STRUCTURAL WORKS

ESTIMATES
MALIMBAN, KATE NICOLE D.
ARCHITECTURE 303

1. Concrete Works

A. Foundation
F-1: 1300x1300x250
Cement = 63 bags
Sand = 2.5 cu. Meter
3/4” gravel = 4.5cu. Meter
2 inches THK Gravel Bedding = 0.293 cu. Meter

B. Columns
C-1: 0.20mts x 0.50mts x 8 mts. H
Cement = 40 bags
Sand =2.9 cu. Meter
3/4” Gravel =4.9 cu. Meter

C. Beams
2nd Floor Beam 1: 0.20mts x 0.50mts x 82.56mts L
Cement = 45 bags
Sand = 4.5 cu. meter
3/4” Gravel = 6.897 cu. meter

2ND Floor Beam 2: 0.20mts x 0.50mts x 122.50mts L


Cement = 40 bags
Sand = 6.24 cu. meter
3/4” Gravel = 8.89 cu. Meter

Roof Beam: 0.20 x 0.40mts x 41.28mts L


Cement = 20 bags
Sand = 2.95 cu.meter
3/4” Gravel = 3.50 cu.meter

D. Slab
Slab on fill: 86.56mts x 101.74mts x 0.60m THK
Cement = 29 bags
Sand = 20.89 cu.meter
3/4” Gravel = 28.543 cu.meter

Suspended Slab: 86.56mts x 101.86 x 0.20 THK


Cement = 33 bags
Sand = 15.506 cu. meter
3/4” Gravel = 12.954 cu. meter
2. Metal Works

A. Foundation
F-1: 1200x1200x300mm
12mmdia. RSB = 11lgths
#16 G.I Tie Wire = .50 kilos

B. Columns
C-1: 0.20mts x 0.50mts x 8mts H
16mmdia. RSB (Vertical Bars) = 15lgths
10mmdia. RSB (Lateral ties) = 10lgths
#16 G.I Tie Wires = 0.75 kilos

C. Beams
2nd Floor Beam 1: 0.20mts x 0.50mts x 82.56 mts L
10mmdia. RSB = 16lgths
12mmdia. RSB = 14lgths
#16 G.I Tire Wires = 0.51 kilos

2nd Floor Beam 2: 0.20mts x 0.40mts x 41.28 mts L


10mmdia. RSB = 18lghts
12mmdia. RSB = 16lgths
#16 G.I Tire Wires = 0.49 kilos

Roof Beam: 0.20mts x 0.40mts x 41.28mts L


10mmdia. RSB = 9lghts
12mmdia. RSB = 13lghts
#16 G.I Tire Wires = 0.21 kilos

D. Slabs
Slab on Fill: 86.56mts x 101.74mts x 0.60m THK
10mmdia. RSB = 15lghts
12mmdia. RSB = 18lghts
#16 G.I Tire Wires = 0.19 kilos

Suspended Slab: 86.56mts x 101.86 x 0.20 THK


10mmdia. RSB = 10lghts
12mmdia. RSB = 21lghts
#16 G.I Tire Wires = 0.22 kilos

3. Form works

A. Columns
C-1: 0.20mts x 0.40mts x 8 mts. H
3/4” Phenolic Board = 5pcs.
2”x4”x10ft. Good Lumber Supports = 600bdft
2”x4”x8ft. Good Lumber Supports = 480bdft

B. Beams
2nd Floor Beam 1: 0.20mts x 0.50mts x 82.56 mts L
3/4” Phenolic Board = 8pcs.
2”x4”x10ft. Good Lumber Supports = 625bdft
2”x4”x8ft. Good Lumber Supports = 482bdft

2nd Floor Beam 2: 0.20mts x 0.40mts x 41.28 mts L


3/4” Phenolic Board = 8pcs.
2”x4”x10ft. Good Lumber Supports = 613bdft
2”x4”x8ft. Good Lumber Supports = 423bdft

Roof Beam: 0.20mts x 0.40mts x 41.28mts L


3/4” Phenolic Board = 4pcs.
2”x4”x10ft. Good Lumber Supports = 584bdft
2”x4”x8ft. Good Lumber Supports = 312bdft

C. Slabs
Slab on Fill: 86.56mts x 101.74mts x 0.60m THK
3/4” Phenolic Board = 5 pcs.
2”x4”x10ft. Good Lumber Supports = 546bdft

Suspended Slab: 86.56mts x 101.86 x 0.20 THK


3/4” Phenolic Board = 5pcs.
2”x4”x10ft. Good Lumber Supports = 598bdft