5/15/2021 5/16/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2251 FDD Checking of WMM Top layer on Minor Junction WMM-II 86+655 RHS 5/15/2021 5/16/2021

EPC-06/HW/2252 Applying primer coat on Minor Junction Prime coat 86+655 RHS 5/15/2021 5/16/2021

EPC-06/HW/2253 Dismantling of existing BT surface BT Scr 45+600 47+000 BHS 5/15/2021 5/16/2021

EPC-06/HW/2258 FDD Checking of WMM 1st layer WMM-I 59+890 60+620 RHS 5/16/2021 5/17/2021

EPC-06/HW/2259 Applying tack coat for DBM Tack coat (DBM) 92+600 93+140 RHS 5/16/2021 5/17/2021

EPC-06/HW/2259 Applying tack coat for DBM Tack coat (DBM) 93+140 93+700 RHS 5/16/2021 5/17/2021

EPC-06/HW/2259 Applying tack coat for DBM Tack coat (DBM) 93+770 94+200 RHS 5/16/2021 5/17/2021

EPC-06/HW/2262 Applying tack coat for DBM Tack coat (DBM) 85+670 86+445 LHS 5/16/2021 5/17/2021

EPC-06/HW/2263 Level checking and laying of DBM DBM 92+600 93+140 RHS 5/16/2021 5/17/2021

EPC-06/HW/2263 Level checking and laying of DBM DBM 93+140 93+700 RHS 5/16/2021 5/17/2021

EPC-06/HW/2263 Level checking and laying of DBM DBM 93+770 94+200 RHS 5/16/2021 5/17/2021

EPC-06/HW/2266 Level checking and laying of DBM DBM 85+670 86+445 LHS 5/16/2021 5/17/2021

EPC-06/HW/2267 Level and FDD checking of DLC layer DLC 49+500 49+900 LHS 5/16/2021 5/17/2021

EPC-06/HW/2268 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+510 68+630 LHS 5/16/2021 5/17/2021

EPC-06/HW/2269 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 86+655 RHS 5/16/2021 5/17/2021

EPC-06/HW/2270 Laying of DBM on Minor Junction DBM 86+655 RHS 5/16/2021 5/17/2021

EPC-06/HW/2271 Dismantling of existing BT surface BT Scr 47+000 48+970 BHS 5/16/2021 5/17/2021

EPC-06/HW/2277 FDD Checking of WMM 1st layer WMM-I 59+070 59+830 RHS 5/17/2021 5/18/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2278 Level & FDD Checking of WMM Top layer WMM-II 59+890 60+620 RHS 5/17/2021 5/18/2021

EPC-06/HW/2279 Applying primer coat Prime coat 59+890 60+620 RHS 5/17/2021 5/18/2021

EPC-06/HW/2280 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 89+270 89+285 LHS 5/17/2021 5/18/2021

EPC-06/HW/2281 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+440 68+510 LHS 5/17/2021 5/18/2021

EPC-06/HW/2282 Level & FDD Checking of Subgrade Top layer SG Top 85+670 86+445 RHS 5/17/2021 5/18/2021

EPC-06/HW/2288 FDD Checking of WMM 1st layer WMM-I 58+840 59+010 RHS 5/18/2021 5/19/2021

EPC-06/HW/2289 FDD Checking of WMM 1st layer WMM-I 58+300 58+740 RHS 5/18/2021 5/19/2021

EPC-06/HW/2290 Level & FDD Checking of WMM Top layer WMM-II 59+070 59+830 RHS 5/18/2021 5/19/2021

EPC-06/HW/2291 Applying primer coat Prime coat 59+070 59+830 RHS 5/18/2021 5/19/2021

EPC-06/HW/2293 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 89+270 89+285 LHS 5/18/2021 5/19/2021

EPC-06/HW/2294 Level & FDD Checking of Subgrade Top layer SG Top 44+400 44+900 LHS 5/18/2021 5/19/2021

EPC-06/HW/2300 Level & FDD Checking of WMM Top layer WMM-II 58+840 59+010 RHS 5/19/2021 5/20/2021

EPC-06/HW/2301 Level & FDD Checking of WMM Top layer WMM-II 58+300 58+740 RHS 5/19/2021 5/20/2021

EPC-06/HW/2302 Applying primer coat Prime coat 58+840 59+010 RHS 5/19/2021 5/20/2021

EPC-06/HW/2303 Applying primer coat Prime coat 58+300 58+740 RHS 5/19/2021 5/20/2021

EPC-06/HW/2304 Level & FDD Checking of Subgrade Top layer SG Top 86+800 86+845 LHS 5/19/2021 5/20/2021

EPC-06/HW/2305 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+620 68+700 LHS 5/19/2021 5/20/2021

EPC-06/HW/2306 Level & FDD Checking of Subgrade Top layer SG Top 44+900 45+600 LHS 5/19/2021 5/20/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2307 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+210 68+300 LHS 5/19/2021 5/20/2021

EPC-06/HW/2312 Applying tack coat for DBM Tack coat (DBM) 60+680 61+000 RHS 5/20/2021 5/21/2021

EPC-06/HW/2312 Applying tack coat for DBM Tack coat (DBM) 59+890 60+620 RHS 5/20/2021 5/21/2021

EPC-06/HW/2314 Applying tack coat for DBM Tack coat (DBM) 59+070 59+830 RHS 5/20/2021 5/21/2021

EPC-06/HW/2314 Applying tack coat for DBM Tack coat (DBM) 58+840 59+010 RHS 5/20/2021 5/21/2021

EPC-06/HW/2314 Applying tack coat for DBM Tack coat (DBM) 58+300 58+740 RHS 5/20/2021 5/21/2021

EPC-06/HW/2317 Level checking and laying of DBM DBM 60+680 61+000 RHS 5/20/2021 5/21/2021

EPC-06/HW/2317 Level checking and laying of DBM DBM 59+890 60+620 RHS 5/20/2021 5/21/2021

EPC-06/HW/2319 Level checking and laying of DBM DBM 59+070 59+830 RHS 5/20/2021 5/21/2021

EPC-06/HW/2319 Level checking and laying of DBM DBM 58+840 59+010 RHS 5/20/2021 5/21/2021

EPC-06/HW/2319 Level checking and laying of DBM DBM 58+300 58+740 RHS 5/20/2021 5/21/2021

EPC-06/HW/2322 Level & FDD Checking of Subgrade Top layer SG Top 86+445 86+530 LHS 5/20/2021 5/21/2021

EPC-06/HW/2323 Level & FDD Checking For GSB layer GSB 86+800 86+845 LHS 5/20/2021 5/21/2021

EPC-06/HW/2324 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+500 68+620 LHS 5/20/2021 5/21/2021

EPC-06/HW/2325 Level & FDD Checking of Subgrade Top layer SG Top 45+600 46+200 LHS 5/20/2021 5/21/2021

EPC-06/HW/2326 Level & FDD Checking For GSB layer GSB 85+670 86+445 RHS 5/20/2021 5/21/2021

EPC-06/HW/2327 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+100 68+210 LHS 5/20/2021 5/21/2021

EPC-06/HW/2331 Level & FDD Checking For GSB layer GSB 86+445 86+530 LHS 5/21/2021 5/22/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2332 Level and FDD checking of DLC layer DLC 86+800 86+845 LHS 5/21/2021 5/22/2021

EPC-06/HW/2333 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+440 68+500 LHS 5/21/2021 5/22/2021

EPC-06/HW/2334 Level & FDD Checking of Subgrade Top layer SG Top 46+200 46+940 LHS 5/21/2021 5/22/2021

EPC-06/HW/2335 Level & FDD Checking For GSB layer GSB 44+400 44+900 LHS 5/21/2021 5/22/2021

EPC-06/HW/2336 FDD Checking of WMM 1st layer WMM-I 85+670 86+445 RHS 5/21/2021 5/22/2021

EPC-06/HW/2337 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+000 68+100 LHS 5/21/2021 5/22/2021

EPC-06/HW/2340 Level and FDD checking of DLC layer DLC 86+445 86+530 LHS 5/22/2021 5/23/2021

EPC-06/HW/2342 Level & FDD Checking of Subgrade Top layer SG Top 50+050 50+950 RHS 5/22/2021 5/23/2021

EPC-06/HW/2343 Level & FDD Checking of Subgrade Top layer SG Top 47+000 47+970 LHS 5/22/2021 5/23/2021

EPC-06/HW/2344 Level & FDD Checking For GSB layer GSB 44+900 45+600 LHS 5/22/2021 5/23/2021

EPC-06/HW/2345 Level & FDD Checking of WMM Top layer WMM-II 85+670 86+445 RHS 5/22/2021 5/23/2021

EPC-06/HW/2346 Applying primer coat Prime coat 85+670 86+445 RHS 5/22/2021 5/23/2021

EPC-06/HW/2347 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+500 49+560 LHS 5/23/2021 5/24/2021

EPC-06/HW/2348 Level & FDD Checking of Subgrade Top layer SG Top 50+950 52+000 RHS 5/23/2021 5/24/2021

EPC-06/HW/2349 Level & FDD Checking of Subgrade Top layer SG Top 48+030 48+970 LHS 5/23/2021 5/24/2021

EPC-06/HW/2350 Level & FDD Checking For GSB layer GSB 45+600 46+200 LHS 5/23/2021 5/24/2021

EPC-06/HW/2351 FDD Checking of WMM 1st layer WMM-I 44+400 44+900 LHS 5/23/2021 5/24/2021

EPC-06/HW/2352 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+210 68+300 LHS 5/23/2021 5/24/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2354 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+560 49+680 LHS 5/24/2021 5/25/2021

EPC-06/HW/2355 Level & FDD Checking of Subgrade Top layer SG Top 52+100 53+000 RHS 5/24/2021 5/25/2021

EPC-06/HW/2356 Level & FDD Checking For GSB layer GSB 50+050 50+950 RHS 5/24/2021 5/25/2021

EPC-06/HW/2357 Level & FDD Checking For GSB layer GSB 46+200 46+940 LHS 5/24/2021 5/25/2021

EPC-06/HW/2358 FDD Checking of WMM 1st layer WMM-I 44+900 45+600 LHS 5/24/2021 5/25/2021

EPC-06/HW/2359 Level & FDD Checking of WMM Top layer WMM-II 44+400 44+900 LHS 5/24/2021 5/25/2021

EPC-06/HW/2360 Applying primer coat Prime coat 44+400 44+900 LHS 5/24/2021 5/25/2021

EPC-06/HW/2361 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+100 68+210 LHS 5/24/2021 5/25/2021

EPC-06/HW/2371 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+680 49+800 LHS 5/25/2021 5/26/2021

EPC-06/HW/2372 Level & FDD Checking For GSB layer GSB 50+950 52+000 RHS 5/25/2021 5/26/2021

EPC-06/HW/2373 Level & FDD Checking For GSB layer GSB 47+000 47+970 LHS 5/25/2021 5/26/2021

EPC-06/HW/2374 FDD Checking of WMM 1st layer WMM-I 50+050 50+950 RHS 5/25/2021 5/26/2021

EPC-06/HW/2375 FDD Checking of WMM 1st layer WMM-I 45+600 46+200 LHS 5/25/2021 5/26/2021

EPC-06/HW/2376 Level & FDD Checking of WMM Top layer WMM-II 44+900 45+600 LHS 5/25/2021 5/26/2021

EPC-06/HW/2377 Applying primer coat Prime coat 44+900 45+600 LHS 5/25/2021 5/26/2021

EPC-06/HW/2378 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+000 68+100 LHS 5/25/2021 5/26/2021

EPC-06/HW/2388 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+800 49+900 LHS 5/26/2021 5/27/2021

EPC-06/HW/2389 Level & FDD Checking For GSB layer GSB 52+100 53+000 RHS 5/26/2021 5/27/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2390 Level & FDD Checking For GSB layer GSB 48+030 48+970 LHS 5/26/2021 5/27/2021

EPC-06/HW/2391 FDD Checking of WMM 1st layer WMM-I 50+950 52+000 RHS 5/26/2021 5/27/2021

EPC-06/HW/2392 FDD Checking of WMM 1st layer WMM-I 46+200 46+940 LHS 5/26/2021 5/27/2021

EPC-06/HW/2393 Level & FDD Checking of WMM Top layer WMM-II 50+050 50+950 RHS 5/26/2021 5/27/2021

EPC-06/HW/2394 Level & FDD Checking of WMM Top layer WMM-II 45+600 46+200 LHS 5/26/2021 5/27/2021

EPC-06/HW/2395 Applying primer coat Prime coat 50+050 50+950 RHS 5/26/2021 5/27/2021

EPC-06/HW/2396 Applying primer coat Prime coat 45+600 46+200 LHS 5/26/2021 5/27/2021

EPC-06/HW/2406 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+500 49+560 LHS 5/27/2021 5/28/2021

EPC-06/HW/2407 FDD Checking of WMM 1st layer WMM-I 52+100 53+000 RHS 5/27/2021 5/28/2021

EPC-06/HW/2408 FDD Checking of WMM 1st layer WMM-I 47+000 47+970 LHS 5/27/2021 5/28/2021

EPC-06/HW/2409 Level & FDD Checking of WMM Top layer WMM-II 50+950 52+000 RHS 5/27/2021 5/28/2021

EPC-06/HW/2410 Level & FDD Checking of WMM Top layer WMM-II 46+200 46+940 LHS 5/27/2021 5/28/2021

EPC-06/HW/2411 Applying primer coat Prime coat 50+950 52+000 RHS 5/27/2021 5/28/2021

EPC-06/HW/2412 Applying primer coat Prime coat 46+200 46+940 LHS 5/27/2021 5/28/2021

EPC-06/HW/2422 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+800 86+845 LHS 5/28/2021 5/29/2021

EPC-06/HW/2423 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+560 49+680 LHS 5/28/2021 5/29/2021

EPC-06/HW/2424 FDD Checking of WMM 1st layer WMM-I 48+030 48+970 LHS 5/28/2021 5/29/2021

EPC-06/HW/2425 Level & FDD Checking of WMM Top layer WMM-II 52+100 53+000 RHS 5/28/2021 5/29/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2426 Level & FDD Checking of WMM Top layer WMM-II 47+000 47+970 LHS 5/28/2021 5/29/2021

EPC-06/HW/2427 Applying primer coat Prime coat 52+100 53+000 RHS 5/28/2021 5/29/2021

EPC-06/HW/2428 Applying primer coat Prime coat 47+000 47+970 LHS 5/28/2021 5/29/2021

EPC-06/HW/2429 Applying tack coat for DBM Tack coat (DBM) 85+670 86+445 RHS 5/28/2021 5/29/2021

EPC-06/HW/2430 Level checking and laying of DBM DBM 85+670 86+445 RHS 5/28/2021 5/29/2021

EPC-06/HW/2440 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+445 86+530 LHS 5/29/2021 5/30/2021

EPC-06/HW/2441 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+800 86+845 LHS 5/29/2021 5/30/2021

EPC-06/HW/2442 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+680 49+800 LHS 5/29/2021 5/30/2021

EPC-06/HW/2443 Level & FDD Checking of WMM Top layer WMM-II 48+030 48+970 LHS 5/29/2021 5/30/2021

EPC-06/HW/2444 Applying primer coat Prime coat 48+030 48+970 LHS 5/29/2021 5/30/2021

EPC-06/HW/2445 Applying tack coat for DBM Tack coat (DBM) 50+050 50+500 RHS 5/29/2021 5/30/2021

EPC-06/HW/2445 Applying tack coat for DBM Tack coat (DBM) 50+500 50+950 RHS 5/29/2021 5/30/2021

EPC-06/HW/2445 Applying tack coat for DBM Tack coat (DBM) 50+950 51+400 RHS 5/29/2021 5/30/2021

EPC-06/HW/2448 Level checking and laying of DBM DBM 50+050 50+500 RHS 5/29/2021 5/30/2021

EPC-06/HW/2448 Level checking and laying of DBM DBM 50+500 50+950 RHS 5/29/2021 5/30/2021

EPC-06/HW/2448 Level checking and laying of DBM DBM 50+950 51+400 RHS 5/29/2021 5/30/2021

EPC-06/HW/2449 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 50+133 RHS 5/29/2021 5/30/2021

EPC-06/HW/2450 Laying of DBM on Minor Junction DBM 50+133 RHS 5/29/2021 5/30/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2460 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 86+445 86+530 LHS 5/30/2021 5/31/2021

EPC-06/HW/2461 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+800 49+900 LHS 5/30/2021 5/31/2021

EPC-06/HW/2462 Applying tack coat for DBM Tack coat (DBM) 51+400 52+000 RHS 5/30/2021 5/31/2021

EPC-06/HW/2462 Applying tack coat for DBM Tack coat (DBM) 52+100 52+550 RHS 5/30/2021 5/31/2021

EPC-06/HW/2462 Applying tack coat for DBM Tack coat (DBM) 52+550 53+000 RHS 5/30/2021 5/31/2021

EPC-06/HW/2465 Level checking and laying of DBM DBM 51+400 52+000 RHS 5/30/2021 5/31/2021

EPC-06/HW/2465 Level checking and laying of DBM DBM 52+100 52+550 RHS 5/30/2021 5/31/2021

EPC-06/HW/2465 Level checking and laying of DBM DBM 52+550 53+000 RHS 5/30/2021 5/31/2021

EPC-06/HW/2480 Level & FDD Checking of Subgrade Top layer SG Top 79+960 80+000 BHS 5/31/2021 6/1/2021

EPC-06/HW/2481 Level & FDD Checking of Subgrade Top layer SG Top 80+440 80+500 BHS 5/31/2021 6/1/2021

EPC-06/HW/2482 Level & FDD Checking of Subgrade Top layer SG Top 80+950 81+050 BHS 5/31/2021 6/1/2021

EPC-06/HW/2483 Level & FDD Checking of Subgrade Top layer SG Top 81+440 81+500 BHS 5/31/2021 6/1/2021

EPC-06/HW/2489 Level & FDD Checking of Subgrade Top layer SG Top 73+560 73+620 BHS 6/1/2021 6/2/2021

EPC-06/HW/2490 Level & FDD Checking of Subgrade Top layer SG Top 74+980 75+180 BHS 6/1/2021 6/2/2021

EPC-06/HW/2491 Level & FDD Checking of Subgrade Top layer SG Top 75+900 76+060 BHS 6/1/2021 6/2/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2492 Level & FDD Checking of Subgrade Top layer SG Top 76+560 76+720 BHS 6/1/2021 6/2/2021

EPC-06/HW/2493 Level & FDD Checking of Subgrade Top layer SG Top 77+220 77+300 BHS 6/1/2021 6/2/2021

EPC-06/HW/2494 Level & FDD Checking of Subgrade Top layer SG Top 79+640 79+700 BHS 6/1/2021 6/2/2021

EPC-06/HW/2495 Level & FDD Checking For GSB layer GSB 79+940 80+020 BHS 6/1/2021 6/2/2021

EPC-06/HW/2496 Level & FDD Checking For GSB layer GSB 80+420 80+500 BHS 6/1/2021 6/2/2021

EPC-06/HW/2497 Level & FDD Checking For GSB layer GSB 80+950 81+050 BHS 6/1/2021 6/2/2021

EPC-06/HW/2498 Level & FDD Checking For GSB layer GSB 81+440 81+500 BHS 6/1/2021 6/2/2021

EPC-06/HW/2504 Level & FDD Checking of Subgrade Top layer SG Top 70+900 71+100 LHS 6/2/2021 6/3/2021

EPC-06/HW/2505 Level & FDD Checking of Subgrade Top layer SG Top 70+980 71+100 RHS 6/2/2021 6/3/2021

EPC-06/HW/2506 Level & FDD Checking of Subgrade Top layer SG Top 73+040 73+120 LHS 6/2/2021 6/3/2021

EPC-06/HW/2507 Level & FDD Checking of Subgrade Top layer SG Top 73+045 73+120 RHS 6/2/2021 6/3/2021

EPC-06/HW/2508 Level & FDD Checking For GSB layer GSB 73+560 73+620 BHS 6/2/2021 6/3/2021

EPC-06/HW/2509 Level & FDD Checking For GSB layer GSB 74+980 75+180 BHS 6/2/2021 6/3/2021

EPC-06/HW/2510 Level & FDD Checking For GSB layer GSB 75+900 76+060 BHS 6/2/2021 6/3/2021

EPC-06/HW/2511 Level & FDD Checking For GSB layer GSB 76+560 76+720 BHS 6/2/2021 6/3/2021

EPC-06/HW/2512 Level & FDD Checking For GSB layer GSB 77+220 77+300 BHS 6/2/2021 6/3/2021

EPC-06/HW/2513 Level & FDD Checking For GSB layer GSB 79+640 79+700 BHS 6/2/2021 6/3/2021

EPC-06/HW/2514 FDD Checking of WMM 1st layer WMM-I 79+940 80+020 BHS 6/2/2021 6/3/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2515 FDD Checking of WMM 1st layer WMM-I 80+420 80+500 BHS 6/2/2021 6/3/2021

EPC-06/HW/2516 FDD Checking of WMM 1st layer WMM-I 80+950 81+050 BHS 6/2/2021 6/3/2021

EPC-06/HW/2517 FDD Checking of WMM 1st layer WMM-I 81+440 81+500 BHS 6/2/2021 6/3/2021

EPC-06/HW/2524 Level & FDD Checking of Subgrade Top layer SG Top 70+280 70+340 LHS 6/3/2021 6/4/2021

EPC-06/HW/2525 Level & FDD Checking of Subgrade Top layer SG Top 70+280 70+335 RHS 6/3/2021 6/4/2021

EPC-06/HW/2526 Level & FDD Checking of Subgrade Top layer SG Top 70+710 70+750 BHS 6/3/2021 6/4/2021

EPC-06/HW/2527 Level & FDD Checking For GSB layer GSB 70+900 71+100 LHS 6/3/2021 6/4/2021

EPC-06/HW/2528 Level & FDD Checking For GSB layer GSB 70+980 71+100 RHS 6/3/2021 6/4/2021

EPC-06/HW/2529 Level & FDD Checking For GSB layer GSB 73+040 73+120 BHS 6/3/2021 6/4/2021

EPC-06/HW/2530 FDD Checking of WMM 1st layer WMM-I 73+560 73+620 BHS 6/3/2021 6/4/2021

EPC-06/HW/2531 FDD Checking of WMM 1st layer WMM-I 74+980 75+180 BHS 6/3/2021 6/4/2021

EPC-06/HW/2532 FDD Checking of WMM 1st layer WMM-I 75+900 76+060 BHS 6/3/2021 6/4/2021

EPC-06/HW/2533 FDD Checking of WMM 1st layer WMM-I 76+560 76+720 BHS 6/3/2021 6/4/2021

EPC-06/HW/2534 FDD Checking of WMM 1st layer WMM-I 77+220 77+300 BHS 6/3/2021 6/4/2021

EPC-06/HW/2535 FDD Checking of WMM 1st layer WMM-I 79+640 79+700 BHS 6/3/2021 6/4/2021

EPC-06/HW/2536 Level & FDD Checking of WMM Top layer WMM-II 79+940 80+020 BHS 6/3/2021 6/4/2021

EPC-06/HW/2537 Level & FDD Checking of WMM Top layer WMM-II 80+420 80+500 BHS 6/3/2021 6/4/2021

EPC-06/HW/2538 Level & FDD Checking of WMM Top layer WMM-II 80+950 81+050 BHS 6/3/2021 6/4/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2539 Level & FDD Checking of WMM Top layer WMM-II 81+440 81+500 BHS 6/3/2021 6/4/2021

EPC-06/HW/2540 Applying primer coat Prime coat 79+940 80+020 BHS 6/3/2021 6/4/2021

EPC-06/HW/2540 Applying primer coat Prime coat 80+420 80+500 BHS 6/3/2021 6/4/2021

EPC-06/HW/2540 Applying primer coat Prime coat 80+950 81+050 BHS 6/3/2021 6/4/2021

EPC-06/HW/2540 Applying primer coat Prime coat 81+440 81+500 BHS 6/3/2021 6/4/2021

EPC-06/HW/2549 Level & FDD Checking For GSB layer GSB 70+280 70+340 BHS 6/4/2021 6/5/2021

