Planning and Designing of
L.I. Schemes
BY

Abhay L. Pathak
(Mobile No. 9284533309)

Superintending Engineer and Deputy Secretary,


Mantralaya, Water Resources Dept.
Mumbai.

2
TOPICS
1. Types of L.I.S.

2. Concept of L.I.S planning and feasibility.

3. Important Parameters in L.I.S.

4. Finalisation of parameters of L.I.S.

5. Major components of L.I.S.

6. Design of Various components of L.I.S.

7. Important Govt. GR / Circulars.

3
WHAT IS L.I.S. :-
 A Mechanical arrangement provided to irrigate the
area which is at higher level than the water source.
 History : After drought in 1972, Maharashtra Irrigation
Development Commission (IDCOM) was established
to facilitate financial support to Lift schemes. Water
users co-operative society will be formed to bear the
electricity charges and water cess.
 Later on Govt.of Maharashtra under took small L.I.
schemes in trible and hilly areas.
 In Western Maharashtra lots of K.T.Weir were
constructed and due to facility of releasing water from
U/s dam several co-operative L.I.S. are established.
 Success of these Schemes lies in sowing of cash crops,
sugar cane, vegetables, fruits etc.
 Vishnupuri Lift Irrigation Scheme in Nanded Dist. is
the first major L.I.Scheme administratively
approved in 1979 in the state.
TYPES OF L.I.S. :-
 (1) According to Ownership :-
a) Government L.I.S. Schemes.
b) Co-Operative L.I.S. Schemes.
c) Private L.I.S. Schemes

(2) According to Command Area :-


a) Large L.I.S. (More than 10,000 Ha. Area)
b) Medium L.I.S. ( above 2,000 Ha.& upto 10,000
Ha.Area )
c) Small L.I.S. ( upto 2,000 Ha.Area)
TYPES OF L.I.S. :-
 According to Head :-
a) Low Head ( Lifting head up to 10 meter.)
b) Medium Head (above 10 meters & upto 40 meter)
c) High Head (above 40 meters)

According to Stages :-
a) Single Stage :- Water is lifted in single stage.
b) Multi stage :- Water is lifted in more than one
stage.
According to Way of Pumping :-
a) Series pumping :- Discharge remains same
head goes on adding. Also called as inline pumping
system. Pumps are frequntely operated in series to
supply grater head than individual pumps

b) Parallel pumping :- Here discharges get added

head remains same. Multiple pumps are run

parallely and connected one common header

(Raising main).
 CONCEPT OF L.I.S. PLANNING :
 L.I.S. should be technically feasible, economically
viable, socially accepted and environmentally
sustainable.
 Croping pattern should be appropriate and realistic.
 Height of Lifting
 Distribution system.
 Economical feasibility.
 Design discharge of the scheme
 No.of lifting stages & No.of Rows of Raising Mains.
 Beneficiaries involvement
 Planning of Construction.
FEASIBILITY OF L.I.S. :-
 Before taking any LIS scheme the following criteria's
should be checked
 Availability of required electric load from M.S.E.D.C.L.
consent should be taken.
 Govt. GR dt 23/11/2016 gives the guide lines where LIS
can be taken.
 Draught prone areas (declared by Govt) .
 Tribal areas (declared by Govt) .
 Hilly areas (declared by Govt) .
 Where annual rainfall is less than 15 inch.
Contd…….
 Where it is necessary to lift and utilise the allocated
water awarded by the interstate tribunal
 For the rehabilitation of project affected peoples.
 Atleast one of the above condition should be fullfilled.
 Prior approval to the scheme from the Chief Minister
is necessary.
 The minor LIS will be taken in hand at the cost of
Govt. of Maharashtra in tribal area where
 No alternative is available.
 Written demand by the beneficires.
 Water availability is ensured .
 Identification of command area & cropping pattern.
 Calculation of discharge for rising main which will be
70% of the peak discharge required.
 Calculations of H.P. required for the project.
 Calculation of diameter & rows of rising main & No. of
Pumps, size of pump house etc.
13
14
0.4025

15
DISCHARGE (Q)
Discharge is calculated as per Govt. circular dt.6.7.2009.
• Total net crop water requirement at root zone in Mm3 per 1000 Ha.
for peak fortnight as per modified penman method = X
• Conveyance efficiency of project = 70%
• Field application efficiency = 70%
• Overall efficiency of the project = 0.7 x 0.7= 0.49 Say= 50%
• Discharge required for 1000 Ha considering 12 days on and 2 days
off.

