NOTIFICATION OF INSPECTION (NOI)

MDR PROJECT : LTA-II Contract # 6600035821 (OOK) & 6600035804 (IK)


EPCI of MRJN TP-10 & Associated Facilities Project (LSTK) (BI-10-02016) (BI-12-18000)
CRPO No. 6510907788 (OOK) & 6510911347, 6510911556 (IK)
MMEI Project Ref. D7057 (OOK) & MACL Project ref. D7354 (IK)

Procurement Details:
NOI No. : NOI Revision: NOI Date:
033 07 08.09.2020
MDR Purchase Order No (& Rev.): Vendor / Supplier Name: PO Description: Corrosion inhibitor
D7057-PO-0923-ALL-MMP08- PETRONASH ARABIA injection package
0002-0-01
Inspection Lot No. : (To be filled by MDR) Saudi Aramco Dummy PO No.:
107000156734 CMCI-G75-49-A076-D

Material Inspection Details:


MDR Inspector’s Name: (To be filled by Date & Time of Inspection/Period: No of Days of Inspection:
MDR) 9, 10, 12 & 16-Sep 2020 / 4 Days
TBA 9.00AM to 5.00PM
Place of Inspection: Name of Contact Person for this Inspection:
Suresh.T
Petronash Arabia, PO Box 41027
Dammam – 31521
Contact No of Person for this Inspection:
Kingdom of Saudi Arabia
013 8067040 EXT:1366 (Mobile : 00966 595608709)

Type of Inspection: ** (Please mention the stages of ITP / QCP proposed to be carried out on the notified date)

ITP No & Rev: ** D7057-VD-MMP08-01-H03-0002 Rev 00B


ITP Activity Inspection Date ITP Activity Description ITP intervention (H/ W/ R/ M)
No MCDERMOTT ARAMCO
Blasting Inspection for tank
12.3 09-Sep-2020 W RW
(G75-43-U-0005)
In-process coating inspection of
12.4 10-Sep-2020 RW M
tank -primer (G75-43-U-0005)
In-process coating inspection of
12.4 12-Sep-2020 RW M
tank -Mid-coat (G75-43-U-0005)
Final painting inspection of tank
12.5 16-Sep-2020 W M
(G75-43-U-0005)

(Extend this Table for additional entries)


Material Offered Details:
PO Item numbers / Tag Nos. and Quantity to be inspected: **

Quantity (Unit 07)


PO Material Description
Offered in Previously
It. No PO Qty (Include Tag No for Tagged Items)
this NOI Released
1 to 07 07 02 5 Corrosion inhibitor injection package
(Extend this Table for additional entries)

PO completion Status ** Partial; If partial _______ %


(Considering this NOI quantities) Complete

** - Information is mandatory and to be consistent with approved ITP / PO.