EPC-06/HW/2550 Level & FDD Checking For GSB layer GSB 70+710 70+750 BHS 6/4/2021 6/5/2021

EPC-06/HW/2551 FDD Checking of WMM 1st layer WMM-I 70+900 71+100 LHS 6/4/2021 6/5/2021

EPC-06/HW/2552 FDD Checking of WMM 1st layer WMM-I 70+980 71+100 RHS 6/4/2021 6/5/2021

EPC-06/HW/2553 FDD Checking of WMM 1st layer WMM-I 73+040 73+120 BHS 6/4/2021 6/5/2021

EPC-06/HW/2554 Level & FDD Checking of WMM Top layer WMM-II 73+560 73+620 BHS 6/4/2021 6/5/2021

EPC-06/HW/2555 Level & FDD Checking of WMM Top layer WMM-II 74+980 75+180 BHS 6/4/2021 6/5/2021

EPC-06/HW/2556 Level & FDD Checking of WMM Top layer WMM-II 75+900 76+060 BHS 6/4/2021 6/5/2021

EPC-06/HW/2557 Level & FDD Checking of WMM Top layer WMM-II 76+560 76+720 BHS 6/4/2021 6/5/2021

EPC-06/HW/2558 Level & FDD Checking of WMM Top layer WMM-II 77+220 77+300 BHS 6/4/2021 6/5/2021

EPC-06/HW/2559 Level & FDD Checking of WMM Top layer WMM-II 79+640 79+700 BHS 6/4/2021 6/5/2021

EPC-06/HW/2560 Applying primer coat Prime coat 73+560 73+620 BHS 6/4/2021 6/5/2021

EPC-06/HW/2560 Applying primer coat Prime coat 74+980 75+180 BHS 6/4/2021 6/5/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2560 Applying primer coat Prime coat 75+900 76+060 BHS 6/4/2021 6/5/2021

EPC-06/HW/2563 Applying primer coat Prime coat 76+560 76+720 BHS 6/4/2021 6/5/2021

EPC-06/HW/2563 Applying primer coat Prime coat 77+220 77+300 BHS 6/4/2021 6/5/2021

EPC-06/HW/2563 Applying primer coat Prime coat 79+640 79+700 BHS 6/4/2021 6/5/2021

EPC-06/HW/2571 FDD Checking of WMM 1st layer WMM-I 70+280 70+340 BHS 6/5/2021 6/6/2021

EPC-06/HW/2572 FDD Checking of WMM 1st layer WMM-I 70+710 70+750 BHS 6/5/2021 6/6/2021

EPC-06/HW/2573 Level & FDD Checking of WMM Top layer WMM-II 70+900 71+100 LHS 6/5/2021 6/6/2021

EPC-06/HW/2574 Level & FDD Checking of WMM Top layer WMM-II 70+980 71+100 RHS 6/5/2021 6/6/2021

EPC-06/HW/2575 Level & FDD Checking of WMM Top layer WMM-II 73+040 73+120 BHS 6/5/2021 6/6/2021

EPC-06/HW/2576 Applying primer coat Prime coat 70+900 71+100 LHS 6/5/2021 6/6/2021

EPC-06/HW/2576 Applying primer coat Prime coat 70+980 71+100 RHS 6/5/2021 6/6/2021

EPC-06/HW/2576 Applying primer coat Prime coat 73+040 73+120 BHS 6/5/2021 6/6/2021

EPC-06/HW/2579 Applying tack coat for DBM Tack coat (DBM) 76+560 76+720 BHS 6/5/2021 6/6/2021

EPC-06/HW/2579 Applying tack coat for DBM Tack coat (DBM) 77+220 77+300 BHS 6/5/2021 6/6/2021

EPC-06/HW/2579 Applying tack coat for DBM Tack coat (DBM) 79+630 79+700 LHS 6/5/2021 6/6/2021

EPC-06/HW/2579 Applying tack coat for DBM Tack coat (DBM) 79+640 79+700 RHS 6/5/2021 6/6/2021

EPC-06/HW/2583 Applying tack coat for DBM Tack coat (DBM) 79+940 80+020 BHS 6/5/2021 6/6/2021

EPC-06/HW/2583 Applying tack coat for DBM Tack coat (DBM) 80+420 80+500 BHS 6/5/2021 6/6/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2583 Applying tack coat for DBM Tack coat (DBM) 80+950 81+050 BHS 6/5/2021 6/6/2021

EPC-06/HW/2583 Applying tack coat for DBM Tack coat (DBM) 81+440 81+500 BHS 6/5/2021 6/6/2021

EPC-06/HW/2587 Level checking and laying of DBM DBM 76+560 76+720 BHS 6/5/2021 6/6/2021

EPC-06/HW/2587 Level checking and laying of DBM DBM 77+220 77+300 BHS 6/5/2021 6/6/2021

EPC-06/HW/2587 Level checking and laying of DBM DBM 79+630 79+700 LHS 6/5/2021 6/6/2021

EPC-06/HW/2587 Level checking and laying of DBM DBM 79+640 79+700 RHS 6/5/2021 6/6/2021

EPC-06/HW/2591 Level checking and laying of DBM DBM 79+940 80+020 BHS 6/5/2021 6/6/2021

EPC-06/HW/2591 Level checking and laying of DBM DBM 80+420 80+500 BHS 6/5/2021 6/6/2021

EPC-06/HW/2591 Level checking and laying of DBM DBM 80+950 81+050 BHS 6/5/2021 6/6/2021

EPC-06/HW/2591 Level checking and laying of DBM DBM 81+440 81+500 BHS 6/5/2021 6/6/2021

EPC-06/HW/2600 Level & FDD Checking of WMM Top layer WMM-II 70+280 70+340 BHS 6/6/2021 6/7/2021

EPC-06/HW/2601 Level & FDD Checking of WMM Top layer WMM-II 70+710 70+750 BHS 6/6/2021 6/7/2021

EPC-06/HW/2602 Applying primer coat Prime coat 70+280 70+340 BHS 6/6/2021 6/7/2021

EPC-06/HW/2602 Applying primer coat Prime coat 70+710 70+750 BHS 6/6/2021 6/7/2021

EPC-06/HW/2609 Applying tack coat for DBM Tack coat (DBM) 70+280 70+340 BHS 6/7/2021 6/8/2021

EPC-06/HW/2609 Applying tack coat for DBM Tack coat (DBM) 70+710 70+750 BHS 6/7/2021 6/8/2021

EPC-06/HW/2609 Applying tack coat for DBM Tack coat (DBM) 70+900 71+100 LHS 6/7/2021 6/8/2021

EPC-06/HW/2609 Applying tack coat for DBM Tack coat (DBM) 70+980 71+100 RHS 6/7/2021 6/8/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2613 Applying tack coat for DBM Tack coat (DBM) 73+040 73+120 BHS 6/7/2021 6/8/2021

EPC-06/HW/2613 Applying tack coat for DBM Tack coat (DBM) 73+560 73+620 BHS 6/7/2021 6/8/2021

EPC-06/HW/2613 Applying tack coat for DBM Tack coat (DBM) 74+980 75+180 BHS 6/7/2021 6/8/2021

EPC-06/HW/2613 Applying tack coat for DBM Tack coat (DBM) 75+900 76+060 BHS 6/7/2021 6/8/2021

EPC-06/HW/2617 Level checking and laying of DBM DBM 70+280 70+340 BHS 6/7/2021 6/8/2021

EPC-06/HW/2617 Level checking and laying of DBM DBM 70+710 70+750 BHS 6/7/2021 6/8/2021

EPC-06/HW/2617 Level checking and laying of DBM DBM 70+900 71+100 LHS 6/7/2021 6/8/2021

EPC-06/HW/2617 Level checking and laying of DBM DBM 70+980 71+100 RHS 6/7/2021 6/8/2021

EPC-06/HW/2620 Level checking and laying of DBM DBM 73+040 73+120 BHS 6/7/2021 6/8/2021

EPC-06/HW/2620 Level checking and laying of DBM DBM 73+560 73+620 BHS 6/7/2021 6/8/2021

EPC-06/HW/2620 Level checking and laying of DBM DBM 74+980 75+180 BHS 6/7/2021 6/8/2021

EPC-06/HW/2620 Level checking and laying of DBM DBM 75+900 76+060 BHS 6/7/2021 6/8/2021

EPC-06/HW/2634 Level & FDD Checking of Subgrade Top layer SG Top 64+450 64+520 BHS 6/11/2021 6/12/2021

EPC-06/HW/2635 Level & FDD Checking of Subgrade Top layer SG Top 64+890 65+010 BHS 6/11/2021 6/12/2021

EPC-06/HW/2636 Level & FDD Checking of Subgrade Top layer SG Top 65+900 65+970 BHS 6/11/2021 6/12/2021

EPC-06/HW/2637 Level & FDD Checking of Subgrade Top layer SG Top 66+250 66+320 BHS 6/11/2021 6/12/2021

EPC-06/HW/2638 Level & FDD Checking of Subgrade Top layer SG Top 67+070 67+130 BHS 6/11/2021 6/12/2021

EPC-06/HW/2644 Level & FDD Checking For GSB layer GSB 64+450 64+520 BHS 6/12/2021 6/13/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2645 Level & FDD Checking For GSB layer GSB 64+890 65+010 BHS 6/12/2021 6/13/2021

EPC-06/HW/2646 Level & FDD Checking For GSB layer GSB 65+900 65+970 BHS 6/12/2021 6/13/2021

EPC-06/HW/2647 Level & FDD Checking For GSB layer GSB 66+250 66+320 BHS 6/12/2021 6/13/2021

EPC-06/HW/2648 Level & FDD Checking For GSB layer GSB 67+070 67+130 BHS 6/12/2021 6/13/2021

EPC-06/HW/2654 FDD Checking of WMM 1st layer WMM-I 64+450 64+520 BHS 6/13/2021 6/14/2021

EPC-06/HW/2655 FDD Checking of WMM 1st layer WMM-I 64+890 65+010 BHS 6/13/2021 6/14/2021

EPC-06/HW/2656 FDD Checking of WMM 1st layer WMM-I 65+900 65+970 BHS 6/13/2021 6/14/2021

EPC-06/HW/2657 FDD Checking of WMM 1st layer WMM-I 66+250 66+320 BHS 6/13/2021 6/14/2021

EPC-06/HW/2658 FDD Checking of WMM 1st layer WMM-I 67+070 67+130 BHS 6/13/2021 6/14/2021

EPC-06/HW/2664 Level & FDD Checking of WMM Top layer WMM-II 64+450 64+520 BHS 6/14/2021 6/15/2021

EPC-06/HW/2665 Level & FDD Checking of WMM Top layer WMM-II 64+890 65+010 BHS 6/14/2021 6/15/2021

EPC-06/HW/2666 Level & FDD Checking of WMM Top layer WMM-II 65+900 65+970 BHS 6/14/2021 6/15/2021

EPC-06/HW/2667 Level & FDD Checking of WMM Top layer WMM-II 66+250 66+320 BHS 6/14/2021 6/15/2021

EPC-06/HW/2668 Level & FDD Checking of WMM Top layer WMM-II 67+070 67+130 BHS 6/14/2021 6/15/2021

EPC-06/HW/2669 Applying primer coat Prime coat 64+450 64+520 BHS 6/14/2021 6/15/2021

EPC-06/HW/2669 Applying primer coat Prime coat 64+890 65+010 BHS 6/14/2021 6/15/2021

EPC-06/HW/2669 Applying primer coat Prime coat 65+900 65+970 BHS 6/14/2021 6/15/2021

EPC-06/HW/2672 Applying primer coat Prime coat 66+250 66+320 BHS 6/14/2021 6/15/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2672 Applying primer coat Prime coat 67+070 67+130 BHS 6/14/2021 6/15/2021

EPC-06/HW/2679 Level & FDD Checking of Subgrade Top layer SG Top 59+010 59+070 BHS 6/15/2021 6/16/2021

EPC-06/HW/2680 Level & FDD Checking of Subgrade Top layer SG Top 59+830 59+890 BHS 6/15/2021 6/16/2021

EPC-06/HW/2681 Level & FDD Checking of Subgrade Top layer SG Top 60+620 60+680 BHS 6/15/2021 6/16/2021

EPC-06/HW/2682 Level & FDD Checking of Subgrade Top layer SG Top 64+250 64+310 BHS 6/15/2021 6/16/2021

EPC-06/HW/2688 Applying tack coat for DBM Tack coat (DBM) 64+450 64+520 BHS 6/16/2021 6/17/2021

EPC-06/HW/2688 Applying tack coat for DBM Tack coat (DBM) 64+890 65+010 BHS 6/16/2021 6/17/2021

EPC-06/HW/2688 Applying tack coat for DBM Tack coat (DBM) 65+900 65+970 BHS 6/16/2021 6/17/2021

EPC-06/HW/2691 Applying tack coat for DBM Tack coat (DBM) 66+250 66+320 BHS 6/16/2021 6/17/2021

EPC-06/HW/2691 Applying tack coat for DBM Tack coat (DBM) 67+070 67+130 BHS 6/16/2021 6/17/2021

EPC-06/HW/2693 Level checking and laying of DBM DBM 64+450 64+520 BHS 6/16/2021 6/17/2021

EPC-06/HW/2693 Level checking and laying of DBM DBM 64+890 65+010 BHS 6/16/2021 6/17/2021

EPC-06/HW/2693 Level checking and laying of DBM DBM 65+900 65+970 BHS 6/16/2021 6/17/2021

EPC-06/HW/2696 Level checking and laying of DBM DBM 66+250 66+320 BHS 6/16/2021 6/17/2021

EPC-06/HW/2696 Level checking and laying of DBM DBM 67+070 67+130 BHS 6/16/2021 6/17/2021

EPC-06/HW/2703 Level & FDD Checking For GSB layer GSB 59+010 59+070 BHS 6/17/2021 6/18/2021

EPC-06/HW/2704 Level & FDD Checking For GSB layer GSB 59+830 59+890 BHS 6/17/2021 6/18/2021

EPC-06/HW/2705 Level & FDD Checking For GSB layer GSB 60+620 60+680 BHS 6/17/2021 6/18/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2706 Level & FDD Checking For GSB layer GSB 64+250 64+310 BHS 6/17/2021 6/18/2021

EPC-06/HW/2716 FDD Checking of WMM 1st layer WMM-I 59+010 59+070 BHS 6/19/2021 6/20/2021

EPC-06/HW/2717 FDD Checking of WMM 1st layer WMM-I 59+830 59+890 BHS 6/19/2021 6/20/2021

EPC-06/HW/2718 FDD Checking of WMM 1st layer WMM-I 60+620 60+680 BHS 6/19/2021 6/20/2021

EPC-06/HW/2719 FDD Checking of WMM 1st layer WMM-I 64+250 64+310 BHS 6/19/2021 6/20/2021

EPC-06/HW/2720 Dismantling of existing BT surface BT Scr 88+520 88+900 BHS 6/19/2021 6/20/2021

EPC-06/HW/2725 Level & FDD Checking of WMM Top layer WMM-II 59+010 59+070 BHS 6/20/2021 6/21/2021

EPC-06/HW/2726 Level & FDD Checking of WMM Top layer WMM-II 59+830 59+890 BHS 6/20/2021 6/21/2021

EPC-06/HW/2727 Level & FDD Checking of WMM Top layer WMM-II 60+620 60+680 BHS 6/20/2021 6/21/2021

EPC-06/HW/2728 Level & FDD Checking of WMM Top layer WMM-II 64+250 64+310 BHS 6/20/2021 6/21/2021

EPC-06/HW/2729 Applying primer coat Prime coat 59+010 59+070 BHS 6/20/2021 6/21/2021

EPC-06/HW/2729 Applying primer coat Prime coat 59+830 59+890 BHS 6/20/2021 6/21/2021

EPC-06/HW/2729 Applying primer coat Prime coat 60+620 60+680 BHS 6/20/2021 6/21/2021

EPC-06/HW/2729 Applying primer coat Prime coat 64+250 64+310 BHS 6/20/2021 6/21/2021

EPC-06/HW/2738 Level & FDD Checking of Subgrade Top layer SG Top 68+000 68+080 LHS 6/21/2021 6/22/2021

EPC-06/HW/2739 Level & FDD Checking of Subgrade Top layer SG Top 68+780 69+230 LHS 6/21/2021 6/22/2021

EPC-06/HW/2740 Level & FDD Checking of Subgrade Top layer SG Top 68+000 68+080 RHS 6/21/2021 6/22/2021

EPC-06/HW/2746 Level & FDD Checking For GSB layer GSB 68+000 68+080 LHS 6/22/2021 6/23/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2747 Level & FDD Checking For GSB layer GSB 68+780 69+230 LHS 6/22/2021 6/23/2021

EPC-06/HW/2748 Level & FDD Checking For GSB layer GSB 68+000 68+080 RHS 6/22/2021 6/23/2021

EPC-06/HW/2749 Applying tack coat for DBM Tack coat (DBM) 59+010 59+070 BHS 6/22/2021 6/23/2021

EPC-06/HW/2749 Applying tack coat for DBM Tack coat (DBM) 59+830 59+890 BHS 6/22/2021 6/23/2021

EPC-06/HW/2749 Applying tack coat for DBM Tack coat (DBM) 60+620 60+680 BHS 6/22/2021 6/23/2021

EPC-06/HW/2749 Applying tack coat for DBM Tack coat (DBM) 64+250 64+310 BHS 6/22/2021 6/23/2021

EPC-06/HW/2753 Level checking and laying of DBM DBM 59+010 59+070 BHS 6/22/2021 6/23/2021

EPC-06/HW/2753 Level checking and laying of DBM DBM 59+830 59+890 BHS 6/22/2021 6/23/2021

EPC-06/HW/2755 Level checking and laying of DBM DBM 60+620 60+680 BHS 6/22/2021 6/23/2021

EPC-06/HW/2755 Level checking and laying of DBM DBM 64+250 64+310 BHS 6/22/2021 6/23/2021

EPC-06/HW/2757 FDD Checking of Subgrade Top layer on Minor Junction SG Top 47+755 LHS 6/22/2021 6/23/2021

EPC-06/HW/2758 FDD Checking of Subgrade Top layer on Minor Junction SG Top 47+847 LHS 6/22/2021 6/23/2021

EPC-06/HW/2765 FDD Checking of WMM 1st layer WMM-I 68+000 68+080 LHS 6/23/2021 6/24/2021

EPC-06/HW/2766 FDD Checking of WMM 1st layer WMM-I 68+780 69+230 LHS 6/23/2021 6/24/2021

EPC-06/HW/2767 FDD Checking of WMM 1st layer WMM-I 68+000 68+080 RHS 6/23/2021 6/24/2021

EPC-06/HW/2768 FDD Checking For GSB layer on Minor Junction GSB 47+755 LHS 6/23/2021 6/24/2021

EPC-06/HW/2769 FDD Checking For GSB layer on Minor Junction GSB 47+847 LHS 6/23/2021 6/24/2021

EPC-06/HW/2776 Level & FDD Checking of Subgrade Top layer SG Top 88+650 88+850 BHS 6/24/2021 6/25/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2777 Level & FDD Checking of WMM Top layer WMM-II 68+000 68+080 LHS 6/24/2021 6/25/2021

EPC-06/HW/2778 Level & FDD Checking of WMM Top layer WMM-II 68+780 69+230 LHS 6/24/2021 6/25/2021

EPC-06/HW/2779 Level & FDD Checking of WMM Top layer WMM-II 68+000 68+080 RHS 6/24/2021 6/25/2021

EPC-06/HW/2780 Applying primer coat Prime coat 68+000 68+080 LHS 6/24/2021 6/25/2021

EPC-06/HW/2780 Applying primer coat Prime coat 68+780 69+230 LHS 6/24/2021 6/25/2021

EPC-06/HW/2780 Applying primer coat Prime coat 68+000 68+080 RHS 6/24/2021 6/25/2021

EPC-06/HW/2783 Level & FDD Checking of Subgrade Top layer SG Top 68+440 68+780 RHS 6/24/2021 6/25/2021

EPC-06/HW/2793 FDD Checking of WMM Top layer on Minor Junction WMM-II 47+755 LHS 6/26/2021 6/27/2021

EPC-06/HW/2794 Applying primer coat on Minor Junction Prime coat 47+755 LHS 6/26/2021 6/27/2021

EPC-06/HW/2795 FDD Checking of WMM Top layer on Minor Junction WMM-II 47+847 LHS 6/26/2021 6/27/2021

EPC-06/HW/2794 Applying primer coat on Minor Junction Prime coat 47+847 LHS 6/26/2021 6/27/2021

EPC-06/HW/2802 Level & FDD Checking For GSB layer GSB 88+650 88+850 BHS 6/27/2021 6/28/2021

EPC-06/HW/2803 Applying tack coat for DBM Tack coat (DBM) 68+000 68+080 LHS 6/27/2021 6/28/2021

EPC-06/HW/2803 Applying tack coat for DBM Tack coat (DBM) 68+780 69+230 LHS 6/27/2021 6/28/2021

EPC-06/HW/2803 Applying tack coat for DBM Tack coat (DBM) 68+000 68+080 RHS 6/27/2021 6/28/2021

EPC-06/HW/2806 Level checking and laying of DBM DBM 68+000 68+080 LHS 6/27/2021 6/28/2021

EPC-06/HW/2806 Level checking and laying of DBM DBM 68+780 69+230 LHS 6/27/2021 6/28/2021

EPC-06/HW/2806 Level checking and laying of DBM DBM 68+000 68+080 RHS 6/27/2021 6/28/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2809 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 47+755 LHS 6/27/2021 6/28/2021

EPC-06/HW/2810 Laying of DBM on Minor Junction DBM 47+755 LHS 6/27/2021 6/28/2021

EPC-06/HW/2809 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 47+847 LHS 6/27/2021 6/28/2021

EPC-06/HW/2812 Laying of DBM on Minor Junction DBM 47+847 LHS 6/27/2021 6/28/2021

EPC-06/HW/2822 Level & FDD Checking For GSB layer GSB 68+440 68+780 RHS 6/29/2021 6/30/2021

EPC-06/HW/2828 FDD Checking of WMM 1st layer WMM-I 88+650 88+850 BHS 6/30/2021 7/1/2021

EPC-06/HW/2834 Level & FDD Checking of WMM Top layer WMM-II 88+650 88+850 BHS 7/1/2021 7/2/2021

EPC-06/HW/2835 Applying primer coat Prime coat 88+650 88+850 BHS 7/1/2021 7/2/2021

EPC-06/HW/2836 Level and FDD checking of DLC layer DLC 68+440 68+780 RHS 7/1/2021 7/2/2021

EPC-06/HW/2837 Dismantling of existing BT surface BT Scr 68+780 69+230 BHS 7/1/2021 7/2/2021

EPC-06/HW/2846 Applying tack coat for DBM Tack coat (DBM) 88+650 88+850 BHS 7/3/2021 7/4/2021

EPC-06/HW/2847 Level checking and laying of DBM DBM 88+650 88+850 BHS 7/3/2021 7/4/2021

EPC-06/HW/2848 Laying of DBM on Minor Junction DBM 58+360 RHS 7/3/2021 7/4/2021

EPC-06/HW/2854 Level & FDD Checking of Subgrade Top layer SG Top 68+780 69+230 RHS 7/5/2021 7/6/2021

EPC-06/HW/2865 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+440 68+570 RHS 7/13/2021 7/14/2021

EPC-06/HW/2872 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+570 68+680 RHS 7/15/2021 7/16/2021

EPC-06/HW/2877 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+680 68+780 RHS 7/16/2021 7/17/2021

EPC-06/HW/2884 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+440 68+600 RHS 7/18/2021 7/19/2021

EPC-06/HW/2894 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+600 68+690 RHS 7/22/2021 7/23/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/2900 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+690 68+780 RHS 7/24/2021 7/25/2021

EPC-06/HW/2911 Level & FDD Checking of Subgrade Top layer SG Top 49+500 49+900 RHS 7/29/2021 7/30/2021