X * 106
= =1.929 * X m3/Sec
12 x 24 x 60 x 60 x 0.5
• Designed discharge
= 0.70 * 1.929 * X
= 1.3503 * X m3/Sec. / 1000 Ha.

16
PUMPING CAPACITY

To be worked out with respective to Gross Head of pumping.

• Gross Head for pumping = H = Static head for pumps +


Frictional loss in rising main + losses in bend.

• Total H. P. Required = w Q H /75 X η

w = Density of water (1000 Kg /m3)

Q = Discharge ( m3 /sec)

H = Gross Head (m) for pumping.

η = Efficiency of pump

17
IMPORTANT PARAMETRS OF L.I.S. :
 G.L.
 A.H.F.L.
 F.S.L. /H.F.L. of K.T.Weir
 M.D.D.L.
 Sum Bottom level
 Pump operating level (POL)
 Pump Floor level
 Centre line of delivery pipe
 FSL in delivery chamber
 N.I.R/1000 Ha
 Discharge
 Contd.
 Length of Rising Main
 Static Head for rising main
 Number of Rows
 Diameter of Rising Main
 Thickness of Rising Main
 Type of Rising Main
 Static Head for Pump
 Duty Head of Pump
 Total HP
 No. of Pumps
 HP / pump
 Type of Pump.
FINALISATION OF PARAMETERS OF LIS :
 Pumping mechaniary Note :- Based on the field
data which includes control levels, design discharges,
pump HP, etc. pumping mechainary note is prepared
by C.D.O., LIS, Nashik and is to be sent to S.E.,Mech.,
S.E.,Elec., S.E.,Civil for the comments.
 Sub Committee for LIS :- (formed by Govt.)
 S.E.,CDO, LIS, Nashik, - Chairman
 S.E.,Mech., - Member
 S.E.,Elec. - Member
 S.E.,Civil (Related to Proj.) - Member/Secretary.
 In sub committee meeting approval to P.M. Note along
with parameters Study General Layout is put up for
approval.
 Standing Committee (formed by Corporation)
 C.E., Civil (approved by corpotation)- Chairman
 C.E.,Civil (within corporation) - Member
 C.E.,Mech. - Member
 C.E.,Elec. - Member
 S.E.,LIS - Member
 S.E.,Civil (appointed by corpotation)-Member/Secretary
 Also S.E.(Mech.), S.E.(Elect.) related to particular
scheme are invited.
Contd…..
 Parameters approved in sub committee are filaised in
standing committee.General Layout of the scheme
showing various components is prepared in
Consultation with mechanical and electrical
organization by CDO and is sent for the approval of
field C.E. (competant Authority).
MAJOR COMPONENTS OF L.I.S. :
 Major Components of L.I.Schemes are as follows :
 Civil :-
 Approach channel
 Intake Structure (Guide wall , Piers) :
 Forebay : Prefrably tapezoidal in shape
 Pump house
 Manifold
 Raising Main
 Anti-surge arrangements
 Delivery Chamber
 Mechanical :
 Pump ( Vertical turbine, H.S.C., Submerged pumps) etc.
 Motor
 Control protection unit
 H.T. / L.T. Panel
 EOT Crane
 Valves
 Delivery pipe
 Battery bank DCDB
 Cables within pump house
 All electro mechanical components within pump house.
 Antisurge arrangements.
 Intake Structure Embedment in piers Gates & Hoist.
 Embedments on pump / valve floor.

 Electrical :
 Transmission lines
 Switchyard.
 DESIGN OF VARIOUS COMPONENTS
• General layout of pump house , design and
drawing of various civil components for scheme is
prepared by Central Designs Organisation and
approved by concerned Regional Chief Engineer.

• For component wise design & drawing prepared by


CDO & approved by Regional Chief Engineer,
guidelines given in Govt. Marathi circular dt.
08.04.2008.
 BASIC DATA REQUIRED FOR DESIGN FROM FIELD
AUTHORITY
1. Copy of Administrative Approval of the scheme
2. General Layout of Scheme / Pump House
• Source of water.
• Controlling levels of L.I.S.:- MDDL, FRL, MWL, HFL of
source and FSL at delivery point.
• Details of approach channel.
• Contour map of water conductor system.
• Longitudinal section of water conductor system.
• Length of rising main.
• Bore holes / Trial pits data from source to D.C. (Certified
by the Geologist).
• Location of switch yard.
• Approach road.
3. Pump House Structure

• Weight of pump, weight of motor, Gantry load details.


