ESTIMATES
MALIMBAN, KATE NICOLE D.
ARCHITECTURE 303
1. Concrete Works
A. Foundation
F-1: 1300x1300x250
Cement = 63 bags
Sand = 2.5 cu. Meter
3/4” gravel = 4.5cu. Meter
2 inches THK Gravel Bedding = 0.293 cu. Meter
B. Columns
C-1: 0.20mts x 0.50mts x 8 mts. H
Cement = 40 bags
Sand =2.9 cu. Meter
3/4” Gravel =4.9 cu. Meter
C. Beams
2nd Floor Beam 1: 0.20mts x 0.50mts x 82.56mts L
Cement = 45 bags
Sand = 4.5 cu. meter
3/4” Gravel = 6.897 cu. meter
D. Slab
Slab on fill: 86.56mts x 101.74mts x 0.60m THK
Cement = 29 bags
Sand = 20.89 cu.meter
3/4” Gravel = 28.543 cu.meter
A. Foundation
F-1: 1200x1200x300mm
12mmdia. RSB = 11lgths
#16 G.I Tie Wire = .50 kilos
B. Columns
C-1: 0.20mts x 0.50mts x 8mts H
16mmdia. RSB (Vertical Bars) = 15lgths
10mmdia. RSB (Lateral ties) = 10lgths
#16 G.I Tie Wires = 0.75 kilos
C. Beams
2nd Floor Beam 1: 0.20mts x 0.50mts x 82.56 mts L
10mmdia. RSB = 16lgths
12mmdia. RSB = 14lgths
#16 G.I Tire Wires = 0.51 kilos
D. Slabs
Slab on Fill: 86.56mts x 101.74mts x 0.60m THK
10mmdia. RSB = 15lghts
12mmdia. RSB = 18lghts
#16 G.I Tire Wires = 0.19 kilos
3. Form works
A. Columns
C-1: 0.20mts x 0.40mts x 8 mts. H
3/4” Phenolic Board = 5pcs.
2”x4”x10ft. Good Lumber Supports = 600bdft
2”x4”x8ft. Good Lumber Supports = 480bdft
B. Beams
2nd Floor Beam 1: 0.20mts x 0.50mts x 82.56 mts L
3/4” Phenolic Board = 8pcs.
2”x4”x10ft. Good Lumber Supports = 625bdft
2”x4”x8ft. Good Lumber Supports = 482bdft
C. Slabs
Slab on Fill: 86.56mts x 101.74mts x 0.60m THK
3/4” Phenolic Board = 5 pcs.
2”x4”x10ft. Good Lumber Supports = 546bdft