EPC-06/HW/2923 Level & FDD Checking For GSB layer GSB 49+500 49+900 RHS 8/2/2021 8/3/2021

EPC-06/HW/2930 Level and FDD checking of DLC layer DLC 49+500 49+900 RHS 8/4/2021 8/5/2021

EPC-06/HW/2942 Level & FDD Checking of Subgrade Top layer SG Top 68+080 68+300 RHS 8/9/2021 8/10/2021

EPC-06/HW/2952 Level & FDD Checking For GSB layer GSB 68+080 68+300 RHS 8/12/2021 8/13/2021

EPC-06/HW/2959 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+500 49+620 RHS 8/15/2021 8/16/2021

EPC-06/HW/2964 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+620 49+730 RHS 8/16/2021 8/17/2021

EPC-06/HW/2969 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+730 49+800 RHS 8/17/2021 8/18/2021

EPC-06/HW/2977 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 49+800 49+900 RHS 8/19/2021 8/20/2021

EPC-06/HW/2987 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+500 49+600 RHS 8/22/2021 8/23/2021

EPC-06/HW/2992 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+600 49+690 RHS 8/24/2021 8/25/2021

EPC-06/HW/2997 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+690 49+830 RHS 8/25/2021 8/26/2021

EPC-06/HW/3003 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 49+830 49+900 RHS 8/26/2021 8/27/2021

EPC-06/HW/3053 Dismantling of existing BT surface BT Scr 44+300 44+400 BHS 8/31/2021 9/1/2021

EPC-06/HW/3054 Dismantling of existing BT surface BT Scr 48+970 49+500 BHS 8/31/2021 9/1/2021

EPC-06/HW/3055 Dismantling of existing BT surface BT Scr 49+900 50+050 BHS 8/31/2021 9/1/2021

EPC-06/HW/3058 Level & FDD Checking of Subgrade Top layer SG Top 44+300 44+400 LHS 9/1/2021 9/2/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3059 Level & FDD Checking of Subgrade Top layer SG Top 46+940 47+000 LHS 9/1/2021 9/2/2021

EPC-06/HW/3060 Level & FDD Checking of Subgrade Top layer SG Top 47+970 48+030 LHS 9/1/2021 9/2/2021

EPC-06/HW/3065 Level & FDD Checking For GSB layer GSB 44+300 44+400 LHS 9/3/2021 9/4/2021

EPC-06/HW/3066 Level & FDD Checking For GSB layer GSB 46+940 47+000 LHS 9/3/2021 9/4/2021

EPC-06/HW/3067 Level & FDD Checking For GSB layer GSB 47+970 48+030 LHS 9/3/2021 9/4/2021

EPC-06/HW/3077 FDD Checking of WMM 1st layer WMM-I 44+300 44+400 LHS 9/8/2021 9/9/2021

EPC-06/HW/3078 FDD Checking of WMM 1st layer WMM-I 46+940 47+000 LHS 9/8/2021 9/9/2021

EPC-06/HW/3079 FDD Checking of WMM 1st layer WMM-I 47+970 48+030 LHS 9/8/2021 9/9/2021

EPC-06/HW/3080 FDD Checking of Subgrade Top layer on Minor Junction SG Top 45+065 LHS 9/8/2021 9/9/2021

EPC-06/HW/3083 Level & FDD Checking of WMM Top layer WMM-II 44+300 44+400 LHS 9/9/2021 9/10/2021

EPC-06/HW/3084 Level & FDD Checking of WMM Top layer WMM-II 46+940 47+000 LHS 9/9/2021 9/10/2021

EPC-06/HW/3085 Level & FDD Checking of WMM Top layer WMM-II 47+970 48+030 LHS 9/9/2021 9/10/2021

EPC-06/HW/3086 Applying primer coat Prime coat 44+300 44+400 LHS 9/9/2021 9/10/2021

EPC-06/HW/3086 Applying primer coat Prime coat 46+940 47+000 LHS 9/9/2021 9/10/2021

EPC-06/HW/3086 Applying primer coat Prime coat 47+970 48+030 LHS 9/9/2021 9/10/2021

EPC-06/HW/3089 FDD Checking For GSB layer on Minor Junction GSB 45+065 LHS 9/9/2021 9/10/2021

EPC-06/HW/3092 FDD Checking of Subgrade Top layer on Minor Junction SG Top 47+275 LHS 9/10/2021 9/11/2021

EPC-06/HW/3095 FDD Checking For GSB layer on Minor Junction GSB 47+275 LHS 9/11/2021 9/12/2021

EPC-06/HW/3098 FDD Checking of WMM Top layer on Minor Junction WMM-II 45+065 LHS 9/12/2021 9/13/2021

EPC-06/HW/3099 Applying primer coat on Minor Junction Prime coat 45+065 LHS 9/12/2021 9/13/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3102 Level & FDD Checking of Subgrade Top layer SG Top 91+230 91+300 LHS 9/13/2021 9/14/2021

EPC-06/HW/3103 Level & FDD Checking of Subgrade Top layer SG Top 93+700 93+770 LHS 9/13/2021 9/14/2021

EPC-06/HW/3104 Level & FDD Checking of Subgrade Top layer SG Top 91+230 91+300 RHS 9/13/2021 9/14/2021

EPC-06/HW/3105 Level & FDD Checking of Subgrade Top layer SG Top 93+700 93+770 RHS 9/13/2021 9/14/2021

EPC-06/HW/3106 Applying tack coat for DBM Tack coat (DBM) 44+300 46+250 LHS 9/13/2021 9/14/2021

EPC-06/HW/3107 Level checking and laying of DBM DBM 44+300 46+250 LHS 9/13/2021 9/14/2021

EPC-06/HW/3108 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 45+065 LHS 9/13/2021 9/14/2021

EPC-06/HW/3109 Laying of DBM on Minor Junction DBM 45+065 LHS 9/13/2021 9/14/2021

EPC-06/HW/3112 FDD Checking of WMM Top layer on Minor Junction WMM-II 47+275 LHS 9/14/2021 9/15/2021

EPC-06/HW/3113 Applying primer coat on Minor Junction Prime coat 47+275 LHS 9/14/2021 9/15/2021

EPC-06/HW/3116 Level & FDD Checking For GSB layer GSB 91+230 91+300 LHS 9/15/2021 9/16/2021

EPC-06/HW/3117 Level & FDD Checking For GSB layer GSB 93+700 93+770 LHS 9/15/2021 9/16/2021

EPC-06/HW/3118 Level & FDD Checking For GSB layer GSB 91+230 91+300 RHS 9/15/2021 9/16/2021

EPC-06/HW/3119 Level & FDD Checking For GSB layer GSB 93+700 93+770 RHS 9/15/2021 9/16/2021

EPC-06/HW/3120 Applying tack coat for DBM Tack coat (DBM) 46+320 47+900 LHS 9/15/2021 9/16/2021

EPC-06/HW/3121 Level checking and laying of DBM DBM 46+320 47+900 LHS 9/15/2021 9/16/2021

EPC-06/HW/3122 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 47+275 LHS 9/15/2021 9/16/2021

EPC-06/HW/3123 Laying of DBM on Minor Junction DBM 47+275 LHS 9/15/2021 9/16/2021

EPC-06/HW/3133 Level & FDD Checking of Subgrade Top layer SG Top 49+050 49+500 LHS 9/21/2021 9/22/2021

EPC-06/HW/3138 Level & FDD Checking of Subgrade Top layer SG Top 52+000 52+100 LHS 9/23/2021 9/24/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3139 Level & FDD Checking of Subgrade Top layer SG Top 58+740 58+840 LHS 9/23/2021 9/24/2021

EPC-06/HW/3140 Level & FDD Checking of Subgrade Top layer SG Top 52+000 52+100 RHS 9/23/2021 9/24/2021

EPC-06/HW/3141 Level & FDD Checking of Subgrade Top layer SG Top 58+740 58+840 RHS 9/23/2021 9/24/2021

EPC-06/HW/3142 Level & FDD Checking For GSB layer GSB 49+050 49+500 LHS 9/23/2021 9/24/2021

EPC-06/HW/3143 FDD Checking of WMM 1st layer WMM-I 91+230 91+300 LHS 9/23/2021 9/24/2021

EPC-06/HW/3144 FDD Checking of WMM 1st layer WMM-I 93+700 93+770 LHS 9/23/2021 9/24/2021

EPC-06/HW/3145 FDD Checking of WMM 1st layer WMM-I 91+230 91+300 RHS 9/23/2021 9/24/2021

EPC-06/HW/3146 FDD Checking of WMM 1st layer WMM-I 93+700 93+770 RHS 9/23/2021 9/24/2021

EPC-06/HW/3149 Level & FDD Checking of WMM Top layer WMM-II 91+230 91+300 LHS 9/24/2021 9/25/2021

EPC-06/HW/3150 Level & FDD Checking of WMM Top layer WMM-II 93+700 93+770 LHS 9/24/2021 9/25/2021

EPC-06/HW/3151 Level & FDD Checking of WMM Top layer WMM-II 91+230 91+300 RHS 9/24/2021 9/25/2021

EPC-06/HW/3152 Level & FDD Checking of WMM Top layer WMM-II 93+700 93+770 RHS 9/24/2021 9/25/2021

EPC-06/HW/3153 Applying primer coat Prime coat 91+230 91+300 LHS 9/24/2021 9/25/2021

EPC-06/HW/3153 Applying primer coat Prime coat 93+700 93+770 LHS 9/24/2021 9/25/2021

EPC-06/HW/3153 Applying primer coat Prime coat 91+230 91+300 RHS 9/24/2021 9/25/2021

EPC-06/HW/3153 Applying primer coat Prime coat 93+700 93+770 RHS 9/24/2021 9/25/2021

EPC-06/HW/3160 Level & FDD Checking For GSB layer GSB 52+000 52+100 LHS 9/26/2021 9/27/2021

EPC-06/HW/3161 Level & FDD Checking For GSB layer GSB 58+740 58+840 LHS 9/26/2021 9/27/2021

EPC-06/HW/3162 Level & FDD Checking For GSB layer GSB 52+000 52+100 RHS 9/26/2021 9/27/2021

EPC-06/HW/3163 Level & FDD Checking For GSB layer GSB 58+740 58+840 RHS 9/26/2021 9/27/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3167 FDD Checking of WMM 1st layer WMM-I 49+050 49+500 LHS 9/28/2021 9/29/2021

EPC-06/HW/3170 Level & FDD Checking of WMM Top layer WMM-II 49+050 49+500 LHS 9/29/2021 9/30/2021

EPC-06/HW/3171 Applying primer coat Prime coat 49+050 49+500 LHS 9/29/2021 9/30/2021

EPC-06/HW/3174 Applying tack coat for DBM Tack coat (DBM) 91+230 91+300 LHS 9/30/2021 10/1/2021

EPC-06/HW/3174 Applying tack coat for DBM Tack coat (DBM) 93+700 93+770 LHS 9/30/2021 10/1/2021

EPC-06/HW/3174 Applying tack coat for DBM Tack coat (DBM) 91+230 91+300 RHS 9/30/2021 10/1/2021

EPC-06/HW/3174 Applying tack coat for DBM Tack coat (DBM) 93+700 93+770 RHS 9/30/2021 10/1/2021

EPC-06/HW/3178 Level checking and laying of DBM DBM 91+230 91+300 LHS 9/30/2021 10/1/2021

EPC-06/HW/3178 Level checking and laying of DBM DBM 93+700 93+770 LHS 9/30/2021 10/1/2021

EPC-06/HW/3178 Level checking and laying of DBM DBM 91+230 91+300 RHS 9/30/2021 10/1/2021

EPC-06/HW/3178 Level checking and laying of DBM DBM 93+700 93+770 RHS 9/30/2021 10/1/2021

EPC-06/HW/3184 FDD Checking of WMM 1st layer WMM-I 52+000 52+100 LHS 10/1/2021 10/2/2021

EPC-06/HW/3185 FDD Checking of WMM 1st layer WMM-I 58+740 58+840 LHS 10/1/2021 10/2/2021

EPC-06/HW/3186 FDD Checking of WMM 1st layer WMM-I 52+000 52+100 RHS 10/1/2021 10/2/2021

EPC-06/HW/3187 FDD Checking of WMM 1st layer WMM-I 58+740 58+840 RHS 10/1/2021 10/2/2021

EPC-06/HW/3190 Level & FDD Checking of WMM Top layer WMM-II 52+000 52+100 LHS 10/2/2021 10/3/2021

EPC-06/HW/3191 Level & FDD Checking of WMM Top layer WMM-II 58+740 58+840 LHS 10/2/2021 10/3/2021

EPC-06/HW/3192 Level & FDD Checking of WMM Top layer WMM-II 52+000 52+100 RHS 10/2/2021 10/3/2021

EPC-06/HW/3193 Level & FDD Checking of WMM Top layer WMM-II 58+740 58+840 RHS 10/2/2021 10/3/2021

EPC-06/HW/3194 Applying primer coat Prime coat 52+000 52+100 LHS 10/2/2021 10/3/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3194 Applying primer coat Prime coat 58+740 58+840 LHS 10/2/2021 10/3/2021

EPC-06/HW/3194 Applying primer coat Prime coat 52+000 52+100 RHS 10/2/2021 10/3/2021

EPC-06/HW/3194 Applying primer coat Prime coat 58+740 58+840 RHS 10/2/2021 10/3/2021

EPC-06/HW/3200 Applying tack coat for DBM Tack coat (DBM) 52+000 52+100 LHS 10/3/2021 10/4/2021

EPC-06/HW/3200 Applying tack coat for DBM Tack coat (DBM) 58+740 58+840 LHS 10/3/2021 10/4/2021

EPC-06/HW/3200 Applying tack coat for DBM Tack coat (DBM) 52+000 52+100 RHS 10/3/2021 10/4/2021

EPC-06/HW/3200 Applying tack coat for DBM Tack coat (DBM) 58+740 58+840 RHS 10/3/2021 10/4/2021

EPC-06/HW/3209 Level checking and laying of DBM DBM 52+000 52+100 LHS 10/4/2021 10/5/2021

EPC-06/HW/3209 Level checking and laying of DBM DBM 58+740 58+840 LHS 10/4/2021 10/5/2021

EPC-06/HW/3209 Level checking and laying of DBM DBM 52+000 52+100 RHS 10/4/2021 10/5/2021

EPC-06/HW/3209 Level checking and laying of DBM DBM 58+740 58+840 RHS 10/4/2021 10/5/2021

EPC-06/HW/3210 Applying tack coat for DBM Tack coat (DBM) 47+900 48+970 LHS 10/4/2021 10/5/2021

EPC-06/HW/3210 Applying tack coat for DBM Tack coat (DBM) 49+050 49+500 LHS 10/4/2021 10/5/2021

EPC-06/HW/3212 Level checking and laying of DBM DBM 47+900 48+970 LHS 10/4/2021 10/5/2021

EPC-06/HW/3212 Level checking and laying of DBM DBM 49+050 49+500 LHS 10/4/2021 10/5/2021

EPC-06/HW/3223 Level & FDD Checking For GSB layer GSB 68+780 69+230 RHS 10/9/2021 10/10/2021

EPC-06/HW/3227 Level & FDD Checking of Subgrade Top layer SG Top 44+300 45+200 RHS 10/11/2021 10/12/2021

EPC-06/HW/3230 Level & FDD Checking of Subgrade Top layer SG Top 45+200 46+250 RHS 10/12/2021 10/13/2021

EPC-06/HW/3233 Level & FDD Checking of Subgrade Top layer SG Top 46+320 47+200 RHS 10/13/2021 10/14/2021

EPC-06/HW/3236 Level & FDD Checking of Subgrade Top layer SG Top 47+200 48+100 RHS 10/14/2021 10/15/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3237 Level & FDD Checking For GSB layer GSB 44+300 44+900 RHS 10/14/2021 10/15/2021

EPC-06/HW/3240 Level & FDD Checking of Subgrade Top layer SG Top 48+100 48+970 RHS 10/15/2021 10/16/2021

EPC-06/HW/3241 Level & FDD Checking For GSB layer GSB 44+900 45+600 RHS 10/15/2021 10/16/2021

EPC-06/HW/3242 FDD Checking of WMM 1st layer WMM-I 68+780 69+230 RHS 10/15/2021 10/16/2021

EPC-06/HW/3245 Level & FDD Checking of Subgrade Top layer SG Top 49+050 49+500 RHS 10/16/2021 10/17/2021

EPC-06/HW/3246 Level & FDD Checking For GSB layer GSB 45+600 46+250 RHS 10/16/2021 10/17/2021

EPC-06/HW/3247 Level & FDD Checking of WMM Top layer WMM-II 68+780 69+230 RHS 10/16/2021 10/17/2021

EPC-06/HW/3248 Applying primer coat Prime coat 68+780 69+230 RHS 10/16/2021 10/17/2021

EPC-06/HW/3251 Level & FDD Checking For GSB layer GSB 46+320 47+150 RHS 10/17/2021 10/18/2021

EPC-06/HW/3254 Level & FDD Checking For GSB layer GSB 47+150 47+800 RHS 10/18/2021 10/19/2021

EPC-06/HW/3257 Level & FDD Checking For GSB layer GSB 47+800 48+350 RHS 10/19/2021 10/20/2021

EPC-06/HW/3260 Level & FDD Checking For GSB layer GSB 48+350 48+970 RHS 10/20/2021 10/21/2021

EPC-06/HW/3261 FDD Checking of WMM 1st layer WMM-I 44+300 45+000 RHS 10/20/2021 10/21/2021

EPC-06/HW/3264 Level & FDD Checking For GSB layer GSB 49+050 49+500 RHS 10/21/2021 10/22/2021

EPC-06/HW/3265 FDD Checking of WMM 1st layer WMM-I 45+000 45+700 RHS 10/21/2021 10/22/2021

EPC-06/HW/3266 Level & FDD Checking of WMM Top layer WMM-II 44+300 45+000 RHS 10/21/2021 10/22/2021

EPC-06/HW/3267 Applying primer coat Prime coat 44+300 45+000 RHS 10/21/2021 10/22/2021

EPC-06/HW/3270 FDD Checking of WMM 1st layer WMM-I 45+700 46+250 RHS 10/22/2021 10/23/2021

EPC-06/HW/3271 Level & FDD Checking of WMM Top layer WMM-II 45+000 45+700 RHS 10/22/2021 10/23/2021

EPC-06/HW/3272 Applying primer coat Prime coat 45+000 45+700 RHS 10/22/2021 10/23/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3273 Applying tack coat for DBM Tack coat (DBM) 68+780 69+230 RHS 10/22/2021 10/23/2021

EPC-06/HW/3274 Level checking and laying of DBM DBM 68+780 69+230 RHS 10/22/2021 10/23/2021

EPC-06/HW/3277 FDD Checking of WMM 1st layer WMM-I 46+320 47+100 RHS 10/23/2021 10/24/2021

EPC-06/HW/3278 Level & FDD Checking of WMM Top layer WMM-II 45+700 46+250 RHS 10/23/2021 10/24/2021

EPC-06/HW/3279 Applying primer coat Prime coat 45+700 46+250 RHS 10/23/2021 10/24/2021

EPC-06/HW/3282 FDD Checking of WMM 1st layer WMM-I 47+100 48+000 RHS 10/24/2021 10/25/2021

EPC-06/HW/3283 Level & FDD Checking of WMM Top layer WMM-II 46+320 47+100 RHS 10/24/2021 10/25/2021

EPC-06/HW/3284 Applying primer coat Prime coat 46+320 47+100 RHS 10/24/2021 10/25/2021

EPC-06/HW/3287 Level & FDD Checking of WMM Top layer WMM-II 47+100 48+000 RHS 10/25/2021 10/26/2021

EPC-06/HW/3288 Applying primer coat Prime coat 47+100 48+000 RHS 10/25/2021 10/26/2021

EPC-06/HW/3291 FDD Checking of WMM 1st layer WMM-I 48+000 48+550 RHS 10/26/2021 10/27/2021

EPC-06/HW/3292 Applying tack coat for DBM Tack coat (DBM) 44+300 46+250 RHS 10/26/2021 10/27/2021

EPC-06/HW/3293 Level checking and laying of DBM DBM 44+300 46+250 RHS 10/26/2021 10/27/2021

EPC-06/HW/3296 FDD Checking of WMM 1st layer WMM-I 48+550 48+970 RHS 10/27/2021 10/28/2021

EPC-06/HW/3297 Level & FDD Checking of WMM Top layer WMM-II 48+000 48+550 RHS 10/27/2021 10/28/2021

EPC-06/HW/3298 Applying primer coat Prime coat 48+000 48+550 RHS 10/27/2021 10/28/2021

EPC-06/HW/3301 Level & FDD Checking of Subgrade Top layer SG Top (OL) 54+600 55+150 RHS 10/28/2021 10/29/2021

EPC-06/HW/3302 FDD Checking of WMM 1st layer WMM-I 49+050 49+500 RHS 10/28/2021 10/29/2021

EPC-06/HW/3303 Level & FDD Checking of WMM Top layer WMM-II 48+550 48+970 RHS 10/28/2021 10/29/2021

EPC-06/HW/3304 Applying primer coat Prime coat 48+550 48+970 RHS 10/28/2021 10/29/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3307 Level & FDD Checking of Subgrade Top layer SG Top (OL) 55+150 55+620 RHS 10/29/2021 10/30/2021

EPC-06/HW/3308 Level & FDD Checking of WMM Top layer WMM-II 49+050 49+500 RHS 10/29/2021 10/30/2021

EPC-06/HW/3309 Applying primer coat Prime coat 49+050 49+500 RHS 10/29/2021 10/30/2021

EPC-06/HW/3310 Applying tack coat for DBM Tack coat (DBM) 46+320 48+000 RHS 10/29/2021 10/30/2021

EPC-06/HW/3311 Level checking and laying of DBM DBM 46+320 48+000 RHS 10/29/2021 10/30/2021

EPC-06/HW/3314 Level & FDD Checking of Subgrade Top layer SG Top (OL) 53+000 53+850 RHS 10/30/2021 10/31/2021

EPC-06/HW/3315 Level & FDD Checking For GSB layer GSB (OL) 54+600 55+150 RHS 10/30/2021 10/31/2021

EPC-06/HW/3318 Level & FDD Checking of Subgrade Top layer SG Top (OL) 53+850 54+600 RHS 10/31/2021 11/1/2021

EPC-06/HW/3319 Level & FDD Checking For GSB layer GSB (OL) 55+150 55+620 RHS 10/31/2021 11/1/2021

EPC-06/HW/3320 Applying tack coat for DBM Tack coat (DBM) 48+000 48+970 RHS 10/31/2021 11/1/2021

EPC-06/HW/3320 Applying tack coat for DBM Tack coat (DBM) 49+050 49+500 RHS 10/31/2021 11/1/2021

EPC-06/HW/3322 Level checking and laying of DBM DBM 48+000 48+970 RHS 10/31/2021 11/1/2021

EPC-06/HW/3322 Level checking and laying of DBM DBM 49+050 49+500 RHS 10/31/2021 11/1/2021

EPC-06/HW/3326 Level & FDD Checking For GSB layer GSB (OL) 53+000 53+850 RHS 11/1/2021 11/2/2021

EPC-06/HW/3329 Level & FDD Checking For GSB layer GSB (OL) 53+850 54+600 RHS 11/2/2021 11/3/2021

EPC-06/HW/3334 FDD Checking of WMM 1st layer WMM-I (OL) 54+600 55+150 RHS 11/5/2021 11/6/2021

EPC-06/HW/3337 FDD Checking of WMM 1st layer WMM-I (OL) 55+150 55+620 RHS 11/6/2021 11/7/2021

EPC-06/HW/3338 Level & FDD Checking of WMM Top layer WMM-II (OL) 54+600 55+150 RHS 11/6/2021 11/7/2021

EPC-06/HW/3339 Applying primer coat Prime coat 54+600 55+150 RHS 11/6/2021 11/7/2021

EPC-06/HW/3342 FDD Checking of WMM 1st layer WMM-I (OL) 53+000 53+850 RHS 11/7/2021 11/8/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3343 Level & FDD Checking of WMM Top layer WMM-II (OL) 55+150 55+620 RHS 11/7/2021 11/8/2021