• Safe bearing capacity of foundation strata.
• Block out details and locations @ pump floor, control
room floor.
 4. Rising main
• Approved alignment, Plan & longitudinal section of rising
main
• Bore holes / Trial pit details.
 Note: All field data to be certified by Superintending
Engineer
APPROACH CHANNEL
● Approach channel is designed for the discharge of
1.10 times of the required discharge.

● Bed level of Approach channel near start of fore bay


(MDDL-FSD of approach channel.)

● A reverse bed slope towards source to prevent the


incoming silt.

● Silt pit to be provided before the gated intake structure

31
FORE BAY
● Preferably Trapezoidal in shape.

● Depending upon the width of the Approach channel & width


of pump sump, length of fore bay is fixed considering not
greater than, 15° diversion angle in plan and 10° angle in
profile/in vertical plane

● Purpose :

i) To avoid turbulence

ii) To obtain uniform distribution of the inflow to all the


operating pumps

● Velocity at end 0.3 m/Sec. (manual on water supply &


treatment)

● Silt trap provision


32
33
34
PUMP SUMP
● For better performance of pump, sump dimensions such as diameter of bell
mouth, bottom clearance, distance between centre line of pumps from
back wall, centre to centre distance between two pumps etc. are finalised
on the basis of provisions given in various standards.

● Proposed by C.D.O., finalised by mechanical organisation.

● If necessary, Model Study as mentioned in IS 15310:2003

Ref.
● Water supply & Treatment Manual published by Ministry of Urban
Development, GOI.

● B H R A – British Hydraulic Research Association Publication

● I.S. 1710 : 1989 & IS 15310 : 2003

● Standardization Report by Mechanical Organisation. 35


36
●Width of Pump House
HP of Pump Width (in meter) Remarks
501-1000 8.0

1001-1500 9.0 KAV & Butterfly valve to be installed


in the pump house & NRV to be
1501-2000 10.0 placed outside the pump house, if
NRV is to be placed in the pump
2001-2500 11.0 house the width may be changed
accordingly
Above 2501 12.0

● Height of Pump House


Motor floor to corbel top Corbel top to roof tie level
HP of Pump
height (in meter) height (in meter)
501-1000 8.0 3.0

1001-2000 8.0 3.2

2001-2500 8.5 3.5

Above 2501 9.0 4.0

37
● SERVICE BAY : The width & height of the service bay normally
be equal to the pump house width and height.

Number of pumps Number of Service bays


Up to 5 1

From 6-10 2

Above 10 3

Service bay length = center to center distance between two adjacent pumps

● CONTROL ROOM

HP of the pump Control Room size (W X H X L)


500-1000 6.0 x 4.5 x Pump house length

1000 – 2000 7.0 x 4.5 x Pump house length

2001 & above 8.0 x 5.0 x Pump house length

38
CABLE SPREAD ROOM
● Width & length of the cable spread room as per the
control room.

● The height not to be less than 3.50 meters.

OTHER FACILITIES
● Space for staircase, office, store as per site convenience.

39
40
41
DELIVERY PIPE

● Each pump connected through discharging pipe called as delivery pipe


to common manifold by radial tee or by 30° or 45° bend.

● Center line of delivery pipe


For Surface delivery = Motor floor level + 1 m (Tentative)
For Sub Surface delivery = Valve floor level + 1 m (Tentative)

● Air valve, Dismantling joint, BFV, NRV provided in sequence on


delivery pipe.

● Velocity not more than 2.5 m / sec. (Ref: Standardization report by


Mechanical Organisation )`
42
MANIFOLD

● Connection between delivery pipe and rising main.

● Combining the flow from delivery of individual pump to


rising main.

● Dia. of manifold = Dia. of rising main.

● Rising main to manifold at an angle of 300 or 450.

43
44
RISING MAIN

● Water from pumps delivered through rising main to delivery


chamber.

● Economical Diameter Program.

● Valves such as air valve / scour valve.

● Anti surge devices : Air vessel, One way surge tank Two way
surge tank, Bladder type air vessel, Air cushion valves, Zero
velocity valve, pressure relief valve.

● 1.2 m cover is provided on top of buried rising main.

