1 Press Change Gear 1 Rivetting 550
2 Solder loading Motor ( G- 1) Soldering 400
3 Solder loading Motor ( G- 2) Soldering 400
4 Solder Mode Sw ( G- 1) Soldering 500
5 Solder Mode Sw ( G- 2) Soldering 400
6 Solder Rest Sw ( G- 1) Soldering 500
7 Solder Rest Sw ( G- 2) Soldering 420
8 Solder Mode Sw ( G- 3) Soldering 460
9 Press Feed Gear 2 Rivetting 600
10 Solder Relay PWB Soldering 360
11 Pemasangan Cover Pick Up Assembling 500
G Upper Frame Assy ( G - 1)
1 Upper Frame Assy - 1 Assembling 400
2 Upper Frame Assy - 2 Assembling 400
3 Upper Frame Assy - 3 Assembling 450
4 Upper Frame Assy - 4 Assembling 400
5 Upper Frame Assy - 5 Assembling 450
6 Upper Frame Assy - 6 Assembling 500
H Upper Frame Assy ( G - 2)
1 Upper Frame Assy - 1 Assembling 500
2 Upper Frame Assy - 2 Assembling 480
3 Upper Frame Assy - 3 Assembling 480
4 Upper Frame Assy - 4 Assembling 400
5 Upper Frame Assy - 5 Assembling 500
6 Upper Frame Assy - 6 Assembling 400
I Upper Frame Assy ( G - 3)
1 Upper Frame Assy - 1 Assembling 400
2 Upper Frame Assy - 2 Assembling 400
3 Upper Frame Assy - 3 Assembling 400
4 Upper Frame Assy - 4 Assembling 400
J Handling Rest Sw & Mode SwAssembling 620
K Packing ML 10 Handling Mecha 400
L Packing ML 11 Handling Mecha 440