EPC-06/HW/3344 Applying primer coat Prime coat 55+150 55+620 RHS 11/7/2021 11/8/2021

EPC-06/HW/3347 FDD Checking of WMM 1st layer WMM-I (OL) 53+850 54+600 RHS 11/8/2021 11/9/2021

EPC-06/HW/3348 Level & FDD Checking of WMM Top layer WMM-II (OL) 53+000 53+850 RHS 11/8/2021 11/9/2021

EPC-06/HW/3349 Applying primer coat Prime coat 53+000 53+850 RHS 11/8/2021 11/9/2021

EPC-06/HW/3352 Level & FDD Checking of WMM Top layer WMM-II (OL) 53+850 54+600 RHS 11/9/2021 11/10/2021

EPC-06/HW/3353 Applying primer coat Prime coat 53+850 54+600 RHS 11/9/2021 11/10/2021

EPC-06/HW/3358 Level & FDD Checking of Subgrade Top layer SG Top (OL) 54+600 55+100 LHS 11/11/2021 11/12/2021

EPC-06/HW/3361 Level & FDD Checking of Subgrade Top layer SG Top (OL) 55+100 55+620 LHS 11/12/2021 11/13/2021

EPC-06/HW/3362 FDD Checking of WMM 1st layer WMM-I (OL) 61+000 61+110 LHS 11/12/2021 11/13/2021

EPC-06/HW/3363 FDD Checking of WMM 1st layer WMM-I (OL) 62+130 62+900 LHS 11/12/2021 11/13/2021

EPC-06/HW/3366 Level & FDD Checking of Subgrade Top layer SG Top (OL) 53+000 53+800 LHS 11/13/2021 11/14/2021

EPC-06/HW/3367 Level & FDD Checking For GSB layer GSB (OL) 54+600 55+100 LHS 11/13/2021 11/14/2021

EPC-06/HW/3368 FDD Checking of WMM 1st layer WMM-I (OL) 62+900 63+550 LHS 11/13/2021 11/14/2021

EPC-06/HW/3369 FDD Checking of WMM 1st layer WMM-I (OL) 63+950 64+000 LHS 11/13/2021 11/14/2021

EPC-06/HW/3370 Level & FDD Checking of WMM Top layer WMM-II (OL) 61+000 61+110 LHS 11/13/2021 11/14/2021

EPC-06/HW/3371 Level & FDD Checking of WMM Top layer WMM-II (OL) 62+130 62+900 LHS 11/13/2021 11/14/2021

EPC-06/HW/3372 Applying primer coat Prime coat 61+000 61+110 LHS 11/13/2021 11/14/2021

EPC-06/HW/3372 Applying primer coat Prime coat 62+130 62+900 LHS 11/13/2021 11/14/2021

EPC-06/HW/3376 Level & FDD Checking of Subgrade Top layer SG Top (OL) 53+800 54+600 LHS 11/14/2021 11/15/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3377 Level & FDD Checking For GSB layer GSB (OL) 55+100 55+620 LHS 11/14/2021 11/15/2021

EPC-06/HW/3378 Level & FDD Checking of WMM Top layer WMM-II (OL) 62+900 63+550 LHS 11/14/2021 11/15/2021

EPC-06/HW/3379 Level & FDD Checking of WMM Top layer WMM-II (OL) 63+950 64+000 LHS 11/14/2021 11/15/2021

EPC-06/HW/3380 Applying primer coat Prime coat 62+900 63+550 LHS 11/14/2021 11/15/2021

EPC-06/HW/3380 Applying primer coat Prime coat 63+950 64+000 LHS 11/14/2021 11/15/2021

EPC-06/HW/3384 Level & FDD Checking For GSB layer GSB (OL) 53+000 53+800 LHS 11/15/2021 11/16/2021

EPC-06/HW/3387 Level & FDD Checking For GSB layer GSB (OL) 53+800 54+600 LHS 11/16/2021 11/17/2021

EPC-06/HW/3388 Level and FDD checking of DLC layer DLC 68+080 68+300 RHS 11/16/2021 11/17/2021

EPC-06/HW/3393 Dismantling of existing BT surface BT Scr 61+110 61+550 BHS 11/19/2021 11/20/2021

EPC-06/HW/3394 Dismantling of existing BT surface BT Scr 63+550 63+950 BHS 11/19/2021 11/20/2021

EPC-06/HW/3395 FDD Checking of WMM 1st layer WMM-I (OL) 54+600 55+100 LHS 11/19/2021 11/20/2021

EPC-06/HW/3398 FDD Checking of WMM 1st layer WMM-I (OL) 55+100 55+620 LHS 11/20/2021 11/21/2021

EPC-06/HW/3399 Level & FDD Checking of WMM Top layer WMM-II (OL) 54+600 55+100 LHS 11/20/2021 11/21/2021

EPC-06/HW/3400 Applying primer coat Prime coat 54+600 55+100 LHS 11/20/2021 11/21/2021

EPC-06/HW/3401 FDD Checking of Subgrade Top layer on Minor Junction SG Top 53+845 LHS 11/20/2021 11/21/2021

EPC-06/HW/3404 FDD Checking of WMM 1st layer WMM-I (OL) 53+000 53+800 LHS 11/21/2021 11/22/2021

EPC-06/HW/3405 Level & FDD Checking of WMM Top layer WMM-II (OL) 55+100 55+620 LHS 11/21/2021 11/22/2021

EPC-06/HW/3406 Applying primer coat Prime coat 55+100 55+620 LHS 11/21/2021 11/22/2021

EPC-06/HW/3407 FDD Checking For GSB layer on Minor Junction GSB 53+845 LHS 11/21/2021 11/22/2021

EPC-06/HW/3410 Applying tack coat for BM Tack coat (BM) 54+600 55+620 LHS 11/22/2021 11/23/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3411 Level checking and laying of BM BM 54+600 55+620 LHS 11/22/2021 11/23/2021

EPC-06/HW/3412 FDD Checking of WMM 1st layer WMM-I (OL) 53+800 54+600 LHS 11/22/2021 11/23/2021

EPC-06/HW/3413 Level & FDD Checking of WMM Top layer WMM-II (OL) 53+000 53+800 LHS 11/22/2021 11/23/2021

EPC-06/HW/3414 Applying primer coat Prime coat 53+000 53+800 LHS 11/22/2021 11/23/2021

EPC-06/HW/3417 Level & FDD Checking of Subgrade Top layer SG Top 61+110 61+550 LHS 11/23/2021 11/24/2021

EPC-06/HW/3418 Level & FDD Checking of Subgrade Top layer SG Top (OL) 02+700 03+550 LHS 11/23/2021 11/24/2021

EPC-06/HW/3419 Applying tack coat for BM Tack coat (BM) 53+000 54+600 LHS 11/23/2021 11/24/2021

EPC-06/HW/3420 Level checking and laying of BM BM 53+000 54+600 LHS 11/23/2021 11/24/2021

EPC-06/HW/3421 Level & FDD Checking of WMM Top layer WMM-II (OL) 53+800 54+600 LHS 11/23/2021 11/24/2021

EPC-06/HW/3422 Applying primer coat Prime coat 53+800 54+600 LHS 11/23/2021 11/24/2021

EPC-06/HW/3425 Level & FDD Checking of Subgrade Top layer SG Top 63+550 63+950 LHS 11/24/2021 11/25/2021

EPC-06/HW/3426 Level & FDD Checking of Subgrade Top layer SG Top (OL) 03+550 04+300 LHS 11/24/2021 11/25/2021

EPC-06/HW/3427 Applying tack coat for DBM Tack coat (DBM) (OL) 54+600 55+620 LHS 11/24/2021 11/25/2021

EPC-06/HW/3428 Level checking and laying of DBM DBM (OL) 54+600 55+620 LHS 11/24/2021 11/25/2021

EPC-06/HW/3429 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+080 68+300 RHS 11/24/2021 11/25/2021

EPC-06/HW/3430 FDD Checking of WMM Top layer on Minor Junction WMM-II 53+845 LHS 11/24/2021 11/25/2021

EPC-06/HW/3431 Applying primer coat on Minor Junction Prime coat 53+845 LHS 11/24/2021 11/25/2021

EPC-06/HW/3434 Level & FDD Checking of Subgrade Top layer SG Top (OL) 61+000 61+110 RHS 11/25/2021 11/26/2021

EPC-06/HW/3435 Level & FDD Checking of Subgrade Top layer SG Top (OL) 62+130 62+900 RHS 11/25/2021 11/26/2021

EPC-06/HW/3436 Level & FDD Checking of Subgrade Top layer SG Top (OL) 04+300 05+000 LHS 11/25/2021 11/26/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3437 Level & FDD Checking For GSB layer GSB 61+110 61+550 LHS 11/25/2021 11/26/2021

EPC-06/HW/3438 Level & FDD Checking For GSB layer GSB (OL) 02+700 03+550 LHS 11/25/2021 11/26/2021

EPC-06/HW/3439 Applying tack coat for DBM Tack coat (DBM) (OL) 53+000 54+600 LHS 11/25/2021 11/26/2021

EPC-06/HW/3440 Level checking and laying of DBM DBM (OL) 53+000 54+600 LHS 11/25/2021 11/26/2021

EPC-06/HW/3441 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 53+845 LHS 11/25/2021 11/26/2021

EPC-06/HW/3442 Laying of DBM on Minor Junction DBM 53+845 LHS 11/25/2021 11/26/2021

EPC-06/HW/3445 Level & FDD Checking of Subgrade Top layer SG Top (OL) 62+900 63+550 RHS 11/26/2021 11/27/2021

EPC-06/HW/3446 Level & FDD Checking of Subgrade Top layer SG Top (OL) 63+950 64+000 RHS 11/26/2021 11/27/2021

EPC-06/HW/3447 Level & FDD Checking of Subgrade Top layer SG Top (OL) 05+000 05+750 LHS 11/26/2021 11/27/2021

EPC-06/HW/3448 Level & FDD Checking For GSB layer GSB 63+550 63+950 LHS 11/26/2021 11/27/2021

EPC-06/HW/3449 Level & FDD Checking For GSB layer GSB (OL) 03+550 04+200 LHS 11/26/2021 11/27/2021

EPC-06/HW/3450 Applying tack coat for BM Tack coat (BM) 54+600 55+620 RHS 11/26/2021 11/27/2021

EPC-06/HW/3451 Level checking and laying of BM BM 54+600 55+620 RHS 11/26/2021 11/27/2021

EPC-06/HW/3452 Level checking and laying of PQC (Paved shoulder Portion) PQC (PS) 68+080 68+300 RHS 11/26/2021 11/27/2021

EPC-06/HW/3455 Level & FDD Checking of Subgrade Top layer SG Top (OL) 05+750 06+500 LHS 11/27/2021 11/28/2021

EPC-06/HW/3456 Level & FDD Checking For GSB layer GSB (OL) 61+000 61+110 RHS 11/27/2021 11/28/2021

EPC-06/HW/3457 Level & FDD Checking For GSB layer GSB (OL) 62+130 62+850 RHS 11/27/2021 11/28/2021

EPC-06/HW/3458 Level & FDD Checking For GSB layer GSB (OL) 04+200 04+850 LHS 11/27/2021 11/28/2021

EPC-06/HW/3459 Applying tack coat for BM Tack coat (BM) 53+000 54+600 RHS 11/27/2021 11/28/2021

EPC-06/HW/3460 Level checking and laying of BM BM 53+000 54+600 RHS 11/27/2021 11/28/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3463 Level & FDD Checking For GSB layer GSB (OL) 62+850 63+550 RHS 11/28/2021 11/29/2021

EPC-06/HW/3464 Level & FDD Checking For GSB layer GSB (OL) 63+950 64+000 RHS 11/28/2021 11/29/2021

EPC-06/HW/3465 Level & FDD Checking For GSB layer GSB (OL) 04+850 05+700 LHS 11/28/2021 11/29/2021

EPC-06/HW/3466 Applying tack coat for DBM Tack coat (DBM) (OL) 54+600 55+620 RHS 11/28/2021 11/29/2021

EPC-06/HW/3467 Level checking and laying of DBM DBM (OL) 54+600 55+620 RHS 11/28/2021 11/29/2021

EPC-06/HW/3470 Level & FDD Checking For GSB layer GSB (OL) 05+700 06+500 LHS 11/29/2021 11/30/2021

EPC-06/HW/3471 Applying tack coat for DBM Tack coat (DBM) (OL) 53+000 54+600 RHS 11/29/2021 11/30/2021

EPC-06/HW/3472 Level checking and laying of DBM DBM (OL) 53+000 54+600 RHS 11/29/2021 11/30/2021

EPC-06/HW/3476 FDD Checking of WMM 1st layer WMM-I (OL) 02+700 03+500 LHS 12/1/2021 12/2/2021

EPC-06/HW/3477 FDD Checking of Subgrade Top layer on Minor Junction SG Top 62+545 RHS 12/1/2021 12/2/2021

EPC-06/HW/3478 Level & FDD Checking of Subgrade Top layer SG Top 48+970 49+050 BHS 12/1/2021 12/2/2021

EPC-06/HW/3479 Level & FDD Checking of Subgrade Top layer SG Top 49+900 50+050 BHS 12/1/2021 12/2/2021

EPC-06/HW/3480 FDD Checking of WMM 1st layer WMM-I 61+110 61+550 LHS 12/2/2021 12/3/2021

EPC-06/HW/3481 FDD Checking of WMM 1st layer WMM-I (OL) 61+000 61+110 RHS 12/2/2021 12/3/2021

EPC-06/HW/3482 FDD Checking of WMM 1st layer WMM-I (OL) 62+130 62+800 RHS 12/2/2021 12/3/2021

EPC-06/HW/3483 FDD Checking of WMM 1st layer WMM-I (OL) 03+500 04+200 LHS 12/2/2021 12/3/2021

EPC-06/HW/3484 Level & FDD Checking of WMM Top layer WMM-II (OL) 02+700 03+500 LHS 12/2/2021 12/3/2021

EPC-06/HW/3485 Applying primer coat Prime coat 02+700 03+500 LHS 12/2/2021 12/3/2021

EPC-06/HW/3486 FDD Checking For GSB layer on Minor Junction GSB 62+545 RHS 12/2/2021 12/3/2021

EPC-06/HW/3487 Level & FDD Checking For GSB layer GSB 48+970 49+050 BHS 12/2/2021 12/3/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3488 Level & FDD Checking For GSB layer GSB 49+900 50+050 BHS 12/2/2021 12/3/2021

EPC-06/HW/3489 Level & FDD Checking of Subgrade Top layer SG Top 61+110 61+550 RHS 12/3/2021 12/4/2021

EPC-06/HW/3490 FDD Checking of WMM 1st layer WMM-I 63+550 63+950 LHS 12/3/2021 12/4/2021

EPC-06/HW/3491 FDD Checking of WMM 1st layer WMM-I (OL) 62+800 63+550 RHS 12/3/2021 12/4/2021

EPC-06/HW/3492 FDD Checking of WMM 1st layer WMM-I (OL) 63+950 64+000 RHS 12/3/2021 12/4/2021

EPC-06/HW/3493 FDD Checking of WMM 1st layer WMM-I (OL) 04+200 04+800 LHS 12/3/2021 12/4/2021

EPC-06/HW/3494 Level & FDD Checking of WMM Top layer WMM-II 61+110 61+550 LHS 12/3/2021 12/4/2021

EPC-06/HW/3495 Level & FDD Checking of WMM Top layer WMM-II (OL) 61+000 61+110 RHS 12/3/2021 12/4/2021

EPC-06/HW/3496 Level & FDD Checking of WMM Top layer WMM-II (OL) 62+130 62+800 RHS 12/3/2021 12/4/2021

EPC-06/HW/3497 Level & FDD Checking of WMM Top layer WMM-II (OL) 03+500 04+200 LHS 12/3/2021 12/4/2021

EPC-06/HW/3498 Applying primer coat Prime coat 61+110 61+550 LHS 12/3/2021 12/4/2021

EPC-06/HW/3498 Applying primer coat Prime coat 61+000 61+110 RHS 12/3/2021 12/4/2021

EPC-06/HW/3498 Applying primer coat Prime coat 62+130 62+800 RHS 12/3/2021 12/4/2021

EPC-06/HW/3498 Applying primer coat Prime coat 03+500 04+200 LHS 12/3/2021 12/4/2021

EPC-06/HW/3499 FDD Checking of WMM 1st layer WMM-I 48+970 49+050 BHS 12/3/2021 12/4/2021

EPC-06/HW/3500 FDD Checking of WMM 1st layer WMM-I 49+900 50+050 BHS 12/3/2021 12/4/2021

EPC-06/HW/3504 Level & FDD Checking of Subgrade Top layer SG Top 63+550 63+950 RHS 12/4/2021 12/5/2021

EPC-06/HW/3505 Applying tack coat for BM Tack coat (BM) 61+000 61+110 RHS 12/4/2021 12/5/2021

EPC-06/HW/3505 Applying tack coat for BM Tack coat (BM) 62+130 63+550 RHS 12/4/2021 12/5/2021

EPC-06/HW/3505 Applying tack coat for BM Tack coat (BM) 63+950 64+000 RHS 12/4/2021 12/5/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3508 Level checking and laying of BM BM 61+000 61+110 RHS 12/4/2021 12/5/2021

EPC-06/HW/3508 Level checking and laying of BM BM 62+130 63+550 RHS 12/4/2021 12/5/2021

EPC-06/HW/3508 Level checking and laying of BM BM 63+950 64+000 RHS 12/4/2021 12/5/2021

EPC-06/HW/3511 FDD Checking of WMM 1st layer WMM-I (OL) 04+800 05+600 LHS 12/4/2021 12/5/2021

EPC-06/HW/3512 Level & FDD Checking of WMM Top layer WMM-II 63+550 63+950 LHS 12/4/2021 12/5/2021

EPC-06/HW/3513 Level & FDD Checking of WMM Top layer WMM-II (OL) 62+800 63+550 RHS 12/4/2021 12/5/2021

EPC-06/HW/3514 Level & FDD Checking of WMM Top layer WMM-II (OL) 63+950 64+000 RHS 12/4/2021 12/5/2021

EPC-06/HW/3515 Level & FDD Checking of WMM Top layer WMM-II (OL) 04+200 04+800 LHS 12/4/2021 12/5/2021

EPC-06/HW/3516 Applying primer coat Prime coat 63+550 63+950 LHS 12/4/2021 12/5/2021

EPC-06/HW/3516 Applying primer coat Prime coat 62+800 63+550 RHS 12/4/2021 12/5/2021

EPC-06/HW/3516 Applying primer coat Prime coat 63+950 64+000 RHS 12/4/2021 12/5/2021

EPC-06/HW/3516 Applying primer coat Prime coat 04+200 04+800 LHS 12/4/2021 12/5/2021

EPC-06/HW/3517 Level & FDD Checking of WMM Top layer WMM-II 48+970 49+050 BHS 12/4/2021 12/5/2021

EPC-06/HW/3518 Level & FDD Checking of WMM Top layer WMM-II 49+900 50+050 BHS 12/4/2021 12/5/2021

EPC-06/HW/3522 Level & FDD Checking For GSB layer GSB 61+110 61+550 RHS 12/5/2021 12/6/2021

EPC-06/HW/3523 FDD Checking of WMM 1st layer WMM-I (OL) 05+600 06+500 LHS 12/5/2021 12/6/2021

EPC-06/HW/3524 Level & FDD Checking of WMM Top layer WMM-II (OL) 04+800 05+600 LHS 12/5/2021 12/6/2021

EPC-06/HW/3525 Applying primer coat Prime coat 04+800 05+600 LHS 12/5/2021 12/6/2021

EPC-06/HW/3526 FDD Checking of WMM Top layer on Minor Junction WMM-II 62+545 RHS 12/5/2021 12/6/2021

EPC-06/HW/3527 Applying primer coat on Minor Junction Prime coat 62+545 RHS 12/5/2021 12/6/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3528 Applying primer coat Prime coat 48+970 49+050 BHS 12/5/2021 12/6/2021

EPC-06/HW/3529 Applying primer coat Prime coat 49+900 50+050 BHS 12/5/2021 12/6/2021

EPC-06/HW/3530 Level & FDD Checking For GSB layer GSB 63+550 63+950 RHS 12/6/2021 12/7/2021

EPC-06/HW/3531 Level & FDD Checking of WMM Top layer WMM-II (OL) 05+600 06+500 LHS 12/6/2021 12/7/2021

EPC-06/HW/3532 Applying primer coat Prime coat 05+600 06+500 LHS 12/6/2021 12/7/2021

EPC-06/HW/3533 Applying tack coat for DBM Tack coat (DBM) 61+110 61+550 RHS 12/6/2021 12/7/2021

EPC-06/HW/3533 Applying tack coat for DBM Tack coat (DBM) 63+550 63+950 RHS 12/6/2021 12/7/2021

EPC-06/HW/3535 Applying tack coat for DBM Tack coat (DBM) (OL) 61+000 61+110 RHS 12/6/2021 12/7/2021

EPC-06/HW/3535 Applying tack coat for DBM Tack coat (DBM) (OL) 62+130 63+550 RHS 12/6/2021 12/7/2021

EPC-06/HW/3535 Applying tack coat for DBM Tack coat (DBM) (OL) 63+950 64+000 RHS 12/6/2021 12/7/2021

EPC-06/HW/3538 Level checking and laying of DBM DBM 61+110 61+550 RHS 12/6/2021 12/7/2021

EPC-06/HW/3538 Level checking and laying of DBM DBM 63+550 63+950 RHS 12/6/2021 12/7/2021

EPC-06/HW/3540 Level checking and laying of DBM DBM (OL) 61+000 61+110 RHS 12/6/2021 12/7/2021

EPC-06/HW/3540 Level checking and laying of DBM DBM (OL) 62+130 63+550 RHS 12/6/2021 12/7/2021

EPC-06/HW/3540 Level checking and laying of DBM DBM (OL) 63+950 64+000 RHS 12/6/2021 12/7/2021

EPC-06/HW/3543 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 62+545 RHS 12/6/2021 12/7/2021

EPC-06/HW/3544 Laying of DBM on Minor Junction DBM 62+545 RHS 12/6/2021 12/7/2021

EPC-06/HW/3545 Applying tack coat for DBM Tack coat (DBM) 48+970 49+050 BHS 12/6/2021 12/7/2021

EPC-06/HW/3545 Applying tack coat for DBM Tack coat (DBM) 49+900 50+050 BHS 12/6/2021 12/7/2021

EPC-06/HW/3546 Level checking and laying of DBM DBM 48+970 49+050 BHS 12/6/2021 12/7/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3546 Level checking and laying of DBM DBM 49+900 50+050 BHS 12/6/2021 12/7/2021

EPC-06/HW/3547 Level & FDD Checking of Subgrade Top layer SG Top (OL) 61+000 61+110 LHS 12/7/2021 12/8/2021

EPC-06/HW/3548 Level & FDD Checking of Subgrade Top layer SG Top (OL) 62+130 62+800 LHS 12/7/2021 12/8/2021

EPC-06/HW/3549 Level & FDD Checking of Subgrade Top layer SG Top (OL) 02+700 03+450 RHS 12/7/2021 12/8/2021

EPC-06/HW/3552 Level & FDD Checking of Subgrade Top layer SG Top (OL) 62+800 63+550 LHS 12/8/2021 12/9/2021

EPC-06/HW/3553 Level & FDD Checking of Subgrade Top layer SG Top (OL) 63+950 64+000 LHS 12/8/2021 12/9/2021

EPC-06/HW/3554 Level & FDD Checking of Subgrade Top layer SG Top (OL) 03+450 04+200 RHS 12/8/2021 12/9/2021

EPC-06/HW/3557 Level & FDD Checking of Subgrade Top layer SG Top (OL) 04+200 04+800 RHS 12/9/2021 12/10/2021

EPC-06/HW/3558 Level & FDD Checking For GSB layer GSB (OL) 61+000 61+110 LHS 12/9/2021 12/10/2021

EPC-06/HW/3559 Level & FDD Checking For GSB layer GSB (OL) 62+130 62+800 LHS 12/9/2021 12/10/2021