● Thrust blocks are provided at horizontal / vertical bends

● Preferably underground pipe line


45
RISING MAIN THICKNESS
● Thickness T1 : For internal positive pressure as per IS : 5822 : 1994
Clause B-9.2
PxD
t=
2xaxexf +P
Where,
P = pressure in kg/cm2
D = Outer Diameter of Rising Main in cms.
a = Design Factor (0.9 for surge pressure)
f = Specified yield stress (2500 kg/cm2 up to 20
mm thick shell thickness)
(Table 2 of IS:2062:1992)
e = 0.8 (for field welding)
46
● Thickness T2 : For negative pressure IS : 5822:1994
Clause B-3.1)

2 x E x ( t / D )3
Pα =
1 - λ2

Where,
Pα = Vacuum pressure, 1/3 rd of atmospheric pressure
+ Over burden of 1.2m above for underground pipe
E= Young’s Modulus of Pipe material = 2.1 x 106
kg/cm2
λ = Poisson’s ratio of steel = 0.3
D= Internal Diameter of pipe.

47
● Thickness T3 : As per IS:4880 (Part-7) : 1975 Clues 5.1.1

D + 50
t=
400

Where,

D = Internal Diameter in cms

• For T1, T2 & T3, manufacturing tolerance of 12.5% is


taken in to account as per IS 3589:2001

● Thickness T4 : Minimum specified as per Table-5 of IS:3589:1991

48
REFERENCES FOR DELIVERY PIPE, MANIFOLD
& RISING MAIN

● Water Supply Manual.

● IWWA Publication M 1.

● IS 5822 : 1994.

● IS 3589 : 1991 ( RM)

● IS 2062 : 2011

● IS 4880 (Part VIII) : 1975

● IS 15310:2003

● Standardisation Report by Mech. Organisation


49
DELIVERY CHAMBER

● The water lifted from sump through Rising Main to be


delivered in delivery chamber. Water from delivery chamber
to be distributed through gravity main /distribution network.

Location : Selection Criteria

● Highest ground level location for gravity flow.

● To have a shortest length of Rising Main

● Reduction in Lengths, Minor, Sub-minor, Delivery Main etc. to


be achieved.

● Should be in full or partially cutting.


50
51
52
53
ANNEXURE

(Name of the Scheme : - )


(Ref. letter No. : )
1. Basic data considered as received from field
Peak fortnight NIR in mm3/1000 Ha. 0.42 mm3
Design Discharge 20.60 Cumecs
MDDL 441.16 m
FRL 448.16 m
AHFL 453.56 m
2. Controlling levels decided
Sump bottom level 437.16 m
Pump operating level (POL) 445.83 m
Pump floor level 454.56 m
Centre line of delivery pipe 456.06 m
FSL in delivery chamber 490.00 m
54
3. Rising main parameters
Length of rising main 5480 m
Static head for rising main 33.94 m
No. of rows 2 No.
Diameter of rising main 2500 mm
Thickness of rising main 15 mm
Type of rising main Under ground
Material for rising main Fe-410 grade conforming to IS: 2062-1992
4. Pumping parameters
Static head for pumping 44.97 m
Total H.P. for pumps 15840 HP
Number of pumps 6 No.
H.P. per pump 2640 HP
Type of pump V.T.

Member And Superintending Member Secretary & Superintending Engineer


Engineer
Mechanical Circle Project Circle

Member And Superintending Chairman & Superintending Engineer(PHs)


Engineer
Electrical Circle Central Designs Organisation, Nashik.
55
TECHNIQUES ADOPTED FOR DESIGN
All design procedure has been formulated, standardized and
made available to the designers (i.e. S.D.E., A.E.-II, Sectional
Engineer ) as printed manual. Since the procedures /
responsibilities has been documented, uniformity in the
design is achieved.
USE OF SOFTWARES
• STAAD – PRO
Internationally accepted 'STAAD_PRO' software is used for the
analysis of frame structure of power house / pump house. Due
to this, 3 dimensional analysis in a short time can be done
owing to speedy and economical solutions of the problem. The
limit state method of design is adopted for the structural
design of R.C.C. components
• SAP 2 & PIPE 2010 USED FOR SURGE ANALYSIS OF L. I. S.
56
IN HOUSE SOFTWARE DEVELOPMENT

Computer programs developed in advanced Excel by


Engineers of this wing as listed below

• Design of retaining wall.