EPC-06/HW/3560 Level & FDD Checking For GSB layer GSB (OL) 02+700 03+450 RHS 12/9/2021 12/10/2021

EPC-06/HW/3563 Level & FDD Checking of Subgrade Top layer SG Top (OL) 04+800 05+700 RHS 12/10/2021 12/11/2021

EPC-06/HW/3564 Level & FDD Checking For GSB layer GSB (OL) 62+800 63+550 LHS 12/10/2021 12/11/2021

EPC-06/HW/3565 Level & FDD Checking For GSB layer GSB (OL) 63+950 64+000 LHS 12/10/2021 12/11/2021

EPC-06/HW/3566 Level & FDD Checking For GSB layer GSB (OL) 03+450 04+200 RHS 12/10/2021 12/11/2021

EPC-06/HW/3569 Level & FDD Checking of Subgrade Top layer SG Top (OL) 05+700 06+500 RHS 12/11/2021 12/12/2021

EPC-06/HW/3570 Level & FDD Checking For GSB layer GSB (OL) 04+200 04+800 RHS 12/11/2021 12/12/2021

EPC-06/HW/3573 Level & FDD Checking of Subgrade Top layer SG Top (OL) 00+000 00+950 RHS 12/12/2021 12/13/2021

EPC-06/HW/3574 Level & FDD Checking For GSB layer GSB (OL) 04+800 05+600 RHS 12/12/2021 12/13/2021

EPC-06/HW/3575 FDD Checking of WMM 1st layer WMM-I 61+110 61+550 RHS 12/12/2021 12/13/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3578 Level & FDD Checking of Subgrade Top layer SG Top (OL) 00+950 01+950 RHS 12/13/2021 12/14/2021

EPC-06/HW/3579 Level & FDD Checking For GSB layer GSB (OL) 05+600 06+500 RHS 12/13/2021 12/14/2021

EPC-06/HW/3580 FDD Checking of WMM 1st layer WMM-I 63+550 63+950 RHS 12/13/2021 12/14/2021

EPC-06/HW/3581 Level & FDD Checking of WMM Top layer WMM-II 61+110 61+550 RHS 12/13/2021 12/14/2021

EPC-06/HW/3582 Applying primer coat Prime coat 61+110 61+550 RHS 12/13/2021 12/14/2021

EPC-06/HW/3585 Level & FDD Checking For GSB layer GSB (OL) 00+000 01+000 RHS 12/14/2021 12/15/2021

EPC-06/HW/3586 Applying tack coat for BM Tack coat (BM) 61+000 61+110 LHS 12/14/2021 12/15/2021

EPC-06/HW/3586 Applying tack coat for BM Tack coat (BM) 02+700 06+500 LHS 12/14/2021 12/15/2021

EPC-06/HW/3587 Level checking and laying of BM BM 61+000 61+110 LHS 12/14/2021 12/15/2021

EPC-06/HW/3587 Level checking and laying of BM BM 02+700 06+500 LHS 12/14/2021 12/15/2021

EPC-06/HW/3588 Level & FDD Checking of WMM Top layer WMM-II 63+550 63+950 RHS 12/14/2021 12/15/2021

EPC-06/HW/3589 Applying primer coat Prime coat 63+550 63+950 RHS 12/14/2021 12/15/2021

EPC-06/HW/3592 Level & FDD Checking For GSB layer GSB (OL) 01+000 01+950 RHS 12/15/2021 12/16/2021

EPC-06/HW/3593 Applying tack coat for BM Tack coat (BM) 62+130 63+550 LHS 12/15/2021 12/16/2021

EPC-06/HW/3593 Applying tack coat for BM Tack coat (BM) 63+950 64+000 LHS 12/15/2021 12/16/2021

EPC-06/HW/3595 Level checking and laying of BM BM 62+130 63+550 LHS 12/15/2021 12/16/2021

EPC-06/HW/3595 Level checking and laying of BM BM 63+950 64+000 LHS 12/15/2021 12/16/2021

EPC-06/HW/3597 FDD Checking of WMM 1st layer WMM-I (OL) 02+700 03+400 RHS 12/15/2021 12/16/2021

EPC-06/HW/3599 FDD Checking of WMM 1st layer WMM-I (OL) 00+000 00+900 RHS 12/16/2021 12/17/2021

EPC-06/HW/3600 FDD Checking of WMM 1st layer WMM-I (OL) 03+400 04+150 RHS 12/16/2021 12/17/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3601 Level & FDD Checking of WMM Top layer WMM-II (OL) 02+700 03+400 RHS 12/16/2021 12/17/2021

EPC-06/HW/3602 Applying primer coat Prime coat 02+700 03+400 RHS 12/16/2021 12/17/2021

EPC-06/HW/3603 Applying tack coat for DBM Tack coat (DBM) 61+110 61+550 LHS 12/16/2021 12/17/2021

EPC-06/HW/3604 Applying tack coat for DBM Tack coat (DBM) (OL) 61+000 61+110 LHS 12/16/2021 12/17/2021

EPC-06/HW/3605 Applying tack coat for DBM Tack coat (DBM) (OL) 02+700 04+500 LHS 12/16/2021 12/17/2021

EPC-06/HW/3606 Level checking and laying of DBM DBM (OL) 02+700 04+500 LHS 12/16/2021 12/17/2021

EPC-06/HW/3609 FDD Checking of WMM 1st layer WMM-I (OL) 04+150 04+800 RHS 12/17/2021 12/18/2021

EPC-06/HW/3610 Level & FDD Checking of WMM Top layer WMM-II (OL) 03+400 04+150 RHS 12/17/2021 12/18/2021

EPC-06/HW/3611 Applying primer coat Prime coat 03+400 04+150 RHS 12/17/2021 12/18/2021

EPC-06/HW/3612 Applying tack coat for DBM Tack coat (DBM) 63+550 63+950 LHS 12/17/2021 12/18/2021

EPC-06/HW/3613 Applying tack coat for DBM Tack coat (DBM) (OL) 62+130 63+550 LHS 12/17/2021 12/18/2021

EPC-06/HW/3613 Applying tack coat for DBM Tack coat (DBM) (OL) 63+950 64+000 LHS 12/17/2021 12/18/2021

EPC-06/HW/3615 Level checking and laying of DBM DBM 61+110 61+550 LHS 12/17/2021 12/18/2021

EPC-06/HW/3615 Level checking and laying of DBM DBM 63+550 63+950 LHS 12/17/2021 12/18/2021

EPC-06/HW/3616 Level checking and laying of DBM DBM (OL) 61+000 61+110 LHS 12/17/2021 12/18/2021

EPC-06/HW/3616 Level checking and laying of DBM DBM (OL) 62+130 63+550 LHS 12/17/2021 12/18/2021

EPC-06/HW/3616 Level checking and laying of DBM DBM (OL) 63+950 64+000 LHS 12/17/2021 12/18/2021

EPC-06/HW/3617 FDD Checking of WMM 1st layer WMM-I (OL) 00+900 01+950 RHS 12/17/2021 12/18/2021

EPC-06/HW/3619 Level & FDD Checking of WMM Top layer WMM-II (OL) 00+000 00+900 RHS 12/18/2021 12/19/2021

EPC-06/HW/3620 Applying tack coat for BM Tack coat (BM) 02+700 04+600 RHS 12/18/2021 12/19/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3621 Level checking and laying of BM BM 02+700 04+600 RHS 12/18/2021 12/19/2021

EPC-06/HW/3622 FDD Checking of WMM 1st layer WMM-I (OL) 04+800 05+650 RHS 12/18/2021 12/19/2021

EPC-06/HW/3623 Level & FDD Checking of WMM Top layer WMM-II (OL) 04+150 04+800 RHS 12/18/2021 12/19/2021

EPC-06/HW/3624 Applying primer coat Prime coat 04+150 04+800 RHS 12/18/2021 12/19/2021

EPC-06/HW/3625 Applying tack coat for DBM Tack coat (DBM) (OL) 04+500 06+500 LHS 12/18/2021 12/19/2021

EPC-06/HW/3626 Level checking and laying of DBM DBM (OL) 04+500 06+500 LHS 12/18/2021 12/19/2021

EPC-06/HW/3627 Applying tack coat for BM Tack coat (BM) 04+600 06+500 RHS 12/19/2021 12/20/2021

EPC-06/HW/3628 Level checking and laying of BM BM 04+600 06+500 RHS 12/19/2021 12/20/2021

EPC-06/HW/3629 FDD Checking of WMM 1st layer WMM-I (OL) 05+650 06+500 RHS 12/19/2021 12/20/2021

EPC-06/HW/3630 Level & FDD Checking of WMM Top layer WMM-II (OL) 04+800 05+650 RHS 12/19/2021 12/20/2021

EPC-06/HW/3631 Applying primer coat Prime coat 04+800 05+650 RHS 12/19/2021 12/20/2021

EPC-06/HW/3632 Level & FDD Checking of WMM Top layer WMM-II (OL) 00+900 01+950 RHS 12/19/2021 12/20/2021

EPC-06/HW/3634 Level & FDD Checking of WMM Top layer WMM-II (OL) 05+650 06+500 RHS 12/20/2021 12/21/2021

EPC-06/HW/3635 Applying primer coat Prime coat 05+650 06+500 RHS 12/20/2021 12/21/2021

EPC-06/HW/3636 Applying tack coat for DBM Tack coat (DBM) (OL) 02+700 04+600 RHS 12/20/2021 12/21/2021

EPC-06/HW/3637 Level checking and laying of DBM DBM (OL) 02+700 04+600 RHS 12/20/2021 12/21/2021

EPC-06/HW/3640 Applying tack coat for DBM Tack coat (DBM) (OL) 04+600 06+500 RHS 12/21/2021 12/22/2021

EPC-06/HW/3641 Level checking and laying of DBM DBM (OL) 04+600 06+500 RHS 12/21/2021 12/22/2021

EPC-06/HW/3670 FDD Checking of Subgrade Top layer on Minor Junction SG Top 01+587 LHS 12/28/2021 12/29/2021
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3671 FDD Checking of Subgrade Top layer on Minor Junction SG Top 68+740 LHS 12/28/2021 12/29/2021

EPC-06/HW/3675 FDD Checking For GSB layer on Minor Junction GSB 01+587 LHS 12/29/2021 12/30/2021

EPC-06/HW/3676 FDD Checking For GSB layer on Minor Junction GSB 68+740 LHS 12/29/2021 12/30/2021

EPC-06/HW/3680 Applying primer coat Prime coat (OL) 00+000 01+950 RHS 12/30/2021 12/31/2021

EPC-06/HW/3681 FDD Checking of WMM Top layer on Minor Junction WMM-II 01+587 LHS 12/30/2021 12/31/2021

EPC-06/HW/3682 Applying primer coat on Minor Junction Prime coat 01+587 LHS 12/30/2021 12/31/2021

EPC-06/HW/3683 FDD Checking of WMM Top layer on Minor Junction WMM-II 68+740 LHS 12/30/2021 12/31/2021

EPC-06/HW/3684 Applying primer coat on Minor Junction Prime coat 68+740 LHS 12/30/2021 12/31/2021

EPC-06/HW/3688 Applying tack coat for DBM Tack coat (DBM) (OL) 00+000 01+950 RHS 12/31/2021 1/1/2022

EPC-06/HW/3689 Level checking and laying of DBM DBM (OL) 00+000 01+950 RHS 12/31/2021 1/1/2022

EPC-06/HW/3690 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 01+587 LHS 12/31/2021 1/1/2022

EPC-06/HW/3691 Laying of DBM on Minor Junction DBM 01+587 LHS 12/31/2021 1/1/2022

EPC-06/HW/3692 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 68+740 LHS 12/31/2021 1/1/2022

EPC-06/HW/3693 Laying of DBM on Minor Junction DBM 68+740 LHS 12/31/2021 1/1/2022

EPC-06/HW/3703 Level & FDD Checking of Subgrade Top layer SG Top (OL) 00+000 01+950 LHS 1/3/2022 1/4/2022

EPC-06/HW/3704 Level & FDD Checking of Subgrade Top layer SG Top (OL) 06+500 06+560 BHS 1/3/2022 1/4/2022

EPC-06/HW/3714 Level & FDD Checking For GSB layer GSB (OL) 00+000 01+950 LHS 1/7/2022 1/8/2022

EPC-06/HW/3715 Level & FDD Checking For GSB layer GSB (OL) 06+500 06+560 BHS 1/7/2022 1/8/2022

EPC-06/HW/3723 FDD Checking of WMM 1st layer WMM-I (OL) 00+000 01+950 LHS 1/9/2022 1/10/2022

EPC-06/HW/3724 FDD Checking of WMM 1st layer WMM-I (OL) 06+500 06+560 BHS 1/9/2022 1/10/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3728 FDD Checking of Subgrade Top layer on Major Junction SG Top 03+185 LHS 1/10/2022 1/11/2022

EPC-06/HW/3729 FDD Checking of Subgrade Top layer on Major Junction SG Top 05+710 RHS 1/10/2022 1/11/2022

EPC-06/HW/3730 FDD Checking of Subgrade Top layer on Major Junction SG Top 82+130 LHS 1/10/2022 1/11/2022

EPC-06/HW/3734 Level & FDD Checking of WMM Top layer WMM-II (OL) 00+000 01+950 LHS 1/11/2022 1/12/2022

EPC-06/HW/3735 Level & FDD Checking of WMM Top layer WMM-II (OL) 06+500 06+560 BHS 1/11/2022 1/12/2022

EPC-06/HW/3736 FDD Checking For GSB layer on Major Junction GSB 03+185 LHS 1/11/2022 1/12/2022

EPC-06/HW/3737 FDD Checking For GSB layer on Major Junction GSB 05+710 RHS 1/11/2022 1/12/2022

EPC-06/HW/3738 FDD Checking For GSB layer on Major Junction GSB 82+130 LHS 1/11/2022 1/12/2022

EPC-06/HW/3742 Applying primer coat Prime coat (OL) 00+000 01+950 LHS 1/12/2022 1/13/2022

EPC-06/HW/3743 Applying primer coat Prime coat (OL) 06+500 06+560 BHS 1/12/2022 1/13/2022

EPC-06/HW/3744 FDD Checking of WMM Top layer on Major Junction WMM-II 03+185 LHS 1/12/2022 1/13/2022

EPC-06/HW/3745 Applying primer coat on Major Junction Prime coat 03+185 LHS 1/12/2022 1/13/2022

EPC-06/HW/3746 FDD Checking of WMM Top layer on Major Junction WMM-II 05+710 RHS 1/12/2022 1/13/2022

EPC-06/HW/3747 Applying primer coat on Major Junction Prime coat 05+710 RHS 1/12/2022 1/13/2022

EPC-06/HW/3748 FDD Checking of WMM Top layer on Major Junction WMM-II 82+130 LHS 1/12/2022 1/13/2022

EPC-06/HW/3749 Applying primer coat on Major Junction Prime coat 82+130 LHS 1/12/2022 1/13/2022

EPC-06/HW/3753 Applying tack coat for DBM Tack coat (DBM) (OL) 00+000 01+950 LHS 1/13/2022 1/14/2022

EPC-06/HW/3754 Applying tack coat for DBM Tack coat (DBM) (OL) 06+500 06+560 BHS 1/13/2022 1/14/2022

EPC-06/HW/3755 Level checking and laying of DBM DBM (OL) 00+000 01+950 LHS 1/13/2022 1/14/2022

EPC-06/HW/3756 Level checking and laying of DBM DBM (OL) 06+500 06+560 BHS 1/13/2022 1/14/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3757 Applying tack coat for DBM on Major Junction Tack coat (DBM) 03+185 LHS 1/13/2022 1/14/2022

EPC-06/HW/3758 Laying of DBM on Major Junction DBM 03+185 LHS 1/13/2022 1/14/2022

EPC-06/HW/3759 Applying tack coat for DBM on Major Junction Tack coat (DBM) 05+710 RHS 1/13/2022 1/14/2022

EPC-06/HW/3760 Laying of DBM on Major Junction DBM 05+710 RHS 1/13/2022 1/14/2022

EPC-06/HW/3761 Applying tack coat for DBM on Major Junction Tack coat (DBM) 82+130 LHS 1/13/2022 1/14/2022

EPC-06/HW/3762 Laying of DBM on Major Junction DBM 82+130 LHS 1/13/2022 1/14/2022

EPC-06/HW/3812 Dismantling of existing BT surface BT Scr 94+500 96+600 BHS 2/8/2022 2/9/2022

EPC-06/HW/3816 Dismantling of existing BT surface BT Scr 94+200 94+300 BHS 2/9/2022 2/10/2022

EPC-06/HW/3817 Dismantling of existing BT surface BT Scr 96+600 96+800 BHS 2/9/2022 2/10/2022

EPC-06/HW/3818 Level & FDD Checking of Subgrade Top layer SG Top 94+500 96+150 LHS 2/9/2022 2/10/2022

EPC-06/HW/3822 Dismantling of existing BT surface BT Scr 96+800 98+700 BHS 2/10/2022 2/11/2022

EPC-06/HW/3823 Level & FDD Checking of Subgrade Top layer SG Top 96+150 97+680 LHS 2/10/2022 2/11/2022

EPC-06/HW/3827 Dismantling of existing BT surface BT Scr 98+700 100+500 BHS 2/11/2022 2/12/2022

EPC-06/HW/3828 Level & FDD Checking of Subgrade Top layer SG Top 97+750 98+500 LHS 2/11/2022 2/12/2022

EPC-06/HW/3829 Level & FDD Checking For GSB layer GSB 94+500 95+200 LHS 2/11/2022 2/12/2022

EPC-06/HW/3833 Dismantling of existing BT surface BT Scr 100+500 102+100 BHS 2/12/2022 2/13/2022

EPC-06/HW/3834 Level & FDD Checking of Subgrade Top layer SG Top 98+500 99+300 LHS 2/12/2022 2/13/2022

EPC-06/HW/3835 Level & FDD Checking For GSB layer GSB 95+200 96+100 LHS 2/12/2022 2/13/2022

EPC-06/HW/3839 Level & FDD Checking of Subgrade Top layer SG Top 86+860 86+868 BHS 2/13/2022 2/14/2022

EPC-06/HW/3839 Level & FDD Checking of Subgrade Top layer SG Top 88+520 88+650 BHS 2/13/2022 2/14/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3841 Level & FDD Checking of Subgrade Top layer SG Top 88+850 88+900 BHS 2/13/2022 2/14/2022

EPC-06/HW/3841 Level & FDD Checking of Subgrade Top layer SG Top 94+200 94+300 BHS 2/13/2022 2/14/2022

EPC-06/HW/3843 Level & FDD Checking of Subgrade Top layer SG Top 99+360 100+600 LHS 2/13/2022 2/14/2022

EPC-06/HW/3844 Level & FDD Checking For GSB layer GSB 96+100 96+850 LHS 2/13/2022 2/14/2022

EPC-06/HW/3848 Level & FDD Checking For GSB layer GSB 96+850 97+680 LHS 2/14/2022 2/15/2022

EPC-06/HW/3852 Level & FDD Checking For GSB layer GSB 86+860 86+868 BHS 2/15/2022 2/16/2022

EPC-06/HW/3852 Level & FDD Checking For GSB layer GSB 88+520 88+650 BHS 2/15/2022 2/16/2022

EPC-06/HW/3854 Level & FDD Checking For GSB layer GSB 88+850 88+900 BHS 2/15/2022 2/16/2022

EPC-06/HW/3854 Level & FDD Checking For GSB layer GSB 94+200 94+300 BHS 2/15/2022 2/16/2022

EPC-06/HW/3856 Level & FDD Checking For GSB layer GSB 97+750 98+500 LHS 2/15/2022 2/16/2022

EPC-06/HW/3857 FDD Checking of WMM 1st layer WMM-I 94+500 95+200 LHS 2/15/2022 2/16/2022

EPC-06/HW/3861 Level & FDD Checking For GSB layer GSB 98+500 99+300 LHS 2/16/2022 2/17/2022

EPC-06/HW/3862 FDD Checking of WMM 1st layer WMM-I 95+200 96+100 LHS 2/16/2022 2/17/2022

EPC-06/HW/3863 Level & FDD Checking of WMM Top layer WMM-II 94+500 95+200 LHS 2/16/2022 2/17/2022

EPC-06/HW/3867 Level & FDD Checking For GSB layer GSB 99+360 99+950 LHS 2/17/2022 2/18/2022

EPC-06/HW/3868 FDD Checking of WMM 1st layer WMM-I 96+100 96+850 LHS 2/17/2022 2/18/2022

EPC-06/HW/3869 Level & FDD Checking of WMM Top layer WMM-II 95+200 96+100 LHS 2/17/2022 2/18/2022

EPC-06/HW/3873 FDD Checking of WMM 1st layer WMM-I 86+860 86+868 BHS 2/18/2022 2/19/2022

EPC-06/HW/3873 FDD Checking of WMM 1st layer WMM-I 88+520 88+650 BHS 2/18/2022 2/19/2022

EPC-06/HW/3875 FDD Checking of WMM 1st layer WMM-I 88+850 88+900 BHS 2/18/2022 2/19/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3875 FDD Checking of WMM 1st layer WMM-I 94+200 94+300 BHS 2/18/2022 2/19/2022

EPC-06/HW/3877 Level & FDD Checking For GSB layer GSB 99+950 100+600 LHS 2/18/2022 2/19/2022

EPC-06/HW/3878 FDD Checking of WMM 1st layer WMM-I 96+850 97+680 LHS 2/18/2022 2/19/2022

EPC-06/HW/3879 Level & FDD Checking of WMM Top layer WMM-II 96+100 96+850 LHS 2/18/2022 2/19/2022

EPC-06/HW/3883 Level & FDD Checking of WMM Top layer WMM-II 86+860 86+868 BHS 2/19/2022 2/20/2022

EPC-06/HW/3883 Level & FDD Checking of WMM Top layer WMM-II 88+520 88+650 BHS 2/19/2022 2/20/2022

EPC-06/HW/3885 Level & FDD Checking of WMM Top layer WMM-II 88+850 88+900 BHS 2/19/2022 2/20/2022

EPC-06/HW/3885 Level & FDD Checking of WMM Top layer WMM-II 94+200 94+300 BHS 2/19/2022 2/20/2022

EPC-06/HW/3887 FDD Checking of WMM 1st layer WMM-I 97+750 98+500 LHS 2/19/2022 2/20/2022

EPC-06/HW/3888 Level & FDD Checking of WMM Top layer WMM-II 96+850 97+680 LHS 2/19/2022 2/20/2022

EPC-06/HW/3892 FDD Checking of Subgrade Top layer on Major Junction SG Top 85+670 LHS 2/20/2022 2/21/2022

EPC-06/HW/3893 FDD Checking of Subgrade Top layer on Major Junction SG Top 94+270 BHS 2/20/2022 2/21/2022

EPC-06/HW/3894 FDD Checking of Subgrade Top layer on Minor Junction SG Top 97+095 LHS 2/20/2022 2/21/2022

EPC-06/HW/3895 FDD Checking of WMM 1st layer WMM-I 98+500 99+300 LHS 2/20/2022 2/21/2022

EPC-06/HW/3896 Level & FDD Checking of WMM Top layer WMM-II 97+750 98+500 LHS 2/20/2022 2/21/2022

EPC-06/HW/3900 FDD Checking For GSB layer on Major Junction GSB 85+670 LHS 2/21/2022 2/22/2022

EPC-06/HW/3901 FDD Checking For GSB layer on Major Junction GSB 94+270 BHS 2/21/2022 2/22/2022

EPC-06/HW/3902 FDD Checking For GSB layer on Minor Junction GSB 97+095 LHS 2/21/2022 2/22/2022

EPC-06/HW/3903 FDD Checking of WMM 1st layer WMM-I 99+360 99+950 LHS 2/21/2022 2/22/2022

EPC-06/HW/3904 Level & FDD Checking of WMM Top layer WMM-II 98+500 99+300 LHS 2/21/2022 2/22/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3905 Applying primer coat Prime coat 94+500 96+040 LHS 2/21/2022 2/22/2022