• Optimization study for economical diameter and thickness of rising
main
• Design of saddle support on rising main.
• Design of Anchor & Thrust block on rising main
• Design of R.C.C. slab.
• Design of Isolated footing for columns carrying axial load and biaxial
moment.
57
ABSTRACT

Major Schemes Minor Schemes


Sr. No. Parameters
Unit Name Unit Name
Gross head for
Dhapewada L.I.S.
1 pumping in 127 m 5.5 m Gosi L.I.S. No.I
Stage-I
single stage

Purandar L.I.S.
2 H.P. / pump 2750 HP 25 HP Ambade L.I.S
Stage-I

Tembhu L.I.S.
3 Total HP/ stage 79200 HP 35 HP Saiganga L.I.S. Stage-2 B
Stage-I-B
Rising Main
4 2700 mm Mokhabardi L.I.S. 150 mm Korle-Titeghar L.I.S.
a) Diameter
Regadi vikaspalli,
Tembhu L.I.S.
b) Thickness 18 mm 4 mm Korlevastumbi, Kamathi &
Stage-I-B
Ambavade L.I.S.
Dhapewada L.I.S.
c) Length 22110 m 30 m Gosi BK & Akot L.I.S.
Stage-I

5 ICA 70547 Ha Tembhu L.I.S. 139 Ha Korle-Titeghar L.I.S.


58
Bladder vessels
IMPORTANT GOVT. G.R. /CIRCULARS
No. Reference Subject
Procedure regarding surge analysis and
Irrigation Deptt.Marathi Lr.No.MIP-094/
1 anti surge arrangements through expert
2500/ [204094] MP(P)/, Dt.8.2.1995
consultant
Irrigation Deptt.Marathi L.No.MCN/10.01/
2 No provision for stand by pump
37998/(57/2001) Mechanical, Dt.5-7-2002.
Irrigation Deptt.Marathi G. R MCN/10.01 Standing committee meeting –
3
(57/2001) Mech. dt. 16.07.2002 Purchasing of pumping machinery
Irrigation Deptt.Marathi L.No.MCN/ 1540/ Standardization of mechanical
4
126/ 2002) Mechanical, Dt.16.08.2002 components for L. I. S

Irrigation Deptt. Marathi L.No.MCN Standardizations of mechanical


5
10.02/1540/ (126/2002) Mech. Dt.18.8.2002 components for L.I.S.
Director General, MERI, Nashik L.No.CDO/
Circular/ (1205)/ (67/2005) PH-2/2113, Dt.21-
6 Guide lines for design of L.I.S.
12-2005. & Govt circular No.
CDO/0208/(83/2008)/MP-1 Dt. 12.01.2009
W.R.D.(Mantralaya) Circular No.misc.0308/ Regarding design proposals entrusted
7
(173/2008)MP-1, Dt.8/4/2008. to C.D.O.
P.T.O. 67
No. Reference Subject
Irrigation Deptt.Govt. Circular No. Execution of L.I.S. – Preparation of
MISC/ 1095/ (205/95), Dt.16-12-1995 & general layout of schemes etc.
8
W.R.D. L.No. 0609/ 311/ 09/MP-1, Responsibilities of various
Dt.22/6/2009 organisations.
W.R.D.(Mantralaya) Circular Guide lines for design discharge of
9
LIS/0609/366/09/MP-1, Dt.6/7/2009 L.I.S.
W.R.D.(Mantralaya) L.No.MISC/ Preparation general layout & detailed
10
2010/(61/10)/MP-2, Dt.25/3/2010 design of L.I.S.
Director General, MERI, Nashik Preparation of design & drawing of
11
L.No.CDO/PH/620, Dt.15/4/2010 L.I.S.
S.E, (PHs), C.D.O., Nasik Lr.No. Procedure for deciding parameters &
12 /PH1/LIS/ Sub committee/791, Dt. general layout of L.I.S by Sub
30/04/2010 committee
Guidelines for preparation of Surge
W.R.D.(Mantralaya) Circular analysis report (Anti- surge devices )
13
LIS/0609/(311/09)/MP-1, Dt. 1/02/2011 for LIS from recognized govt.
Institutions
68
No. Reference Subject
Irrigation Dept. Govt. Resolution No. Guide lines Regarding preparation of
14 मसंसं-1014/(प्र.क्र.334/14) मोप्र-1 Layouts and Design of Lift Irrigation
Dt.20/11/2014 Schemes
Guide lines for preparation of design
Irrigation Dept. Govt. Resolution No.
and drawing for project to be prepare
15 मसंसं-1014/(प्र.क्र.334/14) मोप्र-1
by Central Design Organisation,
Dt.16/01/2015
Nashik
Irrigation Dept. Govt. Resolution No. Regarding implementation of Work
संकीर्ण-2014/(96/14)/जसं(आस्था) Procedure for preparing report of
16 Dt.23/11/2016 new government Lift irrigation Plan
70

You might also like