EPC-06/HW/3909 Applying primer coat Prime coat 86+860 86+868 BHS 2/22/2022 2/23/2022

EPC-06/HW/3909 Applying primer coat Prime coat 88+520 88+650 BHS 2/22/2022 2/23/2022

EPC-06/HW/3909 Applying primer coat Prime coat 88+850 88+900 BHS 2/22/2022 2/23/2022

EPC-06/HW/3909 Applying primer coat Prime coat 94+200 94+300 BHS 2/22/2022 2/23/2022

EPC-06/HW/3913 FDD Checking of WMM Top layer on Major Junction WMM-II 85+670 LHS 2/22/2022 2/23/2022

EPC-06/HW/3914 Applying primer coat on Major Junction Prime coat 85+670 LHS 2/22/2022 2/23/2022

EPC-06/HW/3915 FDD Checking of WMM Top layer on Major Junction WMM-II 94+270 BHS 2/22/2022 2/23/2022

EPC-06/HW/3916 Applying primer coat on Major Junction Prime coat 94+270 BHS 2/22/2022 2/23/2022

EPC-06/HW/3917 FDD Checking of WMM Top layer on Minor Junction WMM-II 97+095 LHS 2/22/2022 2/23/2022

EPC-06/HW/3918 Applying primer coat on Minor Junction Prime coat 97+095 LHS 2/22/2022 2/23/2022

EPC-06/HW/3919 FDD Checking of WMM 1st layer WMM-I 99+950 100+550 LHS 2/22/2022 2/23/2022

EPC-06/HW/3920 Level & FDD Checking of WMM Top layer WMM-II 99+360 99+950 LHS 2/22/2022 2/23/2022

EPC-06/HW/3921 Applying primer coat Prime coat 96+040 97+680 LHS 2/22/2022 2/23/2022

EPC-06/HW/3922 Applying tack coat for DBM Tack coat (DBM) 94+500 96+040 LHS 2/22/2022 2/23/2022

EPC-06/HW/3923 Level checking and laying of DBM DBM 94+500 96+040 LHS 2/22/2022 2/23/2022

EPC-06/HW/3927 Applying tack coat for DBM Tack coat (DBM) 86+860 86+868 BHS 2/23/2022 2/24/2022

EPC-06/HW/3927 Applying tack coat for DBM Tack coat (DBM) 88+520 88+650 BHS 2/23/2022 2/24/2022

EPC-06/HW/3927 Applying tack coat for DBM Tack coat (DBM) 88+850 88+900 BHS 2/23/2022 2/24/2022

EPC-06/HW/3927 Applying tack coat for DBM Tack coat (DBM) 94+200 94+300 BHS 2/23/2022 2/24/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3931 Level checking and laying of DBM DBM 86+860 86+868 BHS 2/23/2022 2/24/2022

EPC-06/HW/3931 Level checking and laying of DBM DBM 88+520 88+650 BHS 2/23/2022 2/24/2022

EPC-06/HW/3931 Level checking and laying of DBM DBM 88+850 88+900 BHS 2/23/2022 2/24/2022

EPC-06/HW/3931 Level checking and laying of DBM DBM 94+200 94+300 BHS 2/23/2022 2/24/2022

EPC-06/HW/3935 Applying tack coat for DBM on Major Junction Tack coat (DBM) 85+670 LHS 2/23/2022 2/24/2022

EPC-06/HW/3936 Laying of DBM on Major Junction DBM 85+670 LHS 2/23/2022 2/24/2022

EPC-06/HW/3937 Applying tack coat for DBM on Major Junction Tack coat (DBM) 94+270 BHS 2/23/2022 2/24/2022

EPC-06/HW/3938 Laying of DBM on Major Junction DBM 94+270 BHS 2/23/2022 2/24/2022

EPC-06/HW/3939 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 97+095 LHS 2/23/2022 2/24/2022

EPC-06/HW/3940 Laying of DBM on Minor Junction DBM 97+095 LHS 2/23/2022 2/24/2022

EPC-06/HW/3941 Level & FDD Checking of Subgrade Top layer SG Top 94+500 96+000 RHS 2/23/2022 2/24/2022

EPC-06/HW/3942 Level & FDD Checking of WMM Top layer WMM-II 99+950 100+550 LHS 2/23/2022 2/24/2022

EPC-06/HW/3943 Applying primer coat Prime coat 97+750 99+300 LHS 2/23/2022 2/24/2022

EPC-06/HW/3943 Applying primer coat Prime coat 99+360 100+500 LHS 2/23/2022 2/24/2022

EPC-06/HW/3945 Applying tack coat for DBM Tack coat (DBM) 96+040 97+680 LHS 2/23/2022 2/24/2022

EPC-06/HW/3946 Level checking and laying of DBM DBM 96+040 97+680 LHS 2/23/2022 2/24/2022

EPC-06/HW/3950 Level & FDD Checking of Subgrade Top layer SG Top 96+000 97+680 RHS 2/24/2022 2/25/2022

EPC-06/HW/3951 Applying tack coat for DBM Tack coat (DBM) 97+750 99+300 LHS 2/24/2022 2/25/2022

EPC-06/HW/3951 Applying tack coat for DBM Tack coat (DBM) 99+360 100+500 LHS 2/24/2022 2/25/2022

EPC-06/HW/3953 Level checking and laying of DBM DBM 97+750 99+300 LHS 2/24/2022 2/25/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/3953 Level checking and laying of DBM DBM 99+360 100+500 LHS 2/24/2022 2/25/2022

EPC-06/HW/3958 Level & FDD Checking For GSB layer GSB 94+500 95+300 RHS 2/25/2022 2/26/2022

EPC-06/HW/3962 Level & FDD Checking of Subgrade Top layer SG Top 97+750 99+300 RHS 2/26/2022 2/27/2022

EPC-06/HW/3963 Level & FDD Checking For GSB layer GSB 95+300 96+150 RHS 2/26/2022 2/27/2022

EPC-06/HW/3967 Level & FDD Checking of Subgrade Top layer SG Top 99+360 100+500 RHS 2/27/2022 2/28/2022

EPC-06/HW/3968 Level & FDD Checking For GSB layer GSB 96+150 96+900 RHS 2/27/2022 2/28/2022

EPC-06/HW/3972 Applying tack coat for BC Tack coat (BC) 75+900 78+700 RHS 2/28/2022 3/1/2022

EPC-06/HW/3973 Level checking and laying of BC BC 75+900 78+700 RHS 2/28/2022 3/1/2022

EPC-06/HW/3974 Level & FDD Checking For GSB layer GSB 96+900 97+680 RHS 2/28/2022 3/1/2022

EPC-06/HW/3978 Level & FDD Checking For GSB layer GSB 97+750 98+500 RHS 3/1/2022 3/2/2022

EPC-06/HW/3982 Applying tack coat for BC Tack coat (BC) 75+900 79+000 LHS 3/2/2022 3/3/2022

EPC-06/HW/3983 Level checking and laying of BC BC 75+900 79+000 LHS 3/2/2022 3/3/2022

EPC-06/HW/3984 Level & FDD Checking For GSB layer GSB 98+500 99+300 RHS 3/2/2022 3/3/2022

EPC-06/HW/3988 Applying tack coat for BC Tack coat (BC) 79+000 82+150 LHS 3/3/2022 3/4/2022

EPC-06/HW/3989 Level checking and laying of BC BC 79+000 82+150 LHS 3/3/2022 3/4/2022

EPC-06/HW/3990 Level & FDD Checking For GSB layer GSB 99+360 99+900 RHS 3/3/2022 3/4/2022

EPC-06/HW/3994 Applying tack coat for BC Tack coat (BC) 78+700 82+150 RHS 3/4/2022 3/5/2022

EPC-06/HW/3995 Level checking and laying of BC BC 78+700 82+150 RHS 3/4/2022 3/5/2022

EPC-06/HW/3996 Level & FDD Checking of Subgrade Top layer SG Top 100+600 101+800 LHS 3/4/2022 3/5/2022

EPC-06/HW/3997 Level & FDD Checking For GSB layer GSB 99+900 100+400 RHS 3/4/2022 3/5/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4001 FDD Checking of WMM 1st layer WMM-I 94+500 95+300 RHS 3/5/2022 3/6/2022

EPC-06/HW/4005 Applying tack coat for BC Tack coat (BC) 74+170 75+700 RHS 3/6/2022 3/7/2022

EPC-06/HW/4006 Applying tack coat for BC Tack coat (BC) 72+200 73+770 RHS 3/6/2022 3/7/2022

EPC-06/HW/4007 Level checking and laying of BC BC 74+170 75+700 RHS 3/6/2022 3/7/2022

EPC-06/HW/4007 Level checking and laying of BC BC 72+200 73+770 RHS 3/6/2022 3/7/2022

EPC-06/HW/4009 FDD Checking of WMM 1st layer WMM-I 95+300 96+150 RHS 3/6/2022 3/7/2022

EPC-06/HW/4010 Level & FDD Checking of WMM Top layer WMM-II 94+500 95+300 RHS 3/6/2022 3/7/2022

EPC-06/HW/4014 Applying tack coat for BC Tack coat (BC) 71+600 72+200 RHS 3/7/2022 3/8/2022

EPC-06/HW/4015 Applying tack coat for BC Tack coat (BC) 70+070 71+100 RHS 3/7/2022 3/8/2022

EPC-06/HW/4016 Applying tack coat for BC Tack coat (BC) 74+170 75+700 LHS 3/7/2022 3/8/2022

EPC-06/HW/4017 Level checking and laying of BC BC 71+600 72+200 RHS 3/7/2022 3/8/2022

EPC-06/HW/4017 Level checking and laying of BC BC 70+070 71+100 RHS 3/7/2022 3/8/2022

EPC-06/HW/4017 Level checking and laying of BC BC 74+170 75+700 LHS 3/7/2022 3/8/2022

EPC-06/HW/4020 FDD Checking of WMM 1st layer WMM-I 96+150 96+900 RHS 3/7/2022 3/8/2022

EPC-06/HW/4021 Level & FDD Checking of WMM Top layer WMM-II 95+300 96+150 RHS 3/7/2022 3/8/2022

EPC-06/HW/4025 Applying tack coat for BC Tack coat (BC) 71+600 73+770 LHS 3/8/2022 3/9/2022

EPC-06/HW/4026 Applying tack coat for BC Tack coat (BC) 70+070 71+100 LHS 3/8/2022 3/9/2022

EPC-06/HW/4027 Level checking and laying of BC BC 71+600 73+770 LHS 3/8/2022 3/9/2022

EPC-06/HW/4027 Level checking and laying of BC BC 70+070 71+100 LHS 3/8/2022 3/9/2022

EPC-06/HW/4029 FDD Checking of WMM 1st layer WMM-I 96+900 97+680 RHS 3/8/2022 3/9/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4030 Level & FDD Checking of WMM Top layer WMM-II 96+150 96+900 RHS 3/8/2022 3/9/2022

EPC-06/HW/4034 Applying tack coat for BC Tack coat (BC) 64+600 67+500 LHS 3/9/2022 3/10/2022

EPC-06/HW/4035 Level checking and laying of BC BC 64+600 67+500 LHS 3/9/2022 3/10/2022

EPC-06/HW/4036 FDD Checking of WMM 1st layer WMM-I 97+750 98+500 RHS 3/9/2022 3/10/2022

EPC-06/HW/4037 Level & FDD Checking of WMM Top layer WMM-II 96+900 97+680 RHS 3/9/2022 3/10/2022

EPC-06/HW/4041 Applying tack coat for BC Tack coat (BC) (OL) 63+950 64+000 LHS 3/10/2022 3/11/2022

EPC-06/HW/4042 Applying tack coat for BC Tack coat (BC) (OL) 61+550 63+550 LHS 3/10/2022 3/11/2022

EPC-06/HW/4043 Level checking and laying of BC BC (OL) 63+950 64+000 LHS 3/10/2022 3/11/2022

EPC-06/HW/4043 Level checking and laying of BC BC (OL) 61+550 63+550 LHS 3/10/2022 3/11/2022

EPC-06/HW/4045 Applying tack coat for BC Tack coat (BC) 64+000 64+600 LHS 3/10/2022 3/11/2022

EPC-06/HW/4046 Applying tack coat for BC Tack coat (BC) 63+550 63+950 LHS 3/10/2022 3/11/2022

EPC-06/HW/4047 Level checking and laying of BC BC 64+000 64+600 LHS 3/10/2022 3/11/2022

EPC-06/HW/4047 Level checking and laying of BC BC 63+550 63+950 LHS 3/10/2022 3/11/2022

EPC-06/HW/4049 FDD Checking of WMM 1st layer WMM-I 98+500 99+300 RHS 3/10/2022 3/11/2022

EPC-06/HW/4050 Level & FDD Checking of WMM Top layer WMM-II 97+750 98+500 RHS 3/10/2022 3/11/2022

EPC-06/HW/4051 Dismantling of existing BT surface BT Scr 102+100 104+000 BHS 3/10/2022 3/11/2022

EPC-06/HW/4054 Applying tack coat for BC Tack coat (BC) (OL) 61+000 61+110 LHS 3/11/2022 3/12/2022

EPC-06/HW/4055 Level checking and laying of BC BC (OL) 61+000 61+110 LHS 3/11/2022 3/12/2022

EPC-06/HW/4056 Applying tack coat for BC Tack coat (BC) 61+110 61+550 LHS 3/11/2022 3/12/2022

EPC-06/HW/4057 Applying tack coat for BC Tack coat (BC) 58+130 61+000 LHS 3/11/2022 3/12/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4058 Level checking and laying of BC BC 61+110 61+550 LHS 3/11/2022 3/12/2022

EPC-06/HW/4058 Level checking and laying of BC BC 58+130 61+000 LHS 3/11/2022 3/12/2022

EPC-06/HW/4060 FDD Checking of WMM 1st layer WMM-I 99+360 99+900 RHS 3/11/2022 3/12/2022

EPC-06/HW/4061 Level & FDD Checking of WMM Top layer WMM-II 98+500 99+300 RHS 3/11/2022 3/12/2022

EPC-06/HW/4062 Applying primer coat Prime coat 94+500 96+500 RHS 3/11/2022 3/12/2022

EPC-06/HW/4063 Dismantling of existing BT surface BT Scr 104+000 106+000 BHS 3/11/2022 3/12/2022

EPC-06/HW/4064 FDD Checking of Subgrade Top layer on Minor Junction SG Top 98+340 LHS 3/11/2022 3/12/2022

EPC-06/HW/4065 FDD Checking of Subgrade Top layer on Minor Junction SG Top 100+260 LHS 3/11/2022 3/12/2022

EPC-06/HW/4067 FDD Checking of WMM 1st layer WMM-I 99+900 100+450 RHS 3/12/2022 3/13/2022

EPC-06/HW/4068 Level & FDD Checking of WMM Top layer WMM-II 99+360 99+900 RHS 3/12/2022 3/13/2022

EPC-06/HW/4069 Applying primer coat Prime coat 96+500 97+680 RHS 3/12/2022 3/13/2022

EPC-06/HW/4069 Applying primer coat Prime coat 97+750 98+500 RHS 3/12/2022 3/13/2022

EPC-06/HW/4071 Applying tack coat for DBM Tack coat (DBM) 94+500 96+500 RHS 3/12/2022 3/13/2022

EPC-06/HW/4072 Level checking and laying of DBM DBM 94+500 96+500 RHS 3/12/2022 3/13/2022

EPC-06/HW/4073 FDD Checking For GSB layer on Minor Junction GSB 98+340 LHS 3/12/2022 3/13/2022

EPC-06/HW/4074 FDD Checking For GSB layer on Minor Junction GSB 100+260 LHS 3/12/2022 3/13/2022

EPC-06/HW/4077 Level & FDD Checking of WMM Top layer WMM-II 99+900 100+450 RHS 3/13/2022 3/14/2022

EPC-06/HW/4078 Applying primer coat Prime coat 98+500 99+300 RHS 3/13/2022 3/14/2022

EPC-06/HW/4078 Applying primer coat Prime coat 99+360 100+400 RHS 3/13/2022 3/14/2022

EPC-06/HW/4080 Applying tack coat for DBM Tack coat (DBM) 96+500 97+680 RHS 3/13/2022 3/14/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4080 Applying tack coat for DBM Tack coat (DBM) 97+750 98+500 RHS 3/13/2022 3/14/2022

EPC-06/HW/4082 Level checking and laying of DBM DBM 96+500 97+680 RHS 3/13/2022 3/14/2022

EPC-06/HW/4082 Level checking and laying of DBM DBM 97+750 98+500 RHS 3/13/2022 3/14/2022

EPC-06/HW/4083 Level & FDD Checking of Subgrade Top layer SG Top 101+800 102+900 LHS 3/13/2022 3/14/2022

EPC-06/HW/4084 Level & FDD Checking For GSB layer GSB 100+600 101+500 LHS 3/13/2022 3/14/2022

EPC-06/HW/4085 FDD Checking of WMM Top layer on Minor Junction WMM-II 98+340 LHS 3/13/2022 3/14/2022

EPC-06/HW/4086 FDD Checking of WMM Top layer on Minor Junction WMM-II 100+260 LHS 3/13/2022 3/14/2022

EPC-06/HW/4087 Applying primer coat on Minor Junction Prime coat 98+340 LHS 3/13/2022 3/14/2022

EPC-06/HW/4087 Applying primer coat on Minor Junction Prime coat 100+260 LHS 3/13/2022 3/14/2022

EPC-06/HW/4088 Applying tack coat for DBM Tack coat (DBM) 98+500 99+300 RHS 3/14/2022 3/15/2022

EPC-06/HW/4088 Applying tack coat for DBM Tack coat (DBM) 99+360 100+400 RHS 3/14/2022 3/15/2022

EPC-06/HW/4090 Level checking and laying of DBM DBM 98+500 99+300 RHS 3/14/2022 3/15/2022

EPC-06/HW/4090 Level checking and laying of DBM DBM 99+360 100+400 RHS 3/14/2022 3/15/2022

EPC-06/HW/4091 Level & FDD Checking of Subgrade Top layer SG Top 102+900 104+100 LHS 3/14/2022 3/15/2022

EPC-06/HW/4092 Level & FDD Checking For GSB layer GSB 101+500 102+350 LHS 3/14/2022 3/15/2022

EPC-06/HW/4093 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 98+340 LHS 3/14/2022 3/15/2022

EPC-06/HW/4093 Applying tack coat for DBM on Minor Junction Tack coat (DBM) 100+260 LHS 3/14/2022 3/15/2022

EPC-06/HW/4094 Laying of DBM on Minor Junction DBM 98+340 LHS 3/14/2022 3/15/2022

EPC-06/HW/4094 Laying of DBM on Minor Junction DBM 100+260 LHS 3/14/2022 3/15/2022

EPC-06/HW/4095 Level & FDD Checking For GSB layer GSB 102+350 103+300 LHS 3/14/2022 3/15/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4096 Applying tack coat for BC Tack coat (BC) 58+130 61+000 RHS 3/15/2022 3/16/2022

EPC-06/HW/4097 Level checking and laying of BC BC 58+130 61+000 RHS 3/15/2022 3/16/2022

EPC-06/HW/4098 Level & FDD Checking of Subgrade Top layer SG Top 100+500 101+800 RHS 3/15/2022 3/16/2022

EPC-06/HW/4099 Level & FDD Checking of Subgrade Top layer SG Top 104+100 105+100 LHS 3/16/2022 3/17/2022

EPC-06/HW/4100 Level & FDD Checking For GSB layer GSB 103+300 104+100 LHS 3/16/2022 3/17/2022

EPC-06/HW/4101 Level & FDD Checking of WMM Top layer WMM-II 100+550 101+450 LHS 3/16/2022 3/17/2022

EPC-06/HW/4102 Level & FDD Checking of Subgrade Top layer SG Top 101+800 102+800 RHS 3/17/2022 3/18/2022

EPC-06/HW/4103 Level & FDD Checking For GSB layer GSB 104+100 105+000 LHS 3/17/2022 3/18/2022

EPC-06/HW/4104 Level & FDD Checking of WMM Top layer WMM-II 101+450 102+350 LHS 3/17/2022 3/18/2022

EPC-06/HW/4105 Level & FDD Checking of Subgrade Top layer SG Top 102+800 104+100 RHS 3/18/2022 3/19/2022

EPC-06/HW/4106 Level & FDD Checking For GSB layer GSB 100+400 101+350 RHS 3/18/2022 3/19/2022

EPC-06/HW/4107 Level & FDD Checking of WMM Top layer WMM-II 102+350 103+250 LHS 3/18/2022 3/19/2022

EPC-06/HW/4108 Level & FDD Checking of Subgrade Top layer SG Top 104+100 105+200 RHS 3/19/2022 3/20/2022

EPC-06/HW/4109 Level & FDD Checking For GSB layer GSB 101+350 102+250 RHS 3/19/2022 3/20/2022

EPC-06/HW/4110 Level & FDD Checking of WMM Top layer WMM-II 103+250 104+200 LHS 3/19/2022 3/20/2022

EPC-06/HW/4111 Level & FDD Checking For GSB layer GSB 102+250 103+200 RHS 3/20/2022 3/21/2022

EPC-06/HW/4112 Level & FDD Checking of WMM Top layer WMM-II 104+200 105+000 LHS 3/20/2022 3/21/2022

EPC-06/HW/4113 Applying tack coat for BC Tack coat (BC) (OL) 61+000 61+110 RHS 3/21/2022 3/22/2022

EPC-06/HW/4114 Applying tack coat for BC Tack coat (BC) (OL) 61+550 63+550 RHS 3/21/2022 3/22/2022

EPC-06/HW/4115 Level checking and laying of BC BC (OL) 61+000 61+110 RHS 3/21/2022 3/22/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4115 Level checking and laying of BC BC (OL) 61+550 63+550 RHS 3/21/2022 3/22/2022

EPC-06/HW/4117 Applying tack coat for BC Tack coat (BC) 61+110 61+550 RHS 3/21/2022 3/22/2022

EPC-06/HW/4118 Applying tack coat for BC Tack coat (BC) 63+550 63+950 RHS 3/21/2022 3/22/2022

EPC-06/HW/4119 Level checking and laying of BC BC 61+110 61+550 RHS 3/21/2022 3/22/2022

EPC-06/HW/4119 Level checking and laying of BC BC 63+550 63+950 RHS 3/21/2022 3/22/2022

EPC-06/HW/4120 Level & FDD Checking For GSB layer GSB 103+200 104+100 RHS 3/21/2022 3/22/2022

EPC-06/HW/4121 FDD Checking of WMM 1st layer WMM-I 101+400 102+300 RHS 3/21/2022 3/22/2022

EPC-06/HW/4122 Level & FDD Checking of WMM Top layer WMM-II 100+450 101+400 RHS 3/21/2022 3/22/2022

EPC-06/HW/4125 Applying tack coat for BC Tack coat (BC) (OL) 63+950 64+000 RHS 3/22/2022 3/23/2022

EPC-06/HW/4126 Level checking and laying of BC BC (OL) 63+950 64+000 RHS 3/22/2022 3/23/2022

EPC-06/HW/4127 Applying tack coat for BC Tack coat (BC) 64+000 67+500 RHS 3/22/2022 3/23/2022

EPC-06/HW/4128 Level checking and laying of BC BC 64+000 67+500 RHS 3/22/2022 3/23/2022

EPC-06/HW/4129 Level & FDD Checking For GSB layer GSB 104+100 105+000 RHS 3/22/2022 3/23/2022

EPC-06/HW/4130 FDD Checking of WMM 1st layer WMM-I 102+300 103+200 RHS 3/22/2022 3/23/2022

EPC-06/HW/4131 Level & FDD Checking of WMM Top layer WMM-II 101+400 102+300 RHS 3/22/2022 3/23/2022

EPC-06/HW/4133 Applying tack coat for BC Tack coat (BC) (OL) 53+000 55+620 RHS 3/23/2022 3/24/2022

EPC-06/HW/4134 Level checking and laying of BC BC (OL) 53+000 55+620 RHS 3/23/2022 3/24/2022

EPC-06/HW/4135 FDD Checking of WMM 1st layer WMM-I 103+200 104+050 RHS 3/23/2022 3/24/2022

EPC-06/HW/4136 Level & FDD Checking of WMM Top layer WMM-II 102+300 103+200 RHS 3/23/2022 3/24/2022

EPC-06/HW/4142 FDD Checking of WMM 1st layer WMM-I 104+050 105+000 RHS 3/24/2022 3/25/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4143 Level & FDD Checking of WMM Top layer WMM-II 103+200 104+050 RHS 3/24/2022 3/25/2022

EPC-06/HW/4155 Level & FDD Checking of WMM Top layer WMM-II 104+050 105+000 RHS 3/25/2022 3/26/2022

EPC-06/HW/4215 Applying tack coat for BC Tack coat (BC) 85+670 86+445 LHS 4/15/2022 4/16/2022

EPC-06/HW/4216 Applying tack coat for BC Tack coat (BC) 88+520 88+900 LHS 4/15/2022 4/16/2022

EPC-06/HW/4217 Applying tack coat for BC Tack coat (BC) 89+285 90+300 LHS 4/15/2022 4/16/2022

EPC-06/HW/4218 Level checking and laying of BC BC 85+670 86+445 LHS 4/15/2022 4/16/2022

EPC-06/HW/4219 Level checking and laying of BC BC 88+520 88+900 LHS 4/15/2022 4/16/2022

EPC-06/HW/4220 Level checking and laying of BC BC 89+285 90+300 LHS 4/15/2022 4/16/2022

EPC-06/HW/4232 Applying tack coat for BC Tack coat (BC) 90+300 92+200 LHS 4/17/2022 4/18/2022

EPC-06/HW/4233 Level checking and laying of BC BC 90+300 92+200 LHS 4/17/2022 4/18/2022

EPC-06/HW/4243 Applying tack coat for BC Tack coat (BC) 92+200 94+300 LHS 4/18/2022 4/19/2022

EPC-06/HW/4244 Level checking and laying of BC BC 92+200 94+300 LHS 4/18/2022 4/19/2022

EPC-06/HW/4259 Applying tack coat for BC Tack coat (BC) 85+670 86+445 RHS 4/21/2022 4/22/2022

EPC-06/HW/4260 Applying tack coat for BC Tack coat (BC) 86+860 86+868 BHS 4/21/2022 4/22/2022

EPC-06/HW/4261 Applying tack coat for BC Tack coat (BC) 88+520 88+900 RHS 4/21/2022 4/22/2022

EPC-06/HW/4262 Applying tack coat for BC Tack coat (BC) 89+285 90+200 RHS 4/21/2022 4/22/2022

EPC-06/HW/4263 Level checking and laying of BC BC 85+670 86+445 RHS 4/21/2022 4/22/2022

EPC-06/HW/4264 Level checking and laying of BC BC 86+860 86+868 BHS 4/21/2022 4/22/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4265 Level checking and laying of BC BC 88+520 88+900 RHS 4/21/2022 4/22/2022

EPC-06/HW/4266 Level checking and laying of BC BC 89+285 90+200 RHS 4/21/2022 4/22/2022

EPC-06/HW/4276 Applying tack coat for BC Tack coat (BC) 90+200 92+300 RHS 4/22/2022 4/23/2022

EPC-06/HW/4277 Level checking and laying of BC BC 90+200 92+300 RHS 4/22/2022 4/23/2022

EPC-06/HW/4292 Applying tack coat for BC Tack coat (BC) 92+300 94+300 RHS 4/24/2022 4/25/2022

EPC-06/HW/4293 Level checking and laying of BC BC 92+300 94+300 RHS 4/24/2022 4/25/2022

EPC-06/HW/4323 Applying tack coat for BC Tack coat (BC) 44+300 46+250 LHS 4/30/2022 5/1/2022

EPC-06/HW/4324 Level checking and laying of BC BC 44+300 46+250 LHS 4/30/2022 5/1/2022

EPC-06/HW/4334 Applying tack coat for BC Tack coat (BC) 46+320 49+500 LHS 5/1/2022 5/2/2022

EPC-06/HW/4335 Level checking and laying of BC BC 46+320 49+500 LHS 5/1/2022 5/2/2022

EPC-06/HW/4345 Applying tack coat for BC Tack coat (BC) 49+900 53+000 LHS 5/2/2022 5/3/2022

EPC-06/HW/4346 Level checking and laying of BC BC 49+900 53+000 LHS 5/2/2022 5/3/2022

EPC-06/HW/4361 Level & FDD Checking of Subgrade Top layer SG Top 105+100 105+900 LHS 5/5/2022 5/6/2022

EPC-06/HW/4362 Applying tack coat for BC Tack coat (BC) (OL) 53+000 55+620 LHS 5/5/2022 5/6/2022

EPC-06/HW/4363 Level checking and laying of BC BC (OL) 53+000 55+620 LHS 5/5/2022 5/6/2022

EPC-06/HW/4070 Laying of BC on Minor Junction BC 56+230 LHS 5/5/2022 5/6/2022

EPC-06/HW/4373 Dismantling of existing BT surface BT Scr 106+000 108+300 BHS 5/6/2022 5/7/2022

EPC-06/HW/4374 Applying tack coat for BC Tack coat (BC) 44+300 46+250 RHS 5/6/2022 5/7/2022

EPC-06/HW/4375 Level checking and laying of BC BC 44+300 46+250 RHS 5/6/2022 5/7/2022

EPC-06/HW/4385 Level & FDD Checking For GSB layer GSB 105+000 105+700 LHS 5/7/2022 5/8/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4395 Level & FDD Checking of Subgrade Top layer SG Top 105+900 106+700 LHS 5/8/2022 5/9/2022

EPC-06/HW/4405 FDD Checking of WMM 1st layer WMM-I 105+000 105+800 LHS 5/9/2022 5/10/2022

EPC-06/HW/4415 Dismantling of existing BT surface BT Scr 94+300 94+500 BHS 5/10/2022 5/11/2022

EPC-06/HW/4416 Level & FDD Checking For GSB layer GSB 105+700 106+700 LHS 5/10/2022 5/11/2022

EPC-06/HW/4417 Level & FDD Checking of WMM Top layer WMM-II 105+000 105+800 LHS 5/10/2022 5/11/2022

EPC-06/HW/4427 Level & FDD Checking of Subgrade Top layer SG Top 106+700 107+500 LHS 5/11/2022 5/12/2022

EPC-06/HW/4437 FDD Checking of WMM 1st layer WMM-I 105+800 106+700 LHS 5/12/2022 5/13/2022

EPC-06/HW/4447 Level & FDD Checking For GSB layer GSB 106+700 107+600 LHS 5/13/2022 5/14/2022

EPC-06/HW/4448 Level & FDD Checking of WMM Top layer WMM-II 105+800 106+700 LHS 5/13/2022 5/14/2022

EPC-06/HW/4449 Applying tack coat for BC Tack coat (BC) 46+320 49+500 RHS 5/13/2022 5/14/2022

EPC-06/HW/4450 Level checking and laying of BC BC 46+320 49+500 RHS 5/13/2022 5/14/2022

EPC-06/HW/4460 Level & FDD Checking of Subgrade Top layer SG Top 107+500 108+300 LHS 5/14/2022 5/15/2022

EPC-06/HW/4461 Applying tack coat for BC Tack coat (BC) 49+900 53+000 RHS 5/14/2022 5/15/2022

EPC-06/HW/4462 Level checking and laying of BC BC 49+900 53+000 RHS 5/14/2022 5/15/2022

EPC-06/HW/4472 FDD Checking of WMM 1st layer WMM-I 106+700 107+500 LHS 5/15/2022 5/16/2022

EPC-06/HW/4482 Level & FDD Checking For GSB layer GSB 107+600 108+300 LHS 5/16/2022 5/17/2022

EPC-06/HW/4483 Level & FDD Checking of WMM Top layer WMM-II 106+700 107+500 LHS 5/16/2022 5/17/2022

EPC-06/HW/4493 Applying tack coat for BC Tack coat (BC) 68+000 68+080 LHS 5/17/2022 5/18/2022

EPC-06/HW/4494 Applying tack coat for BC Tack coat (BC) 68+780 69+230 LHS 5/17/2022 5/18/2022

EPC-06/HW/4495 Applying tack coat for BC Tack coat (BC) 68+000 68+080 RHS 5/17/2022 5/18/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4496 Applying tack coat for BC Tack coat (BC) 68+780 69+230 RHS 5/17/2022 5/18/2022

EPC-06/HW/4497 Level checking and laying of BC BC 68+000 68+080 LHS 5/17/2022 5/18/2022

EPC-06/HW/4498 Level checking and laying of BC BC 68+780 69+230 LHS 5/17/2022 5/18/2022

EPC-06/HW/4499 Level checking and laying of BC BC 68+000 68+080 RHS 5/17/2022 5/18/2022

EPC-06/HW/4500 Level checking and laying of BC BC 68+780 69+230 RHS 5/17/2022 5/18/2022

EPC-06/HW/4505 Laying of DBM on Minor Junction DBM 69+550 LHS 5/17/2022 5/18/2022

EPC-06/HW/4510 Level & FDD Checking of Subgrade Top layer SG Top 99+300 99+360 BHS 5/18/2022 5/19/2022

EPC-06/HW/4511 Level & FDD Checking of Subgrade Top layer SG Top 94+300 94+500 LHS 5/18/2022 5/19/2022

EPC-06/HW/4512 Level & FDD Checking of Subgrade Top layer SG Top 94+300 94+500 RHS 5/18/2022 5/19/2022

EPC-06/HW/4513 FDD Checking of WMM 1st layer WMM-I 107+500 108+300 LHS 5/18/2022 5/19/2022

EPC-06/HW/4523 Level & FDD Checking of WMM Top layer WMM-II 107+500 108+300 LHS 5/19/2022 5/20/2022

EPC-06/HW/4533 Level & FDD Checking For GSB layer GSB 99+300 99+360 BHS 5/20/2022 5/21/2022

EPC-06/HW/4534 Level & FDD Checking For GSB layer GSB 94+300 94+500 LHS 5/20/2022 5/21/2022

EPC-06/HW/4535 Level & FDD Checking For GSB layer GSB 94+300 94+500 RHS 5/20/2022 5/21/2022

EPC-06/HW/4550 FDD Checking of WMM 1st layer WMM-I 99+300 99+360 BHS 5/22/2022 5/23/2022

EPC-06/HW/4551 FDD Checking of WMM 1st layer WMM-I 94+300 94+500 LHS 5/22/2022 5/23/2022

EPC-06/HW/4552 FDD Checking of WMM 1st layer WMM-I 94+300 94+500 RHS 5/22/2022 5/23/2022

EPC-06/HW/4562 Level & FDD Checking of WMM Top layer WMM-II 99+300 99+360 BHS 5/23/2022 5/24/2022

EPC-06/HW/4563 Level & FDD Checking of WMM Top layer WMM-II 94+300 94+500 LHS 5/23/2022 5/24/2022

EPC-06/HW/4564 Level & FDD Checking of WMM Top layer WMM-II 94+300 94+500 RHS 5/23/2022 5/24/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4579 Level & FDD Checking of Subgrade Top layer SG Top 105+200 106+000 RHS 5/25/2022 5/26/2022

EPC-06/HW/4580 Applying primer coat Prime coat 99+300 99+360 LHS 5/25/2022 5/26/2022

EPC-06/HW/4581 Applying primer coat Prime coat 100+500 102+400 LHS 5/25/2022 5/26/2022

EPC-06/HW/4596 Applying tack coat for DBM Tack coat (DBM) 99+300 99+360 LHS 5/26/2022 5/27/2022

EPC-06/HW/4597 Applying tack coat for DBM Tack coat (DBM) 100+500 102+400 LHS 5/26/2022 5/27/2022

EPC-06/HW/4598 Level checking and laying of DBM DBM 99+300 99+360 LHS 5/26/2022 5/27/2022

EPC-06/HW/4599 Level checking and laying of DBM DBM 100+500 102+400 LHS 5/26/2022 5/27/2022

EPC-06/HW/4605 Laying of DBM on Minor Junction DBM 98+340 LHS 5/26/2022 5/27/2022

EPC-06/HW/4605 Laying of DBM on Minor Junction DBM 100+480 BHS 5/26/2022 5/27/2022

EPC-06/HW/4614 Level & FDD Checking of Subgrade Top layer SG Top 106+000 106+800 RHS 5/27/2022 5/28/2022

EPC-06/HW/4615 Level & FDD Checking For GSB layer GSB 105+000 105+800 RHS 5/27/2022 5/28/2022

EPC-06/HW/4616 Applying primer coat Prime coat 102+400 104+500 LHS 5/27/2022 5/28/2022

EPC-06/HW/4631 Applying primer coat Prime coat 104+500 106+200 LHS 5/28/2022 5/29/2022

EPC-06/HW/4632 Applying tack coat for DBM Tack coat (DBM) 102+400 104+500 LHS 5/28/2022 5/29/2022

EPC-06/HW/4633 Level checking and laying of DBM DBM 102+400 104+500 LHS 5/28/2022 5/29/2022

EPC-06/HW/4640 Laying of DBM on Minor Junction DBM 102+060 RHS 5/28/2022 5/29/2022

EPC-06/HW/4648 Level & FDD Checking of Subgrade Top layer SG Top 106+800 107+500 RHS 5/29/2022 5/30/2022

EPC-06/HW/4649 Level & FDD Checking For GSB layer GSB 105+800 106+400 RHS 5/29/2022 5/30/2022

EPC-06/HW/4650 FDD Checking of WMM 1st layer WMM-I 105+000 105+700 RHS 5/29/2022 5/30/2022

EPC-06/HW/4651 Applying primer coat Prime coat 106+200 108+300 LHS 5/29/2022 5/30/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4652 Applying tack coat for DBM Tack coat (DBM) 104+500 106+200 LHS 5/29/2022 5/30/2022

EPC-06/HW/4653 Level checking and laying of DBM DBM 104+500 106+200 LHS 5/29/2022 5/30/2022

EPC-06/HW/4668 Level & FDD Checking of WMM Top layer WMM-II 105+000 105+700 RHS 5/30/2022 5/31/2022

EPC-06/HW/4669 Applying tack coat for DBM Tack coat (DBM) 106+200 108+300 LHS 5/30/2022 5/31/2022

EPC-06/HW/4670 Level checking and laying of DBM DBM 106+200 108+300 LHS 5/30/2022 5/31/2022

EPC-06/HW/4680 Level & FDD Checking of Subgrade Top layer SG Top 107+500 108+300 RHS 5/31/2022 6/1/2022

EPC-06/HW/4681 Level & FDD Checking For GSB layer GSB 106+400 107+400 RHS 5/31/2022 6/1/2022

EPC-06/HW/4682 FDD Checking of WMM 1st layer WMM-I 105+700 106+400 RHS 5/31/2022 6/1/2022

EPC-06/HW/4692 Level & FDD Checking of WMM Top layer WMM-II 105+700 106+400 RHS 6/1/2022 6/2/2022

EPC-06/HW/4693 Applying primer coat Prime coat 99+300 99+360 RHS 6/1/2022 6/2/2022

EPC-06/HW/4694 Applying primer coat Prime coat 100+400 102+500 RHS 6/1/2022 6/2/2022

EPC-06/HW/4704 Level & FDD Checking For GSB layer GSB 107+400 108+300 RHS 6/2/2022 6/3/2022

EPC-06/HW/4705 FDD Checking of WMM 1st layer WMM-I 106+400 107+300 RHS 6/2/2022 6/3/2022

EPC-06/HW/4706 Applying primer coat Prime coat 102+500 104+200 RHS 6/2/2022 6/3/2022

EPC-06/HW/4707 Applying primer coat Prime coat 94+300 94+500 LHS 6/2/2022 6/3/2022

EPC-06/HW/4708 Applying tack coat for DBM Tack coat (DBM) 99+300 99+360 RHS 6/2/2022 6/3/2022

EPC-06/HW/4709 Applying tack coat for DBM Tack coat (DBM) 100+400 102+500 RHS 6/2/2022 6/3/2022

EPC-06/HW/4710 Level checking and laying of DBM DBM 99+300 99+360 RHS 6/2/2022 6/3/2022

EPC-06/HW/4711 Level checking and laying of DBM DBM 100+400 102+500 RHS 6/2/2022 6/3/2022

EPC-06/HW/4721 Level & FDD Checking of WMM Top layer WMM-II 106+400 107+300 RHS 6/3/2022 6/4/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4722 Applying primer coat Prime coat 104+200 106+100 RHS 6/3/2022 6/4/2022

EPC-06/HW/4723 Applying primer coat Prime coat 94+300 94+500 RHS 6/3/2022 6/4/2022

EPC-06/HW/4724 Applying tack coat for DBM Tack coat (DBM) 102+500 104+200 RHS 6/3/2022 6/4/2022

EPC-06/HW/4725 Applying tack coat for DBM Tack coat (DBM) 94+300 94+500 LHS 6/3/2022 6/4/2022

EPC-06/HW/4726 Level checking and laying of DBM DBM 102+500 104+200 RHS 6/3/2022 6/4/2022

EPC-06/HW/4727 Level checking and laying of DBM DBM 94+300 94+500 LHS 6/3/2022 6/4/2022

EPC-06/HW/4730 Laying of DBM on Minor Junction DBM 102+565 RHS 6/3/2022 6/4/2022

EPC-06/HW/4730 Laying of DBM on Minor Junction DBM 103+760 RHS 6/3/2022 6/4/2022

EPC-06/HW/4737 FDD Checking of WMM 1st layer WMM-I 107+300 108+300 RHS 6/4/2022 6/5/2022

EPC-06/HW/4738 Applying tack coat for DBM Tack coat (DBM) 104+200 106+100 RHS 6/4/2022 6/5/2022

EPC-06/HW/4739 Applying tack coat for DBM Tack coat (DBM) 94+300 94+500 RHS 6/4/2022 6/5/2022

EPC-06/HW/4740 Level checking and laying of DBM DBM 104+200 106+100 RHS 6/4/2022 6/5/2022

EPC-06/HW/4741 Level checking and laying of DBM DBM 94+300 94+500 RHS 6/4/2022 6/5/2022

EPC-06/HW/4745 Laying of DBM on Minor Junction DBM 104+715 LHS 6/4/2022 6/5/2022

EPC-06/HW/4751 Level & FDD Checking of WMM Top layer WMM-II 107+300 108+300 RHS 6/5/2022 6/6/2022

EPC-06/HW/4761 Applying primer coat Prime coat 106+100 108+300 RHS 6/6/2022 6/7/2022

EPC-06/HW/4771 Applying tack coat for DBM Tack coat (DBM) 106+100 108+300 RHS 6/7/2022 6/8/2022

EPC-06/HW/4772 Level checking and laying of DBM DBM 106+100 108+300 RHS 6/7/2022 6/8/2022

EPC-06/HW/4773 Applying tack coat for BC Tack coat (BC) (OL) 00+000 01+950 LHS 6/7/2022 6/8/2022

EPC-06/HW/4774 Level checking and laying of BC BC (OL) 00+000 01+950 LHS 6/7/2022 6/8/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4776 Laying of DBM on Minor Junction DBM 108+205 LHS 6/7/2022 6/8/2022

EPC-06/HW/4784 Applying tack coat for BC Tack coat (BC) (OL) 02+700 04+600 LHS 6/8/2022 6/9/2022

EPC-06/HW/4785 Level checking and laying of BC BC (OL) 02+700 04+600 LHS 6/8/2022 6/9/2022

EPC-06/HW/4795 Applying tack coat for BC Tack coat (BC) (OL) 04+600 06+560 LHS 6/9/2022 6/10/2022

EPC-06/HW/4796 Level checking and laying of BC BC (OL) 04+600 06+560 LHS 6/9/2022 6/10/2022

EPC-06/HW/4806 Applying tack coat for BC Tack coat (BC) (OL) 00+000 01+950 RHS 6/10/2022 6/11/2022

EPC-06/HW/4807 Level checking and laying of BC BC (OL) 00+000 01+950 RHS 6/10/2022 6/11/2022

EPC-06/HW/4827 Applying tack coat for BC Tack coat (BC) (OL) 02+700 04+500 RHS 6/13/2022 6/14/2022

EPC-06/HW/4828 Level checking and laying of BC BC (OL) 02+700 04+500 RHS 6/13/2022 6/14/2022

EPC-06/HW/4848 Applying tack coat for BC Tack coat (BC) (OL) 04+500 06+560 RHS 6/14/2022 6/15/2022

EPC-06/HW/4849 Level checking and laying of BC BC (OL) 04+500 06+560 RHS 6/14/2022 6/15/2022

EPC-06/HW/4895 Level & FDD Checking of Subgrade Top layer SG Top 55+620 56+250 RHS 6/15/2022 6/16/2022

EPC-06/HW/4896 Level & FDD Checking of Subgrade Top layer SG Top 61+550 62+130 RHS 6/15/2022 6/16/2022

EPC-06/HW/4897 Level & FDD Checking of Subgrade Top layer SG Top 69+230 70+070 RHS 6/15/2022 6/16/2022

EPC-06/HW/4898 Level & FDD Checking of Subgrade Top layer SG Top 01+950 02+700 RHS 6/15/2022 6/16/2022

EPC-06/HW/4899 Level & FDD Checking of Subgrade Top layer SG Top 68+300 68+440 RHS 6/15/2022 6/16/2022

EPC-06/HW/4900 Level & FDD Checking of Subgrade Top layer SG Top 86+860 86+868 RHS 6/15/2022 6/16/2022

EPC-06/HW/4905 Level & FDD Checking of Subgrade Top layer SG Top 55+620 56+250 LHS 6/16/2022 6/17/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4906 Level & FDD Checking of Subgrade Top layer SG Top 61+550 62+130 LHS 6/16/2022 6/17/2022

EPC-06/HW/4907 Level & FDD Checking of Subgrade Top layer SG Top 69+230 70+070 LHS 6/16/2022 6/17/2022

EPC-06/HW/4908 Level & FDD Checking of Subgrade Top layer SG Top 01+950 02+700 LHS 6/16/2022 6/17/2022

EPC-06/HW/4909 Level & FDD Checking For GSB layer GSB 55+620 56+250 RHS 6/16/2022 6/17/2022

EPC-06/HW/4910 Level & FDD Checking For GSB layer GSB 61+550 62+130 RHS 6/16/2022 6/17/2022

EPC-06/HW/4911 Level & FDD Checking For GSB layer GSB 69+230 70+070 RHS 6/16/2022 6/17/2022

EPC-06/HW/4912 Level & FDD Checking For GSB layer GSB 01+950 02+700 RHS 6/16/2022 6/17/2022

EPC-06/HW/4913 Level & FDD Checking For GSB layer GSB 68+300 68+440 RHS 6/16/2022 6/17/2022

EPC-06/HW/4914 Level & FDD Checking For GSB layer GSB 86+860 86+868 RHS 6/16/2022 6/17/2022

EPC-06/HW/4922 Level & FDD Checking of Subgrade Top layer SG Top 46+250 46+320 RHS 6/17/2022 6/18/2022

EPC-06/HW/4923 Level & FDD Checking For GSB layer GSB 55+620 56+250 LHS 6/17/2022 6/18/2022

EPC-06/HW/4924 Level & FDD Checking For GSB layer GSB 61+550 62+130 LHS 6/17/2022 6/18/2022

EPC-06/HW/4925 Level & FDD Checking For GSB layer GSB 69+230 70+070 LHS 6/17/2022 6/18/2022

EPC-06/HW/4926 Level & FDD Checking For GSB layer GSB 01+950 02+700 LHS 6/17/2022 6/18/2022

EPC-06/HW/4927 FDD Checking of WMM 1st layer WMM-I 55+620 56+250 RHS 6/17/2022 6/18/2022

EPC-06/HW/4928 FDD Checking of WMM 1st layer WMM-I 61+550 62+130 RHS 6/17/2022 6/18/2022

EPC-06/HW/4929 FDD Checking of WMM 1st layer WMM-I 69+230 70+070 RHS 6/17/2022 6/18/2022

EPC-06/HW/4930 FDD Checking of WMM 1st layer WMM-I 1+950 2+700 RHS 6/17/2022 6/18/2022

EPC-06/HW/4931 FDD Checking of WMM 1st layer WMM-I 97+680 97+750 RHS 6/17/2022 6/18/2022

EPC-06/HW/4932 FDD Checking of WMM 1st layer WMM-I 97+680 97+750 LHS 6/17/2022 6/18/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4933 FDD and level checking of DLC laying DLC 68+300 68+440 RHS 6/17/2022 6/18/2022

EPC-06/HW/4934 FDD and level checking of DLC laying DLC 86+860 86+868 RHS 6/17/2022 6/18/2022

EPC-06/HW/4943 Level & FDD Checking of Subgrade Top layer SG Top 46+250 46+320 LHS 6/18/2022 6/19/2022

EPC-06/HW/4944 FDD Checking of WMM 1st layer WMM-I 55+620 56+250 LHS 6/18/2022 6/19/2022

EPC-06/HW/4945 FDD Checking of WMM 1st layer WMM-I 61+550 62+130 LHS 6/18/2022 6/19/2022

EPC-06/HW/4946 FDD Checking of WMM 1st layer WMM-I 69+230 70+070 LHS 6/18/2022 6/19/2022

EPC-06/HW/4947 FDD Checking of WMM 1st layer WMM-I 1+950 2+700 LHS 6/18/2022 6/19/2022

EPC-06/HW/4948 Level & FDD Checking of WMM Top layer WMM-II 55+620 56+250 RHS 6/18/2022 6/19/2022

EPC-06/HW/4949 Level & FDD Checking of WMM Top layer WMM-II 61+550 62+130 RHS 6/18/2022 6/19/2022

EPC-06/HW/4950 Level & FDD Checking of WMM Top layer WMM-II 69+230 70+070 RHS 6/18/2022 6/19/2022

EPC-06/HW/4951 Level & FDD Checking of WMM Top layer WMM-II 1+950 2+700 RHS 6/18/2022 6/19/2022

EPC-06/HW/4952 Level & FDD Checking of WMM Top layer WMM-II 97+680 97+750 RHS 6/18/2022 6/19/2022

EPC-06/HW/4953 Level & FDD Checking of WMM Top layer WMM-II 97+680 97+750 LHS 6/18/2022 6/19/2022

EPC-06/HW/4954 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+300 68+440 RHS 6/18/2022 6/19/2022

EPC-06/HW/4955 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+860 86+868 RHS 6/18/2022 6/19/2022

EPC-06/HW/4960 Level & FDD Checking For GSB layer GSB 46+250 46+320 RHS 6/19/2022 6/20/2022

EPC-06/HW/4961 Level & FDD Checking of WMM Top layer WMM-II 55+620 56+250 LHS 6/19/2022 6/20/2022

EPC-06/HW/4962 Level & FDD Checking of WMM Top layer WMM-II 61+550 62+130 LHS 6/19/2022 6/20/2022

EPC-06/HW/4963 Level & FDD Checking of WMM Top layer WMM-II 69+230 70+070 LHS 6/19/2022 6/20/2022

EPC-06/HW/4964 Level & FDD Checking of WMM Top layer WMM-II 1+950 2+700 LHS 6/19/2022 6/20/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4965 Applying primer coat Prime coat 55+620 56+250 LHS 6/19/2022 6/20/2022

EPC-06/HW/4966 Applying primer coat Prime coat 61+550 62+130 LHS 6/19/2022 6/20/2022

EPC-06/HW/4967 Applying primer coat Prime coat 69+230 70+070 LHS 6/19/2022 6/20/2022

EPC-06/HW/4968 Applying primer coat Prime coat 01+950 02+700 LHS 6/19/2022 6/20/2022

EPC-06/HW/4969 Applying primer coat Prime coat 97+680 97+750 LHS 6/19/2022 6/20/2022

EPC-06/HW/4977 Level & FDD Checking For GSB layer GSB 46+250 46+320 LHS 6/20/2022 6/21/2022

EPC-06/HW/4978 FDD Checking of WMM 1st layer WMM-I 46+250 46+320 RHS 6/20/2022 6/21/2022

EPC-06/HW/4979 Applying tack coat for DBM Tack coat (DBM) 55+620 56+250 LHS 6/20/2022 6/21/2022

EPC-06/HW/4980 Applying tack coat for DBM Tack coat (DBM) 61+550 62+130 LHS 6/20/2022 6/21/2022

EPC-06/HW/4981 Applying tack coat for DBM Tack coat (DBM) 69+230 70+070 LHS 6/20/2022 6/21/2022

EPC-06/HW/4982 Applying tack coat for DBM Tack coat (DBM) 01+950 02+700 LHS 6/20/2022 6/21/2022

EPC-06/HW/4983 Level checking and laying of DBM DBM 55+620 56+250 LHS 6/20/2022 6/21/2022

EPC-06/HW/4984 Level checking and laying of DBM DBM 61+550 62+130 LHS 6/20/2022 6/21/2022

EPC-06/HW/4985 Level checking and laying of DBM DBM 69+230 70+070 LHS 6/20/2022 6/21/2022

EPC-06/HW/4986 Level checking and laying of DBM DBM 01+950 02+700 LHS 6/20/2022 6/21/2022

EPC-06/HW/4994 Level & FDD Checking of Subgrade Top layer SG Top 68+300 68+440 LHS 6/21/2022 6/22/2022

EPC-06/HW/4995 Level & FDD Checking of Subgrade Top layer SG Top 86+860 86+868 LHS 6/21/2022 6/22/2022

EPC-06/HW/4996 FDD Checking of WMM 1st layer WMM-I 46+250 46+320 LHS 6/21/2022 6/22/2022

EPC-06/HW/4997 Level & FDD Checking of WMM Top layer WMM-II 46+250 46+320 RHS 6/21/2022 6/22/2022

EPC-06/HW/4998 Applying primer coat Prime coat 46+250 46+320 RHS 6/21/2022 6/22/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/4999 Applying tack coat for DBM Tack coat (DBM) 46+250 46+320 RHS 6/21/2022 6/22/2022

EPC-06/HW/5000 Applying tack coat for DBM Tack coat (DBM) 46+250 46+320 LHS 6/21/2022 6/22/2022

EPC-06/HW/5001 Level checking and laying of DBM DBM 46+250 46+320 RHS 6/21/2022 6/22/2022

EPC-06/HW/5002 Level checking and laying of DBM DBM 46+250 46+320 LHS 6/21/2022 6/22/2022

EPC-06/HW/5003 Applying primer coat Prime coat 55+620 56+250 RHS 6/21/2022 6/22/2022

EPC-06/HW/5004 Applying primer coat Prime coat 61+550 62+130 RHS 6/21/2022 6/22/2022

EPC-06/HW/5005 Applying primer coat Prime coat 69+230 70+070 RHS 6/21/2022 6/22/2022

EPC-06/HW/5006 Applying primer coat Prime coat 01+950 02+700 RHS 6/21/2022 6/22/2022

EPC-06/HW/5007 Applying primer coat Prime coat 97+680 97+750 RHS 6/21/2022 6/22/2022

EPC-06/HW/5008 Applying tack coat for DBM Tack coat (DBM) 97+680 97+750 LHS 6/21/2022 6/22/2022

EPC-06/HW/5009 Level checking and laying of DBM DBM 97+680 97+750 LHS 6/21/2022 6/22/2022

EPC-06/HW/5014 Level & FDD Checking For GSB layer GSB 68+300 68+440 LHS 6/22/2022 6/23/2022

EPC-06/HW/5015 Level & FDD Checking For GSB layer GSB 86+860 86+868 LHS 6/22/2022 6/23/2022

EPC-06/HW/5016 Level & FDD Checking of WMM Top layer WMM-II 46+250 46+320 LHS 6/22/2022 6/23/2022

EPC-06/HW/5017 Applying primer coat Prime coat 46+250 46+320 LHS 6/22/2022 6/23/2022

EPC-06/HW/5018 Applying tack coat for DBM Tack coat (DBM) 55+620 56+250 RHS 6/22/2022 6/23/2022

EPC-06/HW/5019 Applying tack coat for DBM Tack coat (DBM) 61+550 62+130 RHS 6/22/2022 6/23/2022

EPC-06/HW/5020 Applying tack coat for DBM Tack coat (DBM) 69+230 70+070 RHS 6/22/2022 6/23/2022

EPC-06/HW/5021 Applying tack coat for DBM Tack coat (DBM) 01+950 02+700 RHS 6/22/2022 6/23/2022

EPC-06/HW/5022 Applying tack coat for DBM Tack coat (DBM) 97+680 97+750 RHS 6/22/2022 6/23/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5023 Level checking and laying of DBM DBM 55+620 56+250 RHS 6/22/2022 6/23/2022

EPC-06/HW/5024 Level checking and laying of DBM DBM 61+550 62+130 RHS 6/22/2022 6/23/2022

EPC-06/HW/5025 Level checking and laying of DBM DBM 69+230 70+070 RHS 6/22/2022 6/23/2022

EPC-06/HW/5026 Level checking and laying of DBM DBM 01+950 02+700 RHS 6/22/2022 6/23/2022

EPC-06/HW/5027 Level checking and laying of DBM DBM 97+680 97+750 RHS 6/22/2022 6/23/2022

EPC-06/HW/5032 Applying tack coat for BC Tack coat (BC) (OL) 55+620 56+250 RHS 6/23/2022 6/24/2022

EPC-06/HW/5033 Applying tack coat for BC Tack coat (BC) (OL) 61+550 62+130 RHS 6/23/2022 6/24/2022

EPC-06/HW/5034 Applying tack coat for BC Tack coat (BC) 69+230 70+070 RHS 6/23/2022 6/24/2022

EPC-06/HW/5035 Applying tack coat for BC Tack coat (BC) (OL) 01+950 02+700 RHS 6/23/2022 6/24/2022

EPC-06/HW/5036 Level checking and laying of BC BC(OL) 55+620 56+250 RHS 6/23/2022 6/24/2022

EPC-06/HW/5037 Level checking and laying of BC BC(OL) 61+550 62+130 RHS 6/23/2022 6/24/2022

EPC-06/HW/5038 Level checking and laying of BC BC 69+230 70+070 RHS 6/23/2022 6/24/2022

EPC-06/HW/5039 Level checking and laying of BC BC(OL) 01+950 02+700 RHS 6/23/2022 6/24/2022

EPC-06/HW/5040 FDD and level checking of DLC laying DLC 68+300 68+440 LHS 6/23/2022 6/24/2022

EPC-06/HW/5041 FDD and level checking of DLC laying DLC 86+860 86+868 LHS 6/23/2022 6/24/2022

EPC-06/HW/5049 Applying tack coat for BC Tack coat (BC) 94+300 96+200 RHS 6/24/2022 6/25/2022

EPC-06/HW/5050 Applying tack coat for BC Tack coat (BC) 96+200 97+800 RHS 6/24/2022 6/25/2022

EPC-06/HW/5051 Applying tack coat for BC Tack coat (BC) 97+800 100+000 RHS 6/24/2022 6/25/2022

EPC-06/HW/5052 Level checking and laying of BC BC 94+300 96+200 RHS 6/24/2022 6/25/2022

EPC-06/HW/5053 Level checking and laying of BC BC 96+200 97+800 RHS 6/24/2022 6/25/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5054 Level checking and laying of BC BC 97+800 100+000 RHS 6/24/2022 6/25/2022

EPC-06/HW/5055 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 68+300 68+440 LHS 6/24/2022 6/25/2022

EPC-06/HW/5056 Level checking and laying of PQC (Carriageway Portion) PQC (CW) 86+860 86+868 LHS 6/24/2022 6/25/2022

EPC-06/HW/5064 Applying tack coat for BC Tack coat (BC) 100+000 102+000 RHS 6/25/2022 6/26/2022

EPC-06/HW/5065 Applying tack coat for BC Tack coat (BC) 102+000 104+000 RHS 6/25/2022 6/26/2022

EPC-06/HW/5066 Applying tack coat for BC Tack coat (BC) 104+000 106+400 RHS 6/25/2022 6/26/2022

EPC-06/HW/5067 Applying tack coat for BC Tack coat (BC) 106+400 108+300 RHS 6/25/2022 6/26/2022

EPC-06/HW/5068 Level checking and laying of BC BC 100+000 102+000 RHS 6/25/2022 6/26/2022

EPC-06/HW/5069 Level checking and laying of BC BC 102+000 104+000 RHS 6/25/2022 6/26/2022

EPC-06/HW/5070 Level checking and laying of BC BC 104+000 106+400 RHS 6/25/2022 6/26/2022

EPC-06/HW/5071 Level checking and laying of BC BC 106+400 108+300 RHS 6/25/2022 6/26/2022

EPC-06/HW/5080 Applying tack coat for BC Tack coat (BC) 46+250 46+320 RHS 6/26/2022 6/27/2022

EPC-06/HW/5081 Applying tack coat for BC Tack coat (BC) 46+250 46+320 LHS 6/26/2022 6/27/2022

EPC-06/HW/5082 Level checking and laying of BC BC 46+250 46+320 RHS 6/26/2022 6/27/2022

EPC-06/HW/5083 Level checking and laying of BC BC 46+250 46+320 LHS 6/26/2022 6/27/2022

EPC-06/HW/5084 Applying tack coat for BC Tack coat (BC) (OL) 55+620 56+250 LHS 6/26/2022 6/27/2022

EPC-06/HW/5085 Applying tack coat for BC Tack coat (BC) (OL) 61+550 62+130 LHS 6/26/2022 6/27/2022

EPC-06/HW/5086 Applying tack coat for BC Tack coat (BC) 69+230 70+070 LHS 6/26/2022 6/27/2022

EPC-06/HW/5087 Applying tack coat for BC Tack coat (BC) (OL) 01+950 02+700 LHS 6/26/2022 6/27/2022

EPC-06/HW/5088 Level checking and laying of BC BC(OL) 55+620 56+250 LHS 6/26/2022 6/27/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5089 Level checking and laying of BC BC(OL) 61+550 62+130 LHS 6/26/2022 6/27/2022

EPC-06/HW/5090 Level checking and laying of BC BC 69+230 70+070 LHS 6/26/2022 6/27/2022

EPC-06/HW/5091 Level checking and laying of BC BC(OL) 01+950 02+700 LHS 6/26/2022 6/27/2022

EPC-06/HW/5099 Applying tack coat for BC Tack coat (BC) 94+300 96+100 LHS 6/27/2022 6/28/2022

EPC-06/HW/5100 Applying tack coat for BC Tack coat (BC) 96+100 97+700 LHS 6/27/2022 6/28/2022

EPC-06/HW/5101 Applying tack coat for BC Tack coat (BC) 97+700 100+000 LHS 6/27/2022 6/28/2022

EPC-06/HW/5102 Level checking and laying of BC BC 94+300 96+100 LHS 6/27/2022 6/28/2022

EPC-06/HW/5103 Level checking and laying of BC BC 96+100 97+700 LHS 6/27/2022 6/28/2022

EPC-06/HW/5104 Level checking and laying of BC BC 97+700 100+000 LHS 6/27/2022 6/28/2022

EPC-06/HW/5113 Applying tack coat for BC Tack coat (BC) 100+000 102+100 LHS 6/28/2022 6/29/2022

EPC-06/HW/5114 Applying tack coat for BC Tack coat (BC) 102+100 104+300 LHS 6/28/2022 6/29/2022

EPC-06/HW/5115 Level checking and laying of BC BC 100+000 102+100 LHS 6/28/2022 6/29/2022

EPC-06/HW/5116 Level checking and laying of BC BC 102+100 104+300 LHS 6/28/2022 6/29/2022

EPC-06/HW/5121 Applying tack coat for BC Tack coat (BC) 104+300 106+300 LHS 6/29/2022 6/30/2022

EPC-06/HW/5122 Applying tack coat for BC Tack coat (BC) 106+300 108+300 LHS 6/29/2022 6/30/2022

EPC-06/HW/5123 Level checking and laying of BC BC 104+300 106+300 LHS 6/29/2022 6/30/2022

EPC-06/HW/5124 Level checking and laying of BC BC 106+300 108+300 LHS 6/29/2022 6/30/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5150 Road signs, markings, km stones, safety device R,M,K,S 44+300 46+251 BHS 7/1/2022

EPC-06/HW/5151 Road signs, markings, km stones, safety device R,M,K,S 46+320 48+500 RHS 7/1/2022

EPC-06/HW/5152 Road signs, markings, km stones, safety device R,M,K,S 46+320 48+500 LHS 7/1/2022

EPC-06/HW/5153 Road signs, markings, km stones, safety device R,M,K,S 48+500 50+050 BHS 7/1/2022

EPC-06/HW/5154 Road signs, markings, km stones, safety device R,M,K,S 50+050 51+500 RHS 7/1/2022

EPC-06/HW/5155 Road signs, markings, km stones, safety device R,M,K,S 50+050 51+500 LHS 7/1/2022

EPC-06/HW/5156 Road side plantation Plantation 44+300 46+251 BHS 7/1/2022

EPC-06/HW/5165 Road signs, markings, km stones, safety device R,M,K,S 51+500 53+820 RHS 7/2/2022

EPC-06/HW/5166 Road signs, markings, km stones, safety device R,M,K,S 51+500 53+820 LHS 7/2/2022

EPC-06/HW/5167 Road side plantation Plantation 46+320 48+500 BHS 7/2/2022

EPC-06/HW/5172 Road signs, markings, km stones, safety device R,M,K,S 53+820 55+623 BHS 7/3/2022

EPC-06/HW/5173 Road signs, markings, km stones, safety device R,M,K,S 58+130 60+100 LHS 7/3/2022

EPC-06/HW/5174 Road signs, markings, km stones, safety device R,M,K,S 58+130 60+100 RHS 7/3/2022

EPC-06/HW/5175 Road side plantation Plantation 48+500 49+500 BHS 7/3/2022

EPC-06/HW/5181 Road signs, markings, km stones, safety device R,M,K,S 60+100 61+550 LHS 7/4/2022

EPC-06/HW/5182 Road signs, markings, km stones, safety device R,M,K,S 60+100 61+550 RHS 7/4/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5183 Road signs, markings, km stones, safety device R,M,K,S 62+130 64+870 BHS 7/4/2022

EPC-06/HW/5184 Road signs, markings, km stones, safety device R,M,K,S 64+870 66+190 RHS 7/4/2022

EPC-06/HW/5185 Road side plantation Plantation 49+900 51+500 BHS 7/4/2022

EPC-06/HW/5191 Road signs, markings, km stones, safety device R,M,K,S 64+870 66+190 LHS 7/5/2022

EPC-06/HW/5192 Road signs, markings, km stones, safety device R,M,K,S 66+190 67+500 BHS 7/5/2022

EPC-06/HW/5193 Road signs, markings, km stones, safety device R,M,K,S 68+000 68+080 BHS 7/5/2022

EPC-06/HW/5194 Road signs, markings, km stones, safety device R,M,K,S 68+772 69+230 BHS 7/5/2022

EPC-06/HW/5195 Road side plantation Plantation 51+500 53+820 BHS 7/5/2022

EPC-06/HW/5202 Road signs, markings, km stones, safety device R,M,K,S 70+067 72+090 BHS 7/6/2022

EPC-06/HW/5203 Road signs, markings, km stones, safety device R,M,K,S 72+090 74+000 BHS 7/6/2022

EPC-06/HW/5204 Road signs, markings, km stones, safety device R,M,K,S 74+000 75+910 RHS 7/6/2022

EPC-06/HW/5205 Road signs, markings, km stones, safety device R,M,K,S 74+000 75+910 LHS 7/6/2022

EPC-06/HW/5206 Road side plantation Plantation 53+820 55+623 BHS 7/6/2022

EPC-06/HW/5214 Road signs, markings, km stones, safety device R,M,K,S 75+910 78+100 BHS 7/7/2022

EPC-06/HW/5215 Road signs, markings, km stones, safety device R,M,K,S 78+100 80+250 BHS 7/7/2022

EPC-06/HW/5216 Road signs, markings, km stones, safety device R,M,K,S 80+250 82+150 BHS 7/7/2022

EPC-06/HW/5217 Road signs, markings, km stones, safety device R,M,K,S 00+000 01+950 BHS 7/7/2022

EPC-06/HW/5218 Road side plantation Plantation 58+130 60+100 BHS 7/7/2022

EPC-06/HW/5226 Road signs, markings, km stones, safety device R,M,K,S 02+700 04+500 BHS 7/8/2022

EPC-06/HW/5227 Road signs, markings, km stones, safety device R,M,K,S 04+500 06+560 BHS 7/8/2022
Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5228 Road signs, markings, km stones, safety device R,M,K,S 85+670 86+868 LHS 7/8/2022

EPC-06/HW/5229 Road signs, markings, km stones, safety device R,M,K,S 85+670 86+868 RHS 7/8/2022

EPC-06/HW/5230 Road signs, markings, km stones, safety device R,M,K,S 86+868 89+005 BHS 7/8/2022

EPC-06/HW/5231 Road signs, markings, km stones, safety device R,M,K,S 89+005 92+000 RHS 7/8/2022

EPC-06/HW/5232 Road signs, markings, km stones, safety device R,M,K,S 89+005 92+000 LHS 7/8/2022

EPC-06/HW/5233 Road signs, markings, km stones, safety device R,M,K,S 92+000 94+300 BHS 7/8/2022

EPC-06/HW/5234 Road side plantation Plantation 60+100 61+550 BHS 7/8/2022

EPC-06/HW/5241 Road side plantation Plantation 62+130 64+870 BHS 7/9/2022

EPC-06/HW/5250 Road side plantation Plantation 64+870 66+190 BHS 7/10/2022

EPC-06/HW/5251 Road side plantation Plantation 66+190 67+500 BHS 7/10/2022

EPC-06/HW/5256 Road side plantation Plantation 68+772 69+230 BHS 7/11/2022

EPC-06/HW/5257 Road side plantation Plantation 70+067 71+100 BHS 7/11/2022

EPC-06/HW/5259 Road side plantation Plantation 71+600 73+770 BHS 7/12/2022

EPC-06/HW/5260 Road side plantation Plantation 74+170 75+700 BHS 7/13/2022

EPC-06/HW/5265 Road side plantation Plantation 75+900 78+100 BHS 7/14/2022

EPC-06/HW/5266 Road side plantation Plantation 78+100 80+250 BHS 7/15/2022

EPC-06/HW/5267 Road side plantation Plantation 80+250 82+150 BHS 7/16/2022

EPC-06/HW/5268 Road side plantation Plantation 00+000 01+950 BHS 7/17/2022

EPC-06/HW/5269 Road side plantation Plantation 02+700 04+500 BHS 7/18/2022

EPC-06/HW/5270 Road side plantation Plantation 04+500 06+560 BHS 7/19/2022


Chainage
Sr. Date of Date of
RFI No. Description Layer/ Lift Side Time Remarks
No. From To Submission Inspection

EPC-06/HW/5271 Road side plantation Plantation 85+670 86+868 BHS 7/20/2022

EPC-06/HW/5272 Road side plantation Plantation 86+868 88+520 BHS 7/21/2022

EPC-06/HW/5273 Road side plantation Plantation 88+520 88+900 BHS 7/22/2022

EPC-06/HW/5274 Road side plantation Plantation 89+285 92+000 BHS 7/23/2022

EPC-06/HW/5275 Road side plantation Plantation 89+005 92+000 BHS 7/24/2022

EPC-06/HW/5276 Road side plantation Plantation 92+000 94+300 BHS 7/25/2022

EPC-06/HW/5281 Road side plantation Plantation 94+300 97+750 BHS 7/26/2022

EPC-06/HW/5282 Road side plantation Plantation 97+750 100+500 BHS 7/27/2022

EPC-06/HW/5283 Road side plantation Plantation 100+500 102+800 BHS 7/28/2022

EPC-06/HW/5284 Road side plantation Plantation 102+800 105+150 BHS 7/29/2022

EPC-06/HW/5285 Road side plantation Plantation 105+150 107+200 BHS 7/30/2022

EPC-06/HW/5286 Road side plantation Plantation 107+200 108+300 BHS 7/31/2022